Page 1: EXPEDITING THE RIGHT OF WAY PROCESS the Right...RIGHT OF WAY LIFE CYCLE •Right of Way planning begins during the Feasibility Phase of a project. •Determining the magnitude of the

EXPEDITING THE RIGHT OF WAY

PROCESS

Page 2: EXPEDITING THE RIGHT OF WAY PROCESS the Right...RIGHT OF WAY LIFE CYCLE •Right of Way planning begins during the Feasibility Phase of a project. •Determining the magnitude of the

RIGHT OF WAY LIFE CYCLE

• Right of Way planning begins during the Feasibility Phase of a

project.

• Determining the magnitude of the Right of Way Phase allows the

LDOTD Real Estate Section to allocate resources to the project

upon receiving FHWA Authorization

Page 3: EXPEDITING THE RIGHT OF WAY PROCESS the Right...RIGHT OF WAY LIFE CYCLE •Right of Way planning begins during the Feasibility Phase of a project. •Determining the magnitude of the

RIGHT OF WAY LIFE CYCLE

Page 4: EXPEDITING THE RIGHT OF WAY PROCESS the Right...RIGHT OF WAY LIFE CYCLE •Right of Way planning begins during the Feasibility Phase of a project. •Determining the magnitude of the

INCOMPRESSIBLE TIMELINES

• Property owners’ rights are protected by Federal and State Laws,

State Policy and Procedure, and LADOTD’s Real Estate Operations

Manual.

Page 5: EXPEDITING THE RIGHT OF WAY PROCESS the Right...RIGHT OF WAY LIFE CYCLE •Right of Way planning begins during the Feasibility Phase of a project. •Determining the magnitude of the

RIGHT OF WAY ACQUISITION PROCESS

Page 6: EXPEDITING THE RIGHT OF WAY PROCESS the Right...RIGHT OF WAY LIFE CYCLE •Right of Way planning begins during the Feasibility Phase of a project. •Determining the magnitude of the

P R E -A C Q U I S I T I O N A C T I V I T I E S

Page 7: EXPEDITING THE RIGHT OF WAY PROCESS the Right...RIGHT OF WAY LIFE CYCLE •Right of Way planning begins during the Feasibility Phase of a project. •Determining the magnitude of the

RETAINER CONTRACTS

• Competitive selection to retain Right of Way consultants for all

specialties.

– Appraisers and Specialty Valuation Consultants

– Title Abstractors

– Negotiation and Relocation Agents

– Asbestos Inspectors

Page 8: EXPEDITING THE RIGHT OF WAY PROCESS the Right...RIGHT OF WAY LIFE CYCLE •Right of Way planning begins during the Feasibility Phase of a project. •Determining the magnitude of the

TASK ORDERS – SECONDARY SELECTION PROCESS • Consultants are selected from our list of firms with Retainer

Contracts

• Consultants are sent a query with project specific information and

a list of questions

– Are you interested?

– Can you meet or beat our timeline?

– What is your relevant experience?

• Interested consultants who can meet our timeline are scored based

on their relevant experience.

Page 9: EXPEDITING THE RIGHT OF WAY PROCESS the Right...RIGHT OF WAY LIFE CYCLE •Right of Way planning begins during the Feasibility Phase of a project. •Determining the magnitude of the

TASK ORDERS - CONTINUED

• The final selection is based on scores for:

– Relevant Experience

– Current Right of Way projects in progress

– Projects awarded within the past twelve months

– Past performance scores from the previous three years

– Expedited timeline – if applicable

• Notice to Proceed is sent within two weeks of the request for a

consultant.

Page 10: EXPEDITING THE RIGHT OF WAY PROCESS the Right...RIGHT OF WAY LIFE CYCLE •Right of Way planning begins during the Feasibility Phase of a project. •Determining the magnitude of the

TITLE RESEARCH

• Property rights are researched prior to FHWA authorization of the

Right of Way Phase of the project.

• Determines which property rights must be acquired and who

currently holds those property rights.

Page 11: EXPEDITING THE RIGHT OF WAY PROCESS the Right...RIGHT OF WAY LIFE CYCLE •Right of Way planning begins during the Feasibility Phase of a project. •Determining the magnitude of the

QUESTIONS?

Page 12: EXPEDITING THE RIGHT OF WAY PROCESS the Right...RIGHT OF WAY LIFE CYCLE •Right of Way planning begins during the Feasibility Phase of a project. •Determining the magnitude of the

A P P R A I S A L

Page 13: EXPEDITING THE RIGHT OF WAY PROCESS the Right...RIGHT OF WAY LIFE CYCLE •Right of Way planning begins during the Feasibility Phase of a project. •Determining the magnitude of the
Page 14: EXPEDITING THE RIGHT OF WAY PROCESS the Right...RIGHT OF WAY LIFE CYCLE •Right of Way planning begins during the Feasibility Phase of a project. •Determining the magnitude of the

How can we assist

Employees and Associates

of

Engineering Firms,

Management Companies,

Public Real Estate Agency Managers,

and other firms.

Expedite the Appraisal of Property

For Real Estate Acquisition

Page 15: EXPEDITING THE RIGHT OF WAY PROCESS the Right...RIGHT OF WAY LIFE CYCLE •Right of Way planning begins during the Feasibility Phase of a project. •Determining the magnitude of the

Over the past 30+ years

of

• Appraising

• Reviewing Appraisals

• Setting up Appraisal Projects

• Reviewing Appraisal Plans

Several factors have been found

to expedite the process

and avoid delays

Page 16: EXPEDITING THE RIGHT OF WAY PROCESS the Right...RIGHT OF WAY LIFE CYCLE •Right of Way planning begins during the Feasibility Phase of a project. •Determining the magnitude of the

EXPEDITING THE APPRAISAL PROCESS “PROJECT PL ANNING PRIOR TO APPRAISAL ACTIVITIES AND AREAS THAT MAY CAUSE DEL AYS ”

• The Review Appraiser should make visits to the project in order to

provide recommendations that may reduce acquisition cost.

• Current Title Data – Title Data that is outdated results in map

changes late in the appraisal process

• Current Right of Way Maps – Right of Way Maps need to reflect

any new title data, so as to eliminate map changes late in the

appraisal process

Page 17: EXPEDITING THE RIGHT OF WAY PROCESS the Right...RIGHT OF WAY LIFE CYCLE •Right of Way planning begins during the Feasibility Phase of a project. •Determining the magnitude of the

PREPARATION OF A PROJECT COST ESTIMATE • The appraisal unit provides a Cost Estimate in order to determine the

anticipated cost of the project.

• The Project Cost Estimate should contain:

– The estimated cost of the land and improvements in the right of way

– Potential damages

– Relocation costs

– Consultant service fees

– Legal fees

Page 18: EXPEDITING THE RIGHT OF WAY PROCESS the Right...RIGHT OF WAY LIFE CYCLE •Right of Way planning begins during the Feasibility Phase of a project. •Determining the magnitude of the

CONSULTANT SCOPE OF WORK

• The scope of work is prepared by the Review Appraiser outlining each

appraiser’s assignment.

• Acquisition Types

– Partial acquisition remainder unaffected

– Partial acquisition remainder is affected (before and after appraisal)

– Total acquisition

• The scope of work should show the parcels requiring relocation.

• The scope of work should show the appraisers and any specialty consultants

and their fees.

• The scope of work should have a statement that the appraiser must meet with

the owner and the relocation agent.

Page 19: EXPEDITING THE RIGHT OF WAY PROCESS the Right...RIGHT OF WAY LIFE CYCLE •Right of Way planning begins during the Feasibility Phase of a project. •Determining the magnitude of the

CONSULTANT SCOPE OF WORK - CONTINUED • The owner and tenant-occupied parcels should always be

completed first in order to allow for relocating the occupants.

• The start of construction could be delayed until the owners can be

relocated to new housing.

• Relocation guidelines require that we allow 90 day from the date of

the offer before we can require the occupants to vacate the

property.

Page 20: EXPEDITING THE RIGHT OF WAY PROCESS the Right...RIGHT OF WAY LIFE CYCLE •Right of Way planning begins during the Feasibility Phase of a project. •Determining the magnitude of the

CONSULTANT SCOPE OF WORK - CONTINUED • Valuation of properties that may exceed $30,000 should be

assigned two appraisers for that parcel.

• If the second appraiser is hired toward the end of the project when

negotiation becomes eminent, two problems can develop:

– The second appraiser’s value may exceed the first offer, requiring restarting

the negotiation process.

– A new offer may have to be made and time must be allowed for the owner

to consider the offer. This delay may force a change in the time to complete

the project acquisition process.

Page 21: EXPEDITING THE RIGHT OF WAY PROCESS the Right...RIGHT OF WAY LIFE CYCLE •Right of Way planning begins during the Feasibility Phase of a project. •Determining the magnitude of the

PROPERTY OWNERS’ NOTIFICATION “APPRAISAL ACTIVITIES BEGIN”

• The Uniform Act requires that the property owner (or his designated representative)

be given the opportunity to accompany the appraiser during inspection of the

property. The purpose of this requirement is to ensure that the owner has the

opportunity to advise the appraiser of features of the property that might impact the

valuation of the property as well as allow the owner to identify features that are not

obvious to the appraiser. The appraiser must offer the owner the opportunity to

accompany him/her during the inspection of the property.

• The earlier the letter is mailed to the owner, the earlier the appraiser can complete

the appraisal. It is important to provide the appraiser contact information that allows

him to begin the appraisal as early as possible.

• Failure to notify the owner could result in having to go back and meet with the owner

later and delay negotiations.

Page 22: EXPEDITING THE RIGHT OF WAY PROCESS the Right...RIGHT OF WAY LIFE CYCLE •Right of Way planning begins during the Feasibility Phase of a project. •Determining the magnitude of the

PROPERTY INSPECTION

• A meeting between the appraiser and the relocation agent is

essential with the property owner.

– Determination of fixtures and personal properties

– Determination of what will be relocated and what will be acquired

– Opportunity for the property owner to relay his/her concerns, as well as

provide any special features regarding his property

– The meeting with the property owner should include all of the parties that

will be meeting with the property owner. Having multiple individual

appointments causes delays in the acquisition process.

Page 23: EXPEDITING THE RIGHT OF WAY PROCESS the Right...RIGHT OF WAY LIFE CYCLE •Right of Way planning begins during the Feasibility Phase of a project. •Determining the magnitude of the

CHANGES TO THE ASSIGNMENT

• Should be done without delay

• Can affect delivery of the required appraisal

• Meeting with the property owner may result in additional changes

Page 24: EXPEDITING THE RIGHT OF WAY PROCESS the Right...RIGHT OF WAY LIFE CYCLE •Right of Way planning begins during the Feasibility Phase of a project. •Determining the magnitude of the

A P P R A I S A L R E V I E W

Page 25: EXPEDITING THE RIGHT OF WAY PROCESS the Right...RIGHT OF WAY LIFE CYCLE •Right of Way planning begins during the Feasibility Phase of a project. •Determining the magnitude of the

THE ROLE OF THE REVIEW APPRAISER • Outlines and implements the Scope of Work for the project

• Appraisal Plan

• Appraisal Forms

• Appraisal Plan Process

• The Appraisal

• The Review Process

Page 26: EXPEDITING THE RIGHT OF WAY PROCESS the Right...RIGHT OF WAY LIFE CYCLE •Right of Way planning begins during the Feasibility Phase of a project. •Determining the magnitude of the

QUESTIONS?

Page 27: EXPEDITING THE RIGHT OF WAY PROCESS the Right...RIGHT OF WAY LIFE CYCLE •Right of Way planning begins during the Feasibility Phase of a project. •Determining the magnitude of the

N E G O T I AT I O N

Page 28: EXPEDITING THE RIGHT OF WAY PROCESS the Right...RIGHT OF WAY LIFE CYCLE •Right of Way planning begins during the Feasibility Phase of a project. •Determining the magnitude of the

NEGOTIATION

• Certain procedural time protocols must be followed as set by

Federal Law and State Policy and Procedure

• Time required to acquire all property rights needed for a project

can vary from six months to several years

Page 29: EXPEDITING THE RIGHT OF WAY PROCESS the Right...RIGHT OF WAY LIFE CYCLE •Right of Way planning begins during the Feasibility Phase of a project. •Determining the magnitude of the

THE RIGHT OF WAY PHASE DOES NOT BEGIN UNTIL CERTAIN REQUIREMENTS ARE MET:

• Environmental clearance has been received

• Right of Way Maps have been finalized

• Funding is in place

Page 30: EXPEDITING THE RIGHT OF WAY PROCESS the Right...RIGHT OF WAY LIFE CYCLE •Right of Way planning begins during the Feasibility Phase of a project. •Determining the magnitude of the

KEY ACQUISITION STEPS

• Appraisal

• Negotiation

• Relocation Assistance, when applicable

• Closeout

• Expropriation, where property cannot be acquired through

negotiation

• Certification

Page 31: EXPEDITING THE RIGHT OF WAY PROCESS the Right...RIGHT OF WAY LIFE CYCLE •Right of Way planning begins during the Feasibility Phase of a project. •Determining the magnitude of the

NEGOTIATION

• Once the appraisal is complete, the negotiating agent is provided with a copy of the appraisal

and the appraisal review sheet.

• The agent will become familiar with the acquisition facts, including:

– Is there an uneconomic remainder?

– Is the parcel improved?

– Is there relocation on this parcel?

– Are there any other mitigating factors that may impede negotiation?

Page 32: EXPEDITING THE RIGHT OF WAY PROCESS the Right...RIGHT OF WAY LIFE CYCLE •Right of Way planning begins during the Feasibility Phase of a project. •Determining the magnitude of the

INITIATION OF NEGOTIATIONS • Property owners residing within the State of Louisiana are offered the opportunity to meet in

person with the negotiating agent.

• Owners are presented with a Just Compensation Offer Package

– The just compensation offer letter

– The summary of just compensation

– The retention value of any improvement

– The proposed Act of Sale

– A copy of the right of way maps showing the property they own and what the Department intends to

acquire

– A copy of the construction plan sheet showing their property

– A copy of the Department’s brochure entitled Acquisition of Right of Way and Relocation

Assistance

– Relocation assistance offers, if applicable

Page 33: EXPEDITING THE RIGHT OF WAY PROCESS the Right...RIGHT OF WAY LIFE CYCLE •Right of Way planning begins during the Feasibility Phase of a project. •Determining the magnitude of the

CONTINUING NEGOTIATIONS

• Federal Law requires that a property owner must be allowed a

minimum of 30 days to consider the offer

• The owner may accept the offer, reject the offer or submit a

counter-offer for the Department to consider

• Any property remainders that were determined to uneconomic to

the property owner are addressed

Page 34: EXPEDITING THE RIGHT OF WAY PROCESS the Right...RIGHT OF WAY LIFE CYCLE •Right of Way planning begins during the Feasibility Phase of a project. •Determining the magnitude of the

AMICABLE ACQUISITION

• Once an offer or counter-offer is accepted, the property owner

executes the Act of Sale pursuant to the requirements of Louisiana Law

• The negotiation agent will ensure that the property is free of

encumbrances or that the Department will be able to obtain the

necessary partial releases

• An acquisition check is then requested and delivered to the property

owner

• The agent then delivers the acquisition deed to the Parish Clerk of

Court for recordation

Page 35: EXPEDITING THE RIGHT OF WAY PROCESS the Right...RIGHT OF WAY LIFE CYCLE •Right of Way planning begins during the Feasibility Phase of a project. •Determining the magnitude of the

EXPROPRIATION

• Amicable acquisition may not be possible

– Title issues

– Rejection of the offer

– Other issues

• When amicable acquisition is not possible, the negotiating agent will

advise the Real Estate Region Manager who will make a

recommendation to expropriate the ownership

Page 36: EXPEDITING THE RIGHT OF WAY PROCESS the Right...RIGHT OF WAY LIFE CYCLE •Right of Way planning begins during the Feasibility Phase of a project. •Determining the magnitude of the

CERTIFICATION

• When all required properties have been

acquired, a right of way Certification Letter is

prepared to be forwarded to the Federal

Highway Administration

Page 37: EXPEDITING THE RIGHT OF WAY PROCESS the Right...RIGHT OF WAY LIFE CYCLE •Right of Way planning begins during the Feasibility Phase of a project. •Determining the magnitude of the

EARLY ACQUISITION

• Large or complex projects

• Projects involving multiple relocations of residential and/or non-

residential displacees

• Environmental approval and/or Final Right of Way Maps are delayed

• House are available for sale on the market on or near the corridor

• Property owners in the corridor voluntarily approach the agency

• Corridor preservation to prevent development

Page 38: EXPEDITING THE RIGHT OF WAY PROCESS the Right...RIGHT OF WAY LIFE CYCLE •Right of Way planning begins during the Feasibility Phase of a project. •Determining the magnitude of the

QUESTIONS?

Page 39: EXPEDITING THE RIGHT OF WAY PROCESS the Right...RIGHT OF WAY LIFE CYCLE •Right of Way planning begins during the Feasibility Phase of a project. •Determining the magnitude of the

R E L O C A T I O N P L A N N I N G A N D A S S I S T A N C E U N D E R T H E U N I F O R M R E L O C A T I O N A C T

Page 40: EXPEDITING THE RIGHT OF WAY PROCESS the Right...RIGHT OF WAY LIFE CYCLE •Right of Way planning begins during the Feasibility Phase of a project. •Determining the magnitude of the

UNIFORM RELOCATION ACT (URA) • Uniform Relocation Assistance and Real Property Acquisition Policies Act of

1970, as amended

• Applies to all Federally Funded Projects

• Protects the Right of Property Owners

• Provides Assistance to Displaced Persons

• To have uniform, fair and equitable treatment of persons from whom real

property is acquired or for persons displaced on a federally funded project

• To treat individuals fairly, equally and consistently

• For Agencies to act efficiently and in a cost effective manner

Page 41: EXPEDITING THE RIGHT OF WAY PROCESS the Right...RIGHT OF WAY LIFE CYCLE •Right of Way planning begins during the Feasibility Phase of a project. •Determining the magnitude of the

RELOCATION PLANNING

Page 42: EXPEDITING THE RIGHT OF WAY PROCESS the Right...RIGHT OF WAY LIFE CYCLE •Right of Way planning begins during the Feasibility Phase of a project. •Determining the magnitude of the

RELOCATION PLANNING

• Begins early in the developmental process

• Minimizes adverse impact to displaced persons

• Expedites program or project completion

• Occurs at various project times

– Early Project Planning Stage

– Environmental Assessment

– Project Implementation

Page 43: EXPEDITING THE RIGHT OF WAY PROCESS the Right...RIGHT OF WAY LIFE CYCLE •Right of Way planning begins during the Feasibility Phase of a project. •Determining the magnitude of the

RELOCATION PLANNING – CONTINUED

• Estimate the:

– Number of households

– Availability of comparable replacement dwellings

– Number of businesses

– Availability of replacement business sites

• Identify special relocation services needed

• Housing of Last Resort

Page 44: EXPEDITING THE RIGHT OF WAY PROCESS the Right...RIGHT OF WAY LIFE CYCLE •Right of Way planning begins during the Feasibility Phase of a project. •Determining the magnitude of the

RELOCATION TOOLS

• Temporary moves

• Protective rent

• Advance relocation

• Purchasing vacant properties

Page 45: EXPEDITING THE RIGHT OF WAY PROCESS the Right...RIGHT OF WAY LIFE CYCLE •Right of Way planning begins during the Feasibility Phase of a project. •Determining the magnitude of the

THE RELOCATION PROCESS

• Collect and verify data during the planning process

• Identify specific site or replacement unit

• Issue Eligibility Notice or Nondisplacement Notice

• Move Occupants

• Approve and pay relocation and/or displacement claims

Page 46: EXPEDITING THE RIGHT OF WAY PROCESS the Right...RIGHT OF WAY LIFE CYCLE •Right of Way planning begins during the Feasibility Phase of a project. •Determining the magnitude of the

CHALLENGES & ISSUES

• Must be Decent, Safe & Sanitary (DS&S)

• Must be comparable and “make them whole”

• What’s suitable may be larger than what they are currently living in

• New Construction or model required

• Occupants may be under-housed or pay little or no rent

• May have large storage facilities or major external attributes

• Individual needs – Transportation, Health Issues, Accessibility, Frail or Diminished Capacity

• Social Issues

• Zoning Issues

• Multiple family units in a house – Cannot relocate to separate locations

• Hard to find comparable housing that is equivalent and functional

Page 47: EXPEDITING THE RIGHT OF WAY PROCESS the Right...RIGHT OF WAY LIFE CYCLE •Right of Way planning begins during the Feasibility Phase of a project. •Determining the magnitude of the

QUESTIONS?