hindustan lng limited - a p 070619/hindustan... · hindustan lng limited consultant bhagavathi ana...
TRANSCRIPT
English - Executive Summary (Submitted for Public Consultation Process as per EIA notification 2006 & Amendments thereof)
Project Proposal
Proposed LNG, LPG import facilities & Handling Facilities with
Captive Jetty & Breakwaters
at
T. Challapalli Village. E. Godavari District,AP
Proposal No: IA/AP/MIS/64642/2017
File No: 10-32/2017-IA-III
Proponent
Hindustan LNG Limited
Consultant
Bhagavathi Ana Labs Pvt. Limited (A Bureau Veritas Group Company)
7-2-C14, Industrial Estate, Sanath Nagar, Hyderabad- 500018 NABET/EIA/1619/SA080 dated Jan 11th 2019
BALPL Document No: IND.BH.41.16.0310/HSR
January , 2019
Executive Summary For Proposed LNG & LPG Import Facilities With Captive Jetty and Breakwaters at T.
Challapalli (V), Uppalaguptam Mandal, East Godavari District, Andhra Pradesh by M/s Hindustan LNG
Ltd.
EXECUTIVE SUMMARY
Bhagavathi Ana Labs Pvt. Ltd. (a Bureau Veritas Group Company) Project Reference : IND.BH.41.16.0310/HSR 2
EXECUTIVE SUMMARY
E.1 Introduction
M/s Hindustan LNG Limited (HLNG) a registered company in Hyderabad, India is
desirous of supplying natural gas. HLNG intends to import LNG and LPG import facilities
with Captive Jetty & Breakwaters at T.Challapalli village, Uppalaguptam Mandal, East
Godavari District, Andhra Pradesh.
(a) LNG import & handling facility with Capacity of 11 MMTPA (Phase I - 5.5
MMTPA, Phase II - 5.5 MMTPA) and Floating Storage Unit (FSU), Land based
Storage Tanks (240000 m³ each in 2 stages) to store the LNG and Truck Loading
Terminal (12 Bay) to store and transport the LNG, re-gasify and deliver Natural
Gas to Gas Authority of India Limited (GAIL); and
(b) LPG import & handling facility with capacity of 4 MMTPA (Phase I - 2.0 MMTPA,
Phase II - 2.0 MMTPA) with Onshore Storage Tanks and transport facility.
E.1.1 Classification of Project as per EIA Notification
The proposed setting of the LNG & LPG Import and handling facilities with Captive Jetty
& Breakwaters At T. Challapalli Village By Hindustan LNG Limited attracts the provisions
of Environmental Impact Assessment (EIA) Notification, 2006 (as amended thereof) and
Coastal Regulation Zone (CRZ) Notification, 2011 (as amended thereof) in view of
construction activities, dredging, widening/deepening of channels, etc. The proposed
project is categorized as under.
6(a) Oil & gas transportation pipeline (crude and refinery / petrochemical products),
passing through national parks /sanctuaries/coral reefs/ecologically sensitive areas
including LNG Terminal.
7(e) Captive Jetty with breakwaters and 4 berths. The project also consists of
Floating Storage Unit (FSU) of 5 Million Tons Per Annum (MTPA).
With all the above components, the proposed integrated project is classified as Category
“A”.
E.1.2 CRZ Status of the Project
As per Coastal Regulation Zone Notification 2011, the proposed project can be classified
as Regulated Permissible activity under clause 4 Sub clause 4 (i) (a). Clearance shall be
given for any such activity within the CRZ only if it requires waterfront and foreshore
facilities.
As per the CRZ demarcation study conducted by Institute of Remote Sensing (IRS),
Anna University, Chennai in line with Coastal Regulation Zone Act 2011, the proposed
project falls in CRZ – 1B, CRZ - III, CRZ - IVA, CRZ – IVB zones.
E.2 Importance and Need of the Proposed Project
The forecasts of total domestic demand for gas (with the exception of the conservative
IEP estimate), when compared with likely domestic supply of 150 MMSCMD, indicate a
Executive Summary For Proposed LNG & LPG Import Facilities With Captive Jetty and Breakwaters at T.
Challapalli (V), Uppalaguptam Mandal, East Godavari District, Andhra Pradesh by M/s Hindustan LNG
Ltd.
EXECUTIVE SUMMARY
Bhagavathi Ana Labs Pvt. Ltd. (a Bureau Veritas Group Company) Project Reference : IND.BH.41.16.0310/HSR 3
supply shortfall of at least 100 MMSCMD in the short term. Policy makers have pursued
two options for meeting shortfalls in gas LNG imports and transnational pipelines.
Gas consumption in India is driven by five sectors: fertilizer (34% of total gas demand in
fiscal year 2015-16), electric power (23%), refining (11%), city gas distribution, including
transport (11%), and petrochemical (8%) industries. In 2016, after five years of
consecutive declines, gas consumption increased to 55 bcm (Billion Cubic Meter),
boosted by sales to city gas distribution mainly. The country faces a widening gap
between indigenous gas production and demand, which is met by increasing Liquefied
Natural Gas (LNG) imports. LNG imports surged by 34% over 2015 to 25 bcm (Billion
Cubic Meter) in 2016, making India the fourth largest importer in the world.
E.2.2 Advantages of LNG
Regasified Liquefied Natural Gas (LNG) is having considerable advantage in terms of
environmental benefits when compared to fossil fuel like Methylated spirit, High speed
diesel, and furnace oil etc. There are many advantages of using LNG. Few of them are
listed below:
It makes it possible to use natural gas in areas where natural gas is not available via
the national delivery network or distribution system;
It is an economic source of energy when compared to black products (fuel oil and
diesel) and LPG;
It is suitable for consumer purposes such as process, steam recovery, heating and
cooking in sectors like tourism, steel, paper and ceramic;
It expands 600 times to reach its gaseous state (1 unit of LNG = 600 units of natural
gas) - large amount of natural gas can be stored and transported at low pressure;
Because it is a clean fuel, it contributes to improve product quality and reduces
maintenance costs;
60–90% less smog-producing pollutants and 30–40% less greenhouse gas
emissions; and
Less expensive than gasoline.
E.2.3 Brief Description of the Project
HLNG intends to setup LNG & LPG handling terminal to import and store liquefied LNG
and LPG. Further, HLNG intends to use pipeline and Road Tankers for regular transfer of
regasified LNG and LPG from terminal to various customers/ end users.
The Regasified LNG will be supplied to Konaseema Gas Power Limited of 445 & 820
MW capacity located in Ravulapalem, near Rajahmundry, East Godavari District, Andhra
Pradesh and also to the following gas based power generation plants located in the State
of Andhra Pradesh:
GMR Vemagiri Power Corporation Limited, 388 MW NG/ RLNG Combined Cycle Power Plant
(CCPP), Rajahmundry, A.P.
GVK’s Power Private Limited, 445 MW Jegurupadu Combined Cycle Power Plant (CCPP),
East Godavari Dist., A.P.
GVK Gauthami Power Limited, (464 MW CCPP), Pedapuram, East Godavari Dist., A.P.
Lanco Kondapalli Power Ltd., Stage-II (368 MW CCPP), Kondapalli, Krishna Dist., A.P.
Liquefied Natural Gas (LNG) is the environmental friendly fuel with a very high efficiency
and most preferred fuel. The latest trends in the advanced countries are that, all the
Executive Summary For Proposed LNG & LPG Import Facilities With Captive Jetty and Breakwaters at T.
Challapalli (V), Uppalaguptam Mandal, East Godavari District, Andhra Pradesh by M/s Hindustan LNG
Ltd.
EXECUTIVE SUMMARY
Bhagavathi Ana Labs Pvt. Ltd. (a Bureau Veritas Group Company) Project Reference : IND.BH.41.16.0310/HSR 4
transport vehicles are directly having LNG combustion facilities replacing diesel and
petrol. HLNG propose to market LNG to all the bulk Consumers.
The Government of India (GOI) wants to provide LPG connections to the BPL
households to ensure the universal coverage of cooking gas in the country to empower
women and protect their health. As per the statistical survey of the GOI, the consumer
base BPL using the LPG is estimated as about 1.5 Crores. As on date, there is no LPG
facility in the eastern part of India. This facility proposed by HLNG will support the GOI
initiatives of LPG supply to BPL households as well as to others.
E.3 Cost of the Project
Estimated project cost along with analysis in terms of economic viability of the project is
(approx.) Rs.2800 Crores (Rupees Two thousand and Eight hundred Crores only).
E.4 Environmental Setting
The study area map of 10-km radius around the proposed site is given in FigureE1. The
environmental setting of the proposed plant site is as follows:
Captive Jetty will be located in the water front of Bay of Bengal whereas the on-shore
terminal is located at an elevation of 2 to 6 m above Mean Sea Level (MSL);
The geographical co-ordinates of the proposed integrated plant range between 160
27' 57.95" N 820 05' 14.37" E;
Present land use at the proposed on-shore terminal site is D-Patta lands owned by
GoAP;
Amalapuram to Bendamurlanka Road (SH # 294) is at 8-km and Narsapuram -
Pamarru Road (NH # 216) is at 16-KM from the proposed plant boundary;
Kotipalli Railway station located at a distance of 27-km, N;
The nearest airport to the project site is located at Rajahmundry at a distance of
about 60-km, NW;
Vanateyam Godavari river is flowing at a distance of 10.5-km in the West from the
project site;
Nearest city is Kakinada (70-km, NE) and nearest town is Amalapuram (14-km, NW);
No forest blocks, Hills & Valleys, Tourist Places, Archeologically Important Places
exists within 10-km radius;
No ESA, Biosphere Reserves, Protected areas as per wildlife protected act 1972
existing within the 10-km radius of proposed project site;
The project area falls under Seismic Zone-III as per Indian Standards, IS: 1893 (Part-
1) 2002; and
ONGC Refinery (13-km, W), Cairn Energy Ltd’s crude processing facility (3.6-km,
NE) and Ravva/ KG basin (adjacent) are the industries exists in the vicinity
E.5 Resource Requirement
Resources are the means to achieve the project deliverables and its objectives. The
primary resource is obviously people with applicable skills and competencies. The
other main grouping of resources are Land, Power, Raw Material and Water
Executive Summary For Proposed LNG & LPG Import Facilities With Captive Jetty and Breakwaters at T.
Challapalli (V), Uppalaguptam Mandal, East Godavari District, Andhra Pradesh by M/s Hindustan LNG
Ltd.
EXECUTIVE SUMMARY
Bhagavathi Ana Labs Pvt. Ltd. (a Bureau Veritas Group Company) Project Reference : IND.BH.41.16.0310/HSR 5
E.5.1 Land Requirement and Status
The total land requirement for the proposed LNG terminal is 298.53 Acres. The present
land use of the land is D-Patta Government land and is in the process of allocation to
HLNG by converting it into industrial land use by Govt. of Andhra Pradesh.
E.5.2 Power Requirement
During construction, power will be drawn from State Electricity Board and temporary DG
sets. During operation phase, energy requirement will be 3 MW and shall be met through
captive gas engines using boil off gas.
E.5.3 Water Requirement
It is estimated that the water requirement during the construction stage will be 200 KLD
and approximately 70 KLD during the operation stage of FSU. During operation stage of
the FSU, it is envisaged that about 50 people will be deployed at the terminal. About 70
liters of water is consumed per person per day; as such, only about 3.5 KLD is being
used for domestic consumption. Remaining water will be used for ship supply and
miscellaneous use. LNG regasification and LPG handling do not require any water.
E.5.4 Manpower Requirement
The construction phase of the LNG terminal would generate the employment for nearly
500 managerial, skilled and unskilled workers, and during operation phase, it is
envisaged that 50 people will be deployed at the terminal.
Draft EIA For Proposed LNG & LPG Import Facilities With Captive Jetty and Breakwaters at T. Challapalli (V), Uppalaguptam Mandal, East Godavari
District, Andhra Pradesh by M/s Hindustan LNG Ltd.
EXECUTIVE SUMMARY
Bhagavathi Ana Labs Pvt. Ltd. (a Bureau Veritas Group Company) Project Reference : IND.BH.41.16.0310/HSR 6
Figure E-1: Project Location - Topo map 10 km Radius
Draft EIA For Proposed LNG & LPG Import Facilities With Captive Jetty and Breakwaters at T.
Challapalli (V), Uppalaguptam Mandal, East Godavari District, Andhra Pradesh by M/s
Hindustan LNG Ltd.
Executive Summary
Bhagavathi Ana Labs Pvt. Ltd. (a Bureau Veritas Group Company) Project Reference : IND.BH.41.16.0310/HSR 7
E.6 Waste Management & Handling
Waste management or waste disposal are all the activities and actions required to
manage waste from its inception to its final disposal. This includes amongst other things
collection, transport, treatment and disposal of waste together with monitoring and
regulation. It also encompasses the legal and regulatory framework that relates to waste
management encompassing guidance on recycling.
E.6.1 Solid Waste Management
The cargo to be handled at proposed FSU will be LNG and is only handled/transported
through pipelines. As such, cargo operations are not envisaged to generate solid waste.
Use of the facilities at the berth may however lead to small amounts of solid waste
generation. The total solid waste generated is envisaged to be about 2.5 kg/day.
Adequate facilities for collection and conveyance of municipal wastes will be provided.
The solid waste collected from the ships berthing at FSU terminal will be collected
appropriately, transported by small boats to land side regularly, and disposed from the
docks to appropriate locations identified by APPCB.
E.6.2 Wastewater Management
There will be no industrial effluent being generated from this project. Sewage generated
from domestic sources will be treated in Skid mounted STP. In case any open spillage
from tank the same will be treated by oil water separator (OWS).
E.6.3 Hazardous Waste Management
The hazardous waste comprising empty barrels, spent oils / lubricants, pipeline, pigging
wastes etc. shall be managed as per the Hazardous and Other Wastes (Management
and Transboundary Movement) Rules, 2016.
Table ES 1 – Solid Waste and Hazardous Waste
Solid Waste
Type
Source Quantity per Month Mode of Transport &
Disposal
MSW Garbage, rubbish
from unpacking,
discarded materials,
plastic materials
2.5 kg
(0.01 kg/capita/day)
Collected in bins and disposed
in consent with Municipal
Authorities; Strictly no disposal
in sea water.
Hazardous
waste
Used/ spent oils 0.5 Collected, stored and reused
E.7 Baseline Environmental Status
The baseline environmental quality has been assessed through field studies within the
impact zone for various components of the environment, viz. air, noise, water, land and
socio‐economic. Baseline environmental monitoring was carried in Post Monsoon from
October 2017 to December 2017 within 10-km radius area surrounding captive jetty and
on-shore terminal for LNG & LPG import, storage and handling facility area as core zone.
Draft EIA For Proposed LNG & LPG Import Facilities With Captive Jetty and Breakwaters at T.
Challapalli (V), Uppalaguptam Mandal, East Godavari District, Andhra Pradesh by M/s
Hindustan LNG Ltd.
Executive Summary
Bhagavathi Ana Labs Pvt. Ltd. (a Bureau Veritas Group Company) Project Reference : IND.BH.41.16.0310/HSR 8
E.7.1 Air Environment
Metrological data was collected by installing weather station and major parameters
recorded like temperature, relative humidity, rainfall, wind speed and predominant wind
direction.
Ambient Air Quality monitoring (AAQM) has been estimated at 8 locations during the
study period and AAQM locations were selected based on the local meteorology. The
AAQ within 10-km radius is given in the Table ES 2.The AAQ is in general conforming to
the limits.
Table ES 2 – Air Quality
Sl. No. Parameter Ranges in Post monsoon 2017 Limits as per G.S.R826 (E), dated 16.11.2009
1 PM2.5 µɡ/m3 18.8 – 22.2 60
2 PM10 µɡ/m3 44.0 – 57.5 100
3 SO2 µɡ/m3 7.9 – 14.0 80
4 NOX µɡ/m3 9.0 – 16.0 80
E.7.2 Water Environment
Physico-chemical Parameters of groundwater and surface water are analyzed and
compared with the standards for assessing the baseline status of water environment and
identification of impacts due to proposed developmental activities. In order to assess the
water quality, standard methods (IS Standards10500-2012) were followed for sample
collection, preservation and analysis in the laboratory.
Table ES 3 - Groundwater Quality
Sl. No Parameter Units
Limits as per IS:10500 Ranges in Post Monsoon 2017
Acceptable Limits
Permissible Limits
1 pH - 6.5-8.5 No Relaxation 7.37 – 8.13
2 Electrical conductivity
µs/cm - - 1040 – 25200
3 TDS mg/l 500 2000 676 – 16380
4 Chloride mg/l 250 1000 125.0 – 7964.0
5 Fluoride mg/l 1 1.5 0.2 – 0.8
6 Sodium mg/l - - 145.3 – 3284
7 Nitrate mg/l 45 No Relaxation 0.4 – 46.4
Table ES 4 - Surface Water Quality
Sl.No Parameter Units Limits as per IS:10500
Ranges in Post Monsoon 2017 Acceptable Limits
Permissible Limits
1 pH - 6.5-8.5 No Relaxation 7.38 – 7.91
2 Electrical conductivity
µs/cm - - 492 – 39420
3 TDS mg/l 500 2000 319.8 – 25623
4 Chloride mg/l 250 1000 48.5 – 11512
5 Fluoride mg/l 1 1.5 0.1 – 0.6
6 Sodium mg/l - - 46 – 5893
7 Nitrate mg/l - - 0.6 – 0.8
Draft EIA For Proposed LNG & LPG Import Facilities With Captive Jetty and Breakwaters at T.
Challapalli (V), Uppalaguptam Mandal, East Godavari District, Andhra Pradesh by M/s
Hindustan LNG Ltd.
Executive Summary
Bhagavathi Ana Labs Pvt. Ltd. (a Bureau Veritas Group Company) Project Reference : IND.BH.41.16.0310/HSR 9
E.7.3 Soil Characteristics
Seven soil samples were collected from 30 cm depth using an auger and homogenized
after quartering in line with IS: 2720 and Methods of Soil Analysis, Part-1, 2nd edition,
1986 of (American Society for Agronomy and Soil Science Society of America). The
homogenized samples were analyzed for physical and chemical characteristics. The
available nitrogen in the soil is ranging from 0.73 Kg/Ha – 3.92 Kg/Ha, available
Phosphorous is ranging from 5 kg/Ha – 2909 Kg/ha, available Potassium from 230.3
kg/ha - 1803 kg/ha, organic carbon from 0.13 - 3.14 %, and organic matter from 2 – 5.42
%.
E.7.4 Noise Levels
The noise level monitoring at nine selected locations on 24 hourly basis was conducted
once during the study period. The results are compared with the standards notified by
MoEF&CC in 2000 and found to be well within the standards. The noise levels in the
study area ranging from 39.5 dB to 64.3 dB in daytime and 31.8 dB to 55.8 dB at night
time.
E.7.5 Socio Economic Environment
Socioeconomic survey was carried out to know the infrastructural activities amenities
available within 10 km radius of plant. The information regarding facilities available and
the opinion of the people was sought by floating questionnaires and interaction with the
people so that the impact due to the project wrt social aspects could be evaluated and
actions / measures could be taken up for the benefit of the people (economically and wrt
quality of life) and the project.
E.7.6 Land Use Land Cover
The land use and land cover analysis has been carried out within 10 Km radius around
the project site, using satellite imagery IRS Resources at 2A, Path 103 row, 61 sub scene
B, image dated on 20th January 2017. From the classified image, it could be found that
almost half (54.14%) of the study area is covered by sea, Agricultural land: 24.72 %,
built- up area: 2.39 %, wetlands: 1.02%, wastelands 0.15 % and others 17.67%.
In the landward study area land-use is marked by rural area, intensive agriculture
activities with majority of double cropping paddy fields as well as coconut, banana,
Coastline areas have mix of mangroves, aquaculture ponds and saltpans. The project
area is marked with the presence to major industries i.e. ONGC and Cairn Energy Ltd.
E.8 Impact Assessment
The proposed project will have impact on Ambient Air Quality, Water resources and water
quality, Noise, Ecology, and Socio Economic Environment in surrounding area due to the
generation, handling and disposal of stack emissions, liquid effluents and solid wastes
during construction and operation phase and various related industrial activities.
The impacts and mitigation measures at Construction Phase & Operation Phase is
outlined below. The proposed manufacturing plant may have adverse impact on
surrounding environment in a number of ways in absence of mitigation measures.
Therefore, mitigation measures and environmental management plan have been
suggested for environmental components likely to be affected. The detailed impact
Draft EIA For Proposed LNG & LPG Import Facilities With Captive Jetty and Breakwaters at T.
Challapalli (V), Uppalaguptam Mandal, East Godavari District, Andhra Pradesh by M/s
Hindustan LNG Ltd.
Executive Summary
Bhagavathi Ana Labs Pvt. Ltd. (a Bureau Veritas Group Company) Project Reference : IND.BH.41.16.0310/HSR 10
assessment at the time of construction and operations and its mitigation measures is
given in Table ES 5.
E.9 Analysis of Alternatives
In regards with alternatives, following are the main constraints/factors that are
considered for any development activity.
The choice or alternatives for any additional operations is always confined within
the Port Water Limits or immediately adjacent to it. This choice is always the best
choice to meet the requirements as well as to reduce cost and improve safety.
All additional facilities such as berths, land reclamation, etc. are considered due
to possible business expansion needs and alternatives models and technological
considerations or technological up gradation including changing environmental
and other legal compliances.
E.9.1 Site Selection
The selected site T.Challapalli in East Godavari District is selected based on the various
factors such as;
Proximity to coastline
Proximity to customers
Bathymetry and water depth
Safety to neighboring areas
Topography
Proximity to shipping routes
Capital Expenditure
Operational Cost
Draft EIA For Proposed LNG & LPG Import Facilities With Captive Jetty and Breakwaters at T. Challapalli (V), Uppalaguptam Mandal, East Godavari District,
Andhra Pradesh by M/s Hindustan LNG Ltd.
Executive Summary
Bhagavathi Ana Labs Pvt. Ltd. (a Bureau Veritas Group Company) Project Reference : IND.BH.41.16.0310/HSR 11
Table ES 5 – Impact Assessment Construction and Operation Phase
Construction Phase Operational Phase
Attribute Anticipated Impacts
Mitigation Measures Proposed Anticipated Impacts Mitigation Measures Proposed
Land
Transportation of construction material
Existing roads shall be used for the construction material transportation; the port will have an operational inland water transport network, material transportation will also be carried out using the waterways (via barges, etc.).
Discharges from ships on the land
The quantity of sewage generation would be very less. The FSU unit will be fitted with septic tank or equivalent. The ships and barges shall comply with MARPOL convention 73/78. No waste/wastewater shall be discharged directly on land hence; no significant impact on land is envisaged.
Land Acquisition There will be no private land procurement for the project; hence there will be no direct Project Affected Areas (PAPs), Project Affected Families due to this project (PAFs).
Shoreline changes – Erosion/accretion
The shoreline/coastline changes such as erosion/accretion is usually expected due to the development of marine structures such as breakwaters, groynes, jetties, wharfs, etc. The proposed FSU development consists of marine terminal inclusive of berthing and mooring facilities for FSU, LNG carrier, offloading & transfer of LNG from FSU to onshore Re-gas terminal, and pipeline for gas send-out. The transportation transfer of RLNG will be through from the FSU onto the land-based tanks, so the subsea export is not proposed for the project. It is concluded that the project will not interfere with the sediment transport or cause shoreline changes – erosion/accretion.
Changes in land pattern
Since the present project is an offshore and onshore development and located within area under the jurisdiction of Government of Andhra Pradesh, impact is not expected on this account.
Water quality due to cargo LNG operation
The proposed LNG terminal will be received from the offshore and the regasification will be done on the land based through FSU. The Offshore FSU will have bilge water (oily water) management facility. Hence, during normal operations, there are no liquid effluents except the sanitary water (sewage) is envisaged at Offshore FSU
Water
Impacts due to wastewater generation
Vessels involved in construction and other construction equipment are a possible cause of oil spill, garbage discharge, etc. However, mitigation measures have been recommended as part of the Environmental Management Plan to ameliorate even the marginal impacts
Wastewater Discharges The discharges will meet the requirements of the Marine Environment Protection Committee (MEPC159 (55)) and General Standards for discharge of Environment Pollutants GSR 422(E); The Environmental (Protection) Rules, 1986.
Impacts on existing water resources
As the facility is proposed in offshore and due to easy availability of seawater, the heating medium for regasification, firefighting and
Draft EIA For Proposed LNG & LPG Import Facilities With Captive Jetty and Breakwaters at T. Challapalli (V), Uppalaguptam Mandal, East Godavari District,
Andhra Pradesh by M/s Hindustan LNG Ltd.
Executive Summary
Bhagavathi Ana Labs Pvt. Ltd. (a Bureau Veritas Group Company) Project Reference : IND.BH.41.16.0310/HSR 12
Construction Phase Operational Phase
Attribute Anticipated Impacts
Mitigation Measures Proposed Anticipated Impacts Mitigation Measures Proposed
fresh water supply on board will be met from seawater. As such, impacts on existing water resources are not anticipated due to development of the proposed FSU based import terminal.
Marine Environment
Littoral Drift/Sediment Transport
The offshore marine structures will be pile supported which will allow transmission and transport of sediment, which in any case is not significant at approximately 15 m depth. Since sediment transport remains unchanged with the introduction of pile supported structures, it is concluded that proposed development of the marine structures will not interfere with the alongshore sediment transport.
Aqueous discharges sufficient reception facilities will be provided to receive the residues and oily mixtures generated from ship operations according to provisions of the International Convention for the Prevention of Pollution from Ships, 1973/78 (MARPOL). In addition, reception facilities for garbage, waste oil and bilge water from the ships shall also be provided.
Turbulence – Changes in DO levels
DO levels in bottom sediments, which are usually low, would increase during trenching activity. Changes in DO levels are likely to result in localized and short-term impacts on marine ecology.
Wastewater from sanitary system
The toilet facility will be provided at the berth to the Toilet facility will be provided inside the terminal and not on berth. Toilet facility will be used by the workers on the shift duty. The quantity of sewage generation would be very less.
Removal of Benthic Communities associated with Bottom Sediments:
To mitigate impacts on marine ecology, measures such as selection of trenching equipment, environmental monitoring and regulating activities based on monitoring results will be adopted.
Due to LNG (Cargo) Spills during Handling
Spills are not anticipated to occur during normal operations, as the cargo LNG will be handled by specialized loading arms (Marine Transfer Arms). In the event of accidental spill of LNG during transfer from / to the ships, LNG is automatically evaporated in the atmosphere and leaves insignificant impact on the marine water quality, sediment quality and ecology. LNG spill and gas detection system will be provided.
Changes in seabed profile
A post construction/implementation survey of the sub seabed pipeline is suggested in the Environmental Management Plan to mitigate the impacts. During the survey, stretches that may become unstable due to adverse weather conditions will be stabilized along with restoration of the altered seabed profile if any, which are unlikely. It will be ensured that barges / workboats have
Oil spills during fueling:
In the event of accidental oil spills during fueling of port crafts/service barges and accidental spillage of oil from LNGC or FSU offshore terminal, the marine water quality in the harbor basin will be impacted. To minimize the impacts on marine water quality, the spills will be recovered.
Draft EIA For Proposed LNG & LPG Import Facilities With Captive Jetty and Breakwaters at T. Challapalli (V), Uppalaguptam Mandal, East Godavari District,
Andhra Pradesh by M/s Hindustan LNG Ltd.
Executive Summary
Bhagavathi Ana Labs Pvt. Ltd. (a Bureau Veritas Group Company) Project Reference : IND.BH.41.16.0310/HSR 13
Construction Phase Operational Phase
Attribute Anticipated Impacts
Mitigation Measures Proposed Anticipated Impacts Mitigation Measures Proposed
slop tanks for collection of liquid / solid waste generated on board. Discharge of wastes into sea will be prohibited. Trenching activity will be regulated during rough sea conditions.
Impact due to Cold Seawater Discharge
The temperature of used seawater will be around 5 - 100C below the ambient sea water temperature. The volume and salinity of sea water will remain same as that of the intake water. The environmental impact, both long-term and short-term, of this cold water emission needs to be considered for the area where it is supposed to operate. As such, no major impact is anticipated as the quantity of discharge will be very less
Ships shall conduct ballast water exchange at least 200 nautical miles from the nearest land and in water at least 200 m in depth prior to calling at a port. Ships shall carry out ballast water exchange with an efficiency of at least 95% volumetric exchange. Master and crew of the vessel shall be familiar with the essential shipboard procedures relating to ballast water. Each ship shall have on board a ballast water record book which may be an electronic recording system. Port officers may inspect the ballast water record book and ask for relevant copies of record book.
Air Transportation of construction materials
Movement of material will be mostly during non-peak hours (4:00 PM to 8:00 PM) and regulated during peak hours (6:00 AM to 10:00 AM). Mobile equipment such as intermittently used machines and transport vehicles will be either switched off or throttled down to a minimum.
Power generators Due to the high efficiency and the clean fuel used in a dual fuel engine in gas mode, the exhaust gas emissions when running on gas are extremely low. In the proposed offshore LNG FSU sufficient availability of gas in the form of BoG and from storage ensures that most of the time the generators will be running with Natural Gas as Fuel.
Draft EIA For Proposed LNG & LPG Import Facilities With Captive Jetty and Breakwaters at T. Challapalli (V), Uppalaguptam Mandal, East Godavari District,
Andhra Pradesh by M/s Hindustan LNG Ltd.
Executive Summary
Bhagavathi Ana Labs Pvt. Ltd. (a Bureau Veritas Group Company) Project Reference : IND.BH.41.16.0310/HSR 14
Construction Phase Operational Phase
Attribute Anticipated Impacts
Mitigation Measures Proposed Anticipated Impacts Mitigation Measures Proposed
On-site vehicle speeds will be controlled to reduce excessive dust suspension in air and dispersion by traffic. Construction equipment and transport vehicles will be periodically washed to remove accumulated dirt.
LNG Unloading Operations
Potential sources of emissions of vessels (LNGC) are from the Main Engine (ME) and Auxiliary Engines (AE) and others such as boilers, emergency diesel engines and waste incinerators. (Emissions from others are relatively very small and can be considered negligible) MEs will be used primarily for ship propulsion.
Emergency emissions In emergency situations due to fire/etc., the vapor will be released to the atmosphere through an elevated flare or cold vent system (on topside), including a knock-out drum, for safe disposal. The Flare system will be designed according to international standard. During Normal operation there is no flaring envisaged. It is proposed to install Emergency Diesel Generator Set also. As all these emissions are expected only during emergency situation.
Fugitive Emissions The valve ratings shall be in accordance with ASME standards, and be fire-safe with metallic or soft seals. Insulation suitable for cryogenic service shall be specified for all lines 0°C and below. In addition, insulation may be required for some non-cryogenic services. Fugitive emissions may be controlled by adopting appropriate control and precautionary measures.
Noise Construction Activities
During construction, noise levels will be maintained below threshold levels stipulated by Central Pollution Control Board (CPCB) by selecting appropriate equipment, machinery and using enclosures. Procurement of machinery / construction equipment will be done in accordance with specifications conforming to source noise levels less than 85 dB (A).
Operation Activities Noise attenuation will be practiced for noisy equipment by employing suitable techniques such as acoustic controls, insulation and vibration dampers. The attenuation devices will be properly maintained.
Rotation of personnel will be adopted to minimize the exposure to high noise levels.
Periodic maintenance of the equipment to be used will be carried out. Worn out parts will be replaced and
Draft EIA For Proposed LNG & LPG Import Facilities With Captive Jetty and Breakwaters at T. Challapalli (V), Uppalaguptam Mandal, East Godavari District,
Andhra Pradesh by M/s Hindustan LNG Ltd.
Executive Summary
Bhagavathi Ana Labs Pvt. Ltd. (a Bureau Veritas Group Company) Project Reference : IND.BH.41.16.0310/HSR 15
Construction Phase Operational Phase
Attribute Anticipated Impacts
Mitigation Measures Proposed Anticipated Impacts Mitigation Measures Proposed
All haul roads (for truck transport and other vehicles) within the boundary and outside will be maintained properly to avoid excessive noise levels from Engine acceleration and deceleration.
Noise levels will be monitored at regular intervals during construction phase of the project.
Periodic maintenance of the equipment to be used in the developmental works will be carried out. Worn out parts will be replaced and rotating parts will be lubricated to minimize noise emissions.
Personnel exposed to noise levels beyond threshold limits will be provided with personal protective equipment (PPE) like earplugs, muffs, etc. especially construction personnel involved in pile driving operations. Rotation of personnel will also be adopted.
Noise attenuation will be practiced for noisy equipment by employing suitable techniques such as acoustic controls, insulation and vibration dampers. The attenuation devices will be properly maintained throughout the construction period.
rotating parts will be lubricated to minimize noise emissions. Ambient noise levels will be monitored at regular intervals during operation phase of the project. Labelling equipment at a prominent location to indicate the approximate level of noise it generates in operation will also be done. Where the reading is less than 85 dB, then the equipment should be labelled using the green colored label with no specific noise exposure precautions required for usage of less than 8 hours. Where the reading is equal to or greater than 85 dB, then the equipment should be labelled using the red colored label and the operator should wear hearing protectors. In addition, those persons working within 5 m of the equipment should also wear hearing protectors or take other appropriate control measures to protect against noise.
Solid waste & Hazardous waste management
Construction and other waste
Construction waste will be properly segregated and utilized Construction waste which can be re-cycled will be given to Appropriate agency.
General residual waste generated on-site will be collected in waste skips and separated
A local authorized waste recycler will be employed to remove general residual waste from the site, separately from construction waste and hazardous wastes, on regular basis to minimize odor, pest and litter impacts. The burning of refuse at construction sites will be prohibited.
Draft EIA For Proposed LNG & LPG Import Facilities With Captive Jetty and Breakwaters at T. Challapalli (V), Uppalaguptam Mandal, East Godavari District,
Andhra Pradesh by M/s Hindustan LNG Ltd.
Executive Summary
Bhagavathi Ana Labs Pvt. Ltd. (a Bureau Veritas Group Company) Project Reference : IND.BH.41.16.0310/HSR 16
Construction Phase Operational Phase
Attribute Anticipated Impacts
Mitigation Measures Proposed Anticipated Impacts Mitigation Measures Proposed
from construction waste. Hazardous materials such as lubricants, paints, compressed gases, and varnishes etc., will be stored as per the prescribed/approved safety norms. The construction site will be secured by fencing with controlled/limited entry points.
If removal of waste materials at the end of the working day is not possible, the materials should be covered with tarpaulin or similar. Hazardous wastes will be disposed at nearest Treatment, Storage and Disposal Facility (TSDF) through approved APPCB vendors. Hazardous materials will be stored as per prescribed safety norms in locations with restricted entry and with fire-fighting facilities.
Socio cultural impact
R&R Issues The proposed project has no settlements at the project area, and the nearest habitation is located 5 Km away from the FSU location. Hence the proposed activity is not envisaged to bring any significant or additional negative impacts on the activities of other users. The impact on nearby settlements during construction phase will be due to air pollution and noise generating activities. However, the activities are limited to the construction phase and will cease upon completion of the construction. Hence, this impact is considered to be negligible and therefore can be classified as insignificant.
Public Health and Safety The proposed activity consists of handling/storage of LNG and re-gasified gas. Suitable safety/mitigation measures and procedures will be followed by HLNG and developer while carrying out these activities to minimize any potential adverse impacts. HLNG has in place an Oil Spill Response Plan, an integrated fire protection System, and a Disaster Management Plan. All these will help minimize/avoid the probability of occurrence of emergency situations and mitigate the impacts
Draft EIA For Proposed LNG & LPG Import Facilities With Captive Jetty and Breakwaters at T. Challapalli
(V), Uppalaguptam Mandal, East Godavari District, Andhra Pradesh by M/s Hindustan LNG Ltd.
Executive Summary
Bhagavathi Ana Labs Pvt. Ltd. (a Bureau Veritas Group Company) Project Reference : IND.BH.41.16.0310/HSR 17
E.9.2 Technology Selection
The three sources of thermal energy typically used to warm LNG from a liquid to a gaseous
state are ambient air, natural gas (heat from combustion), and seawater. The basic types of
vaporization systems that utilize these sources of thermal energy include:
Intermediate Fluid Vaporizers
Ambient Air Vaporizers
Open Rack Vaporizers
Shell and Tube vaporizers
Submerged Combustion Vaporizers
The final technology to be adopted for proposed FSU will be selected by the PPP developer
after further analysis.
E.10 Environmental Monitoring Program
Environmental monitoring program is a vital process of any management plan of the
development project. This helps in signaling the potential problems resulting from the
proposed project and will allow for prompt implementation of effective corrective measures.
The environmental monitoring will be required for the construction and operational phases.
The Environmental Monitoring Program has been framed for the proposed Captive jetty, and
for the operations involving on the land based for LNG and LPG. Recognized agencies are
engaged for carrying out the above stated monitoring works. A centralized environmental
monitoring cell has been established for monitoring of important and crucial environmental
parameters which are of immense importance to assess the status of environment during
LNG Terminal operation.
E.11 Additional Studies (RA&DMP)
In additional studies, Risk Analysis followed by DMP from installation of storage tanks for
storage capacity plant has been prepared, which will help in identifying the vulnerable points
and to promote towards preparedness to counter any mishap. For meeting the emergencies
caused by major accidents, planning response strategies are termed as Disaster
Management Plans (DMPs). Risk analysis and disaster management plant have been
prepared and incorporated in EIA Report. Risk Assessment output is provided below.
E.11.1 Risk Assessment
Composition of LNG is 90% Methane, 7% Ethane, 2% Propane and 1% Higher
Hydrocarbons. LNG cannot catch fire unless until there is the right mix of LNG Vapor in the
air. (5-15%) and a source if ignition. As auto ignition temperature is 595oC, it will not catch
fire on its own. The storage tanks used for LNG are Double containment tanks.
The risk due to LPG is 0.1 LEL i.e 1600ppm is reaching the maximum distance of 7-Kms The
occurrence of this is very rare and unlikely. The fatal radiation due to fire accident will be
within the 0.7-km and there is no habitation within 0.7 km.
The LNG and LPG Ships failure probability per annum of ship docked for unloading in the
HLNG Premises will be only for two days in a month. So the frequency of accident will be
very less and unlikely due to the safety measures to be implemented during operation phase.
Draft EIA For Proposed LNG & LPG Import Facilities With Captive Jetty and Breakwaters at T. Challapalli
(V), Uppalaguptam Mandal, East Godavari District, Andhra Pradesh by M/s Hindustan LNG Ltd.
Executive Summary
Bhagavathi Ana Labs Pvt. Ltd. (a Bureau Veritas Group Company) Project Reference : IND.BH.41.16.0310/HSR 18
Nearby Habitation is Nakka Rameswaram Hamlet at a distance of 1 km from the tank farm.
The connection of the loading arms to the manifold of the ship shall be automated. This will
help in disconnecting the vessel quickly. Hence loading arms with Quick-connect-Disconnect
facility shall be used.
E.12 Project Benefits
The proposed LNG terminal has benefits depending on the market potential and energy
security and also the induced development to the project area. The broad benefits is given
below;
Safe, cost effective and environment friendly as compared to other fuels;
Combustion of re-gasified LNG emits negligible or no Sulphur dioxide, thereby will
lead to clean burning;
Because of its clean burning, it doesn’t leave behind any unpleasant soot, ash, or
odors;
It is reliable as the pipeline system can’t be easily damaged by weather or affected
by weather conditions, in comparison to oil;
In case of minor spillage LNG will evaporate and disperse quickly, leaving no residue
behind and therefore requiring no environmental clean-up;
Reduction in carbon emissions and increases conservation of coal resource can be
achieved.
Promote opportunities for further industrial growth in the region. It will indirectly assist
in the creation more employment to the local population. This in turn will lead to
employment generation and meeting the occupational requirements of the local
population.
The proposed facility will add to the revenue of both the State and Central
Government in the form of various taxes and duties. It will help to spur additional
industrial and commercial growth that would benefit from the availability of Natural
Gas and lower energy prices, as it is comparatively cheaper than alternative
fuels/feedstock's e.g. Naphtha, Furnace Oil, LSHS, Light Diesel Oil, LPG.
Project development will attract investments in the region and thereby contribute to
economic growth.
E.13 Overall Conclusion of the Proposed Project
The proposed Project is Environmentally, Technically and economically feasible with respect
to the following attributes;
LNG plays an important role for the diversification of gas supplies and for the
establishment of a global market; both factors are beneficial for the security of supply;
The LNG market is already very dynamic and is becoming more as the number of market
participants, projects and operations increases. Low transport costs in relation to prices
and spare shipping capacity are much contributing to the globalization of LNG trade;
Since it has been liquefied, LNG does not include H2O, CO2 or incondensable agents.
Therefore, LNG has better energy qualities corresponding to a Gross Calorific Power
(GCV) of approximately 10,000 kcal/m3.
Draft EIA For Proposed LNG & LPG Import Facilities With Captive Jetty and Breakwaters at T. Challapalli
(V), Uppalaguptam Mandal, East Godavari District, Andhra Pradesh by M/s Hindustan LNG Ltd.
Executive Summary
Bhagavathi Ana Labs Pvt. Ltd. (a Bureau Veritas Group Company) Project Reference : IND.BH.41.16.0310/HSR 19
The comparison of LNG based power plants and that of other fossil fuel (coal and LSHS/
Naphtha) based thermal power plants with respect to fuel efficiency and emissions of
conventional pollutants indicate that the LNG based plants do not generate conventional
pollutants (SPM & SO2) except NOx.
Apart from fulfilling the immediate shortage of natural gas (cleaner fuel) for power
generation, the RLNG supply will also contribute indirectly to food security of the region,
state/ nation by enhancing fertilizer manufacturing capability with a cleaner feedstock.
The proposed project will provide availability of additional quantum of natural gas to meet
industrial, automobile and domestic energy requirements. This will have a direct positive
effect on the development of Andhra Pradesh state income generation base. Natural gas
supply will partially replace fuel-oil based energy production which will also have an
indirect positive impact on the environment by reducing the emission of air pollutants that
result from combustion of oil.
The project proponent will develop plans to upgrade skills amongst the local community
to improve their employability prospects. As a matter of policy, the project proponent will
aim to maximize employment of local personnel meeting the required skill set during
construction and operation phases.
The project proponent is committed to improve the community services like sanitation,
road development, drinking water etc. through development activities that are
channelized under Corporate Social Responsibility.
Concluding Remarks
Thus it can be concluded on a positive note that after the implementation of the
mitigation measures, Environmental Management and Monitoring Plans as enumerated
above the normal operation of Hindustan LNG Limited will have no significant impact
on environment and the project will be benefitted to local people with an economic
growth in state/ country level.
E.14 No Project Scenario
In the absence of proposed project, the existing electricity / power shortage will adversely
impact economic development of the state. The requirement of fuel or feedstock for
power, fertilizer and other industries would likely remain unfulfilled. In case the power
requirement is met through other fossil fuels, viz. coal, diesel etc., this would cause
adverse impacts on the environment as discussed in earlier sections. Compared to a “No
Project Scenario”, this project is expected to deliver significant higher value to the society
in an environmentally sustainable manner with the implementation of proposed EMP and
risk mitigation measures.