micropiles for roadway support, bridge abutments … for roadway support, bridge abutments and metal...
TRANSCRIPT
Micropiles for Roadway Support,
Bridge Abutments and Metal
Signal Poles on US-158 from
US-17B to East of Pasquotank
River, in Elizabeth City, NC
Schnabel Foundation Company
Presenter: Stephen Dimino, P.E.
Team
• Owner -NCDOT
• Prime Contractor-Archer Western Construction
• Micropile Subcontractor-Schnabel Foundation
Company
Project Overview
• Install micropiles to support the roadway, metal
signal poles (MSP), bridge abutment and pump
station
• The roadway and approach micropiles were
installed through the concrete roadway deck
• Bridge micropiles were installed in the river
• MSP micropiles and the pump station piles were
installed in foundation excavation.
Project Overview
• Install 258 Roadway Micropiles
• Install 16 Bridge Approach Micropiles
• Install 10 ea. Bridge Abutment Micropiles
• Install 4 Micropiles at 8 separate MSP foundations
for a total of 32 piles.
• Install 8 Pump Station Support Micropiles
• Install 4 Generator Slab Support Micropiles
• Install 4 Electrical Building Micropiles
Roadway/Approach Piles
• Install 258 Roadway Micropiles
– 8-5/8” x 60 ft. casing with casing tip elevation
of -52 ft.
– Bond length of 28 ft.
– Full length of corrosion protected Center bar
– Three sacrificial demonstration piles
– Fifteen proof tests on production piles
Bridge Piles
• Install 10 Bridge Abutment Micropiles
– 10-3/4” x 60 ft. casing with casing tip elevation
of -58 ft.
– Bond length of 40 ft.
– Full length of corrosion protected center bar
tied into pile cap
– One sacrificial demonstration piles
– Two proof tests on production piles
MSP Piles
• Install 32 Bridge Abutment Micropiles
(4 each at 8 separate pile caps)
– 10-3/4” casing with casing tip elevation varies
from -40 ft. to -58 ft.
– Bond length of 22 ft.
– Full length of corrosion protected center bar
tied into pile cap
– One proof tests at each of the 8 pile caps
Pump Station Piles
• Install 16 Pump Station Micropiles
– 7” casing with casing tip elevation of -40 ft.
– Bond length of 20 ft.
– Full length of corrosion protected center bar
tied into pile cap
– One proof tests at each of the 8 pile caps
– One demonstration test for the 7” piles
Design
• The permanent micropile design is in accordance
with
– FHWA Implementation Manual for Micropile Design
and Construction Guidelines (FHWA-SA-97-070),
dated June 2000 using the Load Factor Design (LFD)
Method;
– AASHTO LRFD Bridge Design Specifications 2010;
and The Recommendations of Prestressed Rock and
Soil Anchors, PTI, 2004.
– In this design the micropiles are “Type A” micropiles
Design
• Design loads and test loads given in Contract
Documents
– Roadway/Approach DL=25T (comp) TL=36T
– Bridge DL=50T (comp) TL=72T
– MSP DL=24T (comp) ;14T (tension)
• Specified casing diameter and thickness based on
method of installation
Design
• The overburden soils were very soft/weak.
• The grout to ground bond strengths are per Table
6.3 in The Recommendations of Prestressed Rock
and Soil Anchors, PTI, 2004, and AASHTO Table
C10.9.3.5.2-1. The bond strengths of the soils of
the pile above the minimum tip elevation shown
the plans were neglected.
– Roadway and Approach Piles 3.8klf
– Bridge Piles 4.5klf
– MSP Piles 4.5klf
Design
• Grout mix design Use either of the two
grouts:
– A neat mix of Portland Cement (Type I/II) and
potable water at an approximate mix ratio of 5
to 6 gallons of water per cubic foot of grout.
Minimum compressive strength at 28 days,
fc=3,500 psi.
– An approved ready mix grout with a minimum
compressive strength at 28 days, fc=3,500 psi
Testing • Tested per ASTM D3689 8.1.2 Quick Test
• Roadway Piles-The contract called for 3
Demonstration Tests and 15 Proof Tests. Roadway
micropiles test load is 36T (72 kips)
• Bridge Piles-The contract called for 1 Demonstration
Test and 2 Proof Tests. Bridge micropiles test load is
72T (144 kips)
• MSP Piles-The contract called for 1 Proof Test at
each pile cap. MSP micropiles test load is 24T (48
kips)
Issues
• We had to stabilize the hole and the environmental
requirements affected our planning
• Original method was not productive
• Constraints of working on road deck limited our
work process
• Tight schedule due to MOT
• Changing methods is time consuming
• Working near the water
Construction Method 1
• 100 lf x 11” dia. Continuous Flight Auger
• Drill down to depth and pump grout through auger
• Push casing and center bar down through plastic
grout
• Main issue was that the auger walked and we
could not put the casing in to depth
• Cleaning the “fat” clay off the auger took a long
time.
Construction Method 2
• Drill down to pile tip elevation using the casing as
the drill string
• Pump grout through the casing as the casing is
pulled up to so that the bottom of casing matches
pile tip elevation. The casing and grout stabilize
the hole.
• Push bar through plastic grout.
• Hooking the casing up at the rotary head took a
long time.
Construction Method 3
• Vibrate casing down to casing tip elevation
• Drill through casing and down to pile tip
elevation.
• Pump grout through drill string as we retracted the
inner rod.
• Very successful in the soil type. We were able to
use smaller equipment.