xtod fy07 plan
DESCRIPTION
XTOD FY07 Plan. LCLS FAC Review October 12, 2006. LCLS Layout at SLAC. XTOD Transports Photons from e- Dump to FEH. e - Beam Dump (40M e - and g beam). Undulator Hall (175m e - and g beam). Near Expt. Hall. Linac-to-Undulator (227m e - beam). Far Expt. Hall. Linac e - beam. - PowerPoint PPT PresentationTRANSCRIPT
Donn H. McMahon
XTOD Breakout: XTOD FY07 Schedule [email protected]
October 12, 2006UCRL-PRES-225471
XTOD FY07 Plan
LCLS FAC Review
October 12, 2006
Donn H. McMahon
XTOD Breakout: XTOD FY07 Schedule [email protected]
October 12, 2006UCRL-PRES-225471
Linac-to-Undulator
(227me- beam)
UndulatorHall (175m
e- and beam)
NearExpt.Hall
X-ray VacuumTransport(250m beam)
FarExpt.Hall
e- Beam Dump (40M e- and beam)
(FEE) Front End
Enclosure (29m beam)
Linac e- beam
LCLS Layout at SLACXTOD Transports Photons from e- Dump to FEH
Donn H. McMahon
XTOD Breakout: XTOD FY07 Schedule [email protected]
October 12, 2006UCRL-PRES-225471
XTOD plan has stabilized with minor modifications
Modifications:FEL spectrometer has been redefined as the Low Energy Spectrometer
Number of “Pop-up” cameras in the FEE reduced from 13 to 9
Additions:K-measurement system in FEE moved from XES to XTOD scope w/ XES providing crystals
Deletions:none
Donn H. McMahon
XTOD Breakout: XTOD FY07 Schedule [email protected]
October 12, 2006UCRL-PRES-225471
The Proposed Baseline has nearly all XTOD instruments and diagnostics in the FEE
FEE
NEH
FEH
Donn H. McMahon
XTOD Breakout: XTOD FY07 Schedule [email protected]
October 12, 2006UCRL-PRES-225471
Diagnostics Occupy Upstream End of the Front End Enclosure (FEE)Slit
Gas Detector
GasDetector
Gas Attenuator
SolidAttenuators
Direct Imager(Scintillator)
Total Energy
FEL Offset Mirror System
Collimator 1SpectrometerPackage
Fixed Mask
Beam Direction
Donn H. McMahon
XTOD Breakout: XTOD FY07 Schedule [email protected]
October 12, 2006UCRL-PRES-225471
FEE Schematic
SolidAttenuator
Gas Attenuator
Fixed Mask, High-Energy
Slit
Start of Experimental
Hutches
5 mm diameter
collimators
Muon Shield
FEL Offset mirror
system
TotalEnergyThermal Detector
WFOV
NFOV
Windowless Gas
Detector
Windowless Gas
Detector
e-
Direct ImagerK Spectrometer
Grating
Donn H. McMahon
XTOD Breakout: XTOD FY07 Schedule [email protected]
October 12, 2006UCRL-PRES-225471
Tunnel Contains XTOD X-Ray Beam Transport System
Donn H. McMahon
XTOD Breakout: XTOD FY07 Schedule [email protected]
October 12, 2006UCRL-PRES-225471
XTOD Staff by Discipline
R. BiontaLLNL LCLS Project Leader
D. McMahonXTOD Project Engineer
C. Kelly-ClarkAdministrator
R. SouzaProcurement
Rodney VictorineResource Manager
Jay DoubravaPMCS
HazardsR. Beale
EEE. AblesP. PaxB. Abraham
MEP. DuffyM. MckernanS. ShenJ. TrentL. TungP. TirapelleM. Roeben
Comp. & CtrlsK. FongK. KishiyamaS. LewisL. Ott
PhysicsS. FriedrichS. Hau-ReigeR. LondonM. PivovaroffD. Ryutov
Donn H. McMahon
XTOD Breakout: XTOD FY07 Schedule [email protected]
October 12, 2006UCRL-PRES-225471
1.5.1Management and Safety
Account # 8866-01
XTOD Organization by WBS
Richard Bionta x 3-4846
Donn McMahon x 3-1475
Rodney Victorine x 3-3326
Hazards Control
Richard Beale x 2-3112
Steve Lewis x 3-4751
Keith Kishiyama x 2-8602
William Abraham x 2-6418
1.5.2.1Controls
Account #8866-81
1.5.3.2FEE Mech/Vac Design
Account #8866-04
Mark McKernan x 3-3825
John Trent x 2-5723
Stewart Shen x 3-4826
Pat Duffy x 2-8747
Louann Tung x 2-1274
1.5.3.3NEH Mech & Vacuum
Account #8866-29
Stewart Shen x 3-4826
Pat Duffy x 2-8747
Louann Tung x 2-1274
John Trent x 2-5723
1.5.4.2.3Slit
Account #8866-08
John Trent x 2-5723
Pete Tirapelle x 2-8749
1.5.4.2.5Gas/Solid Attenuator
Account #8866-10
Dmitri Ryutov x 2-9832
Stewart Shen x 3-4826
Martin Roeben x 3-0612
Keith Kishiyama x 2-8602
1.5.4.2.6TTF Damage Experiment
Account #8862-85
Stefan Hau-Riege x 2-5892
Rich London x 3-2021
2.5.5.2Modeling & Simulation
Account #8866-71
Linda Ott x 2-6446
Kirby Fong x 2-4205
1.5.4.2.7FEL Offset Mirror System
Account #8866-16
Mike Pivovaroff x 2-7779
Sasa Bajt x 4-3768
1.5.5.3.1Direct Imager
Account #8866-39
Paul Pax x 4-3004
Elden Ables x 2-4809
1.5.5.4.2Total Energy
Account #8866-53
Stephan Friedrich x 3-1527
Owen Drury x 2-0034
Elden Ables x 2-4809
1.5.5.4.4Low Energy Spectrometer
Account #8866-56
Mike Pivovaroff x 2-7779
Paul Pax x 4-3004
Procurement
Ray Souza
Keith Stickle
Mary Ross
1.5.5.3.6Gas Detector
Account #8866-43
Dmitri Ryutov x 2-9832
Stewart Shen x 3-4826
Martin Roeben x 3-0612
Paul Pax x 4-3004
Stefan Hau-Riege x3-2021
1.5.3.4X-Ray Tunnel Mech & Vacuum
Account #8866-29
Stewart Shen x 3-4826
Pat Duffy x 2-8747
Louann Tung x 2-1274
John Trent x 2-5723
1.5.3.5FEH Mech & Vacuum
Account #8866-29
Stewart Shen x 3-4826
Pat Duffy x 2-8747
Louann Tung x 2-1274
John Trent x 2-5723
1.5.4.2.1Fast Valve
Account #8866-TBD
Pat Duffy x 2-8747
1.5.4.2.2Fixed Mask
Account #8866-06
Pat Duffy x 2-8747
1.5.5.4.5Pop-Up Cameras
Account #8866-TBD
Paul Pax x 4-3004Elden Ables x 2-4809
1.5.5.4.6K-Spectrometer
Account #8866-TBD
Mike Pivovaroff x 2-7779Paul Pax x 4-3004
Donn H. McMahon
XTOD Breakout: XTOD FY07 Schedule [email protected]
October 12, 2006UCRL-PRES-225471
XTOD scope has stabilized and a revised go forward plan has been defined
Design completion of all systems: [FY07]:Complete final design and procurement of most XTOD systems
Fixed Mask, Slit, Gas Detectors, Attenuators, Low Energy Spectrometer, Total Energy Calorimeter, Direct Imagers, LE Offset Mirror System, Mechanical and Vacuum systems for FEE, NEH, Tunnel, and FEH
Remaining systems will be in FDR/fabrication stagesHE Offset Mirrors System, NEH & FEH Imagers, K-Measurement System, and Pop-up Cameras
Finalize details for Beneficial Occupancy (2.15.08,3.21.08) and commissioning activities: [FY07-2nd Half/FY08-1st Qtr]:
Test systems @ LLNL Conduct readiness reviewsDevelop shipping/staging plansVet installation plansDevelop commissioning plans
Donn H. McMahon
XTOD Breakout: XTOD FY07 Schedule [email protected]
October 12, 2006UCRL-PRES-225471
XTOD FY07 Development Status & PlanWBS Description Status FY07 Plan
1.05.03.02 FEE M&V Need RP input for 10.06 PRDLeverage off XVTS, Complete Final Design & Procure, Ready
for B.O.
1.05.03.03(.01) NEH M&V Need RP input for 10.06 PRDLeverage off XVTS, Complete Final Design & Procure Ready
for B.O.
1.05.03.04 XVTS M&VFinal Design scheduled for
10.18.06Complete Design, Procure, Ready for B.O..
1.05.03.05(.01) FEH M&V Need RP input for 10.06 PRD Leverage off XVTS, Complete Final Design & Procure
Fast Valve Commence preliminary design Place in EBD,Complete Final Design & Procure Ready for B.O.
1.05.04.02.02 Fixed Mask Finish ESD, Nearing FDR (11.06) Complete Design, Procure, Ready for B.O.
1.05.04.02.03 Slit Finish ESD, Nearing FDR (12..06) Complete Design, Procure, Ready for B.O.
1.05.04.02.05 Attenuator Finish ESD & Prototype Activities Complete Design, Procure, Ready for B.O.
1.05.04.02.06 TTF Damage Experiment Sept Experiments @ FLASH VUVFEL Complete analyses
1.05.04.02.07.01
FEL Offset - Low PRD in review Complete Design, Procure, Ready for B.O.
1.05.04.02.07.02
FEL Offset - High PRD to commence Complete Final Design (8.07), Procure Substrates
1.05.05.03.01 Direct Imager Finish PRD, Prototype, Component Eval Complete Design, Procure, Ready for B.O.
1.05.05.03.02 Gas Detector SCR complete, PrototypingConduct Calibration Tests (SSRL), Complete Design, Procure,
Ready for B.O
1.05.05.03.07 NEH Imager PRD (12.06) Leverage off DI, Complete Final Design, Procure systems
1.05.05.03.08 FEH Imager PRD (12.06) Leverage off DI, Complete Final Design, Procure systems
1.05.05.04.02 Total Energy Monitor SCR Complete, Prototyping Complete Design, Procure, Ready for B.O.
1.05.05.04.04 Low Energy Spectrometer PRD to start (11.06) Complete Design, Procure, Ready for B.O.
1.05..05.04.05 Pop Ups (N) PRD (1.07) Complete Final Design, Procure systems
1.05..05.04.06 K-Spectrometer PRD to start (11.06) Complete Final Design, Procure systems
Donn H. McMahon
XTOD Breakout: XTOD FY07 Schedule [email protected]
October 12, 2006UCRL-PRES-225471
Target XTOD Dates
Key Documents Design Reviews Install B.O.
WBS Description PRD ESD SCR PDR FDR Cooccupancy
1.05.03.02 FEE M&V (need RP Input) 10.06 2.22.07 1.24.07 3.12.07 4.23.07 2.15.08 11.08.07
1.05.03.03(.01) NEH M&V (need RP Input) 10.06 2.22.07 1.24.07 3.12.07 4.23.07 2.15.08 11.01.07
1.05.03.04 XVTS M&V 2.15.06 1.25.06 - 11.14.05 10.18.06 3.21.08 12.11.07
1.05.03.05(.01) FEH M&V (need RP Input) 11.07.06 2.22.07 Combine w/ NEH reviews 2.15.08 1.02.08
Fast Valve - 11.10.06 -- 11.28.06 1.30.07 2.15.08 11.08.07
1.05.04.02.02 Fixed Mask
5.14.04
10.20.06 4.06;5.4.06
8.14.06
11.14.06 2.15.08 11.08.07
1.05.04.02.03 Slit10.20.06 4.06;
5.4.0612.14.06 2.15.08 11.08.07
1.05.04.02.05 Attenuator 2.03.06 10.31.06 4.13.06 12.01.06 3.02.07 2.15.08 11.08.07
1.05.04.02.07.01 FEL Offset - Low 10.27.06 1.08.07 11.22.06 2..06.07 4.23.07 2.15.08 11.08.07
1.05.04.02.07.02 FEL Offset - High 1.03.07 2.07 2.07 5.07 8.07 4.29.08 11.08.07
1.05.05.03.01 Direct Imager 10.13.06 11.28.06 10.27.06 1.12.07 3.15.07 2.15.08 11.08.07
1.05.05.03.02 Gas Detector 6.23.06 10.30.06 6.27.06 10.27.06 1.29.07 2.15.08 11.08.07
1.05.05.03.07 NEH Imager 2.05.07 4.24.07 3.27.07 5.22.07 8.10.07 2.15.08 11.01.07
1.05.05.03.08 FEH Imager 2.20.07 5.08.07 4.10.07 6.06.07 8.10.07 2.15.08 1.02.08
1.05.05.04.02 Total Energy Monitor 8.06 10.068.17.0610.06.06
12.06 3.07 2.15.08 11.08.07
1.05.05.04.04 Low Energy Spectrometer 11.03.06 1.05.07 11.21.06 1.23.07 3.21.07 2.15.08 11.08.07
1.05..05.04.05 Pop Ups (N) 1.23.07 3.28.07 2.28.07 5.16.07 8.08.07 4.16.08 11.08.07
1.05..05.04.06 K-Spectrometer 12.14.06 2.28.07 1.30.06 4.25.07 7.20.07 3.08? 11.08.07
XTOD Key Dates
Completed Near Term Completion (<1mo)
Donn H. McMahon
XTOD Breakout: XTOD FY07 Schedule [email protected]
October 12, 2006UCRL-PRES-225471
Target XTOD Dates
Key Documents Design Reviews Install B.O.
WBS Description PRD ESD SCR PDR FDR Cooccupancy
1.05.03.02 FEE M&V (need RP Input) 10.06 2.22.07 1.24.07 3.12.07 4.23.07 2.15.08 11.08.07
1.05.03.03(.01) NEH M&V (need RP Input) 10.06 2.22.07 1.24.07 3.12.07 4.23.07 2.15.08 11.01.07
1.05.03.04 XVTS M&V 2.15.06 1.25.06 - 11.14.05 10.18.06 3.21.08 12.11.07
1.05.03.05(.01) FEH M&V (need RP Input) 11.07.06 2.22.07 Combine w/ NEH reviews 2.15.08 1.02.08
Fast Valve - 11.10.06 -- 11.28.06 1.30.07 2.15.08 11.08.07
1.05.04.02.02 Fixed Mask
5.14.04
10.20.06 4.06;5.4.06
8.14.06
11.14.06 2.15.08 11.08.07
1.05.04.02.03 Slit10.20.06 4.06;
5.4.0612.14.06 2.15.08 11.08.07
1.05.04.02.05 Attenuator 2.03.06 10.31.06 4.13.06 12.01.06 3.02.07 2.15.08 11.08.07
1.05.04.02.07.01 FEL Offset - Low 10.27.06 1.08.07 11.22.06 2..06.07 4.23.07 2.15.08 11.08.07
1.05.04.02.07.02 FEL Offset - High 1.03.07 2.07 2.07 5.07 8.07 4.29.08 11.08.07
1.05.05.03.01 Direct Imager 10.13.06 11.28.06 10.27.06 1.12.07 3.15.07 2.15.08 11.08.07
1.05.05.03.02 Gas Detector 6.23.06 10.30.06 6.27.06 10.27.06 1.29.07 2.15.08 11.08.07
1.05.05.03.07 NEH Imager 2.05.07 4.24.07 3.27.07 5.22.07 8.10.07 2.15.08 11.01.07
1.05.05.03.08 FEH Imager 2.20.07 5.08.07 4.10.07 6.06.07 8.10.07 2.15.08 1.02.08
1.05.05.04.02 Total Energy Monitor 8.06 10.068.17.0610.06.06
12.06 3.07 2.15.08 11.08.07
1.05.05.04.04 Low Energy Spectrometer 11.03.06 1.05.07 11.21.06 1.23.07 3.21.07 2.15.08 11.08.07
1.05..05.04.05 Pop Ups (N) 1.23.07 3.28.07 2.28.07 5.16.07 8.08.07 4.16.08 11.08.07
1.05..05.04.06 K-Spectrometer 12.14.06 2.28.07 1.30.06 4.25.07 7.20.07 3.08? 11.08.07
XTOD Key Dates – 6 Month Look ahead (<6/07)
Completed
Donn H. McMahon
XTOD Breakout: XTOD FY07 Schedule [email protected]
October 12, 2006UCRL-PRES-225471
XTOD milestones have been revised per scope changes and new Beneficial Occupancy dates
XTOD Level 3 Milestones
MS # MS ID Milestone Title Date* Milestone Completion Criteria
113
MS3_XT035 Low Energy Spectral Measurement Design Review Complete
7/21/2007 This milestone is complete when the designs of the low energy spectral measurement instruments have been certified as ready for procurement.
122
MS3_XT009 Far Hall Mech/Vac Design Review Complete
5/27/2007 This milestone is complete when the design of the mechanical and vacuum assemblies of the Endstation Systems that are located in the Far Experimental Hall has been approved as ready for procurement.
116
MS3_XT025 Solid Attenuator Ready to Ship to SLAC
4/15/08 This milestone is complete when the solid attenuator system has been completed by the vendor and is ready to ship to SLAC.
117
MS3_XT043 Start XTOD Installation in Near Hall 4/15/2008 This milestone is complete when the NEH has been certified as ready for installation of x-ray transport and optics components.
120
MS3_XT030 Fixed Mask Ready to Ship to SLAC 4/15/2008 This milestone is complete when the fixed Mask system has been completed by the vendor and is ready to ship to SLAC.
121MS3_XT007 Tunnel Mech/Vac Design Review
Complete12/26/2006 This milestone is complete when the LCLS X-TOD transport
tunnel hardware design is complete.
128MS3_XT060 Total Energy Measurement Installation
Complete5/13/08 This milestone is complete when the total energy
measurement system has been installed.
123MS3_XT040 Solid Attenuator Installation Complete 5/7/08 This milestone is complete when the solid attenuator system
has been installed.
* Proposed Dates
Donn H. McMahon
XTOD Breakout: XTOD FY07 Schedule [email protected]
October 12, 2006UCRL-PRES-225471
XTOD milestones have been revised per scope changes and new Beneficial Occupancy dates
* Proposed Dates
XTOD Level 3 Milestones
MS # MS ID Milestone Title Date* Milestone Completion Criteria
124MS3_XT045 Gas Attenuator Installation Complete 5/7/08 This milestone is complete when the gas attenuator system
has been installed.
131MS3_XT050 Tunnel Mech/Vac Installation
Complete6/15/2008 This milestone is complete when the LCLS X-TOD transport
tunnel hardware has been installed and is ready for x-rays.
127
MS3_XT000 FEE Mechanical/Vacuum Installation Complete
9/16/08 This milestone is complete when the mechanical and vacuum components of the Endstation Systems have been installed and certified as operational in the FEE.
126
MS3_XT080 Start Front End Enclosure Checkout 9/16/08 This milestone is complete when the XTOD instrumentation has been installed through the FEE and it is possible to pump down the beam line through the FEE, and the XTOD instrumentation can be powered up.
129
MS3_XT066 Start Near Experimental Hall Checkout 8/17/2008 This milestone is complete when the XTOD instrumentation and vacuum systems have been installed in the first hutch, and it is possible to have an unobstructed vacuum pathway from the FEE through the first hutch, and the XTOD instrumentation can be powered
130
MS3_XT071 Start Far Experimental Hall Checkout 8/17/2008 This milestone is complete when the XTOD instrumentation and vacuum systems have been installed in the first hutch, and it is possible to have an unobstructed vacuum pathway from the tumble through the first hutch, and the XTOD instrumentation can be powered
Donn H. McMahon
XTOD Breakout: XTOD FY07 Schedule [email protected]
October 12, 2006UCRL-PRES-225471
The FEL Offset Mirror Systems are critical systems for LCLS Experimental Operations
Low Energy Mirror System: Final PRD preparation
nearly complete
Donn H. McMahon
XTOD Breakout: XTOD FY07 Schedule [email protected]
October 12, 2006UCRL-PRES-225471
The FEL Offset Mirror Systems are critical systems for LCLS Experimental Operations
The High Energy Mirror System requires long
lead procurements
Donn H. McMahon
XTOD Breakout: XTOD FY07 Schedule [email protected]
October 12, 2006UCRL-PRES-225471
XTOD is approximately 36% complete (current baseline) and is tracking schedule and performance plans
FY07 is the largest funding year at $12M and includes nearly all XTOD procurements
X-RAY TRANSPORT & DIAGNOSTICS SYSTEMS (TEC) - Cost + Open Commitments vs BCWS ($K)
-5,000.0
0.0
5,000.0
10,000.0
15,000.0
20,000.0
25,000.0
Mo S+O 601.1 459.0 -37.4 620.4 646.0 623.8 542.9 595.1 643.8 522.1 486.5 436.8 1,489.8 285.2 832.6 1,261.2 2,761.8 1,806.1 652.9 162.0 229.7 279.4 717.2 486.5
Mo S
Cum S+O
Cum S
10_05 11_05 12_05 01_06 02_06 03_06 04_06 05_06 06_06 07_06 08_06 09_06 10_06 11_06 12_06 01_07 02_07 03_07 04_07 05_07 06_07 07_07 08_07 09_07
-2,000,000
0
2,000,000
4,000,000
6,000,000
8,000,000
10,000,000
12,000,000
Mo S 4,355,692 451,262 601,056 458,997 -34,418 590,136 515,929 582,847 541,147 595,091 -111,160 505,660 752,608
Mo P
Mo A
Cum S
Cum P
Cum A
Prior Mo's SEP_05 OCT_05 NOV_05 DEC_05 JAN_06 FEB_06 MAR_06 APR_06 MAY_06 JUN_06 JUL_06 AUG_06
FY06
Donn H. McMahon
XTOD Breakout: XTOD FY07 Schedule [email protected]
October 12, 2006UCRL-PRES-225471
XTOD work flow will follow ISMS practices for each WBS element
LCLS Physics Requirements
WBS Dictionary
Eng. Safety Notes Certified Parts
Lists
ICDs
IWS (Integrated Work Sheet) is LLNL wide e-form for documenting ISMS for each work
package:Scope
HazardsControls
Roles (RI…) Responsibilities
TrainingSignoff
Designs
HardwareInstallationOperationsServicing
ESDs
Donn H. McMahon
XTOD Breakout: XTOD FY07 Schedule [email protected]
October 12, 2006UCRL-PRES-225471
Integrated Safety Worksheets will be Developed for Each Task
12599 B Testing of Prototype Gas Attenuator Vacuum System Shen 132S/1571 approved
12662 BLLNL Collaboration at Stanford LCLS: Off-Site Work Bionta SLAC approved
12877 BLCLS Optics testing at DESY laboratory in Hamburg Germany Bionta DESY approved
12920 B LCLS X-Ray Tunnel Vacuum Transport System BiontaTrent/ McKernan 132S/Labs SLAC in review
up to R. Bionta
13253 B LCLS Solid Attenuator Shen 132S/1571 SLAC
awaiting pre-start review
13321 C LCLS Total Energy Monitor Friedrich Niedermayr132S/various in review
up to Friedrich
13453 B LCLS Fixed Mask, and X-Ray Slit Bionta Trent 132S/1571 141/1145 SLAC in review
awaiting pre-start review
13474 B B141 LCLS lab Bionta McKernan 141/1145 approved
13474 B B141 LCLS lab .01 version Bionta McKernan 141/1145 in review
waiting on ES&H Team
13527 B LCLS Gas Detector Bionta McMahon 132S/1571 141/1145 SLAC in review
awaiting pre-start review
13680 B LCLS Direct Imager Bionta McMahon 132S/1571 141/1145 SLAC draft
awaiting pre-start review
Status NotesAlt-RILocation
1Location
2Location
3IWS# WAL Title RI
Donn H. McMahon
XTOD Breakout: XTOD FY07 Schedule [email protected]
October 12, 2006UCRL-PRES-225471
SummaryFY2006 was a design and replan year
Scope changes were accommodatedRevised Estimate to Complete (ETC)The go forward plan will meet required install and commissioning dates
FY07 is characterized by the design completion and procurement of all systems with most ready for shipping to SLAC for BO
Many physics requirements have been finalizedXTOD designs have been undergoing reviews
Nearly all XTOD staff has been added and aligned with WBS elementsXTOD is tracking the current planCritical path items are being actively scrutinized to ensure success (concurrent tasking and early procurement of long lead items)Work flow follows the principle of ISM (development to install/commissioning)