current situation of nuclear power generation in...
TRANSCRIPT
The Federation of Electric Power Companies
Current Situation of Nuclear
Power Generation in Japan
The Federation of Electric Power
Companies of Japan
February 24, 2016
The Federation of Electric Power Companies
1 1 Current Situation of Nuclear Power Generation in Japan
Fukushima Daini
➊➋➌➍
Takahama ➊➋➌➍
Kashiwazaki kariwa ➊➋➌➍➎➏➐
Shika ➊➋
Tsuruga ➊➋
Mihama ➊➋➌
Ohi ➊➋➌➍
Shimane ➊➋
Genkai
➊➋➌➍
Ikata ➊➋➌
Hamaoka ➌➍➎
Tokai Daini ➊
Fukushima Daiichi
➊➋➌➍➎➏
Onagawa ➊➋➌
Higashidori ➊
Tomari ➊➋➌
● In Operation ● Under review/Inspection ● Under preparation ● To be decommissioned
As of 31 Jan., 2016
Sendai ➊➋
Due to the earthquake on March 11, 2011 and outage that followed, all 54 units were shut down in May 2012. Since then, 6 units declared decommissioning due to the accident, and 5 units declared decommissioning in March 2015. Sendai Unit 1 restarted commercial operation on September 10, 2015.
Operating Units after 3.11 in Japan
0
5
10
15
20
25
30
35
40
10 units were shutdown due
to the earthquake
Ohi 3 and 4 restarted
in July 2012
Ohi 3 and 4 went into
the outage in
September 2013
Sendai 1
restarted in
August 2015
Before 3.11
2011 2012 2013 2014 2015
Nu
mb
er o
f O
per
atin
g U
nit
s
The Federation of Electric Power Companies
2 Impact of Shutdown of Nuclear Power Stations since the Earthquake
Due to increase of burnup at thermal power stations following shutdown of all nuclear power plants after the earthquake, approximately 90% of generated energy relies on thermal power. All 3E’s were impaired.
31.0%
25.0%
46.2%
29.3%
10.6%
7.5% 28.6%
9.0%
8.5%
3.2%
1.1%
0 10 20 30 40 50 60 70 80 90 100
After the
earthquake (2014)
Before the
earthquake (2010)
Coal LNG Oil Nuclear power Hydraulic power Renewable energy (excluding hydraulic power)
All 3E’s (energy security, economy, environmental conservation) are impaired
Energy security
(reliance on fossil fuel)
(approx. 60% ⇒ approx. 90%)
Composition ratio of generated energy
Economy (increase of thermal power fuel cost)
(increase of approx. 4 trillion yen)
Environmental conservation
(increase of amount of CO2 emitted)
(increase of approx. 100 million tons of CO2)
Note: Figures in red in ( ) are comparison of FY2010 and FY2014
Reliance on thermal power increases
The Federation of Electric Power Companies
3 Energy Policy in Japan after the Earthquake
0.0
10.0
20.0
30.0
40.0
Nuclear power Oil Coal LNG Wind power (land) Solar power (mega)
Policy expenses
Accident risk response cost
CO2 measure expenses
Fuel cost
Operation maintenance cost
Additional safety measure expenses
Capital cost
○Nuclear power generation is an important base load power supply, but its ratio will be reduced as much as possible
○Restart is promoted for nuclear power stations that have conformed to new regulatory requirements
○Nuclear fuel cycle including reprocessing and use of MOX will continue to be promoted
Framework of basic energy plan (related to nuclear power) [April 2014]
Development of energy mix plan [April 2015]
○Composition ratio of power supply in 2030
Nuclear power Oil Coal LNG Renewable energy
Around 20-22% Around 3% Around 26% Around 27% Around 22-24%
For simultaneous achievement of S and 3E’s, nuclear power generation is an important base load power supply.
Cost of nuclear power generation is cheap, even when taking accident risk response cost into account.
Ratio of nuclear power generation among power supplies will be maintained at around 20-22% in FY2030.
Trial calculation of cost by power supply (trial calculation of 2014 model plant) [April 2015] (Yen/kWh)
The Federation of Electric Power Companies
4 Approach of Operators in Japan Concerning Nuclear Power
(1) Continue to use nuclear power as an
important power supply excelling in 3E’s.
(2) Promote restart of nuclear power stations
that conform to regulatory requirements, in
full-scale.
(3) Make efforts for the completion of the
reprocessing facility as there is no change in
importance of the nuclear fuel cycle.
Viewpoint of “S+3E” is important
when thinking about energy
Approach of operators in Japan concerning
“nuclear power”
Energy Security
Economy Environmental
Conservation
Safety For use of nuclear power, major premise is
safety (S)
We, the operators in Japan, continue to make efforts to use nuclear power station and to establish nuclear fuel cycle. For use of nuclear power, major premise is safety.
The Federation of Electric Power Companies
5 Years of Operation about Nuclear Power Generation in Japan (As of January 31,2016)
1966
1
1967 1968 1969 1970
3
1971
4
1972
5
1973 1974
8
1975
10
1976
13
1977
14
1978
18
1979
21
1980 1981
22
1982
24
1983 1984
27
1985
32
1986 1987
35
1988 1989
37
1990
39
1991
41
1992 1993
45
1994
48
1995
49
1996
50
1997
52
1998 1999 2000 2001 2002
53
2003 2004 2005
55
2006
56
2007 2008 2099
57
Tokai Fukushima
Daiichi-1
: Decided to be decommissioned
Over 40 years
:Applied for over 40 years operation
After 30 ~ 39 years
After 10 ~ 19 years After 20 ~ 29 years After 0 ~ 9 years
○April,2015 5 units were declared decommissioning ○March,1998
The Japan Atomic Power Company Tokai was decommissioned
○January,2009 Chubu Electric Power
Hamaoka 1,2 were decommissioned
○April,2012 TOKYO ELECTRIC POWER COMPANY
Fukushima Daiichi 1~4 were declared decommissioning →Being carried out decommissioning and contaminated water countermeasures based on medium and long term road map ○January,2014
TOKYO ELECTRIC POWER COMPANY
Fukushima Daiichi 5,6 were declared decommissioning
Tsuruga
1
Mihama
1 Mihama
2
Fukushima
Daiichi-2
Fukushima
Daiichi-3
Fukushima
Daiichi-4 Fukushima
Daiichi-6
Fukushima
Daiichi-5
Takahama
1
Takahama
2 Mihama
3
Hamaoka
1
Hamaoka
2
Hamaoka
3
Hamaoka
4
Hamaoka
5
Ohi 1
Ohi 2
Ohi 3
Ohi 4
Shimane
1
Shimane
2
Ikata 2 Ikata 1
Ikata 3
Fukushima
Daini-1
Fukushima
Daini-2
Fukushima
Daini-3
Fukushima
Daini-4
Takahama
3
Takahama
4
Sendai
1
Sendai
2
Onagawa
2
Onagawa
1
Genkai
2 Genkai
1
Genkai
3
Genkai
4
Onagawa
3
Kashiwazaki
kariwa -1
Kashiwazaki
kariwa -5
Kashiwazaki
kariwa -2
Kashiwazaki
kariwa -3
Kashiwazaki
kariwa -4
Kashiwazaki
kariwa -6
Kashiwazaki
kariwa -7 Tomari
2
Tsuruga
2
Tokai Daini
Tomari
1
Tomari
3
Shika 1
Higashidori
1 Shika 2
Commencement of commercial operation
Commencement of commercial operation
Number of Units
Number of Units
The Federation of Electric Power Companies
6 Decommissioning Schedule (Tokai Power Station)
97 98 99 00 01 02 03 04 05 06 07 08 09 10 11 12 13 15 16 17 18 19 20 21 22 23 24 25
【Japanese fiscal year】
▼Termination of operation (Mar.31)
▼Submission of reactor dismantling application (Oct.4)
Discharge and shipment of fuel
May 28 Jun.21
Reactor area dismantling
Dismantling of RPV
Preparatory work Removal of conventional facilities etc.
Removal of buildings
Actual achievement
▼Notification of charge(Jul.30)
Removal of SRUs etc.
Removal of except reactor area
▼Approval of decommissioning plan(Jun.30)
14
Reactor area safe-store
▼Notification of charge(Dec.19)
Removal of conventional facilities of each building etc.
The Federation of Electric Power Companies
7 Outline of Tokai Power Station Decommissioning Work
:Decommissioning work area
First Phase Second Phase
Removal of except reactor area Removal of except reactor area (mainly SRUs)
Third Phase
Reactor area dismantling Removal of building
Charge machine
FeedWater Pump and others
Turbine-generators and others
House Boiler and others
Cartridge Cooling Pond
and cleaning and draining of CCP
SRU: steam raising unit
Biological shield
Reactor internals & Reactor Pressure Vessel
Note: Basement and foundation of building will not be removed
House Boiler and others
Charge machine
(Figures in red were completed)
The Federation of Electric Power Companies
8 Outline of SRU Removal
【 Illustrated image of work 】 remote-operated cutting device
〔Layout of cutting device 〕 〔Primary cutting 〕 〔Transport of cut piece〕 〔Secondary cutting 〕
Install of temporary
frame and jack device
Jacking down
(tier 1-9)
Removal of temporary
frame and jack device
Cutting area
(3FL)
jack device ・SRU height:24m diameter:6m weight:750t
・‘Tier’ height :1.7~3.2m
diameter :6m
weight :54~135t thickness:54~94mm
The Federation of Electric Power Companies
9 Enhancement of Safety Improvement Measures
after the Fukushima Daiichi Accident
Scope of measures after the Fukushima Daiichi Nuclear Power
Station accident
- Accident management
measures by normal
system equipment to
avoid core damage and
containment vessel
damage caused
Desig
n b
asis B
eyo
nd
desig
n b
asis (severe accid
ent)
Mitig
ation o
f imp
act of accid
ent
Prevention of large-scale release
Prevention of damage of
containment vessel
(suppression of release /
mitigation of spread)
4th phase
Interlock, etc. Prevention of abnormality 1st phase
Detection of abnormality / shutdown system, etc. Prevention of
abnormal spread 2nd phase
Emergency core cooling system, containment vessel spray system, etc.
Prevention of core damage
Maintaining integrity of
containment vessel
Prevention of
severe core
damage
3rd phase
Prevention of human damages
Recovery of environment
5th phase
【Measures immediately
after the accident】
【Further safety improvement
measures】
Accident management
- Establishment of nuclear emergency support organization
- Emergency safety measures Securing of power supply Securing of cooling Flooding measures
【Measures before the
accident】
- Severe accident measures - Preparation of heavy
machinery for removal of debris, etc.
- Enhancement of emergency response structure
【Enhancement of design for natural events】
Disaster
prevention
- Securing of power supply
- Securing of cooling
- Anti-seismic administration building
- Filter vent facility
- Facilities for handling specific severe accidents
(Key
)
Scope of measures before the Fukushima Daiichi Nuclear Power
Station accident
- Enhancement of tornado measures
- Enhancement of earthquake measures
- Enhancement of tsunami measures
- Enhancement of fire measures
The Federation of Electric Power Companies
10
Measures immediately after the accident
Measures to Secure Power Supply and Cooling, and to Prevent Flooding (Examples of Measures by Hardware)
Emergency safety measures
Securing of power supply
Preparation of power source cars
Securing of cooling
Preparation of portable pumps and hoses
Flooding measures
Application of waterproofing seal to penetration
Currently being implemented (examples of measures)
Further safety improvement measures
Preparation of air-cooled emergency generator
Preparation of large-capacity pump truck
Replacement to watertight door
Seawater pump waterproof wall
Raising of seawall
Preparation of reserve seawater pump motor components
Anti-seismic building
Water cannon
The Federation of Electric Power Companies
11 Natural Event Measures (Examples of Measures by Hardware)
Further safety improvement measures – natural event measures
Earthquake measures (example)
(1) Seismic reinforcement of pipe support Enhance seismic support
Add seismic support
(2) Stabilization of surrounding slope
Amount of excavated earth and sand Mountaintop: 60,200m3
Hillside: 34,000m3
Tsunami measures (example)
(1) Raising of seawall (2) Installation of tide gate (3) Seawater pump
waterproof wall
[Intake side]
Enhancement of fire measures (example)
(1) Installation of sprinklers (2) Installation of fire
spread prevention wall
Installation of sprinklers
(approx. 1600 areas / 2 units)
Tornado measures (example) <Top> Steel fence
absorbs energy of flying objects
(1) Measure to protect against flying objects
<Side> Penetration is prevented with steel plate
The Federation of Electric Power Companies
12 Measures to Improve Emergency Response Structure (Examples of Measures by Software)
Measures immediately after the accident
Enhancement of emergency response
structure
○Increase of initial response
personnel
○Development of operation
assistance structure
○Enhancement of liaison and
support structure with
manufacturer
○Development of manual and
training
○Securing of communication
method that does not
breakdown, etc.
Establishment of nuclear emergency
Support Center
Transfer to nuclear emergency support
organization
Currently being implemented (examples of measures)
○24-hour on-call standby for 365 days ○Training and development of personnel ○Maintenance and management of robots and other equipment and materials, etc.
Robot operation training
Further safety improvement measures
Development as a disaster response organization with the world’s highest level of standards that is capable of diversified and high-level disaster response under high radiation dose
Small robot, small UAV Wireless heavy machinery
Wireless relay van
Collection of information, opening and closing of door
Removal of obstacles and debris
Heavy machinery control truck
The Federation of Electric Power Companies
13 Status of Review for Checking Conformity to New Regulatory Requirements
Restart
Ap
plic
atio
n fo
r perm
ission
an
d
ap
pro
val fro
m o
pera
tors
(1) Review for permission for changes
in reactor installation
(2) Review for approval of plan for construction works
(3) Review for approval of technical specifications
Prep
ara
tion
for
startu
p
(4)
Pre-service
inspection
Perm
ission
(com
pletio
n o
f rev
iew o
f (1)
)
(3)
Ap
pro
val
Review of earthquakes and
tsunami
[Design basis earthquake
ground motion]
Review of plant facilities
Rev
ised a
s
necessa
ry
Dev
elop
men
t of
dra
ft review
d
ocu
men
ts
Pu
blic
com
men
ts
(5) Procedures to gain understanding of
the local community
Revised as necessary
(2)
Ap
pro
val
Ap
plica
tion
*Takahama Units 1 and 2 applied for approval of extension of operation period to 60 years
Tom
ari 1
2 3
Ohi 3
4
Gen
kai 3
4
Tak
aham
a 3
Sen
dai 1
2
Ikata 3
Mih
ama 3
Tak
aham
a
1 2
Tak
aham
a 4
24 units applied for review for checking conformity to New Regulatory Requirements. 5 units gained permission for changes in reactor installation, 1 unit restarted operation, 2 units are undergoing pre-service inspection, and 2 units are having their plan for construction works reviewed.
Revised as necessary
BW
R u
nits
The Federation of Electric Power Companies
14 Restart status of nuclear power plants in Japan
【Restart status】
Sendai unit 1 restarted commercial operation in September 2015, and Sendai unit 2
restarted commercial operation in November 2015.
Takahama unit 3 started up the reactor (on January 29, 2016) and reached criticality
(on January 30, 2016) and connected the generator in parallel and started generating
power (on February 1, 2016) and now is preparing for commercial operation.
Takahama unit 4 finished fuel loading and now is preparing for start-up.
Takahama unit 3 Takahama unit 4
Plan for construction Aug. 4, 2015 approval Oct. 9, 2015 approval
Operational safty program
Oct. 9, 2015 approval
Pre-operational inspection
Aug. 4, 2015 applied Aug. 17, 2015 started
Oct. 14, 2015 applied Oct. 21, 2015 started
Fuel loading finished(Dec. 25~Dec. 28) finished(Jan. 31~Feb. 3)
Reactor startup Jan. 29, 2016 In Feb. 2016 scheduled
Comprehensive inspection
In late Feb. 2016 scheduled
In Mar. 2016 scheduled
The Federation of Electric Power Companies
15
Restart of
operationAug
Aug. 2
015
No
v. 2
015
Jun. 2
016
Local consent
No
v. 2
014
No
v. 2
014
Dec. 2
015
Dec. 2
015
Oct. 2
015
Technical
Specifications
May
. 2015
May
. 2015
Oct. 2
015
Oct. 2
015
Inspection
Mar. –
2015
Ju
n. –
2015
A
ug. –
2015
O
ct. –
2015
Construction
plan
authorization
Mar.
2015
May
.
2015
Aug.
2015
Oct.
2015
6m
8m
6m
8m
Approval (Review period)
Sep
.
2014
Sep
.
2014
Feb
.
2015
Feb
.
2015
Jul.
2016
6m
6m
9m
9m
8m
Ss finalized (Period)
Mar.
2014
Mar.
2014
May
2014
May
2014
Aug.
2014
Aug.
2014
Oct.
2014
Oct.
20
14
Dec.
20
14
May
2014
May
2014
Dec.
2015
Dec.
2015
Dec
2014
Jun.
2016
Jun.
2016
Dec.
20
14
Oct.
20
14
Oct.
20
14
Aug
.
20
14
Dec.
20
14
8m
8m
10m
10m
13m
13m
15m
15m
17m
29m
29m
29m
28m
28m
Application
Jul. 2
013
Jul. 2
013
Jul. 2
013
Jul. 2
013
Jul. 2
013
Jul. 2
013
Jul. 2
013
Jul. 2
013
Jul. 2
013
Mar. 2
015
Mar. 2
015
Jul. 2
013
Jul. 2
013
Jul. 2
013
Sep
. 2013
Sep
. 2013
Dec.2
013
Dec.2
013
Feb
. 2014
May
2014
Jun. 2
014
Aug. 2
014
Dec.2
014
Mar. 2
015
Jun. 2
015
No
v. 2
015
Examination
Team B C A B A C C C C D D D D B B B B A D
Plant
Sen
dai 1
Sen
dai 2
Tak
aham
a 3
Tak
aham
a 4
Gen
kai 3
Gen
kai 4
Oh
i 3
Oh
i 4
Ikata 3
Tak
aham
a 1
Tak
aham
a 2
To
mari 1
To
mari 2
To
mari 3
KK
6
KK
7
Sh
iman
e 2
On
agaw
a 2
Ham
aoka 4
To
kai D
aini
Hig
ashid
ori 1
Sh
ika 2
Om
a
Mih
ama 3
Ham
aoak
a 3
Tsu
ruga 2
Ikata 1
Oh
i 1
Oh
i 2
Gen
kai 2
Ikata 2
Fu
ku
shim
a Dain
i 2
Fu
ku
shim
a Dain
i 2
On
agaw
a 1
Fu
ku
shim
a Dain
i 3
KK
1
Fu
ku
shim
a Dain
i 4
KK
5
KK
2
Sh
ika 1
KK
3
KK
4
On
agaw
a 3
Ham
aoak
a 5
Sh
iman
e 3
※2 ※2 ※1 ※1 ※1 ※1 ※1
No application presented
yet: 19 plants
Examination teams
Plants: 4 teams A~D
Seismic ground motion: 1 team E
※1: Issue presented by fracture zone inspection within site
No. of plants
※2: NRA decided to give priority to Kashiwazaki Kariwa 6&7 by
reviewing TEPCO’s license application regarding their
facilities (not the seismic issue) first among the applications of
four utilities operating BWR reactors. NRA added that this
does not mean these two reactors will restart the earliest
among BWR plants
Progress Toward Restart of operation
The Federation of Electric Power Companies
16 Efforts Made to Improve Safety -Aiming for the World’s Highest Level of Safety-
Imp
rov
emen
t of sa
fety a
nd
reliab
ility
- On-site electric facility measures
- Cooling and water injection facility
measures
- Flooding prevention measures
- Containment vessel damage and
hydrogen explosion measures - Enhancement of disaster prevention measures
Reflection of good practices
and new knowledge inside and
outside Japan
Engage in the entire nuclear
power industry Further safety improvement measures
Before accident
Immediately after accident
Present Efforts aiming
for the world’s
highest level of
safety
Establishment of JANSI and Nuclear
Risk Research Center
Core damage is prevented even
when all 3 functions (all AC
power supply, seawater cooling
function, spent fuel pool
cooling function) are lost due
to beyond-design-basis tsunami
as it occurred at Fukushima
Daiichi Nuclear Power Station.
Emergency safety
measures
- Securing of power
supply
- Securing of cooling
- Flooding measures
etc.
Thorough safety improvement measures are implemented under a strong leadership with the determination to “continue making reforms and aim for the world’s highest level of safety”.
The Federation of Electric Power Companies
17
JANSI
Nuclear operator
Nuclear Risk Research Center
Plant manufacturer
Reflection of Good Practices and New Knowledge Inside and Outside Japan
Reflection of good practices and new knowledge inside and outside Japan
Role of JANSI and Nuclear Risk Research Center
Good practices inside and outside Japan, etc.
Continuous
improvement of safety
Suggestion and recommendation for achieving excellence through peer reviews
Excellence setting
Research result Suggestion based on research result, checking of implementation status
Proposal of improvement measures
Sharing
The Federation of Electric Power Companies
18
JANSI
Efforts of JANSI
All presidents are to support activities of JANSI under the strong sense of crisis that “there will be no future for nuclear power in Japan unless JANSI functions”.
JANSI was established in November 2012 aiming to become Japan’s version of INPO, under the determination to “never again let the Fukushima Daiichi accident occur”. Mission is “untiring pursuit of the highest standards of excellence” in
Japan’s nuclear power industry. Aim to acquire equivalency as WANO peer review. Plan to establish a structure as a self-regulation organization after 5
years of establishment.
The Federation of Electric Power Companies
19 Efforts of Nuclear Risk Research Center
Nuclear Risk Research Center (NRRC)
Operators are to commit to activities of NRRC and reflect the result in their safety improvement activities, in order to make the risk management structure more robust.
On October 1, 2014, NRRC was established as the base for research and development necessary for voluntary improvement of safety of nuclear power generation. Research concerning low-frequency external events such as
earthquakes and tsunami
Supports structuring of PRA comparable to international standards, in order to structure “good PRA” which is helpful in decision-making of operators using risk information
The Federation of Electric Power Companies
20 Conclusion
We, nuclear operators in Japan, will continue to
proactively take action aiming for world’s highest level of
safety as the ones with prime responsibility for securing
safety of nuclear power stations.
We will continue to operate nuclear power stations with
safety first policy.