4.december 2011 mpr

Upload: henrique-xavi-inesta

Post on 04-Apr-2018

220 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/31/2019 4.December 2011 MPR

    1/39

    Third Party Q

    National Cyclone Ri(NC

    Revenue (D

    Government of

    National Cyclone Ri(NC

    Revenue (D

    Government of

    i

    ality Audit(TPQA)

    k Mitigation ProjectMP)

    ) Department

    Andhra Pradesh

    kMitigation ProjectMP)

    ) Department

    Andhra Pradesh

    n Joint

    enture

    with

  • 7/31/2019 4.December 2011 MPR

    2/39

    MONTHLY REPORT

    1 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    INDEX

    1.0 Project Background 2

    2.0 Third Party Quality Audit Consultant 3

    3.0 Status of TPQA Visits 4

    4.0 Progress of NCRMP works 5

    5.0 District wise status of tests conducted by TPQA 27

    6.0 Details of Audit Reports Submitted during this Month 28

    7.0 Observations of Submitted Reports 30

  • 7/31/2019 4.December 2011 MPR

    3/39

    MONTHLY REPORT

    2 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    1.0 Project Background

    Andhra Pradesh (AP) state has one of the longest coastal belts in India. Out of 67,362 Km of road network in the state, the

    nine coastal districts cover 26,000 km of road length. Every year during the period of April-May and September-December,cyclonic situations set in to the Bay of Bengal. With the recent changes in climatic conditions, the catastrophic events are

    increasing resulting in very devastating cyclones like Laila, Jal etc where the loss is enormous. In the 97 years ranging

    from 1892 to 1989, there were as many as 67 cyclones within the State.

    It is essential to provide safe residential accommodation to the vulnerable population during any eventuality or disaster due

    to natural calamities such as cyclones and associated tidal waves and storm surges. The project is formulated based on

    experiences of Government of Andhra Pradesh in mitigating such disasters during the past and also keeping in view the

    existing facilities available in the project area in Andhra Pradesh.

    The Government of India has applied for a credit of US$ 255 Million equivalent from the International Development

    Association (IDA) toward the cost of National Cyclone Risk Mitigation Project (NCRMP), and it intends to apply theproceeds to payments for goods, works, related services and consulting services under this Project.

    National Cyclone Risk Mitigation Project (NCRMP) Project Implementation Unit (PIU), Andhra Pradesh, headquartered at

    Hyderabad has invited the consultants to submit proposals for providing the consultancy services for Third Party Quality

    Audit for 9 coastal districts namely Srikakulam, Vijayanagaram, Visakhapatnam, East Godavari, West Godavari, Krishna,

    Guntur, Prakasam and Nellore. The project Construction of Multipurpose Cyclone Shelters, Roads to Cyclone

    Shelters, and Roads to habitations and Roads & Bridges under NCRMP is funded by International Development

    Association and received through Government of India. This consultancy is envisaged to audit the quality of works being

    implemented by various line departments working under PIU. The number of works under progress / for which

    agreements are concluded in each district is shown in the table below.

    District

    No. of works(Under Concluded Agreements) No. of works under ProgressNo. ofworks

    notstarted

    RHB RCS MPCS BridgesRoads(R&B)

    Total RHB RCS MPCS BridgesRoads(R&B)

    Srikakulam 6 8 2 4 1 21 6 4 2 3 1 5

    Vizianagaram - - - 2 1 3 - - - 2 1 0

    Visakhapatnam 8 6 7 - - 21 8 5 6 - - 2

    East Godavari 2 8 3 - - 13 2 6 - - - 5

    West Godavari 10 - - - - 10 8 - - - - 2

    Krishna 5 3 - - - 8 5 2 - - - 1

    Guntur 3 12 - 2 - 17 2 3 - 2 - 10

    Prakasham 14 7 2 1 - 24 13 4 2 1 - 4

    Nellore 16 8 - - - 24 16 5 - - 3

  • 7/31/2019 4.December 2011 MPR

    4/39

    MONTHLY REPORT

    3 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    2.0 Third Party Quality Audit Consultant.

    To provide Consulting Services of Third Party Quality Auditor for Construction of Multipurpose Cyclone Shelters, Roads to

    Cyclone Shelters, Roads to habitations, and Roads and Bridges under NCRMP in 9 coastal districts The Commissioner for

    Disaster Management & Project Director, Project Implementation Unit (PIU) NCRMP has selected Egis International in JV

    with Egis India Consulting Engineers (I) Pvt. Ltd. On 31st

    May2011, the Contract for Consultancy Service was signed

    between The Commissioner for Disaster Management & Project Director, Project Implementation Unit (PIU) NCRMP and

    the Egis International in JV with Egis India Consulting Engineers (I) Pvt. Ltd.

  • 7/31/2019 4.December 2011 MPR

    5/39

    MONTHLY REPORT

    4 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    3.0 Status of TPQA Visits:

    The following table shows the details of TPQA visits to sites in respective districts.

    DistrictTotal Number of Visits

    Up to Nov.'2011 In Dec.'2011 Up to Dec.'2011

    Srikakulam 101 18 119

    Vizianagaram 49 3 52

    Vishakhapatnam 80 26 106

    East Godavari 103 40 143

    West Godavari 110 32 142

    Krishna 76 27 103

    Guntur 92 20 112

    Prakasam 123 27 150

    Nellore 109 14 123

    No. of Visits by TPQA

  • 7/31/2019 4.December 2011 MPR

    6/39

    MONTHLY REPORT

    5 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    4.0 Progress of NCRMP works:

    The district wise progress of works is shown below. The works in the West Godavari are not started and the works in

    Krishna District has just started. At many places the first milestone is completed but works are not started. The line

    departments are to analyze the reasons for the slow progress and if necessary penalty for the slow progress as per theagreement conditions should be imposed.

    Third Party Quality Audit by Egis India consulting services

    Summary of Activities

    S.No. District

    Agreements for PackagesCommunicated

    Status of works

    PR R&B Progress Not Started

    1 Srikakulam 6 5 16 5

    2 Vizianagaram - 3 3 0

    3 Visakhapatnam 13 0 19 2

    4 East Godavari 7 0 8 5

    5 West Godavari 3 0 8 2

    6 Krishna 4 0 7 1

    7 Guntur 6 2 7 10

    8 Prakasham 12 1 20 4

    9 Nellore 16 0 21 3

    Total 67 11 109 32

    Total Packages for which Agreements are received 78

    Total Number of works in the above packages 141

  • 7/31/2019 4.December 2011 MPR

    7/39

    MONTHLY REPORT

    6 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    TPQA Status Report for NCRMP Works To the end of December 31-12-2011

    S.No. District

    Packages /Works

    entrustedStatus of Works No. of

    Visitsof

    TPQA

    TotalNo.

    of QCtestsdone

    NCRs

    QCReportsIssued

    Environmentaland Social

    Reports IssuedIssued closed PendingPR R&B Started

    Not

    Started

    1 Srikakulam 06_16 5_5 16 5 119 227 7 3 4 10 7

    2 Vizianagaram - 3_3 3 0 52 190 - - - 6 2

    3 Visakhapatnam 13_21 - 19 2 106 417 7 5 2 9 12

    4 East Godavari 07_13 - 8 5 143 145 4 4 - 7 3

    5 West Godavari 03_10 - 8 2 142 29 - - - 2 10

    6 Krishna 04_08 - 7 1 103 8 2 1 1 - 5

    7 Guntur 06_15 2_2 7 10 112 230 6 3 3 6 3

    8 Prakasham 12_23 1_1 21 3 150 402 7 6 1 18 13

    9 Nellore 16_24 - 21 3 123 277 6 2 4 11 8

    Total 67_130 11_11 110 31 1050 1925 39 24 15 69 63

  • 7/31/2019 4.December 2011 MPR

    8/39

    MONTHLY REPORT

    7 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Status of works in Srikakulam District up to 31.12.2011

    Category Packages allotted under Phase - 1Names of works undereach package

    Agreement No. / Date DHS DFCProgress up to31.12.2011

    RHB

    NCRMP/B-W/AP/RHB/PRED/01/Santhabommali/003

    Road from DPN R&Broad to Uddandapalem

    /2010-11, Dt.30.04.2011

    30.04.11 30.04.12WBM GR-II,GR-III &

    Shoulders

    Road from K. UmiladaJunction to Koduru (LinkRoad)

    /2010-11, Dt.30.04.2011

    30.04.11 30.04.12 WBM GR-II,GR-III &Shoulders

    Road from Borubhadra,Malagam to Kollipadu viaSeepuram, Gantapeta

    /2010-11, Dt.30.04.2011

    30.04.11 30.04.12WBM GR-II,GR-III &

    Shoulders

    NCRMP/B-W/AP/RHB/PRED/01/Polaki/006

    Road from R&B roadMobagam toDuubakavanipeta viaGajapathinagaram

    /2010-11, Dt.30.04.2011

    30.04.11 30.04.12

    First Milestone i.eEarthwork & Cd

    works &GSB

    Road fromTalasamudram to DolaRegulator

    /2010-11, Dt.30.04.2011

    30.04.11 30.04.12

    First Milestone i.eEarthwork & Cd

    works &GSB

    NCRMP/B-W/AP/RHB/PRED/01/Polaki/005

    Road from R&B roadEdulavalasa - Killam toJonnam viaTalasamudram

    /2011-12, Dt.30.04.2011

    30.04.11 31.01.12

    First Milestone i.eEarthwork & Cd

    works &GSB

    Bridges

    NCRMP/B-W/ AP/Br/R&B/01/Patnavanipeta/001

    Construction of bridge atKm 11/6-8 of NH-5 toPatnavanipetaConnectingSundarapalem

    46/2011, Dt.17.12.2010

    17.12.10 17.06.12

    First Milestone i.eFoundation upto well

    capping

    NCRMP/B-W/AP/Br/R&B/01/ Surampeta/003

    Construction of MinorBridge at Km 12/2-4 ofNH-5 to SurampetaRoad via Naruva,Mentada

    45/2010-2011,Dt17.12.2010

    17.12.10 17.03.12

    Second Milestone i.eCompletion up to

    below the deck slab.

  • 7/31/2019 4.December 2011 MPR

    9/39

    MONTHLY REPORT

    8 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    NCRMP/B-W/AP/Br/R&B/01/Bendigadda/004

    Construction of Highlevel bridge acrossBendigadda at KM 4/10of Pundi-Parlakimidi roadin Srikakulam Dt, A.P.

    1/2010,Dt.11.11.2010 11.11.10 11.05.12

    First Milestone i.eFoundation upto well

    caping

    Roads NCRMP/B-W/AP/RD/R&B/01/Nowpada/006)Improvements Naupada-Venkatapuram road from0/0to15/0km

    43/2010-11,17.12.2010 17.12.10 17.03.12

    Second mile stonei.e.WMM,Shoulders

    RCS

    NCRMP/B-W/AP/RCS/PRED/01/V.Kotturui/002

    Road from NP road toURK Puram

    G.O.Rt.No.451, Dt.06.04.2011

    06.04.11 29.09.12 E/W,pipeculverts,GSB,R/W

    Road from Deppuru,Bahadapalli road toOnkuluru to CycloneShelter

    G.O.Rt.No.451, Dt.06.04.2011

    06.04.11 29.09.12E/W,pipe

    culverts,GSB,R/W

    Road from R & B Roadto Devunthalada

    G.O.Rt.No.451, Dt.06.04.2011

    06.04.11 29.09.12E/W,pipe

    culverts,GSB,R/W

    Road from Pollada toKomarthalada toCyclone Shelter

    G.O.Rt.No.451, Dt.06.04.2011

    06.04.11 29.09.12E/W,pipe

    culverts,GSB,R/W

    NCRMP/B-W/AP/RCS/PRED/01/Etcherla/005

    Road from Koyyam R &B Road toMoosavanipeta

    G.O.Rt.No.451, Dt.06.04.2011

    30.04.11 07.05.12E/W, pipe culverts,

    GSB.

    Road from Mentada toDovupeta

    G.O.Rt.No.451, Dt.06.04.2011

    30.04.11 07.05.12E/W, pipe culverts,

    GSB.

    Road from Kotcherelaroad to Kollibhemavaram& Cyclone Shelter

    G.O.Rt.No.451, Dt.06.04.2011

    30.04.11 07.05.12E/W, pipe culverts,

    GSB.

    Road from Kotcherlaroad toPathesundrapalem

    G.O.Rt.No.451, Dt.06.04.2011

    30.04.11 07.05.12E/W, pipe culverts,

    GSB.

  • 7/31/2019 4.December 2011 MPR

    10/39

    MONTHLY REPORT

    9 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    MPCS NCRMP/B_W/AP/MPCS/PRED/01/Santhabommali/005

    Construction of Cycloneshelter at Kollipadu

    G.o rt No 451dt 06.04.2010

    07.01.2013Completion ofGround floorPlinth level

    PCC Completed

    Construction of CycloneShelter at Runku

    G.o rt No 451dt 06.04.2010

    07.01.2013Completion ofGround floorPlinth level

    Earthwork is inprogress

    Status of works in Vizianagaram District up to 31.12.2011

    CategoryPackages allottedunder Phase - 1

    Names of works under eachpackage

    Agreement No./ Date DHS DFCProgress up to

    31.12.2011

    Bridges

    NCRMP/ B-W/ AP/Br/ R&B/ 02/

    Puligadda/ 007

    Construction of Minor Bridge atKm. 7/2 near Puligadda of Konada Ramatheertham R&B Road toKonathalapalem via Yerukonda,Pasupam, Kollayavalasa (Z.P.

    Road)

    31/2010-201 Dt.1.12.2010

    01.12.10 31.05.1250.68% of work

    completed

    NCRMP/ B-W/ AP/

    Br/ R&B/ 02/Chakaligadda / 008

    Construction of Minor Bridge atKm 15/2 near Chakaligedda of

    Konada Ramatheertham R&B roadto Konatalapalem (via) Yerukonda,

    Pasupam, Kollayavalasa (ZPRoad)

    34/2010-2011 Dt.8.12.2010 08.12.10 07.06.12

    77.19% of workcompleted

    Road (R&B)NCRMP/B-

    W/AP/RD/R&B/ 02/Konada/009

    Improvements to Road fromKonada Ramatheertham (R&B)Road to Konathalapalem (Via)

    Pasupam, Yerukonda,Kollayavalasa from Km 12/0 to

    16/5 (Km 0/0 to 4/0 i.e. up to NH-5crossing)

    33/2010-201 Dt.8.12.2010

    08.12.10 07.03.1295% of workcompleted

  • 7/31/2019 4.December 2011 MPR

    11/39

    MONTHLY REPORT

    10 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Status of works in Visakhapatnam District up to 31.12.2011

    Category Packages allotted under Phase - 1Names of works

    under eachpackage

    AgreementNo. / Date

    DHS DFC Progress up to 31.12.2011

    RHB

    NCRMP/B-W/AP/RHB/PRED/03/Nakkapalli/001

    Road from Vempadu toPatimeeda

    /2010-11, Dt.11.01.2011

    11.01.11 11.01.12

    Third Milestone i.e Roadfurniture

    is in progress

    Milestone is completed

    Road from R&B road toMulaparra up to Beach

    end

    /2010-11, Dt.11.01.2011

    11.01.11 27.10.11

    For Second Milestone i.eWBM Gr-III is completed

    Third Milestone i.e Shouldersand Road furniture

    are in progress

    NCRMP/B-W/AP/RHB/PRED/03/Anandapuram/003

    Road from R&B B.PKallalu to

    Matchvanipalem

    /2010-11, Dt.10.03.2011

    10.03.11 09.12.11

    Third Milestone i.e C.C road& Road furniture

    is in progress

    NCRMP/B-W/AP/RHB/PRED/03/Paravada/004

    Road from R & B roadto Pothu Rajannapalem

    /2010-11, Dt.28.03.2011

    28.03.11 27.12.11

    Third Milestone i.e Roadfurniture

    is in progress

    Road from R & B roadto Jalaripeta

    /2010-11, Dt.28.03.2011

    28.03.22 28.12.11

    Third Milestone i.e Shouldersand Road furniture

    are in progress

    NCRMP/B-W/AP/RHB/PRED/03/Rambilli/006Road from R & B road

    to Venkayyapalem/2010-11, Dt.11.01.2011

    11.01.11 11.10.11Third Milestone i.e Road

    furnitureis in progress

    Milestone is completed

    NCRMP/B-W/AP/RHB/PRED/03/Atchutapuram/007

    Road from R&B road toAva- Somavaram

    /2011-12, Dt.27.04.2011

    27.04.11 26.01.12

    For Second Milestone i.eWBM Gr-III is completed

    Third Milestone i.e Shouldersand Road furniture

    are in progress

    Road from R&B Roadto Avarajam

    /2011-12, Dt.27.04.2011

    27.04.11 26.01.12Third Milestone i.e C.C road

    & Road furniture

  • 7/31/2019 4.December 2011 MPR

    12/39

    MONTHLY REPORT

    11 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    is in progress

    Status of works in Visakhapatnam District up to 31.12.2011

    CategoryPackages allotted under

    Phase - 1Names of works under each

    packageAgreement No. /

    DateDHS DFC

    Progress upto

    31.12.2011

    RCS

    NCRMP/B-W/AP/RCS/PRED/03/

    Anandapuram/001

    Road from NH-5 to

    Ramarayadupalem

    /2010-11, Dt. 15.09.2011 15.09.11 14.06.12

    For SecondMilestone i.e

    WBM Gr-III iscompleted

    NCRMP/B-W/AP/RCS/PRED/03/Rambilli/002

    Road from R&B road toKrishnampalem

    /2010-11, Dt. 15.09.2011 15.09.11 14.09.12

    1st Milestonei.e CD works

    are completed& WBM Grade-

    III is inprogress.

    Road from R & B road toKattubolu to Marripalem

    /2010-11, Dt. 15.09.2011 15.09.11 14.09.12Ready tostarted

    Road from R & B road toRajakoduru

    /2010-11, Dt. 15.09.2011 15.09.11 14.09.12

    1st Milestonei.e CD works

    are completed& WBM Grade-

    III is inprogress.

    NCRMP/B-W/AP/RCS/PRED/03/Nakkapalli/003

    Road from R & B road toPedateenarla to Chinateenarla

    /2010-11, Dt. 15.09.2011 15.09.11 14.06.12

    For SecondMilestone i.e

    E/W iscompleted

    Road from Upamaka RajayyapetaR & B road to Janakayyapeta

    /2010-11, Dt. 15.09.2011 15.09.11 14.06.12

    For SecondMilestone i.e

    WBM is inprogress

  • 7/31/2019 4.December 2011 MPR

    13/39

    MONTHLY REPORT

    12 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Status of works in Visakhapatnam District up to 31.12.2011

    Category Packages allotted under Phase - 1Names of works under

    each packageAgreement No.

    / Date

    Milestone Completion DatesProgress w.r.t.milestone up to

    31.12.2011First Second Third

    MPCS

    NCRMP/B-W/AP/MPCS/PRED/03/Payakaraopeta/003

    Construction of cyclone

    shelter at GajapathiNagaram

    /2011-12, Dt.

    03.10.2011 02.02.12 02.06.12 02.10.12

    To be handed over to

    the contractor.

    Construction of cycloneshelter at Ratnayampeta

    /2011-12, Dt.03.10.2011

    02.02.12 02.06.12 02.10.12Foundation footingwork is in progress

    NCRMP/B-W/AP/MPCS/PRED/03/Nakkapalli/002

    Construction of cycloneshelter at Patimeeda

    /2011-12, Dt.03.10.2011

    02.03.12 02.08.12 02.01.13E/W Foundation to bestarted

    Construction of cycloneshelter at Moolaparra

    /2011-12, Dt.03.10.2011

    02.03.12 02.08.12 02.01.13Foundation footingwork is in progress

    Construction of cycloneshelter at Bangarampeta

    /2011-12, Dt.03.10.2011

    02.03.12 02.08.12 02.01.13Foundation footingwork is in progress

    NCRMP/B-W/AP/MPCS/PRED/03/Rambillii/004Construction of cyclone

    shelter atVenkayyapalem

    /2011-12, Dt.03.10.2011

    02.01.12 02.04.12 02.07.12E/W foundationexcavation is

    completed

    NCRMP/B-W/AP/MPCS/PRED/03/Parawada/001Construction of cyclone

    shelter atTikkavanipalem

    /2011-12, Dt.07.10.2011

    06.01.12 06.04.12 06.07.12E/W foundationexcavation is

    completed

  • 7/31/2019 4.December 2011 MPR

    14/39

    MONTHLY REPORT

    13 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Status of works in East Godavari District up to 31.12.2011

    Category Packages allotted under Phase - INames of works

    under eachpackage

    AgreementNo. / Date

    Mile stonesRemarks

    First Second Third

    RHB (2 )RCS (8)MPCS (3)

    NCRMP/B-W/AP/RHB/PRED/04/Katrenikona/003

    Road from PR roads

    to Dasarivanipeta andto Cyclone Shelter

    /2011-12Dt:27.04.2011

    30-11-2011 30-11-2011 20-01-2012

    Work stopped due to land

    acquisition problemIn between chainage

    Km.1.400 to Km.2.280

    NCRMP/B-W /RCS/PRED/04/Karapa/001Approach Road tocyclone Shelter at

    Adavipudi

    2011-12Dt:20.05.2011

    30-11-2011 31-10-2011 31-01-2012

    Work stopped due to landacquisition problem

    Pipe Culverts completedin Km :0/2 & 1/6

    Culverts completed inKm:0/2 & WBM Gr. iii

    Layer work is in progressin between chainage

    Km.1.100 to Km. 1.775

    NCRMP/B-W/AP/RHB/PRED/04/Karapa/001/

    Road fromGurajanapalli to

    Bandulavaripalem

    2011-12Dt:27.04.2011

    30-09-2011 31-10-2011 31-01-2012Jungle clearance & Np3600 mm dia pipe Culvert

    Completed in Km. 0/2

    NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004

    Road from R&B Roadto P.Chodipallipeta CS

    2011-12Dt:07.09.2011

    3 months 3 months 3 monthsJungle clearance & Np3600 mm dia pipe Culvert

    Completed in Km. 0/2

    NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004

    Road from R&B Roadto K.Chodipallipeta CS

    /2011-12Dt:07.09.2011

    3 months 3 months 3 monthsJungle clearance & Np3600 mm dia pipe Culvert

    Completed in Km. 0/2

    NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004

    Road from R&B Roadto Hukumpeta CS

    /2011-12Dt:07.09.2011

    3 months 3 months 3 months

    Work stopped due to landacquisition problem

    Pipe Culverts completedin Km :0/2 & 1/6

  • 7/31/2019 4.December 2011 MPR

    15/39

    MONTHLY REPORT

    14 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004

    Road from R&B Roadto Gaddipeta CS

    /2011-12Dt:07.09.2011

    3 months 3 months 3 monthsJungle clearance is in

    progress

    NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004

    Road from R&B Roadto Danavaipeta CS

    /2011-12Dt:07.09.2011

    3 months 3 months 3 monthsJungle clearance is in

    progress

    NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004/

    Road from R&B Roadto G.Musalayyapeta

    CS

    2011-12Dt:07.09.2011

    3 months 3 months 3 months To be started

    NCRMP/B-W/AP/RCS/PRED/04/Uppalaguptam/003

    Road from R&B Roadto Chinaraghavulapeta

    Cyclone Shelter

    /2011-12 Dt:23.09.2011

    3 months/22.11.2011

    3 months22.06.2011

    ----------- Not yet Started

    NCRMP/B-W/AP/MPCS/PRED/04/Uppalaguptam/002

    Construction ofCyclone Shelter at

    Pedaraghavulapeta ofUppalaguptam Mandal

    E.G.Dt.

    /2011-12Dt:17.10.2011

    3 months16.01.2012

    3 months16.04.2012

    3 months16.07.2012

    Foundation Marking isin Progress

    NCRMP/B-W/AP/MPCS/PRED/04/Thondangi/004

    Construction ofCyclone Shelter atLaxamanudupadu

    inThondangi

    /2011-12Dt:07.09.2011

    Foundation Marking isin Progress

    NCRMP/B-W/AP/MPCS/PRED/04/Thondangi/004

    Construction ofCyclone Shelter at

    Avulamanda

    /2011-12Dt:07.09.2011 Not yet Started

  • 7/31/2019 4.December 2011 MPR

    16/39

    MONTHLY REPORT

    15 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Status of works in West Godavari District up to 31.12.2011

    CategoryPackages allotted under Phase

    - 1Names of works under

    each packageAgreementNo. / Date

    Milestone Completion Dates Progress w.r.t.milestone up to

    31.12.2011Remarks

    First Second Third

    RHB

    Mogalthuru Mandal NCRMPW.G.Dist

    Road from NH 214 A atRanga Statue center to

    Harijanawada of Kalipatnam(E) (Mogalthuru Mandal

    W.G.Dist.)

    16 /2011-12Dt.27.04.2011

    27/4/2011to

    22/9/2011

    23/9/2011to

    24/2/2012

    25/2/2012to

    26/7/2012

    8.46%GSB Completed G-II Layer

    Materal stacking is inProgress.

    R&B road at PanchayatOffice to Pulaparthivarithota

    via Badava(Mogalthuru Mandal

    W.G.Dist.)

    10.50%GSB Completed G-II Layer

    Materal stacking is inProgress

    Mogalthuru Vempa R&BRoad at Uchintha Kalava

    Bridge to GogulammaHarijanapeta (Mogalthuru

    Mandal W.G.Dist.)

    15.54% WBM G-II Layer Completed

    From Narsapur MogalthurR&B road to Dayadaldaspeta

    via Venkateswara Swamytemple (Mogalthuru Mandal

    W.G.Dist.)

    0%GSB Materal stacking is in

    Progress

    Road from NH 214 A road toHarijanapeta of Kothota

    (Mogalthuru Mandal

    W.G.Dist.)

    27/4/2011to

    22/9/2011

    23/9/2011to

    24/2/2012

    25/2/2012to

    26/7/201285% CC Road 300 m Completed.

    Narsapur Mandal W.G.Dist.

    R&B road to Indira Nagar(via) Pochamma temple

    (Narsapur Mandal W.G.Dist.)

    21 /2011-12Dt.09.05.2011

    09/05/2011to

    04/09/2011

    05/09/2011to

    06/01/2012

    07/01/2011to

    08/5/2012

    0% Work not Started

    Road from R&B road toPedalanka (Narsapur Mandal

    W.G.Dist.)8.88%

    GSB Completed G-II LayerMateral stacking is in

    Progress

    Road from LB Cheria CCroad to Chillapalemm of LBCheria (Narsapur Mandal

    W.G.Dist.

    9.72%GSB Completed G-II Layer

    Materal stacking is inProgress

  • 7/31/2019 4.December 2011 MPR

    17/39

    MONTHLY REPORT

    16 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Status of works in Krishna District up to 31.12.2011

    Category Packages allotted under Phase - 1Names of works under each

    packageAgreement No. /

    DateDHS DFC

    Progress up to31.12.2011

    RHB

    NCRMP/B-W/AP/RHB/PRED/06/Machipatnam/001

    Road connecting R&B roadthrough Gantalammapalem

    /2011-12Dt.27.4.2011

    27.04.11 26.01.2012

    3 cd works concertework completed,GSB WORK INPROGRESS

    NCRMP/B-W/AP/RHB/PRED/06/Machipatnam/002

    Road from R & B Road to B.VThota

    /2011-12Dt.27.4.2011

    27.04.11 26.01.2012

    JUNGLECLEARENCE WORK

    IN PROGRESS

    Road from Potlapalem Z.P roadto Chikativanipalem

    earth work inprogress and GSB

    collection is in

    progress

    NCRMP/B-W/AP/RHB/PRED/06/Kruthivennu/003

    Road from Intheru R&B Road toRangaraopet

    /2011-12Dt.27.4.2011

    27.04.11 26.01.2012

    JUNGLECLEARENCE WORK

    IN PROGRESS

    Road from R&B road to CycloneShelter at Chandala

    1 cd work completedand material

    collection work inprogress

    Kalla Mandal W.G.Dist.

    From A-U R&B Road toSatyanarayanapuram (Kalla

    Mandal W.G.Dist.)25 /2011-12Dt.26.05.2011

    26/5/2011To

    20/8/2011

    20/8/2011to

    21/11/2011

    22/11/2011To

    23/2/2012

    9.68%GSB Completed G-II Layer

    Materal stacking is inProgress

    From A-U R&B Road toMekaladibba (Kalla Mandal

    W.G.Dist.)11.10%

    GSB Completed G-II LayerMateral stacking is in

    Progress

  • 7/31/2019 4.December 2011 MPR

    18/39

    MONTHLY REPORT

    17 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Status of works in Krishna Districts up to 31.12.2011

    Category Packages allotted under Phase - 1Names of works

    under eachpackage

    AgreementNo. / Date

    Milestone Completion Dates Progressw.r.t.

    milestoneup to

    31.12.2011

    RemarksFirst Second Third

    RCSNCRMP/B-W

    /AP/RCS/PRED/06/Machipatnam/001

    Road fromBhogireddipalli R&B

    Road toRamakhandam

    /2011-12/Dt.02.09.2011

    01.12.2011 01.03.12 01.06.12 5%JUNGLE

    CLEARENCEWORK

    INPROGRESS

    Road from R&BRoad Chinnapuram

    to Gundupalem

    /2011-12/27.04.2011

    01.12.2011 01.03.12 01.06.12 10%GSB WORKCompleted.

    Road fromPotlapalem Z.P

    road to Pothepalli.

    /2011-12/Dt.02.09.2011

    01.12.2011 01.03.12 01.06.12 10%

    GSB WORKCOMPLETEDAND WBM

    COLLECTIONIN

    PROGRESS

  • 7/31/2019 4.December 2011 MPR

    19/39

    MONTHLY REPORT

    18 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Status of works in GUNTUR District up to 31.12.2011

    CategoryPackages allotted under

    Phase - 1Names of works under each package

    Agreement No./Date

    DHS DFCProgress up to

    31.12.2011

    RHB

    NCRMP/B-W/AP/RHB/PRED/07/KARLAPAL

    EM/001

    R/f Ganapavaram R&BRoad t o Kesavapuri ST colony 7/2011-2012

    27.04.201127.04.11 26.01.2012

    Last month ofaggrent period

    ,Work yet tobe start

    NCRMP/B-W/AP/PRED/07/Nagaram/002

    R/f R&B Road to Mohammad Alipalem

    8/2011-201227.04.2011

    27.04.11 26.4.2012

    CC Road 285 mtrscompleted.

    R/f R&B Road to Katuivaripalem. CC Road Shoewalls are inProgress.

    Bridges

    NCRMP/B-W/AP/Br/R&B/07/Bapatla/010

    Reconstruction of High level Bridge @Km5/2 ofBapatla-Suryalanka Road across Perali drain in

    Guntur79/2010-2011

    1.12.201001.12.10 31.5.2012

    Super structer is inprogress. 5 slabscompleted. WorkCompleted value is217.00 Lakhs.

    NCRMP/B-W/AP/Br/R&B/07/Bapatla/011

    Reconstruction of High level Bridge @Km2/4 ofBapatla-Pandurangapuram Road across Perali

    drain in Guntur78/2010-2011

    1.12.201001.12.10 31.5.2012

    Super structer is inprogress. 9 slabscompleted, Railingis in Progress.Work completedvalue is 285.00Lakhs

  • 7/31/2019 4.December 2011 MPR

    20/39

    MONTHLY REPORT

    19 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Status of works in GUNTUR District up to 31.12.2011

    Category Packages allotted under Phase - 1Names of works under each

    package

    Agreement No. /

    DateDHS DFC Progress up to 31.12.201

    RCS

    NCRMP/B-W/AP/RCS/PRED/07/P

    Palem/001

    Road from R&B Road to

    Mandevaripalem

    /2010-11

    Dt.01.11.201101.11.11 31.07.2012 Not yet started

    Road from R&B Road Alluru toYadavapalem

    /2010-11Dt.01.11.2011

    01.11.11 31.07.2012 Not yet started

    NCRMP/B-

    W/AP/RCS/PRED/07/KarlaPalem/002

    Road from Ganapavaram R & B

    road to Pedamarpuvaripalem

    /2010-11

    Dt.01.11.201101.11.11 31.10.2012 Not yet started

    Road from R & B Road to

    Chinapuluguvaripalem

    /2010-11

    Dt.01.11.201101.11.11 31.10.2011 Not yet started

    Road from R & B road to

    Yaramvaripalem

    /2010-11

    Dt.01.11.201101.11.11 31.10.2011 Not yet started

    Road from R & B road to

    Pedagollapalem Cyclone Shelter

    /2010-11

    Dt.01.11.201101.11.11 31.10.201 Not yet started

    Pedagollapalem PR Road toBonthagorlapalem

    /2010-11Dt.01.11.2011

    01.11.11 31.10.201 Not yet started

    NCRMP/B-

    W/AP/RCS/PRED/07/Nizampatnam/003

    Road from R&B Road to

    Gurunadhanagar

    /2010-11 Dt.

    17.10.201117.10.11 16.07.12 Work to be Grounded

    Road from R&B Road to Adavala

    H/O Bavajipalem

    /2010-11 Dt.

    17.10.201117.10.11 16.07.12

    CC Road work is inprogress

  • 7/31/2019 4.December 2011 MPR

    21/39

    MONTHLY REPORT

    20 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Road from R&B Road to

    Atlavaripalem

    /2010-11 Dt.

    17.10.201117.10.11 16.07.12 Work to be Grounded

    NCRMP/B-

    W/AP/RCS/PRED/07/Bapatla/004

    Road from R&B Road to

    Hanumanthanagar2010-11

    Dt13.10.201113.10.11 12.07.2012

    CC Road work is in progress

    Road from R & B road to

    Adarsanagar

    CC Road work is in progress

    Status of works in Prakasam District up to 31.12.2011

    CategoryPackages allotted under

    Phase- 1Names of works under each

    packageAgreement No. / Date DHS DFC

    Progress up to31.12.2011

    BRIDGESNCRMP/B-W/AP/Br/R&B/08/

    Kanaparthi/012

    Construction of High level Bridgeat Km 16/10 of Naguluppalapadu Kanaparthi road in Prakasam

    District76/2010-11 Dated 1/12/2010 01.12.10 31.5.12

    Deck slab to beconducted & Abutmen

    filter media & rampworking progress

    RHB

    NCRMP/B-

    W/AP/RHB/PRED/08/S.Konda/001

    Road from Pakala ZP Road toAtlavaripalem Cyclone shelter

    NCRMP/B-W/AP/RHB/PRED/08/S.Konda/001

    Dated 10/02/201110.02.11 9.2.12

    cc road completed &pipe culvert complete

    Road from R&B Road to

    Somarajupalli

    NCRMP/B-W/AP/RHB/PRED/08/S.Konda/001

    Dated 10/02/2011

    10.02.11 9.2.12CC road laying

    completed, side berm

    progress

    Road from R&B road toNarravaripalem

    NCRMP/B-W/AP/RHB/PRED/08/S.Konda/001

    Dated 10/02/201110.02.11 9.2.12

    earth work complted work not resumed

    NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002

    Road from NH5 to MulaguntapaduNCRMP/B-

    W/AP/RHB/PRED/08/S.Konda/002dated 10/02/2011

    10.02.11 10.02.12200 meters lengthcompleted out of

    512meters

    Road from R&B road toChalivendradibba

    NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002

    dated -10/02/201110.02.11 10.02.12

    C.D work is completeGsb is in progress.

    Road from Pakala R&B road toNCRMP/B-

    W/AP/RHB/PRED/08/S.Konda/00210.02.11 10.02.12

    earth work wideningprogress,Gsb to bedon

  • 7/31/2019 4.December 2011 MPR

    22/39

    MONTHLY REPORT

    21 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Mosanaladinne dated 10/02/2011

    Road from R&B road toBinginapalli Harijanawada

    Cyclone Shelter

    NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002

    dated 10/02/201110.02.11 10.02.12

    earth work wideningprogress

    Status of works in Prakasam District up to 31.12.2011

    CategoryPackages allotted under Phase -

    1Names of works under

    each packageAgreement No. / Date DHS DFC

    Progress up to31.12.2011

    RHB

    NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/00

    3

    Road from R&B Road Allurto M T Raju colony

    NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/003

    Dated 27/04/201127.04.11 27.04.12

    CC road compleetd, Gsprogress material approv

    shall be taken fromcompetent authority.

    NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/00

    4

    Road from KEM R&B Roadto Sankuvarigunta

    NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/004

    Dated 27/04/201127.04.11 27.04.12 WBM Gr-III progress

    Road from KEM R & BRoad to Pullareddypalem

    NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/004

    Dated 27/04/201127.04.11 27.04.12 WBM Gr-III progress

    NCRMP/B-W/AP/RHB/PRED/08/Ulavapadu/07

    Road from MC Road toSubbarayudu Satram

    NCRMP/B-W/AP/RHB/PRED/08/Ulavapadu/07

    dated 27/04/201127.04.11 27.04.12 Gsb progress

    NCRMP/B-W/AP/RHB/PRED/08/Ulavapadu/08

    Road from R&B road Tettuto Ramayapatnam

    NCRMP/B-W/AP/RHB/PRED/08/Ulavapadu/08

    dated 27/04/201127.04.11 27.04.12

    cc road and BT layingcompleted, shoulders

    progress

    NCRMP/B-W/AP/RHB/PRED/08/Tangutur/09

    Road from R&B road Pellurto Vasepallipadu

    NCRMP/B-W/AP/RHB/PRED/08/Tangutur/09 dated

    16/03/201116.03.11 16.03.12

    CC road compleetd,Gsprogress material approv

    shall be taken fromcompetent authority.C.D

    work is in progress

    NCRMP/B-W/AP/RHB/PRED/08/Tangutur/10

    Road from R&B road toKesupalem

    NCRMP/B-W/AP/RHB/PRED/08/Tangutur/10 dated

    16/03/201116.03.11 16.03.12

    CD works and culvertencasement work is

    completed & gsb is inprogress.

  • 7/31/2019 4.December 2011 MPR

    23/39

    MONTHLY REPORT

    22 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Status of works in Prakasam District up to 31.12.2011

    CategoryPackages allotted under Phase

    - I

    Names of worksunder each

    packageAgreement No. / Date

    Mile stonesRemarks

    First Second Third

    RCS

    NCRMP/B-W/AP/RCS/PRED/08/Vetapalem/001

    Road from R&Broad to vijayanagar

    colony cycloneshelter

    NCRMP/B-W/AP/RCS/PRED/08/Vetapalem/00

    1 dated 2011/12 dated30.09.2011

    29.01.2012

    29.05.2012

    29.09.2012

    cc roadcompleted & BT

    road completed

    Road from NH roadto

    Challareddypalem

    Grade-IIIprogress

    Road from R&Broad to jeevaraksh

    nagar colonycyclone shelter

    422 meters ccroad completed

    out of 500meters

    Road from R&Broad to Ramnagar

    colony cycloneshelter

    Not Grounded

    Road from R&Broad to cyclone

    shelter atMankenavaripalem

    Not Grounded

    NCRMP/B-W/AP/RCS/PRED/08/Chirala/002

    Road from R&BRoad to

    Keertivaripalemcyclone shelter

    NCRMP/B-W/AP/RCS/PRED/08/Chirala/002

    dated 27.08.2011

    Not Grounded

    Road from R&BRoad to Devinutalacyclone shelter ofchirala mandal inprakasam district.

    cc road laid 770m out of 800 m

    work isprogress.

  • 7/31/2019 4.December 2011 MPR

    24/39

    MONTHLY REPORT

    23 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Status of works in Prakasam District up to 31.12.2011

    Category Packages allotted under Phase - 1

    Names of worksunder each

    package Agreement No. / Date DHS DFC

    Progress upto

    31.12.2011

    MPCS

    Chakicherla cyclone

    shelter in Ulavapadu

    Mandal Prakasam

    District

    Not furnishedStilt floor roof

    slab fabrication ofsteel is inprogress.

    Stilt floor plinthbeam work to be

    taken yp.

    Kanaparthy cyclone

    shelter in

    Nagulappapadu

    Mandal Prakasam

    District

    Not furnished

  • 7/31/2019 4.December 2011 MPR

    25/39

    MONTHLY REPORT

    24 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Status of works in Nellore District up to 31.12.2011

    Category Packages allotted under Phase - 1 Names of works under each packageAgreement No. /

    DateDHS DFC

    Progress up to31.12.2011

    RHB

    NCRMP/B-W/AP/RHB/PRED/09/Bogole/001

    Road from NH 5 to Sambasivapuram

    34/2010-11, Dt.19.01.2011

    19.01.11 19.4.12

    WBMGr-II completd

    Road from 9/6 of Zuvvaladinne R&B Road to11/0 of Zuvvaladinne R&B viaVenkideshpalem (Venkideshpalem) WBMGr-II completd

    NCRMP/B-W/AP/RHB/PRED/09/Bogole/002Road from 1/6 of Zuvvaladinne R&B road toTellagunta

    / 2010 - 11, Dt.07.02.2011

    07.02.11 06.11.11 WBM Gr-II Completed

    NCRMP/B-W/AP/RHB/PRED/09/Chittamur/003

    Road from R&B road to Muttembake ViaPittuvanipalli 2010-11Dt

    18.01.201118.01.11 18.4.12

    wbm gr -II

    Road from R&B Chittamur to SomaSamudram

    GSB is in progress

    NCRMP/B-W/AP/RHB/PRED/09/Kavali/004

    Road from K.T R&B Road to Alliguntapalem

    32/2010-11, Dt.17.01.2011

    17.01.11 27.4.12

    BT is in progress ,Shoulders is inprogress

    Road from Km 5/8 of Chennayapalem Roadto Gummadi Bandala BT Completed

    Road from Pedapattapupalem R&B road toChennayapalem H. Wada

    Earth workembankment is inprogress

    NCRMP/B-W/AP/RHB/PRED/09/Vidavalur/005

    Road from R&B Road Alaganipadu to Vavilla/ 2011 - 12, Dt.27.04.2011

    27.04.11 27.7.12

    CC pavementcompleted

    Road from R&B road Kancharapalem HW toAlaganipadu

    Earth workembankment is inprogress

    RHB

    NCRMP/B-W/AP/RHB/PRED/09/Muthukur/006

    Road from R&B Road to PatuvariKandriga/2010-11Dt.25.04.2011

    25.04.11 25.1.2012 BT Completed

    NCRMP/B-W/AP/RHB/PRED/09/V.Chalam/007

    Survepalli Pudiparthi Road to SrikanthColony / 2011 - 12, Dt.

    27.04.201127.04.11 27.4.2012

    BT is in progress ,Shoulders is inprogress

    Road from R & B Road to Edagali Kandriga BT Completed

  • 7/31/2019 4.December 2011 MPR

    26/39

    MONTHLY REPORT

    25 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    NCRMP/B-W/AP/RHB/PRED/09/Allur/009Road from R&B Road Allur to Galidibbalu(via) Chukavanidibba

    /2010-11 Dt.24.01.2011

    24.01.11 24.4.2012 GSB is Completed

    RCS

    NCRMP/B-W/AP/RCS/PRED/09/Kota/001Road from R&B Road to A.S. Puram 2010-

    11Dt10.05.201110.05.11 10.2.2012

    GSB is completed,CCROADS ISPROGRESS.

    Road from GD road to Vavillapalem GSB is completed

    NCRMP/B-

    W/AP/RCS/PRED/09/Muthukur/002

    Road from R&B road Kappaladoruvu to

    Bandlapalem H.Wada

    /2010-11 Dt.

    21.04.201121.04.11 21.1.2012

    WBMGr-3 is

    Completed

    NCRMP/B-W/AP/RCS/PRED/09/Chillakur/004Road from Katuivaripalem R&B Road toVellapalm

    /2010-11Dt23.05.2011

    23.05.2011 23.2.2012Jungle clearance is inprogress

    NCRMP/B-W/AP/RCS/PRED/09/T.P.Gudur/005

    Road from 7/2 M.C road to VenkannapalemPattapupalem

    2011-10 Dt17.05.2011

    17.05.2011 17.2.2012WBMGr-3 isCompleted

    NCRMP/B-W/AP/RCS/PRED/09/DV.Satram/008

    Road from R&B road to Sullurpeta Mallam toBerjengalapalli cyclone shelter

    /2010-11 Dated9.05.2011

    09.05.2011 9.2.2012

    construction of pipeculverts iscompleted,gsb is inprogress

    NCRMP/B-W/AP/RCS/PRED/09/KAVALI/007

    Road from Kotha satram R&B to Indrsanagar(via) Thumalapenta palam, Patharavadupalam, Ramudu palam, Karaduvari palam&Sreeramapuram in SPSR Nellore District.

    Aggrement Concluded

    NCRMP/B-W/AP/RCS/PRED/09/KAVALI/006Road Connecting R&B Road through VoturuVillage in SPSR Nellore District.

    Aggrement Concluded

    NCRMP/B-W/AP/RCS/09/DVSatram/RCS/008

    Road from R&B road to Sullurpeta Mallam toberjengalapalli cyclone shelter

    Construction ofpipeculvert iscompleted , Gsb is inprogress

    NCRMP/B-W/AP/RCS/09/TPGudur/RCS/005Road from7/2 M.C Road to venkannapalempattapupalem

    GSB is Completed

    NCRMP/B-W/AP/09chillakur/RCS/004Road from kakuvaripalem R&B road tovellapalm

    agreement concluded

  • 7/31/2019 4.December 2011 MPR

    27/39

    MONTHLY REPORT

    26 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    NCRMP/B-W/AP/09kota/RCS/001

    road from R&B road to A.S PURAM GSB is Completed

    Road from GD Road to Vavillapalem GSB is Completed

  • 7/31/2019 4.December 2011 MPR

    28/39

    MONTHLY REPORT

    27 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    5.0 District wise status of tests conducted by TPQA:

    Apart from monitoring the tests being conducted by the implementation team (contractors & Line department) at

    various stages, the Third party Quality Audit team also conducted tests to confirm its compliance with the standards.

    These tests are carried out in the site itself and in some cases samples are collected and testing done in outside

    laboratories. The details of tests conducted in the field till end of September 2011 are presented.

    Summary of QC Tests - Up to 31.12.2011

    S.No. DistrictTotal No. Tests

    Done

    Total no. of Tests

    Passed Failed

    1 Srikakulam 227 207 20

    2 Vizianagaram 190 187 3

    3 Visakhapatnam 417 411 6

    4 East Godavari 145 141 4

    5 West Godavari 29 29 0

    6 Krishna 8 8 0

    7 Guntur 230 226 4

    8 Prakasham 402 401 1

    9 Nellore 277 272 5

    Total 1925 1882 43

    The works in West Godavari and Krishna Districts were just started

  • 7/31/2019 4.December 2011 MPR

    29/39

    MONTHLY REPORT

    28 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    6.0 Details of Audit Reports Submitted During this Month:

    S.NO District Package Number Name of work

    1 VishakhapatnamNCRMP/B-

    W/AP/RHB/PRED/03/Achyutapuram/007

    PROVIDING BT SURFACE TO THEROAD FROM R &B ROAD TO

    AVASOMAVARAM INACHUTAPURAM MANDAL

    2 VishakhapatnamNCRMP/B-

    W/AP/RHB/PRED/03/Achyutapuram/007

    PROVIDING BT SURFACE TO THEROAD FROM R &B ROAD TO

    AVARAJAM IN ACHUTAPURAMMANDAL

    3 West Godavari NCRMP/B-W/AP/RHB/PRED/05/MOGALTHURU/001

    Road from Mogalthuru - Vempa R&B

    road at Uchintha Kalava Bridge toGogulamma Harijanapeta ofMogalthuru Mandal in West Godavari

    District.

    4 Vishakhapatnam NCRMP/B-W/AP/RHB/PRED/03/Paravada/004 Road from R&B Road to Jalaripeta

  • 7/31/2019 4.December 2011 MPR

    30/39

    MONTHLY REPORT

    29 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    5 West GodavariNCRMP/B-

    W/AP/RHB/PRED/05/MOGALTHURU/001

    Road from NH 214 A road toHarijanapeta of Kothota of

    Mogalthuru Mandal in West GodavariDistrict.

    6 Srikakulam NCRMP/BW/AP/BR/R&B/001/Surampeta/003

    Construction of Minor bridge At KM12/2-4 of Nh-5 to Surampeta road via

    naruva, Mentada in SrikakulamDistrict.

    7 East GodavariNCRMP/B-

    W/AP/RCS/PRED/04/KARAPA/001/2011

    ROAD FROM APPROACH ROADTO CYCLONE SHELTER AT

    ADAVIPUDI.

    8 East Godavari NCRMP/B-W/AP/RHB/PRED/04/KARAPA/001ROAD FROM GURAJANAPALLI TO

    BANDULAVANIPALEM

    9 PrakasamNCRMP/B-

    W/AP/RCS/PRED/08/VETAPALEM/002Road from NH to Challareddypalem

    In Prakasam District

    10 PrakasamNCRMP/B-

    W/AP/RCS/PRED/08/VETAPALEM/002Road from R&B Road to

    Jeevarakshanpadu In PrakasamDistrict

    11 East GodavariNCRMP/B-

    W/AP/MPCS/PRED/04/Uppalaguptam/002

    Construction of Cyclone Shelter atPedaraghavulapeta of

    Uppalaguptam Mandal, E.G.Dt.

    12 PrakasamNCRMP/B-

    W/AP/RCS/PRED/08/VETAPALEM/002

    Road from R&B Road to Vijayanagarcolony cyclone shulter In Prakasam

    District

    13 Vijayanagaram NCRMP/ B-W/ AP/ Br/ R&B/ 02/ Puligadda/ 007

    Construction of Minor Bridge at Km.7/2 near Pulligadda of Konada Ramatheertham R&B Road to

    Konathalapalem via Yerukonda,Pasupam, Kollayavalasa (Z.P. Road)

    in Vizianagaram District

    14 VishakhapatnamNCRMP/B-

    W/AP/RCS/PRED/03/Anandapuram/001

    Providing B.T to the Road from NH-5to Ramarayadupalem in

    Yelamanchilli Mandal

  • 7/31/2019 4.December 2011 MPR

    31/39

    MONTHLY REPORT

    30 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    7.0 Observations in the submitted reports:

    Name ofWork:

    PROVIDING BT SURFACE TO THE ROAD FROM R &B ROAD TO AVASOMAVARAMIN ACHUTAPURAM MANDAL

    1. Two works are there in this package:1) PROVIDING BT SURFACE TO THE ROAD FROM R &B ROAD TO AVASOMAVARAM INACHUTAPURAM MANDAL and2)PROVIDING BT SURFACE TO THE ROAD FROM R &B ROAD TO AVARAJAM INACHUTAPURAM MANDALThe individual progress of this work is 91% value of work is completed. Shoulder works are inprogress.The combined progress of this package is 91.61%.

    2. Works to be done as per Common Milestone for Two works in this Package:Mile stone 1 to the end of Dt: 26.07.11- Earthwork, CD Works and GSB.Mile stone 2 to the end of Dt: 26.10.11- WBM Gr-II, Gr-III and Shoulders.Mile stone 3 to the end of Dt: 26.01.12- BT and Road furniture.

    3. The formation widths and Earthen shoulder widths are verified from Km 0/0 to Km 0/775 and at somelocations shoulders have slipped and the same shall be rectified.

    4.It is observed that the shoulder material of sand and gravel is not properly mixed. It shall be scarified,suitably remixed, watered to OMC and compacted to achieve the required relative compaction ofmin.98% of lab MDD as per the agreement clause.

    5. At some locations the formation width is observed to be less than the estimated width. The fieldofficers are requested to furnish the reasons for the same.

    6. The measurements like width and thickness of the WBM Gr.-3 Layer from Km 0/0 to Km 0/775 isverified and found tallying with the required measurements. The details are given in Annexure - 2.

    7. Volumetric analysis tests were conducted for WBM layer from Km 0/0 to Km 0/775. It is fairly tallyingTo specfication of clause 405.13 of MORD.

    8. Gradation is conducted for OGPC and Seal coat CA material and results are found to be within thespecified limits as per agreement specification.

    9. During execution, The rate of spraying of prime coat is verified and found to be within the specifiedlimits as per Table 502.1 of MORD. The spraying temperatures are also observed during executionand found to be varying from 320C to 350 C, which is within the specified limits as per MORD.

    10. During execution, the rate of spreading of tack coat is verified and found to be within the specified

    limits as per Clause 503 and Table 503.1 of MORD. The spraying temperatures are also observedduring execution and found to be varying from 38C to 42C, which are within the specified limits asper MORD specifications.

    11. During execution, Temparature at mixing, laying and at compaction are verified during execution andfound to be within the specified temperature range.

    12. The obtained values of Bitumen Extraction Test Results for OGPC and Seal Coat in % as per IRC:SP: 20 and IRC: SP: 11 from Km 0/0 to Km 0/775 are verified and found tallying with therequired.The details are given in Annexure - 4.

    13. White wash shall be done to parapet walls of the existing culverts for the clear visibility of vechiculartraffic.

    14. Village name boards, cautionary and mandatory signboards at necessary points all along the outeredge of sharp curves and at school locations shall be erected.

    15. Some of the KM and HM Stones are missing in this working road stretch.The field officers arerequested to erect them immediately.

    Name ofWork:

    PROVIDING BT SURFACE TO THE ROAD FROM R &B ROAD TO AVARAJAM INACHUTAPURAM MANDAL

    1. Two works are i n this package1) PROVIDING BT SURFACE TO THE ROAD FROM R &B ROAD TO AVASOMAVARAM INACHUTAPURAM MANDAL and2)PROVIDING BT SURFACE TO THE ROAD FROM R &B ROAD TO AVARAJAM IN

  • 7/31/2019 4.December 2011 MPR

    32/39

    MONTHLY REPORT

    31 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    ACHUTAPURAM MANDALThe individual progress of this work is 90 % value of work is completed. Shoulder work is in progress.The combined progress of this package is 91.61%.

    2. Works to be done as per Milestone:Mile stone 1 to the end of Dt: 26.07.11- Earthwork, CD Works and GSB.Mile stone 2 to the end of Dt: 26.10.11- WBM Gr-II, Gr-III and Shoulders.Mile stone 3 to the end of Dt: 26.01.12- BT and Road furniture.

    3. The formation widths and Earthen shoulder widths are verified from Km 0/0 to Km 1/112 and at somelocations shoulders have slipped and the same shall be rectified.

    4. It is observed that the shoulder material of sand and gravel is not properly mixed. It shall be scarified,suitably remixed, watered to OMC and compacted to achieve the required relative compaction ofmin.98% of lab MDD as per the agreement clause.

    5. At some locations the formation width is observed less than the estimated width. The field officers arerequested to furnish the reasons for the same.

    6. QC laboratory is not provided at site. The line deportment is requested to take necessary action andsee that the Quality lab is established at site at an early stage.

    7. Gradation is conducted for OGPC and Seal coat CA material and results are found to be within thespecified limits as per agreement specification.

    8. During execution the rate of spraying of prime coat is verified and found to be within the specifiedlimits as per Table 502.1 of MORD.And the spraying temperature is observed as 300C to 360 C andwithin the specified limits as MORD

    9. During execution the rate of spreading of tack coat is verified and found to be within the specifiedlimits as per Clause 503 and Table 503.1 of MORD.And the spraying temperature is observed as400C to 440 C and within the specified limits as MORD

    10. During execution, Temperature at mixing, laying and at compaction are verified and found within thespecified temperature limits.

    11. Bitumen Extraction Test conducted for OGPC and Seal Coat as per IRC: SP: 20 and IRC: SP: 11from Km 0/0 to Km 1/112 and the results are found tallying with the required. The details are given inAnnexure - 4.

    12. The measurements like width and length of parapets and pipes of all the culverts are verified andfound tallying with the estimate.

    13. Some of the KM and HM Stones are missing in this working road stretch. The field officers arerequested to make arrangement to rectify them immediately.

    14. Village name boards, cautionary and mandatory signboards at necessary points all along the outeredge of sharp curves and at school locations shall be erected.

    15. Parawise compliance report shall be furnished duly attending to the above remarks.

    Name ofWork:

    Road from Mogalthuru - Vempa R&B road at Uchintha Kalava Bridge to GogulammaHarijanapeta of Mogalthuru Mandal in West Godavari District.

    1. 12.34 % value of the work is completed for this one work in the package which contains five no. ofworks under one agreement.

    2. Works to be done as per Milestone:Mile stone 1 (i.e, Earth work, Pipe culverts, GSB) to the end of Dt: 26.09.2011 - 16.24 lakhs.(9.03%)Mile stone 2 (I.e, WBM Gr II, Gr III and Shoulders) to the end of Dt: 26.02.2012 - 76.44 lakhs.(42.51%)Mile stone 3 (i.e, BT, CC pavament and Road furniture) to the end of Dt: 26.07.2012 - 87.13 lakhs.(48.46%)

    3. The 600mm dia single row pipe culvert (2 No's) completed up to road level in 0/6. Further work has tobe taken up.

    4. WBM Gr-II of 595 meters length is completed .Shoulders need to be compacted simultaneously alongwith WBM layers. But shoulder work is not yet started.

    5. Widening earthwork formation and CD works is to be done prior to taking up WBM layers6. The thickness of the WBM Gr-II is observed to be varying from 75 to 100 mm as against the

    requirement of 75mm. Details are enclosed in annexure - 1..7. The project informatory boards with all details, Cautionary sign boards at necessary points and Village

  • 7/31/2019 4.December 2011 MPR

    33/39

    MONTHLY REPORT

    32 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    name boards are not provided as per aggregement.The same shall be provided as per the guidelinesgiven by PIU,NCRMP.

    8. The Quality Control Lab is not provided at site for testing of material. The line department officers arerequested to take necessary action to establish Quality Lab at site at early stage.

    Name ofWork:

    Road from R&B Road to Jalaripeta

    1. 85.05 % value of the work is completed. Shoulders works are in progress. The combined progress ofthis package is 85%

    2. Works to be done as per Combined Mi le stones :Mile stone 1 to the end of Dt: 28.06.11- Earthwork, CD Works and GSB.Mile stone 2 to the end of Dt: 28.09.11- WBM Gr-II, Gr-III and Shoulders.Mile stone 3 to the end of Dt: 28.12.11- BT and Road funiture.

    3. The formation widths and shoulder widths are verified from Km 0/0 to Km 0/860 and Km 1/163 to Km1/492 and at some locations shoulders have slipped and the same shall be rectified.

    4. It is observed that the shoulder material of sand and gravel is not properly mixed. It shall be scarified,suitably remixed, watered to OMC and compacted to achieve the required relative compaction ofmin.98% of lab MDD as per the agreement clause.

    5. It is observed that in between KM 1250m to 1260m the RHS shoulder width is less than (i.e 1.5m) therequired width of 1.875m.It is requested the field officers to furnish the reasons for the same andrectify.

    6. The measurements like width and thickness of the GSB Layer from Km 0/0 to Km 0/860 and Km 1/163to Km 1/492 are verified and found to be tallying with the required measurements. The details aregiven in Annexure - 1. As per MORD specifications minimum CBR requirement for GSB is 20%. Inspecial cases, the minimum CBR can be restricted to 15%. It is to be specified in the agrrementspecification. As it was not specified in the aggrement of this work, permission from the competentauthority is necessary.

    7. The measurements like width and thickness of the WBM Grade-II and WBM Grade-III layers from Km0/0 to Km 0/860 and Km 1/163 to Km 1/492 are verified and found to be tallying with the requiredmeasurements. The details are given in Annexure - 2.

    8. Gradation is conducted for OGPC and Seal coat CA material and results are found to be within thespecified limits as per agreement specification.

    9. During execution, The rate of spraying of prime coat is verified and found to be within the specified

    limits as per Table 502.1 of MORD. The spraying temperatures are also observed during executionand found to be varying from 300C to 360 C, which is within the specified limits as per MORD.

    10. During execution, the rate of spreading of tack coat is verified and found to be within the specifiedlimits as per Clause 503 and Table 503.1 of MORD. The spraying temperatures are also observedduring execution and found to be varying from 38C to 44C, which are within the specified limits asper MORD specifications.

    11. During execution, Temparature at mixing, laying and at compaction are verified during execution andfound to be within the specified temperature range.

    12. The measurements like width and thickness of the OGPC and Seal coat between Km 0/650 and Km1/163 to Km 1/492 are verified and found to be tallying with the required measurements. The detailsare given in Annexure - 3.

    13. The obtained values of Bitumen Extraction Test Results for OGPC and Seal Coat as per IRC: SP: 20and IRC: SP: 11 from Km 0/0 to Km 0/860 and Km 1/163 to Km 1/492 are verified and found tallyingwith the required.The details are given in Annexure - 4.

    14. White wash shall be done to parapet walls of the existing culverts for the clear visibility of vechiculartraffic.

    15. Temporary KM and HM Stones are erected in this working road stretch. The field officers arerequested to erect permanent stones immediately.

    16. Village name boards, cautionary and mandatory signboards at necessary points all along the outeredge of sharp curves and at school locations shall be erected.The field officers are requested toprovide the same.

    17. The field officers are requested to provide the invoices bills of the materials for verification.

  • 7/31/2019 4.December 2011 MPR

    34/39

    MONTHLY REPORT

    33 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    18. The informatory and identification of semi - reflective sign boards with all details shall be provided asper the aggrement.

    Name of

    Work:

    Road from NH 214 A road to Harijanapeta of Kothota of Mogalthuru Mandal in West

    Godavari District.1. 55.33 % value of the work is completed for this one work in the package which contains five no. ofworks under one agreement.

    2. Works to be done as per Milestone for the package:Mile stone 1 (i.e, Earth work, Pipe culverts, GSB) to the end of Dt: 26.09.2011 - 16.24 lakhs.(9.03%)Mile stone 2 (I.e, WBM Gr II, Gr III and Shoulders) to the end of Dt: 26.02.2012 - 76.44 lakhs.(42.51%)Mile stone 3 (i.e, BT, CC pavament and Road furniture) to the end of Dt: 26.07.2012 - 87.13 lakhs.(48.46%)

    3. i) C.C Road of 300 meters length is completed out of 380 meters length including Key walls.Shoulders works is not yet started.

    4. The compressive strength of CC Road is tested for approximate values with Rebound Hammer on dtd.14.11.2011 and the results are varying from 29.33 to 36.33 N/mm2.

    5. Two sets of cubes tested for compressive strength of 7 days and 28 days seperately at laboratary. Theaverage value of compressive strength is observed for 7 days as 22.736 N/mm2 and for 28 days as30.66 & 31.99 N/mm2.

    6. The thickness of the CC Road is observed as 202 to 213mm.7. The Quality Control Lab is not provided at site for testing of material. The line department officers are

    requested to take necessary action to establish Quality Lab at site at early stage.8. Cores will be taken to verify depth and compressive strength after 28 days of lying.9. MORD Specifications and IRC: SP-62-2004, Guidelines for the construction and design of Cement

    Concrete roads for low volume roads, need to be followed in cutting and spacing of joints and curingthe CC road as mentioned below.

    1. Construction of joints shall be mechanically sawn joints spaced 2.5 m to 3.75 m2. Length of the panel in the direction of traffic shall not be less than the width of the pavement.3. Joints shall be cut when the pavement is neither too soft nor too hard and able to bear the

    weight of the machine and crew. Normly it may vary from 8 to 12 hrs depending on weathercondtions

    10. Construction joints shall be butt joints and placed after a days work is over or when work is suspendedfor more then 30 minutes

    11. Expansion joints shall be provided near bridges and slab culverts and consists of a bitumenimpregranted joints/ premoulded synthetic joints filler board about 20 mm thick.

    12. 1. After completion of the finishing operations, the surface of the pavement shall be coverd with wetHessain cloth, burlap or jute mats. They shall be maintained fully wetted and in position for 24 hrs2. Upon the removal of the wet covering out the end of 24 hrs, the slab shall be thoroughly wetted andcured by ponding or sprinklers.

    13. After minimum 28 dys after casting the concrete pavement ,joints groove at contraction joint shall bewidened to a 10 mm width and to a depth 18 to 20mm and shall be sealed

    Name ofWork: Construction of Minor bridge At KM 12/2-4 of Nh-5 to Surampeta road via naruva,Mentada in Srikakulam District.

    1. Progress: About 70.80% of work is completed.The progress of work is slightly slow.2. Abutment (A1) to pier P1 Deck slab completed, Wing walls upto deckslab height completed, Approach

    road work not started.

    3. Milestone for this works in package 1: Compltion of Foundations upto Sill level (17.05.2011)-5 months.Milestone 2: Completion upto below the Deck slab (17.10.2011) - 10 months.Milestone 3: Completion of entire work (15.03.2012) - 15 months.

  • 7/31/2019 4.December 2011 MPR

    35/39

    MONTHLY REPORT

    34 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    4. During execution Gradation and AIV are conducted for Coarse aggregate.Gradation, F.M, and Siltcontent tests are conducted for fine aggregates the results are found with in the specified limits as perMORT8H section 1000.

    5. During execution Water Ph value, temparature and slump of concrete are tested and found within thespecified limits as per MORT8H section 1700.

    6. The reinforcement mat for deck slab is verified and found fairly tallying with drawing No.SD No.104

    7. The physical measurements are verified for slab and found fairly tallying with the drawing8. The informatory & identification of semi reflective sign boards with all details were not provided as per

    aggregement. The same may be provided immediately at site.

    9. Cautionary and mandatory signboards at necessary points on along the edge of sharp curves, schoolplaces and village name boards shall be errected,

    10. The field officers are also requested to test the samples of cement from every consignment, conduct allthe required tests on cement such as cube strength, initial setting time, Final setting time, consistency,soundness etc.

    11. The field officers are requested to provide the invoices bills of the materials for verification.

    12. Compliance shall be submitted parawise earlier after attending to the above remarks. Compliance shallbe subbmitted for the first QCR also.

    Name of

    Work:

    ROAD FROM APPROACH ROAD TO CYCLONE SHELTER AT ADAVIPUDI.

    1. 35% value of the work is completed. WBM grade III work is in progress.2. As per the Agreement the Milestones fixed are as follows.

    Milestone 1 - to the end of Dt.31.11.2011, Earth work, Pipe culverts.Milestone 2 - to the end of Dt.31.11.2011, WBM Gr-II, Gr-III and Shoulders.Milestone 3 - to the end of Dt.31.01.2012, BT and Road Furniture.1st & 2nd Mile stones completed but Earth work, Shoulders and CC pavement works are not yetstarted. Progress needs to be improved

    3. The measurements like width and thickness of the WBM Gr-II Layer from Km.0.000 to Km 1.250 isverified and found to be fairly tallying with the required measurements. The details are given inAnnexure - 1.

    4. Volumetric analysis tests were conducted for WBM Grade II layer from Km 0.000 to Km 1.250. QCtests conducted for WBM Grade II (field and lab) ie Gradation, AIV, FIV and Water absorption.Thedetails are given in QC Test summary. They are fairly tallying with the specfication requirements of

    clause 405 of MORD.5. Guard stones are to be fixed along the outer edge of sharp curves and White wash is to be done toexisting gaurd stones and pipe culvert body walls for the clear visibility to vechicular traffic.

    6. CD Works: 1) Pipe culverts 600mm dia 2no.s in KM 0/2 & Km.1/6 Completed. CC road of 50m lengthfrom Km.1.930 to Km.1.980 is to be done.

    7. Village name of work boards, cautionary and mandatory signboards at necessary points at schoollocations shall be erected as per the NCRMP norms.

    8. Parawise compliance report shall be furnished duly attending to the above remarks and the earlierQCR.

    Name ofWork:

    ROAD FROM GURAJANAPALLI TO BANDULAVANIPALEM

    1. 50% value of the work is completed. WBM grade III works is in progress.2. As per the Agreement the Mile stones fixed are as follows.

    Milestone 1 Earth work & Pipe culverts, GSB : to the end of Dtd. 30.09.2011Milestone 2 CC Pavement, WBM Gr II and Gr III and Shoulders : to the end of Dtd. 31.10.2011Milestone 3 BT and Road Furniture : to the end of Dtd. 31.01.2012

    3. 1st & 2nd Mile stones completed but Earth work and Shoulders are not yet started. Progress needs tobe improved

  • 7/31/2019 4.December 2011 MPR

    36/39

    MONTHLY REPORT

    35 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    4. The measurements like width and thickness of the WBM Gr.-III Layer from Km.1.100 to Km 1.825 isverified and found to be fairly tallying with the required measurements. The details are given inAnnexure - 2.

    5. Volumetric analysis tests were conducted for WBM grade III layer from Km 1.100 to Km 1.825. It isfairly tallying with the specfication of clause 405.13 of MORD. QC tests conducted for WBM GRADE II(field and lab) ie Gradation, AIV, FIV and water obsorption.The details are given in QC Test summary.The results are fairly tallying with the specfications of clause 405 of MORD

    6. WBM Grade III layar was distrubed due to vehicle movement. Regular wate sprinkling shall be donebefore taking up BT work. The disturbed WBM layer shall be properly rectified.

    7. Guard stones are to be fixed along the outer edge of sharp curves and white wash is to be done toguard stones and pipe culvert body walls for the clear visibility to vechicular traffic.

    8. Village name boards, cautionary and mandatory signboards at necessary points and at schoollocations shall be erected as per the NCRMP norms.

    9. CD Works: Pipe culverts 600mm dia 2no.s in KM 0/2 and Km.1/6 Completed.10. Parawise compliance report shall be furnished duly attending to the above remarks and earlierQCR.

    Name ofWork:

    Road from NH to Challareddypalem In Prakasam District

    1. 10.42 % of the work is completed.2. Works to be done as per Milestone:

    Mile stone 1 to the end of Dt: 29.01.12- Earthwork, and GSB.Mile stone 2 to the end of Dt: 29.05.12- WBM Gr-II, Gr-III and Shoulders.Mile stone 3 to the end of Dt: 29.09.12- BT, CC pavements and Road funiture.

    3. Grade -II WBM layer completed and Grade-III WBM lying is in progress from Km 0/0 to Km 0/370.

    4. During inspection on 2-11-2011, oversized metal was observed and the metal was asked to be eitherremoved or rectified by rebreaking to correct size. During inspection on 12-11-2011, it was observedthat the earier insructions were complied.

    5. Gradation tests were done on Grade III metal were also done and found to be satisfactory.6. The thickness of WBM Grade-II verified at random locations. From the results the thickness are tallying

    with the required thickness7. The volumetric test was conducted for Grade-II metal. It is as per requirements8. Shoulder formation was not done simultaneously with the WBM GrII and Gr III layers. Hence it is

    instructed to construct the shoulders simultaneously along with WBM Grade-II &III layers.9. The Shoulder width's are found to be less than required as per drawing at some locations in village

    portion.10. Camber is not properly provided at some location in between stretches Km 0/0 to Km 0/370. It is

    instructed to maintain proper camber as per approved drawing duly using camber board andtemplates...

    11. Km and HM stones are not available on the the road stretch.The field officers are requested to providethe same.

    12. Cautionary sign boards at necessary points and village name boards are not provided.13. The project informatory boards with all details were not provided as per aggregement.The same shall

    be provided as per the guidelines given by PIU, NCRMP.14. The quality control tests shall be conducted as per MORD section 1800 and QC records shall be

    produced for verification by TPQA staff.15. QC laboratory is not established at site.The fied officers are requested to take necessary action and

    see that the Quality lab is estabilished at site at an early stage.

    Nameof

    Work:

    Road from R&B Road to Jeevarakshanpadu In Prakasam District

    1. 81.82 % of the work is completed.2. Works to be done as per Milestone:

    Mile stone 1 to the end of Dt: 26.08.11- Earthwork, CD Works and GSB.Mile stone 2 to the end of Dt: 26.12.11- WBM Gr-II, Gr-III and Shoulders.Mile stone 3 to the end of Dt: 26.04.12- BT and Road funiture.

  • 7/31/2019 4.December 2011 MPR

    37/39

    MONTHLY REPORT

    36 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    3. CC road completed from Km 0/0 to Km 0/5004. Shoulder formation has to be done to support the CC road.5. It is observed that the following MORD & IRC: SP-62-2004 guidelines regarding joints and curing were not

    followed at site.6. MORD Specifications and IRC: SP-62-2004, Guidelines for the construction and design of Cement Concrete

    roads for low volume roads, need to be followed in cutting and spacing of joints and curing the CC road asmentioned below

    1. Construction of joints shall be mechanically sawn joints spaced 2.5 m to 3.75 m2. Length of the panel in the direction of traffic shall not be lessthen the width of the pavement.3. Joints shall be cut when the pavement is neither too soft nor too hard and able to bear the weight of

    the machine and crew. Normly it may vary from 8 to 12 hrs depending on weather condtions.4. Construction joints shall be butt joints and placed after a days work is over or when work is

    suspended for more then 30 minutes.5. Expansion joints shall be provided near bridges and slab culverts and consists of a bitumen

    impregnated joints/ remoulded synthetic joints filler board about 20 mm thick, and dowel bars.6. Longitudinal joints shall be provided for two lane road and shall be saw cut.

    Curing:

    (i) After completion of the finishing operations, the surface of the pavement shall be coverd with wet Hessain

    cloth, burlap or jute mats. They shall be maintained fully wetted and in position for 24 hrs

    (ii) upon the removal of the wet covering out the end of 24 hrs, the slab shall be thoroughly wetted and curedby ponding or sprinklers

    7. Km and HM stones are not available on the the road stretch.The field officers are requested to provide thesame.

    8. Cautionary sign boards at necessary points and village name boards are not provided.9. The project informatory boards with all details were not provided as per aggregement.The same shall be

    provided as per the guidelines given by PIU, NCRMP.10. The quality control tests should be conducted as per IRC SP-11, Maintain QC record and the same shall be

    produced to QA wing for verification.11. QC laboratory is not provided at site.The line deportment is requested to take necessary action and see that

    the Quality lab is estabilished at site at an early stage.

    Name ofWork:

    Construction of Cyclone Shelter at Pedaraghavulapeta of Uppalaguptam Mandal,E.G.Dt.

    1. As per the Agreement the Milestones are fixed as follows.Milestone 1 Ground Floor Plinth Level : 3 Months (16.01.2011)Milestone 2 First Floor Roof Slab Cast : 3 Months (16.04.2011)Milestone 3 Compleion of Works : 3 Months (16.07.2012)

    2. There is a narrow slab culvert at the approach to the cyclone shelter road. At present this is the onlyapproach to the site. For movement of bigger vehicles, the approach needs to be widened dulyconstructing wing walls on four sides.

    3. Another approach can be provided by constructing a pipe culvert on the southeren side of the sheltersite. Proper approaches are necessary during cyclone or other natural calamities.

    4. It is noticed that ground water table is high and required to be dewatered by suaitable beams forexcavation and construction of foundation.

    Name ofWork:

    Road from R&B Road to Vijayanagar colony cyclone shulter In Prakasam District

    1. 54.16 % of the work is completed.2. Works to be done as per Milestone:

    Mile stone 1 to the end of Dt: 29.01.12- Earthwork, and GSB.

  • 7/31/2019 4.December 2011 MPR

    38/39

    MONTHLY REPORT

    37 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Mile stone 2 to the end of Dt: 29.05.12- WBM Gr-II, Gr-III and Shoulders.Mile stone 3 to the end of Dt: 29.09.12- BT, CC pavements and Road funiture.

    3. Grade -III WBM completed from Km 0/0 to Km 0/475.

    4. During inspection by Site engineers, oversized metal was observed in grade III metal collected and itwas instructed to remove or rebreak the oversizes metal. During inspection on 12-11-2011, it wasnoticed tha the oversized material was removed and correct sized metal was collected.

    5. The thickness of WBM Grade-III layer was verified at random location thicknesses are as perrequirement. Camber and longitudinal undulations were also measured and tabulated in annexure-I.6. The volumetric test conducted for Grade-III metal layer and it satisfied the requirements.7. Shoulders foramtion is in progress. Shoulder formation has to be done simultaneously with the WBM

    Gr III layer. Hence it is instructed to construct the shoulders8. The Shoulder width's are found to be less than the width specified as per drawing at some locations in

    village portion.9. Camber is not properly provided at some locations. It is instructed to maintain proper camber as per

    approved drawing using camber board and thickness templates.10. Km and HM stones are not available on the road stretch.The field officers are requested to provide the

    same.11. Cautionary sign boards at necessary points and village name boards are not provided.12. All the Quality Control tests as per MORD section 1800 shall be conducted by the contractor and the

    field officers and the test records shall be produced to the TPQA staff for verification.13. QC laboratory is not provided at site. The line deportment is requested to take necessary action and

    see that the Quality lab is established at site at an early stage.14. CC pavement is completed from Km 0/475 to Km 0/525.15. It is observed that the following MORD & IRC: SP-62-2004 guidelines were not followed regarding

    joints and curing in CC road constructionMORD Specifications and IRC: SP-62-2004, Guidelines for the construction and design of CementConcrete roads for low volume roads, need be followed in cutting and spacing of joints and curing theCC road as mentioned below

    (i) Construction of joints shall be mechanically sawn joints spaced 2.5 m to 3.75 m(ii) length of the panel in the direction of traffic shall not be less then the width of the pavement(iii) Joints shall be cut when the pavement is neither too soft nor too hard and able to bear the

    weight of the machine and crew. Normly it may vary from 8 to 12 hrs depending onweather condtions

    (iv) Construction joints shall be butt joints and placed after a days work is over or when work issuspended for more then 30 minutes

    (v) Expansion joints shall be provided near bridges and slab culverts and consists of a bitumenimpregnated joints/ remolded synthetic joints filler board about 20 mm thick, and dowelbars

    (vi) Longitudinal joints shall be provided for two lane road and shall be saw cut.16. Curing: (I) After completion of the finishing operations, the surface of the pavement shall be covered

    with wet Hessian cloth, burlap or jute mats. They shall be maintained fully wetted and in position for 24hrs

    Name ofWork:

    Construction of Minor Bridge at Km. 7/2 near Pulligadda of Konada RamatheerthamR&B Road to Konathalapalem via Yerukonda, Pasupam, Kollayavalasa (Z.P. Road) inVizianagaram District

    1. Progress: About 44.12% of work is completed as against 52.00%. The progress of work is slightlyslow.

    2. Works to be done as per Milestone:Mile stone 1 to the end of Dt: 30.06.2011-Earthwork for foundation,PCC for Foundation,Footings.Mile stone 2 to the end of Dt: 31.01.2012-Substructure for abutments and wing walls, Supply and fixing of elastomeric neoprene bearings, Superstructure and 300mm thick Grouted rough stone revetment, Earth work for approaches etc.,.Mile stone 3 to the end of Dt: 30.05.2012-Super structure and construction of precast RCC railing,Streep seal expansion joints,SDBC etc.

    3. The width of filter media is verified and found between o.6m to 0.65m.

  • 7/31/2019 4.December 2011 MPR

    39/39

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    4. Gradation,AIV and FI are conducted for Coarse aggregate.Gradation ,F.M,and Silt content tests areconducted for fine aggregate the results are found with in the specified limits as per IS: 383-1970table- 1 & 2.

    5. During execution, tests are conducted for Water Ph value, temparature and slump of concrete aretested and found within the specified limits in MORT8H standard specification for Roads and Bridgeworks.

    6. The reinforcement mat for slab and beams are verified and found to be fairly tallying with drawingdetails.

    7. The physical measurements for elastomeric neoprene bearings are verified and found OK.8. The field officers have furnished the test results for Water, steel and cement obtained from Department

    of Civil Engineering, Andhra University, and Visakhapatnam.9. The field officers are also requested to apply cement slurry to the steel bars so as to protect them from

    rusting.10. The field officers are also requested to test the samples of cement from every consignment, conduct

    all the required tests on cement such as cube strength, initial setting time, Final setting time,consistency, soundness etc.

    11. The field officers are requested to provide the invoices bills of the materials for verification.12. The reinforcement steel shall be neatly stored on wooden blocks, racks or platforms above the ground

    in clean and suitably marked to facilitate inspection and identification as per Cl.1603 of MORTH.

    Name ofWork:

    Providing B.T to the Road from NH-5 to Ramarayadupalem in Yelamanchilli Mandal

    1. 18.82 % value of the work is completed. WBM Grade- II is completed.2. Works to be done as per Milestone:

    Mile stone 1 to the end of Dt: 14.12.11- Earthwork, CD Works and GSB.Mile stone 2 to the end of Dt: 14.03.12- WBM Gr-II, Gr-III and Shoulders.Mile stone 3 to the end of Dt: 14.06.12- BT and Road funiture.

    3. The earth work done in the widening portion is not compacted properly, it is to be constructed inlayers, sectioned, watered to OMC and compacted to achieve the required relative compaction ofmin.98% of lab MDD as per the agreement clause. The field officers were instructed to rectify thesame.

    4. Site registers are not available. The field officers are requested to maintain the material registers andthe same shall be furnished to the TPQA for verification.

    5. The formed width is less than the approved drawing width of 7.5m. The formed width is varying from

    6.0 to 7.0m. It is observed Hand pump and electrical poles are inside the road width on both sides fromCH: 0/0 to 0/390m. The field officers were asked to take necessary actions to shift them.6. The formation widths and earthen shoulder widths are verified from Km 0/0 to Km 0/390 and at some

    locations shoulders have slipped and the same shall be rectified.7. The measurements like width and thickness of the WBM Gr.-2 Layer from Km 0/0 to Km 0/390 is

    verified and found to be fairly tallying with the required measurements. The details are given inAnnexure-2.

    8. Volumetric analysis tests conducted for WBM layer from Km 0/0 to Km 0/390. It is fairly tallying tospecfication of clause 405.13 of MORD.

    9. Quality Control lab is not available at site. The Executive Engineer is requested to give necessaryinstructions to the contractor and see that the quality lab is established at site.

    10. Village name boards, cautionary and mandatory signboards at necessary points all along the outeredge of sharp curves and at school locations shall be erected.

    11. The Project informatory boards with all details were not provided as per aggrement. The same may beprovided immediately at site as per the guide lines by PIU, NCRMP.