what can we learn from the hoover dam
TRANSCRIPT
What can we learn from the Hoover Dam project that influenced modern project management?
INTERNATIONAL JOURNAL OF PROJECT MANAGEMENT VOL.32(2014) P.256-264
YOUNG HOON KWAK, JOHN WALEWSKI, DANA SLEEPER AND HESSAM SADATSAFAVI
102034550 簡翊真102034611 董咨均
Index
Introduce
Video
Abstract
Background
History of the Hoover Dam project by project phases
Hoover Dam Project challenges and innovative management
Lessons learned from comparing megaproject framework by the Department of Energy (DOE)
Conclusion
Introduction
Location: Clark County/ Arizona, US
Duration: 1931 ~ 1936 (2 yrs earlier)
Life cost: 112 person
Cost: $ 833 million with inflation
Length: 379m, Height: 221.4m, Width: 200m
Company: Six Companies, Inc.
Purpose: control floods, provide irrigation water and produce hydroelectric power for Nevada, Arizona, and California.
Introduction
Why Hoover Dam is so special?
Reason1 - Breakthrough
• Never built such large dam before
• Techniques were unproven
Reason2 – Time limit
• Get fund if not on time
• Built the road on canyon before start
Video
One is from the history aspect
One is from the construction aspect
Abstract
This paper examines project and program management practices applied to the building of the Hoover Dam, and discusses how these factors contributed to the establishment and evolution of modern project management principles, tools, and techniques.
BackgroundThe greatest engineering and construction projects
In the Great Depression
Completed in 1936 Two years ahead of schedule and under
budget
History of the Hoover Dam project by project phases
Conceptual phase
Planning, execution
and construction
phase
Close out phase
History of the Hoover Dam project by project phases
Colorado River Compact In Black Canyon dividing generated electricity
Fourth version of the Boulder Canyon Project Act
1920 1928
12190419
History of the Hoover Dam project by project phases
Frank T. Crowe
Work on the foundation Technical and productivity innovations
Electric lighting Aerial tramways
Planning, execution and construction phase
1931
General Superintendent
30192919
History of the Hoover Dam project by project phases
The dam and power house were turned over to the Interior Department in February 1936, 26 months ahead of schedule and $15 million under budget.
Six Companies, Inc. was also able to overcome many obstacles in the construction of the dam and secure a profit of $13 million.
Close out phase
1936
35193419
Hoover Dam Project challenges and innovative management
Human resources
Innovative project
management
There are various issues, including organizational, managerial, planning, and implemental challenges, obstacles, solutions, and suggestions related to the Hoover Dam project.
Strategic
value
creation
Economical and managerial challenges
Ensuring the profitability of the project
Determining the hydroelectric power rate
Dividing the water and power to seven Basin states
Supporting the construction activities
Safety and health issues
Hoover Dam Project challenges and innovative management Strategic
value
creation
Government relations
Hoover Dam project was one of the first examples of a partnership between public and private sectors
Joint ventures
Foremost among innovative managerial solutions was the employment of a joint venture involving eight different firms, organized into six partners.
Hoover Dam Project challenges and innovative management Strategic
value
creation
Innovative resources allocations
Unbalanced bid
Technological innovations
Overhead cableway
Jumbo Drill
Concrete mixing plant
Innovative
project
management
Hoover Dam Project challenges and innovative management
Human Resources
Managing workers relations
Pushing workers on output
Taking a non-negotiation stance with unions
providing healthcare
Special medical dispensaries
lack of safety programs
Human
resources
Hoover Dam Project challenges and innovative management
Lessons learned from comparing megaproject framework by the Department of Energy (DOE)
Method
Frame Work developed by the Department of Energy (DOE) Four Major phases:
Key factors that were common to large construction projects delivered successfully from the standpoint of cost, schedule, and scope.
Purpose
Checklist can be used in different types of projects as a benchmark against generally accepted characteristics of successful project.
Preconception
Conception Execution Closeout
Clear define everything (1/6)
Project Champion (2/6)
Relationship (3/6)
Leadership (4/6)
Contract (5/6)
Government (6/6)
Condition cited as essential to success by DOE & Hoover Dam project
Clear define everything (1/6)
DOE
1. Project sponsors know what they need and afford.
2. Has a purpose and benefits are clearly defined.
Hoover Dam
1. All the essential need understood by both public and private agencies.
2. All revenue were divided long before the operation of the dam.
Project Champion (2/6)
DOE
Has one project champion whose position and behavior can benefits the project.
Hoover Dam
Agency maintain a close relationship with parties, state and labors.
For instance:• Address conflicts between public
against private interests and states benefits.
• Deal with the strike problem. • Secure adequately annual funds.
Relationship (3/6)
DOE
Open communications, mutual trust, and close coordination are maintained between owner/users and project.
Hoover Dam
Government (Parties, Federal..)
Bureau of Reclamation
Contractor of the project( Six Companies, resident construction engineer…)r
Project manager (4/6)
DOE
1. Experienced project manager
2. Project builder, possesses the requisite technical, managerial, and communications skills, and is brought into the project early.
Hoover Dam
1. Interior secretary : addressing
financial and political considerations of the project
2. Commissioner of the Bureau of Reclamation : playing the role
of project champion .
3. Resident construction engineer : strengthen the chain of
command between site superintendent and company's senior management.
Contract (5/6)
DOE
1. Contract incentives are clear and unambiguous, appropriate to the performance objectives.
2. Adequately compensate the contractor for the use of resources, risks.
Hoover Dam
1. Construction phase is divided into major sub-phase and deadline were set for each one of them.
2. Penalty for each delay
For instance: • The deadline for diversion of the
Colorado River was set as October 1st, 1933. Had to pay $3000 for each day passing this deadline.
Government(6/6)
DOE
The half life of the political sponsors that decided to proceed with the project exceeds the half life of the project.
Hoover Dam
Mainly support by federal government from the initiation to the final.
Conclusion
Project need to satisfying legislative requirements as the result of which challenges can overcome by the parties involved.
Both Bureau of Reclamation and Six Companies, Inc. at the field level and the executive level.
Ensuring the construction are review board which minimized rework and delay during construction.
Establishing a clear chain of command in the owner and contractor.
Securing adequate annual funding and relevant legislative and regulatory facilities.
Thank for your attention.
Thank for your attention.