福島核災後龍門電廠(核四廠)壓力測試評估 review of the post

64
1 福島核災後龍門電廠(核四廠)壓力測試評估 Review of the post-Fukushima nuclear stress-tests of the Lungmen nuclear power plant (NPP4) 綠色和平東亞辦公室委托壓力測試評估報告 歐妲.貝克 漢諾瓦 2013 8 Study commissioned by Greenpeace East Asia Oda Becker Hannover, August 2013 主要作者:Dipl. Phys. 歐妲.貝克漢諾瓦(德國), [email protected] 協助:瑪格.帕特里夏.洛倫茨 Author: Dipl. Phys. Oda Becker, Hannover (Germany), [email protected] with Mag. Patricia Lorenz

Upload: tranngoc

Post on 30-Dec-2016

261 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 福島核災後龍門電廠(核四廠)壓力測試評估 Review of the post

1

福島核災後龍門電廠(核四廠)壓力測試評估

Review of the post-Fukushima nuclear stress-tests of the

Lungmen nuclear power plant (NPP4)

綠色和平東亞辦公室委托壓力測試評估報告

歐妲.貝克

漢諾瓦 2013 年 8 月

Study commissioned by Greenpeace East Asia

Oda Becker

Hannover, August 2013

主要作者:Dipl. Phys. 歐妲.貝克,漢諾瓦(德國), [email protected]

協助:瑪格.帕特里夏.洛倫茨

Author:

Dipl. Phys. Oda Becker, Hannover (Germany), [email protected]

with Mag. Patricia Lorenz

Page 2: 福島核災後龍門電廠(核四廠)壓力測試評估 Review of the post

2

摘要

臺灣原能會在 2012 年宣布將採用在歐盟實施的福島核災後壓力測試方式作為基礎,進行

臺灣核電廠的壓力測試。

如同歐盟,綠色和平邀請物理學家 Oda Becker 針對臺灣目前核能計畫的重點──核四廠的

壓力測試報告進行評估。此次評估中得到一個清楚的結論,若要改善反應爐目前的狀態以

把核災風險降至最低是有困難的。此外,再加上因福島核災後對於核四廠的核安升級建議

不甚明確,便已足夠構成充分的理由說明核四廠不應該繼續興建,直至最終取得運轉執

照。核四廠與臺北市的距離很近,因此不可能將 核四廠提升至相應合理的安全水準。如此

不可排除的核災發生時,將會造成數百萬人的災難。

本報告的第一章介紹臺灣核能發電的現況以及核四廠的歷史。

接著評析福島核災後歐盟執行的壓力測試程序,該程序為臺灣目前核安壓力測試的基礎。

福島核災的恐怖結果是由數十年來錯誤的安全管理原則所造成,強大核能工業壓力的影響

下,導致核能管制機構的安全規範極度鬆散,這問題不只存在於日本。該事件讓歐盟感到

震撼,促使歐盟深切的希望能對於核能及其相關安全性之問題有所改變,並且將絕對有可

能發生的意外事件,但以往因發生的機率很小而被忽略的事件均納入核安的考量之中。

針對此次事件的回應,歐盟進行了一系列的壓力測試,希望這些測試可以降低歐洲國家的

核災風險。此次壓力測試讓歐洲建有核電廠的國家開始著手訂立國家型行動計劃,就過去

兩年中所發現的缺失加以改善。綠色和平針對這些計劃進行評估,而評估結果指出,儘管

在壓力測試後歐盟國家已經大量投入與核能安全相關的安全升級,但許多關鍵的核安相關

的問題仍然未獲解決。另外,即使是目前已經在處理的問題,也需要再幾年的時間才能予

以修正,在此期間,歐洲人民仍暴露在核災風險之中。

針對歐盟壓力測試的批評包括:其測試廣度有限、缺乏明確標準、同儕審核(peer-review

)流程的侷限性以及參與的專家缺乏獨立性。歐盟管制機構之所以宣稱其壓力測試獲得最

高分,是因為這些國家即使知道自己的反應爐有缺陷,仍然打算持續運轉。公民組織的代

表及專家憂心,歐盟的壓力測試主要目的僅是用來提升歐洲核電管理部門對於核能安全的

信心,而不是真正探究核能本身已經或將會產生的問題。

第三章在描述臺灣壓力測試的設計和現狀。其中發現,臺灣的壓力測試重蹈歐盟壓力測試

中的缺失。本報告更進一步的聚焦於核四廠執行的壓力測試。

在臺灣,地震是重要的現實問題。目前的評估採用 400 年的地震歷史,並不足以當作為設

計基準地震(DBE)。歐盟的地震重現期建議以一萬年做週期計算。臺灣的核安管制機構

原能會沒有訂立出設計基準地震(DBE)的標準要求。核四廠 的耐震設計更被認定無法應

付設計基準以外的狀況。目前無法得知臺電在核四取得執照運轉前,是否會先改善原能會

所提出的缺失。

核四廠目前無法應付海嘯和極端氣候所導致的洪水風險。再者,目前的洪水設計所依據的

海嘯數據分析不夠充足,必須重新定義。

排水系統亦不足以因應歐盟建議的以每一萬年一次的極端降雨狀況,而僅能因應一百年一

次的極端降雨標準。壓力測試揭露了核四的危險性和斷崖效應(cliff edge effects),並且

顯示洪水可能會導致危險事故。

此外,政府間氣候變遷小組(IPCC)預測極端氣候發生頻率將增加的趨勢,核四廠亦未充

分考量。

Page 3: 福島核災後龍門電廠(核四廠)壓力測試評估 Review of the post

3

這份評估結果點出幾項當核電廠遇到廠外電源喪失(off-site power losses)的情況時會有的

弱點。尤其在一些事故,如:地震或者極端天然災害發生時,並不能確保可以仰賴場外緊

急應變措施。目前臺電提出少數可增加緊急應變措施健全性措施,且該類措施需要額外的

人為手動啟用,而前述災害發生時,人為手動啟用很可能受阻。

缺少備用的最終熱沉(loss of ultimate hear sink),此為歐盟核電廠用以大幅減低最終熱沉

失效的風險的常見措施,但原委會僅為消極的建議臺電就此進行評估。目前提出的評估報

告中,於考量可能的意外狀況範疇時,一直都沒有充分地評估如果設備雙重故障(兩個反

應爐同時失效)或輻射外洩意外時該如何應變。

評估發現,嚴重事故的管理(SAM)也大有問題,包括:洩壓和反應爐壓力槽(RPV)失

效的問題。原能會皆未積極要求核四廠須具備圍阻體過濾排氣系統以及能防止氫爆的被動

式氫氣再結合器(PAR)。報告強調,嚴重事故管理(SAM)措施如果沒有做好將會使放

射性物質釋放到環境中。

近期較新式的進步型沸水式反應器已配有爐心捕集器(core-catcher),但核四廠卻採用舊

型進步型沸水式反應器的設計,無法得知若產生爐心熔穿效應(melt-through)發生時,是

否有足以因應。

針對發生重大事故時,放射性廢水水量的分析和防止其廢水洩漏到海中的管理措施不夠充

分。另外,有關重大事故中的用過燃料池的相關分析,與歐盟壓力測試報告中相同議題的

分析結果相比,極為不足。

斷然處置措施(Urgent Response Guidelines)裡實施的時機不適當,並且使人擔憂。經濟合

作暨發展組織(OECD)特別提出,若將斷然處置程序措施引(ultimate response guideline)

與緊急操作程序書(emergency operating procedures)、嚴重事故處理指引(severe accident

management guidelines)及大範圍廠區受損救援指引(extensive damage mitigation guidelines )

進行整合,將導致更多的困惑。

第四章闡述壓力測試以外的其他議題。部份內容主要取得於《遠見雜誌》2013 年 3 月對林

宗堯先生的專訪。報導指出核四廠在設備採購和設計修改時的缺失、核四廠不安全之處、

施工中所發生的事以及失敗的品質保證(QA)。儀控(I&C)系統架構相關的問題則涵蓋

缺乏傳統類比硬體接線(hard-wired)系統作為後備,此項後備系統目前在芬蘭和美國的歐

洲壓水式反應爐(EPR)為必要的設計。另外一個問題則是,試運轉流程並非由獨立的測

試人員進行,而是臺電公司自己的員工進行檢測。本章於結論中亦分析臺灣核能管理機構

--原能會是否能提供獨立性的有效監督與控管。

第五章分析比較新型歐洲進步型沸水式反應器(EU-ABWR)與核四廠所採用的過時進步

型沸水式反應器(ABWR)設計,並突顯一些未被解決的問題,包括:大型飛機撞擊防護

、被動式隔離冷凝器系統、爐心捕集器、被動式圍阻體冷卻系統,以及嚴重事故專用的電

源供應管理。

從第六章的總結中可得到清楚的評斷:就現有的天然災害而言,核四廠 具有設計上的弱點

以及在結構、系統與組件上的缺陷,這些缺陷不可能因改善而達到可被接受的安全層級。

因此,導致大量放射性物質外洩的嚴重意外是有可能發生。考量到核四廠與臺北市相距甚

近,若發生此類嚴重意外,數百萬人將會受災。

根據所列出的種種事實,建議終止核四廠計畫並且不讓核四廠運轉。

Oda Becker

2013 年於漢諾威

Page 4: 福島核災後龍門電廠(核四廠)壓力測試評估 Review of the post

4

EXECUTIVE SUMMARY

The nuclear regulator of Taiwan announced in 2012 it wanted to carry out nuclear stress

tests of its nuclear park on the basis of the post-Fukushima nuclear stress tests carried out

in the EU.

Like in the EU, Greenpeace commissioned physicist Oda Becker to carry out an

assessment of the stress test reports of a key project for the Taiwanese nuclear

programme, the Lungmen nuclear power plant (NPP4). The review comes to the

conclusion that it would be difficult to backfit the reactor in its current state so that it

would meet state of the art risk reduction levels. Furthermore, lack of clarity about the

proposed post-Fukushima upgrades should be sufficient reason not forward the project to

final licensing. It is not feasible to bring the NPP4 to a safety level that can be justified

facing the fact of its short distance to the city of Taipei. A severe accident, which cannot

be excluded, would have disastrous consequences for millions of people.

In Chapter 1, this report provides an introduction into the status of nuclear power in

Taiwan and the history of the Lungmen nuclear power plant, also known as the Fourth

nuclear power plant (NPP4).

This is followed by a critical overview of the EU post-Fukushima nuclear stress tests that

form the basis for those in Taiwan. The Fukushima catastrophe was the horrible result of

decades of mistaken safety philosophy, a very lax safety regulation under strong industry

influence on the regulators – not only in Japan. The first shock led in the EU to the honest

wish to change this, to also involve events which are definitely possible but were kept out

of the safety cases by using probabilities.

In response, the European Union carried out a series of nuclear stress tests, introduced as

a transparent exercise to reduce the risk of nuclear energy in Europe. As a result, the

countries with nuclear power stations worked out national action plans to address

weaknesses that emerged during the two years of analysis. In spite of significant

investments into safety upgrades following the tests1, many vital and known issues were,

however, not addressed. Even problems that are being dealt with will take years to be

remedied – leaving European citizens exposed to these risks in the meantime.

Criticism on the EU stress tests include its limited scope, the lack of clear criteria, the

limitations of the peer-review process and insufficient independence of the involved

experts.

While national regulators claimed receiving the highest scores for their stress tests, they

intend to let reactors continue to run despite known flaws. This gave credence to the fear

of representatives of civil society and independent experts that the stress tests were

mainly set up to improve the confidence in the safety of the European nuclear power

sector regardless of his findings.

In Chapter 3, the set-up and state of the Taiwanese nuclear stress tests is described. It is

found that these stress tests repeat the flaws of the EU stress tests. It further concentrates

on the stress tests of the Lungmen nuclear power station (NPP4).

1 The European Commission estimates the total costs of nuclear upgrades in the EU following the stress-

tests at around 25 Billion EUR; http://www.nytimes.com/2012/10/04/world/europe/safety-review-says-

europes-nuclear-reactors-need-repair.html?_r=0

Page 5: 福島核災後龍門電廠(核四廠)壓力測試評估 Review of the post

5

The issue of earthquakes is a crucial one for Taiwan reality. It is concluded that the

current assessment of 400 years of earthquake history is insufficient for determining

design based earthquake (DBE) criteria. Taiwanese nuclear regulator AEC does not give

requirements for the return frequency of earthquakes for determining DBE, whereas the

EU recommends one of 10-4

per annum. The seismic resistance of NPP4 is furthermore

deemed insufficient in beyond design base situations. It remains unclear whether the

already by AEC acknowledged shortfalls have to be remedied before the start-up license

is received.

Flooding risks continue to be of unacceptable level both during tsunamis and extreme

weather. The analysis for the design basis tsunami are inadequate and needs to be

redefined.

Drainage systems are not sufficient to deal with the EU recommended standard of once in

10 000 years, but only once in 100 years extreme precipitation. The stress tests revealed

dangerous weak points and cliff edge effects that show that flooding could result in a

dangerous accident situation.

Also the preparation for an increase in extreme weather events as predicted by the

Intergovernmental Panel on Climate Change (IPCC) is insufficient.

This review surfaces several weaknesses in meeting off-site power losses. Especially the

reliance on off-site emergency services in some cases cannot be guaranteed in cases of an

earthquake or extreme weather catastrophe. Envisioned measures to increase robustness

are limited and need additional manual action, which might be challenging under extreme

circumstances.

The lack of an alternate ultimate heat sink, a usual EU practice that could reduce risks of

loss of ultimate heat sink (UHS) considerably, is only recommended by the regulator

AEC for evaluation. Dual unit failure (both reactors failing at the same time) and

accidents with the spent fuel have been insufficiently included in potential accident

scenarios.

The study finds several important issues in severe accident management (SAM),

including issues concerning depressurisation and reactor pressure vessel (RPV) failure.

The lack of a filtered containment venting system is criticised, as well as the lack of

passive autocatalytic recombiners (PARs) to prevent hydrogen explosions and the fact

that AEC does not aggressively prescribe these. The issue of SAM measures that would

de-facto release radioactive substances into the environment is highlighted.

Where newer ABWR designs are equipped with a so called core catcher, it is not clear

whether the measures for melt-through at NPP4, which is an older ABWR version, are

sufficient.

Management of radioactive water amounts and leakage to the sea during large accidents

are found insufficiently analysed. Accidents involving the spent fuel pools are in

comparison with the already inadequate EU recommendations insufficiently analysed.

The implementation timing of the Urgent Response Guidelines (URGs) appear

insufficient, and there exists concern, among others voiced by the OECD, that the

proposed integration of emergency operating procedures (EOPs), severe accident

management guidelines (SAMGs), and extensive damage mitigation guidelines (EDMGs)

with the ultimate response guidelines (URGs) will lead to more confusion.

Page 6: 福島核災後龍門電廠(核四廠)壓力測試評估 Review of the post

6

Chapter 4 highlights issues that are not addressed in the stress tests. This is largely based

on a March 2013 special interview with Tsung Yao Lin by Global View Monthly. It

points out shortcomings during procurement of equipment, design alternations,

inadequacies in safety culture, incidents during the construction process and failing

quality insurance (QA). Concerns regarding the information and control (I&C) system

architecture include the lack of a hard-wired back-up as now required for the EPR reactor

designs in Finland and the US. Problems during test-operation procedures created a

situation in which not independent test operators, but TPC own operators carried out tests.

The chapter concludes with an analysis of the question whether the regulator AEC is

sufficiently equipped to provide independent oversight.

In Chapter 5, the newer EU-ABWR is analysed and compared with the outdated ABWR

design of the NPP4, highlighting several issues that remain unaddressed. This includes

protection against impacts from large aircraft, a passive isolation condenser system, a

core catcher, a passive containment cooling system and a dedicated power supply for

severe accident management.

The conclusions in Chapter 6 lead to a final sobering judgment:

Regarding the existing natural hazards, the design weaknesses and the deficiencies of the

structures, system and components, it is not possible to retrospectively bring the NPP4 to

an acceptable safety level. Therefore, a severe accident with a major release of

radioactive substances cannot be excluded.

Considering the short distance of the NPP4 to the city of Taipei, such a severe accident

would have disastrous consequences for millions of people.

Taking all facts into account it is recommended to stop the NPP4 project and to not

commission this nuclear power plant.

Oda Becker

Hannover, 2013

Page 7: 福島核災後龍門電廠(核四廠)壓力測試評估 Review of the post

7

Table of Contents 1 Introduction .............................................................................................................................. 8

1.1 Nuclear Power in Taiwan.................................................................................................. 9

1.2 Introduction Lungmen NPP ............................................................................................ 10

2 The EU stress tests ................................................................................................................. 12

2.1 Shortcomings of the EU stress tests ................................................................................ 12

2.2 Procedure ........................................................................................................................ 15

2.3 ENSREG s results of the National Actions Plans........................................................... 16

2.4 Discussion of the ENSREG s results .............................................................................. 17

2.5 Conclusion of the critical review of the EU stress tests .................................................. 18

3 Weaknesses the Taiwanese stress tests revealed ................................................................... 21

3.1 Earthquakes ..................................................................................................................... 21

3.2 Flooding .......................................................................................................................... 26

3.3 Other extreme natural hazards ........................................................................................ 30

3.4 Loss of all power supply (SBO) and ultimate heat sink (UHS) ...................................... 32

3.5 Severe Accident Management ........................................................................................ 36

4 Weaknesses the Taiwanese stress tests ignored ..................................................................... 43

4.1 Shortcoming during procurement of equipment ............................................................. 43

4.2 Many design changes ...................................................................................................... 44

4.3 Inadequate safety culture ................................................................................................ 44

4.4 Incidents during the construction process ....................................................................... 45

4.5 Insufficient quality assurance (QA) ................................................................................ 46

4.6 Concerns regarding the I&C System .............................................................................. 47

4.7 Inappropriate test-operation procedures ......................................................................... 47

4.8 Role of the Atomic Energy Council (AEC) .................................................................... 48

5 The EU-ABWR ...................................................................................................................... 50

5.1 Defence-in-Depth Concept ............................................................................................. 51

5.2 Technical realisation of DiD requirements ..................................................................... 52

5.3 Severe Accidents (DiD Level 4) ..................................................................................... 53

6 Discussion of the results and conclusions .............................................................................. 55

7 References .............................................................................................................................. 60

8 Abbreviations ......................................................................................................................... 63

Page 8: 福島核災後龍門電廠(核四廠)壓力測試評估 Review of the post

8

1 Introduction

One important lesson of the Fukushima accident is that nuclear accidents really occur –

even in developed industrialised countries. The operation of nuclear power plants is

always without any exception connected with the residual risk of an uncontrolled nuclear

accident.2

Nuclear safety in the absolute sense does not exist. The expression “a nuclear

plant is safe” only means that the residual risk is accepted [WENISCH 2012].

Taiwan has performed a stress tests exercise for its nuclear power plants largely based

upon the EU stress tests model. In late 2012, Taiwan invited the European Commission to

set up a peer review of these stress tests. Based upon this request, the Commission

organised a review team by selecting volunteering experts from its ENSREG group as

well as from its own Services. A nine-person team of nuclear safety specialists will

conduct a peer review of the country's three operating nuclear power plants and the unit

under construction (Lungmen NPP).

In April 2013, Greenpeace East Asia commissioned Oda Becker, a German nuclear

expert, to prepare a critical review of the stress tests of the Forth Nuclear Power Plant in

Taiwan (Lungmen NPP or NPP4).

These evaluations3 do not claim to be exhaustive, but the findings contribute to a more

comprehensive understanding of safety and risk of the NPP4.

After a short general introduction about nuclear power in Taiwan, chapter 2 of this report

gives an overview on the stress tests performed in Europe. It describes the shortcomings

and limits of the stress tests specifications as well as the intermediate results (including a

critical review) of the ongoing follow-up stress tests procedure.

Chapter 3 discusses the weaknesses of the NPP4 that have been revealed during the stress

tests and the measures proposed by the operator (Taiwan Power Company – TPC) and

national regulator (Atomic Energy Council – AEC) to remedy these weaknesses.

The construction of the NPP4 was accompanied with several problems. These problems

result in safety issues which are out of the scope of the stress tests. The most important

shortcomings are discussed in chapter 4.

2 The core melt probability of nuclear power plants is about 1: 100,000 per year and plant. This means a

core melt probability in any plant around the world of about 1: 230 per year and a core melt probability

of about 1:2500 per plant within an operation time of 40 years. But the accidents at Chernobyl and

Fukushima proved that the real occurrence of accidents is not the same as the calculated probability. 3 The evaluations are based on the studies “Critical Review of the EU Stress Test performed on Nuclear

Power Plants” published in May 2012 and the “Critical Review of the National Action Plan (NAcP); EU

Stress Test performed on Nuclear Power Plants” published in April 2013 [WENISCH 2012; BECKER

2013].

Page 9: 福島核災後龍門電廠(核四廠)壓力測試評估 Review of the post

9

To complete the picture, chapter 5 presents the design improvements of the EU-ABWR,

which is the adaption of the reactor design of the NPP4 to the European market.

The last chapter discusses the findings and formulates conclusions.

1.1 Nuclear Power in Taiwan

In Taiwan, there are currently three operating nuclear power plants (NPPs): Chinshan,

Kuosheng and Maanshan, which are also called the first, second and third NPP,

respectively. Each of these NPPs is equipped with two identical reactors. In addition,

there is a nuclear power plant under construction, the Lungmen NPP (LMNPP), or the

fourth NPP (NPP4), comprising two units. All the nuclear power plants are owned and

operated by the state-owned Taiwan Power Company (TPC).

In 2012, the three operating NPPs provided 38.7 TWh or 18.4 percent of the country’s

electricity (down from a maximum of 41 percent in 1988). Taiwan’s nuclear program has

a certain number of very specific problems. The nuclear plants are located in areas with

high population density, high seismicity and at risk from tsunamis. In addition, with the

absence of a long-term waste strategy, the spent fuel pools are filling up and, in spite of

re-racking and dense-packing, the first pools are expected to be full by 2014

[SCHNEIDER 2013].

In November 2011, the government presented a new energy strategy to “steadily reduce

nuclear dependency, create a low-carbon green energy environment and gradually move

towards a nuclear-free homeland” [WNN 2011a].

The new policy4 states that the three operating nuclear power plants will not operate

beyond their planned 40-year lives and that Taiwan's fourth nuclear power plant at

Lungmen will not begin operation until all safety requirements are met. Furthermore, the

island's oldest units at Chinshan (grid connection 1977 and 1978) will face early closure

when both Lungmen units will start commercial operation. In parallel, Taiwan plans to

accelerate its energy efficiency and renewable energy policy.

The Taiwanese public is increasingly critical towards the country’s nuclear power

program, and on March 9, 2013 more than 200,000 people demonstrated in various cities

against the start-up of the Lungmen plant. An opinion survey released in late March 2013

indicated that a 73 percent majority is in favor of stopping the construction of the

Lungmen plant.

In fact, in recent years the Taiwanese anti-nuke campaign has grown from minor or rare

social events to a new major movement. On May 28, 2012, movie directors Yi Cheng Ko

and Li Ren Dai have initiated the “I am human being and I refuse nuclear power”

4 The new policy is in line with Article 23 of the Basic Environment Act, which directs the government to

make plans that will eventually see Taiwan become nuclear-free.

Page 10: 福島核災後龍門電廠(核四廠)壓力測試評估 Review of the post

10

campaign. They made use of the traffic light and arranged a big “human being” in

Chinese characters on Ketagalan Boulevard, right in front of the presidential office

building. This received a sizeable response.

While performing at Golden Melody Awards in 2012, influential band Mayday also

showed their stance by shining “I am human and I refuse nuclear power” LED lighting on

stage. Other famous entertainers have also publicly stated their anti-nuke attitude.

1.2 Introduction Lungmen NPP

The Lungmen nuclear power plant (LMNPP) or the Fourth nuclear power plant (NPP4)

facing the Pacific Ocean is located at an inward bay area of northeast Taiwan. The site is

situated only approximately 40 kilometres east of Taipei city. About 1.5 million people

are living in the the 30-km-radius of the site and about 9.14 million people are living in

the 75-km-radius [NATURE 2011].

The NPP4 comprises two units. The reactor type used is ABWR (Advanced Boiling

Water Reactors).

Since the Atomic Energy Council (AEC) issued a construction permit for the fourth

nuclear power plant in March 1999, the plant has remained a highly controversial issue5.

On October 27, 2000, Taiwan’s cabinet ordered a halt to the construction of the Lungmen

NPP. The decision was taken by the ruling Democratic People’s Party (DPP) and was

opposed by the opposition Kuomintang (KMT) [NEI 2000a]. The project restarted in

2001 after a legal appeal and a government resolution in favor of the plant.

In 2005, it was announced that commissioning of the plant would be delayed to 2009

from the original schedule of 2006 – 2007. Rising oil import costs and a local economic

slowdown had apparently affected investment in the project, which in turn affected the

construction progress. The units were put on track for completion in 2011 and 2012 by a

funding decision in March 2009 [WNN 2011c]. In May 2012, media reports gave 2014 –

15 as the currently planned start-up date.

TPC anticipates that at least 40,000 million NTD need to be added in 2013, which means

the overall budget for NPP4 is likely to top 320,000 million NTD.

In February 2013, the budget was temporarily frozen. According to the Atomic Energy

Council (AEC), the first unit was nearly finished and operator TPC was presently

carrying out on-site testing of operating procedures and systems functions by April 2013.

5 This was the same with the history of the NPP4: TPC has presented the plan to construct NPP4 in May

1980. However, in July 1986 the budget was frozen. In February 1992, the Ministry of Executive

approved to resume implementation of the NPP4 plan. In May 1996, Legislative Yuan passed a bill to

abolish all NPP programs, including stop constructing NPP4. In October 1996, the Legislative Yuan

passed a re-vote bill to nuclear abolition proposed by Executive Yuen.

Page 11: 福島核災後龍門電廠(核四廠)壓力測試評估 Review of the post

11

On April 26, 2013, the ruling party introduced a bill in the legislature to organize a

national referendum over the future of the Lungmen project. What appears to be an

exemplary exercise of democracy is seen by many as a manoeuvre to get a silent majority

for the project’s completion. The referendum legislation requires a quorum of at least 50

percent to make the outcome binding, a score difficult to achieve nationwide

[SCHNEIDER 2013]. All six national referendums held so far in Taiwan have failed to

reach the 50 percent turnout threshold [NW 27/06/13].

Page 12: 福島核災後龍門電廠(核四廠)壓力測試評估 Review of the post

12

2 The EU stress tests

The March 2011 accident at the Fukushima Daiichi nuclear power plant (NPP) proved

that it was not justified to exclude highly unlikely accidents from happening. In a prompt

reaction to this catastrophic accident, the European Council concluded on 25 March,

2011 that the safety of all European (EU) nuclear power plants should be reviewed on the

basis of a comprehensive and transparent risk and safety assessment ("stress tests"). The

European Nuclear Safety Regulators Group (ENSREG) took over this task.

However, two months later the scope of the EU stress tests was reduced: The EU stress

tests were defined as a targeted reassessment of the safety margins of nuclear power

plants developed by ENSREG, with contributions from the European Commission. The

EU stress tests comprise three topics: (1) External Hazards, (2) Loss of Safety Systems

and (3) Management of Severe Accidents.

The idea of a comprehensive risk assessment of the European power plants was not the

intention any more. The specifications of the ENSREG stress test do not provide a

method for comparing the safety of the different plants, nor does it answer how safe

European plants actually are.

2.1 Shortcomings of the EU stress tests

It is important to underline that the EU stress tests cannot be understood as a

comprehensive safety check of the NPP in Europe. The EU stress tests did not take into

account all key safety issues, thus the scope of these tests was not designed to deliver a

comprehensive risk assessment.

Representatives of civil society and independent experts were pointing out that the stress

tests were mainly set up to improve the confidence in the safety of the European NPPs.

In advance to the EU stress tests Wolfgang Renneberg, former head of the Reactor Safety

Department of the German Federal Environment Ministry, analysed the specifications of

the EU stress tests and published his results in a study commissioned by the Greens in the

European Parliament. According to his study, the EU stress tests cannot assess the safety

of the European nuclear power plants and therefore cannot serve as basis to decide which

nuclear power plants need to be shut down. The stress tests will not provide information

about the reliability of plant safety measures to prevent postulated failures of the safety

systems or about all those other scenarios and serious events that could lead to a severe

accident [RENNEBERG 2011].

The specifications and the procedure of the EU stress tests have the following important

shortcomings and limitations [WENISCH 2012]:

Page 13: 福島核災後龍門電廠(核四廠)壓力測試評估 Review of the post

13

Limited scope

The scenarios that are under review are incomplete. Accident scenarios and failure

modes typical for e.g. an airplane crash or internal fire, human failure including

combinations of those events that until now have not been under consideration, are

not covered by the stress tests.

Particularly an air plane crash is not considered in the frame of the stress tests.

ENSREG regards this scenario under the terms of security and therefore claims not

to be competent to include it in the stress tests.6 This is an evidently misleading

argument. The fact that air planes might crash on a nuclear power plant is

completely independent of its cause and it might therefore happen without any

terrorist background. An airplane crash has to be considered as a relevant safety

issue.

Obviously, it is always better to prevent accidents from happening than to deal with

the consequences of an occurred accident, but safety features of the plant that are

needed to prevent an accident are only partly under review.

The quality of the plants’ safety-related systems and components, such as the

material of pipes, reactor vessel, valves and pumps, control and instrumentation

equipment are not investigated in the stress tests. This issue is of particular concern

for NPP4.

Ageing effects of structures, systems and components (SSCs) are not considered in

the stress tests. The tests take no account of degradation effects, even though these

could significantly aggravate the development of an accident caused by an external

event. Ageing-related incidents have the potential to trigger, but particularly to

aggravate accidents sequence.

The stress tests take for granted that all the SSCs assessed are in place and without

fault, but the operational experience shows this is not the reality. Incidents caused

by defective mounting or forgotten scrap etc. are possible. This issue is of

particular concern for NPP4.

The stress test specifications require descriptions of the plant properties, but

requirements on the quality and the comprehensiveness of the descriptions are not

defined. So far as the specifications rely on the licensed design and its safety case,

they rely on aged criteria and methods.

The safety management of nuclear power plants, which is of acute importance, is

not included in the stress tests.

6 Risks due to security threats are not part of the mandate of ENSREG and the prevention and response to

incidents due to malevolent or terrorists acts (including aircraft crashes) involve different competent

authorities, hence it is proposed that the Council establishes a specific working group composed of

Member States and associating the European Commission, within their respective competences, to deal

with these issues [ENSREG 2011].

Page 14: 福島核災後龍門電廠(核四廠)壓力測試評估 Review of the post

14

Another important area of special attention regarding the safety of nuclear power

plants, the quality of personnel training, is not included in the stress tests.

Lack of criteria

One of the major weaknesses is the lack of definition in the stress test specifications,

what level of safety should be achieved if the plants should be back-fitted or should

be shut down. Any criteria that define the required robustness of a plant are missing.

This fact makes it very difficult for politicians and the public to assess the safety

level of the plant.7

Limited peer review process

To enhance the credibility of the stress test process, the national reports will be

subjected to a peer review process. The complexity of data, of calculation methods,

of assumptions about the safety parameters and their interdependence within the

system of a nuclear power plant is extremely high. Regarding the short time frame

(about three months) and the immense workload, it is not possible to perform a

well-founded peer review process.

Insufficient independence of the involved experts

The operators reports are the most important basis for the final national report and

the assessment of the safety of the plant. For obvious reasons, the operators cannot

be considered independent: It is in their interest to demonstrate that a plant does not

require costly back-fitting measures.

The national stress test reports are written be the national nuclear authority. In the

past, those experts and their technical support organisations legitimated the

operation of the power plants under their supervision and they informed the public

that the plants were operating safely. Conducting stress tests makes them review

their own practice and their own statements about safety and about acceptable risks.

Almost none of the other experts involved in the peer review process is really

“independent”. Beside the members of those countries without nuclear power plants

the ENSREG consists mostly of the chairpersons of the nuclear authorities of the

countries operating nuclear power plants. Realistically it is necessary to expect that

this peer review process will identify only evident deficiencies. Furthermore,

criticising colleagues within an official process whose results shall be open to the

public is difficult.

7 The German Reactor Safety Commission has defined four levels of robustness in the frame of the

German stress test. The basic level is chosen as a level that must be fulfilled by all operating plants,

taking into account that all plants meet the licensing conditions and have realised all back-fitting

measures required by the authority. Each of the three levels of robustness defines a specific larger kind

of safety-margin.

Page 15: 福島核災後龍門電廠(核四廠)壓力測試評估 Review of the post

15

Considering the limited scope of the stress tests, the missing of clear assessment criteria,

and taking into account the interests of the involved experts, reports might serve mainly

to demonstrate to the public that the plants are operating safely.

Nevertheless, the stress tests could serve as a first assessment of the plants capability to

withstand several external events. One important new feature which has now been

introduced is the evaluation of the so-called “cliff edge effects”: A cliff edge effect

describes a qualitative degradation of the plant’s safety conditions (comparable to

walking on a cliff and the next step fall down). The tests may result in technical and

organisational recommendations to be better prepared in the case of such accidents.

2.2 Procedure

The first phase of the EU Stress tests started in June 2011 – the operators of the NPPs

prepared a self-evaluation of their plants. Licensees had to provide a final report by

October 31, 2011.

In the second phase, the national regulator reviewed final reports submitted by the

operators. All final national stress test reports were handed over to the EU Commission

by December 31, 2011.

Then the third phase started: the peer review process, which was conducted by experts

nominated by the national states to review the national reports. The peer review was

completed with a main report that includes final conclusions and recommendations at

European level regarding the three topical parts and 17 country reports including country-

specific conclusions and recommendations. The report was published by the ENSREG on

April 26, 2012.

In June 2012, when the ENSREG report was presented to the European Council, the EU

Commission did not see the Council mandate for the stress tests fulfilled and demanded

further testing; six additional so-called fact-finding visits were undertaken. Those follow-

up reports were published in late October 2012.

To implement the stress test findings, an ENSREG action plan (published in August 2012)

was developed to track implementation of the recommendations. In October 2012,

ENSREG published a compilation of recommendations to assist the preparation as well

as the review of National Action Plans (NAcPs).

In line with the ENSREG action plan, each national regulator had set up a NAcP to

remedy the identified shortcomings during the EU stress tests and published it by the end

of 2012. In January 2013, the NAcPs were published at the ENSREG website. Despite

the fact that all participating countries are strongly committed to the issue of transparency,

only about half of them posted the NAcP in their national language on a dedicated

website.

Page 16: 福島核災後龍門電廠(核四廠)壓力測試評估 Review of the post

16

The ENSREG action plan specified the need to peer review these NAcPs via a common

discussion at a dedicated ENSREG-workshop to share lessons learned on the

implementation of post-Fukushima safety improvements. This ENSREG-workshop to

discuss the NAcPs took place in Brussels on 22 – 26 April 2013.

It was the intention to present the outcomes of the workshop to the public in the

following ENSREG conference on June 11 and 12, 2013. However, the presentation was

very general, no country-specific shortcomings were explained. One of the key objectives

of ENSREG to improve the overall transparency on issues relating to the safety of

nuclear installations was not at all fulfilled.

2.3 ENSREG s results of the National Actions Plans

During the EU stress test process, all countries identified the need for analysis, hardware

improvements, procedural modifications and regulatory actions, and corresponding

implementation schedules in their National Actions Plans (NAcPs). In a number of

countries significant safety improvement programmes had been completed or were on-

going prior to the Fukushima accident. On-going programmes were updated to reflect the

ENSREG recommendations and new plans were prepared. Further national review is still

pending, on the basis of on-going investigations and analyses, and may lead to additional

measures [ENSREG 2013].

The ENSREG summarised the following observations after review of the NAcPs:

In all countries, a variety of additional mobile equipment like pumps, diesel

generators, air compressors and other equipment has already been procured.

Some countries are planning new, permanently installed and partly bunkered

systems to ensure the decay heat removal from reactor core and spent fuel pools,

while most countries rely more on mobile equipment to ensure decay heat removal

from reactor core and spent fuel pools in case of extreme situations and loss of the

safety systems.

One of the main issues is the definition of robustness, i.e. the scope of the safety

margins beyond design basis. The question is how robust the equipment necessary

to cope with beyond design situations has to be.

Maintaining containment integrity under severe accident conditions remains an

important unresolved issue for the accident management.

Filtered containment venting to prevent containment overpressure has already been

implemented in certain countries. Some other countries are now implementing the

Filtered Containment Venting System (FCVS) while others are considering

improving the existing ones. Several countries, but in particular those with small

reactors, are implementing or analysing different complementary technical

measures for long-term heat removal from the containment.

Page 17: 福島核災後龍門電廠(核四廠)壓力測試評估 Review of the post

17

As a reaction to the Fukushima Daiichi accident many countries are now installing

Passive Autocatalytic Recombiners (PAR) to manage hydrogen in the containment

to cope with beyond design basis accident conditions or are reconsidering their

number and position.

Studies necessary to re-evaluate the Severe Accident Management (SAM) strategy

taking into account the Fukushima lessons have to be performed. This will take

several years and a lot of money, because conducting experiments in the field of

severe accidents is very complex. Enhancing international exchanges on research

and solutions on molten core cooling and stabilisation are necessary.

One important issue is the provision of the necessary resources and arrangements to

cope with simultaneous severe accidents on several installations of the same site in

the context of regional devastation resulting from a natural disaster.

The qualification of instrumentations used during severe accident conditions

especially in the long term is another issue.

Also, the dealing with large volumes of contaminated water remains an unsolved

issue.

2.4 Discussion of the ENSREG s results

As main results of its peer review process, the ENSREG concluded in April 2012 that all

countries have taken significant steps to improve the safety of their plants, with varying

degrees of practical implementation [ENSREG 2012a].

The April 2013 ENSREG peer review workshop to review the nation actions plans

concluded – and that was its only actual result – that a follow-up peer review would be

valuable by providing an opportunity for exchange of information among participants.

According to the ENSREG, such a follow-up peer review could be conducted in 2015 or

later when the results of important studies and assessments are available.

The key issue, which is still open, is how comprehensively these follow-up peer reviews

of the NAcPs will be conducted. This might be seen as the last opportunity to force the

nuclear regulators to formulate mandatory requirements which need to be fulfilled in a

rather stringent time schedule – in contrast to the years or even decades currently planned

in many countries. This could make operators decide to shut down old and unsafe nuclear

power plants instead of investing into extensive modernisation measures. From today s

point of view it cannot be assumed that the ENSREG would chose to act this way.

It is very disappointing what happened with the alarming findings of EU stress tests.

Despite the fact that the stress tests revealed a number of shortcomings regarding the

plants capability to withstand several external hazards and the lack of possibilities to

Page 18: 福島核災後龍門電廠(核四廠)壓力測試評估 Review of the post

18

cope with the consequences, the outcomes of the peer review consist only of

recommendations for “further improvements”.

The fear of representatives of civil society and independent experts that the stress tests

were mainly set up to improve the confidence in the safety of the European NPPs

regardless of his findings becomes true.

Until now, the ENSREG does not assess, but only describe the shortcomings of the

European NPPs. The country stress test reports do not formulate any overall

conclusions – not even if a specific NPP has shortcomings similar to those at the

Fukushima NPP. However, this is insufficient to use as a basis for deciding on the future

of a NPP. A comprehensive assessment taking into account all facts is necessary for the

politicians and the public to decide about the risk for people and environment.

During the stress tests peer review, the ENSREG did not look at the current safety level

of the European nuclear power plants, but the potential increase of the safety level in the

next decade. Furthermore, the ENSREG has not defined or even recommended any time

schedule for the implementation of the required measures.8 The operation of dangerous

NPPs is ongoing.

The ENSREG summary of the current status of the National Action Plans (NAcPs) again

only describes the plans’ weaknesses. An assessment of the sufficiency to remedy the

dangerous situation is not provided. The ENSREG avoids mentioning, whether the

NAcPs are sufficient to amend the dangerous situation if completely implemented.

2.5 Conclusion of the critical review of the EU stress tests

The Fukushima catastrophe was the horrible result of decades of mistaken safety

philosophy, a very lax safety regulation under strong industry influence on the

regulators – not only in Japan. The first shock led to the honest attempt to change this, to

also involve events which are definitely possible but were kept out of the safety cases by

using probabilities [BECKER 2013].

On October 12, 2012, Tokyo Electric Power Co (TEPCO) admitted that the company had

failed to prevent the Fukushima accident, reversing its earlier statement that the accident

could not have been foreseen. TEPCO attributed those facts to multiple root causes: First,

the management assumed a severe accident was extremely unlikely to occur in Japan, and

feared that retrofitting safety systems would increase anxiety among the public,

especially among the residents near the plant and would require a costly shutdown period

[NW 18/10/12].

8 The ENSREG does not have a regulatory mandate. To define, require and monitor the implementation

of safety improvements stays in the competence of the national regulatory authorities, who are members

of the ENSREG.

Page 19: 福島核災後龍門電廠(核四廠)壓力測試評估 Review of the post

19

The risk of natural hazard exists to a different extent for all European NPPs, but like in

Japan the operators insist on the low probabilities to avoid high investments and anti-

nuclear activities of the public.

The EU tried to respond to this “new experience” of Fukushima by conducting the stress

tests and hoping that the results will lead to higher safety. It is evident, however, that

some countries treated this task rather as a formality or paperwork than a plant safety

upgrade program.

In general, there are different possibilities for operators and nuclear authorities to deal

with the shortcomings the stress tests revealed:

A quick response, but without any guarantee that the measures are sufficient (e.g.

Cernavoda NPP, Romania).

A comprehensive evaluation of possible hazards and protective measures, which

will take more than ten years (e.g. France).

Business-as-usual (e.g. Dukovany, Czech Republic), i.e. the idea of the stress tests

is more or less ignored; the already on-going (insufficient) back-fitting programs

are listed within the NAcPs.

However, none of these options increases the nuclear safety to an acceptable level. The

very obvious solution – permanent shutdown – needs to be considered and is in several

cases the only safe option. One of the major problems of the stress tests is the lack of

definition what level of safety (robustness) should be achieved or in which cases the

plants should be back-fitted or shutdown, thus the peer review process does not provide

any advice for this decision.

To which extent the envisaged measures will improve the safety level is in particular an

economical issue. Better protection will result in higher costs. However, to improve the

safety level in an area prone of seismic or flooding hazards is also a technical issue.

Necessary safety levels could not be achieved subsequently.

However, the operators are heavily relying on the new magic solution to severe

deficiencies at the plants due to design or the site: mobile equipment, which is easy to

plan and store in the plant and therefore a cheaper solution than the installation of new

systems protected against external hazards. Mobile equipment is presented as the solution

to compensate deficiencies of the reactors and the spent fuel pools. But under severe

accident conditions, it is very unlikely that the proposed mobile equipment can be put to

work as quickly as necessary; to rely to such a large extent on manual actions is

irresponsible in regard of the consequences of a severe accident [BECKER 2013].

Furthermore, the new mobile equipment is useless if the staff response during the

accident is not perfectly according to plan. Not only the “know-how” but also the “know-

Page 20: 福島核災後龍門電廠(核四廠)壓力測試評估 Review of the post

20

why” is very important. This is an important lesson learnt from the Fukushima accident,

which should result in the implementation of passive safety systems designed to

withstand beyond design accidents with appropriate safety margins.

Thus, the authors concluded: Up to now, no lessons learnt from the accident at

Fukushima. At all European nuclear power plants severe accidents can occur – any time

[BECKER 2013].

Page 21: 福島核災後龍門電廠(核四廠)壓力測試評估 Review of the post

21

3 Weaknesses the Taiwanese stress tests revealed

Taiwan has performed a stress tests exercise for its nuclear power plants largely based

upon the EU stress tests model. The stress tests report has been written by the licensee,

the Taiwan Power Company (TPC), for the operating units and the units under

constructions (NPP4). These reports were submitted to the regulator, the Atomic Energy

Council (AEC) for review. The AEC prepared a national stress tests report (NR)

documenting the results of its review. The NR was published in May 2013 [AEC 2013].

Building on the results of the stress tests and insights from the actions being taken by

other countries, on November 5, 2012, the AEC established requirements to implement

enhancements. These requirements were embodied in regulatory orders issued by the

AEC to TPC. However, these requirements are non-binding requirements. TPC may

propose alternatives subject to AEC approval. Additionally, at the end of each chapter of

the national stress tests report, the AEC formulates several general requirements. For

none of the requirements any time schedule for implementation is set.

This chapter presents a review of the safety issues of the fourth nuclear power plant based

on the stress tests reports. The following chapter is mainly based on the information

provided by the national stress tests report. Some information provided in TPC s stress

tests report of Lungmen NPP is also presented [TPC 2013].

In spring 2013, a peer review of the stress tests has been conducted by a six-person team

assembled with the involvement the Organization for Economic Cooperation and

Development (OECD) and the Nuclear Energy Agency (NEA). The NR and three stress

test reports of the operating nuclear power plants were provided to OECD/NEA experts

in January 2013 [OECD 2013]. Some of the findings of the OECD/NEA report published

in April 2013 are included in the following chapter.

3.1 Earthquakes

Taiwan is located at a complex juncture between the Eurasian Plate and Philippine Sea

Plate, where earthquakes occur frequently. Due to the collision of these two plates, the

eastern part of Taiwan moves toward northwest at a rate of about 2.5 – 8.0cm/year.

Hence, the seismic design of structures, systems and components (SSCs) of nuclear

power plants in Taiwan is an important issue [NEI 2009a].

Although Taiwan is prone to earthquakes, up to now, the country has not experienced an

earthquake strong enough to challenge the seismic design of its nuclear power plants. The

biggest earthquake in 100 years, the magnitude 7.3 Chi-Chi quake on September 21, 1999,

had no impact on the three existing plants, supposedly only due to the great hypocentre

distance [NEI 2009a].

Page 22: 福島核災後龍門電廠(核四廠)壓力測試評估 Review of the post

22

Seismic hazard evaluation

The Lungmen nuclear power plant site is located in a high seismic risk zone, thus

earthquakes are an important hazard for the plant. To determine the Design Basis

Earthquake (DBE), the historical earthquake records of the past 400 years of the area

within a 320 kilometres radius of the site were collected. In 1992, the DBE was

determined based on the assumption that an earthquake of a local magnitude of 7.3,

which occurred in east of Taiwan in 1908, happened 5 kilometres east of the site. The

calculated values of peak ground acceleration (PGA) of this earthquake are between

0.23g and 0.41g. The PGA of the DBE for the NPP4 is determined to be 0.4g.

Historical records for only 400 years are a rather brief period to assess the possible

earthquake intensity. But the use of paleoseismic investigations for determining the DBE

is not mentioned.9

In 2004, the Taiwan Power Company (TPC) contracted a project10

to study the possible

earthquake hazards of NPP4. The results showed that the 0.4g DBE is still adequate. But

now this evaluation is nearly 10 years old, and thus outdated. Re-evaluation of seismic

hazards for any site nearly always shows that the earthquake hazard was

underestimated.11

The OECD/NEA group pointed out that it is clear that historical data can only be used as

supporting information for seismic hazards, because of the lack of a sufficiently long

seismological catalogue. The major source of information should come from the

seismotectonic characterization of faults12

[OECD 2013].

Aybars Gurpinar, a consultant on earthquake resistance with more than 20 years

experience with the IAEA and responsible for the review of the seismic hazard

evaluations, questioned TPC's position that its nuclear power plants only needed to

withstand an earthquake with a magnitude of 8.1 – 8.2. These values were used during

the stress tests and were developed based on a general country wide investigation of the

seismic hazards. The expert emphasised from the discussions with TPC it was not clear

whether there were sufficient tectonic arguments to use the countrywide seismic values

[OECD 2013].

9 Paleoseismology looks at geological sediments and rocks for signs of ancient earthquakes. It is used to

supplement seismic monitoring, for the calculation of seismic hazards. 10

“Re-analysis and evaluation of Earthquake Threats to the NPP4 Site”(National Centre of Research

Institute) 11

On December 26, 2006, two consecutive strong earthquakes – both with a local magnitude of 7.0 – hit

the most southern part of Taiwan, Hengchun village, where the Maanshan nuclear power plant is

located. It was the strongest earthquake ever experienced by Taiwan’s existing nuclear power units, and

it raised public concerns about the seismic safety of the nuclear power plant. Before the Hengchun

earthquake, the determined maximum potential earthquake in the subzone to which Maanshan belongs

was 5.9 [NEI 2009a]. 12

This includes the dimensions of the fault (length, down-dip, width), orientation (strike, dip), amount and

direction of displacement, rate of deformation, maximum historical intensity and magnitude,

paleoseismic data, geological complexity (segmentation, branching, structural relationships), earthquake

data and comparisons with similar structures.

Page 23: 福島核災後龍門電廠(核四廠)壓力測試評估 Review of the post

23

A lesson learnt from the Fukushima accident is that countrywide investigations do not

provide sufficient details that are needed to appropriately consider the seismic and

tsunami hazards for nuclear power plants. Thus, site-specific investigations are necessary,

but not available yet.

The expert stated in the context of a site-specific seismic hazard analysis, it may be

necessary to revise maximum magnitude values for faults. He suggested a value of 9.0.

This was the magnitude of the Tohoku earthquake of 2011 that triggered the Fukushima

accident [OECD 2013].

One of the most important weaknesses is the lack of calculation of the return frequency

for earthquakes, which is crucial for determining the DBE. The return frequency was an

important approach to assess the adequacy of the evaluation of the DBE in the frame of

the EU stress tests. The use of a return frequency of 10-4

per annum is recommended by

the ENSREG [ENSREG 2012b].

The AEC required to perform an updated and thorough seismic evaluation and to take

every measure needed to fulfil the ENSREG stress test requirements. A re-analysis of the

seismic hazard curve is to be conducted to see whether the annual exceedance frequency

of current DBE is adequate. However, there is no specific AEC requirement regarding

the return frequency.

Seismic resistance of the NPP4

According to TPC, all safety related-systems, structures, and components (SSCs) as well

as their subsystems can sustain integrity and assure their safety function during a DBE;

also indirect effects of a DBE (as internal flooding) are no hazards for the plant.

After the Fukushima accident, TPC initiated a re-inforcement action plan (RAP) to

improve the seismic resistance of equipment under severe earthquake conditions. The

installation of seismic resistance pipes connecting the ground floor of the reactor building

to the water source to make-up water to the spent fuel pool (SFP) is planned. Also, the

water level and temperature instrumentation of the SFP has to be improved.

The evaluation of seismic margins revealed that the off-site power supply is the weakest

seismic capacity equipment. According to TPC, the off-site power gets lost due to an

earthquake with an intensity above 0.3g, which is even below the DBE. TPC pointed out

there are four successful paths to achieve reactor core long-term heat removal.

For the successful path 1, all the necessary safety functions for the unit normal cold

shutdown paths via a residual heat removal (RHR) system can be successfully performed.

The emergency diesel generators (EDGs) provide the AC power for the important

equipment. The medium seismic withstanding value is 2.0g. Thus, the calculated safety

Page 24: 福島核災後龍門電廠(核四廠)壓力測試評估 Review of the post

24

margin is 1.6g compared to the DBE. This value is pretty good. However, there are

doubts about the reliability of the structures, systems and components (see chapter 4).

For the three other successful paths, when the RHR system is unavailable due to

earthquake, the fire water system has to provide the reactor core long-term cooling. The

seismic withstanding value of the fire water storage tank (1.1g) is the lowest, but a

substantial improvement of the fire water storage tank is not feasible. Instead, TPC is

considering modifying the interface of the fire water and raw water systems. Thereby, the

raw water can be introduced directly into the intake pipe of the fire water pump.

According to TPC, the raw water reservoirs can provide a stable water supply to the fire

water system after an earthquake. The raw water reservoir is located on the west side flat

hills with 116 meters of elevation, 112 meters long and 63 meters wide. The volume of

water storage is 48,000 m³. However, the raw water reservoir is only designed not to

collapse during DBE. Its capability against an earthquake with seismic intensity higher

than 0.4 g is probably very limited.

If an earthquake occurs with an intensity exceeding the DBE, the structure of the raw

water reservoir may collapse due to structural crack. According to TPC, however, the

leakage is limited (maximum peak leakage flow of 46.6 m³/s), and the flood is

transported to the downstream of marine outfall. Thus, a reinforcement of the raw water

reservoir is not envisaged.

But the leakage of the raw water reservoir can obviously threaten the safety of the plant,

because the water needed to cool the reactors and the spent fuel pools during an accident

will flow out.

The AEC required upgrading the seismic resistance of the raw water reservoir. This is to

be appreciated. However, until now it is not known whether this reinforcement will be

performed, i.e. whether it is technically and economically feasible.

According to the NR, only the direct effects of earthquakes beyond the design basis are

considered, but also indirect effects have the potential to endanger successful paths.

Indirect impacts of earthquakes are internal flooding due to pipe-breaks, fires due to the

release of flammable substances or impacts due to damage of non-seismically qualified

components. This is an additional reason why it is not completely credible that the plant

could withstand a beyond design basis earthquake.

However, the envisaged measures to increase the seismic margins of the plant are very

limited. It is intended to shorten the time needed to establish the fire water system: The

operator must manually open at least two isolation valves, which are located in

equipment channel C of the reactor building. In addition, the operator must manually

Page 25: 福島核災後龍門電廠(核四廠)壓力測試評估 Review of the post

25

open the electric valve. It is also planned to shorten the decision making process by

making clear guidelines. However, the main problem is not solved at all: manual actions

of the operator are necessary.

On July 16, 2007, in Japan, where the earthquake focal mechanisms are very similar to

those in Taiwan, all seven reactors at the Kashiwazaki-Kariwa site were struck by the 6.8

magnitude Niigata Chuetsu offshore (NCO) earthquake. The location and magnitude of

this earthquake has never been expected in the design of the plant. Some 63 incidents

were confirmed, including a release of radioactive iodine through the main stack at unit 7,

which is the same reactor type (ABWR) as the units of the NPP4. The safety margin of

the plant’s SSCs prevented a severe accident after the hit of the earthquake; however,

failures of some non-safety SSCs caused unexpected damages to the plant13

[NEI 2007a;

NEI 2009a; WNN 2009a].

One important lesson learnt from the NCO earthquake is that a well-protected nuclear

power plant should have substantial seismic margin. It is not clear from the NR, whether

a comprehensive seismic Probabilistic Risk Assessment (PRA) has been performed for

NPP4. If not, this would be an important approach to provide insights that are necessary

to develop backfitting measures to obtain seismic margins.

The AEC considers that the resulting action plan of TPCs seismic re-assessment is

adequate, but pointed out that the schedule should be more efficient and speeded-up.

Thus, the question comes up, how the schedule is set, in particular, could operation start

licence before the re-assessment and the necessary improvement measures are done?

Additional to the limited upgrading measures envisaged by TPC, the AEC required a

seismic upgrade of the plant fire brigade building structures. This is very crucial, because

of the important tasks of the fire brigade to cope with an accident. Also, necessary

functionality upgrades of the emergency response facilities and the enhancement of the

power durability of seismic monitoring sensors are needed.

The reinforcement of the structures of the Technical Support Centre (TSC) is required,

which is not able to withstand an earthquake yet. In addition, the AEC’s Department of

Nuclear Technology is requesting TPC to consider building a seismically isolated TSC

based on the practice being implemented in Japan in the light of the Fukushima accident.

However, establishment of a TSC that could be very useful during an emergency

regarding the protection of the people should only be considered, and thus probably not

built.

13

The unit 7 was restarted after almost 22 months of checks and repairs.

Page 26: 福島核災後龍門電廠(核四廠)壓力測試評估 Review of the post

26

3.2 Flooding

The Fukushima accident highlighted the hazard of flooding events for nuclear power

plants. One of the main questions after the Fukushima accident was the predictability of

the wave height of the tsunami. In 2008/2009, two studies regarding the tsunami hazard

were performed on behalf of TEPCO.14

Accordingly, the calculated wave heights at the

intake points at Fukushima Daiichi NPP were 9 to 10 meters.15

Thus, TEPCO knew that

the implemented protection (against wave height of about 6 meters) was not sufficient.

But nevertheless the wave height of the tsunami which triggered the Fukushima accident

(14 meters) was not to be expected. Thus, for all NPPs that are threatened by tsunamis,

safety margins of at least 6 meters are to be considered.

Note, according to TEPCO s post-Fukushima stress tests report for unit 7 of the

Kashiwazaki-Kariwa16

, after additional safety measures, the allowable tsunami height

over the 3.3 meters design basis is 15 meters [NEI 2012c].

Generally, the expected main effects of flooding – that could all threaten the NPP4 – are

as follows [IAEA 2003]:

The presence of water in many areas of the plant may be a common cause failure

(CCF) for safety-related systems, such as the emergency power supply systems or

the electric switchyard.

Considerable damage can also be caused by the infiltration of water into internal

areas of the plant, by rise of the water table induced by high flood levels. Water

pressure on walls and foundations may challenge their structural capacity.

Deficiencies in the site drainage systems may also cause flooding of the plant.

The dynamic effect of the water can damage the structure and the foundations of

the plant as well as many systems and components located outside the plant.

Flooding can also contribute to the dispersion of radioactive material to the

environment.

Protection against tsunamis

The Design Basis Tsunami (DBT), i.e. current protection against a tsunami, is based on

the worst tsunami in the history of Taiwan. According to the historic records, two severe

tsunamis occurred in Taiwan in 1867 and 1918, respectively. The wave height of the

tsunami happened on June 11, 1867 at 134 km north of Keelung was approximately 7.5

meters. After considering the influence of tides and geographic factors, the height of the

DBT for NPP4 is set to be 8.57 meters.

14

One study investigated the possible impact of the wave height of the Jogan-Tsunami at the intake points

of the NPP Fukushima. The second study evaluated a possible undersea earthquake at the coast near the

NPP Fukushima. 15

The authors thank A.Y. Indradiningrat (cervus nuclear consulting) for helpful advice to this issue. 16

which is the same reactor type (ABWR) as in the NPP4

Page 27: 福島核災後龍門電廠(核四廠)壓力測試評估 Review of the post

27

This methodology to assess an external hazard is not in accordance with the ENSREG

recommendations that ask for the use of a return frequency of 10-4

per annum with

respect to external hazards.

The ground elevation of the main building area at the Lungmen site is 12 meters, which is

3.4 meters higher than the calculated wave heights. Therefore, in the opinion of TPC,

NPP4 would not be threatened by tsunamis.

On August 19, 2011, the National Science Council (NSC) published a tsunami report17

,

after assessing the 22 earthquake origins of potential maximum tsunami in Taiwan.

According to the NSC, the result shows that the potential tsunami run-up height is lower

than the evaluated DBT. However, it is pointed out, that there are still significant

uncertainties in tsunami run-up predictions due to the definition of tsunami sources.

The OECD/NEA experts suggested the deletion of the analysis provided by the National

Science Council (NSC) from the stress tests report. They criticise several issues: As

mentioned above, higher earthquake magnitudes are to be considered. The maximum

magnitudes have a major impact both on the seismic hazard as well as the tsunami hazard

results. The NSC analyses did not model a tsunami resulting from undersea landslides

and undersea volcanic eruptions. But, for example an active submarine volcano was

identified in the north of Taiwan that can be considered a potential tsunami source.

Another source of significant uncertainty in tsunami run-up predictions is the use of

approximate near-shore topography instead of accurate bathymetry. The experts

recommended to re-analyse the tsunami hazard using state-of-the-art modeling [NW

16/05/13; OECD 2013].

Thus, the necessary tsunami run-up, against which the NPP4 has to be protected, is not

known so far. The design basis tsunami has to be redefined.

Nevertheless, TPC is required to enhance the water tightness of buildings or build a sea

wall to a level of 6 meters above current licensing to address the uncertainty from the

original DBT height.

TPC plans to build a tsunami wall to cover the uncertainty. The envisaged height of this

protection wall is 2.5 meters or elevation 14.5 meters respectively. This value means a

safety margin of nearly 6 meters compared to the calculated waves of the DBT. However,

this value would be only sufficient if the evaluation of the DBT was correct, but obviously

it is not.

Therefore, it is a matter of fact that the protection against tsunamis is not adequate, even

after building the sea wall.

17

Influence of Tsunami Induced by Potential Massive Scale of Earthquakes on the Nuclear Power Station

in Taiwan

Page 28: 福島核災後龍門電廠(核四廠)壓力測試評估 Review of the post

28

The AEC formulates only very general requirements: TPC should further review the

appropriateness of the DBT and take the associated improvements to its nuclear power

plants. A detailed scenario simulation of seismic and tsunami hazards are to be performed.

However, even a tsunami similar to the current DBT could be a danger for the plant.

When the tsunami run-up height reaches 8.6 meters, the exterior walls of the pump house

(at an elevation of 5.3 meters) will sustain additional water pressure as well as impact

force. According to TPC´s “Lungmen NPP Tsunami Prevention Capability Review

Report”, the integrity of the pump house structure needs to be strengthened. Additionally,

the plant needs to confirm that the sealing material for openings of the pump house can

sustain the water pressure caused by tsunamis.

Furthermore, the stress tests reveal that, if an earthquake-triggered tsunami seizes the

shore near the plant and causes the plant to lose its ultimate heat sink (UHS), there is only

one successful path to achieve reactor core long-term heat removal and prevent an

accident18

.

Protection against extreme rainfall

To determine the Design Basis Flood (DBF)19

, the plant adopts the precipitation records

measured at Keelung Weather Station from 1901 to 1982. The calculated probable

maximum precipitation (PMP) is 310 mm/h. Even though the annual maximum

precipitation data recorded in the years 1961 to 2006 shows a slightly increasing trend,

the design of the drainage capability is assessed as adequate by TPC.

To prevent internal flooding, rainfall-induced surface flows in the main building area

(power block) should be removed via the drainage system into the sea. The drainage

system is designed to deal with 100-yearly maximum precipitation as well as to carry the

run-off from a storm with 100-yearly return. The methodology is not in accordance with

the ENSREG recommendations that ask for the use of a return frequency of 10,000 per

year.

Climate changes have caused severe rainfall in the form of typhoons and/or tropical

storms in recent years. Thus, the AEC requires reviewing the appropriateness of the DBF;

associated improvements should be taken to increase the robustness of the plants against

flooding. However, it is stated that these should be reviewed and approved by the AEC

through the process of periodic safety review every ten years. Thus, it is not clarified

whether the measures should take place before operation of the plant starts.

18

RCIC system starts its short-term water feeding function, which should give operators the time to

manually start the Safety Relief Valve (SRV) and set up AC-Independent Water Addition (ACIWA).

Thereafter, the ACIWA system has to provide long-term water feeding to reactors and the Containment

Overpressure Protection System (COPS) has to provide containments long-term heat removal. 19

i.e. the flooding that the plant has to be protected against

Page 29: 福島核災後龍門電廠(核四廠)壓力測試評估 Review of the post

29

The stress tests revealed dangerous weak points and cliff edge effects, because all

exterior doors on the ground floor of the plant buildings are not watertight; internal

flooding would occur in case of a beyond design basis flood. Thus, flood barrier plates

have been installed at the doors on ground floors directly connecting to the outside of

buildings, at the tunnel where the radwaste building enters the reactor/control building,

and at the passage where the access control building enters reactor buildings.

To prevent internal flooding resulting from water outside of buildings, penetrations of

buildings sealed with the water stops are only 30 cm higher than ground floor. Structures

of safety-related systems as well as their components are also 30 cm higher than ground

elevation.

The flooding risks are of concern due to a “cliff-edge” effect, in that the safety

consequences of a flooding event may increase sharply with a small increase in the water

level [NRC 2012]. A safety margin of only 30 cm seems to be very small.

To prevent internal flooding caused by leakage from damaged equipment (e.g. because of

rupture of pipes) inside the buildings, some areas of the reactor building are equipped

with watertight doors or semi-watertight doors.

If the floors in reactor buildings (at elevation 4,800 mm) containing safety-related electric

switchgear are flooded, all safety-related AC electric equipment would fail. This situation

would lead to a station blackout (SBO) and the loss of the ultimate heat sink (UHS). To

increase the protection against flooding, water-tight doors to prevent flooding from

flowing into rooms at elevation 4,800 mm have been added.

However, during former flooding events at nuclear power plants (e.g. at the Blayais NPP,

France, in 1999) safety equipment located below the level of the site was damaged,

because the water resistance/tightness of doors was miscalculated or seals of cable

penetration were corroded.

In case of an internal flooding draining the water by pumps is envisaged to restore the

function of the equipment located on the ground floor of the plant as soon as possible.

TPC has concluded that the drainage capability inside buildings is sufficient, nevertheless,

in addition to the existing sump pumps, mobile drainage pumps have been procured.20

There is no information regarding how soon the function of this equipment can be

restored and how long the flooding would have to persist for a critical situation to

develop. However, the loss of equipment caused by a sudden flooding could not be

prevented by sump pumps. Furthermore, additional manual actions are necessary to

perform this measure.

20

The plant will add 2 manoeuvrable engine-driven drain sump pumps and 20 electric drainage pumps. 6

engine-driven mobile drainage pumps and 12 electric drainage pumps are already procured.

Page 30: 福島核災後龍門電廠(核四廠)壓力測試評估 Review of the post

30

In addition to the limited measures envisaged by TPC, the AEC requires upgrading the

watertight capability of doors of buildings containing important safety-related equipment,

fire-fighting doors as well as pipeline penetrations seals.

These requirements sound appropriate in regard of the threat of flooding. However, they

are very general, so it cannot be judged whether the scope is sufficient. Furthermore, the

time schedule is not mentioned. Therefore, it cannot be assured that necessary backfitting

measures will take place before NPP4 starts operation.

3.3 Other extreme natural hazards

According to the Intergovernmental Panel on Climate Change (IPCC), the type,

frequency and intensity of extreme weather events are expected to change as the earth’s

climate changes. These changes could occur even with relatively small mean climate

changes. Changes in some types of extreme events have already been observed, for

example, increases in the frequency and intensity of heat waves and heavy precipitation

[IPCC 2007].

Generally, the frequency of occurrence of more intense rainfall events in many parts of

Asia has increased, causing severe floods, landslides, and mud flows, while the number

of rainy days and total annual amount of precipitation has decreased [IPCC 2013].

Recently a typhoon showed its potential to threaten a nuclear power plant: On July 13,

2013, during the typhoon Soulik that caused widespread damage to the power grid, a

large amount of debris was washed into the sea water intake of Chinshan unit 2, clogging

it, damaging three debris screens and prompting operators to shut the unit down [WNN

2013a].

Extreme weather events, such as typhoons, heavy rain, and mudslides, can affect the

Lungmen NPP site. Possible flooding events are the main resulting hazard of extreme

weather events, which was dealt in the previous chapter. But also further effects of

extreme weather events could threaten the safety of the plant.

The design wind speed of all relevant buildings21

, i.e. the wind speed all buildings have to

be resistant against, is only 54m/s. Given the fact that typhoons of high intensities were

observed in the past years, an evaluation of the protection of the buildings containing

safety-related equipment against projectiles in case of a beyond design typhoon (with

wind speed exceeding 70.2 m/s) is required by the AEC. Because these evaluations are

missing, the threat of projectiles resulting from typhoons is not yet known.

21

reactor buildings, control buildings, the switchgear building, the auxiliary fuel building, and the off gas

stack turbine buildings, the radwaste building, the water plant, the fire-fighting pump house, and the

switchyard

Page 31: 福島核災後龍門電廠(核四廠)壓力測試評估 Review of the post

31

The Lungmen NPP site is located within the watersheds of Shiding Stream and Shuangxi

Stream. According to the record of the Soil and Water Conservation Bureau (SWCB),

both streams are not mudslide-prone; the landscape of this area is relatively flat. However,

if unexpected mudslides happen and cause flooding to reroute and to flood the main

building area, units may be affected.

Regarding extreme weather events, further weak points are identified:

If a beyond design basis (BDB) storm seizes the plant, and if the BDB

precipitation could not be drained by the drainage trenches and the surface flow

floods the main building area, units may be affected.

If the inlets of the sea water pump house in the reactor buildings are stuck by

massive debris, causing further clogging at the mesh and affecting the water

intake of the pumps, reactors lose the ultimate heat sink (UHS).

Main weak point is flooding on the bottom floor, -8,200 mm of the reactor

building, because this floor contains all safety-related emergency core cooling

systems.

The improvement of protection against extreme weather events – besides the limited

flood protection as discussed above – envisaged by TPC are in particular the introduction

of procedures. It is stated for example: If beyond design basis events happen and reactors

lose all AC power source and all water supply, the plant must get prepared to take actions

to provide cooling to the reactor according to the Ultimate Response Guideline (URG)

(see chapter 3.5).

The OECD/NEA group concluded that, although some combinations of events were

considered in the determination of elevations of DBT, a systematic evaluation of

combinations of events in the areas of flooding and extreme natural hazards was not

performed. The experts recommended to implement a systematic approach for selecting

and combining extreme hazards, including re-evaluating the probable maximum

precipitation (PMP) with regional topographic maps [NW 16/05/13; OECD 2013].

The AEC required performing a systematic evaluation of combinations of extreme

weather events.

The AEC recommended that TPC should conduct a quantitative risk assessment

concerning the potential volcanic hazard. According to the AEC s non-binding

requirements, a volcanic probabilistic risk assessment (PRA) is to be performed and the

impacts from ash dispersion are to be studied.

All in all, nearly all evaluations about extreme weather events/natural hazards are

missing, thus there are a lot of threats that are not yet known.

Page 32: 福島核災後龍門電廠(核四廠)壓力測試評估 Review of the post

32

3.4 Loss of all power supply (SBO) and ultimate heat sink (UHS)

Even when a nuclear power plant is shut down, it needs electric power supply,

particularly to operate the pumps of cooling circuit, and also it needs an ultimate heat

sink (UHS) to remove heat from the cooling circuit and other vital systems necessary to

avoid an accident. Total loss of offsite and onsite power supply – Station Black-out

(SBO) – and loss of Ultimate Heat Sink (UHS) scenarios could result in severe accidents.

If a loss of offsite power (LOOP) occurs22

, Lungmen NPP’s three seismic resistance

emergency diesel generators (EDGs) will start automatically to provide power supply.

The EDGs are located on three corners of the reactor building at an elevation of 12.3

meters. This is only 30 cm above the site elevation, which guarantees not enough safety

margins against flooding events.

The function of the EDGs relies on cooling water, which is provided by the Reactor

Building Cooling Water (RBCW) system. Heat absorbed by RBCW is removed by the

Reactor Building Service Water (RBSW) system and then dissipated to the sea.23

In case of loss of EDGs, the 7th

EDG can take over its design function. This 7th

EDG is

seismically designed and located in the Auxiliary Fuel Building (AFB), but also only at

an elevation of 12.3 meters. However, the 7th

EDG is air-cooled, thus it does not depend

on cooling water. Its start and control power is provided by an independent battery set,

which can deliver DC power for 3.5 hours.

The 7th

EDG is designed to totally replace the water-cooled EDGs of either unit 1 or unit

2. After the Fukushima accident, which highlighted that an external hazard may affect all

the units on a site, TPC added a new procedure. Accordingly, the 7th

EDG may be used to

simultaneously supply power to unit 1 and 2.

However, the output of the 7th

EDG is only sufficient to supply power to operate one

division of both units. It is not required by the AEC to install a second air-cooled EDG,

but only to perform an evaluation regarding this issue.

The installation of two air-cooled gas turbine generators located inside a seismically

isolated building at the switchyard at an elevation of 29.8 meters is envisaged.24

Note that

without these gas turbines, AC emergency power supply is rather weak – with the 7th

EDG as the only element of a second stationary line of defence. With the gas turbines, the

emergency power supply would be on a level comparable to that in the EU.

22

TPC is required to improve the reliability of offsite power supplies. 23

Each EDG is equipped with a tank capacity to run continuously for 5 hours, and one storage tank that

can provide fuel for 7 days (only for one EDG), but can be refilled from a tank truck. Unit 1 EDGs and

Unit 2 EDGs can support each other in case of emergency. 24

Besides, in order to increase the reliability of transmitting power to reactor safety systems from gas

turbine generators, it is planned to add 4.16kV independent transmission lines.

Page 33: 福島核災後龍門電廠(核四廠)壓力測試評估 Review of the post

33

In case of loss of AC power, i.e. in case of Station Black-Out (SBO), the reactor water

level shall be maintained by the Reactor Core Isolation Cooling (RCIC) system. RCIC

operation relies on DC power.25

Based on the existing design, DC power can be supplied

by a battery set for 8 hours.26

The water source is the suppression pool of the containment

or the condensate storage tank (CST).

Within this 8 hours period, the operator shall set up normal power supply and alternative

power supply including the 7th

EDG, gas turbines, and backup mobile power.27

However, the RCIC system has only one division, i.e. if any failure occurs, it gets lost.28

To prevent fuel degradation after RCIC operation has stopped, it is planned to connect

the outlet of the fire engine to the AC-Independent Water Addition (ACIWA) pipe to

inject water into the reactor or suppression pool. The station has several fire engines,

which should take suction water, e.g. from a raw water reservoir, or take sea water from

the discharge channel.

According to TPC, offsite supports are available; the Fire Bureau of New Taipei City will

provide manpower, vehicles, and equipment. However, after an extreme natural disaster,

the fire engines will probably be called for use at other locations.

The required time (only 10 – 30 minutes) for the onsite and offsite fire engines etc. to be

ready for operation onsite seems to be calculated without considering conditions after a

natural disaster (like an earthquake).

Another possible way to provide water to the reactor is by gravity from a raw water

reservoir located at an elevation of 116 meters, through fire piping to the ACIWA piping.

However, as mentioned above, probably the water would no longer be available after an

extreme earthquake.

Envisaged measures to increase the robustness of the plant to prevent fuel damage are

limited and need several additional manual actions: The RCIC system may be manually

restarted if its DC power supply is lost. According to TPC, the operating steps have been

demonstrated to be feasible and have been incorporated in the procedure. Furthermore, if

the Safety Relief Valves (SRVs) should suffer a loss of operating gas or electrical power

due to a beyond design basis event, manual actions are possible to open the SRVs.

25

The speed governor of the RCIC turbine requires DC power 26

According to TPC, the duration of DC power supply to RCIC (and SRV/ADS) can be extended to 24

hours with load shedding. However, this measure is not reliable and demands additional manual actions. 27

Additionally, two mobile diesel generators to provide power to the 4.16kV bus as well as five small

mobile diesel generators to provide power to battery chargers will be procured. 28

The safety-related systems have mostly three independent divisions.

Page 34: 福島核災後龍門電廠(核四廠)壓力測試評估 Review of the post

34

Loss of Ultimate Heat Sink (UHS)

During normal operation, the Circulating Water Pump (CWP) removes the heat of the

condenser to the sea. After a reactor shutdown, decay heat is removed by the Residual

Heat Removal (RHR) System through heat exchangers to the Reactor Building Cooling

Water (RBCW) System and then to the Reactor Building Service Water (RBSW) System

and finally to the sea, which serves as the ultimate heat sink (UHS).

The function of the UHS gets lost, when the water intake is unavailable, e.g. because of

clogging. Furthermore, UHS function gets lost, if the RBSW and/or RBCW system(s)

lose(s) function (e.g. because pump room temperature is not maintained below 40°C by

its safety-related ventilation system).29

If UHS function gets lost, the reactor is to be depressurized by releasing steam into the

containment; at the same time, water from all possible water sources is continuously

provided through AC-Independent Water Addition (ACIWA) to the reactor (see chapter

3.5).

TPC s envisaged measures to increase the robustness of the plant regarding loss of UHS

are very limited: an emergency sea cooling water recovery plan has been established;

furthermore, spare RBSW and RBCW motors for emergency replacement have been

prepared.

Fuel damage can occur in the reactor core and/or spent fuel pool quite rapidly, in case the

UHS is lost. An additional alternate UHS that is installed at several EU nuclear power

plants could considerably reduce the risk of the total UHS loss. However, only the

evaluation about this issue is required by the AEC: TPC is required to perform an

evaluation regarding the establishment of an additional alternate heat sink such as the

water fed by groundwater wells.

TPC is also required to study the feasibility of adding the mobile heat exchanger to

remove the heat from the containment and/or reactor.

Spent fuel pool

The Spent Fuel Pool (SFP) is located on the upper part of the reactor building (elevation

31.7 meter), outside the primary containment.30

29

If RBSW system fails, but RBCW system is still available, it is an option to provide cooling water to the

RBCW heat exchanger through temporary piping. 30

The primary containment is a cylindrical steel-lined reinforced concrete structure integrated with the

reactor building. The reactor building provides a secondary containment around the primary

containment

Page 35: 福島核災後龍門電廠(核四廠)壓力測試評估 Review of the post

35

During normal operation, the residual heat removal and water makeup of the spent fuel

pool (SFP) is by ways of fuel pool cooling and cleanup system (FPCU). The heat is

removed by the RBCW and the RBSW system to the sea (ultimate heat sink).

If the ultimate heat sink (UHS) gets lost, the fuel pool cooling system can perform the

water make up function. Since decay heat cannot dissipate into the UHS, evaporation will

be the only way to remove decay heat.

In case of loss of offsite power, the non-safety related bus will not be able to provide AC

power, thus the FPCU pump cannot operate. In this case, the residual heat removal

system (operating in RHR FPC mode) will perform the fuel pool water makeup and

cooling function.

In case of SBO, the SFP will lose forced cooling and normal water makeup function.

Back-up design provisions are not available. Thus, firewater in reactor building 7th

floor

has to be injected into the SFP by using the fire hose located on the side of the SFP.31

The

diesel driven fire pump of the fire water system can provide water from the fire water

storage tank, through only one division of the RHR system (RHR-C piping) or directly

through the firewater system. However, the seismic capability of fire water storage tank

is low. The back-up water shall be provided from the raw water reservoir, however the

structures of the raw water reservoir are threatened by an extreme earthquake.

The installation of seismically designed firewater piping to make up and spray firewater

is planned. This backfitting measure is to be appreciated; however without an

appropriate water reservoir it could be nearly useless. A lot of manpower is needed to

transport water via fire engines to the SFP.

The plant plans to purchase mobile water injection equipment: 4 mobile firewater pumps

and air inflated water tanks (15 tons) are to be provided as the fire water backup system.

But this is also a limited measure, regarding the large amount of water needed to prevent

a severe accident.

AEC s conclusion and requirements

The measures to prevent and mitigate SBO and loss of UHS situations that are envisaged

by TPC are very limited. Obviously, the evaluations of the different accident scenarios

are not sufficient. Therefore, TPC is required to analyse the consequences of both units in

the site being affected. This is one of the most important lessons learnt from the

Fukushima accident, and thus all EU Countries with operating multi-unit plants have

dealt with this issue.

31

During power outage, the SFP and reactor cavity are interlinked. Firewater pumps, tank truck engines,

or mobile fire engines shall makeup water into the SFP (or reactor core) through the RHR system.

Page 36: 福島核災後龍門電廠(核四廠)壓力測試評估 Review of the post

36

Furthermore the consequential impact on the spent fuel pool (including the integrity of

the pool structure) in case of a loss of all power supply (SBO) and complete loss of the

heat sink should be evaluated. This is also one of the most important lessons learnt from

the Fukushima accident.

With respect to the SBO, the TPC is required to establish the equipment, procedures, and

training necessary to implement an extended loss of all AC power supply of 72 hours for

core and spent fuel pool cooling and for the reactor coolant system and primary

containment integrity as needed.

In the opinion of the AEC, the feasibility of TPC s accident management is not assured.

Thus, the AEC required: The operability of the non-conventional means including mobile

equipment, fire trucks, etc. should be justified on the basis of technical data32

. A

systematic review of the non-conventional provisions should be performed, focusing

appropriate operation of plant equipment in the relevant circumstances, taking into

account extreme external hazards and a potentially harsh working environment. Thus, all

of TPC s measures to cope with a loss of all power supply (SBO) and loss of ultimate

heat sink (UHS) could fail and a severe accident could occur.

3.5 Severe Accident Management

Severe Accident Management is necessary to prevent or mitigate major releases of

radioactive substances.

In order to cope with the compound disaster condition, for example earthquake and

tsunami, TPC had prepared the Ultimate Response Guidelines (URG), developed

following the Fukushima accident. Their relevant items (including reactor pressure relief,

alternative water injection and the required power for essential systems and

instrumentation control via mobile power source) in phase-1 shall be independently

completed by the station manpower itself within only one hour.

However, only if the measures can be performed as fast as envisaged, fuel damage will

not occur. After only 1.6 hours, the time of core water level drops to top of active fuel

(TAF), and then fuel damage starts. This time span is very short to take appropriate

measures. However, the strategy for preventing fuel damage described in the NR remains

vague. It is stated that all possible and available manpower and materials are mobilized to

arrange all available water sources including each kind of alternative water flooding path,

power sources, and water sources etc. It has to be considered that after an extreme

earthquake and/or tsunami it is very difficult and dangerous to perform these measures.

32

design, operation, alignment and connections, periodic testing, preventive maintenance, etc.

Page 37: 福島核災後龍門電廠(核四廠)壓力測試評估 Review of the post

37

A very large amount of water is required to prevent a core melt accident with a major

release of radioactive substances. For combined events that occur in both units, the total

required makeup water, including reactor and SFP, is 442.2 tons per hour (1947 gpm).

Several possibilities for water supply exist. However, the capacity of the onsite fire

engine, for example, is 12 tons. TPC stated that the raw water reservoir can supply

continuously for 86.84 hours (3.62 days). But in case it fails during an earthquake, it is

very difficult to provide such a large amount of cooling water.

Depressurization of the reactor

According to TPC, if the Emergency Core Cooling System (ECCS), including RCIC, is

expected to be unavailable, a controlled depressurization of the reactor must be

performed while the ECCS is still available. Once the ECCS is unavailable, an

emergency depressurization of the reactor must be performed immediately by opening

safety relief valves (SRVs).

The AEC highlighted the problem of the two step depressurization strategy that has been

adopted for prolonged SBO situation: With the slow and controlled depressurization

process (first stage), the reactor can be brought to and maintained at a relatively safe state.

In the second stage, the fast emergency depressurization of the reactor is performed. But

if the reactor is at a relatively high danger state (namely, a high pressure state), fast

depressurization of the reactor will lead to a core uncover even if the water level is high

before depressurization. Thus the envisaged procedure according to the URGs could have

negatve effects.

The AEC alerts that the subtle detail matters. The controlled depressurization should not

be confused with the emergency depressurization. However, the two terminologies are

not well distinguished in TPC’s stress test report.

Prevention of RPV failure

According to TPC, the station’s overall program for URG can assure the integrity of the

reactor pressure vessel (RPV). If fuel is damaged, the station shall perform the evaluation

of rescue measures and proposed actions in coordination with severe accident

management guidelines (SAMGs).

However the measures that should be taken after occurrence of fuel damage are only

described very briefly and vague. Thus, there are doubts that these measures could be

conducted under the catastrophic conditions after an extreme natural event. After stop of

operation of the RCIC, the reactor pressure vessel (RPV) will fail after only 9.7 hour.33

33

If RCIC keeps operation for 24 hours, the time of core water level drops to TAF (top of active fuel) is 4.3

hours. The time RPV failed: 15.1 hrs.

Page 38: 福島核災後龍門電廠(核四廠)壓力測試評估 Review of the post

38

Note: ENSREG warns the depressurization of the reactor coolant system (RCS) after core

melt is considered to be a crucial action to avoid high-pressure core melt ejection from

the RPV, which could potentially challenge the containment integrity and facilitate water

injection from low-pressure sources [ENSREG 2012b].

Prevention of containment overpressure

After loss of function of the ultimate heat sink (UHS), the reactor has to be depressurized.

Heat generated in the reactor will be removed to the primary containment. Thus, the

suppression pool water temperature will increase rapidly. Because it is likely that its

temperature and consequently the primary containment pressure will exceed design limits,

the containment pressure has to be released to protect the containment integrity.

As a filtered containment venting system (FCVS) is not installed, the release of a large

amount of radioactive substance will result. FCVS is a filtering system for removing the

radioactive material throughout different highly efficient filter stages.

TPC has not the intention to implement a FCVS. TPC has only set power recovery of the

Standby Gas Treatment System (SGTS) as the first priority item in the URGs. The

release of radioactive substances shall be mitigated by the SGTS, which depends on

power supply.

Despite the fact that the lack of FCVS is a serious shortcoming, there is no AEC

requirement concerning the implementation for such a system.

Note: in the design of the EU-ABWR, a FCVS is implemented (see chapter 5). FCVS are

to be installed in the ABWRs in Japan.34

Prevention of hydrogen explosion

If the fuel loses adequate cooling during an accident, hydrogen can be generated by

zirconium water reaction. To manage hydrogen risks inside the containment and prevent

hydrogen explosions, hydrogen igniters and recombiners or containment spray shall be

used to reduce the containment hydrogen concentration. However, AC power supply is

necessary to use these devices. Thus, containment exhaust is planned to reduce hydrogen

concentration, despite the fact that this measure will cause a release of radioactive

substances.

It is a serious shortcoming that passive autocatalytic recombiners (PARs) to prevent

hydrogen explosions are not installed, and the chief measure to prevent hydrogen

explosions and overpressure in the containment is by venting. Note that PARs sufficient

34

Hitachi-GE Nuclear Energy and Areva will work together to install filtered containment venting systems

(FCVS) at boiling water reactors (BWRs) in Japan [NUCNET 2013].

Page 39: 福島核災後龍門電廠(核四廠)壓力測試評估 Review of the post

39

for BDBA are installed or definitely planned in the European nuclear power plants

(apart from those with inertisation).

TPC is required to install PARs, but only by the still non-binding requirements of the

AEC. Thus, it is not clear, whether PARs are to be installed and if so, when this has to

happen.

In order to prevent hydrogen accumulation in the secondary containment (reactor

building) that could result in hydrogen explosions, the station shall open blasting

windows located on the upper part of the reactor building to release hydrogen outside by

natural convection.

During an accident this measure will also result in a release of radioactive material.

Prevention of basemat melt-through

To prevent containment basemat melt-through after the reactor pressure vessel (RPV), the

lower drywell shall be flooded via the AC-Independent Water Addition (ACIWA) system.

If the diesel-driven fire pumps failed to start, it is planned to flood with raw water by

gravity.

If the ACIWA system failed, the Lower Drywell Flooding (LDF) system, a passive

system, shall be used as an alternative flooding system: After the molten core will drop

down upon the drywell basemat, suppression pool water would flood into the lower

drywell when its high temperature fusible plug acts. According to TPC, the reaction

between molten core and concrete would be limited.

It is not discussed in the NR whether the flooding is fast enough to protect the basemat

and the penetrations in the lower drywell. Furthermore, it is questionable, whether in this

stage of the accident a sufficient amount of water will be available.

All in all, the measures for the prevention of the basemat melt-through are not sufficient.

This fact is underlined by the new safety feature of the EU-ABWR (core catcher) to cool

and stabilise the molten core (see chapter 5).

Prevention of liquid radioactive releases

During and after an accident, the liquid radioactive release can only be prevented if the

waste system and release routes are guaranteed to be safe. Otherwise, the radioactive

liquid will first flow into the reactor building sump and then overflow. In the worst case,

the liquid submerges into the first and second floors of the building. Then it further flows

outside the building into rain-water sewers or sinks into the bottom layer sea water

draining tunnel. The release will flow into the sea via the cooling sea water outlets.

Page 40: 福島核災後龍門電廠(核四廠)壓力測試評估 Review of the post

40

According to the NR, the release of the radioactive water should be stopped immediately.

However, the procedure is not explained. Furthermore, the worst case of liquid releases

into the sea is mentioned without indication how fast such releases could overflow in

different accident scenarios, and which amounts of radioactive water could be released.

The storage capacity is limited (17,968 m³). Thus, it has to be expected that large

amounts of liquid radioactive releases will enter into the environment.

ENSREG points out that conceptual solutions for post-accident fixing of contamination

and the treatment of potentially large volumes of contaminated water should be addressed

[ENSREG 2012b]. This important issue highlighted by the Fukushima accident is neither

addressed by TPC nor by the AEC.

Spent fuel pools (SFP)

If the spent fuel pool (SFP) water level is dropped, SFP emergency water makeup shall

be performed by ways of fire hydrants, fire water tankers and engine-driven fire water

pumps. The arrangement of the phase-1 strategies of the URG shall be completed within

2 hours.

In the worst case, after loss of SFP cooling and water makeup, the pool water temperature

will rise and the water will begin to boil after 9.5 hours.35

TPC stated that after 9.5 hours,

the members of support teams36

should be on site and the supporting should be ready.

TPC has the opinion that there is sufficient time to restore the power supply or to prepare

the alternative power supply for restoring SFP cooling or water makeup, because fuels

degradation will not start before 98.37 hours. Even in case adequate radiation shielding is

lost (after 52 hours), the station will be able to carry out SFP water makeup or spray

through its dedicated water makeup or spray piping.

However, to secure cooling of the SFP, comprehensive manual actions are required. It is

difficult to add water in the spent fuel pool, which is located at a height of about 32

meters under accident conditions. The Fukushima accident has highlighted this issue.

The location of the SFP outside the primary containment aggravates the situation, thus a

release of radioactive material is threatening during a severe accident.

If SFP water temperature increases, second containment venting to discharge heat into

atmosphere has to be performed. However, this measure will cause a release of

radioactive substances.

35

The decay heat in the SFP is the maximum if all core fuel is transferred to the SFP in the shortest time

after unit shutdown. The decay heat of the spent fuel is calculated based on the assumptions that spent

fuels are discharged into the pool from last 9 cycles and all core fuels are discharged after 7 days of unit

shutdown. 36

Technical Support Centre (TSC), Accident Management Team (AMT), Operation Support Centre (OSC),

Health Physic Centre (HPC), and Emergency Public Information Centre (EPIC)

Page 41: 福島核災後龍門電廠(核四廠)壓力測試評估 Review of the post

41

For the case of spent fuel becoming uncovered, there is no discussion in the NR about the

possibility of a steam-water reaction or zirconium fire or about the hydrogen which will

be produced. It has to be assumed that there are no measures available to cope with such

a severe accident.

Note that in the EU, it is under consideration to take measures to practically eliminate

spent fuel uncover in the pool, because the situation after fuel uncover is extremely

dangerous.37

According to the ENSREG, the hydrogen production in SFPs has to be carefully analyzed

and adequate countermeasures adopted if necessary [ENSREG 2012a].

The means for reliably monitoring the water level in the SFP under accident conditions

are not addressed by TPC. The AEC required installing SFP instrumentation to monitor

key spent fuel pool parameters (i.e., water level, temperature, and area radiation levels)

consistent with the recommendation 7.1 of the USNRC NTTF Report. Accordingly, only

the protection against design-basis events is required. This is not in accordance with the

ENSREG recommendation, which ask for the use of dedicated instrumentation resistant

to extreme external hazards (i.e. beyond design events), either passive or powered from

reliable sources.

AEC s conclusion and requirements

The assessment and conclusions of the AEC indicates that the severe accident

management of the NPP4 is not sufficient at all:

AEC highlighted the importance of the justification of the URG; of particular concern is

the depressurization of the reactor. This is the key measure to be able to prevent a severe

accident.

Regarding the establishment of the URGs, the AEC requires TPC to identify their

implementation timing, the subsequent measures and monitoring strategy, including the

monitoring of radioactive releases, backup ability of present systems and equipment, etc.

In the opinion of AEC, the hydrogen and containment pressure control strategies in the

URG do not take into account various accident scenarios.

The AEC has obviously doubts that the operator is able to cope with a severe accident

that affects both units simultaneously. TPC is required to estimate the duration of

37

ENSREG highlighted: “Maintained coolant inventory in the SFP needs to be ensured by verification or

by upgrading SFP structural integrity, installation of qualified monitoring, and by provisions for

redundant and diverse sources of additional coolant resistant to external hazards in order to practically

eliminate the risk of fuel uncovery“ [ENSREG 2012a].

Page 42: 福島核災後龍門電廠(核四廠)壓力測試評估 Review of the post

42

independent response capability for various severe accidents, beyond design accidents,

and multi-event accidents.

Furthermore, the AEC requires ensuring the capability of DC power for instrumentation

and control (I&C) systems of main control room (MCR) during SBO accidents.

The AEC requires the integration of the emergency operating procedures (EOPs), severe

accident management guidelines (SAMGs), and extensive damage mitigation guidelines

(EDMGs) with the ultimate response guidelines (URGs). Note: The OECD/NEA group

pointed out that there could be a little confusion on how the URGs are to be used in

conjunction with EOPs and SAMGs [OECD 2013].

Regarding procedures, training and exercises, the AEC requires combining the additional

equipment and operations into the procedures or guideline, to re-evaluate the feasibility

of EOPs and SAMGs with the involvement of new procedures/guidelines, to ensure that

the SAMGs are appropriate for multi-unit events and to improve the emergency

preparedness staffing and communications.

The ENSREG recommended to asses and ensure the radiation protection of operators and

all other staff involved in the SAM and emergency arrangements by adequate monitoring,

guaranteed habitability of the facilities needed for accident control [ENSREG 2012b].

This important issue is not adequately addressed by TPC or the AEC.

The ENSREG pointed out that the means for maintaining containment integrity should in

particular include depressurization of the reactor coolant system, prevention of damaging

hydrogen explosions, and means of addressing long-term containment over-

pressurization, such as filtered venting [ENSREG 2012b]. None of these means is

sufficiently addressed by TPC. The means are also only partly included in the AEC

requirements, i.e. containment failure and thus the release of radioactive material will

not be prevented adequately in the future – not even if technical means are available.

Page 43: 福島核災後龍門電廠(核四廠)壓力測試評估 Review of the post

43

4 Weaknesses the Taiwanese stress tests ignored

Several safety issues that can trigger or aggregate an accident have not been evaluated

during the stress tests. They are discussed in this chapter.

This chapter is mainly based on a special edition magazine published in March 2013 in

Taiwan38

. This article includes comprehensive information provided by Tsung Yao Lin39

,

an expert with practical experiences in nuclear power plant construction and safety

analysis and a former member of the Fourth Nuclear Power Plant Safety Monitoring

Committee.

In July 2011, Tsung Yao Lin stated that NPP4’s problems are so sizable and serious that

TPC will not be able to solve this by itself. He wrote a paper titled “Essay on the Fourth

Nuclear Power Plant”, in which he described structural issues of NPP4 (including

equipment, construction, quality assurance and supervision). Later he published

“Strategies for the Fourth Nuclear Power Plant”, suggesting practical solutions. The

chairman of the Fourth Nuclear Power Plant Safety Monitoring Committee placed a very

high value on this report.

4.1 Shortcoming during procurement of equipment

In the beginning, TPC wanted to have a consulting firm to organise and handle all the

contracts. However, the bidding price for experienced foreign consulting firms would

have been relatively high, because they would take more risks. Unfortunately, no bidder

won the bid as their offers exceeded the 20% of the base price.

Under the limited budget, TPC outsourced the two ABWRs to GE, and then hired Stone

and Webster International Corporation (SWIC) as the consultant taking charge of the

design. According to the agreement, SWIC was responsible to come up with the purchase

specifications, and TPC was in charge of the procurement. It was difficult to ensure the

quality of the equipment purchased through low bidding prices; furthermore, it disrupted

the working procedure. The incident mentioned below with the fire plug reveals that there

are shortcomings in TPC’s expertise in procurement.

In July 2007, TPC decided to terminate the agreement. Many projects were unfinished at

the time of termination, such as NPP4’s final safety analysis report (FSAR). TPC had to

undertake those tasks; however, TPC does not have sufficient experience to do so.

38

Author: Wang Mei Zhen (王美珍), Special edition on Longmen Nuclear Power Plant (NPP4)

Controversies, Global View Monthly, March 2013 39

He graduated from Department of Nuclear Engineering of Ching Hua University in 1969 and worked

for both GE and Bechtel Corporation as a consultant. During the time when NPP2 and NPP3 were

under construction, Lin worked as the representative of a US consultant company for seven years.

Page 44: 福島核災後龍門電廠(核四廠)壓力測試評估 Review of the post

44

4.2 Many design changes

The Atomic Energy Council (AEC) pointed out that between 2007 and February 2012,

TPC has made at least 15 major violations, including changing construction design at will.

During the construction process, up to 1,530 items underwent changes in design. TPC

mentioned three reasons: First, the consulting firm, SWIC, left the project. SWIC made

lots of mistakes in design drawings, and those all had to be corrected.

Second, from the very beginning, General Electric Co. (GE), who won the bid for the

nuclear island, planned to completely copy the model of Japan’s Kashiwazaki-Kariwa

nuclear power plant. However, the facilities Japan bought were made in Japan, whereas

the facilities GE bought were made in Europe and the US. They all differed in size. It was

figured out in the beginning that many facilities could not fit in the nuclear island. Motors

and pipelines were all somewhat different from original designs.

Third, the sequence of facilities installation also results in design changes. For example,

if water pipes are installed first, then it is likely that air pipes and electrical lines will not

fit. To avoid changes, the sequence has to be exactly the same as design drawings show,

but in fact it is impossible as NPP4 must adhere to the government’s Procurement Act.

What came first would be installed first, and this was likely to affect the facilities

delivered later. Therefore, changes had to be made and there was no way to stick to the

original design.

Because of all design changes the design of the actual plant is not similar to the original

design. This could affect the plant behaviour during accidents or the resistance against

earthquakes.

4.3 Inadequate safety culture

International experts pointed to the inadequate safety culture during the construction

process:

Some years ago, the Atomic Energy Council invited representatives of Japan

Nuclear Energy Safety Organization (JNES) to assist in check-up. Later on, those

Japanese representatives wrote in the report: “This construction site was not safe.

We were worried it would pose threats to Japanese representatives’ safety. As a

result, we were unsure whether we would be able to come to assistance again.”

A couple of years ago, a former designer of GE, Yoichi Kikuchi, came to Taiwan

to inspect NPP4’s construction site. In an interview he commented: “In every

aspect, I didn’t think this power plant would be worked. Rusted steel reinforcing

bars were scattered everywhere. Engineering and construction management was

commissioned to downstream contractors, and no one was overseeing the

construction prudently.”

Page 45: 福島核災後龍門電廠(核四廠)壓力測試評估 Review of the post

45

Several important shortcomings that could result in accidents during operation were

identified and remedied. In 2002, for example, TPC had to reassemble four of five layers

of the reactor pressure vessel (RPV) support platform of unit 1, after regulators confirmed

that workers used improper welding material in assembling it the first time. Workers had

used low-intensity welding material to assemble the platform where high-intensity

material had been specified.

One important reason for the insufficient safety culture during the construction phase is

the following: NPP4 workers revealed that Hung Chi Shih, former vice president of TPC,

insisted on speeding up the work to meet the deadline. He would set up a completion date,

and if the team failed, all managers and directors would be demoted to technicians. As a

result, many issues were left unreported to avoid getting scolded.

Safety culture in the construction site should be conscientious and must be extremely

strict. However, quite the opposite seems to be the case.

4.4 Incidents during the construction process

The construction of NPP4 did not only take a long time, it was also accompanied by a lot

of troubles. In the last few years, several incidents, among them fires and floods, occurred

during NPP4’s construction phase:

Jul. 2008: When typhoon Sinlaku hit Taiwan, the lack of disaster prevention carried

out by TPC caused accumulated water flood into the second machine room

that reached two meters high, immersing facilities such as the emergency

cooling system.

Jan. 2010: Piles of electric cords were burned up, causing fire at the construction site.

Mar. 2010: The first reactor’s uninterruptible power system failed, causing fire in the

central control room.

May 2010: TPC workers followed the method used in the three nuclear power plants

to clean the electronic enclosure of the central control room with vacuum

cleaners. Unexpectedly, the static electricity generated interfered with the

output voltage, and caused a short-circuit.

Jul. 2010: The electrical system was burned out, causing power outage in the plant.

Aug. 2010: Rain damaged a voltage transformer, causing abnormal power supply for

three days.

Sep. 2010: Electric cables were not laid as required (see below).

Jan. 2011: Electric cables in the central room were damaged by mice. Only after this

incident, a strict rule has been made that no food is allowed at the

construction site.

Page 46: 福島核災後龍門電廠(核四廠)壓力測試評估 Review of the post

46

Aug. 2011: Operators pumped water from the condensate water tank to the

suppression pool without following the maintenance rules. This caused a

large volume of water to emit from the valve body. The control rod

accumulator’s level switch and some other safety-related equipment were

affected by the water.

Oct. 2011: TPC commissioned an inexperienced company to manufacture electric

machinery pipes.

Mar. 2012: The tap of the fire hydrant in the first unit room of NPP4 failed and water

poured out, causing up to 30 cm of water accumulation in the equipment

operating room. The reason was that for the hydrant a Japanese model was

used, whereas the connecting extinguisher pipe was from the US. Merely

26.1% of the parts fit properly.

Apr. 2012: A malfunctioning automatic bleeder vent of the sea water system caused

the overflow of sea water, resulting in 150 cm of water accumulation.

However, the same thing already happened in September, October, and

December 2011. This showed that TPC is incapable of completely

resolving issues concerning equipment design and quality that cause the

incidents to happen again.

Up to now, only the failures of structures, systems and components (SSCs) running into

problems were exposed. But it has to be expected that other parts have deficiencies as

well and that there are several deficiencies that remain undiscovered.

Additionally, since the plant has been under construction for so long, it is possible that

degradations effects take place already.

4.5 Insufficient quality assurance (QA)

In August 2011, cable re-arrangement was needed since cables were laid incorrectly. In

total, those cables were 2120 thousand meters in length. This example showed that NPP4

had problems with supervision and quality assurance.

There are three layers of quality assurance. The first layer is the internal quality assurance

from contractors, the second one is supervision from Lungmen Construction Office, and

the third one is quality assurance from the safety unit of the TPC head office.

In the past, TPC deployed their own staff, but now many operating staff are employed by

contractors. At Lungmen Construction Office, there are around 1,500 quality assurance

testers (second layer), among them around 680 persons from TPC.

TPC failed to identify the problem of cable rearrangement at the first and second layers

and discovered the problems at the third layer, only.

Page 47: 福島核災後龍門電廠(核四廠)壓力測試評估 Review of the post

47

Tsung Yao Lin highlighted another issue regarding insufficient quality assurance.

Welding operation had been problematic while he was a member of the Fourth Nuclear

Power Plant Safety Monitoring Committee. If welding is not done properly, pipes would

break and water would leak.

The Quality Assurance (QA) should guarantee, among others, that deficiencies are

remedied, however the QA is insufficient.

4.6 Concerns regarding the I&C System

The instrumentation and control (I&C) system architecture, together with plant

operations personnel, serves as the "central nervous system" of a nuclear power plant

(NPP). Through its various elements (e.g., sensors, transmitters, actuators, etc.), the plant

I&C system senses basic physical parameters, integrates information, and makes

automatic adjustments to plant operations. It also responds to failures and off-normal

events, thus it is necessary to cope with accidents. The IAEA recommended giving as

much attention as their importance for design, testing, operation, maintenance, licensing,

operation, and modernization of I&C systems [IAEA 2013].

NPP4 is the first Taiwanese NPP designed to be totally digitally controlled. The operation

and maintenance of the Information and Control (I&C) system will be an issue for the

system operator and regulator. 40,000 digital signals brought up safety concerns. This

system had been assigned to three different contractors. Thus, there are doubts whether

the interfaces will work together or not, and their accuracy and stability remain an

underlying concern [NW 16/05/13].

The Finnish regulator, for example, requires a hard-wired backup to the digital system for

the EPR (also with a digitized I&C system) under construction at Olkiluoto nuclear

power site. In 2010, the US NRC required AREVA to modify its US EPR design to

include a hard-wired back-up.

The AEC needs to require the installation of a hard-wired backup I&C system in NPP4.

4.7 Inappropriate test-operation procedures

SWIC, the company responsible for the test-operation, lacked the necessary expertise.

According to TPC, SWIC did a very poor job. They even returned the money for

compiling the procedures before the agreement was terminated, and asked TPC to write

down the procedures themselves.

However, this could also lead to shortcomings, because TPC has not enough experience

to do this. Test-operation begins with composing the procedures, because the way the

Page 48: 福島核災後龍門電廠(核四廠)壓力測試評估 Review of the post

48

procedures are written determines how the tests are to be conducted. Things that are not

mentioned in the procedures will not be checked.

Another major issue is in the primary stage during NPP4’s test operation: those

performing the tests and those taking over the plant were the same group of TPC people.

Thus, it has to be feared that not all failures of the systems will be discovered. To

overlook failures of the I&C system is of particular concern.

4.8 Role of the Atomic Energy Council (AEC)

As described above, TPC has not enough experience to guarantee that the structures,

systems and components (SSCs) are installed as intended and with the appropriate

quality. This situation is aggravated by lack of experience of the Atomic Energy Council

(AEC).

According to Tsung Yao Lin, under the existing circumstances the safety of NPP4 could

not be guaranteed by the AEC. Tsung Yao Lin criticized that the AEC was merely

checking the laws, regulations, and procedures.

Lin explained that the AEC has adopted the regulatory style used for the operating plants.

However, since these plants adopted a standard design and were built by foreign

consulting firms under turnkey contracts, in a way they were already checked by the

nuclear energy control authority in the US. The AEC only had to make sure all things

abide by relevant laws and regulations, and check the procedures.

As NPP4 has a unique design and its contract with the original foreign consulting firm

had been terminated, the consulting firm’s duties, such as design, procurement, and

supervision were handed over to TPC and other contractors. However, the AEC did not

have the manpower to run on-site inspections for the designs, facilities, constructions and

test-operations.

According to Tsung Yao Lin, the US nuclear regulatory commission (NRC) has more

than 2,000 engineers to provide consulting services; thus, their inspections and audits can

be thorough. Although the AEC has tried its best, it is still inadequate. The AEC could

only conduct random inspections, not general ones, even for those safety-related systems.

The above-mentioned incident with the fire plug reveals that there are shortcomings in

TPC’s expertise in procurement. However, the appropriateness of TPC’s procurements

and the installation process are not under the AEC’s control.

Furthermore, the AEC admitted that it is impossible to check through all the test

operation procedures.

Page 49: 福島核災後龍門電廠(核四廠)壓力測試評估 Review of the post

49

Lin criticized the ministry for incompetence in solving problems regarding the plant. In

addition, Lin said that the AEC is incapable of comprehensively supervising the

construction of the nuclear power plant, adding that the there is no guarantee for the

power plant’s safety and quality.

However, the ministry answered that the government will fulfil its duty, ensuring that the

NPP4 will not be allowed to function unless security checks prove its safety; even if a

referendum accepts to continue construction of the nuclear power plant [TAIPEITIMES

2013a].

Lin added that it is difficult to find solutions for problems at NPP4, because there are too

few professionals at the Ministry of Economic Affairs and the council who understand

the issues [TAIPEITIMES 2013c].

Page 50: 福島核災後龍門電廠(核四廠)壓力測試評估 Review of the post

50

5 The EU-ABWR

There are two Advanced Boiling Water Reactors (ABWR) installed in the NPP4. The

ABWR nuclear island is designed and manufactured by General Electric Co. (GE).

The ABWR was originally developed in Japan. The first ABWRs (Kashiwazaki-Kariwa-

6 and -7) entered into commercial operation in 1996 and 1997, respectively. Since then,

only three more units started commercial operation in Japan: Hamaoka-5 (2005),

Higashidori-1 (2005) and Shika-2 (2006). However, these plants are offline for safety

checks following the Fukushima accident.

The ABWR was developed jointly by General Electric Co. (GE), Toshiba and Hitachi,

following on from GE's development of the BWR concept in the 1950s [WNN 2009b].

Today, both GE-Hitachi (who merged their nuclear businesses in 2007) and Toshiba

assert the right to build the ABWR [WNN 2009b].

GE-Hitachi Nuclear Energy (GEH)40

has submitted an application to the US Nuclear

Regulatory Commission (NRC) to renew the certification for its ABWR. Formerly, only

GE-Hitachi owned the US design certification. The US NRC issued a final rule certifying

the design on May 12, 1997. The original 15 year ABWR certification is set to expire in

June 2012. The latest application includes a design update to reflect the current NRC

requirement for an aircraft impact assessment [NEI 2010c].

In April 2013, Hitachi-GE signed agreements with UK nuclear regulators to carry out a

generic design assessment (GDA) of its new ABWR reactor design41

[NEI 2013b]. GDA

is a long-term and rigorous process, which will ultimately determine whether the

regulators will consider the ABWR suitable for construction in the UK [NEI 2013c].

Two ABWRs are planned for the South Texas Project (STP) in the US42

, but Toshiba was

selected as the prime contractor for the development in March 2008 [NEI 2009b; WNN

2009c].

Toshiba subsequently developed its own variant of the certified ABWR design for

construction at units 3 and 4 of the existing STP site, which were scheduled to come

online in 2016 and 2017, respectively. This design was submitted to the NRC in June

2009 and had to meet new aircraft impact rules. The Toshiba version of the ABWR

40

GEH is a global nuclear alliance created by General Electric and Hitachi. In Japan, the alliance is

Hitachi-GE Nuclear Energy Ltd. 41

Horizon Nuclear Power plans to build two to three 1300 MW-class ABWR-based nuclear power plants

at Wylfa and Oldbury (UK) 42

The future development of South Texas Project (STP) units 3 and 4 looks unlikely after majority

shareholder NRG Energy announced in April 2011 that it was withdrawing from the project, writing

down a $481 million investment and excluding any further investment [SCHNEIDER 2013].

Page 51: 福島核災後龍門電廠(核四廠)壓力測試評估 Review of the post

51

would be considered safe even if one was hit by a large civilian aircraft. Following such

an impact, only minimal operator input should prove necessary in order to keep the

reactor core cooled and to maintain integrity and cooling at the used fuel pools. In

November 2011, NRC certified an amended version of Toshiba s ABWR [WNN 2010a;

WNN 2011d].

Toshiba is currently adapting the ABWR design also for the European market, first for

Finland. Toshiba's 1600 MW EU-ABWR design is under consideration for an envisaged

new nuclear power plant at the Hanhikivi site in northern Finland [NEI 2013a]. The

European version of the ABWR has been called EU-ABWR. Safety improvements based

on the defence-in-depth (DiD) concept have been implemented for instance to prevent

and mitigate long-term Station Black-Outs (SBO) and severe accidents.

The following chapter highlights the shortcoming of the outdated design of the ABWR

constructed at the Lungmen NPP, because these ABWRs have not implemented these

necessary safety features according to the state-of-the-art.

However, it is not clear whether it is technically feasible to upgrade the ABWR design of

NPP4 to the EU-ABWR standard. The feasibility could be limited due to two reasons:

First, it is physically impossible that the new safety features fit into the existing structures.

Second, it is not clear whether the safety systems which are sufficient for a European

nuclear power plant site are also appropriate for the Lungmen nuclear power plant site,

which is threatened by severe earthquakes.

5.1 Defence-in-Depth Concept

Principally, the Defence-in-Depth (DiD) concept was already part of the very early power

reactor designs. However, additional considerations have been done in order to take plant

conditions into account which are beyond the original design basis. The most recent

advancements have been done based on major lessons learnt from the Fukushima

accident [YAMAZAKI 2013].

The operational principle of the DiD concept shall be implemented to

1. ensure reliable prevention of anticipated operational occurrences (AOO) and

accidents (prevention)

2. facilitate the quick and reliable detection of AOO and accidents and prevent the

aggravation of any event (control of anticipated operational occurrences and

accidents)

3. mitigate the consequence of any accident and prevent radiation hazards (mitigation

of consequences)

Page 52: 福島核災後龍門電廠(核四廠)壓力測試評估 Review of the post

52

The DiD concept of the EU-ABWR is based on the concept that is established by the

Reactor Harmonization Working Group (RHWG) of Western European Nuclear

Regulators Association (WENRA). Accordingly, the safety functions concept shall be

assured through five successive levels of protection. An illustration of the safety levels is

given in Figure 1.

Figure 1: Defence in Depth (DiD) Concept according to the WENRA

5.2 Technical realisation of DiD requirements

In the DiD Level 2, the safety functions are implemented to restore and maintain a

normal state after defined Anticipated Operational Occurrence (AOO) using for example

the Isolation Condenser (IC). The IC system is implemented in the EU-ABWR to

enhance the safety level. It is a passive system that condenses steam from the reactor and

feeds the condensate through the feedwater lines back to the reactor. The heat from the IC

is transferred to the coolant water of the IC tanks and from there directly to the

atmosphere. A schematic of the IC, that partly uses the same components as the Passive

Containment Cooling System (PCCS), is given in Figure 2.

Page 53: 福島核災後龍門電廠(核四廠)壓力測試評估 Review of the post

53

Figure 2: Isolation Condenser (IC) and Passive Containment Cooling System (PCCS)

The structures, systems, and components (SSCs) designated to DiD level 3a – Design

Basis Accident (DBA) – fulfil safety functions in case of postulated single initiating

events. These SSCs are independent of those used in normal operation and in case of

AOO.

The initiating events for DiD Level 3b – Design Extension Condition (DEC) – are

defined as postulated accidents with coincident common cause failure (CCF), multiple

failures and rare events, such as extreme weather phenomena or a commercial air plane

crash.

Compared to the previous ABWR versions EU-ABWR adopts an Emergency Core

Cooling System (ECCS) that consists of three divisions of different sub-systems.

5.3 Severe Accidents (DiD Level 4)

The EU-ABWR includes complementary safety features specifically designed to fulfil

safety functions required in postulated core melt accidents (DiD level 4).

Several Severe Accident Management (SAM) measures are implemented in the EU-

ABWR design preventing or mitigating containment failures. The SAM strategy utilises a

core catcher against molten core-concrete interaction and loss of core melt cooling. To

prevent containment overpressure, the Passive Containment Cooling System (PCCS) is

used for containment heat removal. Figure 3 illustrates the interaction of the core catcher

and the PCCS.

Page 54: 福島核災後龍門電廠(核四廠)壓力測試評估 Review of the post

54

Figure 3: Operation of EU-ABWR Passive Containment Heat Removal System during Severe

Accident

The initial cooling water for the core catcher is supplied from the suppression pool.

Fusible valves will open the PCCS condensate drain. A large amount of steam is then

generated at the core catcher and released into the drywell. The gas mixture including

steam and non-condensable (NC) gases flows from the drywell into the PCCS. The steam

is condensed inside the PCCS heat exchanger which is located in the same tanks as the IC.

The condensate is drained gravitationally to the core catcher down-comer. NC gases are

purged to the wet well pool through the NC gas vent lines.

The passive severe accident mitigation systems aim to maintain the containment integrity

without containment venting. The initial cooling water capacity lasts for at least 72 hours.

No external power is necessary to initiate the driving force opening motor operated

valves or starting pumps. The EU-ABWR has a dedicated power supply for the

instrumentation and control system for SAM measures even in the event of SBO and loss

of essential power supply.

Note: These are the statements of the supplier, who is interested in selling his product.

Certainly, whether all systems will operate in a severe accident situation during or after

an earthquake is not guaranteed. Nevertheless, the design is improved compared to the

original ABWR design by adding passive systems to avoid manual actions of the operator

in case of loss of all power supply and/or ultimate heat sink.

Page 55: 福島核災後龍門電廠(核四廠)壓力測試評估 Review of the post

55

6 Discussion of the results and conclusions

Experience of the stress tests in Europe

Despite the fact that the stress tests revealed a number of shortcomings regarding the

plants’ capability to withstand several external hazards and the lack of possibilities to

cope with the consequences, the outcomes of the peer reviews of the European nuclear

power plants consist only of recommendations for “further improvements”. The fear of

representatives of civil society and independent experts that the stress tests were mainly

set up to improve the confidence in the safety of the European NPPs regardless of his

findings becomes true. The operation of dangerous NPPs is ongoing.

The experience highlights: the ENSREG did not assess, but only describe the

shortcomings of the European NPPs. The peer review of the stress test reports did not

formulate any overall conclusions – not even if a specific NPP showed shortcomings

similar to those of the Fukushima NPP.

Furthermore, the ENSREG avoided mentioning, whether the national action plans (NAcP)

to remedy the weaknesses are sufficient to amend the dangerous situation if completely

implemented.

One of the major weaknesses is the lack of definition in the stress test specifications,

which level of safety should be achieved if the plants should be back-fitted or shut down.

This deficit makes it very difficult for politicians and the public to assess the safety level

of the plant.

Therefore, it cannot to be expected that the peer review of the ENSREG/EC group will

give any advice about the decision to commission NPP4 or not – regardless of the

findings.

Limited scope of the stress tests

The EU stress tests cannot be understood as a comprehensive safety check of nuclear

power plants, because the stress tests did not take into account all key safety issues.

However, the safety issues that are out of the scope of the stress tests are of utmost

importance to assess the risk of the NPP4.

The quality of the plants’ structures, systems and components (SSCs) are not investigated

during the stress tests. Furthermore, the stress tests take for granted that all the SSCs are

in place and without faults. This assumption is not correct for any nuclear power plant,

but particularly not for the NPP4. TPC could not guarantee that the SSCs are installed

with the appropriate quality and without deficiencies. This situation is aggravated by

excessive demands of the Atomic Energy Council (AEC).

Page 56: 福島核災後龍門電廠(核四廠)壓力測試評估 Review of the post

56

Several failures of structures, systems and components (SSCs) have been discovered

during the construction process. However, up-to now only failures running into problems

were exposed. Because quality assurance programs as well as test procedures are

insufficient, there are real fears that not all failures of the SSCs will be discovered before

commissioning. In addition, the overlook of potential failures of the I&C system are of

particular concern.

Numerous design changes could affect the plant’s behaviour during accidents and its

capability to resist against earthquakes.

All these failures could aggravate an accident situations triggered by a natural hazard.

Stress test results and measures to remedy weaknesses

The Lungmen nuclear power plant site is located in a high seismic risk zone, thus

earthquakes are an important hazard for the plant. Since a site-specific seismic hazard

analysis is lacking, it may be necessary to revise maximum magnitude values for faults.

A value of 9.0, which was the magnitude of the 2011 Tohoku earthquake that triggered

the Fukushima accident, is possible. However, the envisaged measures to increase the

seismic margins of the plant are very limited.

Regarding earthquake hazards, there is also an unsolvable problem: There are doubts

about the reliability of the structures, systems and components (SSCs) of the NPP4. It is

probably impossible to calculate the seismic resistance of the plant, due to the numerous

shortcomings during the construction phase. Those construction mistakes will make the

resistance of the plant unpredictable and the plant especially vulnerable to seismic

hazards.

Fukushima highlighted the danger of flooding triggered by a tsunami. But it is highly

questionable whether the operator, TPC, and the regulatory authority, AEC, are fully

aware of this problem. An adequate evaluation of the tsunami hazard using state-of-the-

art modelling is missing. Thus, the wave run-up, against which the NPP4 has to be

protected, is not known so far. Therefore, it is a matter of fact that the protection against

tsunamis is not adequate, even after implementing the envisaged measures (e.g. building

a sea wall).

The protection (including safety margin) against flooding events caused by storms and

heavy rain is also not sufficient. Extreme weather events, such as typhoons, heavy rain,

and mudslides can affect the Lungmen NPP site. However, the effects are not analysed

adequately. Furthermore, a systematic evaluation of combinations of extreme weather

events is still lacking. The same is true for the risk assessment of the potential volcanic

hazards.

Page 57: 福島核災後龍門電廠(核四廠)壓力測試評估 Review of the post

57

The stress tests in Taiwan should largely be based upon the EU stress test model.

However, the methodology used to evaluate the design basis of natural events is not in

accordance with recommendations of the EU stress tests.

In summary the threat of natural hazards is not sufficiently evaluated. However, the

threat is significantly greater than assumed by TPC.

The ultimate heat sink (UHS) is vulnerable against natural hazards. Nevertheless the

measures to prevent loss of heat removal envisaged by TPC are very limited. A more

expensive, but more effective measure would be the implementation of a new

independent diversified ultimate heat sink (UHS) (without using the sea). But until now

this is not definitely required by the AEC.

According to the AEC, TPC s evaluations of the different accident scenarios are not

sufficient. Furthermore, in the opinion of the AEC, the feasibility of TPC s accident

management to prevent a severe accident is not assured.

All in all, both the design and the non-conventional means (e.g. mobile equipment) are

not sufficient to cope with a loss of all power supply (SBO) and loss of the ultimate heat

sink (UHS) triggered by an earthquake or another extreme natural event. It is not clarified

to which extent TPC will remedy this dangerous situation which could result in a severe

accident. Measures envisaged by TPC to prevent fuel damage need several additional

manual actions of the operator.

Obviously TEPCO is planning a more comprehensive upgrading program of its ABWR

(Kashiwazaki-Kariwa unit 7) compared to TPC: After performing stress tests, TEPCO

envisaged several backfitting measures. According to TEPCO, after implementing

additional safety measures, even if a Station Black-Out (SBO) occurs, it would take about

12 days until coolant injection functions for the reactor core and spent fuel pool get lost.43

The Severe Accident Management necessary to prevent or mitigate major releases of

radioactive substances envisaged by TPC is not sufficient. In order to cope with the

compound disaster condition, for example earthquake and tsunami, TPC had prepared

procedures (Ultimate Response Guidelines (URG)). AEC highlighted the importance of

the justification of the procedures (URGs) to cope with a severe accident; of particular

concern is the depressurisation of the reactor. This is the key measure to be able to

prevent a severe accident. However, the measure proposed by TPC could have a negative

effect.

43

The additional safety measures included water-tight seals, flood barriers, air-cooled gas turbine

generators, emergency electrical switchgears and back-up truck-mounted heat exchangers. Other

equipment installed includes hydrogen sensors inside the reactor building, filtered containment vents,

spent fuel pool water level gauge and camera, on-site heavy equipment for debris removal and

additional radiation monitoring cameras [NEI 2012c].

Page 58: 福島核災後龍門電廠(核四廠)壓力測試評估 Review of the post

58

Specially, there are doubts about the implementation timing of the URGs. However, only

if the measures can be performed as fast as envisaged, fuel damage will not occur. But

after loss of water supply, the fuel damage would start after only 1.6 hours. It has to be

considered that after an extreme earthquake and/or tsunami it is very difficult and

dangerous to perform these measures.

It is also very difficult – or even impossible – to provide the large amount of water that is

required to prevent a severe accident (442.2 tons per hour for both units). It is not proven

that during and after a natural hazard sufficient water sources exist and water supply is

possible.

None of the means for maintaining containment integrity during a severe accident is

sufficiently addressed by TPC. The means are also only partly included in the

requirements of AEC, i.e. containment failure and thus the subsequent release of

radioactive material during a severe accident will not be prevented adequately – not even

if technical means are available.

The envisaged chief measure to prevent hydrogen explosions and overpressure in the

containment is by venting, despite the fact that this measure will cause a major release of

radioactive substances.

The measures for the prevention of the basemat melt-through are not sufficient.

Furthermore in case of a severe accident, it has to be expected that large amounts of

radioactive water will be released into the environment. Adequate measures suitable to

cope with a severe accident in the spent fuel pools are also lacking.

Toshiba is currently adapting the ABWR design also for the European market. The EU-

ABWR includes complementary safety features specifically designed to fulfil safety

functions required in postulated core melt accidents. Several passive devices to manage a

severe accident and to prevent containment failures are implemented in the EU-ABWR

design. The new safety features of the EU-ABWR highlight the shortcomings of the

design of the ABWRs of the Lungmen NPP that have not implemented these passive

state-of-the-art measures.

Instead, TPC is heavily relying on the new magic solution to compensate the design

deficiencies: mobile equipment, which is easy to plan and store in the plant and therefore

a cheaper solution than the installation of new systems protected against external hazards.

But under severe accident conditions, it is very unlikely that the proposed mobile

equipment can be put to work as quickly as needed. Furthermore, the new mobile

equipment is useless if the staff response during the accident is not functionally according

to plan. This is an important lesson learnt from the Fukushima accident, which should

Page 59: 福島核災後龍門電廠(核四廠)壓力測試評估 Review of the post

59

result in the implementation of passive safety systems designed to withstand beyond

design basis accidents with appropriate safety margins.

To rely to such a large extent on manual actions is irresponsible in regard of the

consequences of a severe accident.

The AEC requirements

It is consensus among experts that the peer review of stress tests cannot provide

exhaustive verification of the comprehensiveness and adequacy of the safety measures.

Consequently, this process cannot replace the more detailed work performed by the

national regulatory bodies. However, there are concerns that the Taiwanese regulator, the

Atomic Energy Council (AEC), has not sufficient experience and resources to cope with

the workload of all necessary evaluations and back-fitting measures.

The AEC’s requirements to remedy the weaknesses of the NPP4 are very general, thus

the scope of the backfitting measures cannot be judged. Furthermore, the time schedule

for implementation of proposed safety measures is not mentioned. Therefore, it cannot be

assured that necessary backfitting measures will be in place before NPP4 starts operating.

The decision about the scope of necessary back-fitting measures is in particular an

economical issue. Comprehensive backfitting will result in better protection but also in

higher costs. However, to improve the safety level in an area prone to seismic or flooding

hazards is a highly technical issue. An adequate safety level cannot be achieved

subsequently. Thus, it is impossible to achieve an acceptable safety level for NPP4.

Conclusion

Regarding the existing natural hazards, the design weaknesses and the deficiencies of the

structures, system and components, it is not possible to retrospectively bring the NPP4 to

an acceptable safety level. Therefore, a severe accident with a major release of

radioactive substances cannot be excluded.

Considering the short distance of the NPP4 to the city of Taipei, such a severe accident

would have disastrous consequences for millions of people.

Taking all facts into account we recommend to stop the NPP4 project and to not

commission this nuclear power plant

Page 60: 福島核災後龍門電廠(核四廠)壓力測試評估 Review of the post

60

7 References

AEC 2013: Atomic Energy Council Taiwan Stress Test National Report for Nuclear Power

Plants, May 28, 2013,

BECKER 2013: Critical Review of the National Action Plan (NAcP); EU Stress Test performed

on Nuclear Power Plants; Study commissioned by Greenpeace; Oda Becker, Patricia Lorenz;

Wien, Hannover, April 2013

ENSREG 2011: European Nuclear Safety Regulators Group (ENSREG): Declaration of

ENSREG, “Stress test” specifications; Brussels, 2011/05/13, http://www.ensreg.eu/node/286

ENSREG 2012a Peer review report; Stress tests performed on European nuclear power plants; 25

April 2012;

www.ensreg.eu/sites/default/files/EU%20Stress%20Test%20Peer%20Review%20Final%20Report_0.pdf

ENSREG 2012b Compilation of recommendations and suggestions; Peer review of stress tests

performed on European nuclear power plants; 27 July 2012;

http://www.ensreg.eu/sites/default/files/Compilation%20of%20Recommendationsl_0.pdf

HSU 2013a: Letter to ENSREG Experts; 3 July 2013; Gloria Kuang-Jung HSU, Jay Fang, Lill

Liu, Chia-Wei Chao, Chou-Han Lee, Irene Chen

HSU 2013b: Comments on Taiwan Stress Test National Report for NPPs; submitted by Gloria

Kunag-Jung HSU Taiwan Environmental Protection Union; 4 July 2013

IAEA 2003: International Atomic Energy Agency (IAEA): Flooding Hazard for Nuclear Power

Plants on Coastal and River Sites, Safety Guide; IAEA Safety Standard Series; NS-G-3.5;

Vienna; December 2003

IAEA 2013: International Atomic Energy Agency (IAEA): Nuclear Power Engineering;

Instrumentation and Control Technologies; Vienna 2013;

http://www.iaea.org/NuclearPower/IandC/index.html

IPCC 2007: Contribution of Work Group 1 to the Fourth Assessment Report of the

Intergovernmental Panel on Climate Change, 2007;

http://www.ipcc.ch/publications_and_data/ar4/wg1/en/contents.html

IPCC 2013: Intergovernmental panel on climate change: IPCC Fourth Assessment Report:

Climate Change 2007; http://www.ipcc.ch/publications_and_data/ar4/wg2/en/ch10s10-2-3.html

JPG 2012: Joint Project Group: Stress Tests & Vulnerability Assessment; Recommendations and

Experience of the Joint Project Group; 2012; www.joint-

project.org/upload/file/JointProjectGroup2012_Brochure_StressTests_VulnerabilityAssessment.p

df

NATURE 2011: Nature International weekly journal of science; Reactors, residents and rsik;

April, 21; 2011 http://www.nature.com/news/2011/110421/full/472400a.html

NEI 2000a: Nuclear Engineering International (NEI): Lungmen closure starts row 29 November

2000; http://www.neimagazine.com/news/newslungmen-closure-starts-row-721/

NEI 2007a: Nuclear Engineering International (NEI): Quake impact on reactor complex explored

2 August 2007; http://www.neimagazine.com/news/newsquake-impact-on-reactor-complex-explored-721/

NEI 2009a: Nuclear Engineering International (NEI): Seismic safety under scrutiny in Taiwan 29

May 2009; http://www.neimagazine.com/features/featureseismic-safety-under-scrutiny-in-taiwan/

NEI 2009b: Nuclear Engineering International (NEI): EPC contract signed for South Texas

ABWRs 26 February 2009; http://www.neimagazine.com/news/newsepc-contract-signed-for-south-

texas-abwrs/

NEI 2010c: Nuclear Engineering International (NEI): GE asks NRC to renew ABWR license, 13

December 2010; http://www.neimagazine.com/news/newsge-asks-nrc-to-renew-abwr-license/

NEI 2012a: Nuclear Engineering International (NEI): Parliament endorses Lithuanian nuclear

project 25 June 2012; http://www.neimagazine.com/news/newsparliament-endorses-lithuanian-nuclear-

project/

Page 61: 福島核災後龍門電廠(核四廠)壓力測試評估 Review of the post

61

NEI 2012c: Nuclear Engineering International (NEI): Kashiwazaki-Kariwa 1&7 stress test results

published, 24 January 2012; http://www.neimagazine.com/news/newskashiwazaki-kariwa-17-stress-test-

results-published/

NEI 2013a: Nuclear Engineering International (NEI): Fennovoima considers mid-sized VVER

reactor for Hanhikivi 8 April 2013 Toshiba's 1600 MW EU-ABWR

http://www.neimagazine.com/news/newsfennovioma-considers-mid-sized-vver-reactor-for-hanhikivi/

NEI 2013b: Nuclear Engineering International (NEI): Horizon and Hitachi-GE sign contract for

design work on Wylfa nuclear plant 16 May 2013; http://www.neimagazine.com/news/newshorizon-

and-hitachi-ge-sign-contract-for-design-work-on-wylfa-nuclear-plant/

NEI 2013c: Nuclear Engineering International (NEI): UK regulators gear up for ABWR review,

11 April 2013; http://www.neimagazine.com/news/newsuk-regulators-gear-up-for-abwr-review/

NRC 2012: Recommendations for enhancing reactor safety in the 21st century; the near-term task

force review of insights from the Fukushima Dai-Ichi accident; Dr. Charles Miller, Amy

Cubbage, Daniel Dorman, Jack Grobe, Gary Holahan, Nathan Sanfilippo; JULY 12, 2011;

http://pbadupws.nrc.gov/docs/ML1118/ML111861807.pdf

NUCNET 2013: The Communications Network for Nuclear Energy and Ionising Radiation:

Hitachi and Areva to install Filtered Venting Systems at Japan’s BWRs; David Dalton; June 5,

2013; www.nucnet.org/all-the-news/2013/06/05/hitachi-and-areva-to-install-filtered-venting-systems-at-

japan-s-bwrs

NW 16/05/13: The McGraw-Hill Companies: Nucleonics Week 54, May 16, 2013

NW 18/10/12: The McGraw-Hill Companies: Nucleonics Week 53, October 18, 2012

NW 27/06/13: The McGraw-Hill Companies: Nucleonics Week 54, June 27, 2013

OECD 2013: Independent Peer Review Report of the Stress Tests Performed on the Operating

Reactors in Chinese Taipei; 23 April 2013

RENNEBERG 2011: Renneberg, W.; Becker, O.; Neumann, W.: The European „Stress test” for

Nuclear Power Plants; Expertise on behalf of the Parliamentary Group of the Greens in the

European Parliament; Bonn, October 2011

SCHNEIDER 2013: The World Nuclear Industry Status Report 2012; Mycle Schneider, Antony

Froggatt, Paris, London, Kyoto, July 2013;

http://www.worldnuclearreport.org/IMG/pdf/20130716msc-worldnuclearreport2013-lr-v4.pdf

TAIPEITIMES 2013a: Taipei Times: Gongliao patience urged; Helen Ku; 02 August 2013;

http://www.taipeitimes.com/News/biz/archives/2013/08/02/2003568699

TAIPEITIMES 2013b: Taipei Times: Nuclear plant may win democracy; Jay Fang; 05 August

2013; http://www.taipeitimes.com/News/editorials/archives/2013/08/05/2003568945

TAIPEITIMES 2013c: Taipei Times: TaiPower vows Gongliao plant is safe; Lee I-chia; 05

August 2013; http://www.taipeitimes.com/News/taiwan/archives/2013/08/05/2003568971

TOSHIBA 2011: Toshiba Corporation: US-ABWR and EU-ABWR Design, Safety Technology,

Operability Features and their Current Deployment; 5 July 2011;

http://www.iaea.org/NuclearPower/Downloadable/Meetings/2011/2011-07-04-07-08-WS-

NPTD/4_JAPAN_ABWR_Toshiba_Ishibashi.pdf

TPC 2013: Taiwan Power Company (OPC): EU Stress Test for Lungmen NPP - Licensee Report

(Rev.1b); May 2013

WENISCH 2012a: Wenisch, A.; Becker, O. Lorenz, P.: Critical Review of the EU Stress Test

performed on Nuclear Power Plants; commissioned by Greenpeace, Wien, Hannover, May 2012

WNN 2009a: World Nuclear News (WNN): Earthquake-hit unit gets OK for full output, 02 June

2009; http://www.world-nuclear-news.org/IT-Earthquake_hit_unit_gets_OK_for_full_output-

0206094.html

WNN 2009b: World Nuclear News (WNN): Toshiba signs contract for South Texas ABWRs, 25

February 2009; http://www.world-nuclear-news.org/newsarticle.aspx?id=24725

WNN 2009c: World Nuclear News (WNN): Exelon opts for resurgent ABWR. 26 March 2009;

http://www.world-nuclear-news.org/C_Exelon_opts_for_ABWR_2603092.html

Page 62: 福島核災後龍門電廠(核四廠)壓力測試評估 Review of the post

62

WNN 2010a: World Nuclear News (WNN): Shaw to be exclusive EPC contractor for Toshiba

ABWR, 30 November 2010;

www.world-nuclear-news.org/C-Shaw_to_be_exclusive_EPC_contractor_for_Toshiba-ABWR-

3011108.html

WNN 2011a: World Nuclear News (WNN): New nuclear energy policy for Taiwan, 03

November 2011; http://www.world-nuclear-news.org/NP-New_nuclear_energy_policy_for_Taiwan-

0311117.html

WNN 2011c: World Nuclear News (WNN): Shaw receives compensation for Lungmen. 01

February 2011; http://www.world-nuclear-news.org/IT-Shaw_receives_compensation_for_Lungmen-

0102115.html

WNN 2011d: World Nuclear News (WNN): ABWR fit for aircraft impact, 02 November 2011;

http://www.world-nuclear-news.org/RS_ABWR_fit_for_aircraft_impact_021111a.html

WNN 2013a: World Nuclear News (WNN): Taiwan reactor offline after typhoon, 16 July 2013;

http://www.world-nuclear-news.org/RS_Taiwan_reactor_offline_after_typhoon_1607131.html

YAMAZAKI 2013: Defence-in-Depth Concept for the EU-ABWR; Hiroshi Yamazaki, Toshiba

International Limited; Steffen Fuchs, (Toshiba International Limited); Annual Meeting on

Nuclear Technology; Berlin; 14-16 May, 2013

Page 63: 福島核災後龍門電廠(核四廠)壓力測試評估 Review of the post

63

8 Abbreviations

ABWR Advanced Boiling Water Reactor

ACIWA AC-Independent Water Addition

AEC Atomic Energy Council

AFB Auxiliary Fuel Building

AMT Accident Management Team

AOO Anticipated Operational Occurrences’

BDB Beyond Design Basis

BDBA Beyond Design Basis Accident

CCF Common Cause Failure

CST Condensate Storage Tank

CWP Circulating Water Pump

DBA Design Basis Accident

DBE Design Basis Earthquake

DBF Design Basis Flood

DBT Design Basis Tsunami

DEC Design Extension Condition

DiD Defence in Depth

DPP Democratic People’s Party

ECCS Emergency Core Cooling System

EDG Emergency Diesel Generator

EDMG Extensive Damage Mitigation Guideline

ENSREG European Nuclear Safety Regulators Group

EOP Emergency Operating Procedure

EPIC Emergency Public Information Centre

EPR European Pressurised Reactor

EU European Union

FPCU Fuel Pool Cooling and Cleanup System

FSAR Final Safety Analysis Report

GDA Generic Design Assessment

GE General Electric Company.

GEH GE-Hitachi Nuclear Energy

HPC Health Physic Centre

I&C Information and Control

IAEA International Atomic Energy Agency

IC Isolation Condenser

IPCC Intergovernmental Panel on Climate Change

JNES Japan Nuclear Energy Safety Organization

KMT Kuomintang

LDF Lower Drywell Flooding

LMNPP Lungmen Nuclear Power Plant

LOOP Loss of Offsite Power

LY Legislative Yuan

MCR Main Control Room

MOEA Ministry of Economic Affairs

NAcP National Action Plan

NC non-condensable

NCO Niigata Chuetsu Offshore

NEA Nuclear Energy Agency

NPP Nuclear Power Plant

NPP4 Forth NPP = Lungmen NPP

NR National Report

Page 64: 福島核災後龍門電廠(核四廠)壓力測試評估 Review of the post

64

NRC Nuclear Regulatory Commission

NSC National Science Council

NTTF Near Term Task Force

OECD Organization for Economic Cooperation and Development

OSC Operation Support Centre

PAR Passive Autocatalytic Recombiners

PCCS Passive Containment Cooling System

PGA Peak Ground Acceleration

PMP Probable Maximum Precipitation

PRA Probabilistic Risk Assessment

QA Quality Assurance

RAP Reinforcement Action Plan

RBCW Reactor Building Cooling Water

RBSW Reactor Building Service Water

RCIC Reactor Core Isolation Cooling

RCS Reactor Coolant System

RHR Residual Heat Removal

RHWG Reactor Harmonization Working Group

RPV Reactor Pressure Vessel

SAM Severe Accident Management

SAMG Severe Accident Management Guideline

SBO Station Blackout

SFP Spent Fuel Pool

SGTS Standby Gas Treatment System

SRV Safety Relief Valve

SSC Structures, Systems and Component

STP South Texas Project

SWCB Soil and Water Conservation Bureau

SWIC Stone and Webster International Corporation

TAF Top of Active Fuel

TEPCO Tokyo Electric Power Company

TPC Taiwan Power Company

TSC Technical Support Centre

UHS Ultimate Heat Sink

URG Ultimate Response Guideline

US United States of America

US NRC US Nuclear Regulatory Commission

WENRA Western European Nuclear Regulators Association