C R O N O G R A M A D E I N S U M OPLAZO DE EJECUCIÓN 180 DIAS CALENDARIOS
PROYECTO : "MANTENIMIENTO DE LOS ACCESOS Y CAMINOS VECINALES DE LA PROVINCIA DE HUARMEY - ANCASH (III - ETAPA) "
PROPIETARIO : MUNICIPALIDAD PROVINCIAL DE HUARMEY
UBICACIÓN : PROVINCIA: HUARMEY DEPARTAMENTO: ANCASH
FECHA : AGOSTO DEL 2015
Item DESCRIPCIÓN UNIDAD CANTIDADMES 1 MES 2 MES 3 MES 4 MES 5 MES 6
30 Dias 30 Dias 30 Dias 30 Dias 30 Dias 30 Dias
MANTENIMIENTO DE LOS CAMINOS VECINALES 243,127.88
01.00.00 INSUMOS A UTILIZAR 243,127.88
01.01.00 SERVICIOS GENERALES UND 9,000.0016.67% 16.67% 16.67% 16.67% 16.67% 16.67%
S/. 1,500.00 S/. 1,500.00 S/. 1,500.00 S/. 1,500.00 S/. 1,500.00 S/. 1,500.00 9000.00
01.02.00 ELABORACION, IMPLEMENTACION DEL PLAN DE MANEJO AMBIENTAL GLB 39,090.0050.00% 50.00%
S/. 19,545.00 S/. 19,545.00 39090.00
01.03.00 SEÑALIZACION DE CUIDADO DEL MEDIO AMBIENTE GLB 13,220.00100.00%
S/. 13,220.00 13220.00
01.04.00 CAPACITACION SOBRE CUIDADO DEL MEDIO AMBIENTE GLB 5,916.6850.00% 50.00%
S/. 2,958.34 S/. 2,958.34 5916.68
01.05.00 PETROLEO DIESSEL GAL 175,901.2016.67% 16.67% 16.67% 16.67% 16.67% 16.67%
S/. 29,316.87 S/. 29,316.87 S/. 29,316.87 S/. 29,316.87 S/. 29,316.87 S/. 29,316.87 175901.20
Galones 2459.47 2459.47 2459.47 2459.47 2459.47 2459.47
AVANCE MENSUAL S/. 243,127.88 S/. 66,540.21 S/. 30,816.87 S/. 30,816.87 S/. 53,320.21 S/. 30,816.87 S/. 30,816.87 S/. 243,127.88
PORCENTAJE DE AVANCE MENSUAL 27.37% 12.68% 12.68% 21.93% 12.68% 12.68% 100.00%
PORCENTAJE ACUMULADO 27.37% 40.04% 52.72% 74.65% 87.32% 100.00%
MUNICIPALIDAD PROVINCIAL DE
HUARMEY
SUB GERENCIA DE ESTUDIOS Y
PROYECTOS
TOTAL VALORIZADO