- Description of the instrument
- Philosophy approach
- Subsystems development plan
E U S O - B A L L O O N D E S I G N R E V I E W, 1 8 . 1 2 . 2 0 1 2 , C N E S T O U L O U S E
Guillaume PrévôtAPC, Paris
Development Plan
Description of the instrument
The EUSO Balloon instrument consisting of a three lenses system, a Focal plane with its electronics, referred as the PDM, and the flight electronics:
CDR – 18.12.2012
Development Plan 2
The Euso Balloon payload The Euso Balloon ‘carambola’
Optical Bench (OB) Instrument Booth (IB)
Description of the instrument
- The architecture of the EUSO-BALLOON payload is characterized by a Scientific Instrument that is also the balloon gondola.
- All components and subsystems will be integrated into the optical bench (OB) and instrument booth (IB) in CNES Clean room.
- In order to allow for recovery at sea, the "instrument-booth" will be entirely watertight by using the lens-3-assembly as a watertight porthole.
- Most of the components are commercial, off-the-shelf. Some components are military grade. No ITAR components are used.
CDR – 18.12.2012
Development Plan 3
Philosophy approach of our development plan
- The EUSO-BALLOON instrument is a PFM (Proto Flight Model). Some subsystems having a critical design may require the development of EM (Engineering Model).
- For the standard part, the FM (Flight Model) will be directly produced.
- EUSO-Balloon instrument is identical or similar to the JEM-EUSO instrument: the international partners within the JEM-EUSO collaboration contribute to the instrument according to their corresponding tasks and responsibilities in JEM-EUSO, under the management and responsibility of the French team, which acts in coordination with the JEM-EUSO management.
- The EUSO-BALLOON development plan has not changed.
- We just did the modification / additions that CNES asked for during the PRR:
- 3.2 Description of the instrument - 5.4 Telescope system chapter - 5.5 Infrared Camera chapter - 5.5.7 Addition of a new software chapter - 5.8 Addition of a summarized thermal tests table
CDR – 18.12.2012
4Development Plan
EC_Unit Development Plan
CDR – 18.12.2012
5Development Plan
- The EC_Unit Development Plan:- EC-Dynode board - EC-Anode board - EC_HV & HV Cockroft Walton- EC-ASIC board - MAPMTs procurement
EC_Unit Development Plan
CDR – 18.12.2012
6Development Plan
- The EC_Unit prototypes:- Mechanical prototype : potted by MATRA
- Electrical prototype (non potted) : the analog signals from 1 channel/MAPMT were checked (with oscilloscope) and found satisfactory.
- Potting of the electrical prototype in progress. Will be re-tested late december 2012.
PDM Board Development Plan
CDR – 18.12.2012
7Development Plan
- The PDM Board Development Plan:- EC-Dynode board - EC-Anode board - EC_HV & HV Cockroft Walton- EC-ASIC board - MAPMTs procurement
CPU Board Development Plan
CDR – 18.12.2012
8Development Plan
- The CPU Development Plan:- A prototype of the CPU has been realized in the INFN Naples laboratory.
- The CPU, inserted in a prototype of the DP box has been tested in Vacuum chamber together with a prototype of the CLK board and a of the GPS receiver.
- A perfect replica of the prototype realized will be manufactured as FM.
Clock board development Plan
CDR – 18.12.2012
9Development Plan
- The Clock board Development Plan:- A prototype of the CLK board has been already developed by INFN
Napoli JEM EUSO group.
- Pre-integration with CPU and CCB
- A perfect replica of the prototype realized will be manufactured as FM.
CCB Development Plan
CDR – 18.12.2012
10Development Plan
- The CCB Development Plan:- A prototype of the CCB board has been already developed by IAAT
- Pre-integration with CPU: SpaceWire communication with CPU is working stable
- Communication tests with PDM Board are in progress.
- A perfect replica of the prototype realized will be manufactured as FM.
HK Development Plan
CDR – 18.12.2012
11Development Plan
- The HK boards Development Plan:- Prototypes have been already developed by UNAM.
- Thermal tests have been done
- It was tested in stand alone and communication tests with the others subsystems were done in Naples early November
- A perfect replica of the prototype realized will be manufactured as FM.
- Software related to DP interfaces will be advanced during the integration.
Lenses Development Plan
CDR – 18.12.2012
12Development Plan
- The lenses Development Plan (from mid December 2012 to August 2013):
The Software Development Plan
CDR – 18.12.2012
13Development Plan
- The Software Development Plan:
- design and development of the configuration parameters storage and deployment into the various blocks, up to the end of December 2012;
- extensive tests, debug and optimization of the low level backbone, up to the second week of January 2013;
- development of the handling of the message from the balloon control, from the second week of January 2013 up to the end of March 2013;
- development of the user interface with the run control, from the second week of January 2013 up to the end of March 2013;
- extensive tests, debug, bottleneck fixes from March 2013 up to delivery to CNES;
IRCam Development Plan
CDR – 18.12.2012
14Development Plan
- The IRCam Development Plan:- A Flight Model will be directly built.
- The thermal/vacuum side of this model will be tested at Instituto Nacional de Tecnica Aeroespacial (INTA) facilities.
- Testing will begin as soon as the instrumentation is received (CPU, IR detector…), and then it will be tested 2013 the complete system on April 2013.
- Electrical assembly tests will be done at Orbital-Aerospace (prime contractor) facilities on March 2013.
- The flight hardware will withstand the environmental requirements and its operation is assured by thermal active and passive devices. The thermal/vacuum tests and validation will be carried out at INTA facilities on April 2013.
Thermal tests
CDR – 18.12.2012
15Development Plan
- From Mid December to mid January, thermal tests (temperatures, low pressure) will be done for DP subsystems.
- ASICs and FPGAs of PDM will be tested at differents temperatures.
- WORK IN PROGRESS