dr toby roberts - wj groundwater

34
Dr Toby Roberts FRENG WJ GROUNDWATER LTD Dewatering strategies for tunnels, shafts and excavations

Upload: informa-australia

Post on 11-Jan-2017

200 views

Category:

Engineering


3 download

TRANSCRIPT

Page 1: Dr Toby Roberts - WJ Groundwater

Dr Toby Roberts FRENGWJ GROUNDWATER LTD

Dewatering strategies for tunnels, shafts and excavations

Presenter
Presentation Notes
These guys are installing a wellpoint out of a tunnel, I’ll be explaining why and how later on.
Page 2: Dr Toby Roberts - WJ Groundwater

Groundwater has a habit of seeping through the best theories.Professor Michele JamiołkowskiUniversity of Turin, Italy

Presenter
Presentation Notes
…so there’s no theory in this presentation just practical solutions to real situations. Clean water ingress to a tunnel can be a pain but instability, uncontrolled ingress and associated ground loss is highly dangerous.
Page 3: Dr Toby Roberts - WJ Groundwater

Permeability range for active dewateringCIRIA: C750

ŁódźPoland

Presenter
Presentation Notes
…from CIRIA C750. Plot of drawdown and permeability which are the main drivers for selection of a dewatering technique. Range dictated by several factors including pumping constraints - wellpoints, geotechnics – vacuum needed <10-5, tricky <10-7 and economics – excessive flow.
Page 4: Dr Toby Roberts - WJ Groundwater

Excavation 20 m depthPlan size 780 m by 50/130 m60 m thick sand aquiferPermeability 1.8 x 10-4 m/s

Łódź Station Poland

Presenter
Presentation Notes
New mainline railway station being built underground with tunnel connections. The ultimate in homogeneous isotropic conditions.
Page 5: Dr Toby Roberts - WJ Groundwater

49 wells design flow 600 l/s

Presenter
Presentation Notes
A classic perimeter well arrangement comprising 49 wells with a design flow of 600 l/s.
Page 6: Dr Toby Roberts - WJ Groundwater

Top-down excavation

Presenter
Presentation Notes
Top down, ground flow cast as a top prop followed by mining below. Wells installed internally despite our advice that there is no cut-off benefit in a deep uniform aquifer. Switched to external wells as soon as data proved our numerical model results correct.
Page 7: Dr Toby Roberts - WJ Groundwater

Łódź, Poland: Water level and flow data

General dig

Max dig

15 m

Presenter
Presentation Notes
Useful drawdown / flow data set showing 15 m drawdown with peak flow 450 l/s reducing to 300 l/s after 3 or 4 months. Pumping on subsequent sections commenced part way through which was why flow dropped below 300 l/s
Page 8: Dr Toby Roberts - WJ Groundwater

Crossrail: East LondonStepney GrnCaverns

Limmo shaft

Presenter
Presentation Notes
Crossrail east to west railway which is tunnelled through central London. Dewatering mainly on the eastern section which reached through the London Clay. I have chosen some examples from 34 separate dewatering schemes to illustrate a range of strategies.
Page 9: Dr Toby Roberts - WJ Groundwater

Upper aquifer

Intermediate aquifer

Lower aquifer

Cros

srai

l

Presenter
Presentation Notes
Typical central London soil and groundwater profile. Note aquifers and impact of over abstraction. Crossrail tunnels in the London Clay and below
Page 10: Dr Toby Roberts - WJ Groundwater

Terrace Gravels

Lambeth Group

Thanet Sand

Chalk

London strata permeability ranges

Presenter
Presentation Notes
London soils cover almost the full permeability range for dewatering plus all techniques providing for an interesting test bed.
Page 11: Dr Toby Roberts - WJ Groundwater

LimmoShafts

Presenter
Presentation Notes
Second case study is The Limmo drive shaft, the larger shaft to the left. Close to the Thames as you can see. Water trasnport used for tunnel spoil disposal.
Page 12: Dr Toby Roberts - WJ Groundwater

Main Shaft: - TBM drives

-Ventilation shaft-30m i.d. 44.3m deep

-diaphragm wall to 55 m

Presenter
Presentation Notes
Page 13: Dr Toby Roberts - WJ Groundwater

100

80

60

40

20

London Clay

Lambeth Group sands

Upnor Formation/Thanet Sand

Chalk

MainShaft

Presenter
Presentation Notes
Depressurization required in the Intermediate Aquifer and Lower Aquifer Upper aquifer cut-off Intermediate cut off by D-wall: internal relief only Lower: avoid uplift failure. Required drawdown variable depending on the stage of the excavation. Max (25m) for base slab. Some reduced drawdown required during 3 year tunnelling period with no drawdown on completion of vent shaft.
Page 14: Dr Toby Roberts - WJ Groundwater

Excavation100

80

60

40

20

Presenter
Presentation Notes
Proposed scheme for shaft excavation and base slab based on pumping test data 7 external Chalk wells + 6 external Thanet wells. 3 internal Lambeth Group passive wells + further 6 Thanet Sand.
Page 15: Dr Toby Roberts - WJ Groundwater

Excavation + base slab TBM drives

Presenter
Presentation Notes
Green chalk, red Thanet Sand GWL to left hand scale mTD Blue lines flow to right hand scale: Dark blue chalk, light blue Thanet Sand Initially the Thanet Sand follows the chalk, note additional drawdown when Thanet Sand wells pumping Once excavation and base slab complete chalk decommissioned, then just Thanet passive at greatly reduced flow.
Page 16: Dr Toby Roberts - WJ Groundwater

100

80

60

40

20

Base slab complete

External wells off

Internal passive relief only

Presenter
Presentation Notes
Base slab was installed: required drawdown reduced: external wells decommissioned: internal passive relief only Big reduction in abstraction flow as chalk pumping now ceased.
Page 17: Dr Toby Roberts - WJ Groundwater

Stepney Green: SCL Cavern

17 m

Presenter
Presentation Notes
Large caverns in London Clay with Lambeth Group sands at invert at 1 to 2 bar pressure.
Page 18: Dr Toby Roberts - WJ Groundwater

Access constrained inan advancing SCL cavern

Wellpointpumps

Presenter
Presentation Notes
GI proved a continuous sand horizon across the site. Surface installations preferred as works in an advancing SCL tunnel can be very congested. Note some in-tunnel wellpoint pumping which I will explain.
Page 19: Dr Toby Roberts - WJ Groundwater

Crossrail: Stepney Grn

EBWB

45 Surface ejectors

105 tunnelwellpoints

Presenter
Presentation Notes
Surface scheme comprised 45 vertical and inclined ejector wells with wellpoints in the deeper west bound tunnel. Note pore pressure targets for east and west bound caverns.
Page 20: Dr Toby Roberts - WJ Groundwater

Fall

71

72

KIN

G J

OH

N S

TREE

T

L Twr

GAR

DEN

STR

EET

Farm

L Twr

0 5 10 15 20 25mScale

W1W2W3W4

W5W6W7W8

W9

W10

W11(location to be confirmed)

W12

W13

W14W15

W16W17

W20

W21

W22

W19

W18

W23W24W25W26

W27

W28

W29

W30

W31

W32

W33

W34

W35

W36

W37

W38

W39

W41

W43

W44

W45

W40

W42

20°

20°

20°

20°

10°

30°

20°

10°

20°10°

10°

10°

30°

20°

10°

20°

10°

30°

EB ? PM

EB ? CW

WB ? PM

WB ? CW

EB

WB

Pumpingstation

Discharge point

150mm Supply &return headermains

150mm Supply &return headermains

Pumpingstation

To discharge

Site

SCL caverns

0 25m

Inclined wells reach beyondsite boundary

Presenter
Presentation Notes
SCL caverns Constructed from d-wall shaft Site area does not cover extent of caverns Inclined wells used to achieve a perimeter ring around the structures, particularly the deeper west bound cavern
Page 21: Dr Toby Roberts - WJ Groundwater
Presenter
Presentation Notes
Installation arrangements for an ejector well inclined at 30 deg from vertical. Right hand photo shows a set of operating inclined ejector well heads.
Page 22: Dr Toby Roberts - WJ Groundwater

Surface schemes?• Congested urban area• Intermittent/thin sand channels/horizons• Short screen length in target stratum• Poor flexibility to respond to feedback

Go underground!

Presenter
Presentation Notes
This shows a drilling set-up at a planned intervention because there was a known sand horizon ahead in this case. Planned interventions used to avoid wells being destroyed by the advancing heading.
Page 23: Dr Toby Roberts - WJ Groundwater

Augur probe drilling

Presenter
Presentation Notes
Augur drilling for investigation to prove clay or where conditions uncertain. This is a typical set up for upward augur drilling. Note SGI rings to be removed for cross passage access.
Page 24: Dr Toby Roberts - WJ Groundwater

CP5 PILOT TUNNEL - GEOLOGICAL LONG SECTION SKETCH

Presenter
Presentation Notes
Augur returns logged to build up geological profile. The best geological sections were prepared immediately by hand by the onsite engineering geologists. In this case the pilot tunnel has been constructed in Clay (shown in brown) but the probe holes show that the enlargement will encounter water bearing sand (shown in yellow).
Page 25: Dr Toby Roberts - WJ Groundwater
Presenter
Presentation Notes
Drilling our of a tunnel into sand at 1 bar plus pressure requires careful planning. Essential to always be able to seal the bore rapidly under any circumstances. The strategies used included; grouted inserts, fixed stuffing box with shutoff gland, lost bit drilling for well installation. Sometimes necessary to install short sacrificial wellpoints to reduce the pressures to allow redrilling with longer well screens
Page 26: Dr Toby Roberts - WJ Groundwater

Enlarge ~11m ΦPilot ~6m Φ

SCL

Photo by Dr A. Stärk

LondonClay

Channel Sands

Liverpool St+

Whitechapel

Platform tunnels

1 bar +excess head

Presenter
Presentation Notes
At Liverpool St and Whitechapel stations platform caverns both involved pilot tunnel excavations in London Clay. This was followed by enlargement which extended in to the Lambeth Group with potential for intermittent water bearing channel sands with 1 to 1.5 bar excess head.
Page 27: Dr Toby Roberts - WJ Groundwater

Wellpoints

Dewatered sand channel

Presenter
Presentation Notes
SCL tunnel with sand channel successfully dewatered using wellpoints. Note wellpoints often destroyed by the advancing SCL tunnel: need compact, efficient, easily maintained and adaptable pumping plant.
Page 28: Dr Toby Roberts - WJ Groundwater

High flowElectric piston pumps

Low flowDMVexpumps

Wellpoints pumps

Presenter
Presentation Notes
Wellpoint pumping equipment: high efficient electric piston pumps - for higher flows; Dmvex vacuum pumps for lower flows normally used for remediation. Low power consumption ideally suited for use in a tunnel environment.
Page 29: Dr Toby Roberts - WJ Groundwater

FarringdonTBM enlargement

Sand channel at axis

Presenter
Presentation Notes
At Farringdon we had the luxury of a TBM pilot tunnel but with a sand channel at axis. The TBM tunnel was ‘blind’ so we had to pass the pumping main through he advancing face. Occasionally necessary to install replacement wellpoints as the enlargement advanced. Sometimes able to drill wells or connections from adjacent tunnels to facilitate dewatering or pump connections.
Page 30: Dr Toby Roberts - WJ Groundwater

60

BH LW9

67.12

71.2171.21

70

80

Thanet Sand

UF

LMB

LTB

mTD

EB WB

Lam

beth

Gro

up

UMB

MLH

Combined probe holes + wellpoints

Sump ejector wells

Cross passage 6

Presenter
Presentation Notes
On particular challenge was at CP6: the cross passage was in the upper Lambeth Group with a borehole just 10 m showing cohesive soils at tunnel horizon. The sump reached to the Lower Aquifer requiring an ejector well scheme. The probe drilling required around the cross passage to prove the clay. Risk of a sand channel identified tool box contingency plan.
Page 31: Dr Toby Roberts - WJ Groundwater

Compact ejector pumping stationsump ejectors

Presenter
Presentation Notes
Compact tunnel ejector pumping station incorporates tank, pumps and controls
Page 32: Dr Toby Roberts - WJ Groundwater
Presenter
Presentation Notes
Drilling upwards encountered wet sand instead of expected clay. Switched to cased lost bit drilling and wellpoint installation.
Page 33: Dr Toby Roberts - WJ Groundwater

TCBs

Scale0

LW9

East Bound

West Bound

Key: Sump ejectors Downwards probes/wellponts Upwards probes/wellpoints not installed

5m

CP6 as built: Plan View

Presenter
Presentation Notes
Plan view of the as built well array with sump ejectors plus downwards and upwards installations identified. Installations started as auger bore to get logging data and switched to cased lost bit drilling and wellpoint installation when wet sand encountered. As the pressure reduces installation becomes easier, bore control measures can be relaxed and logger data improves. Local sand channel identified at crown down to invert and fully dewatered to allow cross passage completion highest flow from centre of channel.
Page 34: Dr Toby Roberts - WJ Groundwater

Surface: vertical perimeter wellsSurface: aquifer targeted wellsSurface: inclined wellsTunnel: probingTunnel: wellpoints + ejectors

Dr Toby Roberts FRENGWJ GROUNDWATER LTD

Presenter
Presentation Notes
These case studies represent a range of strategy options for dewatering well installations ranging from: Vitally important to understand the constraints and the opportunities when developing these strategies.