dr rv ahilan th march 2018 · 2018-05-14 · loc group marine and ... •piers needed to meet the...
TRANSCRIPT
ONE PARTNER. WORLDWIDE SUPPORT一个合作伙伴。国际资源支持
LOC Group
Marine and Engineering Consultants
Established 1979
成立
400+ staff
员工
30 offices
办事处
Oil & Gas
能源
Shipping
航运
Renewables
新能源
• Established 1979 建立于1979年
• Premier marine warranty surveying firm in O&G 海上石油天然气领域主要的海事保险检验人
• No.1 marine warranty surveying firm with >30 Offshore wind farms warranted 为超过30个海上风电场执行过海事保险检验,市场份额第一
• Design engineers and analysts on >30 OWFs through sister company Longitude 通过全资子公司Longitude为超过30个海上风电项目提供过独立计算和设计服务
• Just completed the Infrastructure & Logistics scope for the Carbon Trust Floating Wind JIP for 500MW Farm. 刚刚完成了Carbon Trust Floating Wind JIP 500兆瓦的基础设施和物流范围
• Currently running the MWS on one of the largest FIDs ($37bn) taken in 2016.正在进行2016年最大的海事保险检验项目。
• Design and consultancy spanning sky to seabed in offshore wind 离岸上风电项目全套完善服务(从天空到海床的设计和咨询)
Contracting Financing and Constructiing Offshore Wind Farms - Key
Lessons Learned - Taipei - 20 March 2018
2
The Panel 專家組
Liu Ying-Ru, President, CR Classification Society
Dr Tim Camp, Director, Turbine Engineering, LOC Renewables
Tonni Bager, Principal Consultant, Head of Construction, COP
Nicolas Cazeres, Managing Director, Longitude Engineering Singapore
Koen van der Perk, Senior Vice President Commercial, Seaway Heavy Lifting
Three themes to be discussed in the Panel:專家組將討論的三個主題
Cost and technology trends & transfer of
technology
Infrastructure, logistical challenges
and interfaces
Design challenges Taiwan vs rest of the
world
LCOE/Price Trend 價格趨勢
[1] IRENA (2018), Renewable Power Generation Costs in 2017, International Renewable Energy Agency, Abu Dhabi
[2] https://loc-group.com/renewables/news/cfd-awards-dramatic-impact-of-scale-competition-and-finance-on-offshore-wind-energy/
Contracting Financing and Constructiing Offshore Wind Farms - Key
Lessons Learned - Taipei - 20 March 2018
5
Cost reduction pointers 降低成本的指針
[1] https://www.mckinsey.com/business-functions/sustainability-and-resource-productivity/our-insights/winds-of-change-why-offshore-
wind-might-be-the-next-big-thing
Turbine Technology Trends 風力發電機組科技的發展趨勢
Turbines
HAWT
Drivetrains
Scale
Downwind
VAWT
Yaw Bearings
Deck Level Gearbox
Item Units
TURBINE Rating 6MW 10MW
Rated Power MW 6 10
Air Density t/m^3 1.22E-03 1.22E-03
Rotor Diameter m 154 178 206 218
Swept Area m^2 18627 24969 33354 37407
Rated Wind Speed m/s 11.4 11.4
Max Rotor Speed RPM 11 9 8 7.5
Hub Height m 100 119 133 139
Number of Upwind Blades 3 3 3 3
Control VSIP VSIP VSIP VSIP
Drivetrain Direct Gearbox
Rotor mass t 160 231 303 333
Tower Top Mass t 560 677 733 858
Nacelle Mass t 400 446 430 526
Tower Mass t 456 628 1155 1806
Blade Mass t 28 42 66 69
Hub Mass t 76 106 105 125
Overall Mass t 1017 1305 1887 2664
Proposed Design Basis
15
1.22E-03
11.4
Gearbox/Direct
15MW Range
Wind Resource Technology Innovations 風能資源技術創新
Wind Resource
Modelling
Atmospheric & Wake
Modelling
O&G Hindcasts
MeasurementsSatellitte &
LiDAR
Foundation Technology Trends 基礎科技的發展趨勢
Foundations
Fixed
Monopile
Jacket/Tripod
GBS
Floating
Spar
Semi
Barge
TLP
Speed
Turbulence
Scale
2025-30?
Depth
Geotechnics
Natural
Periods
Contracting Financing and Constructiing Offshore Wind Farms - Key
Lessons Learned - Taipei - 20 March 2018
9
Electricity Transmission Technology Trends 輸電科技發展趨勢
Electricity Transmission
Higher Voltage
Dynamic Design
Remote Sensing
Distributed Substations
Cost/Contractual
Installation Trends 安裝趨勢
Installation
Single Unit
Semi, Spar, GBS, Barge
Self Install
Jackup to DPDeeper, Floater, Heavier, Higher
OSP: Floatovervs Modular
Decks
More Installation &
Commissioning
Crystal Ball 水晶球
Individual
Small
Specialist
Fixed
Physical
Variable
Individual
Medium
Integrated
Fixed
Physical
Variable
Farm
>10MW
Control Integrated
Floating
Remote
Dispatchable
Turbine to Farm Model
Small to Large
Component to System
Shallow to Deep
Inspection
Storage
Contracting Financing and Constructiing Offshore Wind Farms - Key
Lessons Learned - Taipei - 20 March 2018
13
Local Capability according to TWTIA, 2017本地能力根據 TWTIA, 2017
Vessels Infrastructure
• > 2 Wharves needed by 2019
• Piers needed to meet the transportation
demand for foundations
• Wharves needed for daily O&M activities
• Construction vessels
• Turbine components
• Grid connections
• Offshore substations
Claims (Ref: PO223, EWEA Offshore Copenhagen, 2015)索賠(Ref: PO223, EWEA Offshore Copenhagen, 2015)
Warnock, McMillan, Pilgrim and Shenton (2016):
Export cable failure rate is 0.07-0.5 failures/year (50km length);
Lost Production ~ £16m (300MW, 3 months) – this does not even cover the replacement/repair cost
Contracting Financing and Constructiing Offshore Wind Farms - Key
Lessons Learned - Taipei - 20 March 2018
15
Global Capacity Forecast by EY (May 2017)EY全球產能預測 (May 2017)
Countries to drop out of the Top 10 by 2024
Countries to enter Top 10
A Banker’s view additionally
identifying Canada & Poland
Contracting Financing and Constructiing Offshore Wind Farms - Key
Lessons Learned - Taipei - 20 March 2018
16
Observations 觀察
• Cost trends in offshore are already dramatic; comparison with onshore shows we ain’t
finished yet!
• Taiwan set to get into the Top 10 by 2024
• Europe did not get it right first time – witness LCOE trend; Taiwan has an opportunity to
learn from somebody else’s mistakes
• In construction phase the dominant failures have occurred with cables and foundations;
a golden opportunity exists to avoid them through relentless focus on design and
construction
• In O&M, gearbox damage dominate; leapfrogging to larger direct drive turbines could
help?
• Taiwan specific issues – typhoon & earthquakes - need focus and have no precedence
in the European experience
Panel Questions 專家提問
1. What key lessons have we learned from designing offshore wind farms form your perspective. Are these lessons easily transferable?
2. Offshore wind in Europe went through a painful learning process with LCOE rising initially – even until 2013 – but seems to have turned the corner. Does Taiwan have to go through the same pain?
3. What lessons have we learned in Europe with respect to construction/installation that we can rapidly transmit? What can we not because of local conditions?
4. We always talk about Typhoons and Earthquakes… what other issues in construction and O&M make it a challenge and an opportunity in Taiwan.
5. Has Taiwan Offshore Wind industry established guidelines for how to deal with typhoons/earthquakes in construction phase even if we have dealt with in-place performance under these conditions? Do we need these?
6. I think scale, competition and finance were keys to unlocking offshore wind costs; In scale, we have technology. Other panels have talked about what we can learn about competitive landscape and finance. What general and Taiwan specific technologies can help us push further, faster
7. Cables have been painful part of OWF – 60%-80% of claims; what recommendations will you make to help Taiwan avoid the same statistics
8. Foundations – the lessons we learned with grouted connections – are they well learned in the specifics as well as the general – that is check for errors in code and don’t extrapolate O&G without thinking?
9. Where do you see the arms race of larger and larger turbines ending up and at what timescale? Gearbox vs DD?
10. What O&M challenges will we face when we have to do major component replacement and having to lift 1000t up 150m?
11. Floating?
12. Final message to our guests today?