ncdp summary framework
TRANSCRIPT
-
8/17/2019 NCDP Summary Framework
1/40
public works
REPUBLIC OF SOUTH AFRICA
Department:
Public Works
public works
REPUBLIC OF SOUTH AFRICA
Department:
Public Works
Framework: National Contractor Development Programme
NCDP Summary Framework
-
8/17/2019 NCDP Summary Framework
2/40II
This docment provides a framework for programme
leadership and implementation by Industry,
championed by Public Works and the ci d b.
Framework: September 2011
Department of Pblic Works
Constrction Indstry Development Board
Updated: September 2011
Prodced by:
-
8/17/2019 NCDP Summary Framework
3/40
cidb | FRAMEWORK - NATIONAL CONTRACTOR DEVELOPMENT PROGRAMME | SEPTEMBER 2011
1
CONTENTS
1. Introdction 3
2. Objectives 5
3 . Backgrond 7
4. Contractor Development Components 9
5. Instrments for Contractor Development 11
6. Key Sccess Factors for Contractor Development 13
7 . Contractor Development Good Practice 15
8. Focs Areas of the NCDP 18
8.1. Establishment of an Enabling Environment for Contractor Development 18
8.2. Contractor Development Programmes 19
8.3. Procrement Driven Developmental Otcomes 19
9 Key Stakeholders 21
10 Monitoring and evalation 23
10.1. Monitoring and Reporting 23
10.2. Evalation 2311 Commnications Strategy 25
12 Implementation Plan 27
Annere: 28
Annere 1: Programme mobilization plan 29
Annere 2: Lessons from eisting programmes 32
Annere 3: Key activities for participating in CDP’s 34
-
8/17/2019 NCDP Summary Framework
4/40
-
8/17/2019 NCDP Summary Framework
5/40
cidb | FRAMEWORK - NATIONAL CONTRACTOR DEVELOPMENT PROGRAMME | SEPTEMBER 2011
3
NATIONAL CONTRACTOR DEVELOPMENT PROGRAMME (NCDP)
Introduction
There is a compelling need to elevate development of previosly disadvantaged individals and enterprises, and leadership
by government is reqired to establish the framework for the development of previosly disadvantages individals and
enterprises. This framework will stimlate the role of indstry and stakeholders for meaningfl empowerment and improved
contractor performance.
The NCDP is a government programme comprising of a partnership between the cidb, national and provincial pblic works
and other willing stakeholders, in which the participating stakeholders:
• Commit their resorces to develop previosly disadvantaged contractors; and
• Align their individal contractor development programmes or initiatives with the principles set ot in the NCDP
framework, meeting both the objectives of the NCDP and their own service delivery objectives.
Dening Contractor Development:
A deliberate and managed process to achieve targeted developmental otcomes that improves contractor:
• Grading stats
• Performance and qality
• Eqity and targeted ownership
-
8/17/2019 NCDP Summary Framework
6/404
02
-
8/17/2019 NCDP Summary Framework
7/40
cidb | FRAMEWORK - NATIONAL CONTRACTOR DEVELOPMENT PROGRAMME | SEPTEMBER 2011
5
OBJECTIVES
The objective of the NCDP is to promote eqity ownership across the different contracting categories and grades, as well
as improving skills and performance in the delivery and maintenance of capital works across the pblic sector.
To achieve this objective, participants within the NCDP will:
• Increase the nmber of black, women, disabled, and yoth-owned companies in targeted categories and grades -
increasing the representatively of contractors in all categories and grades;
• Improve the grading stats of previosly disadvantaged contractors in targeted categories and grades;
• Improve the performance of previosly disadvantaged contractors in terms of qality, employment practices, skills
development, safety, health and the environment; and
• Improve the bsiness management and technical skills of these contractors.
The key principles which nderpin the NCDP are smmarised below:• Government and its entities and partnerships, as well as any role player may se procrement of infrastrctre in
order to achieve contractor development;
• A CDP will enrol contractors based on clearly dened entry criteria, and will provide targeted developmental spport
so as to achieve clearly dened developmental otcomes; and
• Contractors will enter the programme based on predened criteria and will receive spport to enable contractors
to eit the programme on the basis of achieving predened criteria relating to skills, qalications, certication,
sstainability, qality, etc. (The programme mst give attention to ensre avoidance of a ‘dependency syndrome’).
-
8/17/2019 NCDP Summary Framework
8/406
03
-
8/17/2019 NCDP Summary Framework
9/40
cidb | FRAMEWORK - NATIONAL CONTRACTOR DEVELOPMENT PROGRAMME | SEPTEMBER 2011
7
BACKGROUND
The National Department of Pblic Works (NDPW) has provided leadership in contractor development since the inception of
the democratic government in 1994. Initially, NDPW established the Emerging Contractor Development Programme (ECDP)
to advance entry for primarily black contractors into the constrction indstry throgh direct government contracting. The
Epanded Pblic Works Programme was later conceptalised by Cabinet, primarily to enhance job creation in the pblic
sector, bt at the same time afforded government the opportnity to enhance its contractor development initiatives throgh
the V’kphile Programme.
Both the ECDP and V’kphile Programmes are primarily skills development programmes based and implemented throgh a
learnership programme. At the same time NDPW conceptalised the Contractor Incbator Programme (based on principles
of advanced enterprise development), to shift the contractor development focs from small contracts to more sbstantial
contracts and to higher levels of contracting.
Several other government departments and constrction indstry role players/ stakeholders also have their own contractor
development programmes. Lessons learnt from some of these programmes are discssed in the cidb report of March 2009
on the Stats Qo analysis of Contractor Development Programmes in Soth Africa as well as the cidb 2011 Baseline Stdy
of Provincial CDP’s.
Althogh some of these programmes share the same principles, government does not have a consistent and co-ordinated
approach to contractor development, and hence the need for the NCDP and gidelines to be contained within it.
The Constrction Indstry Development Board (cidb) is mandated throgh the Constrction Indstry Development Board
Act 38 of 2000 to spport contractor development and participation of the emerging sector. Specically, MINMEC reqested
the National DPW to work closely with the cidb in collaboration with the Provincial Departments of Pblic Works to devisea framework and implement the NCDP.
This framework establishes the parameters for implementation by the National and Provincial Departments of Pblic Works
and the cidb in their provision of leadership and spport to the pblic sector and other stakeholders in the development of
previosly disadvantaged contractors.
Led by the Minister of Pblic Works and the Provincial MEC’s, the NCDP is geared at enhancing capacity and promoting
eqity ownership across the different contracting categories and grades, as well as improving skills and performance in the
delivery and maintenance of capital works across the pblic sector.
The NCDP seeks to bild on the progress of the past, inclding:
• The achievements of preferential procrement, now evident throgh the cidb Register of Contractors;
• Improving pblic sector procrement capacity nder the impact of the reform roll-ot of the cidb;
• The reglatory framework established by the Register of Contractors and Register of Projects - that provides
information to spport targeted development interventions and to measre progress;
• The learning from a range of development programmes arond the contry;
• The framework for the cidb Best Practice Contractor Recognition Scheme - that sets desirable standards and
competencies that are deemed to be necessary for rnning a sstainable contracting enterprise;
• The framework for the cidb Best Practice Project Assessment Scheme – which, amongst others, establishes project
best practices that spport skills and contractor development; and
• The adoption of the Constrction Charter and the transformation charters of other sectors, providing a platform for
meaningfl pblic and private sector inpt.
-
8/17/2019 NCDP Summary Framework
10/408
04
-
8/17/2019 NCDP Summary Framework
11/40
cidb | FRAMEWORK - NATIONAL CONTRACTOR DEVELOPMENT PROGRAMME | SEPTEMBER 2011
9
CONTRACTOR DEVELOPMENT COMPONENTS
The varios components of contractor development addressed by the NCDP is illstrated in the following Figre, and
discssed in the following sections. Specically, contractor development comprises several components, inclding:
• New entrants (or start-ps);
• Enterprises development; and
• Performance improvement.
cidb Grade Contractor Development Component
9 Performance Improvement
Enterprise Development
2 Contractor Learnerships
1. Contractor Learnerships - incorporate the development of emerging contractor start-ps, and will target cidb
grade 1 to 3 contractors. Typically, in terms of a Capability Matrity Model, the processes within an emerging sector
start-p can be characterised as ad hoc, and occasionally even chaotic. Few processes are dened, and sccess
depends on isolated effort (i.e EPWP and other learnerships which are not herein addressed).
Key instrments which will be sed within the NCDP will be learnerships within Contractor Development Programmes
(CDPs), predominantly incorporating mentorship in which the developing contractor learns the basic bsiness and
constrction components of contracting. This stage will target the cidb grade 2 and 3 contractors. Within the CDPs,
bdget will be allocated to ensre sstainable work for the learner contractors.
2. Enterprise Development - in which the enterprises start growing, developing markets for their services, epandtheir workforce, epand their areas of operation, accmlate capital for ftre growth, epand their plant and
eqipment and bsiness and technical systems. This stage will target the cidb grade 2 to 6 contractors who ehibit
potential to grow and develop.
In terms of a Capability Matrity Model, the processes can be characterized as repeatable to dened , namely:
• Basic project management processes are established and repeatable; the necessary process discipline is in
place to repeat sccesses on previos projects (Level 2); to
• The processes for all activities are docmented, standardised, and integrated into the organization; all
projects se an approved, tailored version of the contractor’s standard process (Level 3).
Key instrments which will be sed will be strctred developmental spport provided within CDP’s or throgh a
strctred relationship with an established contractor. The developmental spport provided will be gided by the
competence standards set by the cidb Best Practice Contractor Recognition Scheme.
3. Performance Improvement - in which the established enterprise introdces best practice systems for health and
safety, qality management, environmental management, etc. in order to improve their performance. This stage will
target the cidb grade 4 to 7 contractors who ehibit potential to develop.
In terms of a Capability Matrity Model, the processes can be characterized as managed to optimised , namely:
• Detailed measres of the processes and prodct qality are collected; both the processes and prodcts are
qantitatively nderstood and controlled; to
• Continos process improvement is enabled by sing feedback from the processes to pilot innovative ideas
and technologies; contractors are consciosly aware of their spply chain and get involved in the spplychain development.
Key instrments sed will typically be strctred procrement-driven relationships specifying developmental spport to
the targeted developing contractors that is aligned with the cidb Best Practice Contractor Recognition Scheme.
-
8/17/2019 NCDP Summary Framework
12/4010
05
-
8/17/2019 NCDP Summary Framework
13/40
cidb | FRAMEWORK - NATIONAL CONTRACTOR DEVELOPMENT PROGRAMME | SEPTEMBER 2011
11
INSTRUMENTS FOR CONTRACTOR DEVELOPMENT
Bilding on government’s procrement of infrastrctre, varios instrments will be sed within the NCDP to spport
contractor development, inclding:
• Contractor Development Programmes (CDPs): A CDP is dened within the NCDP as an entity that is established for
the prpose of providing developmental spport to contractors. Contractors who participate within CDPs receive
strctred developmental spport which is targeted to achieve predetermined developmental objectives.
Work opportnities are typically provided throgh direct contracts with the developing contractors within the CDP.
Strctred developmental spport cold be provided by the government instittion that is providing the work
opportnities, or cold be otsorced to a developmental instittion.
Sch models are referred to within the NCDP as “direct targeting” .
• Procurement driven developmental outcomes: A frther key instrment that will be sed for contractor development
is procrement models that target developmental spport and developmental otcomes to developing contractors.
Sch procrement models cold be:
o Legislated, throgh, for eample, the cidb Best Practice Project Assessment Scheme; or
o Adopted throgh a department’s internal policy formlation processes.
In sch an approach the developmental spport is provided by a main contractor to a JV partner or sb-contractor.
Sch models are referred to within the NCDP as “indirect targeting” .
In addition to the specic contractor development instrments otlined above, the NCDP will address and enabling
environment reqired for contractor development.
-
8/17/2019 NCDP Summary Framework
14/4012
06
-
8/17/2019 NCDP Summary Framework
15/40
cidb | FRAMEWORK - NATIONAL CONTRACTOR DEVELOPMENT PROGRAMME | SEPTEMBER 2011
13
KEY SUCCESS FACTORS FOR CONTRACTOR DEVELOPMENT
There are a nmber of factors which shold be in place for sccessfl contractor development, both on the
demand and spply side, as well as for contractor development throgh CDPs and throgh procrement-driven
models. Key sccess factors for CDPs are given below – many of which cold also apply to procrement-
driven models with developmental otcomes.
Key Success Factors for Contractor Development
Demand Side Measures
• Continos and protable work opportnities to learners / contractors\.
• Procrement strategies and development mechanism to target learners and contractors with continity of work.
• Appropriate contract conditions addressing spportive practices regarding sreties, Good practice elements that
garantees, retention policies, etc.
• Prompt payment of contractors for work completed satisfactorily.
• Client reporting to cidb on Contractor Development initiatives and their varios contribtions.
Supply Side Measures
• Appropriate contract management and qality assrance oversight is provided by the departments rnning the
CDPs.
• Contractors have access to nances for working capital.
• Contractors have appropriate bsiness and technical capability and capacity.
• Contractors have access to an appropriately skilled workforce.
• Contractors have access to cost effective, qality plant and eqipment.
• Contractors have access to information and technology.
-
8/17/2019 NCDP Summary Framework
16/401414
07
-
8/17/2019 NCDP Summary Framework
17/40
cidb | FRAMEWORK - NATIONAL CONTRACTOR DEVELOPMENT PROGRAMME | SEPTEMBER 2011
15
CONTRACTOR DEVELOPMENT GOOD PRACTICE
Development of contractors shold be a well-planned operation that involves commitment of nancial and hman resorces
which incldes the availability of adeqate time to manage the programme. Sch resorces cold be provided directly
throgh strctred pblic or private sector CDPs together with direct preference models (direct targeting), or indirectly
throgh a procrement model with targeted development otcomes (indirect targeting).
Good practice elements that contractor development activities within the NCDP will need to incorporate in order to ensre
that contractor development aligns with the NCDP tenets are otlined below for direct and indirect targeting.
1. Common Elements: Good practice elements that are common to both direct targeting (CDPs) and to indirect
targeting methods are smmarized below:
i. Government or stakeholders will se their procrement of infrastrctre in order to achieve contractor
development.
ii. The focs of contractor development mst relate to components of the NCDP as dened in Section 4.
iii. Only cidb registered contractors may participate within these initiatives.
iv. Contractors to receive development spport mst be assessed to determine their development potential
and needs.
v. Development spport mst be strctred to achieve measrable improvements (e.g. NQF level or
improvement in contractor grading).
vi. Appropriate skills transfer and/or training (theoretical and/or on-site, together with qality control of sch
training) mst be provided.
vii. Clients and stakeholders mst report on contractor development initiatives to the cidb sing prescribed
reporting mechanisms.
2. Contractor Development Programmes: In addition to the good practice elements described in Item 1, good
practice elements within CDPs (direct targeting) inclde:
i. A transparent selection process mst be adopted for entrance to the CDP based on predetermined criteria.
ii. Targets mst be determined for bdget allocation, nmber of projects and nmber of contractors to bedeveloped to ensre continity of appropriate work for the dration of involvement within a CDP.
iii. Sfcient in-hose or otsorced capacity for the management of the CDP mst be ensred.
iv. Eit from a CDP mst be based on predetermined criteria (e.g. a specied timeframe).
Many of these good practice elements of a well-strctred CDP are illstrated in the following gre:
Generic Model for Contractor Development
4. Training &Mentorship
3. WorkOpportunities
ContractorDevelopmentProgramme
To develop keycontracting
competencies
5. Evaluationand Exiting ofContractors
6. Monitoring &Evaluation of the
Programme
1. ProgrammeStrategy &Targeting
2. Contractor Assessment
-
8/17/2019 NCDP Summary Framework
18/40
cidb | FRAMEWORK - NATIONAL CONTRACTOR DEVELOPMENT PROGRAMME | SEPTEMBER 2011
16
3. Procurement driven developmental outcomes: In addition to the good practice elements described in Item
1, good practice elements within procrement models with targeted development otcomes (indirect targeting)
inclde:
i. The reqirements for developmental spport and nomination of the developing contractor shall be specied
in the contract between the client and the main contractor.
ii. A project specic development program with milestones and a schedle of activities mst be developed for
the developing contractor.
iii. Verication that the development programme was sbstantially achieved mst take place at the end of the
contract.
iv. Failre by the main contractor to comply with the contract reqirements for developmental spport shall be
recorded on cidb Contractor Performance Reports that will be reqired to be sbmitted by the client to the
cidb on practical completion of the project. Sch information can then be sed on ftre tenders for the
prpose of:• Assessing the sitability of contractors for registration, pre-qalication, selective tender lists or
epressions of interest; and/or
• Adjdication for the award of a contract.
Reqirements and gidelines for indirect targeting are to be developed by the cidb.
-
8/17/2019 NCDP Summary Framework
19/40
cidb | FRAMEWORK - NATIONAL CONTRACTOR DEVELOPMENT PROGRAMME | SEPTEMBER 2011
17
08
-
8/17/2019 NCDP Summary Framework
20/40
cidb | FRAMEWORK - NATIONAL CONTRACTOR DEVELOPMENT PROGRAMME | SEPTEMBER 2011
18
8. FOCUS AREAS OF THE NCDP
Based on the overview given in the preceding sections, the NCDP will focs on the following strategies:
8.1 Establishment of an Enabling Environment for Contractor Development
This strategy will focs on establishing an enabling environment which will nderpin the development of contractors and
will inclde:
• Partnering between the provincial Departments of Pblic Works and the cidb to establish and operate Constrction
Contact Centres (CCC’s) in the provinces;
• Facilitating access to nance for contractors;
• Facilitating prompt payment of contractors;
• Provision of appropriate contracting conditions which will spport contractor development;
• Facilitating mechanisms that promote skills development by providing for workplace training of interns and p-
skilling of company employees in programmes that reslt in nationally accredited otcomes, sch as, learnerships
and accredited skills programmes, and internships for professional candidacy.
• Client reporting to cidb on Contractor Development initiatives and their varios contribtions, for co-ordination and
identication of areas for spport.
There are a host of responsibilities for client infrastrctre departments and varios stakeholders and roles players
responsible for delivering Contractor Development Programmes or spporting contractor and enterprise development.
To frther spplement this NCDP framework, and to provide a ‘how to’ implementation spport plan for implementing
clients, departments or stakeholders, the cidb has also compiled ‘Gidelines for Implementing Contractor Development
Programmes’.
Each will have to co-ordinate their respective contribtions to the NCDP, and will allocate and mobilise their resorces
towards aligning to their strategies, which in trn will align to the NCDP.
To this end, the cidb ‘Contractor Development Strategy’, in spport of the NCDP, is reected herein, and is contained within
the shaded tet boes, as the cidb responsibilities and commitments to the NCDP. Annere 3 and varios previos stats
and baseline reports also provide pointers on strategizing for Contractor Development.
In support of developing an enabling environment for contractor development, the cidb will:
• Coordinate and facilitate contractor spport initiatives available from government and other Indstry stakeholders;
• Manage the CCC’s and provide staff to provide services to contractors, inclding:
o contractor registration and pgrading services;
o access to appropriate gidelines and tools;
o access to information
• Develop standard generic tendering and contract docmentation;
• Facilitate access to nance for registered contractors;
• (Bilding on the work done by Pblic Works) develop / consolidate gidelines on a balanced approach to sreties
and retentions, for incorporation in contracts, providing options to registered contractors and improved cash ow
management;
• Promoting skills development; and
• Facilitate client reporting to cidb on Contractor Development initiatives and their varios contribtions, for
co-ordination and identication of areas for frther spport.
-
8/17/2019 NCDP Summary Framework
21/40
cidb | FRAMEWORK - NATIONAL CONTRACTOR DEVELOPMENT PROGRAMME | SEPTEMBER 2011
19
8.2 Contractor Development Programmes
This strategy will focs on the development of contractors within strctred CDPs, enabling contractors to gain the
necessary competence, eperience, track record and nancial capital.
This strategy will inclde the alignment and, where necessary, development of CDPs incorporating:
• Learnerships, targeting emerging contractor start-ps (typically cidb grade 2 and 3 contractors); and
• Enterprises development spport (targeting, typically, the cidb grade 2 to 6 contractors).
Participating stakeholders will commit work opportnities to the CDPs, together with resorces for training and mentoring.
In order to facilitate the alignment and implementation of these contractor development mechanisms the
cidb will:
• Package (from the Registers) and make available relevant information on capacity linked to demand and eisting
spply, and provide gidelines for targeting strategies;
• Develop gidelines which CDPs need to comply with as being part of the NCDP, covering assessment/selection
of contractors, training and skills development, spport mechanisms, accreditation of training providers andmentors, fnding reqirements and access to work opportnities, as well as accreditation of contractors on
eiting the programmes; and
• Develop and pilot competence reqirements and reqirements for constrction management systems throgh
the cidb Best Practice Contractor Recognition Scheme which set the basis for standards for which CDPs shold
develop contractors to.
8.3 Procurement Driven Developmental Outcomes
This strategy will focs on the development of contractors throgh procrement models with targeted development
otcomes (indirect targeting), in which skills transfer and development spport is provided by a main contractor to a ci db
registered sb-contractor.
This strategy will inclde the alignment and, where necessary, development of CDPs incorporating:
• Enterprises development spport (targeting, typically, the cidb grade 2 to 6 contractors); and
• Improving the bsiness performance and constrction performance of contractors (targeting, typically, the cidb
grade 4 to 7 contractors)
In support of the above, the cidb will:
• Develop and pilot the cidb Best Practice Contractor Recognition Scheme and the Best Practice Project
Assessment Scheme;
• Develop gidelines for preferencing best practice contractors.
-
8/17/2019 NCDP Summary Framework
22/4020
09
-
8/17/2019 NCDP Summary Framework
23/40
cidb | FRAMEWORK - NATIONAL CONTRACTOR DEVELOPMENT PROGRAMME | SEPTEMBER 2011
21
KEY STAKEHOLDERS
A variety of stakeholders will be involved within the NCDP based pon their willingness to commit appropriate resorces to
spport the NCDP. These stakeholders will be provincially co-ordinated via Contractor Development Forms, representative
of CD practitioners and stakeholders within the respective provinces. These CD Fora will be the platform for information
echange and sharing, provincial statistics reporting, consolidation and monitoring.
Organisations both pblic sector and private sector that are willing to sbscribe to the NCDP and commit resorces inclde:
• cidb – overall programme management and provision of good practice gides, contractor grading statistics,
contractor registration, facilitation of access to information throgh the Constrction Contact Centers, co-ordination
of Provincial CD Fora. It is important to note that the W does not provide nance, training nor projects to contractors;
• National Public Works – lead department within the “family of pblic works”, implementation of contractor
development and alignment of ECDP to NCDP, with the EPWP focsing on job creation and learnerships, as well as
accessing of fnding for grade 1 development;
• Provincial Public Works – crrent and new contractor development programmes aligned to the NCDP;
• Private sector contractor associations and established enterprises – contractor and skills development throgh
training, mentoring, etc.;
• CETA – skills development;
• Banks and nancing organisations – nancing of working capital, insrance and performance garantees for
contractors;
• Other stakeholders – willing to commit resorces and spport.
-
8/17/2019 NCDP Summary Framework
24/4022
10
-
8/17/2019 NCDP Summary Framework
25/40
cidb | FRAMEWORK - NATIONAL CONTRACTOR DEVELOPMENT PROGRAMME | SEPTEMBER 2011
23
MONITORING AND EVALUATION
10.1 Monitoring and Reporting
A monitoring and reporting system will be established for the NCDP by the cidb in collaboration with NDPW in order to be
able to monitor achievement of the otpts and gage these against the targets set. The departments participating withinthe NCDP will be reqired to record participating developing contractors, register projects and complete docments on
time in order to spport the monitoring system. This reporting will occr provincially and be channeled to the MEC’s, HoD’s,
NCDP Steering Committee and Provincial CD Form meetings.
10.2 Evaluation
Evalation of national and provincial CDP’s and the NCDP are considered an essential element to provide feedback and
lessons that can be etracted so that the programme can be periodically modied and rened. Reviews of the programme
will be ndertaken jointly by the cidb and NDPW and dring the programme implementation, pilot benchmarking and
reviews will be ndertaken either as an isse arises or to nderstand a particlar focs area/sector/component. Lessons
learnt will be docmented and pblicized, and promoted via practice notes and gidelines, to assist gide Provincial
implementing agents and CDP’s.
-
8/17/2019 NCDP Summary Framework
26/4024
11
-
8/17/2019 NCDP Summary Framework
27/40
cidb | FRAMEWORK - NATIONAL CONTRACTOR DEVELOPMENT PROGRAMME | SEPTEMBER 2011
25
COMMUNICATIONS STRATEGY
The NCDP is a cross ctting programme reliant on pblic and private sector organisations embracing the development
challenges. Effective commnication of good practice and the benets will form a major focs of the programme dring the
mobilization phase and is a joint responsibility of the collaborating partners.
-
8/17/2019 NCDP Summary Framework
28/4026
12
-
8/17/2019 NCDP Summary Framework
29/40
cidb | FRAMEWORK - NATIONAL CONTRACTOR DEVELOPMENT PROGRAMME | SEPTEMBER 2011
27
IMPLEMENTATION PLAN
The implementation plan to mobilise the programme is smmarised below and set ot in frther detail in attached Annere 1.
-
8/17/2019 NCDP Summary Framework
30/4028
ANNExuRE 1
-
8/17/2019 NCDP Summary Framework
31/40
cidb | FRAMEWORK - NATIONAL CONTRACTOR DEVELOPMENT PROGRAMME | SEPTEMBER 2011
29
PROGRAMME MOBILISATION ACTION PLAN
Action Responsibility Target Date
1. Establish and annually update
NCDP Framework
NDPW with cidb Jan 2008 – Completed
Annual update
a. Sbmit NCDP Framework to PblicWorks cidb Board, HoD’s, MINMEC,and obtain approval
cidb spported by NDPW Jan 2008 - Done
b. Circlate Contractor DevelopmentProgramme (CDP) reporting templateto gide participating organisations
cidb Monthly
c. Establish NCDP monitoring andreporting system
cidb spported by NDPW Jn 2012
d. Workshop NCDP with National andProvincial Pblic Works Departments
cidb spported by NDPW Annally
2. Provincial Launchs of the NCDP
Workshop/ indaba and NCDP
implemetantion launch
Provincial CD For a
National Minister- DPW
Nov 2009 – Done
Nov 2011
3. Inuence and Align Public
Works Contractor Development
Programmes (National and
Provincial)
NDPW & PDPWs supported by cidb Monthly
a. Preparation of ContractorDevelopment Programme (CDP) byPblic Works
NDPW & PDPWs Feb 2008 – Mar 2012
b. Alignment of eisting orestablishment of new ContractorDevelopment Programmes inNational and Provincial Pblic Works
NDPW & PDPWs Feb 2008- Mar 2012
c. Establish procrement strategies tospport contractor development
NDPW & PDPWs with spport from cidb Mar 2009 - Done
d. Assign or appoint resorces tospport Contractor DevelopmentProgrammes
NDPW & PDPWs Apr 2009 - Done
e. Lanches of Provincial ContractorDevelopment Programmes
MECs spported by PDPWs Jl 2008 – Mar 2012
4. Financial Products and Credit/
access to nance for Contractors
Banks and Material Suppliers
supported by cidb
Aug 2011
a. Engage with banks and identifywilling partners
cidb spported by PDPW’s & NDPW Feb 2007 – Mar 2009 = Done
b. Formlate nancial spport strategywith nancial instittions Banks spported by cidb Mar 2009 - Done
c. Conrm nancial and Credit spportprodcts and conditions
Banks and Material Sppliers - MoA Mar 2009 – Done
d. Commnicate nancial spportprodcts to registered contractors
Banks, Material Sppliers & cidb Done
e. Lanch of nancial spport strategiesspporting NCDP
Banks Mar 2012
-
8/17/2019 NCDP Summary Framework
32/40
cidb | FRAMEWORK - NATIONAL CONTRACTOR DEVELOPMENT PROGRAMME | SEPTEMBER 2011
30
5. Construction Contact Centres
(CCC’s)
cidb with PDPWs Mar 2010 (all ecept N-W by end 2011)
a. Establish 4 pilot CCC’s cidb with PDPWs Mar 2008 - Done
b. Open and lanch CCC’s in each of 4pilot provinces
Minister with MEC’s Mar 2008 - Done
c. Role ot CCC’s in all provinces cidb with PDPWs Mar 2010 (all ecept N-W by end 2011)
6. Contractor Guidelines and Tools Jun 2010
a. Identify and prioritize contractorgidelines and tools
cidb spported by NDPW Jan 2008 - Done
b. Develop top priority gidelines andtools
cidb Jan 2008 - Done
c. Establish services for gidelines andtools within CCC’s
cidb Mar 2008 - Done
d. Commnicate availability of
gidelines and tools to registeredcontractors
cidb Mar 2009 - Done
e. NCDP Gidelines cidb Jl 2011
7. Linkages to EPWP
a. Engage with EPWP and forgelinkages and integration based onlessons learnt
cidb spported by NDPW EPWP Sept 2007 - Done
b. Promote net rond of EPWPlearnerships (grades 1 and 2) andensre that all contractors areregistered
cidb with EPWP Nov 2008 - Done
8. Monitoring and reporting cidb with NDPWs & PDPWs Jl 2012
9. Evaluation and lesson learning cidb with by NDPWs & PDPWs Mar 2011 - Done
10. Expose NCDP to Industry
Associations and Established
Industry
cidb spported by stakeholders/roleplayers
Nov 2009 - Done
11. Expose NCDP to Parastatals cidb spported by NDPWs & PDPWs Nov 2009 - Done
12. Expose NCDP to other National
Government Departments
cidb spported by stakeholders/roleplayers
Nov 2009 - Done
13. Expose NCDP to Municipalities cidb spported by NDPWs & PDPWs Nov 2009 - Done
-
8/17/2019 NCDP Summary Framework
33/40
ANNExuRE 2
-
8/17/2019 NCDP Summary Framework
34/40
cidb | FRAMEWORK - NATIONAL CONTRACTOR DEVELOPMENT PROGRAMME | SEPTEMBER 2011
32
LESSONS FROM EXISTING PROGRAMMES
Refer to:
- NCDP Smmary Framework: 2010 and beyond;
- cidb report of March 2009 on the Stats Qo analysis of Contractor Development Programmes in Soth Africa; and
- 2011 Baseline Stdy of Provincial CDP’s.
-
8/17/2019 NCDP Summary Framework
35/40
ANNExuRE 3
-
8/17/2019 NCDP Summary Framework
36/40
cidb | FRAMEWORK - NATIONAL CONTRACTOR DEVELOPMENT PROGRAMME | SEPTEMBER 2011
34
KEY ACTIVITIES FOR PARTICIPATING CONTRACTOR DEVELOPMENT PROGRAMMES
Set down below are some of the key activities which client departments or any stakeholder may be epected to incorporate
within their contractor development programmes or spport towards contractor and enterprise development:
1. Implement procrement strategies which will promote contractor enterprise development and contracting capacity
formation, inclding creating continity of work for contractors within varios grades throgh a competitive tenderingprocess (See cidb Practice Note 1 for advocated approaches to procrement strategies);
2. utilize the cidb iTender and Register of Projects as reqired in terms of the Constrction Reglations to advertise
tenders and track project progress (i.e. contract award or cancellation, completion or termination, completion on
time, within bdget and to specication) in order to provide registered contractors with a track record and measre
of performance improvement;
3. Implement srety provisions appropriate to the level of risk within types of projects and grades of contractors;
4. Ensre that the contractors are paid on time for work approved;
5. Institte appropriate levels of contract management throgh eperienced internal or otsorced bilt environment
service providers as principal agents;
6. Provide appropriate levels of contract administration by eperience service providers (bilt environment professionals)
to oversee the work of the contractors in a facilitator manner in order to improve capacity of contractors;
7. Facilitate qality assrance to improve contractor performance;
8. Facilitate links between contractors and nancial instittions participating within the programme so that contractors
have ready access to working capital;
9. Standardise designs and specications as far as possible in order to facilitate repletion for improved contractor
performance and skills development;
10. Link contractors to skills development programmes established within the NCDP;
11. Commit to and phold the cidb Code of Condct and ensre that their agents do the same; and
12. Monitor and report progress and reslts in terms of the monitoring and reporting system established within the
NCDP.
-
8/17/2019 NCDP Summary Framework
37/40
cidb | FRAMEWORK - NATIONAL CONTRACTOR DEVELOPMENT PROGRAMME | SEPTEMBER 2011
35
Notes:
-
8/17/2019 NCDP Summary Framework
38/40
cidb | FRAMEWORK - NATIONAL CONTRACTOR DEVELOPMENT PROGRAMME | SEPTEMBER 2011
36
Notes:
-
8/17/2019 NCDP Summary Framework
39/40
cidb | FRAMEWORK - NATIONAL CONTRACTOR DEVELOPMENT PROGRAMME | SEPTEMBER 2011
37
Notes:
-
8/17/2019 NCDP Summary Framework
40/40
Website: www.cidb.org.zaE-mail: [email protected]
Tel: +27 12 482 7200 or +27 86 100 cidbFa: +27 12 349 8986 or +27 86 681 9995
Anonymos Frad line: 080 011 2432Postal address: PO Bo 2107, Brooklyn Sqare, 0075
Physical address: Blocks N&R, SABS Camps,2 Dr. Lategan Rd, Groenkloof, Pretoria, Soth Africa