Best Practices in Managing Project Closeout
Kurt FisherOffice of Project Assessment
Office of Science, U.S. Department of Energyhttp://www.science.doe.gov/opa/
OFFICE OF
SCIENCEAgenda
2
• Office of Science Overview • DOE Project Overview• Project Closeout
Office of Science Closeout Process Key Performance Parameters Readiness Review Transition to Operations Project Closeout Independent Project Review Hazard Assessment Report Project Closeout Report Lessons Learned Document
• Open Discussion / High – Low Closeout Exercisehttp://www.science.doe.gov/opa/
OFFICE OF
SCIENCE
Chicago Office
Roxanne Purucker
Office of the Director (SC-1)Patricia M. Dehmer (A)
Advanced ScientificComp. Research (SC-21)
J. S. Binkley
Workforce Development for Teachers/
Scientists (SC-27)
P. DehmerBasic Energy
Sciences (SC-22)Harriet Kung
Fusion EnergySciences (SC-24)
Edmund Synakowski
High EnergyPhysics (SC-25)James Siegrist
Biological & Environ. Research (SC-23)
Sharlene Weatherwax
Nuclear Physics(SC-26)
Timothy Hallman (A) Acting
04/2015
Deputy Directorfor Science Programs (SC-2)
Patricia M. Dehmer
Deputy Directorfor Resource Management (SC-4)
Jeffrey Salmon
Deputy Directorfor Field Operations (SC-3)
Joseph McBrearty
Office of Project
Assessment (SC-28)
Stephen W. Meador
Office of Budget (SC-41)
Kathleen Klausing
Office of Scientific and Tech. Info. (SC-44)
Brian Hitson
Office of SC Program Direction (SC-46)Daniel Division
Office of Grants/ Cont. Support (SC-43)Linda Shariati
Office of Information
Technology and Services (SC-45)
V. Kountouris
SC Communications & Public Affairs
(SC-47)Rick Borchett
Ames SOCynthia Baebler
Thomas Jeff. SOJoe Arango
Stanford SOPaul Golan
Pacific NWest SORoger Snyder
Princeton SOFrank Crescenzo (A)
Oak Ridge SOJohnny Moore
Fermi SOMichael Weis
Brookhaven SOFrank Crescenzo
Berkeley SOPaul Golan (A)
Argonne SOJoanna Livengood
SCIntegratedSupportCenter
Office of Safety and Security Policy
(SC-31)Matthew
D. Carroll
Office of Laboratory
Policy(SC-32)S. Jones
(A)
Human Resources & Admin.(SC-48)
Waltrunette Gardner
Small BusinessInnovationResearch(SC-29)
Manny Oliver
Oak Ridge Office
Kevin Hall
Office of Operations Program
Management(SC-33)Stephen
Trischman
3
SC Organization
OFFICE OF
SCIENCE
4
Project Process—Standard Scenario
CriticalDecisions
DefinitionInitiation Execution Closeout
Operating* Funds
Operating Funds
PEDFunds
Construction & PEDFunds
Conceptual Design
Preliminary Design
Final Design
Construction
CD-1Approve
Alternative Selectionand Cost Range
CD-4ApproveStart of
Operations or Project
Completion
CD-3Approve Start of
Construction or Execution
CD-2Approve
Performance Baseline (PB)
CD-0Approve Mission Need
• CD‐0, Approve Mission Need. There is a need that cannot be met through other than material means;
• CD‐1, Approve Alternative Selection and Cost Range. The selected alternative and approach is the optimum solution;
• CD‐2, Approve Performance Baseline. Definitive scope, schedule and cost baselines have been developed;
• CD‐3, Approve Start of Construction/Execution. The project is ready for implementation; and
• CD‐4, Approve Start of Operations or Project Completion. The project is ready for turnover or transition to operations, if applicable.
OFFICE OF
SCIENCE
5
Project Closeout
What is project closeout ?
OFFICE OF
SCIENCE
6
Project Closeout
Project Closeout is the last phase in the project lifecycle. Closeout begins when the program concludes through completion of Key Performance Parameters (KPPs) that the project has met the goals established.
CriticalDecisions
DefinitionInitiation Execution Closeout
Operating* Funds
Operating Funds
PEDFunds
Construction & PEDFunds
Conceptual Design
Preliminary Design
Final Design
Construction
CD-1Approve
Alternative Selectionand Cost Range
CD-4ApproveStart of
Operations or Project
Completion
CD-3Approve Start of
Construction or Execution
CD-2Approve
Performance Baseline (PB)
CD-0Approve Mission Need
OFFICE OF
SCIENCE
7
Project Closeout
Project closeout phases include:
• Physical Closeout / Technical Closeout – Demonstration that the project has met its completion criteria.
• Administrative Closeout – Ensuring that all project documentation has been approved and is in place.
• Financial Closeout – Contract Closeout and closure of all financial packages.
OFFICE OF
SCIENCE
8
Project Closeout
Roles and Perspectives on Project Closeout
• Project Execution / Contractor – Focus on demonstration of project completion, turnover of project deliverables.
• Program – Focus on ensuring that facilities / instruments meet the intended requirements within budget, and that necessary resources are available for operations.
• Operations – Focus on ensuring that the project has met the operational requirements, and resources are available. Also will receive the deliverables ( i.e. spares, O&M manuals, as-built drawings) for use in operations.
OFFICE OF
SCIENCE
9
SC CD-4Requirements
Verify Achievement of Key Performance
Parameters/Project Completion Criteria
OFFICE OF
SCIENCE
10
Key PerformanceParameters (KPPs)
• A KPP is defined in DOE Order 413.3B as, “A vital function, requirement or design basis, that if changed, would have a major impact on the facility or system performance.”
• KPPs are defined in the Project Execution Plan (PEP) during the project’s definition and execution phases.
• The validation of the KPPs is a key activity for demonstrating that the project has met DOE mission requirements.
OFFICE OF
SCIENCE
11
KPPs
Example : Technical Project—The project, located at xxx lab, designed, constructed, tested, and commissioned an xxx facility. The project was declared complete and the following was achieved:
Facility has completed construction of the XX building and is ready for occupancy Ion source is accelerated up to a minimum energy of xxx MeV peak for xx seconds Calculations have shown that xxx has been achieved. Four experimental facilities installed without beams.
Description of Scope
CD-2 Threshold KPP
CD-2 Objective KPP
Facility Size 175,000 SF 200,000 SF
Brightness 8 KeV 8 KeV
Spatial Resolution 1 nm 1 nm
Energy Resolution 0.1 meV 0.1 meV
Experimental Facilities 2 3
KPP Achieved at CD-4
CD-2 Threshold KPP Met or Exceeded?
200,000 SF Exceeded
8 KeV Met
1 nm Met
0.1 meV Met
3 Exceeded
OFFICE OF
SCIENCE
12
SC CD-4Requirements
Conduct Readiness to Operate Review and
Issue Project Transition to Operations Plan
OFFICE OF
SCIENCE
13
Readiness Reviews
Conduct a Readiness to Operate Review, dependent on the nature of the project undertaken. This could take the form of all or any of the following:
• Beneficial Occupancy Review • Accelerator Readiness Review (ARR)• Instrument Readiness Review (IRR)
OFFICE OF
SCIENCE
14
Transition toOperations Plan
Project Transition to Operations Plan should include activities such as:
• development of operations and maintenance manuals,• generation of as‐built drawings, • identification of operations budget, and • the procurement of any materials required for initial
operations.
Planning should include the operating organization, who will operate the facility or accept the final product.
OFFICE OF
SCIENCE
15
SC CD-4Requirements
Conduct Independent Project Review
OFFICE OF
SCIENCE
16
Project Closeout—Independent Project Review
• The Office of Science conducts an Independent Project Review or Peer Review to ensure that the KPPs have been fully validated and met.
• The IPR also functions as an opportunity to ensure that the administrative / initial financial portion of the closeout is proceeding toward turnover. Some basic questions……….
Have the KPPs been fully satisfied? Are only the necessary control accounts open? Is the proper project documentation in place? Have all project liabilities been identified?
OFFICE OF
SCIENCE
17
SC CD-4Requirements
Finalize the Hazard Analysis Report
OFFICE OF
SCIENCE
18
Hazard Analysis Report
Finalize the Hazard Analysis Report (HAR) (as appropriate)
• The preliminary HAR (PHAR) should be updated to include all current safety / hazard conditions and should be finalized and submitted for approval.
OFFICE OF
SCIENCE
19
SC CD-4Requirements
Complete DraftProject Closeout Report
OFFICE OF
SCIENCE
20
Project Closeout Report
The PCR provides documentation of the overall project performance, and the closure status of the project, contracts, and fiscal condition.
• SC requires that a Draft PCR be developed prior to the CD‐4 Independent Project Review.
• The Initial PCR should be submitted within 90 days after CD‐4 approval.
• The Final PCR should be submitted after all project costs are incurred and invoiced, and all contracts are closed.
OFFICE OF
SCIENCE
21
SC CD-4Requirements
Submit Approved CD or Equivalent Documents
to OECMFinalize in PARS IIProject Completion
Perform Final Administrative and Financial Closeout
Prepare an InitialProject Closeout Report
60 days after CD-4
Submit Lessons Learned90 days after CD-4
OFFICE OF
SCIENCE
22
Lessons Learned—Facility Start-Up
• Within 90 days from CD‐4, the Federal Project Director should submit a Lesson Learned document that should include project execution and facility startup.
• The lessons learned document should include all phases of the project, the contents can be contained with the Project Closeout Report (PCR).
OFFICE OF
SCIENCE
23
Closeout ChallengesLessons Learned
• Formulation of KPPs cannot happen too early in the project!!!
• Establishing KPPs that are challenging and effective, but not impacted by international or outside collaborations beyond the project’s control.
• All essential CD‐4 documentation needs to be submitted prior to approval of CD‐4
PCR Lessons learned ‐ CD‐4 As‐built Drawings and, O&M manuals
• Site visits are necessary to ensure project completion.
OFFICE OF
SCIENCE
24
Closeout ChallengesLessons Learned
• Ensure sufficient funds to cover all project liabilities.
• Be aware of the impacts of tradeoffs made at the end of projects, pushing work over on to operations.
• Don’t “wish the project better”, experience shows we are overly optimistic in our expectations.
• Again, formulation of KPPs cannot happen too early in the project!!!
• And finally, don’t make Closeout more complicated than it needs to be!
OFFICE OF
SCIENCE
25
Closeout “High / Low” Exercise
• The purpose of this exercise is to share real project experiences from project closeout.
• Everyone assemble in groups of three, ideally, this should include members involved in project execution, program management (project sponsor), and facility operations (one of each).
• Each individual is requested to share their one “best” and one “less than perfect” situation from their perspective, and recognize what made each situation fall into their respective categories.