Management of Change (Maintenance Department)
Document ChangeTest Run AuthorizationSubtle ChangeTemporary RepairSub HSE (M)
Controlled Documents
• Mechanical AdministrativeProcedures
• Mechanical Work Procedures
• Area Maintenance ManagementManuals
• Job Plans
• Area Specific StandardOperating Procedures
• Centralized maintenancemanagement system (CMMS)technical database (SAP)
• Equipment specificationdocument/data sheet
• Fixed equipment and machineryreliability
• hprogramme documentation
Final Approval By
• Maintenance Manager
• It includes any kind of changesand revisions in controlleddocuments.
• Any additions or deletions tocontrolled documents also fallunder this catagory .
Examples
• Changing Teporary Repair intopermanent modification.
• For example: Continuous dropwise leakage through furnace
ID Fan U-201 turbine side journal bearing
• New process facilities
• For example: Installation ofElectro chlorination Plant
• Safety devices / systemmodifications
• Changes to material ofconstruction
• For example: Plasma coatedwear rings for 1st, 2nd, 4thstage in P-02 B
• Reinforcement of CDR blowerU-801 inlet guide plate
• New civil facilities required
• For example: Construction ofFM Shacks
• Change in dimensions ofequipment or drawing
Final Approval By
• Sub-HSE (M) Chairman
• Test Run Authorization is required torecord the behaviour of differentparameters after a change isperformed on an equipment or
troubleshooting• TRA is also required to test run t he
plant to establish increasedproduction rates.
• It is a permanent change.
• It includes all the changes which are notreplacement in kind.
•
Any permanent change in processspecifications, change in P&IDs) andsafety critical equipment is not coveredin subtle change
• It is a temporary change.
• It includes all the changes carried outin emergency situations.
• It is for a limited period of time.• Debox date is mentioned on the
temporary repair form and repairshould be reverted before that date
Examples
• Box up of leaks
• Temporary Modif ications
• For example: Temporarymodification required on P-3001
A/B nitrogen vent line• Temporary arrangement for oil
make up at scrapper gear box atH-01 A/B
• Equipment replacement or repairusing non-documented spares
• Replacement of any spares withanother spare which is notrecommended by OriginalEquipment Manufacturer.
• For example: Wear ring materialchange from cast iron to SS410 at11-P-553 B
• Flushing of lines with a fluid notspecified in the procedures because
of unavailability.
Final Approval By
• Sub HSE (M) Chairman
Examples
• Replacement of different brand bearingbut of same type
• For example: Use of FAG bearing insteadof SKF make at 11-H-421
•
Replacement of gasket.(If material isupgraded.
• Installation of a higher grade piping inplace of existing system.(For non-hydrocarbon services)
• Relocation/extension of drains/samplepoints(if open space)
• Replacement of type of valves on drainlines only(if material is upgraded andservice is non-hydrocarbon)
• K-02 compressor packing line valveremoval
• Change of material towards a bettermetallurgy
• Adjustment / extension of monkey ladder
/ support structure, to improveaccessibility(with OSHA standards)
• Change of orientation of valve handwheels
Final Approval By
• Maintenance GL & Operations GL
Applicable to
• The plant is to be operated withindesigned authorized limits, asdetailed in the equipmentprocedures
• The equipment is to be operatedwith some change in manufacturerrecommendations
• For example: P-1403Bintermediate shaft materialchange & In-house machining ofBar
• Startup or shutdown with approvalof new or changed, facilities orprocedures.
Final Approval By
•Sub HSE (M) Chairman(Maintenance Department)
• It is a permanent change
• It includes all the modifications to theplant facilities.(examples given below)
• Any change in already approvedprocess specification, pipe isometrics,change in P&IDs or drawings of aproject also falls under this catagory
-