    Kosovo Energy System

  • 8/3/2019 Kosovo Energy Potential

    2/14

    Energy Situation

    Production of electricity is monopoly ofKosovo Energy Company (KEK)

    Main energy sources

    Coal fired power stations

    Kosovo A 1960s

    Kosovo B 1980s

    Hydroelectric StationsGazivoda

  • 8/3/2019 Kosovo Energy Potential

    3/14

    KEK production capability 2003

    Units ProductionCapacity(MW)

    Remarks

    Kosovo A1 30

    Kosovo A2 100 Out of service since November2002

    Kosovo A3 100

    Kosovo A5 100

    Kosovo B1 250 Damaged by lightning strike July2002 expected return 2003

    Kosovo B2 250 Damaged by lightning strike July2002- expected to return to service

    2003

    Gazivoda (2units)

    35 Out of service

  • 8/3/2019 Kosovo Energy Potential

    4/14

    Energy Reserves

    Coal/Lignite reserves Bardh mine

    Mirash mine

    Drenica, Dukagjin and Anamorava

    Uranium Reserves Gjilan (Stublovaq)

    Thermal water reserve Kllokot,

    Banj e Pejs

  • 8/3/2019 Kosovo Energy Potential

    5/14

    Lignite Mining OperationKey Sections

    Mine Mirash (East and West)

    Mine Bardh

    Transportation systems in mines

    Transportation systems from mines to powerplants

    Separation plants Kosovo A

    Separation plants Kosovo BTransportation system to neighboring countries

  • 8/3/2019 Kosovo Energy Potential

    6/14

    Coal ReservesMirash mine Good

    East West side minesworking surface area of around 30 km21500 employeesMain supplier to Kosovo A power plantPresent reserve of 4 million tones/expandable to 35 mil tonesonce rehabilitatedMain machines in good condition

    NeedsUnstable due to lack of preservation

    Ancillary plant to cover numerous support operationsMachines & belts need to be repositioned (time consuming)Machines req.

    bulldozers, pipe layers, side cranes, front loaders and smallexcavators

  • 8/3/2019 Kosovo Energy Potential

    7/14

    Coal Reserves

    Mine Bardh Good

    working surface area of 4.5 km22512 employees

    main supplier to Kosovo B plantnew equipment from Holland and Germany arrivedPresent reserve of 35 mil tones

    Needsneglect over last 10 years has caused loss of conveyor beltsdue to slippageangle of mining needs to be changed (time consuming)more new machinery and parts for the old onesAncillary plant to cover numerous support operationsnew access routes

  • 8/3/2019 Kosovo Energy Potential

    8/14

    Coal Production

    Improvement of overburden removal processat both mines

    Install better conveyor belts

    Better machineryTogether have around 70 million tons currentcapability

    Overall there is around 11 billion tons of coalvarying quality

  • 8/3/2019 Kosovo Energy Potential

    9/14

    Ancillary Plants

    Need because support main excavators

    Ground preparation

    Positioning of conveyors Preparing roads

    New 8 ancillary machines have been

    delivered to both minesStill need more machines at aprox. cost

    of 7 million

  • 8/3/2019 Kosovo Energy Potential

    10/14

    Overland Transport

    Use of rubber conveyor belts

    Needs fixing up

    Mirash

    Bardth

    Kosovo A

    Kosovo B

    6km Conveyor Belt

    8km Conveyor Belt

  • 8/3/2019 Kosovo Energy Potential

    11/14

    Coal Quality

    Low quality lignite

    Quality ranges from 6500 kg/kJ - 8500 kg/kJ

    Ash content is 25%

    Moisture content is 50%

    Sulfur Content under 1%

    Overburden to coal ratio vary 1 to 1 - 3 to 1

    (3 cubic meters of overburden to 1 ton of lignite)

    Heat base cost for Kosovo lignite is $ 1.3/GJ compare to$2/ton of coal that Western Europe pays to import

  • 8/3/2019 Kosovo Energy Potential

    12/14

    Energy Sector Money Needs

    Total costs estimated by KEK Director Mr A.Mazreku in 2000 Mine Bardh

    25,000,000 EURO

    Mine Mirash40,000,000 EURO

    Seperation and Drying Plant35,000,000 EURO

    Total spending of 100,000,000 EURO on minerepairTotal estimated cost for all damages to the KES 311,000,000 EURO

  • 8/3/2019 Kosovo Energy Potential

    13/14

    Transportation

    Roads

    Mirash mine road is 68,10 km

    Bardh mine road is 59,50 km

    Reconstruction of mine roads started in 2001 Overall roads need improvement if export is to be

    made this way

    Railroads

    Good shape

    Would need access to the mines

    Connected to the neighborhood countries

  • 8/3/2019 Kosovo Energy Potential

    14/14

    Export Possibilities

    Good EU imported approx 154-mil mt of coal in 2000 (80%

    of its fuel)

    Higher oil prices

    Italy, Greece, Bulgaria, Romania depend on importfor their energy needs

    Consumption at 243-mil MT last year

    Gasification

    Bad Europe sees coal as dirty inefficient energy source

    Green revolution