6 pdfsam att-4 blrt-fd-cal-sa-3308 r1 firewater system sizing calculation
TRANSCRIPT
-
8/19/2019 6 Pdfsam Att-4 BLRT-FD-CAL-SA-3308 R1 Firewater System Sizing Calculation
1/1
Engineering and Design forLNG Receiving Terminal Project Bojonegara
BLRT-FD-CAL-SA-3308Firewater System Sizing Calculation
Page 6 of 10 Tokyo Gas Engineering Co., Ltd.
4. Calculation
4.1 Firewater Demand
Firewater demand calculation has been performed for 13 fire zones and trestle.
Detailed theoretical firewater demand for these fire zones is given in Table 3.
4.2 Firewater Pumps
The TERMINAL will be equipped with its own firewater pumps. The pump size
will be based on the total firewater demand on the largest fire event in a single
zone since “double jeopardy” is not considered. There will be 2x100% electric
motor and diesel engine driven firewater pumps. The required capacities of the
pumps for main areas are as follows:
Area Flow rate (m3
Unloading jetty
/h)
943
LNG tank 301
Process area 659
According the calculation, firewater pumps with capacity of 1170 m3/h at 13
kg/cm2
4.3 Firewater Line Sizing
G will be able to meet the firewater requirement for each of main area. The
pressure shall be further verified after the water curtain nozzles are selected.
The ring main is designed in such a way that any damage or maintenance of one
section will not interrupt the fire water supply to the users installed on the other part
of the ring main.
The firewater line sizing and pressure drop calculation is done using the following
equation:
Average liquid velocity in pipe,
v =353.6 Q/d2
Where v= flow velocity (m/s)
Q = flowrate (m3
The maximum line velocity used is 4.6 m/s in most cases according to Section
4.14.3 of NFPA 20, using 150% of the rated flow of 1170 m
/h)
d = internal pipe diameter (mm)
3/h as the maximum flow