annexure 3.2
TRANSCRIPT
-
8/6/2019 Annexure 3.2
1/5
Infrastructure Development Action Plan for Chhattisgarh Final Report
Annexure III.2 1
Captive Power refers to generation from
a unit set up by industry for its exclusiveconsumption. The estimates on captivepower capacity in the country vary withthe Central Electricity Authority puttingthe figure at about 11600 MW whileindustry experts feel that it is muchhigher, close to 20000 MW
Industrial sector is one of the largestconsumers of electrical energy in India.However, a number of industries arenow increasingly relying on their owngeneration (captive and cogeneration)
rather than on grid supply, primarily forthe following reasons:
Non-availability of adequate gridsupply
Poor quality and reliability of gridsupply
High tariff as a result of heavy cross-subsidisation
The State Governments and SEBs havebeen concerned about the growingimportance of Captive Power Plants on
account of the following reasons: Captive plants may have adverse
impacts on the finances of the utility,such as:
Industrial load is the main sourcefor cross-subsidising revenueflows
Billing and collection is muchmore efficient for HT consumers
SEBs ability to service escrowaccounts for security packagesis also reduced
Non-optimal growth of the sector.
Problems in grid managementespecially in case of states withsurplus power
Adverse environmental impactsarising from types of fuels used andfrom higher emissions per unit of
production, as compared to largepower plants
Reliability of power supply fromcaptive and cogen plants as asource of firm power
While on the other hand the concern ofthe owners of captive and cogen plantsstems from: Non-remunerative tariff structure for
surplus power produced by them No risk sharing in case of non-
availability of fuel, change in variablecost due to switching of fuel afterentering into power purchaseagreement (PPA), etc
Inadequacies in wheeling andbanking facilities
High contract demand charges. High level of duties and taxes on
sale of power High wheeling losses assumed for
power to be sold to grid by captive orcogen plant
Need to devote time and energy to
an activity, which is not their corebusiness Restrictions on the minimum amount
of power to be wheeled If the captive power plant (CPP)
fails, charges for back-up or stand-by power from the grid are twice thenormal rate for captive plants
No formal policy for purchase ofcogenerated power (in most of thestates)
It is estimated that about 30% of thetotal energy requirement of the Indianindustry is currently met through inhouse power plants. The state-wisecaptive capacity in 1998 is given in thetable overleaf:
Annexure III.2 CAPTIVE POWER SCENARIO IN INDIA
-
8/6/2019 Annexure 3.2
2/5
Infrastructure Development Action Plan for Chhattisgarh Final Report
Annexure III.2 2
Based on the fuel type used for captivepower generation about 45% of power
generated is from steam, 40% fromDiesel and 15% from Gas/Naphtha.Captive contribution by various industrytypes is as follows:
The feature of the policy ofthe states with respect topromotion of captive powerplants and cogeneration is asfollows:
Orissa
The permission for settingup Cogeneration/captivepower plant will have tobe obtained from theOrissa ElectricityRegulatory Commission(OERC)
The capacity of thecogeneration/captive power plant willbe limited to the extent required tomeet 100% of the heat and powerrequirement of the industriesconcerned on a sustained basis or toa larger extent necessary for theeconomic viability of the project
Surplus power from such plantswould be purchased by the GRIDCOafter negotiation on a project toproject basis
GRIDCO will permit wheeling ofpower over its transmission systemsubject to carrying capacity of thetransmission system. It will alsoallow sale of surplus power by theindustry to other industries withinand outside the state to the extentpermitted by State government. Bi-lateral sale to the other state will bepermitted on a specific approval ofthe state government
Interconnection of theCogeneration/captive power plantwith the State Grid would be at thecost of industry satisfying thetechnical requirement
The Cogeneration/captive powerplant may beset up either bythe promotersthemselves orby a separatecompany andshall abide byall relevant Actsand Rules inforce primarilythe IndianElectricity Act,1910, theElectricitySupply Act,1948 and
State
Installed
Capacity
(MW)
Captive
Capacity
(MW)
Andhra Pradesh 8204 1220
Assam 1078Bihar 4656 614
Delhi 1436
Gujarat 8376 1505
Haryana 882 335
Himachal Pradesh 3570 32
Jammu & Kashmir 1536 3
Karnataka 3462 1045
Kerala 1766 151
Madhya Pradesh 7173 1333
Maharashtra 11072 570
Meghalaya 239
Orissa 3243 1544
Punjab 2620 311
Rajasthan 2176 528
Tamil Nadu 8271 1107
Uttar Pradesh 12473 1240West Bengal 6515 786
Total 89167 12322
Source: Power Line Research
Industry
Capacity
(MW) % Share
Cement 1223 9.9
Chemicals 2076 16.8
Electronics 59 0.5
Engineering 2479 20.1
Jute 207 1.7
Metals & Minerals 2404 19.5
Miscellaneous 784 6.4
Paper 473 3.8
Services 80 0.6
Sugar 706 5.7
Textile 1303 10.6
Unclassified 530 4.3
Total 12322 100
Source: Power Line Research
-
8/6/2019 Annexure 3.2
3/5
Infrastructure Development Action Plan for Chhattisgarh Final Report
Annexure III.2 3
Orissa Electricity Reform Act, 1995
Gujarat
Any industrial undertaking to set upcaptive power plant requires theconsent of the Gujarat ElectricityBoard (GEB) under section 44(1) ofthe Electricity (Supply) Act, 1948
Banking of electrical power withGEB/Licensee would not bepermitted
Permission for installation of standbygenerating sets to work as additionalsource of power would be permittedup to two times the consumerscontract demand/ contracted loadwith GEB/Licensee or demandequivalent to capacity of its ownregular source of power supply
Wheeling of electrical power fromcaptive power plant of an industrialcompany to the other industrial unitswithin the same company or toany/all industrial units of its groupcompanies is allowed. Minimumquantity of power to be wheeledshall not be less than 5% of theinstalled capacity of the captivepower plant or 5MW, whichever ismore, among the group companiestaken together subject to thecondition that supplying companyconsumes at least 50% of thegenerated power
Wheeling charges are 13.5 paisa perkWh and 21 paisa per kWh forpower delivered at EHV and HVlevel respectively subject to revisionfrom time to time
Wheeling of power is also notallowed when system frequency is51 Hz and above
No night hour tariff concession shallbe admissible for power consumed/
drawn from the grid during nightperiod
System losses shall be consideredas 10% for power delivered at EHVand 15% in case of power deliveredat HV and the same would bededucted from the account ofrecipient unit
The rate for purchase of surpluspower would be decided by GEBand will depend on the fuel beingused and would be on cost plusbasis, where the fuel cost will bedecided by GEB on normative basisfor each quarter for each type of fueland gross calorific value
The State government isempowered to prescribe terms andconditions relating to electricitysupply and tariff for such supply
The electrical energysupplied/wheeled to differentrecipient units of group companiesfrom captive power plant of asupplying company would besubjected to payment of ElectricityDuty as per schedule I of theBombay Electricity Duty Act, 1958and Tax on sale of electricity as perthe provisions of Gujarat Tax on saleof electricity Act, 1985, as amendedfrom time to time
Note: In an recent policyannouncement, Gujarat governmenthas reduced the period of exemptionfrom payment of electricity duty tofive years for new captive powerplants (CPP) commencing powergeneration after March 31, 1999
-
8/6/2019 Annexure 3.2
4/5
Infrastructure Development Action Plan for Chhattisgarh Final Report
Annexure III.2 4
Maharashtra
The permission for installation andrunning the captive power plant willbe granted by the government andthe capacity of the CPP will belimited to cover the existing demand(MW) plus 1/3 of existing demand inMW or demand in MW for futureexpansion
Third party sale is allowed and inthis case a tripartite agreement willhave to be signed between theBoard, CPP owner and the thirdparty receiving power from CPP
CPP can sell surplus power tomaximum two industrial units and isalso restricted up to 25 percent ofthe generated units (kWh)
Captive generating company or anyother company intending to sellsurplus electricity to third partieswould require a prior permissionfrom the Energy Department of theState Government under section 28of the Indian Electricity Act 1910
The wheeling charges andtransmission losses are determinedin terms of distance transmitted. Thewheeling charges and transmissionlosses are determined as 2% and5% respectively for a distance of 050km; 4% and 8% respectively for adistance of 50200 km; and 6% and10% respectively for a distanceabove 200 km
Rate at which surplus power wouldbe purchased would be decided byMSEB and it will not purchase anypower during night hours, that is2200 hrs to 0600 hrs
In case of planned shut down of theCPP, the excess demand recordedover and above the revised contractdemand will be charged at double
the normal demand charge rate ofthe respective tariff in force fromtime to time
Uttar Pradesh
Presently, the transmission anddistribution system of the UttarPradesh State Electricity Board(UPSEB) is not in a position tohandle any further load. However,the wheeling of electricity is allowedon a selective basis provided thecaptive developers pay 15%wheeling charges of the energyreceived
While fixing the tariff for captivepower plant UPSEB will not sharethe fixed charges (interest on loans,depreciation, O&M, income tax, etc.)for the captive power plant. Howeverthe UP Government may share thisfixed charges by way of soft loan,subsidy etc. as the consumer isinstalling the captive power plantprimarily for meeting his load due tosophistication of the plant which mayaffect its functioning due to qualityvariation in UPSEB supply system
The board control room may directcaptive power plant control room toregulate the export during the nighthours from 2200 hrs to 0600 hrs
West Bengal
Transmission and wheeling of powergenerated: The Wheeling facility willbe provided by the WBSEB/CESC ata uniform wheeling charge of 2% ofcost of power wheeled, irrespectiveof the distance from the generatingstation
-
8/6/2019 Annexure 3.2
5/5
Infrastructure Development Action Plan for Chhattisgarh Final Report
Annexure III.2 5
Banking facilities: The board permitsthe electricity generated to bebanked for a period of six months.
An industrial undertaking notcarrying on continuous process ofproduction may draw power from thebank at any time of the day exceptduring evening hours
Sale of power to WBSEB/CESC:The generated power not used bythe industrial undertaking within aperiod of six months will be deemedto have been sold to theWBSEB/CESC
Tariff for sale of power will bedetermined for each generatingstation separately uponconsideration of various factors suchas generating cost based on totalinvestment (less central govt. grant),debt equity ratio, depreciation, O&M,return on equity, debt serviceconditions, etc., as is done for largethermal/hydro power generatingstations