christ nishotech
TRANSCRIPT
1, 06.11.2002, Producer
Storage & Distribution Systems
IDMA Workshop
Christ Water Technology Group
3, 06.11.2002, Producer
Na
oH
SMBS
CI F I
Christ Water Technology Group
4, date, SK
Storage & DistributionBasics
5, date, SK
Design Objectives
? Maintaining the quality of water within acceptable limits.? Delivering the water to the use points at the required flowrate
and temperature.? Minimising capital and operating expenses.? Minimising the time the water is held at conditions which favour
microbiological growth.? Minimising changes to water temperature.? Contacting all areas during sanitisation sterilization.
6, date, SK
Microbial Control Design Consideration
Conditions that aggravate the contaminations :
?Stagnant conditions and areas of low flow rates
?Temperatures that promote microbial growth (15-55°C)
?Poor quality supply water
7, date, SK
Microbial Control Design Consideration
Measures that alleviate Microbial Problems :
Maintaining ozone levels of 0.02ppm to 0.2ppm
?Continuous, turbulent flow
?Elevated temperatures
?Proper slope
?Smooth, clean surfaces that minimize nutrient accumulation
?Frequent draining, flushing, or sanitizing
?Air breaks in drain piping
?Ensuring no leaks in the system
?Maintaining positive system pressure
8, date, SK
Distribution Design Concept
Batch Operation (Rarely used)
?Utlizes at least two storage tanks
?One is in service to users while other is filled / tested
?Filled tank enters sevice after successful testing
?Water often drained after 24 hours
?Tank usually sanitized before refill.
9, date, SK
Distribution Design Concept
Continous operation
?Off-sets peak demand with continious make up into single tank
?System supplies users continiously while maintining quality
10, date, SK
Distribution System Design Basis
?Water quality requirement
?QA release required before use
?Continous recirculation requriments
?Limiting hydraulics
?Hot users only
?Low temperature users only
?Combination of above
11, date, SK
?Number of total low temperature users
?Hot storage desired
?Energy consumption critical
?Sanitization method
?Pressure requirements
?Future considerations
Distribution System Design Basis
12, date, SK
Distribution System Basics
?No Use point filters .
?No filters in loop.
?Loop velocity- ISPE :3 ft/sec or 0.9 m/sec
?Slopes/ Gradient – 1:100 standard paractice
?Dead Legs- <3d for ambient systems, <6d for hot systems
?Sanitary clamp connections , No threads
?Increasingly Orbital welding of SS tubes
?Complete drainablity
?SIP/CIP able.
13, date, SK
?Valves
?Gaskets
?Heat Exchangers
?Pumps
?Mechanical seals
?Connection types
System Components
14, date, SK
Regulatory Clarification to Common Industry Practices
15, date, SK
There should be no dead legs
Water scours deadleg
If D=25mm & distance X isgreater than 50mm, we havea dead leg that is too long.
Deadleg section
<2D
Flow direction arrows on pipes are important
Sanitary Valve
D
X
Dead Legs
16, date, SK
3. The water is contaminated as it passes through the valve
2. Bacteria can grow when the valve is closed
1. Ball valves are unacceptable
Stagnant water
inside valve
Water System Design
17, date, SK
1. Sanitary pumps
2. Clamps and O rings versus threaded fittings
3. Heat exchangers
4. Side arm level measuring devices areunacceptable
Water System Design
18, date, SK
Heat
? One of the most reliable methods of disinfection of water systems
Ozone
? Produced easily
? Leaves no residue
Disinfection
19, date, SK
UV 1. UV does not “sterilize”2. Flow rate critical3. Post-irradiation recontamination may be an issue4. Lamps have finite life
Other chemicals1. XO22. Halogen3. Formaldehyde
Disinfection
20, date, SK
Electrolytical Ozone
Growth likely
Growth possible
No Growth
0 0.004 0.008 0.012 0.016 0.020
Ozone concentration (ppm)
Roche, Basel (Swiss Ph. 1983)
21, date, SK
Ozone Unit
ELECTROLYTICALOZONE GENERATOR
- Highest efficiency
- Very low operational costs
- Easy to retrofit systems
- Proven Microbial Reduction
- Guaranteed functionality (100’s of references)
22, date, SK
Sanitisation - Ozone
0
10
20
30
40
50
60
70
80
90
100
110
120
130
1
Operation time
Ger
m c
ou
nt
[ cf
u/ m
l]
Action levelpurified water
Action levelwater for injection
Continuous sanitisation by ozone< 10 cfu/ml
Microbiological behaviour in ambient purified water loops with ozone ( ~20 ppb)
23, date, SK
Sanitisation - Hot water
0
10
20
30
40
50
60
70
80
90
100
110
120
130
1
Operation time
Ger
m c
ount
[ cf
u/ m
l]
Action levelpurified water
Microbiological behaviour in ambient purified water loops with periodic hot water sanitisation
Periodic sanitisation by hot water (>80°C)Accepted contamination
24, date, SK
Validation & Qualification
25, date, SK
V model ensures the quality of your system throughout the Project
Working through the V-model
Validation & Qualification
26, date, SK
Water system Project execution steps
Hand over15
Site Acceptance Tests14
Commissioning & Start-up 213
Shipment12
Factory Acceptance Tests11
Internal pre-FAT10
Commissioning & Start-up 1(Skids)9
Manufacturing8
Receiving inspections7
Software Review (office tests)6
Programming5
Purchasing4
Design3
Quality & Project Plan2
User Requirement Specification (Sales phase)1
QUALITY
CONTROL
Design Qualification
27, date, SK
-Design phase, overview
Design
» P&ID and Functional Specification (FS)
Detailed Design
» Component list
» Functional Logics (FL)
» Software Design Specification (SDS)
» Hardware Design Specification (HDS)
» Hardware Plan, circuit diagram
Design Qualification
28, date, SK
Mechanical installations according to Design specifications
Complete Welding documentation for traceability
Welding Procedure
Isometric drawing with weld numbers
Weld log
Welders‘ Certificates
Material Certificates
Orbital Machine print-outs
Boroscoping
Passivation Procedure
Welding Qualification
29, date, SK
- Factory Acceptance Tests at SUPPLIER Manufacturing sites
P&ID Inspection
?The FAT is performed according to a customer signed protocol
?All tests are documented and witnessed by the customer
?When approved the system is shipped for immediate start-up
FAT
30, date, SK
The Factory Acceptance Tests are divided into four sections and contain the following tests
Certificates
Manuals & Data sheets
Dead-legs
Components
P&ID
Mechanical & Documentation Inspections (IQ)
Analogue outputs
Analogue inputs
Digital outputs
Digital inputs
Power on / off
External cables
Circuit diagram
Hardware, electrical components
Hardware Acceptance Tests (IQ)
URS
Functional Specification
Hardware Design Spec
Software Design Spec
Software Module Design Spec
Control system programming / Code review
Software Module Test
Software Integration Test
Hardware Acceptance Test
System Acceptance Test
FAT
31, date, SK
Back-up
Passwords
Alarms
Function of the loop system, Program steps
Function of the pump, Program steps
HMI Menus
Software Version
System Acceptance Tests (OQ)
System Parameters
Operation Tests (OQ)
URS
Functional Specification
Hardware Design Spec
Software Design Spec
Software Module Design Spec
Control system programming / Code review
Software Module Test
Software Integration Test
Hardware Acceptance Test
System Acceptance Test
FAT
32, date, SK
Site Acceptance Tests
Drainability, Distribution system
Slope, Distribution system
Dead-legs, Distribution system
Air gap to drain
Components
P&ID
System Documentation
FAT Completion
Mechanical & Documentation Inspections (IQ)
Hardware operating environment
Analogue outputs, Distribution system
Analogue inputs, Distribution system
External cables, Distribution system
Emergency stop
Main switch
Hardware Acceptance Tests (IQ)
SAT
33, date, SK
Back-up
Function of the Distribution system, Program steps
Software Version
System Acceptance Tests (OQ)
Sanitisation
Disinfection
Water quality, Distribution system
System Parameters
Operation of the heat exchanger
Operation of the Ozone analyser
Operation of the conductivity sensor
Function Regulations
Operation, uv unit
Operation of the loop pump
Operation of the vent filter
Operation of the level transmitter
Leak test
Calibration of Instruments (OPTION)
Operation Tests (OQ)
The tests are always project specific to your system, which means there could be more tests for a larger system and tests could be deleted if not applicable.
SAT
34, date, SK
Validation Templates
? The templates should be developed in accordance with GMP, cGMP, GAMP and ISPE Baselines.
?Good Testing Procedure, Good Documentation Procedure and that documents are easy to follow and have a logical structure are very important.
? The templates are the base for each project, and are then worked through Project specifically to match your system exactly.
? All test protocols are sent to the customer for approval before test start
Validation
35, date, SK
Description Required Actual Result (Pass/Fail)
2. Calibration QE/QICSA 270.12.1
N/A N/A
3. System in service N/A N/A4. Function of pump P 270.12.1
N/A N/A
5. PH set-point QE/QICSA 270.12.1
Witness, Date / Initials
Comment
Tester, Date / Initials
Pass / Fail + Deviation no’s
Equipment manuals from sub-supplier.
Acceptance criteria
2. Carry out the initial calibration for the pH meter QE/QICSA 270.12.1.
3. Put the system into service according to the Operating instructions.
4. Check that pump P 270.12.1 works correctly.
5. Check that the set-point for the pH value (measured at QE/QICSA 270.12.1) is maintained.
Name of test2.4.6 Operation, NaOH dosing unit
Test procedure1. Check that the dosing unit is supplied with the correct chemicals.
6. Fill in the results in the table below.
1. Correct chemicals NaOH %
Needed document(s) / equipment
Test document format
?Name of test
? Test procedure
?Needed document(s) equipment
?Acceptance criteria
?Pass / Fail + Deviation no‘s
?Comment
? Tester, Date / Initials
?Witness, Date / Initials
Documentation
36, date, SK
The complete documentation consists of the following sections
?Design documentation (Mechanical, Electrical Hardware, Software)
?Operating instructions
?Spare part list
?Equipment documentation (Manuals & Data sheets from sub-suppliers)
?Certificates
?Welding documentation
?Validation protocols
?SW Print-outs
Documentation
37, date, SK
Benefits for Skidded systems
?This offers a fast track project were the pre-validated system is
easy to install and start-up on site ? quick PQ start.
?Validation according to GMP, cGMP and GAMP.
?Customers can review the Validation protocol templates already during the sales phase.
? supplier has its own Validation engineers to work with Protocols and tests.
?Customers are invited for FAT and can witness all tests on supplier manufacturing site.
Current Trends-skids
38, date, SK
Disinfection, distribution and monitoring unit – LOOPO ®Disinfection, distribution and monitoring unit – LOOPO ®
39, date, SK
Standard Distribution, Monitoring and disinfection Compact Unit
Front side with
? Electrolytical ozone cell? Ozone measurement? Flow meters with
contacts? Conductivity
measurement? TOC measurement as
option? Control cabinet with
remote I/O to PW plant or independent
? Completely pre-piped and pre-wired systems
40, date, SK
Backside with
? Variable speed driven distribution pump
? UV ozone destruct
? Sanitary automatic take-off valves for ozone measurement
? Cooling heat exchanger
? Waste water piping
Standard Distribution, Monitoring and disinfection Compact Unit
41, date, SK
Documentation
• All documentation included for full validation– P&ids– General assembly drawings– Electrical drawings– Layout of control panel– Functional description– Control system ladder logic– Description of systems– Manufacturer’s literature– Operating instructions– Maintenance procedures– Commissioning data
42, date, SK
Thank you very much for your attention.
Any Questions ?