national Water Supply and Drainage Board
The Project for Rehabilitation of Killinochchi Water Supply Scheme
Construction Management PlanJuly 2013
20137
NJS Consultants Co., Ltd.
TOKYO, JAPAN
TABLE OF CONTENTS /
Page
1. OUTLINE of the Project/ 1
1.1 Outline of the Project / 1
1.2 Location Map of the Project / 2
1.3 Water Treatment Plant Perspective / 3
1.4 Layout of Intake and Water Treatment Plant /4
1.5 Main Components / 5
2. Supervisory Services / 6 2.1 The Components of Supervise / 6 2.2 Scope of Supervisory Services / 62.3 Application Standards / 72.4 Order of Reference / 73. Emergency Communication Chart / 84 Progress Meeting / 95. Procedure for Approval / 106. Superintendence on Construction Works / 12 1. Progress Control / 122. Organization of Implementation / 123. Construction Management / 124. Temporary Work / 165. Quality Control / 176. Procurement / 177. Safety / 178. Environmental Management / 199. Completion Inspection / 2010. Commissioning / 207. Construction Schedule / 21( Annex-1 ) V-1 Detail of Quality Control / 22( Annex-2 ) V-2 Detail of Progress Control / 29( Annex 3 ) V-3 Photo / 331. OUTLINE OF THE PROJECT /
1.1 Outline of the Project /
PROJECT NAME
:The Project for Rehabilitation of Killinochchi Water Supply Scheme23
CLIENT
: Implementing Agency
National Water Supply and Drainage Board Democratic Socialist Republic of Sri Lanka
CONSULTANT
:NJS Consultants Co., Ltd.
(
CONTRACTOR
:Daiho Corporation(
PROJECT PERIOD
:
7 June 201331 July 2014
2013672014731
1.2 Location Map of the Project /
1.3 Water Treatment Plant Perspective /
1.4 Layout of Water Intake and WTP /
1.5 Major Components /
Item / Unit /
Qty /
Remarks /
1. Preparation /
Site Mobilization / Site Establishment / L.Sum
L.Sum1.00
1.00
2. Water Intake & Water Treatment Plant / New intake pit / Intake sump / Intake pump house / Raughing filter / Aerator / Slow sand filter / Washed sand filter / Storage pond / Administration building / Generator house / Guard house / Raw water transmission pipe / Yard piping / Landscaping / L.Sum
L.Sum
L.Sum
L.Sum
L.Sum
L.Sum
L.Sum
L.Sum
L.Sum
L.Sum
L.Sum
L.Sum
L.Sum
L.Sum1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00Concrete: 4m3 Concrete: 537 m3
Concrete: 19 m3
Concrete: 99 m3
Concrete: 33 m3
Concrete: 53 m3
Concrete: 3 m3
Concrete: 59 m3
3.Central College Water Tower / Construction of water tower / Pipe work, Manhole & Chamber / Landscaping / L.Sum
L.Sum
L.Sum1.00
1.00
1.00Concrete: 671 m3Concrete: 16 m3Concrete: 40 m3
4.Paranthan Water Tower / Construction of water tower /
Pipe work, Manhole & Chamber /
Landscaping / L.Sum
L.Sum
L.Sum1.00
1.00
1.00Concrete: 456 m3Concrete: 10 m3Concrete: 8 m3
5.Pipe Work / Pumping Main / Transmission Main / Distribution Pipe along A9 Road / A9 Distribution Pipe in Killinochchi Town / Distribution Pipe in Paranthan Area / km
km
km
km
km0.42
4.20
15.50
17.00
3.00
6.Mechanical and Electrical Works /
7. Procurement Works of The Equipment / House Connection Equipment / Laboratory Equipment / Operation & Maintenance Equipment / L.Sum
L.Sum
L.Sum1.00
1.00
1.00
8. Test Run and Handover /
2. THE SUPERVISORY SERVICES / 2.1 The Components of Supervise / Maintain schedule control / Maintain progress control by take an accurate measurement / ()
Maintain progress control by photo record / ()
Maintain quality control / 2.2 Scope of Supervisory Services / Based on Agreement between Ministry of Planning and Administrative Development, the Palestinian Interim Self-Government Authority and NJS [ Article3 .1 (3) ] Construction Stage
Article 3.1 (3)1) The consultant shall provide supervisory services for the Project to ensure that the works executed by the Contractor(s) under the Project are the compliance with the Contract(S) in coordination with the Client.
The supervisory services shall include the followings:
a) Inspection and approval of shop drawings and samples submitted by the Contractor.
b) Interpreting design drawings and specifications.
c) Providing a representative and engineer(s) as necessary during the construction stage of the Project.
d) Carrying out factory inspection and / or checking the factory inspection report if the equipment and materials for construction work
e) Examining the materials, workmanship, and measurement and quantity in the Project as prescribed in the design documents.
f) Settling disputes or differences relating to the execution and progress of the construction work that may arise between the Client and the Contractor.
g) Issuing instructions where necessary to prevent delays in construction work.
h) Preparing a recommendation for Amendment and Modification stipulated in the Article 14 hereof and in Article concerning Amendment and Modification in the Contract(s).
Article14i) Participating in discussions between the Client and the Contractor(s) and providing advisory services.
ClientContractor(s)2) The Consultant shall make necessary reports from time to time or according to the instructions of the Client in the execution and progress of the Project.
3) The Consultant shall issue necessary certificates for payments to the Contractor(s) and other certificates as required by the Client.
4) The Consultant shall have the custody of the performance security and the advance payment security to be issued in connection with the Contract(s).
2.3 Application Standards / JIS:Japanese Industrial Standards
ISO:International Standardization Organization
JEC:Standard of the Japan Electrical Committee
JEM:The Standard of Japan Electrical Manufacturers' Association
JCMS:Japan Cable Maker's Standards
JEAC:Japan Electrical Association Code
JWWA:Japan Water Works Association
NEMA:National Electrical Manufacturers Association, USA
IEC:International Electro technical Commission
AWWA:American Water Works Association
AASHO:American Association of State Highway Officials
ASCE
: American Society of Civil Engineers
ASME:American Society for Mechanical Engineers
ASTM:American Society for Testing and Materials
BS
British Standard
2.4 Order of Preference / (1)Condition of Contract (Between PWA and DAI NIPPON CONSTRUCTION)
(2)Technical specification
(3) Drawings
(4) Confirmation items at bidding stage (M/M)
3. Emergency Communication Chart /
4. PROGRESS MEETING / SHolding day / Attendant
/Sri Lankan AgencyConsultantContractor
NWSDB
Other AuthoritiesResident EngineerChief EngineerChief ConsultantProject Manager
Chief EngineerSub-Contractor
Kick-Off Meeting
Steering Committee MeetingAs needed()()
Monthly Progress MeetingEvery month()()()
& Weekly Coordination & Progress MeetingEvery week()()()()
Extra Meeting
As needed()()()()()
() (As per necessary)
5. PROCEDURE FOR APPROVAL /
1) Approval by Consultant on SiteAcknowledger: Mr. Keisei Maekawa (Residence Engineer)
2) Approval by Consultant in TokyoAcknowledger: Mr. Tadao Funamoto (Civil Martials and Items of Procurement Work)Mr. Masatugi Hatano (Mechanical Equipment and Installation)
Mr. Akira Miura (Electrical Equipment and Installation)
3) Approval by Sri Lankan AuthoritiesAcknowledger: Concerned Sri Lankan Authorities such as RDA
6. SUPERINTENDENCE ON CONSTRUCTION WORKS
JICAItems
Description
Management
.Progress control
1.Main progress meeting (Kick off, Steering meeting)As needed
2.Monthly meeting (NWSDB, NJS, DAIHO )Once a Monthly
1/
3.Weekly meeting (NWSDB, NJS, DAIHO )Once a Weekly
1/
4.Each construction works and specialized meeting
,As needed
5.Monthly report (Execution and progress)NJS NWSDBNJSJICA(Sri Lanka, Tokyo)
DAIHO Monthly report (Execution and progress) :Once Monthly
1/
.Organization
of implementation
1.Project organization chart
( : )Construction plan
2.Site management chart
Construction plan
3.Site office location
Construction plan
.Construction
management
1.Before construction
1)Construction plan
1 Basic construction plan
Before construction
Detail construction plan
()Before construction
2) Present conditions investigation of the construction area
Confirmation of position
()Confirmation of bench mark
Confirmation of trial boring
()Progress control
2.Civil works
1)Excavation, Cutting
, Part-2( 1.17)
1 Slope gradient, Sheathing
, Construction plan
Protection of existing facility
Construction plan
Excavation finishing level
Progress control
Method of excavation and transportation
, Construction plan
Drainage plan
Construction plan
2)Hauling and disposal
Construction plan
3)Banking and backfilling
,
1 Compaction method
Construction plan
Compaction(material)
(, , )Quality control
Progress control
,
3.Foundation work
1)plate loading test
() Part-2 ( 1.28) Quality control
2)Soil improvement (If it is necessary)
()Construction plan
Quality control
Progress control
,
3)Cobble stone
Construction plan
Quality control
Progress control
,
4)Lean concrete
Quality control
Progress control
,
4.Concrete works
Part-2 ( 1.30)
1)Scaffolding works
1 Scaffolding plan
()Construction plan
Check
Visual observation
2)Supporting works
1 Supporting plan
()Construction plan
Raising clearance
Construction plan
Support Check
Visual observation
Removal of supporting
Construction plan
3)Form works
1 Shuttering material
Construction plan
Install method
Construction plan
Removal of shuttering Construction plan
Verification of shuttering
Progress control
4)Rebar works
1 Verification of Material
( ,)
( )Quality control
Manufacture certificate
,Quality control
Tensile test at site
Quality control
Stock yard and curing
,Construction plan
Bending schedule
Construction plan
Inspection of fabrication
Progress control
5)Concrete works
Part-2 ( 1.07)
1 Plant erection
Quality control
Material
Quality control
Trial mix
Quality control
Slump, air content, temperature
,,Quality control
Compressive strength
(X-R)Quality control
Casting and transportation
() Construction plan
Compaction
Construction plan
Construction joint
Construction plan
Crazing induction seam
Construction plan
Surface finishing
Construction plan
Curing
Construction plan
Inspection of dimension
Progress control
6)Water retaining
Part-2 ( 1.33)()Construction plan
Quality control
5.Piping works
1) Verification of Material (request and site inspection)
( ,) Part-2 (1.20)Procurement plan
2)Stock and transportation
,,Construction plan
3)Excavation, backfilling, compaction (sand, soil)
,,(,),
1 Construction Method2 Construction plan
Excavation, backfilling, compaction(material, compaction)
,,(,,)Quality control
Progress control
,
4)Piping
1 Construction method
Construction plan
Piping, thrust block, concrete encasement, Box
,,,BOXProgress control
5)Field pressure test /
Part-2 (1.26 )
1 Test method
Construction plan
Flushing & Field hydrostatic test
Quality control
Field leakage test
Quality control
6)Disinfection
Quality control
6.Road Restoration
1)Construction method
Construction plan
2)Compaction, Proof rolling
,Quality control
3)Control of pavement( Road Departments Spec)
(Roads Department) Quality control
Progress control
,
7.Walling work
1)Verification of Material (request and site inspection)
(,) Procurement plan
2) Execution of work
Construction plan
3)Progress and Quality control
Quality control
Progress control
,
8.Stone Walling work
1)Verification of Material (request and site inspection)
(,) )Procurement plan
2)Construction method
Construction plan
3)Progress and Quality control
)Quality control
Progress control
,
9.Pre-cast Concrete work
1)Verification of Material (request and site inspection)
(,) Procurement plan
2)Construction method
Construction plan
3)Progress and Quality control
Quality control
Progress control
,
10.Roofing work
1)Verification of Material (request and site inspection)
(,) Procurement plan
2)Construction method
Construction plan
3)Progress and Quality control
Quality control
Progress control
,
11. Waterproofing work
Part-2 ( 1.33)
1)Verification of Material (request and site inspection)
(,) Procurement plan
2)Construction method
Construction plan
3)Progress and Quality control
Quality control
Progress control
,
12.Carpentry work
1)Verification of Material (request and site inspection)
(,) Procurement plan
2)Construction method
Construction plan
3)Progress and Quality control
Quality control
Progress control
,
13.Other Architectural work
1)Verification of Material (request and site inspection)
(,) Procurement plan
2)Construction method Construction plan
3)Progress and Quality control
Quality control
Progress control
,
14.Mechanical works
1)Verification of Material (request and site inspection)
(,) Part-3 Mechanical worksProcurement plan
2)Construction method
Part-3 Mechanical worksConstruction plan
3)Progress and Quality control
Part-3 Mechanical worksQuality control
Progress control
,
4)Witnessed shop testing
Quality control
15.Electrical works
1)Verification of Material (request and site inspection)
(,) Part-4 Electrical worksProcurement plan
2)Construction method
Part-4 Electrical worksConstruction plan
Progress and Quality control
Part-4 Electrical worksQuality control
Progress control
,
Witnessed shop testing
Quality control
4. Temporary works
1.Temporary facilities and utilities works
(Temporary road, Electric/Water/drainage facility etc)
(,,,)Construction plan
5. Quality Control
1. Quality control
Annex-1
2.Progress control
Annex-2
3.Photo control
Annex-3
6. Procurement
plan
1. Procurement schedule(w / Master list)As needed
2. Local Procurement
1) Approval of procurement materials (w/Shop test)
Cement/Rebar/Filter Sand/Brick/Water Proofing Material / Pipes and associated materials//Paint/Fence & Gate/Conduit Pipe/Electrical wire/Electrical fixture/Fire alarm/others
,
Inspection report
()As needed
2) Site inspection of procurement materials
Cement/Rebar/Filter Sand/Brick/Water Proofing Material / Pipes and associated materials//Paint/Fence & Gate/Conduit Pipe/Electrical wire/Electrical fixture/Fire alarm/others
,Inspection
()As needed
3. Import Procurement of M&E
/
1) Approval of procurement materials (w/Shop test)
Inspection report
()As needed
2) Site inspection of procurement materialsInspection
()As needed
7. Safety
management
Safety
management
1.General / Part-2 ( 1.24)
1)Safety control organization *bulletin board*
Safety Plan
2)Emergency communication chart* bulletin board*
Safety Plan
3)Land Mine/UXOs education
Safety Plan
4)Carry out safety meeting
Safety Plan
5)Conduct safety patrol and correction of indication matter
Every Tuesday
6)Open safety education
Every Wednesday
2.Importance of safety work management
1) Dangerous materials management
Safety Plan
Safety Plan
Safety Plan
Safety Plan
Safety Plan
Safety Plan
Safety Plan
Safety Plan
Safety Plan
1 Election of dangerous materials handling person
The establishment of dangerous materials safekeeping place
Indication of a fire strict prohibition place
2) The establishment of fire extinguishing facility
3) Road safety measures
1 The establishment of a construction signboard, barricade
,
An arrangement of a member of instruction
Closed to the Public measures of the third person
Traffic security of a walker, public vehicle
,
Safety measures of leaving part at night
4) Construction machine
1 Check for opening ago
Driving strict observance of a qualification person
Check of a wire
Check for device prevention of roll up
5)Check for Scaffolding and shuttering
,
6)Put on safety belt at up place
7)Check of sheathing
8 )Work cancellation in the rain
9) Check of electric wiring, earth
,,
3.Workers clothes
1)Put on helmets
Safety Plan
2.Check of working clothes, work shoes, gloves
,, Safety Plan
4.Safety measure
1) Mutually safe confirmation by a signal
Safety Plan
2) Arrangement of a member of traffic guide
5.Cleanliness and arrangements
,
1) Cleaning of cabin, lavatory, rest stations
,, Safety Plan
2) Safekeeping of materials and equipment (keep in order)
()
3) Reasonable disposal of disuse materials
6.Sanitary condition management
1) Labor prohibition of physical condition defectiveness person
Safety Plan
2) Periodic inspection of drinking water
3)Enforcement of gargle and wash a hand
,
4) Establishment of a first-aid kit
Safety Plan
7.Antitheft
1) Arrangement of security guards
Safety Plan
2) Lock of office, warehouses
,
8. Environment
management
1. underground utilities / Construction plan
Damage of underground utilities /
NJS Site Office DAIHO Site Office NWSDB /Vavuniya, Killinochchi
2. Environmental protection / Construction plan
Environmental protection / ()
NJS Site Office DAIHO Site Office
NWSDB /Vavuniya, Killinochchi
3. Vehicle for construction
Construction plan
1 Setting of a speed limit (full-size vehicle, normal car)
(,)
Disposal soil scattering prevention in transportation
4. Noise Control
Construction plan
5. Vibration Control
Construction plan
6. Waste water drainage
Construction plan
7. Disposal of construction waste ()Jericho Construction plan
8. Disposal area for surplus soil
JerichoConstruction plan
9. Publicity relation to local inhabitants
Construction plan
1 Establishment for construction guidance
Prior construction notice
9. Completion
inspection
PWA, Part-1 General Requirements
JICACertificate
10. Commissioning
PWA Part-1 General Requirements Certificate
7. Construction Schedule /
Annex-1 V-1 Detail of Quality Control /
An equal or higher quality than the specifications will be accepted.
Items
Description
Test Method
Allowance
Specification
Frequency
Document
1-1. Before construction /
1-2. Civil works /
Banking , backfilling
,Material (soil)
,(Good quality Soil)
()Conformed
Part-2
(1.18)Suitable
Visual observation
()As needed
Laboratory test
()JIS A 1210Actual measurement
Part-2
(1.18)More than once
/1Inspection result
As needed
Field density
()JIS A 1214, 1203>85%Part-2
(1.18)Every 500m
500m/1Inspection report
()Required
1-3. Foundation works /
Plate bearing test
JIS A 1521
Required on Spec.
Part-2
( 1.25 )Suitable
Inspection report
()Required
Crusher Run
(C-40)
Conformed
Suitable
Visual observation
()As needed
Lean concrete
BS1881>18N/mm2Part-2
( 1.07)Every 100batch/1time
100/1Inspection report
()As needed
1-4. Concrete works /
Reinforcement
Inspection report
BS 4449Conformed
Part-2
(1.06 )Every new material
Inspection report
As needed
Tensile strength test
BS 4449Conformed
Every new material
(3*6kinds)Inspection report
As needed
Plant facility
Batching units
BS 5328Within tolerance
More than once
/1Inspection report
As needed
Mixer
BS 5328Conformed
More than once
/1Inspection report
As needed
Storage facility
Spec
()Conformed
More than once
/1Visual observation
()As needed
Concrete material
Cement
BS12
manufacture certification
Conformed
Part-2
(1.02)More than once
/1manufacture certification
As needed
Mixing water quality
BS3148Conformed
Part-2
( 1.04 )More than once
/1Inspection report
As needed
Fine aggregate / Part-2 ( 1.03)
Specific Gravity
BS 882>2.5g/cm3More than once
/1Inspection report
As needed
Water Absorption Value
BS882-50
Spec JSCE
Reference 1-13Every 50m
50m/Inspection
()
Required
Earth cover
>Design section
Spreading soil depth
()Design Dimension
>Suitable
River crossing
>Design Dimension
>Suitable
Each box
>Design Dimension
>Suitable
2-6.Road pavement /
Gravel Pavement
Gravel Laying , Compaction
Length
Actual Measurement
Inspection report
()Required
Width
>7m Main road to WTP
>5m WTP to 3KmEach 500m
500m
Thickness
>20cm
Asphalt Pavement
Cut/Filled up Ground
Elevation
50mmSpec JSCE
Refer 1-20Each 40m
40mInspection report
()Required
Earth cover
>Design section
Width
>-50mm
Base
Thickness
>-30mmSpec JSCE
Refer 1-20Each80m
80m
width
>-50mm
Asphalt Pavement
Thickness
>-20mmSpec JSCE
Refer1-21Each80m
80m
Width
>--50mm
2-7.Walling works /
Progress
Specification
Suitable
Suitable
Inspection
()Required
2-8.Stone Walling /
Progress
Specification
Suitable
Suitable
Inspection
()Required
2-9.Precast Concrete works /
Progress
Specification
Suitable
Part-2 ( 1.31)Suitable
Inspection
()Required
2-10.Roofing works /
Progress
Specification
Suitable
Part-2 ( 1.32)Suitable
Inspection
()Required
2-11.Waterproofing works. /
Progress
Specification
Suitable
Part-2 ( 1.33)Suitable
Inspection
()Required
2-12.Carpentry works /
Progress
Specification
Suitable
Part-2 ( 1.34)Suitable
Inspection
()Required
2-13.Other architectural works /
Progress
Specification
Suitable
Part-2 ( 1.43)Suitable
Inspection
()Required
2-14.Mechanical works /
Progress
Specification
Suitable
Part-3
( Mechanical )Suitable
Inspection
()Required
2-15.Electrical works /
Progress
Specification
Suitable
Part-4
( Electrical )Suitable
Inspection
()Required
Annex-3 V-3 Photo Control /
Items
Description / Remarks /
Description
Frequency
Attend
1.Progress control /
1.Progress meeting
holding situation
Suitable
As neededDaily management
2.Spot inspection
Inspection situation
2.Organization of implementation /
Organization chart
Notice situation
Suitable
As needed
Daily management
3.Construction management /
1.Before construction /
1) Prior to start work
Whole view
Every 0.5km
EtcAs needed
required
2) Surveying
Suitable
As needed
Daily management
3)Trial excavation
2.Civil works /
1)Excavation, Cutting
,Suitable
As needed
Daily management
2)Banking and backfilling
,
3.Foundation works /
1)Plate loading test
Suitable
As needed
Daily management
2)Soil improvement
3)Coble stone
4)Lean concrete
4.Concrete works /
1)Scaffolding works
Suitable
As needed
Daily management
2)Supporting works
3)Form works
4)Reinforcement works
5)Concrete works
5.Piping works /
1)Verification of material
Suitable
As needed
Daily management
2)Stock and transportation
,,
3)Excavate, backfill, compact
,,
4)piping
5)Field pressure test
6.Road pavement./.
1)Road pavement
Suitable
As needed
Daily management
2)Control of pavement
7. Walling works
Verification of material
Construction
Suitable
As needed
Daily management
8.Stoneblock walling
9.Precast Concrete work
10.Roofing work
11.Waterproofing work
12.Carpentry work
13.Other architectural work
14.Machanical works /
Verification of material
Suitable
As needed
Daily management
Construction
Operation
15.Electrical works /
Factory inspection
Suitable
As needed
Daily management
Verification of material
Construction & inspection
Performance test
Commissioning test
4.Temporary works /
1.Facilities
.Temporary road etc
Suitable
As needed
Daily management
2..Housing
Site office etc
Suitable
As needed
Daily management
5. Quality Control /
1.Quality control
Management result situation
Mention it in -1 ( Annex-1)
-1 (Annex-1)
2.Progress control
Management result situation
Mention it in -2 (Annex-2)
-2 (Annex-2)
6. / Procurement plan
1. Factory inspection
On time
As needed
required
2 Site inspection
.Suitable
As needed
Daily management
7.
1.General /
Safety meeting
Suitable
As needed
Daily management
Safety patrol
2.Safety work management /
Dangerous material manage
Suitable
As needed
Daily management
Road safety measures
High place work
3.Workers clothes /
Put on helmets
Suitable
As needed
Daily management
4.Safety measure /
Member of instruction etc
Suitable
As needed
Daily management
5.cleanliness and arrangements /
Keep in order
Suitable
As needed
Daily management
6.Sanitary condition management /
First-aid kit
Suitable
As needed
Daily management
7.Antitheft /
Arrangement of guard
Suitable
As needed
Daily management
8Environment management /
1.Disposal of waste / ,
Use situation
Suitable
As needed
Daily management
2.Publicity work /
Activity situation
Suitable
As needed
Daily management
9.
Completion inspection /
inspection situation
Suitable
As needed
Daily management
Completion
Whole view
Every 0.5kmAs needed
required