    B. CASING/SCREEN & ACCESSORIES INSTALLATION

    a. Supply & Installation of Materials:

    6mm thick x 250mm

    x6.00m. Spirally Welded Steel Casing 4 pcs. 8,000.00

    6mm thick x 250mm

    x3.00m. Spirally Welded Steel Casing 1 pcs. 5,000.00

    6mm thick x 250mm

    x1.00m. Spirally Welded Steel Casing 1 pcs. 3,000.00

    250mm

    x 6.00m Stainless Wirewound Screen, Slot 40 2 pc.

    4mm thick x 400mm

    x 6.00m. Steel Casing (Conductor pipe) 3 pcs. 18,000.00

    Casing Centralizer 6 pcs. 500.00

    Pea Gravel (10-15) 4 m3

    5,950.00

    50mm x 6.00 Meter G.I. Pipe, Sch. 40 3 pcs. 1,940.00

    50mm

    x 1.00 Meter G.I. Short Pipe, Sch. 40 1 pc. 250.00

    50mm

    G.I. Cap 1 pc. 100.00

    Cement 60 bags 265.00

    15mm Thick x 500mm

    Steel Well Head Cap 1 unit 2,000.00

    Washed Sand 0.5 m3

    650.00

    Gravel 1 m3

    650.00

    Welding Rod, 6011,1/8" 15 kgs. 180.00

    Pilojel Bentonite 1000 kgs. 15.00

    Hemaxethaphosphate (Polyphospate) 100 kgs. 100.00

    b) Drilling Rig Equipment ( 8 Hours of Operation per day)

    to include Mapower (1-Rig Operator, & 4-Laborers);

    Fuel, Oil & Lubricants 3 days 3,000.00

    c) Welding Machine with Genset 3 days 1,500.00

    C. WELL DEVELOPMENT & TESTING

    Block Surging (including bailing out of sediments)

    Pump Surging

    Constant Discharge Rate Pumping

    Step-Drawdown Test ( 3 steps)

    Use of Equipment/others:

    a) Block Surging ( Including bailing out of sediments) 24 Hrs. 1,000.00

    Use of Equipment/others:

    Drilling Rig Equipment ( 8 Hours of Operation per day)

    to include Mapower (1-Rig Operator, & 4-Laborers);

    Fuel, Oil & Lubricants

    Equipment's use Contingencies

    b) Pump Surging ( 8hrs of operation per day) 8 Hrs. 500.00

    c) Recovery Test 1 Test 500.00

    d) Step-Drawdown Test ( 3 Steps) 1 Test 1,000.00

    e) 24 hours Constant Discharge Rate Pumping Test:

    Submersible Pumping Equipment & accessories up to the

    desired pump setting with motor capacity of 7.5Hp or

    greater, complete with motor control & accessories.

    Generating Set for pumping unit power supply. 24 Hrs. 1,500.00

    D. Cement Grouting(15Meters Depth) & Installation of 19mm thick

    x 350mm

    Well Head Steel Cap 1 days 1,500.00

    E. DEMOBILIZATION 1 days 5,000.00

    TOTAL COST OF ITEM II

    Price & Physical Contingencies

    Value Added Tax

    TOTAL COST OF ITEM II

    Prepared by:

    MARL BENEDICT C. REYES

    Mechanical Engineer

    DIREC COS

    TOTAL PROJECT COST

  • 8/12/2019 Ezt Drilling

    3/30

  • 8/12/2019 Ezt Drilling

    4/30

    P

    Total

    5,000.00

    5,000.00

    100,000.00

    105,000.00

    65,000.00

    3,000.00

    1,500.00

    1,500.00

    1,450.00

    3,000.00

    12,000.00

    25,000.00

    327,450.00

    32,745.00

    39,294.00

    399,489.00

    160,000.00

    160,000.00

  • 8/12/2019 Ezt Drilling

    5/30

    32,000.00

    5,000.00

    3,000.00

    -

    54,000.00

    3,000.00

    23,800.00

    5,820.00

    250.00

    100.00

    15,900.00

    2,000.00

    325.00

    650.00

    2,700.00

    15,000.00

    10,000.00

    9,000.00

    4,500.00

    187,045.00

    24,000.00

    4,000.00

    1,500.00

    1,000.00

    36,000.00

    66,500.00

    1,500.00

    5,000.00

    , .

    58,004.50

    69,605.40

    707,654.90

    1,107,143.90

  • 8/12/2019 Ezt Drilling

    6/30

  • 8/12/2019 Ezt Drilling

    7/30

    Project : PROPOSED CAMINS AIRPORT DRILLING PROJECTLocation : Canelar, Zamboanga City Scope of Work : I. WELL EXPLORATION, DEVELOPMENT & TESTING BY CONTRACT

    a) WELL EXPLORATIONb) SITE PREPARATION & SETTING UP OF EQUIPMENTc) WELL BOREHOLE LOGGING/DESIGN

    d) PRELIMINARY WELL TEST BY 72-HRS. CONSTANT RATE DISCHARGE TESTe) WELL BOREHOLE LOGGING DESIGN

    II. WELL CONSTRUCTION, DEVELOPMENT & TESTING

    a) WELL DRILLINGb) CASING/SCREEN & ACCESSORIES INSTALLATIONc) WELL DEVELOPMENT & TESTINGd) CEMENT GROUTING ( 15 METERS DEPTH) & INSTALLATION OF 19mm THICK x 350 mm WELL HEAD STEEL CAPe) DEMOBILIZATION

    Project Cost :

    Quantity Unit Amount

    ENGINEERING BASIC COST ITEMS

    I. WELL EXPLORATION

    A. MOBILIZATION 1 day 5,000.00 B. SITE PREPARATION & SETTING UP OF EQUIPMENT 1 day 5,000.00 C. WELL DRILLING

    200mm

    Pilothole Drilling 40 mtrs. 2,500.00 200mm Hard Penetration Borehole Drilling 40 mtrs. 3,000.00 Use of Equipments/others (Pilot Hole):

    Drilling Rig Equipment ( 8 Hours of Operation per day)to include Mapower (1-Rig Operator, & 4-Laborers);Fuel, Oil & Lubricant

    D. PRELIMINARY WELL TEST BY 24-HRS CONSTANT RATE DISCHARGE TEST (Using 2 Hp Submersible Pumping Unit)

    Supply & Installation of G.I. Temporary Casing & Well Development/Testing

    a) Supply & Installation of Blank/perforated 100mm G.I. Temporary Casing (80mbgl). 14 Pcs. 5,000.00Use of Drilling Rig Equipment (fuel, lubs & labor) 1 day 3,000.00

    (Note: Installation & pull-out of temporary casing)Welding Machine 1 day 1,500.00

    Acetylene & Oxygen (G.I. casing perforation) 1 day 1,500.00 (Note: Location of Perforation depending on logging design)

    6011 Welding Rod 10 kgs. 145.00 b) Well Development by Block Surging, Sand Pumping & Bailing-out of well sediments.

    Use of Drilling Rig Equipment (fuel, lubs & labor) 1 days 3,000.00 c) Well Testing (24 hrs. constant rate discharge test)

    Use of Electro-Mechanical Equipments/accessories & Genset (Labor & Power Supply included):- 2 Hp Submersible Pump / Motor & accessories- Riser Columns & accessories (up to the desired pump setting)

    Constant Discharge Rate Pumping 24 hrs 500.00

    E. WELL BOREHOLE LOGGING/DESIGN 4 days

    Price & Physical Contingencies Value Added Tax

    TOTAL COST OF ITEM 1

    II. WELL CONSTRUCTION, DEVELOPMENT & TESTING

    A. WELL DRILLING (to resume if well water quality passed the Philippine National Standard for Drinking Water

    and if Break Suction occur )

    350mm

    Borehole Drilling (Reaming) 80 mtrs. 2,000.00 400

    mm Borehole Drilling (Reaming) 80 mtrs. 2,000.00

    Use of Equipments/others (Reaming):

    Drilling Rig Equipment ( 8 Hours of Operation per day) to include Mapower (1-Rig Operator, & 4-Laborers);Fuel, Oil & Lubricant

    DIRECT COST

    BILL OF MATERIALS AND COST ESTIMATES

    Php1,503,277.90

  • 8/12/2019 Ezt Drilling

    8/30

    C. WELL DEVELOPMENT & TESTING Block Surging (including bailing out of sediments)Pump SurgingConstant Discharge Rate PumpingStep-Drawdown Test ( 3 steps)Use of Equipment/others:a) Block Surging ( Including bailing out of sediments) 24 Hrs. 1,000.00

    Use of Equipment/others:Drilling Rig Equipment ( 8 Hours of Operation per day)to include Mapower (1-Rig Operator, & 4-Laborers);Fuel, Oil & Lubricants

    Equipment's use Contingenciesb) Pump Surging ( 8hrs of operation per day) 8 Hrs. 500.00 c) Recovery Test 1 Test 500.00d) Step-Drawdown Test ( 3 Steps) 1 Test 1,000.00e) 24 hours Constant Discharge Rate Pumping Test:

    Submersible Pumping Equipment & accessories up to thedesired pump setting with motor capacity of 7.5Hp orgreater, complete with motor control & accessories.Generating Set for pumping unit power supply. 24 Hrs. 1,500.00

    D. Cement Grouting(15Meters Depth) & Installation of 19mm thickx 350

    mm Well Head Steel Cap 1 days 1,500.00

    E. DEMOBILIZATION 1 days 5,000.00 TOTAL COST OF ITEM II

    Price & Physical Contingencies Value Added Tax

    TOTAL COST OF ITEM II 1

    1,

    Prepared by:

    MARK BENEDICT C. REYESMechanical Engineer

    Noted by:

    FRANCIS DOMINIC TORRES

    CONTRACTOR

    O AL PROJEC COS

    DIRECT COST

  • 8/12/2019 Ezt Drilling

    9/30

    Project : PROPOSED WMSU DRILLING PROJECTLocation : Normal Rd., San Jose, Zamboanga City

    Scope of Work : I. WELL EXPLORATION, DEVELOPMENT & TESTING BY CONTRACT

    a) WELL EXPLORATION

    b) SITE PREPARATION & SETTING UP OF EQUIPMENT

    c) WELL BOREHOLE LOGGING/DESIGNd) PRELIMINARY WELL TEST BY 72-HRS. CONSTANT RATE DISCHARGE TEST

    e) WELL BOREHOLE LOGGING DESIGN

    II. WELL CONSTRUCTION, DEVELOPMENT & TESTINGa) WELL DRILLING

    b) CASING/SCREEN & ACCESSORIES INSTALLATIONc) WELL DEVELOPMENT & TESTING

    d) CEMENT GROUTING ( 15 METERS DEPTH) & INSTALLATION OF 19mm THICK x 350 mm WELL HEAD STEEe) DEMOBILIZATION

    Project Cost :

    Quantity Unit Amount

    ENGINEERING BASIC COST ITEMS

    I. WELL EXPLORATION

    A. MOBILIZATION 1 day 5,000

    B. SITE PREPARATION & SETTING UP OF EQUIPMENT 1 day 5,000C. WELL DRILLING

    200mm

    Pilothole Drilling 30 mtrs. 2,500200

    mm Hard Penetration Borehole Drilling 30 mtrs. 3,000

    Use of Equipments/others (Pilot Hole):Drilling Rig Equipment ( 8 Hours of Operation per day)

    to include Mapower (1-Rig Operator, & 4-Laborers);

    Fuel, Oil & Lubricant

    D. PRELIMINARY WELL TEST BY 24-HRS CONSTANT RATE DISCHARGE TEST (Using 2 Hp Submersible Pumping Unit)

    Supply & Installation of G.I. Temporary Casing & Well Development/Testing

    a) Supply & Installation of Blank/perforated 100mm G.I. Temporary Casing (80mbgl). 11 Pcs. 5,00

    Use of Drilling Rig Equipment (fuel, lubs & labor) 1 day 3,000

    (Note: Installation & pull-out of temporary casing)

    Welding Machine 1 day 1,500

    Acetylene & Oxygen (G.I. casing perforation) 1 day 1,500

    (Note: Location of Perforation depending on logging design)6011 Welding Rod 10 kgs. 145

    b) Well Development by Block Surging, Sand Pumping & Bailing-out of well sediments.

    Use of Drilling Rig Equipment (fuel, lubs & labor) 1 days 3,000c) Well Testing (24 hrs. constant rate discharge test)

    Use of Electro-Mechanical Equipments/accessories & Genset (Labor & Power Supply included):

    - 2 Hp Submersible Pump / Motor & accessories

    - Riser Columns & accessories (up to the desired pump setting)

    Constant Discharge Rate Pumping 24 hrs 500

    E. WELL BOREHOLE LOGGING/DESIGN 4 days

    Price & Physical ContingenciesValue Added Tax

    TOTAL COST OF ITEM 1

    II. WELL CONSTRUCTION, DEVELOPMENT & TESTING

    A. WELL DRILLING (to resume if well water quality passed the Philippine National Standard for Drinking Water

    and if Break Suction occur )

    350mm

    Borehole Drilling (Reaming) 30 mtrs. 2,000400

    mm Borehole Drilling (Reaming) 30 mtrs. 2,000

    Use of Equipments/others (Reaming):

    Drilling Rig Equipment ( 8 Hours of Operation per day)

    to include Mapower (1-Rig Operator, & 4-Laborers);

    Php1,058,343.90

    BILL OF MATERIALS AND COST ESTIMATES

    DIRECT COST

  • 8/12/2019 Ezt Drilling

    10/30

    Fuel, Oil & Lubricant

    B. CASING/SCREEN & ACCESSORIES INSTALLATION

    a. Supply & Installation of Materials:6mm thick x 250

    mmx6.00m. Spirally Welded Steel Casing 7 pcs. 8,000

    6mm thick x 250mm

    x 3.00m. Spirally Welded Steel Casing 1 pc. 1,000250

    mm x 3.00m Stainless Wirewound Screen, Slot 40 5 pcs. 39,600

    4mm thick x 400mm

    x 6.00m. Steel Casing (Conductor pipe) 3 pcs. 18,000

    Casing Centralizer 6 pcs. 500

    Pea Gravel (10-15) 4 m 5,95050

    mm x 6.00 Meter G.I. Pipe, Sch. 40 3 pcs. 1,940

    50

    mm

    x 1.00 Meter G.I. Short Pipe, Sch. 40 1 pc. 25050mm

    G.I. Cap 1 pc. 100Cement 60 bags 26515mm Thick x 500

    mm Steel Well Head Cap 1 unit 2,000

    Washed Sand 0.5 m 650

    Gravel 1 m 650

    Welding Rod, 6011,1/8" 15 kgs. 180

    Pilojel Bentonite 1000 kgs. 15

    Hemaxethaphosphate (Polyphospate) 100 kgs. 100

    b) Drilling Rig Equipment ( 8 Hours of Operation per day)

    to include Mapower (1-Rig Operator, & 4-Laborers);

    Fuel, Oil & Lubricants 3 days 3,000

    c) Welding Machine with Genset 3 days 1,500

    C. WELL DEVELOPMENT & TESTING

    Block Surging (including bailing out of sediments)

    Pump Surging

    Constant Discharge Rate Pumping

    Step-Drawdown Test ( 3 steps)

    Use of Equipment/others:

    a) Block Surging ( Including bailing out of sediments) 24 Hrs. 1,00

    Use of Equipment/others:

    Drilling Rig Equipment ( 8 Hours of Operation per day)

    to include Mapower (1-Rig Operator, & 4-Laborers);

    Fuel, Oil & Lubricants

    Equipment's use Contingenciesb) Pump Surging ( 8hrs of operation per day) 8 Hrs. 50

    c) Recovery Test 1 Test 50

    d) Step-Drawdown Test ( 3 Steps) 1 Test 1,00e) 24 hours Constant Discharge Rate Pumping Test:

    Submersible Pumping Equipment & accessories up to the

    desired pump setting with motor capacity of 7.5Hp or

    greater, complete with motor control & accessories.

    Generating Set for pumping unit power supply. 24 Hrs. 1,50

    D. Cement Grouting(15Meters Depth) & Installation of 19mm thickx 350

    mm Well Head Steel Cap 1 days 1,500

    E. DEMOBILIZATION 1 days 5,000

    TOTAL COST OF ITEM II

    Price & Physical Contingencies

    Value Added Tax

    TOTAL COST OF ITEM II

    Prepared by:

    MARK BENEDICT C. REYES

    Mechanical Engineer

    Noted by:

    DIRECT COST

    TOTAL PROJECT COST

  • 8/12/2019 Ezt Drilling

    11/30

    FRANCIS DOMINIC TORRES

    CONTRACTOR

  • 8/12/2019 Ezt Drilling

    12/30

    P

    Total

    3,000.00

    2,000.00

    75,000.0090,000.00

    55,000.00

    3,000.00

    1,500.00

    1,500.00

    1,450.00

    3,000.00

    12,000.00

    25,000.00

    272,450.00

    27,245.0032,694.00

    332,389.00

    60,000.00

    60,000.00

    120,000.00

  • 8/12/2019 Ezt Drilling

    13/30

    56,000.00

    1,000.00198,000.0054,000.00

    3,000.0023,800.005,820.00

    250.00100.00

    15,900.00

    2,000.00325.00650.00

    2,700.00

    15,000.0010,000.00

    9,000.00

    4,500.00402,045.00

    24,000.00

    4,000.001,500.00

    1,000.00

    36,000.00

    66,500.00

    1,500.00

    5,000.00

    595,045.0059,504.5071,405.40

    725,954.90

    1,058,343.90

  • 8/12/2019 Ezt Drilling

    14/30

  • 8/12/2019 Ezt Drilling

    15/30

    Project : PROPOSED TALISAYAN PROJECTLocation : Talisayan, Zamboanga City Scope of Work : I. WELL EXPLORATION, DEVELOPMENT & TESTING BY CONTRACT

    a) WELL EXPLORATIONb) SITE PREPARATION & SETTING UP OF EQUIPMENTc) WELL BOREHOLE LOGGING/DESIGNd) PRELIMINARY WELL TEST BY 72-HRS. CONSTANT RATE DISCHARGE TESTe) WELL BOREHOLE LOGGING DESIGN

    II. WELL CONSTRUCTION, DEVELOPMENT & TESTINGa) WELL DRILLING

    b) CASING/SCREEN & ACCESSORIES INSTALLATIONc) WELL DEVELOPMENT & TESTINGd) CEMENT GROUTING ( 15 METERS DEPTH) & INSTALLATION OF 19mm THICK x 350 mm WELL HEAD STEELe) DEMOBILIZATION

    Project Cost :

    Quantity Unit Amount

    ENGINEERING BASIC COST ITEMS

    I. WELL EXPLORATION

    A. MOBILIZATION 1 day 2,500.00B. SITE PREPARATION & SETTING UP OF EQUIPMENT 1 day 1,000.00C. WELL DRILLING

    200mm

    Pilothole Drilling 30 mtrs. 1,000.00200

    mm Hard Penetration Borehole Drilling 30 mtrs. 1,500.00

    Use of Equipments/others (Pilot Hole):Drilling Rig Equipment ( 8 Hours of Operation per day)to include Mapower (1-Rig Operator, & 4-Laborers);Fuel, Oil & Lubricant

    D. PRELIMINARY WELL TEST BY 24-HRS CONSTANT RATE DISCHARGE TEST (Using 2 Hp Submersible Pumping Unit)

    Supply & Installation of G.I. Temporary Casing & Well Development/Testing

    a) Supply & Installation of Blank/perforated 100mm G.I. Temporary Casing (80mbgl). 11 Pcs. 3,000.0Use of Drilling Rig Equipment (fuel, lubs & labor) 1 day 2,000.00

    (Note: Installation & pull-out of temporary casing)Welding Machine 1 day 1,000.00Acetylene & Oxygen (G.I. casing perforation) 1 day 1,000.00

    (Note: Location of Perforation depending on logging design)6011 Welding Rod 10 kgs. 145.00

    b) Well Development by Block Surging, Sand Pumping & Bailing-out of well sediments.Use of Drilling Rig Equipment (fuel, lubs & labor) 1 day 500.00

    c) Well Testing (24 hrs. constant rate discharge test) Use of Electro-Mechanical Equipments/accessories & Genset (Labor & Power Supply included):

    - 2 Hp Submersible Pump / Motor & accessories- Riser Columns & accessories (up to the desired pump setting)

    Constant Discharge Rate Pumping 24 hrs 500.00

    E. WELL BOREHOLE LOGGING/DESIGN 4 days

    Price & Physical ContingenciesValue Added Tax

    TOTAL COST OF ITEM 1

    II. WELL CONSTRUCTION, DEVELOPMENT & TESTING

    A. WELL DRILLING (to resume if well water quality passed the Philippine National Standard for Drinking Water

    and if Break Suction occur )

    350mm

    Borehole Drilling (Reaming) 60 mtrs. 1,000.00400

    mm Borehole Drilling (Reaming) 60 mtrs. 1,000.00

    Use of Equipments/others (Reaming):Drilling Rig Equipment ( 8 Hours of Operation per day) to include Mapower (1-Rig Operator, & 4-Laborers);

    Fuel, Oil & Lubricant

    B CASING/SCREEN & ACCESSORIES INSTALLATION

    Php523,617.90

    BILL OF MATERIALS AND COST ESTIMATES

    DIRECT COST

  • 8/12/2019 Ezt Drilling

    16/30

    50mm

    G.I. Cap 1 pc. 100.0Cement 60 bags 265.015mm Thick x 500

    mm Steel Well Head Cap 1 unit 2,000.0

    Washed Sand 0.5 m 650.0Gravel 1 m 650.0Welding Rod, 6011,1/8" 15 kgs. 180.0Pilojel Bentonite 1000 kgs. 15.0Hemaxethaphosphate (Polyphospate) 100 kgs. 100.0

    b) Drilling Rig Equipment ( 8 Hours of Operation per day)to include Mapower (1-Rig Operator, & 4-Laborers);Fuel, Oil & Lubricants 3 days 2,000.0

    c) Welding Machine with Genset 3 days 1,000.0

  • 8/12/2019 Ezt Drilling

    17/30

    C. WELL DEVELOPMENT & TESTING

    Block Surging (including bailing out of sediments)Pump SurgingConstant Discharge Rate PumpingStep-Drawdown Test ( 3 steps)

    Use of Equipment/others:a) Block Surging ( Including bailing out of sediments) 24 Hrs. 500.00

    Use of Equipment/others:Drilling Rig Equipment ( 8 Hours of Operation per day)

    to include Mapower (1-Rig Operator, & 4-Laborers);Fuel, Oil & LubricantsEquipment's use Contingencies

    b) Pump Surging ( 8hrs of operation per day) 8 Hrs. 500.00

    c) Recovery Test 1 Test 500.00d) Step-Drawdown Test ( 3 Steps) 1 Test 1,000.00e) 24 hours Constant Discharge Rate Pumping Test:

    Submersible Pumping Equipment & accessories up to thedesired pump setting with motor capacity of 7.5Hp or

    greater, complete with motor control & accessories.Generating Set for pumping unit power supply. 24 Hrs. 500.00

    D. Cement Grouting(15Meters Depth) & Installation of 19mm thickx 350

    mm Well Head Steel Cap 1 days 1,000.00

    E. DEMOBILIZATION 1 days 2,500.00

    TOTAL COST OF ITEM II

    Price & Physical Contingencies

    Value Added Tax

    TOTAL COST OF ITEM II

    Prepared by:

    MARK BENEDICT C. REYESMECHANICAL ENGINEER

    Noted by:

    FRANCIS DOMINIC TORRES

    CONTRACTOR

    DIRECT COST

    TOTAL PROJECT COST

  • 8/12/2019 Ezt Drilling

    18/30

    Project : PROPOSEDLUNZURAN DRILLING PROJECTLocation : Lunzuran, Zamboanga City Scope of Work : I. WELL EXPLORATION, DEVELOPMENT & TESTING BY CONTRACT

    a) WELL EXPLORATIONb) SITE PREPARATION & SETTING UP OF EQUIPMENTc) WELL BOREHOLE LOGGING/DESIGNd) PRELIMINARY WELL TEST BY 72-HRS. CONSTANT RATE DISCHARGE TESTe) WELL BOREHOLE LOGGING DESIGN

    II. WELL CONSTRUCTION, DEVELOPMENT & TESTINGa) WELL DRILLING

    b) CASING/SCREEN & ACCESSORIES INSTALLATIONc) WELL DEVELOPMENT & TESTINGd) CEMENT GROUTING ( 15 METERS DEPTH) & INSTALLATION OF 19mm THICK x 350 mm WELL HEAD STEELe) DEMOBILIZATION

    Project Cost :

    Quantity Unit Amount

    ENGINEERING BASIC COST ITEMS

    I. WELL EXPLORATION

    A. MOBILIZATION 1 day 2,500.00B. SITE PREPARATION & SETTING UP OF EQUIPMENT 1 day 1,000.00C. WELL DRILLING

    200mm

    Pilothole Drilling 60 mtrs. 1,000.00200

    mm Hard Penetration Borehole Drilling 60 mtrs. 1,500.00

    Use of Equipments/others (Pilot Hole):Drilling Rig Equipment ( 8 Hours of Operation per day)to include Mapower (1-Rig Operator, & 4-Laborers);Fuel, Oil & Lubricant

    D. PRELIMINARY WELL TEST BY 24-HRS CONSTANT RATE DISCHARGE TEST (Using 2 Hp Submersible Pumping Unit)

    Supply & Installation of G.I. Temporary Casing & Well Development/Testing

    a) Supply & Installation of Blank/perforated 100mm G.I. Temporary Casing (80mbgl). 11 Pcs. 3,000.0Use of Drilling Rig Equipment (fuel, lubs & labor) 1 day 2,000.00

    (Note: Installation & pull-out of temporary casing)Welding Machine 1 day 1,000.00Acetylene & Oxygen (G.I. casing perforation) 1 day 1,000.00

    (Note: Location of Perforation depending on logging design)6011 Welding Rod 10 kgs. 145.00

    b) Well Development by Block Surging, Sand Pumping & Bailing-out of well sediments.Use of Drilling Rig Equipment (fuel, lubs & labor) 1 day 500.00

    c) Well Testing (24 hrs. constant rate discharge test) Use of Electro-Mechanical Equipments/accessories & Genset (Labor & Power Supply included):

    - 2 Hp Submersible Pump / Motor & accessories- Riser Columns & accessories (up to the desired pump setting)

    Constant Discharge Rate Pumping 24 hrs 500.00

    E. WELL BOREHOLE LOGGING/DESIGN 4 days

    Price & Physical ContingenciesValue Added Tax

    TOTAL COST OF ITEM 1

    II. WELL CONSTRUCTION, DEVELOPMENT & TESTING

    A. WELL DRILLING (to resume if well water quality passed the Philippine National Standard for Drinking Water

    and if Break Suction occur )

    350mm

    Borehole Drilling (Reaming) 120 mtrs. 1,000.00400

    mm Borehole Drilling (Reaming) 120 mtrs. 1,000.00

    Use of Equipments/others (Reaming):Drilling Rig Equipment ( 8 Hours of Operation per day) to include Mapower (1-Rig Operator, & 4-Laborers);

    Fuel, Oil & Lubricant

    B CASING/SCREEN & ACCESSORIES INSTALLATION

    Php825,567.90

    BILL OF MATERIALS AND COST ESTIMATES

    DIRECT COST

  • 8/12/2019 Ezt Drilling

    19/30

    50mm

    G.I. Cap 1 pc. 100.0Cement 60 bags 265.015mm Thick x 500

    mm Steel Well Head Cap 1 unit 2,000.0

    Washed Sand 0.5 m 650.0Gravel 1 m 650.0Welding Rod, 6011,1/8" 15 kgs. 180.0Pilojel Bentonite 1000 kgs. 15.0Hemaxethaphosphate (Polyphospate) 100 kgs. 100.0

    b) Drilling Rig Equipment ( 8 Hours of Operation per day)to include Mapower (1-Rig Operator, & 4-Laborers);Fuel, Oil & Lubricants 3 days 2,000.0

    c) Welding Machine with Genset 3 days 1,000.0

  • 8/12/2019 Ezt Drilling

    20/30

    C. WELL DEVELOPMENT & TESTING Block Surging (including bailing out of sediments)Pump SurgingConstant Discharge Rate PumpingStep-Drawdown Test ( 3 steps)Use of Equipment/others:a) Block Surging ( Including bailing out of sediments) 24 Hrs. 500.00

    Use of Equipment/others:Drilling Rig Equipment ( 8 Hours of Operation per day)to include Mapower (1-Rig Operator, & 4-Laborers);Fuel, Oil & Lubricants

    Equipment's use Contingenciesb) Pump Surging ( 8hrs of operation per day) 8 Hrs. 500.00c) Recovery Test 1 Test 500.00d) Step-Drawdown Test ( 3 Steps) 1 Test 1,000.00e) 24 hours Constant Discharge Rate Pumping Test:

    Submersible Pumping Equipment & accessories up to thedesired pump setting with motor capacity of 7.5Hp orgreater, complete with motor control & accessories.Generating Set for pumping unit power supply. 24 Hrs. 500.00

    D. Cement Grouting(15Meters Depth) & Installation of 19mm thickx 350

    mm Well Head Steel Cap 1 days 1,000.00

    E. DEMOBILIZATION 1 days 2,500.00TOTAL COST OF ITEM II

    Price & Physical ContingenciesValue Added Tax

    TOTAL COST OF ITEM II

    Prepared by:

    MARK BENEDICT C. REYES

    MECHANICAL ENGINEER

    Noted by:

    FRANCIS DOMINIC TORRES

    CONTRACTOR

    DIRECT COST

    TOTAL PROJECT COST

  • 8/12/2019 Ezt Drilling

    21/30

    Project : PROPOSED TALISAYAN PROJECTLocation : Talisayan, Zamboanga City Scope of Work : I. WELL EXPLORATION, DEVELOPMENT & TESTING BY CONTRACT

    a) WELL EXPLORATIONb) SITE PREPARATION & SETTING UP OF EQUIPMENTc) WELL BOREHOLE LOGGING/DESIGNd) PRELIMINARY WELL TEST BY 72-HRS. CONSTANT RATE DISCHARGE TESTe) WELL BOREHOLE LOGGING DESIGN

    II. WELL CONSTRUCTION, DEVELOPMENT & TESTINGa) WELL DRILLING

    b) CASING/SCREEN & ACCESSORIES INSTALLATIONc) WELL DEVELOPMENT & TESTINGd) CEMENT GROUTING ( 15 METERS DEPTH) & INSTALLATION OF 19mm THICK x 350 mm WELL HEAD STEELe) DEMOBILIZATION

    Project Cost :

    Quantity Unit Amount

    ENGINEERING BASIC COST ITEMS

    I. WELL EXPLORATION

    A. MOBILIZATION 1 day 3,000.00B. SITE PREPARATION & SETTING UP OF EQUIPMENT 1 day 1,000.00C. WELL DRILLING

    200mm

    Pilothole Drilling 30 mtrs. 1,000.00200

    mm Hard Penetration Borehole Drilling 30 mtrs. 1,500.00

    Use of Equipments/others (Pilot Hole):Drilling Rig Equipment ( 8 Hours of Operation per day)to include Mapower (1-Rig Operator, & 4-Laborers);Fuel, Oil & Lubricant

    D. PRELIMINARY WELL TEST BY 24-HRS CONSTANT RATE DISCHARGE TEST (Using 2 Hp Submersible Pumping Unit)

    Supply & Installation of G.I. Temporary Casing & Well Development/Testing

    a) Supply & Installation of Blank/perforated 100mm G.I. Temporary Casing (80mbgl). 11 Pcs. 1,000.0Use of Drilling Rig Equipment (fuel, lubs & labor) 1 day 2,000.00

    (Note: Installation & pull-out of temporary casing)Welding Machine 1 day 1,000.00Acetylene & Oxygen (G.I. casing perforation) 1 day 1,000.00

    (Note: Location of Perforation depending on logging design)6011 Welding Rod 10 kgs. 145.00

    b) Well Development by Block Surging, Sand Pumping & Bailing-out of well sediments.Use of Drilling Rig Equipment (fuel, lubs & labor) 1 day 500.00

    c) Well Testing (24 hrs. constant rate discharge test) Use of Electro-Mechanical Equipments/accessories & Genset (Labor & Power Supply included):

    - 2 Hp Submersible Pump / Motor & accessories- Riser Columns & accessories (up to the desired pump setting)

    Constant Discharge Rate Pumping 24 hrs 500.00

    E. WELL BOREHOLE LOGGING/DESIGN 4 days

    Price & Physical ContingenciesValue Added Tax

    TOTAL COST OF ITEM 1

    II. WELL CONSTRUCTION, DEVELOPMENT & TESTING

    A. WELL DRILLING (to resume if well water quality passed the Philippine National Standard for Drinking Water

    and if Break Suction occur )

    350mm

    Borehole Drilling (Reaming) 60 mtrs. 500.00400

    mm Borehole Drilling (Reaming) 60 mtrs. 500.00

    Use of Equipments/others (Reaming):Drilling Rig Equipment ( 8 Hours of Operation per day) to include Mapower (1-Rig Operator, & 4-Laborers);

    Fuel, Oil & Lubricant

    B CASING/SCREEN & ACCESSORIES INSTALLATION

    Php416,257.90

    BILL OF MATERIALS AND COST ESTIMATES

    DIRECT COST

  • 8/12/2019 Ezt Drilling

    22/30

    50mm

    G.I. Cap 1 pc. 100.00Cement 60 bags 265.0015mm Thick x 500

    mm Steel Well Head Cap 1 unit 2,000.00

    Washed Sand 0.5 m 650.00Gravel 1 m 650.00Welding Rod, 6011,1/8" 15 kgs. 180.00Pilojel Bentonite 1000 kgs. 15.00Hemaxethaphosphate (Polyphospate) 100 kgs. 100.00

    b) Drilling Rig Equipment ( 8 Hours of Operation per day)to include Mapower (1-Rig Operator, & 4-Laborers);Fuel, Oil & Lubricants 3 days 2,000.00

    c) Welding Machine with Genset 3 days 1,000.00

    C. WELL DEVELOPMENT & TESTING Block Surging (including bailing out of sediments)Pump SurgingConstant Discharge Rate PumpingStep-Drawdown Test ( 3 steps)Use of Equipment/others:a) Block Surging ( Including bailing out of sediments) 24 Hrs. 500.00

    Use of Equipment/others:Drilling Rig Equipment ( 8 Hours of Operation per day)to include Mapower (1-Rig Operator, & 4-Laborers);Fuel, Oil & LubricantsEquipment's use Contingencies

    b) Pump Surging ( 8hrs of operation per day) 8 Hrs. 500.00c) Recovery Test 1 Test 500.00d) Step-Drawdown Test ( 3 Steps) 1 Test 1,000.00e) 24 hours Constant Discharge Rate Pumping Test:

    Submersible Pumping Equipment & accessories up to thedesired pump setting with motor capacity of 7.5Hp orgreater, complete with motor control & accessories.Generating Set for pumping unit power supply. 24 Hrs. 500.00

    D. Cement Grouting(15Meters Depth) & Installation of 19mm thickx 350

    mm Well Head Steel Cap 1 days 1,000.00

    E. DEMOBILIZATION 1 days 3,000.00TOTAL COST OF ITEM II

    Price & Physical Contingencies

    Value Added Tax

    TOTAL COST OF ITEM II

    Prepared by:

    MARK BENEDICT C. REYESMECHANICAL ENGINEER

    Noted by:

    FRANCIS DOMINIC TORRES

    CONTRACTOR

    DIRECT COST

    TOTAL PROJECT COST

  • 8/12/2019 Ezt Drilling

    23/30

    Project : PROPOSED SAN RAMON ECOZONE DRILLING PROJECTLocation : San Ramon Talisayan, Zamboanga City Scope of Work : I. WELL EXPLORATION, DEVELOPMENT & TESTING BY CONTRACT

    a) WELL EXPLORATIONb) SITE PREPARATION & SETTING UP OF EQUIPMENTc) WELL BOREHOLE LOGGING/DESIGNd) PRELIMINARY WELL TEST BY 72-HRS. CONSTANT RATE DISCHARGE TESTe) WELL BOREHOLE LOGGING DESIGN

    II. WELL CONSTRUCTION, DEVELOPMENT & TESTINGa) WELL DRILLINGb) CASING/SCREEN & ACCESSORIES INSTALLATIONc) WELL DEVELOPMENT & TESTINGd) CEMENT GROUTING ( 15 METERS DEPTH) & INSTALLATION OF 19mm THICK x 350 mm WELL HEAD STEEL CAPe) DEMOBILIZATION

    Project Cost :

    Quantity Unit Amount

    ENGINEERING BASIC COST ITEMS

    I. WELL EXPLORATION

    A. MOBILIZATION 1 day 5,000.00 B. SITE PREPARATION & SETTING UP OF EQUIPMENT 1 day 3,000.00

    C. WELL DRILLING200

    mm Pilothole Drilling 20 mtrs. 2,000.00

    200mm

    Hard Penetration Borehole Drilling 20 mtrs. 2,500.00

    Use of Equipments/others (Pilot Hole):Drilling Rig Equipment ( 8 Hours of Operation per day)to include Mapower (1-Rig Operator, & 4-Laborers);Fuel, Oil & Lubricant

    D. PRELIMINARY WELL TEST BY 24-HRS CONSTANT RATE DISCHARGE TEST (Using 2 Hp Submersible Pumping Unit)

    Supply & Installation of G.I. Temporary Casing & Well Development/Testing

    a) Supply & Installation of Blank/perforated 100mm G.I. Temporary Casing (40mbgl). 7 Pcs. 1,500.00Use of Drilling Rig Equipment (fuel, lubs & labor) 1 day 2,500.00

    (Note: Installation & pull-out of temporary casing)

    Welding Machine 1 day 500.00 Acetylene & Oxygen (G.I. casing perforation) 1 day 1,000.00

    (Note: Location of Perforation depending on logging design)

    6011 Welding Rod 15 kgs. 145.00 b) Well Development by Block Surging, Sand Pumping & Bailing-out of well sediments.

    Use of Drilling Rig Equipment (fuel, lubs & labor) 1 day 500.00 c) Well Testing (24 hrs. constant rate discharge test)

    Use of Electro-Mechanical Equipments/accessories & Genset (Labor & Power Supply included):- 2 Hp Submersible Pump / Motor & accessories

    - Riser Columns & accessories (up to the desired pump setting)

    Constant Discharge Rate Pumping 24 hrs 500.00

    E. WELL BOREHOLE LOGGING/DESIGN 4 days

    Price & Physical Contingencies Value Added Tax

    TOTAL COST OF ITEM 1

    II. WELL CONSTRUCTION, DEVELOPMENT & TESTING

    A. WELL DRILLING (to resume if well water quality passed the Philippine National Standard for Drinking Water

    and if Break Suction occur )

    350mm

    Borehole Drilling (Reaming) 20 mtrs. 1,000.00 400

    mm Borehole Drilling (Reaming) 20 mtrs. 1,500.00

    Use of Equipments/others (Reaming):Drilling Rig Equipment ( 8 Hours of Operation per day) to include Mapower (1-Rig Operator, & 4-Laborers);

    Fuel, Oil & Lubricant

    B CASING/SCREEN & ACCESSORIES INSTALLATION

    665,412.40PhpBILL OF MATERIALS AND COST ESTIMATES

    DIRECT COST

  • 8/12/2019 Ezt Drilling

    24/30

    6mm thick x 250mm

    x3.00m. Spirally Welded Steel Casing 1 pcs. 5,000.00 6mm thick x 250

    mmx1.00m. Spirally Welded Steel Casing 1 pcs. 3,000.00

    250mm

    x 6.00m Stainless Wirewound Screen, Slot 40 2 pc. 95,000.00 Casing Centralizer 6 pcs. 500.00 Pea Gravel (10-15) 4 m 2,000.00 50

    mm x 6.00 Meter G.I. Pipe, Sch. 40 3 pcs. 1,940.00

    50mm

    x 1.00 Meter G.I. Short Pipe, Sch. 40 1 pc. 250.00 50

    mm G.I. Cap 1 pc. 100.00

    Cement 60 bags 265.00 15mm Thick x 500

    mm Steel Well Head Cap 1 unit 2,000.00

    Washed Sand 0.5 m 650.00 Gravel 1 m 650.00 Welding Rod, 6011,1/8" 15 kgs. 180.00 Pilojel Bentonite 1000 kgs. 15.00 Hemaxethaphosphate (Polyphospate) 100 kgs. 100.00

    b) Drilling Rig Equipment ( 8 Hours of Operation per day)to include Mapower (1-Rig Operator, & 4-Laborers);Fuel, Oil & Lubricants 3 days 2,500.00

    c) Welding Machine with Genset 3 days 500.00

    C. WELL DEVELOPMENT & TESTING Block Surging (including bailing out of sediments)Pump SurgingConstant Discharge Rate PumpingStep-Drawdown Test ( 3 steps)

    Use of Equipment/others:a) Block Surging ( Including bailing out of sediments) 24 Hrs. 500.00

    Use of Equipment/others:Drilling Rig Equipment ( 8 Hours of Operation per day)to include Mapower (1-Rig Operator, & 4-Laborers);Fuel, Oil & LubricantsEquipment's use Contingencies

    b) Pump Surging ( 8hrs of operation per day) 8 Hrs. 500.00 c) Recovery Test 1 Test 500.00d) Step-Drawdown Test ( 3 Steps) 1 Test 1,000.00e) 24 hours Constant Discharge Rate Pumping Test:

    Submersible Pumping Equipment & accessories up to thedesired pump setting with motor capacity of 7.5Hp orgreater, complete with motor control & accessories.Generating Set for pumping unit power supply. 24 Hrs. 500.00

    D. Cement Grouting(15Meters Depth) & Installation of 19mm thickx 350

    mm Well Head Steel Cap 1 days 1,000.00

    E. DEMOBILIZATION 1 days 5,000.00 TOTAL COST OF ITEM II

    Price & Physical Contingencies

    Value Added Tax

    TOTAL COST OF ITEM II

    Prepared by:

    MARK BENEDICT C. REYESMECHANICAL ENGINEER

    Noted by:

    FRANCIS DOMINIC TORRES

    CONTRACTOR

    DIRECT COST

    O AL PROJEC COS

  • 8/12/2019 Ezt Drilling

    25/30

    Project : PROPOSED SAN RAMON ECOZONE WELL ELECTRO-MECHANICAL EQUIPMENT

    Location : San Ramon, Talisayan Zamboanga City

    Scope of Work : I. Package Supply, Installation, Testing & Commissioning of One (1) Unit 20Hp Submerssible pump/motor,

    Riser Columns, Motor Controls & accessories, Discharge pipings, Appurtenances and Fittings.

    II. Package Supply, Installation, Testing & Commissioning of One (1) Unit 100mm Mechanical

    Flowmeter & GSM Data Logger complete with accessories.

    Project Cost :

    I. PACKAGE SUPPLY, INSTALLATION, TESTING & COMMISIONING OF ONE (1) UNIT 20HP SUBMERSSIBLE PUMP/ MOTOR, MOTOR CONTROLS & ACCESSORIES, DISCHARGE PIPINGS, APPURTENANCES & FITTINGS,

    TO INCLUDE THE SUPPLY & CONSTRUCTION OF CONCRETE PIPE SUPPORTS UP TO THE FILTRATION SYSTEM:

    (Note: Actual Piping Lay-out to refer on project site)

    A. SUBMERSIBLE PUMP & RISER COLUMNS/ACCESSORIES:

    - Submersible Pump of 45.00 m3/hr (200GPM) capacity against a TDH of 73 meters (239.44Ft.), 6-stages,

    within 61.1% Efficiency, Pump outlet diameter of 75mm, Stainless Steel Body construction, or its equivalent;

    - 6 pcs. 6.02mm thick x 100mm x 6.00 m. B.I. Sch. 40 riser column, anti-rust & epoxy-enamel coated (blue);

    - 1 pc. 6.02mm thick x 100mm x 3.00 m. B.I. Sch. 40 riser column, anti-rust & epoxy-enamel coated (blue);

    - 14 pcs. B.I. Flanges, 19mm thick x 112mmID x 200mmOD with 6 (six) of 17mm holes per flange welded @

    both ends of 6.02mm thick x 100mm x 6.00meters B.I. pipe riser columns, complete with 16mm stainless

    steel bolts, nuts, washers and with 1/4" thick rubber gasket. (See attached Flange Shop Drawing)

    - 1 pc. 6.02mm thick x 100mm x 75mm x 0.40 meter Stainless Steel Adaptor(concentric reducer) with one

    end welded to 19mm x 112mmID x 200mmOD B.I. Flange & threaded at one end which matches the Pump

    outlet diameter.

    - 6.02mm thick x 100mm x 0.70 meter B.I. pipe sch. 40 (top discharge column) heavily welded thru the

    center of the 20mmthick x 350mm steel well seal and 100mm x 90 B.I. long sweep elbow welded @ top

    end of B.I. column pipe, all anti-rust coated & epoxy-enamel coated (blue).

    - 1 length of 19mm x 60.0 meters HDPE Pipe, SDR-11. For Sounding tube. (Refer Installation Drawing)

    - 1 Unit Electro-Sounder with 100 meters of cable at 1.00 meter graduation complete with electrodes and

    markings, winding reel wheel complete with brake and carrying handle, meter and accessories.

    (Note: Pump Setting @ 40.0 mbgl)

    B. SUBMERSIBLE ELECTRIC MOTOR & CONTROLS:

    20 Hp. Submerssible Motor, 3-phase, 230 VAC, 60 Hz., 3500 RPM, complete with the following:

    Motor Controls:

    Main Circuit Breaker, Industrial type (Heavy Duty), 230 VAC, 3-Phase, 150 Amps.

    Softstarter control system with By-pass Contactor and Thermal Overload Relay, Desired motor protection such as

    Electronic over/undervoltage Protection Relay, Motor thermal state with Phase Failure & Unbalance Protections,

    Lock Rotor Motor protection, soft acceleration/decelaration, including the control for the water hammer and

    cavitation, over/under voltage, phase failure/sequence, Ground Fault circuit interruptor, Liquid level controllertype LH/RH with electrodes, Electronic Power-on/Delay timer, Lightning Arrester, Start/stop push buttons and

    pilot lights, Ammeter (0-100A),Voltmeter (0-300VAC), with CurrentTransformer (100:5 x'former ratio) which

    matches the ammeter, H-O-A selector switch. Complete with the desired molded case circuit breakers and

    contactor all in NEMA-3R steel enclosure. 70 mtrs. (22mm2#)4/3 double jacketed submersible electrical cable

    spliced to the motor leads using standard resin type 3M brand (82-A3 Kit No.) splicing kit with two (02) rolls each

    of #23 & #33 Rubber & electrical tapes. (Note: Splicing to be done at project site)

    TOTAL DIRECT COST 1 Lot 5

    C.SUPPLY & INSTALLATION OF DISCHARGE PIPINGS, APPURTENANCES & FITTINGS:

    Unit Qty. Unit Cost Amount

    100mm C.I. Body Check Valve w/ counter weight (PN16), F/F (Imported brand) 1 Pc. 65,000.00

    unit includes two (2) mating flanges

    100mm C.I. Body Gate Valve (PN16) with Hand-wheel, NRS, F/F (Imported brand) 2 Pcs. 10,000.00 unit includes two (2) mating flanges

    100mm Std. Sleeve Type Flexible Coupling (for B.I. pipe) 2 Pcs. 2,500.00

    16mm x 76mm full threaded Stainless Bolt & Nut with washer 60 Pcs. 120.00

    6.02mm. thick x100mm x 6 mtrs. B.I. Pipe, sch.40 with anti-rust & epoxy-enamel coated 3 Pcs. 6,000.00

    "blue"

    6.02mm thick x 100mm x 100mm Fabricated B.I Tee, sch.40, P/P 1 Pc. 1,500.00

    (w/ anti-rust & epoxy-enamel coated)

    (Note: Amount of Fabricated B.I. Tee comprises the cost of welding works & materials

    to get portion from supply of B.I. pipes)

    25 mm Air Release - Air Vacuum & Pressure Gauge Assy. (PN16) 1 Pc. 7,500.00

    Provision for Chlorinator Injection Fittings:

    2" G.I. Coupling, sch. 40 1 Pc. 62.00 2" x 6" G.I. Nipple, sch. 40 1 Pc. 109.00 2" G.I. Cap 1 Pc. 76.00

    3/4" G.I. Coupling, sch.40 1 Pc. 17.00 3/4" x 1/2" G.I. Bushing 1 Pc. 17.00 1/2" G.I. Plug 1 Pc. 9.00

    988,053.00Php

    Materials Breakdown & Cost Estimates

  • 8/12/2019 Ezt Drilling

    26/30

    1/2" G.I. Tee, sch.40 1 Pc. 13.00 1/2" G.I. Coupling, sch.40 1 Pc. 11.00 1/2" x 4" G.I. Nipple, sch. 40 1 Pc. 18.00 1/2" x 1/4" G.I. Bushing 1 Pc. 12.00 1/2" Brass Ball Valve 1 Pc. 442.00 1/4" G.I. Plug 1 Pc. 16.00 2-1/2" Oil-filled Pressure Gauge (0-160 psi) 1 Pc. 3,000.00

    Labor: Cutting & Welding works of B.I. Discharge Pipes, Installation of Appurtenances, 1 lot 15,000.00

    Pressure Gauge assy. and the provision for Chlorinator Injection Fittings.

    TOTAL COST OF ITEM I P 693,053.00

  • 8/12/2019 Ezt Drilling

    27/30

    II. PACKAGE SUPPLY, INSTALLATION, TESTING & COMMISSIONING OF 100mm ELECTRO-MAGNETIC FLOWMETERWITH INTEGRATED GSM DATA LOGGER & COMPLETE ACCESSORIES:

    A. Supply, Installation, Testing & Commissioning of one (1) unit Unit Qty. Unit Cost Amount

    100mm Electromagnetic Flowmeter, Flange-type, with two (2) mating 1 unit 220,000.00 2

    flanges and with wall-mounted type signal converter complete with accessories.

    B. Supply & installation of Integrated GSM Data Logger 2 flow MK3 (flow & pressure) 1 unit 75,000.00

    compatible with the sensor EM Flowmeter with a recording

    interval programmable between 1 second & 1 hour,

    900 MHz with remote downloading powered by lithium battery pack dischargeable

    with a minimum life span of 5 years. Housing fully water proofed (IP68). Data can be accessed remotely using a standard GSM mobile telephone thru simple

    text message to the host computer provided with a windows-based software (one modem per unit).

    The unit includes the following accessories:

    Flow input cable (30 meters), Communication cable from logger to Personal

    computer (5 meters), Windows-based configuration software for PC's,

    Two-channel flow splitter cable (30 meters), Helicoil hose fitting for pressure

    recording, 30 meters hose for pressure line with fittings (Quick fit connection).

    (Logger Lumpsum Amount includes Orientation & Training of personnels)

    TOTAL COST OF ITEM II 2

    TOTAL AMOUNT P 988,053.00

    Prepared by:

    Noted by:

    MARK BENEDICT C. REYES

    MECHANICAL ENGINEER

    FRANCIS DOMINIC TORRES

    CONTRACTOR

  • 8/12/2019 Ezt Drilling

    28/30

    PRODUCTION WELL:

    Bore Hole Diameter : 450 mm

    Casing Diameter : 250 mm

    Well Depth : 40 Meters

    Well Capacity : 200 GPM

    Well Discharge Pipes : 100 mm

    FILTRATION SYSTEM:

    Operating Pressure : 50 psi

    Max. Oprtg. Pressure : 100 psi

    SUBMERSIBLE PUMP DESIGN CAPACITY:

    Pump Discharge Capacity (Q) : 200 GPM

    Headloss in Pipes : 20 Meters

    Pressure Head : 53 Meters

    Total Dynamic Head (TDH) : 73 Meters or (239.44 Ft.)

    Pump Efficiency, from pump curve (Np) : 61%

    Density of Water @ 60 degrees F.(D) : 8.34 Lbs/gal

    SUBMERSIBLE MOTOR DESIGN CAPACITY:

    WATER HORSEPOWER (Whp):

    Q x TDH x D

    200 x 239.44 x 8.34

    INPUT HORSEPOWER (Ihp):

    Whp

    Np

    12.100.61

    The nearest available Submersible Motor capacity is 20Hp, so the recommended pumping unit will be

    20Hp SUBMERSIBLE MOTOR WITH 6-STAGES SUBMERSIBLE PUMP, based on the Pump

    Performance Curve, with Pump capacity of 45.00 m3/hr (200GPM) vs. 73 m.(239.44Ft.)

    Total Dynamic Head (TDH).

    Prepared by:

    DESIGN CAPACITY OF SUBMERSIBLE PUMP AND MOTOR

    FOR SAN RAMON ECOZONE DEEP WELL

    Whp =33,000 Ft-lb/Hp-min

    Whp =

    33,000

    Whp = 12.10 Hp

    Ihp =

    Ihp =

    Ihp = 19.81 Hp

  • 8/12/2019 Ezt Drilling

    29/30

    MARK REYES

    MECHANICAL ENGINEER

  • 8/12/2019 Ezt Drilling

    30/30

    I. PROPOSED SAN RAMON ECOZONE DRILLING PROJECT

    II. PROPOSED SAN RAMON ECOZONE WELL ELECTRO-MECHANICAL EQUIPMENT

    Note: Pump & Motor design are subject for changes upon completion of the drilling, the total well discharge

    are yet to determine upon completion of the drilling.

    III. PROPOSED PUMP HOUSE

    6.00sq.m. floor area, with control room and chlorinator room

    TOTAL 1,842,612.84Php

    COST

    665,412.40Php

    988,053.00Php

    PROJECT COST BREAKDOWN

    189,147.44Php