Contents
1 Executive Summary and Introduction to the 2013 AER………...
1.1Summary Report on 2013
2.0 Monitoring Reports Summary……………………………………3
2.1 Summary Report on Monthly Influent Monitoring……..5
2.2 Discharge from the Agglomeration……………………..6
2.3 Ambient monitoring Summary………………………….7
2.4 Data collection and Reporting Requirements under the
Waste water Treatment Directive……………………… 8
2.5 Pollutant Release and Transfer Register (PRTR)-Report
for the Previous Year……………………………………8
3.0 Operational Reports Summary…………………………………….8
3.1 Treatment Efficiency Report……………………………… 8
3.2 Treatment Capacity Report…………………………………9
3.3 Extent of Agglomeration Summary Report…………… …9
3.4 Complaints Summary……………………………………… 9
3.5 Reported Incidents Summary Report……………………….9
3.6 Sludge/ Other Inputs to the WWTP………………………..10
4.0 Infrastructural Assessments and Programme of Improvements ...11
4.1 Storm Water Overflow Identification and Inspection Report...11
4.2 Report on Progress Made and Proposals being Developed to meet
the Improvement Programme Requirements…………….11
5.0 License Specific Reports………………………………………..14
5.1 Habitats Impact Assessment Report……………………………
6.0 Certification and Sign Off
Mitigation Measures……………………………………………………
Management of Financial Risk…………………………………………
Declaration ….…………………….……………………………18
Appendices………………………………………………… Appendix 1…… Quality Results 2013
Appendix 2…… Non compliance Schedule 2013
Appendix 3…… Ambient Monitoring
Appendix 4…… PRTR Outlet
Appendix 5…….PRTR Inlet
Appendix 6…… Schedule B1 monitoring
Appendix 7……% Removal
Appendix 8…… Emergency Response Procedure/Corrective action Procedure
Appendix 9…… Public Awareness & communications Programme
Appendix 10…..Metals
3
Section 1 Executive Summary and Introduction to 2013 AER
1.1 Introduction and background to 2013 AER
Milford is a small market town located approximately 13 miles north of Letterkenny. The
existing population equivalent (p.e.) of the agglomeration is circa1902 with a projected
growth to 1931 p.e. by 2015. The breakdown in contribution is 43% Domestic, 33%
Commercial and 19% intuitional (see table 1). There are no sources of industrial waste in
Milford.
The waste water collection network is predominantly a combined (foul and storm water)
system. Since 1978, the agglomeration has been served by a secondary waste water
treatment plant (WWTP) located south of the town. Treated effluent, from the WWTP,
discharges into Maggy’s Burn, which is a small designated salmonid river, which flows
into Lough Fern, a distance of 2.2km downstream of the WWTP.
Milford WWTP provides secondary treatment by means of an oxidation ditch and
settlement tank. The WWTP was commissioned in 1978 and refurbished in 2000.
The main elements of the WWTP are:
• Intake works: there were 3 separate intake areas to the WWTP; note 1
(i) main inlet works,
(ii) inlet from Ramelton Road which flows directly into the oxidation ditch, and
(iii) inlet from Kilmacrennan Road, pumped directly into the oxidation ditch.
4
Note 1 The separate intakes were discontinued in December 2013 and all intakes now enter
the treatment works through a single “main inlet works”.
• Storm water overflow: Flows in excess of 3 times the dry weather flow,
(3xDWF), overflow from the main inlet works directly Maggy’s Burn via
discharge point SW2. There is no storm water holding tank at the WWTP.
• Preliminary treatment: manually raked screens at the main inlet works.
• Secondary treatment: Aeration in oval-shaped oxidation ditch (1,234m3
volume)
using surface aerators, followed by settlement in a clarifier;
• Final discharge: treated effluent discharges into Maggy’s Burn (discharge point
SW1)
The WWTP has an estimated capacity of 920p.e. The plant capacity is restricted by the
settlement tank, which treats a maximum of 3xDWF at 920 p.e. Given that the current
loading is circa 1,902 p.e., the plant is significantly overloaded by approximately double
its treatment capacity. Despite the current loading exceedence, Donegal County Council
(DCC) states that the treated effluent quality is capable of complying with the effluent
value of 25mg/l BOD and 35mg/l suspended solids when flows are less than 3xDWF.
DCC has identified the main problem as the inability to control the quantity of storm
water entering the WWTP. Flows in excess of 3xDWF entering the main inlet works are
discharged via storm overflow SW2 to Maggy’s Burn. However, there are no storm water
overflows on the other two inlets to the WWTP, which directly enter the oxidation ditch.
Problems are experienced with the treatment process during periods of heavy rainfall,
causing hydraulic overloading of the WWTP and consequently poor quality effluent.
As a discharge to freshwater from an agglomeration of <2,000 p.e., `appropriate
treatment` of Milford’s waste water was required under the UWWT Regulations by 31st
December 2005. Appropriate treatment in this case is considered to be tertiary treatment
(advanced BOD and nutrient removal), given the extremely limited assimilated capacity
available in Maggy’s Burn, for the waste water discharges (there are only 4 dilutions
available for the normal primary discharges at 95%ile river flow). The existing WWRTP
provides secondary treatment and is significantly overloaded. Therefore, Milford WWTP
requires expansion and upgrade, having regard to the assimilative capacity of the
receiving waters.
Changes to Intake Works in 2013: In December 2013, the three separate influent pipes
were combined into one intake. The intake from the Kilmacrennan Road was combined
with the intake from the Ramelton Road and both of these are now pumped to the main
intake chamber.
There were 6 influent and 6 effluent samples taken in 2013. While the BOD, COD and SS
sample results are all within the prescribed limits of the Discharge Licence, there was two
ELV for Ammonia at 12.6mg/l and 24 mg/l, two ELVs for Ortho Phosphorous at 1.51 and
1.7mg/l.
An analysis of the results would indicate that the primary treatment is effective, but the
secondary treatment is compromised. This can be attributed to the lack of nutrients within
the influent flow, thus limiting the breakdown of Ammonia. The susceptibility of the
treatment works to storm water infiltration in the piped network, compromises the
effectiveness of the treatment.
5
The plant’s estimate design capacity is for 920 p.e. and the estimate loading is 1902 p.e. It
should be noted that, hydraulic overloading of the plant, during heavy rainfall, causes the
treatment unit to surcharge; resulting in deterioration in the quality of effluent leaving the
plant.
This wastewater treatment plant requires upgrading to meet the limits, as set out in the
Discharge Licence.
Section 2. Monitoring Reports summary
2.1 Summary report on monthly influent monitoring
Milford WWTP Monitoring Report Summary 2013
2.1 Influent Monitoring
BOD (mg/l)
COD (mg/l)
SS (mg/l)
Ortho P (mg/l)
Ammonia (as N)
Hydraulic loading m3/d (estimate)
Organic loading PE/day)
Number of samples 6 6 6 6 6 6 6
Annual Max. 158 323 137 2.92 26.1 1303 2352
Annual Mean 104 251 95 2.36 17.7 1155 1902
Note: The results for Milford Quality Monitoring Results are included in Appendix 1
The hydraulic loading is estimated as there is no flow meter on the inflow. The
installation of flow meters is scheduled for the Qtr1, 2014
An examination of the influent BOD, COD, SS, would indicate low influent levels for all
these parameters, giving rise to less than optimum conditions for ammonia conversion.
This indicates that there is considerable dilution of the influent waste, arising from storm
water infiltration through out the network.
2.2 Discharge from the agglomeration
The primary discharge (SWI) is the outfall from the WWTP to Maggy’s Burn. The
discharge point is located adjacent to the WWTP, downstream of the town.
There are no secondary discharges from the agglomeration. Schedule A.1 of the
Discharge Licence sets interim emissions limits up until 31st December 2017 and
thereafter.
6
Discharges from the Agglomeration Summary Table
BOD (mg/l)
COD (mg/l)
SS (mg/l)
Orthophosphate (asP)
Ammonia (as N)
Other Parameters specified in WWDL Comment
WWDL ELV (Schedule A) 25 125 25 1.5 5 none
ELV with condition 2 interpretation included
Number of Sample results 6 6 6 6 6 NA
Number of Sample results above WWDL ELV 0 0 0 2 2 NA
Number of Sample results above WWDL ELV with Condition 2 interpretation included 0 0 0 2 2 NA
Annual Mean (for parameters where ELV applies) 5.08 40.5 9.6 1.1 7.6 NA
Overall compliance (Pass/Fail pass pass pass fail fail
Note: The results for Milford ELVs are shown in Appendix 2
7
While the BOD, COD and SS are within the limits set out in the Waste Water Discharge
licence, there were two non compliances for Ammonia and one for Ortho Phosphorus.
This is attributed to the to the influence of Storm Water infiltration, as can be deducted
from the low influent BOD reading on the 21.02/2013 of 87mg/l and again on the
11/04/2013, when the influent BOD was 83.7mg/l. This, together with the lower ambient
temperatures over the winter months, provides less than ideal conditions for the
conversion of Ammonia to Nitrate and Nitrites.
It should be noted that in June, the incoming BOD is of a similar concentration, but the
increase in temperature has assisted in the reduction of Ammonia.
Despite the load exceeding its theoretical capacity, the effluent records indicate the
effluent quality is currently complying with the target values of 25mg/l BOD and
35mg/l SS when flows do not exceed 3DWF.
2.3 Ambient Monitoring summary
2.3 Ambient Monitoring
Ambient Monitoring Point from WWDL
Irish Grid Reference
EPA Feature Coding Tool code
Does the Assessment of the ambient monitoring results indicate that the discharge is impacting on water quality
Upstream location 219271 426501 RS39M010150 no
Downstream location 218592 424904 RS39M010300 yes
Note: The results of the ambient monitoring are included in Appendix 3.
Bimonthly monitoring samples have been taken for upstream and down stream locations.
An examination of the upstream results would indicate that there is no significant loading
to Maggy’s Burn from the catchment upstream of the treatment works.
The downstream ambient monitoring station is located on Maggy’s Burn, approximately
2 klm from the outlet of the WWTW, on the upstream side of Lough Fern. While the
2013 testing has not indicated any significant increase in the test parameters between the
upstream and downstream ambient monitoring points, the EPA Q value Report of the
17/01/14 indicates a Q value of 2, at monitoring Station RS39N010300, indicating a poor
water quality.
It should be noted that, hydraulic overloading of the plant, during heavy rainfall, causes
the treatment unit to surcharge, resulting in deterioration in the quality of effluent leaving
the plant; also the storm water overflow at the intake to the plant comes into operation
when flows exceed 3DWF sending screened, but untreated waste water to the receiving
waters.
It should also be noted the assimilative capacity of Maggy’s Burn is an issue and the
relocation of the existing outlet should be considered as part of any major upgrade of the
existing treatment plant.
The outlet quality results show the WWTP discharge to be in compliance with the
standards of the Urban Waste Water Treatment Regulations, however the downstream
results shown in attachment F.1 show the effect the discharge is having on the quality of
8
the receiving water. Hydraulic overloading of the plant during heavy rainfall causes the
treatment unit to surcharge resulting in deterioration in the quality of effluent leaving the
plant; also the storm water overflow at the intake to the plant comes into operation when
flows exceed 3DWF sending screened but untreated waste water to the receiving waters.
As Milford is listed on the Water Services Investment Programme as a scheme to advance
to planning, these problems along with a number of other problems already stated in C.1
will be considered, while preparing the preliminary report for the proposed upgrade to
Milford WWTP.
Salmonid Water Regulations
Maggy’s Burn, a tributary of Lough Fern, River Lennon and ultimately Lough Swilly, is a
designated Salmonid River under Regulations SI 293/1988 of the European Communities
Quality of Salmonid Rivers. EPA monitoring site 0300, u/s of Lough Fern i.e. d/s Milford
WWTP, reports a Q value of 2, in it’s 2014 Quality of River Water in Ireland Report.
This indicates a poor quality rating. The impact of the existing discharge from Milford
waste water treatment plant is indicated by the monitoring results shown in appendix 3. It
can be seen from the results that the discharge is having an effect on the quality of the
water downstream from the discharge point.
As stated above, all issues, with regard to the discharge from Milford WWTP, are being
taken into account in preparing the preliminary report for the new upgrade, in order that
all current statutory environmental regulations applying to discharges to freshwater are
observed.
2.4 Data collection and reporting requirements under Urban Waste Water
Treatment Directive The monitoring data has been submitted electronically via EDEN on 14/02/2014
2.5 Pollutant Release and Transfer Register (PRTR) Report not required – PE under 2000
Section 3 Operational Reports Summary
3.1 Treatment Efficiency Report
COD (kg/day)
SS (kg/day)
Total P (kg/day)
Ammonia (as N) kg/day Comment
Influent mass loading (kg/day) average 114 252.6 96.9 2.4 25.6
Effluent mass Emission 5.97 47.94 11.26 1.26 18.37
% Efficiency (% reduction of influent load) 94.5% 82.5% 89.5% 47.5% 28.2%
9
3.2 Treatment Capacity Report
Treatment Capacity Report
Hydraulic Capacity - Design/As Constructed (M3/day) ?
Hydraulic Capacity - Current loading (m3/day) 1158
Hydraulic Capacity - Remaining (m3/day) 0
Organic Capacity - Design/ As constructed (PE) 920
Organic Capacity - Current loading (PE) 1902
Organic Capacity - Remaining (PE) 0
Will the Capacity be exceeded in the next three years? NA
3.3 Extent of Agglomeration Summary Report
% of total load generated in
the agglomeration
Load generated in the agglomeration that is collected in
the sewer network
95%
Load collected in the agglomeration that enters
treatment plant
93%
Load generated in the agglomeration going to individual
and appropriate treatment systems
5%
Load generated in the agglomeration that is not collected
and not individually treated
0%
3.4 Complaints Summary
Number Date &
Time
Nature of
Complaint
Cause of
Complaint
Action taken
to resolve
issue
Closed
(Y/N)
None NR NR NR NR NR
3.5 Reported Incident Summary
Incident
Type
Incident
Description
Cause No of
Incide
nts
Corrective
Action
Authorities
contacted
Closed
(Y/N)
Non
compliance
Ammonia
ELV
In adequate
treatment,
Surface
water
2 none none y
10
infiltration
in network
Non
compliance
Ortho _P ditto 1 none none y
No of incidents 2013 2
Number of Incidents reported to EPA via
EDEN in 2013
2
Explanation of discrepancies between the
two numbers above
3.6 Sludge / Other inputs to the WWTP Input Type M3/year PE/year % of load
Domestic / Septic Tank
Sludge
none NR NR
Industrial / Commercial
Sludge
none NR NR
Landfill Leachate (delivered
by tanker)
none NR NR
Landfill Leachate (delivered
by sewer network
none NR NR
Other (specify) none NR NR
11
Section 4 Infrastructural Assessments and Programme Improvements
4.1 Storm Water Overflow Identification and inspection Report There are 2 SWOs from the agglomeration which discharge directly to Maggie’s Burn;
SW2 (screened) from the WWTP main inlet works, which discharges within 50 m upstream
of SWI
SW 3 (unscreened) from the sewer network upstream of the WWTP, which discharges
approximately 100m upstream of SW1.
The Discharge Licence requires the upgrade of the existing SWOs to comply with dual
criteria, by 31st December 2017. The SWOs can only reasonably be upgraded when the
WWTP capacity has been adequately increased.
WWDL Name / Code for Storm Water Overflow
Irish Grid Reference
Included in Schedule A4 of the WWDL
Compliance with DoEHLG Criteria
No. of times activated in 2012 (No. of events)
Estimated /Measured data
Total volume discharged in 2012 (m3)
Estimated /Measured data
D0342-01
???
Yes
Not Compliant
Not known
Not known
Not known
D0342-01
219287E, 426533N
Yes
Not Compliant
Not known
Not known
Not known
4.2 Report on progress made and proposals being developed to meet the
improvement programme requirements
The Milford Sewerage Scheme is included in the Water Investment Programme 2010 -2012,
as part of the Towns & Villages Sewerage Schemes Bundle. Consultants have been
appointed and a Draft Preliminary Report has been prepared. The infrastructural
improvements required will be subject to funding being made available from Irish Water.
It is the intention of Donegal County Council to carry out the proposed improvement works
by the specified dates, subject to the availability of appropriate funding.
12
Specified Improvement Programmes
(under Schedule A
and C of WWDL)
Licence Schedule (A or C)
Licence Completion
Date
Date Expired? (N/NA/Y)
Status of Works ((i) Not Started; (ii) At planning stage; (iii) Work
ongoing on-site; (iv)
Commissioning Phase; (v)
Completed; (vi) Delayed;)
% Completed
Licensee Timeframe
for Completing
the Work
Comments
Redesign WWTP inlet works for better flow control Diversion of storm water from sewer collection network Upgrade to provide Tertiary treatment Installation of storm water storage tank Upgrading of StormWater Overflows
C C C C C3
31/12/2012 31/12/2012 31/12/2017 31/12/2017 31/12/2017
31/12/2012 31/12/2012 31/12/2012 31/12/2017
complete Survey of the extent of the issue forms part of the Preliminary Report being prepared Planning stage Not started Not started
100% 75% 75%
Overdue 31/12/2017 31/12/2017 31/12/2017
Draft Report being
considered
77% of Planning
stage complete
Improvement Programme (WWTP) summary table:
13
Improvement Programme summary table
Improvement
Identifier
Improvement
Descriprion
Improvement Source Progress (%
completed)
Expected
Completion Date
WWTP assessment
(Condition 5.2)
Sewer Integrity Tool
(condition5.2)
Secondary discharges
assessment (condition 4 &
5.2)
Drinking Water Abstraction
risk Assessment
(condition4)
Shellfish Impact
Assessment (Condition 5)
Pearl Mussel Impact
Assessment (condition4)
Improved operational
Control
Incident Reduction
Elemination/ Reduction of
Priority Substances
Does the Improvement Programme provide an assessment of the existing waste water treatment plant performance for the following:
Licensee self- assessment check to determine whether all relevant information is included in the Programme of Improvements
Reference to relevant section of AER (e.g. Appendix 2 Section 4.
Existing Capacity Yes
ELVs Yes
Receiving Water body designation Yes
14
Downstream abstraction and uses of water Yes
Water quality objectives for the water body Yes
S.16 Water Pollution Act licensed discharges to the works Yes
Comment
Sewer Integrity Risk Assessment tool Improvement Programme (Works) summary
table:
The sewer network has been surveyed in its entirety in 2013. However an analysis of the
survey has not been finalised and the parameters below are unknown at this time
The Improvement Programme should include an assessment of the integrity of the existing wastewater works for the following:
Risk Assessment Rating (High, Medium, Low)
Risk Assessment Score
Reference to relevant section of AER (e.g. Appendix 2 Section4.
Hydraulic Risk Assessment Score
Environmental Risk Assessment Score
Structural Risk Assessment Score
Operation & Maintenance Risk Assessment Score
Overall Risk Score for the agglomeration
Section 5. Licence Specific Reports
Licence Specific Reports summary Table:
Licence Specific Reports Required in
2013 or
outstanding
from previous
AER
Included in 2013
AER
Reference to
relevant section of
AER
Priority Substance Assessment NA NA
Drinking Water Abstraction
Point Risk Assessment
NA NA
Habitats impact assessment NA NA
Shellfish Impact Assessment NA NA
Pearl Mussel Report NA NA
15
Toxicity/ Leachate Management NA NA
Toxicity of final Effluent Report NA NA
5.1 Priority Substances Assessment
Licence self-assessment
checks to determine
whether all relevant
information is included in
the assessment
Does the assessment use the Desk Top Study Method or Screening
analysis to determine if the discharge contains the parameters in
Appendix 1 of the EPA guidance
NA
Does the assessment include a review of Trade Inputs to the works NA
Does the assessment include a review of other inputs to the works NA
Does the report include an assessment of the significance of the
results where a listed material is present in the discharge
NA
Does the assessment identify that priority substances may be
impacting the receiving water?
NA
Does the improvement Programme for the agglomeration include
the elimination / reduction of all priority substances identified as
having an impact on the receiving water quality?
NA
5.2 Drinking Water Abstraction Point risk Assessment
This report is not required as there is no known drinking water abstraction point
downstream of the Waste Water treatment Plan
5.3 Shellfish Impact Assessment Report
Is a Shellfish Impact assessment required in the 2013 AER (or outstanding from a previous AER)?
No
List prescribed organisations consulted when preparing the assessment (BIM, SFPA, MI) NA
Does the assessment identify that any of the discharges from the works are impacting on the microbiological quality of the shellfish?
NA
16
Does the assessment recommend that there is a requirement to install UV/other disinfection equipment on any of the discharges?
NA
Provide details on disinfection system to be employed NA
Has this been completed? NA
If not yet complete what is the expected date for completion? NA
Where disinfection is required, is there a programme in place to demonstrate the efficiency of any disinfection system in place?
NA
What is the demonstrated efficiency of the disinfection system? NA
Is there a shellfish monitoring programme in place? NA
Does the shellfish or shellfish water monitoring programme include results generated by other organisations
NA
List organisations contributing data to the assessment NA
Does the Improvement Programme for the agglomeration include the findings and recommendations of the shellfish impact risk assessment?
NA
5.4 Toxicity / Leachate Management
Is a Toxicity / Leachate Management Report required in the 2013 AER (or outstanding
from previous AER) No
What % of the total influent is leachate? NA
Does the study identify any constituents of the leachate that present an environmental
risk? NA
List leachate constituent identified and impact (insert a row for each constituent) NA
Has the WWTP suitability to treat the leachate been assessed? NA
What are the results of the assessment (Suitable / Not Suitable / Suitable subject to
improvement programme works completion) NA
Has the study identified the max and operational loadings (mass, volume and rate of
addition) for leachate to the WWTP? NA
Is there a monitoring programme for the priority substances identified above? NA
Have trigger and action levels for the concentration of identified leachate constituents
been established to prevent impact on the receiving water? NA
Does the Improvement Programme for the agglomeration include any procedural
and/or infrastructural works to reduce the impacts of leachate acceptance on the
operation of the wwtp? NA
5.5 toxicity of the Final Effluent Report
Is a Toxicity report required? (Condition 4) no
Has the study been carried out against 4 species in 3 trophic levels? NA
Does the report identify that the discharge is toxic to any of the species in the study? NA
17
List species impacted NA Does the Improvement Programme for the agglomeration include any procedural and/or
infrastructural works to reduce the toxicity of the final discharge? NA
5.6 Pearl Mussel Measures Report
Is a Toxicity report required? (Condition 4) No
Has the study been carried out against 4 species in 3 trophic levels? NA
Does the report identify that the discharge is toxic to any of the species in the study? NA
List species impacted NA Does the Improvement Programme for the agglomeration include any procedural and/or
infrastructural works to reduce the toxicity of the final discharge? NA
5.7 Habitats Impact Assessment Report
Licensee self- assessment checks to determine whether all relevant information is included in the Assessment.
Is a Habitats Assessment required in the 2013 AER (includes outstanding
assessments from previous years)? No
Was the scope of the study agreed in advance with NPWS NA
Does the report include a Stage 1 screening assessment? NA Does the screening identify that discharges are causing an impact on
listed sites? NA
Does the report require a Stage 2 Appropriate assessment? NA Does the report identify any European Sites (e.g. SPA, SAC, NHA) that
discharges from the works could have an impact on? NA
List European sites identified (insert a line for each site identified) NA
Does the report include mitigation measures for each identified impact? NA Does each measure explain how the adverse impact will be
avoided/reduced? NA Does the Improvement Programme for the agglomeration include any
procedural and/or infrastructural works to reduce the impacts of
discharges on the a listed site (NHA, SAC, SPA)? NA
18
Does the AER include an executive summary? Yes
Does the AER include an assessment of the performance of the Waste Water Works
(i.e. have the results of assessments been interpreted against WWDL requirements
and or Environmental Quality Standards)?
Yes
Is there a need to advise the EPA for consideration of a technical amendment / review
of the licence? No
List reason e.g. additional SWO identified (insert lines as required) N/A
Is there a need to request/advise the EPA of any modifications to the existing WWDL?
Refer to Condition 1.7 (changes to works/discharges) & Condition 4 (changes to
monitoring location, frequency etc.) No
List reason e.g. failure to complete specified works within dates specified in the
licence, changes to monitoring requirements (insert lines as required) Awaiting funding approval from IW
Have these processes commenced? (i.e. Request for Technical Amendment / Licence
Review / Change Request) N/A
Are all outstanding reports and assessments from previous AERs included as an
appendix to this AER? N/A
List outstanding reports (insert lines as required) Appendix XX of 2013 AER
21
Appendix I Quality Results 2013
Location Lab Ref Date pH COND BOD COD SS Ammonia
(as N) Nitrate (as N)
Nitrite (as N)
Ortho P
Total N Total P
(mg/l) (mg/l) (mg/l) (mg/l) (mg/l) (mg/l) (mg/l) (mg/l) (mg/l)
Milford
Feburary
Upstream 132501637 21/02/2013 7.63 236 1.16 0.75 0.098 0.542 <0.010 <0.010 <1 0.039
Inlet 132501638 21/02/2013 7.53 446 87 264 102 17.8 0.2 0.11 2.92 38.9 4.01
Outlet 132501639 21/02/2013 7.79 432 5.44 51 11 12.6 0.19 0.06 1.08 17.4 1.23
Downstream 132501640 21/02/2013 7.66 252 2.13 2.75 1.2 0.71 0.037 0.096 2.5 0.158
Downstream No. 1 132501641 21/02/2013 7.31 218 2.01 10 0.311 0.737 0.028 <0.010 1.4 0.158
April
upstream 132502365 11/04/2013 7.36 503 4.11 7.25 0.088 0.5 0.012 <0.010 <1 0.086
Inlet 132502366 11/04/2013 7.76 768 83.7 196 84 14.9 0.388 0.07 2.9 30.8 3.75
outlet 132502367 11/04/2013 7.65 732 8.38 54 19 24 0.197 0.054 1.51 22 1.51
Downstream 132502368 11/04/2013 7.58 596 8.54 56.5 2.38 0.787 0.065 0.281 5.1 0.901 Downstream
no.1 132502369 11/04/2013 7.4 372 5.22 12 1.14 0.828 0.037 0.012 2.2 0.603
June
upstream 132503406 18/06/2013 7.45 233 1.17 1.2 0.066 0.015 <0.010 <0.010 <1 <0.01
Inlet 132503407 18/06/2013 7.62 226 99.4 290 88.5 16.5 0.219 <0.010 2.45 29.2 3.31
outlet 132503408 18/06/2013 7.52 404 4.08 37 6.5 0.996 3.08 0.835 0.518 9 0.64
Downstream 132503409 18/06/2013 7.38 226 1.4 8.2 0.087 0.541 0.017 0.014 1.1 0.044
August
22
upstream 132504313 13/08/2013 7.49 315 0.6 2.4 0.16 0.564 <0.010 <0.010 1.2 <0.01
Inlet 132504314 13/08/2013 7.64 142.6 296 137 15.7 0.409 0.324 1.93 26.7 3.85
outlet 132504315 13/08/2013 7.02 373 1.84 21 14 0.694 3.82 1.81 0.981 9.4 1.13
Downstream 132504316 13/08/2013 7.15 297 1.29 8.2 0.077 0.885 <0.010 0.018 1.4 0.099
October
upstream 132505363 15/10/2013 7.68 309 0.71 0.5 0.075 0.522 0.021 0.087 1.2 0.038
Inlet 132505364 15/10/2013 7.81 682 158.2 323 120 26.1 0.04 0.01 2.44 45.7 3.57
outlet 132505365 15/10/2013 6.95 466 7.08 46 3 4.13 5.52 1.02 1.7 21.9 2.07
Downstream 132505366 15/10/2013 7.06 293 0.72 11.25 0.088 1.239 0.021 0.066 2.2 0.205
December
upstream 132506403 12/12/2013 7.69 268 1.01 1.6 0.085 0.779 0.014 0.015 1.2 <0.010
Inlet 132506404 12/12/2013 7.94 451 54.8 140 41 15.3 0.211 0.07 1.53 20 1.74
outlet 132506405 12/12/2013 7.7 422 3.64 34 4 3.31 5.063 0.47 0.9 15.3 0.86
Downstream 132506406 12/12/2013 7.46 238 0.93 9.8 0.159 0.546 0.016 <0.01 1.3 0.042
23
Appendix II Non compliance Schedule 2013
Location Lab. Ref Date pH BOD COD SS NH3-(as N) Ortho P
(mg/l) (mg/l) (mg/l)
Schedule A
ELV 6-9 25 125 35 5 1.5
Milford - outlet 132501639 21/02/2013 7.79 5.44 51 11 12.6 1.08
Milford - outlet 132502367 11/04/2013 7.65 8.38 54 19 24 1.51
Milford - outlet 132503408 18/06/2013 7.52 4.08 37 6.5 0.996 0.518
Milford - outlet 132504315 13/08/2013 7.02 1.84 21 14 0.694 0.981
Milford - outlet 132505365 15/10/2013 6.95 7.08 46 3 4.13 1.7
Milford - outlet 132506405 12/12/2013 7.7 3.64 34 4 3.31 0.9
24
Appendix III Ambient Monitoring
Location Lab. Ref Date pH DO BOD NH3-(as N)
Ortho P
Total P
Total N
Visual Inspection SSRS
Priority Substances
(mg/l) (mg/l) (mg/l) (mg/l) (mg/l) (mg/l)
6/yr 6/yr 6/yr 6/yr 6/yr 6/yr 6/yr Annually As required
Milford
upstream 132501637 21/02/2013 7.63 11.64 1.16 0.098 <0.010 0.039 <1 Nothing Observed
upstream 132502365 11/04/2013 7.36 11.47 4.11 0.088 <0.010 0.086 <1 Nothing Observed
upstream 132503406 18/06/2013 7.45 8.37 1.14 0.066 <0.010 <0.01 <1 Nothing Observed
upstream 132504313 13/08/2013 7.49 10.02 0.6 0.16 <0.010 0.025 1.2 Nothing Observed
upstream 132505363 15/10/2013 7.68 10.44 0.71 0.075 0.087 0.038 1.2 Nothing Observed
upstream 132506403 12/12/2013 7.69 11.14 1.01 0.085 0.015 <0.01 1.2 Nothing Observed
Downstream 132501640 21/02/2013 7.66 10.96 2.13 1.2 0.096 0.158 2.5 Nothing Observed
Downstream 132502368 11/04/2013 7.58 8.68 8.54 2.38 0.281 0.901 5.1 Nothing Observed
Downstream 132503409 18/06/2013 7.38 7.75 1.4 0.087 0.014 0.044 1.1 Nothing Observed
Downstream 132504316 13/08/2013 7.15 10.11 1.29 0.077 0.018 0.099 1.4 Nothing Observed
Downstream 132505366 15/10/2013 7.06 7.77 0.72 0.088 0.066 0.205 2.2 Nothing Observed
Downstream 132506406 12/12/2013 7.46 9.69 0.93 0.159 <0.010 0.042 1.3 Nothing Observed
25
Appendix IV PRTR Outlet
Date pH Cond. BOD COD SS
NH3 as N
Nitrate (as N)
Nitrite (as N) Ortho P Total N Total P Flow
Daily Mass Flow BOD
Daily Mass Flow COD
Daily Mass Flow SS
Daily Mass Flow NH3
Daily Mass Flow NO3
Daily Mass Flow NO2
Ms/cm (mg/l) (mg/l) (mg/l) Mg/l (mg/l) (mg/l) (mg/l) (mg/l) (mg/l) kgs/Day kgs/Day kgs/Day kgs/Day kgs/Day kgs/Day
21/02/2013 7.79 432 5.44 51 11 12.6 0.19 0.06 1.08 17.4 1.23 1303 7.08832 66.453 14.333 16.4178 0.24757 0.07818
11/04/2013 7.65 732 8.38 54 19 24 0.197 0.054 1.51 22 1.51 1303 10.91914 70.362 24.757 31.272 0.256691 0.070362
18/06/2013 7.52 404 4.08 37 6.5 0.996 3.08 0.835 0.518 9 0.64 1303 5.31624 48.211 8.4695 1.297788 4.01324 1.088005
13/08/2013 7.02 373 1.84 21 14 0.694 3.82 1.81 0.981 9.4 1.13 870 1.6008 18.27 12.18 0.60378 3.3234 1.5747
15/10/2013 6.95 466 7.08 46 3 4.13 5.52 1.02 1.7 21.9 2.07 870 6.1596 40.02 2.61 3.5931 4.8024 0.8874
26
12/12/2013 7.7 422 3.64 34 4 3.31 5.063 0.47 0.9 15.3 0.86 1303 4.74292 44.302 5.212 4.31293 6.597089 0.61241
Step 1 6952 35.82702 287.618 67.5615 57.4974 19.24039 4.311057
STEP 2 0.005153 0.041372 0.009718 0.008271 0.002768 0.00062
STEP 3 2399.143 19260.23 4524.23 3850.291 1288.425 288.6883
28
NAME of WWTP: Milford 0
Location Lab Ref Date pH Cond. BOD COD SS NH3 as N
Nitrate (as N)
Nitrite (as N)
Ortho P
Total N
Total P Flow
Daily Mass Flow BOD
Daily Mass Flow COD Daily Mass Flow SS
Ms/cm (mg/l) (mg/l) (mg/l) Mg/l (mg/l) (mg/l) (mg/l) (mg/l) (mg/l) kgs/Day kgs/Day kgs/Day
Febuary
Milford - inlet 132501638 21/02/2013 7.53 446 87 264 102 17.8 0.2 0.11 2.92 38.9 4.01 1303 113.361 343.992 132.906
Milford - outlet
April
Milford - inlet 132502366 11/04/2013 7.76 768 83.7 196 84 14.9 0.388 0.07 2.9 30.8 3.75 1303 109.0611 255.388 109.452
Milford - outlet
June
Milford Inlet 132503407 18/06/2013 7.62 99.4 290 88.5 16.5 0.219 0.01 2.45 3.31 1303 129.5182 377.87 115.3155
Milford - outlet
August
Milford - inlet 132504314 13/08/2013 7.64 514 142.6 296 137 15.7 0.409 0.324 1.93 26.7 3.85 870 124.062 257.52 119.19
Milford - outlet
October
Inlet 132505364 15/10/2013 7.81 682 158.2 323 120 26.1 0.04 0.01 2.44 45.7 3.57 870 137.634 281.01 104.4
Milford - outlet
December
Inlet 132506404 12/12/2013 7.94 451 54.8 140 41 15.3 0.211 0.07 1.53 20 1.74 1303 71.4044
Milford - outlet
TOTAL Step 1 6952 685.0407 1515.78 581.2635
STEP 2 0.098539 0.218035 0.083611
STEP 3 45873.49 101503.6 3
1158.667 114.1735 252.63 9
30
Appendix VI Schedule B1 monitoring
Location Lab. Ref Date Flow pH BOD COD SS NH3-(as N) Ortho P
Priority Substances
Visual Inspection
m3/day (mg/l) (mg/l) (mg/l) (mg/l) (mg/l)
6/yr 6/yr 6/yr 6/yr 6/yr 6/yr As
Required 6/yr
Milford -
outlet 132501639 21/02/2013 1303 7.79 5.44 51 11 12.6 1.08 NT Nothing
Observed
Milford - outlet 132502367 11/04/2013 1303 7.65 8.38 54 19 24 1.51 NT
Nothing Observed
Milford - outlet 132503408 18/06/2013 1303 7.52 4.08 37 6.5 0.996 0.518 NT
Nothing Observed
Milford - outlet 132504315 13/08/2013 870 7.02 1.84 21 14 0.694 0.981 NT
Nothing Observed
Milford - outlet 132505365 15/10/2013 870 6.95 7.08 46 3 4.13 1.7 NT
Nothing Observed
Milford - outlet 132506405 12/12/2013 1303 7.7 3.64 34 4 3.31 0.9 NT
Nothing Observed
6952
Daily avg 1159
NT Not Tested
31
Appendix VII % Removal
Lab Ref Date pH Cond. BOD COD SS NH3 as N
Nitrate (as N)
Nitrite (as N)
Ortho P Total N Total P Flow
Daily Mass Flow BOD
Daily Mass
Flow COD Daily Mass
Flow SS
Daily Mass Flow
Total N
Ms/cm (mg/l) (mg/l) (mg/l) Mg/l (mg/l) (mg/l) (mg/l) (mg/l) (mg/l) kgs/Day kgs/Day kgs/Day kgs/Day
132501638 21/02/2013 7.53 446 87 264 102 17.8 0.2 0.11 2.92 38.9 4.01 1303 113.361 343.992 132.906 50.6867
132501639 21/02/2013 7.79 432 5.44 51 11 12.6 0.19 0.06 1.08 17.4 1.23 1303 7.08832 66.453 14.333 22.6722
132502366 11/04/2013 7.76 768 83.7 196 84 14.9 0.388 0.07 2.9 30.8 3.75 1303 109.0611 255.388 109.452 40.1324
132502367 11/04/2013 7.65 732 8.38 54 19 24 0.197 0.054 1.51 22 1.51 1303 10.91914 70.362 24.757 28.666
132503407 18/06/2013 7.62 99.4 290 88.5 16.5 0.219 <0.010 2.45 29.2 3.31 1303 129.5182 377.87 115.3155 38.0476
132503408 18/06/2013 7.52 404 4.08 37 6.5 0.996 3.08 0.835 0.518 9 0.64 1303 5.31624 48.211 8.4695 11.727
132504314 13/08/2013 7.64 514 142.6 296 137 15.7 0.409 0.324 1.93 26.7 3.85 870 124.062 257.52 119.19 23.229
132504315 13/08/2013 7.02 373 1.84 21 14 0.694 3.82 1.81 0.981 9.4 1.13 870 1.6008 18.27 12.18 8.178
132505364 15/10/2013 7.81 682 158.2 323 120 26.1 0.04 0.01 2.44 45.7 3.57 870 137.634 281.01 104.4 39.759
32
132505365 15/10/2013 6.95 466 7.08 46 3 4.13 5.52 1.02 1.7 21.9 2.07 870 6.1596 40.02 2.61 19.053
132506404 12/12/2013 7.94 451 54.8 140 41 15.3 0.211 0.07 1.53 20 1.74 1303 71.4044 182.42 53.423 26.06
132506405 12/12/2013 7.7 422 3.64 34 4 3.31 5.063 0.47 0.9 15.3 0.86 1303 4.74292 44.302 5.212 19.9359
Average
33
Metals Appendix X
Milford Upstream
Milford Downstream
132506403 132506404
Date 20/12/13 Date 20/12/13
Metals Results Results
Tested ug/l ug/l
Al27 28.8 19
Ba138 22.2 17.6
Cd111 <1 <1
Cd112 <1 <1
Cr52 4.93 5.02
Co59 <1 <1
Cu63 3.4 2.27
Cu65 3.1 2.11
Fe54 577 394
Fe57 809 594
Pb208 <1 <1
Mg24 3520 3390
Mn55 242 230
Na23 17200 15900
Ni60 1.56 1.34
Ti47 2.11 1.49
Zn66 2.99 2.36
As75 0.416 <1
Ti-147 2.11 1.49
Sb123 <1 <1
Sb121 <1 <1
34
Appendix VIII Emergency Response Procedure/Corrective action
Procedure
MILFORD WWTW
CRITICAL INCIDENT MANAGEMENT PROCEDURE
ACTION / RESPONSE IN THE EVENT OF AN INCIDENT
THIS PROCEDURE MUST BE READ IN CONJUNCTION WITH: • DONEGAL COUNTY COUNCIL PARENT SAFETY STATEMENT
• WATER & ENVIRONMENT SERVICES ANCILLARY SAFETY STATEMENT
• MILFORD WWTW SITE SPECIFIC SAFETY STATEMENT AND RISK
ASSESSMENT
35
DONEGAL COUNTY COUNCIL
CONTACT NUMBERS
WATERWORKS
INSPECTORS Liam McBride 087 9057508
AREA SUPERVISOR Thomas Friel 087 6579666
AREA ENGINEER Gerry Keeney 087 6836563
SENIOR EX.
ENGINEER Fitz Howard 087 2422664
FITTER Shaun Bradley 087 9052924
ELECTRICIAN Hugh Whoriskey 087 2543819
DCC LABORATORY
Senior Executive Chemist: Joe Ferry
087 1219339
074 9122423.
DCC LABORATORY
HUGH KERR/
MARGARET O NEILL
OFFICE
087 2705331
0872705332
074 9122787
36
EMERGENCY NUMBERS
LOCAL HOSPITAL LETTERKENNY 074 9125888
LOCAL DOCTOR
Dr Dairmuid Mee
Dr Gerard Lannon
074 9155163
GARDA SIOCHANA Letterkenny 074 9132002
HEALTH AND
SAFETY
AUTHORITY
SLIGO 071 9143942
ENVIRONMENTAL
PROTECTION
AGENCY
CASTLEBAR 094 9048400
LOUGHS AGENCY DERRY 0044 28 71342100
ALL EMERGENCIES 999 / 112
37
This Site Safety Statement should be read in conjunction with the Donegal Local Authorities
Parent Safety Statement.
The Parent Safety Statement covers the general headings and areas:
� The County Manager’s Policy Declaration
� Safety Resources Provided
� Safety Management System
� Distribution List
� Organisation Chart
� Consultation and Safety Representatives
� Safety Responsibilities / Duties of Staff
� Manner and Arrangements for Securing Health & Safety at Work
� Safety Audits
� Safety Policies / Procedures / Rules
� Emergency Plans
CONTENTS
Introduction
General Safety
1. FIRE OUTBREAK
• 1.1 GENERAL
• 1.2 LABORATORY
2. ACCIDENT:
• 1.2 FIRST AID
• 1.3 SERIOUS INJURY
• 1.4 FATALITY
• 1.5 NEAR MISS INCIDENTS
3 TRANSPORTATION/VEHICLE ACCIDENT ON SITE
• 3.1 FATALITY
• 3.2 SERIOUS INJURY
• 3.3 PROPERTY/EQUIPMENT DAMAGE ONLY
4 FALL INTO WATER (OPEN TANK OR CHAMBER) ON SITE
• 4.1 CONSCIOUS CASUALTY
• 4.2 UNCONSCIOUS CASUALTY
• 4.3 FALL INTO AERATION TANK
5 RESCUE FROM A SAFETY HARNESS WHILE WORKING AT HEIGHT
6 CONFINED SPACE RESCUE
7 EXPLOSION ON SITE
38
8 PERSON TRAPPED BY AN OBJECT
9 ELECTRIC SHOCK:
• 9.1 USE OF PORTABLE ELECTRICAL APPLIANCE
• 9.2 CONTACT WITH OVERHEAD POWER LINES
10 EXPOSURE TO TOXIC GAS (NOT CHLORINE)
11 NO WATER TO SUPPLY ESSENTAIL SAFETY EQUIPMENT
12 DISRUPTION OF PROCESS/SERVICE
13 INTRUDER ALARM ACTIVATED OUTSIDE OF NORMAL WORKING
HOURS
14 EXTREME WEATHER CONDITIONS
15 SPILL OR OVERFLOW OF SLUDGE ON SITE
16 ELECTRICTY SUPPLY FAILURE
17 ENVIRONMENTAL POLLUTION
18 RESPONDING TO ALARMS – OUT OF HOURS:
• 18.1 FIRE
• 18.2 PROCESS
• 18.3 POWER FAILURE
39
Introduction
General Safety
First Aid Qualified First Aiders are appointed to cover all activities.
A NOTICE IS POSTED LISTING THE NAMES OF QUALIFIED OCCUPATIONAL FIRST AIDERS
AND THE LOCATION OF THE FIRST AID BOX. THE QUALIFIED FIRST AID PERSONNEL FOR
THIS SITE ARE: TO BE NAMED ON SITE COPY
All treatments given must be recorded in the Accident Record Book.
A record of all medical requisitions dispensed must be kept by the First Aiders & all
treatments given must be recorded in the Accident Record Book.
It should be noted that First Aiders are not empowered to dispense analgesics, pills or
medications. Supplies of such items will not be kept in the First Aid boxes.
An advisory sign indicating the location of first aid facilities is positioned on the exterior of
the site office
1. Personal Protective Equipment
The Parent Safety Statement contains the PPE Policy and details the process for
replenishment of PPE.
The Waterworks Inspector retains a register noting issue and receipt of all PPE.
The receiver must sign to validate the issues of PPE
The Personal Protective Equipment provided to staff on site is:
� PROTECTIVE FOOTWEAR
For use at all times while at work
� HIGH VISIBILITY VEST OR JACKET
For use at all times while at work
� RIGGER GLOVES
For use when handling wood, metal, glass and other items which may cause
cuts etc,
� RUBBER GLOVES
For use when handling batteries etc,
� HARD HAT
To be worn when heavy plant is in operation on site
� EYE PROTECTION
To be worn when heavy plant is crushing wood etc,
When handling potential hazardous chemicals
� CHEMICAL SPILL KIT
For use in event of oil, chemical spills
40
FIRE OUTBREAK GENERAL
EMERGENCY POSSIBLE CAUSES APPLICABLE TO
Fire:
Occurring in specific
areas of the plant.
Could be caused by arson and
extent of fire could require the
assistance of the Fire Services
Fire cannot be safely
extinguished using fire fighting
equipment on the site
Property damage
Equipment damage
Smoke inhalation
Personal injury
Fatality
Evacuation of the plant/site
Shut down off the plant
Operations
THE DESIGNATED FIRE ASSEMBLY POINT FOR SITE IS AT
THE MAIN ENTRANCE OF THE SITE.
THIS POINT IS SIGNED WITH THE APPROPRIATE SAFETY WARNING SIGN
“ASSEMBLY POINT” WHITE LETTERING ON A GREEN BACKGROUND.
ALL PERSONS WILL BE MADE FAMILIAR WITH THE LOCATION OF THE
FIRE ASSEMBLY POINT DURING THEIR SITE SAFETY INDUCTION.
THIS SIGN MUST NOT BE OBSTRUCTED OR DEFACED.
41
IN THE EVENT OF A FIRE:
The principal objective of a Fire / Emergency Evacuation is to ensure that the site is cleared
of all personnel in the shortest possible time.
The first priority is to avoid putting persons in danger and to avoid injury or death
The Fire Officer has overall authority and responsibility during the Emergency.
The following steps should be taken in the event of an Emergency or Fire
DO NOT PANIC
• STOP WORK IMMEDIATELY AND RAISE THE NEAREST
FIRE ALARM.
• DO NOT PUT YOURSELF OR ANY OTHER PERSONS AT
RISK.
• NO PERSON IS PERMITTED TO ENTER OR SEARCH A
BURNING BUILDING/AREA FOR MISSING PERSONS OR
PERSONAL BELONGINGS.
• LEAVE THE BUILDING/AREA IMMEDIATELY BY USING
THE NEAREST FIRE EXIT.
• ENSURE THAT ANYONE WORKING WITH YOU OR NEAR
TO YOU ALSO LEAVES.
• GO TO THE DESIGNATED ASSEMBLY POINT LOCATED
AT THE MAIN ENTRANCE TO THE SITE
• CALL THE FIRE BRIGADE (IF THIS HAS NOT BEEN
DONE ALREADY)
• REMAIN THERE UNTIL YOU ARE GIVEN THE ALL
CLEAR TO RETURN TO THE SITE
THE WATERWORKS INSPECTOR WILL TAKE CHARGE OF
THE INCIDENT. YOU MUST CO-OPERATE WITH THEIR
INSTRUCTIONS.
IF THE SERVICES OF THE FIRE BRIGADE ARE NECESSARY
THE WATERWORKS INSPECTOR WILL CALL THEM.
THE WATERWORKS INSPECTOR WILL ENSURE THAT ALL
PERSONS ARE ACCOUNTED FOR AND WILL ASSIST THE FIRE
BRIGADE IN THE EVENT THAT THEY COME ON SITE.
42
1.2 DEALING WITH A FIRE IN THE LABORATORY Not relevant
2. PROCEDURE IN THE EVENT OF AN ACCIDENT
Should an accident occur on site the following applies:
A) The first priority when an accident/incident happens is not to panic, stay calm and
without putting yourself at risk determine how serious it is and if required:
(i) Give immediate assistance to the injured party and enlist the help of the nearest First
Aider.
(ii) In the event of a fatality/serious injury that requires medical treatment call the
required Emergency Service (Ambulance, Fire Brigade and if necessary the Gardai –
on 999 or 112 ) without delay, speak slowly and clearly and request which service
you need on site.
(iii) The Waterworks Inspector must have a clear account of what has happened. The
Waterworks Inspector must inform the Area Supervisor of the accident. If the injured
party has been taken to hospital, the Waterworks Inspector shall advise if their next
of kin has been contacted. If this has not happened it must be done so promptly by
the Area Supervisor.
B) The Area Supervisor and Area Engineer will ensure that the
accident is investigated and details recorded in the site accident
book and the Accident Report Form completed. C) The completed accident form must be sent to the Water & Environment
Safety Officer.
D) The Safety Officer shall discharge the duty where required to notify the Health and
Safety Authority and shall submit the appropriate IR1 or IR3 form. In the event of a
reportable accident or incident copies of the completed forms will be provide to the
Area Engineer for inclusion in the site accident file.
2.1 PROCEDURE IN THE EVENT OF A FIRST AID INCIDENT
EMERGENCY POSSIBLE
CAUSES/EFFECTS
PHASE OF
PROJECT LIKELY
TO OCCUR
Medical/First Aid
emergencies resulting from
an accident or incident on
the site
Personnel in need of medical
assistance
Personal injury
Operations
• Attend to the injured person and provide assistance
• Use the appropriate first aid facilities and get help.
• Treat the injury and determine if the injured party should be advised to seek further
medical attention from their own GP or attend the nearest A & E hospital.
43
• The Waterworks Inspector will report he accident to the Area Supervisor.
• The Area Supervisor and Area Engineer will ensure that the accident is investigated
and details recorded in the site accident book and the Accident Report Form
completed.
• The completed accident form must be sent to the Water & Environment Safety
Officer.
• The Area Supervisor & Area Engineer shall carry out an investigation of the
accident to identify cause and to ensure that adequate control measures are put in
place prevent a reoccurrence.
2.2 PROCEDURE IN THE EVENT OF A SERIOUS INCIDENT
EMERGENCY POSSIBLE
CAUSES/EFFECTS
PHASE OF
PROJECT LIKELY
TO OCCUR
Serious incident resulting in
a person receiving medical
attention and possible
detainment in hospital
Person in need of medical
assistance
Personal injury
Operations
SERIOUS INJURY:
• Stay calm and keep the injured party at rest.
• Contact the Ambulance Service immediately indicating the precise location and
extent of the incident and injuries and number of persons injured. This is important
to enable the Ambulance service to provide adequate facilities to the site to cover
the emergency.
• Attempt rescue of persons only if it safe to do so and without putting themselves or
any other persons at risk and they have the correct equipment available.
• Try and maintain contact and communication with the injured party assuring them
that help and assistance is on the way.
• Remain with the injured party and ensure someone is designated on site to meet with
the ambulance and other emergency services on their arrival at site and to guide them
to the location of the incident
• Arrange for someone to accompany the injured party in the ambulance.
• The Area Supervisor will contact the person’s next of kin.
• Ensure that the area(s) involved in the incident are secured and that nothing is
tampered with or removed from the scene until the appropriate investigations have
been made by the Water & Environment Safety Officer.
44
• The area may also need to be retained longer to allow for an inspection by the
enforcing authorities. The Water & Environment Safety Officer will advise if this is
necessary.
• Full co-operation must be given to those involved in assisting with the investigation
and details of any witnesses provided.
• Upon completion of the investigation only then can the area be returned for work to
continue.
2.3 PROCEDURE IN THE EVENT OF A FATALITY
EMERGENCY POSSIBLE
CAUSES/EFFECTS
PHASE OF
PROJECT LIKELY
TO OCCUR
Unsafe methods of working
Struck by moving or falling
object
Vehicle accident
Exposure to toxic gas or
acid.
Person(s) found dead or
seriously injured.
Fatality
Serious personal injury
Equipment damage
Property damage
Operations
Where there is an emergency on site that involves the FATALITY:
• The Waterworks Inspector must immediately contact the Gardai and the Ambulance
Services and request their presence on site. Then contact the Area Supervisor and
Area Engineer.
• The Area Supervisor must immediately contact the Health & Safety Officer and the
persons next of kin
• The Health and Safety Officer will contact the Enforcing Authority for the area.
• Secure the area of the site where the emergency has occurred until the Gardai and
Ambulance services have arrived and keep the area secure
• Do not permit any other person to enter the scene of the incident or tamper with
anything
• Provide full co-operation to all enforcement agencies in attendance to facilitate the
investigation.
• Ensure that the area(s) involved in the incident remain secured and unauthorized
access prevented until the appropriate investigations have been made.
• Ensure that details of any witnesses to the emergency have been recorded.
45
• Complete the accident book and accident report form and submit to the Health &
Safety Officer. The Health and Safety Officer will complete the necessary
notifications to the Enforcing Authority.
2.4 PROCEDURE IN THE EVENT OF A NEAR MISS
NEAR MISS
“If something happens which does not result in a reportable injury
but which clearly could have done, then it must be reported
immediately”
The Waterworks Inspector must inform the Area Supervisor of any Near Miss.
All near miss incidents that occur must be investigated by the Area Supervisor and
Area Engineer to establish cause and prevent reoccurrences.
The Near Miss Incident Report Form shall be completed, listing the actions that will be
taken to prevent reoccurrences.
The completed incident form must be submitted to the Water & Environment Health
& Safety Officer as soon as possible after the event.
3. PROCEDURE IN THE EVENT OF A TRANSPORTATION/VEHICLE
ACCIDENT
EMERGENCY POSSIBLE
CAUSES/EFFECTS
PHASE OF
PROJECT LIKELY
TO OCCUR
Transportation/Vehicle
accident
Property and / or equipment
damage
Fatality/casualties requiring
the attendance of the
Emergency services, HSA on
site
Personal injury
Operations
3.1 In the event that this type of incident results in a fatality
• The Waterworks Inspector must immediately contact the Gardai and the Ambulance
Services and request their presence on site. Then contact the Area Supervisor and
Area Engineer.
• The Area Supervisor must immediately contact the Health & Safety Officer and the
persons next of kin
• The Health and Safety Officer will contact the Enforcing Authority for the area.
• Cordon off the area immediately and prevent unauthorized access and prevent on-
lookers accumulating in the area of the incident which may also impede the rescue
attempt.
46
• No person or persons should attempt rescue of the injured party if there is a risk to
their safety
• Secure the area of the site where the emergency has occurred including the plant and
equipment until the Gardai and Ambulance services have arrived.
• Due to the equipment involved it may be necessary to bring in other assistance to lift
and remove plant and equipment that may be causing an obstruction or preventing
access to the injured party.
• Keep the area secure until all investigations have been completed.
• The equipment contributing to the accident shall be secured in a safe area to allow
for any independent tests to be undertaken.
• Complete the accident book and accident report form and submit to the Health &
Safety Officer. The Health and Safety Officer will complete the necessary
notifications to the Enforcing Authority.
• A full investigation of the incident shall be undertaken and the area returned to work
only when all investigations are complete.
47
3.2 PROCEDURE IN THE EVENT OF A TRANSPORTATION / VEHICLE
ACCIDENT
In the event that this type of incident results in serious injury:
Where the emergency involves casualties:
• Use the appropriate first aid facilities and enlist the help of a designated first aider
on the site to provide assistance to the injured party.
• Arrange for someone to call the emergency services ambulance, the fire brigade
may also be required if heavy lifting has to be undertaken. This person should meet
with the emergency services upon their arrival on site and guide them to the location
of the incident
• Attempt rescue of persons only if it safe to do so and without putting themselves or
any other persons at risk and the correct equipment is available on site to assist with
lifting or moving any obstruction.
• Try and maintain contact and communication with the injured party assuring them
that help and assistance is on the way.
• Ensure that the area(s) involved in the incident are secured and that nothing is
tampered with or removed from the scene and keep all other unauthorized persons
away from the scene of the incident
• Due to the equipment involved it may be necessary to bring in other assistance to lift
and remove plant and equipment that may be causing an obstruction or preventing
access to the injured party.
• Keep the area secure until all investigations have been completed
• The equipment contributing to the accident shall be secured in a safe area to allow
for any independent tests to be undertaken.
• The Health & Safety Officer will make the formal notification to the Enforcing
Authority.
• Full investigation of the incident shall be undertaken and area returned to work only
when all investigations are complete.
48
3.3 PROCEDURE IN THE EVENT OF A PROPERTY / EQUIPEMENT
ACCIDENT
Where the emergency involves damage to plant and property or equipment only:
• Without putting themselves or any other persons at risk ensure that the plant and/or
property or equipment is safe to approach.
• Carry out a check of what has happened and identify affected areas.
• Cordon off areas that are affected and contact the appropriate contractor to begin
clear up, repairs etc if this is necessary and where resources are not available on the
site.
• Keep the area cordoned off and prevent unauthorized access until area is safe to
return to work
Where it is deemed that plant, property and/or equipment are not safe:
• The area shall remain cordoned off
• Unauthorized persons will not be permitted access to the area
• The appropriate arrangements shall be taken to make safe the area i.e. repairs made
before the area is deemed safe to return to work.
In the event of this situation the Near Miss Incident Form shall be completed and
submitted to the Health and Safety Officer
4. PROCEDURE IN THE EVENT OF AN EMERGENCY
– FALL INTO WATER
EMERGENCY POSSIBLE
CAUSES/EFFECTS
PHASE OF
PROJECT LIKELY
TO OCCUR
Falling into Water while
working near or adjacent to
water.
Fatality
Personal injury
Operations
ANY PERSON WORKING ABOVE WATER OR ADJACENT TO WATER WHERE
THEY MAY BE AT RISK OF FALLING INTO THE WATER MUST WEAR A
PERSONAL FLOTATION DEVICE (LIFE JACKET)
4.1 CONSCIOUS CASUALTY
• In the event that a person has fallen into water and they are conscious the first person
on the scene throws the life buoy to them holding onto the end of the rope attached
to the buoy
49
• Use the rope to slowly pull the person into safety and the use the life buoy to bring
them into safety. Once they are safely out of the water, keep them warm and get first
aid help if needed.
• If rescue cannot be achieved by using the life buoy raise the alarm immediately and
get assistance do not attempt to enter the water alone.
• The person in contact with the emergency service shall meet with them on their
arrival at site and guide them to the location of the incident.
• Keep unauthorized persons away form the immediate area and maintain a clear and
unobstructed access to facilitate the rescue
• It is advisable for the person to seek medical attention in the event that they have
fallen in the water and been in the water for some time.
• If the person is fit enough to attend their own GP and they are close to the site they
should be brought here if this is not possible the person should be brought to the
nearest Hospital A&E department.
• The Area Supervisor and Area Engineer will complete the accident book and
accident report form and fax to the Health and Safety Officer.
• The Area Supervisor & Area Engineer shall carry out an investigation of the accident
to identify cause and to ensure that adequate control measures are put in place
prevent a reoccurrence.
4.2 UNCONSCIOUS CASUALTY
In the event that the person in the water is unconscious do not attempt alone as you may
put yourself in danger, get help immediately
• Get someone else to call the ambulance and fire brigade
• Put on a life jacket and only attempt to enter/wade into the water to assist the
person if you are not putting yourself at risk.
• Do not go out of your depth. If you cannot rescue the person you must come out
of the water and wait for the emergency services to provide assistance.
• Keep the area restricted and prevent unauthorized access.
• Provide full co-operation to the emergency services.
• In the event that a fatality results the Gardai must be informed and the Health and
Safety Officer shall contact the relevant Enforcing Authority.
• A full investigation of the incident shall be undertaken and area returned to work
only when all investigations are complete.
50
• The Health and Safety Officer will make the formal notification to the Health
and Safety Authority.
4.3 PROCEDURE IN THE EVENT OF A FALL INTO AERATION TANK.
Not relevant
In the event of an accident or incident the following action must be taken:
UNCONSCIOUS CASUALTY
SPEED IS ESSENTIAL TO GET THE PERSON OUT OF THE TANK AS QUICKLY
AS POSSIBLE
• Do not panic, remain calm and do not attempt to enter the tank. Switch off the aerator.
• Raise the alarm and get help from others on site to assist with the rescue.
• Immediately dial 999 or 112 and request the attendance on site of both the fire and
ambulance services – explain clearly what has occurred and provide directions to the
site.
• Do not attempt rescue if the person is not attached to a safety harness. If they are
attached to a safety harness pull the person in to the side of the tank using the safety
harness attachment.
• Do not put yourself at risk of trying to lift an unconscious person from the tank – if
necessary secure yourself with a safety harness to a fixed point and get help from
other site personnel to lift the casualty.
• If the casualty cannot be lifted out of the tank wait for the emergency services to
arrive.
• Upon arrival of the emergency services, provide assistance to them as required.
DURING RESCUE USING OTHER SITE PERSONNEL TO:
• Maintain a clear and unobstructed access to facilitate the rescue
• Get help from other persons present on site to keep all other persons not involved in
the rescue away from the scene.
ACTION AFTER THE INCIDENT:
• The Area Supervisor, Area Engineer or other responsible person shall complete the
site accident book and accident report form.
• The completed form must be submitted to the Health and Safety Officer as soon as
possible. The Health and Safety Officer shall visit the site as soon as possible after
the incident.
51
• The cause of the incident must be investigated immediately to establish cause.
Actions identified during the investigation must be implemented as soon as is
reasonably practicable to prevent reoccurrences.
5 PROCEDURE IN THE EVENT OF A FALL ARREST (RESCUE FROM A SAFETY
HARNESS)
EMERGENCY POSSIBLE
CAUSES/EFFECTS
PHASE OF
PROJECT LIKELY
TO OCCUR
FALL ARREST RESCUE
(SAFETY HARNESS) Fatality
Personal injury
Property damage
Equipment damage
Operations
• Time is critical in this situation and the person must be rescued from the harness as
quickly as possible otherwise they are at serious risk of their circulation being cut off
and a fatality may result.
• Raise the alarm on the site and get help from someone else as quickly as possible.
• Get someone else to ring both the ambulance and the fire brigade to request their
presence on site. This person should meet with the emergency services on their
arrival at site and guide them to the location of the incident.
• Use what ever equipment is available on the site such as lifting equipment or a
platform that can be moved into position under the trapped person to take their
weight
• Two persons should assist with cutting the person down from the harness. These
persons must not put themselves at unnecessary risk or at risk of falling while
assisting with bringing the person down safely.
• Once the cutting of the harness begins one of the persons assisting should move in
close to the injured party to take their weight and prevent them from falling down.
Cut the lanyard through and lower the injured party down safely to a safe location.
• Keep the person at rest and stay with them until the emergency services have arrived
and take control of the situation.
• If necessary arrange for the injured party to be accompanied to hospital. The safety
harness and any other equipment must not be tampered with or removed teed with
and are retained in a safe area for inspection.
• The area where the incident occurred shall be made secure and will not be tampered
with including the fall arrest system and all associated attachments until a full
investigation has been completed.
• The site accident book and accident report form must be completed and submitted to
the Health and Safety Officer as soon as possible.
52
• Failure of fall arrest equipment may require an investigation by the enforcing
authority and by the supplier / manufacturer of the equipment. The Health and Safety
Officer will arrange this where required.
6. EMERGENCY REQUIRING RESCUE FROM A CONFINED SPACE
EMERGENCY POSSIBLE
CAUSES/EFFECTS
PHASE OF
PROJECT LIKELY
TO OCCUR
Persons in need of a rescue
from a confined space.
Confined spaces on site
include: Sewers, sumps,
underground chambers and
manholes where there is a risk
of exposure to toxic gases
Deep water tanks including
effluent, aerated sludge
Person(s) trapped within a
confined space
Drowning, oxygen
deficiency, oxygen
enrichment
Explosion, exposure to
toxic gases
Personal injury
Fatality
Operations
In the event that persons become trapped while working in a confined space:
• Try and maintain contact with the injured party assuring them that help and
assistance is on the way. Do not enter the confined space alone
.
• Get someone to call the both the ambulance and the fire brigade as specialist lifting
equipment may be required to remove the person safely
• While waiting on the arrival of the emergency services rescue should only be
attempted if it safe to do so and using appropriate safety equipment: is on hand i.e.
Tripod and life line, winch, safety harness and full breathing apparatus worn if there
is a risk of exposure to toxic gases
• One person should enter the confined space and attach the injured party to the life
line, the person on top shall slowly winch them to safety with the person in the
confined space guiding the casualty to prevent them hitting the sides of the confined
space.
• When out safely place casualty lying down in a safe location remove the harness
attachment provide first aid assistance and remain with casualty until the emergency
services arrives and takes control of the situation. Keep the person at rest and
reassure them.
• If casualty cannot be rescued safely wait for the emergency services.
• Provide assistance to the emergency services when they arrive on site.
• Arrange for the injured party to be accompanied to hospital
• Ensure that the area(s) involved in the incident are secured and that a full
investigation has been made of the cause of the incident.
• The site accident book and accident report form must be completed and submitted to
the Health and Safety Officer as soon as possible.
53
7 PROCEDURE IN THE EVENT OF AN EXPLOSION ON SITE
EMERGENCY POSSIBLE
CAUSES/EFFECTS
PHASE OF
PROJECT LIKELY
TO OCCUR
Explosion or potential
explosion due to unsafe
working or carrying out
work in high risk areas.
Personal injury
Fatality
Property damage
Equipment damage
Operations
In the event of an explosion on the site:
• Raise the alarm and use the assistance of the other site staff to contact the
appropriate emergency services
• Remove all persons from the site immediately and direct them to a safe area that is
far away from the possibility of flying debris, glass. Ensure that all persons present
on the site are accounted for.
• Prevent all unauthorized persons from the vicinity of the incident and maintain a
clear and unobstructed access to the location of the incident
• In the event that a person(s) are injured attend to them only if safe to do so and there
is no risk of further explosion or fire.
• Anyone with serious injures must not be moved until the emergency services have
arrived and taken control of the situation.
• The only reason an injured person should be moved is in the event that their life is in
immediate danger due to the circumstances of the location and they are at further risk
of injury.
• Ensure that someone stays with the injured person until the emergency services
arrive
• Once the emergency services arrive on site assist them and if necessary arrange for
injured persons to be accompanied to hospital.
• The area where the incident occurred shall be made secure and will not be tampered
with until a full investigation has been completed.
• The site accident book and accident report form must be completed and submitted to
the Health and Safety Officer as soon as possible.
• In the event that the Enforcing Authorities need to be notified this will be done by the
Health & Safety Officer.
54
8 PROCEDURE FOR DEALING WITH PERSONS TRAPPED BY AN
OBJECT:
EMERGENCY POSSIBLE
CAUSES/EFFECTS
PHASE OF
PROJECT LIKELY
TO OCCUR
PERSON TRAPPED BY AN
OBJECT
Fatality
Personal injury
Property damage
Equipment damage
Operations
In the event of an emergency on the site that involves a person being trapped an
object:
• Raise the alarm and call the appropriate emergency services.
• If the person trapped by the object is not in any further danger do not attempt rescue
and the person should not be removed until the emergency services arrive on site.
• Ensure that someone remain with the trapped person and provides reassurance.
• If the person who is trapped is in serious danger and is in danger of suffering greater
injury, before the emergency services arrive on site, action should be taken to try and
prevent the object from causing further entrapment.
• No one should be put at unnecessary risk by trying to assist; the object should be if
possible be mechanically lifted clear and secured in a safe manner.
• Keep all other unauthorized persons away from the vicinity of the incident and
maintain a clear and unobstructed access to the location of the incident.
• Provide assistance to the emergency services when they arrive on site.
• Arrange for the injured party to be accompanied to hospital.
• The area where the incident occurred shall be made secure and will not be tampered
with until a full investigation has been completed.
• The site accident book and accident report form must be completed and submitted to
the Health and Safety Officer as soon as possible.
• The Health & Safety Officer shall undertake to notify the authority of the incident
and will advise if they are attending site.
9.1 PROCEDURE FOR DEALING WITH A PERSON WHO HAS SUFFERED AN
ELECTRIC SHOCK FROM A PORTABLE ELECTRICAL APPLIANCE:
EMERGENCY POSSIBLE
CAUSES/EFFECTS
PHASE OF
PROJECT LIKELY
TO OCCUR
55
ELECTRIC SHOCK/INJURY
FROM UNSAFE, DAMAGED
PORTABLE ELECTRICAL
APPLIANCES
Fatality
Electric shock
Fire
Personal injury
Property damage
Equipment damage
Operations
DO NOT APPROACH THE PERSON WHO HAS BEEN ELECTROCUTED UNTIL
YOU ARE CERTAIN THE AREA IS SAFE.
• The first person on site shall raise the alarm and shall contact the emergency
services. Do not provide assistance to the person if there is a risk to your own safety.
Stand on a rubber mat or stack of newspapers or another non conducting material.
• First break contact between the person and the current by shutting off the current at
the main fuse box, do not use the switch of the appliance. If this is not possible use a
wooden stick to separate the person from the appliance.
• Do not touch the person until you are sure the power supply is turned off and there is
no further risk to the person or to yourself.
• Check that the person is breathing and check for shock. Loosen any tight clothing
and keep the person warm.
• Cover any burnt area with a sterile gauze bandage or a clean cloth.
• If there is no possibility of fracture, get the person to lie down and raise and support
their legs.
• Arrange for the person to be taken to their GP or to the nearest A&E.
• The area where the incident occurred shall be made secure and will not be tampered
with until a full investigation has been completed.
• The site accident book and accident report form must be completed and submitted to
the Health and Safety Officer as soon as possible.
• The equipment shall not be returned into use until it has been checked by a
competent person and it is PAT tested and safe to use. In the event the equipment is
not safe it shall be disposed off in a safe manner.
9.2 PROCEDURE FOR DEALING WITH A PERSON WHO HAS SUFFERED AN
ELECTRIC SHOCK FROM OVERHEAD POWER LINES:
EMERGENCY POSSIBLE
CAUSES/EFFECTS
PHASE OF
PROJECT LIKELY
TO OCCUR
56
ELECTRIC SHOCK / INJURY
FROM CONTACT WITH
OVERHEAD POWER LINES
Fatality
Electric shock
Fire
Personal injury
Property damage
Equipment damage
Operations
DO NOT APPROACH THE PERSON WHO HAS BEEN ELECTROCUTED UNTIL
YOU ARE CERTAIN THE AREA IS SAFE.
• The first person on site shall raise the alarm and shall contact the emergency services.
Do not provide assistance to the person if there is a risk to your own safety.
• Arrange for someone to call the ESB Network supplier as they may be required to attend
site to turn off the power supply.
• It is likely that the person may have sustained back, head or neck injuries, proceed with
caution and handle the person with extreme care.
• Do not touch any plant or equipment that may be in contact with the power supply and
do not touch the person until you are sure there is no risk to your own safety.
• Check that the person is breathing and check for shock in the event that the person is
unconscious start resuscitating them.
• If you have no first aid knowledge follow the emergency services call taker will give
easy to follow instructions over the phone so you can increase the person’s chance of
survival until the ambulance arrives on the site.
• Loosen any tight clothing and keep the person warm and cover any burnt area with a
sterile gauze bandage or a clean cloth.
• In the event that the person is not unconscious and there is no possibility of fracture or
other injury, get the person to lie down and raise and support their legs.
• Monitor and reassure the person until medical assistance arrives.
• Remove any other unauthorized persons well away from the vicinity of the incident.
• Arrange to have the injured party accompanied to hospital.
• The area where the incident occurred shall be made secure and will not be tampered
until a full investigation has been completed.
• The site accident book and accident report form must be completed and submitted to the
Health and Safety Officer as soon as possible.
• The Health and Safety Officer shall liaise with the Health and Safety Authority for the
area and will advise if the enforcing authority are to visit the site and will arrange for the
appropriate notification to be undertaken and a copy provided on the site safety file.
10 EXPOSURE TO A TOXIC GAS
In the event that a person is exposed to a toxic gas the following action must be taken:
57
• Two persons are required to attempt a rescue. They must not put themselves at risk and
must wear chemical resistant personal protection and SCBA, when attempting to remove
the person from the exposure.
• Isolate the source of exposure.
• Speed is essential in all cases where a person has been injured or contaminated.
Irrespective of injury, medical attention must be sought.
• The ambulance service must be contacted and requested to attend site.
• Remain with the injured person keep them at rest and warm.
• If there is a risk of chemical contacting skin and casualty is conscious take them to the
nearest safety shower to drench with water.
• Using the chemical shower wash the affected areas with plenty of water. DO NOT
REMOVE CLOTHING.
• Care must be taken to prevent the spread of material from contaminated clothing.
• Keep drench with water until medical attention arrives on site.
• Arrange for the person to be accompanied to hospital
UNCONSCIOUS PERSON
Only apply artificial respiration if trained and competent to do so and use a VENT-AID
(provided in the site first aid box) to prevent risk of contamination. if breathing is retained
place casualty into the recovery position and stay with them until medical ambulance
arrives and takes control of the situation.
11 PROCEDURE IN THE EVENT THERE IS NO WATER TO SUPPLY
ESSENTIAL SAFETY EQUIPMENT
EMERGENCY POSSIBLE
CAUSES/EFFECTS
PHASE OF
PROJECT LIKELY
TO OCCUR
No water supply No water on site for supply to
safety equipment, to operate
toilets, and for drinking
purposes
Operations
Where there is an emergency on site that involves a failure in the water
supply affecting the operation of essential safety equipment and welfare
facilities the Waterworks Inspector shall:
.
58
• Carry out an inspection of the affected areas and if necessary implement a controlled
shut down of the affected areas and inform all those who are likely to be effected.
• Arrange a temporary supply of drinking water and have it available on the site until
return of normal services
• If the water supply cannot be resumed and there is no water supply to enable fire
hydrants on the site to operate, then any work on site that could result in a fire must
stop until full service has been established.
• Persons in the affected areas will be instructed by the Waterworks Inspector to stop
work and if deemed necessary will ask those at risk to remain off site until the
appropriate arrangements have been made and services are fully resumed.
• The Waterworks Inspector will ascertain if there is a direct effect on the final
effluent water leaving the site. Should this situation arise they will immediately
inform the Area Supervisor and Area Engineer. If it is a notifiable incident the
Senior Executive Engineer will notify the EPA.
• Appropriate arrangements shall be made to restore normal supplies as soon as is
reasonably practicable.
59
12 PROCEDURE IN THE EVENT OF DISRUPTION OF PROCESS/SERVICE
EMERGENCY POSSIBLE
CAUSES/EFFECTS
PHASE OF
PROJECT LIKELY
TO OCCUR
Disruption of
Process/Service
Fault could interfere with
treatment process
Operations
Where there is an emergency on site that involves a disruption in the process
Waterworks Inspector shall:
• Carry out a check of the site and identify all areas affected and the source of the
problem if it exists on the site.
• Organize a controlled shut down of the affected areas of the plant if this is required.
• The Area Supervisor shall be contacted and will remain in contact with the
Waterworks Inspector particularly if there is a direct effect on the quality of water
leaving the site.
• Once the problem has been identified and where it cannot be resolved on site the
Area Supervisor and Area Engineer shall organize the appropriate people to remedy
the situation.
• Once problem has been rectified return plant to normal operation.
• The Waterworks Inspector will carry out a further check to ensure all work processes
are operating safely and inform the Area Supervisor that services have returned to
normal and plant is fully operational.
• If it is a notifiable incident the Senior Executive Engineer shall contact the EPA.
60
13 PROCEDURE IN THE EVENT OF INTRUDER ALARM – SECURITY
BREACH OUTSIDE OF NORMAL WORKING HOURS
EMERGENCY POSSIBLE
CAUSES/EFFECTS
PHASE OF
PROJECT LIKELY
TO OCCUR
Intruder Alarm – security Personal injury
Property damage
Operations
Where there is a security breach and the Intruder Alarm has activated outside
of normal working hours, the contacts for obtaining access to the site are (in
order of which they should be contacted):
• Liam McBride 087 9057508
IN THEIR ABSENCE THE NEXT PERSON IN THE CHAIN OF REPORTING
SHALL BE CONTACTED:
• Thomas Friel AREA SUPERVISOR 087 6579666
• Gerry Keeney AREA ENGINEER 087 6836563
• Fitz Howard SEE/ AREA MANAGER 087 2422664
On receipt of receiving the alarm call, make your way to the site/plant, it is advisable to
have a torch with you DO NOT ENTER THE SITE ALONE.
Next call the local Gardai station at:
• Milford Garda Station 0749153060
• Letterkenny Garda Station 074 9167100
Provide them with a clear account of what has taken place and request
their attendance as you do not wish to enter the premises alone
DO NOT ENTER THE SITE/BUILDING ALONE IT IS POSSIBLE THAT THERE
MAY BE AN INTRUDER STILL ON THE PREMISES
Remain at a safe area until the GARDAI arrive. Upon arrival of the GARDAI,
conduct a joint search of the premises to ascertain:
• How the break in occurred (how did the intruders gain access to the premises)
• What damage (if any) has been caused to the premises and equipment etc
• What property/equipment is missing or misplaced
• Check that there has been no interference with the process of plant and equipment
Take care when undertaking checks of the area affected, there may be broken glass, debris
etc that could cause injury.
Once check has been completed, provide GARDAI with information necessary to enable
them to complete their report i.e. company details, contact persons etc.
If it is possible secure the premises, board up/close any broken windows or doors, (It may
not be possible depending upon the time the break in has occurred to obtain the
services of repair contractors, lock smiths etc if not leave it until the next morning).
Reset the intruder alarms and leave the premises.
61
The Area Engineer shall complete the incident report in conjunction with the
Waterworks Inspector (where they are involved in the incident) and forward it to the Health
and Safety Officer.
In the case of any loss or damage Head Office will notify the Groups Insurers
Any repairs required must be arranged as soon as is reasonably possible.
14 PROCEDURE IN THE EVENT OF EXTREME WEATHER CONDTIONS
EMERGENCY POSSIBLE
CAUSES/EFFECTS
PHASE OF
PROJECT
LIKELY TO
OCCUR Extreme Weather conditions Extreme weather resulting in
damage to property and/or
equipment
Operations
• Without putting themselves or any other persons at risk ensure that the area is safe to
enter.
• Contact the Area Supervisor.
• If safe to do so carry out a check of what has happened and identify affected areas.
• Cordon off areas that are affected and inform any other persons who are coming onto the
site what has occurred.
• If the situation cannot be addressed and satisfactorily dealt with on the site, the Area
Supervisor will contact the appropriate Contractor where needed to begin clear up,
repairs etc.
• The Area Supervisor may also need to contact the Fire Service to assist with clearing up
floodwaters etc.
• No person should be allowed to enter any area where they may be at risk. Only when
area has been cleared up and it is safe should persons be allowed to enter.
62
15 SPILL OR OVERFLOW OF SLUDGE ON SITE
In the event of a spill or over flow the Waterworks Inspector will take charge of the situation
and as follows:
Enlist the help of the other site operators to remove all unauthorised persons from the
affected areas.
Prevent further spill or overflow occurring.
Determine if there are adequate resources available on the site to assist with clean up if this
is not the case will agree with the Area supervisor additional resources necessary.
All persons involved in clean up must wear adequate personal protection.
All areas affected must be pumped out, cleaned down and thoroughly disinfected. Clean up
will remain in progress until all sludge products have been removed and areas affected
cleaned.
Checks must be undertaken to determine if any damage has occurred to electrical and
mechanical installations. Any equipment and installations damaged must be signed
“UNSAFE TO USE”
Where equipment and installations are damaged they must be made safe and the necessary
repairs carried out as soon as possible by a competent person to ensure minimum
disruption to the running of the plant.
All safety alarms must be checked to ensure that they are fully operational and where repairs
are necessary these must be carried out as soon as possible by a competent person.
When satisfied that the areas are clean and persons can return to work those involved in the
clean up should remove all contaminated personal protection and this should be
disposed off or laundered on the site.
SLUDGE REMOVAL FROM SITE – ROUTINE OPERATIONS
• Sludge is removed from site by approved Sludge Removal contractors.
• Samples are taken from the sludge on a regular basis to ensure that they meet
statutory compliance
16 PROCEDURE IN THE EVENT OF ELECTRICITY SUPPLY FAILURE
EMERGENCY POSSIBLE
CAUSES/EFFECTS
PHASE OF
PROJECT LIKELY
TO OCCUR
Electricity supply failure:
Caused by work carried out
on electrical systems on site
Caused externally by other
working on electrical
installations serving the site
No electricity on site
resulting in a shutdown or
electrical equipment
including safety devices
failing to operate
Affects water production on
Operations
63
site
Carry out an organized and controlled shut down of the plant if that is required and:
• Inform others working on the site of the situation.
• Check the site and identify all areas affected and locate the source of the problem.
• Isolate and make safe plant and equipment that may start automatically and without
warning. Operate a lock off and tag out policy if required and put up safety warning
signs to inform others that there is a risk.
• Organise for a competent electrician to carry out any necessary repairs.
• In the event that the electricity supply is on the main network and is a problem outside
of the plant. Contact should be made with the ESB to ascertain extent of problem and
how long it will be before full service resumes.
• Once problem has been repaired the plant should be brought back onto line in a
controlled and safe manner.
• Checks must be undertaken to confirm that all effected plant is now working safely.
• All lock out and tag outs and safety notices to be taken down.
• In the event that services cannot be restored and the problem is outside of the plant, the
Waterworks Inspector will liaise with the Area Supervisor to discuss appropriate
action.
• If events result in a notifiable incident the Senior Executive Engineer shall contact the
EPA.
17 ACTION TO TAKE IN THE EVENT OF A POLLUTION INCIDENT
Operations are carried out on site in a controlled manner to minimize the possibility of a
pollution incident occurring. These controls are monitored and maintained on site by the
Waterworks Inspector.
For the purposes of this plan a pollution incident on site may result from:
Spill or Uncontrolled Release into the Water Course
In the event that an uncontrolled release causes an affect on aquatic life and river/stream quality the EPA shall be notified through the correct reporting channels.
Odour Pollution Appropriate odour abatement and odour reduction equipment put in place for specific
incidents.
64
Noise Pollution
Designs of work equipment and plant take into consideration measures to reduce
environmental noise nuisance. Works on site are restricted so as not to present a nuisance to
neighboring residents. Environmental noise monitoring shall be undertaken in the event that
there is a concern relating to noise levels omitting from the site.
Illegal Dumping of Waste
All waste on the site is stored in skips and is removed by a reputable waste disposal
contractor. All contractors and others working on site are required to comply with site rules
relating to the storing and removal of waste.
Burning of Waste
Burning on site is strictly prohibited at all times. All persons working on this site are made
aware of this requirement.
RESPONDING TO A POLLUTION INCIDENT ON SITE
In the event of pollution incident on the site the Waterworks Inspector will take charge of
the situation immediately and will take the appropriate action necessary to:
• Stop further pollution
• Employ a clean up policy in agreement with the Area Supervisor.
• Take appropriate measures to prevent re-occurrence.
• Ensure that the relevant parties are notified of the pollution occurrence.
• Complete the pollution incident form and submit it to the Health and Safety Officer
as soon as possible.
18. RESPONDING TO ALARMS – OUT OF HOURS
WHEN RESPONDING TO AN ALARM CALL OUT OF HOURS NO OPERATOR
IS PERMITTED TO:
• ENTER A CONFINED SPACE ALONE
• PUT THEMSELVES AT RISK BY TRYING TO CARRY OUT A REPAIR
UNAIDED
• CARRY OUT ANY FORM OF REPAIR WHERE THEY MAY BE AT RISK
OF FALLING INTO A TANK, DEEP CHAMBER, WELL ETC
• ATTEMPT TO FIGHT A FIRE
65
18.1 FIRE ALARM – SMOKE OR FLAMES PRESENT
1) Upon arrival at site PROCEED WITH CAUTION and do a visual inspection from
the external of the building for any obvious signs of smoke and/or flames
2) If smoke and/or fire is observed immediately dial 99 or 112 and request the
presence of the Fire Brigade on site.
3) Go to the designated assembly point and wait for the arrival of the emergency
services
4) Contact line management and alert them of the situation.
5) Remain at the designated assembly point until the emergency services arrive and
provide them with any necessary assistance to locate:
• Turn off valves/switches
• Fire hydrants
• Water supply.
6) The Fire Brigade will take responsibility for ensuring that the fire is extinguished
before they leave the site.
7) Do not permit anyone to enter or interfere into the area where the fire has occurred,
this area should be cordoned of if possible.
8) A full examination of the fire will be carried out the next morning following the
incident and when daylight has resumed.
FIRE ALARM – FALSE ALARM
1) Upon arrival at site PROCEED WITH CAUTION and do a visual inspection from
the external of the building for any obvious signs of smoke and/or flames
2) If smoke and/or fire is NOT observed, continue to proceed with caution opening the
main door to the building.
.3) Stop and check the control panel and identify the cause of the alarm activating
4) If at any time smoke/fire occurs, LEAVE THE PREMISES IMMEDIATELY AND
RING THE FIRE BRIGADE
5) If fault can be rectified on site, proceed and reset alarm.
6) If fault cannot be rectified, then leave the premises and secure the site
7) Inform the Area Supervisor who shall arrange for the fault to be rectified as soon as
possible on the next working day.
66
18.2 PROCESS ALARMS
1) Upon arrival at site, carrying out a preliminary check of where the alarm is occurring
and what is the cause of the alarm.
2) In the event that an alarm has tripped, and there is no obvious sign of a problem,
attempt to reset the alarm.
3) In the event that the alarm fails to reset, it may be necessary to carry out a further
inspection, however this is only permissible if the Waterworks Inspector is not
putting their safety and health at risk.
4) If the cause of the alarm can be determined and it can be rectified by the Waterworks
Inspector, proceed to fix the fault and reset the alarm.
5) In the event that the fault cannot be rectified, the Operator shall leave the area
and secure the site.
6) The Operator shall notify the Area Supervisor
7) The Area Supervisor shall arrange for fault to be rectified as soon as possible on the
next working day.
18.3 POWER FAILURE - ESB
1) Upon arrival at site, the Waterworks Inspector carries out a preliminary check of
what areas are affected.
2) The Waterworks Inspector checks that the back up generator is working and that
power is supplying the site.
3) In the event of a power failure at the main supply external to the site, this remains
outside the control of Donegal County Council and therefore the ESB will need to be
contacted to:
• Alert them to the situation in the event that they are not already aware of the
problem
• Identify how soon power supply will be returned
4) The Waterworks Inspector should secure the site and leave.
5) On return to site the next morning a check is carried out to ensure that power has
been restored and all plant and equipment is checked to ensure that it is operating
safely.
POWER FAILURE – ON SITE FAULT
1) Upon arrival at site, the Waterworks Inspector carries out a preliminary check of
what areas are affected.
67
2) The Waterworks Inspector checks that the back up generator is working and that
power is supplying the site.
3) The Operator undertakes an assessment of the problem and if they are off the opinion
that the fault can be rectified, they will undertake the repair.
4) In the event that the Waterworks Inspector cannot make the repair, they leave the
area safe and secure the site.
5) The Waterworks Inspector notifies the Area Supervisor who shall arrange for repairs
to be undertaken as soon as is reasonably practicable on the next working day.
Appendix IX Public Awareness & communications Programme
Donegal County Council has put in place a Public Awareness & Communications
Programme file in relation to the Milford Waste Water Treatment Plant and can be viewed
at the offices of Donegal County Council, Letterkenny Public Services Centre Neil T Blaney
Road, Letterkenny, County Donegal.