    Management of Change (Maintenance Department)

    Document ChangeTest Run AuthorizationSubtle ChangeTemporary RepairSub HSE (M)

    Controlled Documents

    • Mechanical AdministrativeProcedures

    • Mechanical Work Procedures

    • Area Maintenance ManagementManuals

    • Job Plans

    • Area Specific StandardOperating Procedures

    • Centralized maintenancemanagement system (CMMS)technical database (SAP)

    • Equipment specificationdocument/data sheet

    • Fixed equipment and machineryreliability

    • hprogramme documentation

    Final Approval By

    • Maintenance Manager

    • It includes any kind of changesand revisions in controlleddocuments.

    • Any additions or deletions tocontrolled documents also fallunder this catagory .

    Examples

    • Changing Teporary Repair intopermanent modification.

    • For example: Continuous dropwise leakage through furnace

    ID Fan U-201 turbine side journal bearing

    • New process facilities

    • For example: Installation ofElectro chlorination Plant

    • Safety devices / systemmodifications

    • Changes to material ofconstruction

    • For example: Plasma coatedwear rings for 1st, 2nd, 4thstage in P-02 B

    • Reinforcement of CDR blowerU-801 inlet guide plate

    • New civil facilities required

    • For example: Construction ofFM Shacks

    • Change in dimensions ofequipment or drawing

    Final Approval By

    • Sub-HSE (M) Chairman

    • Test Run Authorization is required torecord the behaviour of differentparameters after a change isperformed on an equipment or

    troubleshooting• TRA is also required to test run t he

    plant to establish increasedproduction rates.

    • It is a permanent change.

    • It includes all the changes which are notreplacement in kind.

    Any permanent change in processspecifications, change in P&IDs) andsafety critical equipment is not coveredin subtle change

    • It is a temporary change.

    • It includes all the changes carried outin emergency situations.

    • It is for a limited period of time.• Debox date is mentioned on the

    temporary repair form and repairshould be reverted before that date

    Examples

    • Box up of leaks

    • Temporary Modif ications

    • For example: Temporarymodification required on P-3001

    A/B nitrogen vent line• Temporary arrangement for oil

    make up at scrapper gear box atH-01 A/B

    • Equipment replacement or repairusing non-documented spares

    • Replacement of any spares withanother spare which is notrecommended by OriginalEquipment Manufacturer.

    • For example: Wear ring materialchange from cast iron to SS410 at11-P-553 B

    • Flushing of lines with a fluid notspecified in the procedures because

    of unavailability.

    Final Approval By

    • Sub HSE (M) Chairman

    Examples

    • Replacement of different brand bearingbut of same type

    • For example: Use of FAG bearing insteadof SKF make at 11-H-421

    Replacement of gasket.(If material isupgraded.

    • Installation of a higher grade piping inplace of existing system.(For non-hydrocarbon services)

    • Relocation/extension of drains/samplepoints(if open space)

    • Replacement of type of valves on drainlines only(if material is upgraded andservice is non-hydrocarbon)

    • K-02 compressor packing line valveremoval

    • Change of material towards a bettermetallurgy

    • Adjustment / extension of monkey ladder

    / support structure, to improveaccessibility(with OSHA standards)

    • Change of orientation of valve handwheels

    Final Approval By

    • Maintenance GL & Operations GL

    Applicable to

    • The plant is to be operated withindesigned authorized limits, asdetailed in the equipmentprocedures

    • The equipment is to be operatedwith some change in manufacturerrecommendations

    • For example: P-1403Bintermediate shaft materialchange & In-house machining ofBar

    • Startup or shutdown with approvalof new or changed, facilities orprocedures.

    Final Approval By

    •Sub HSE (M) Chairman(Maintenance Department)

    • It is a permanent change

    • It includes all the modifications to theplant facilities.(examples given below)

    • Any change in already approvedprocess specification, pipe isometrics,change in P&IDs or drawings of aproject also falls under this catagory