  • 5/19/2018 PMI Framework Processes Presentation

    1/17

    Todays Agenda

    1. Review Project Management Principles

    2. Project Management Institute (PMI) Framework

    3. PMI Processes

    4. Break into Project Teams and Knowledge Area

    5. Agenda for Next Class

  • 5/19/2018 PMI Framework Processes Presentation

    2/17

    PMI FrameworkProject Objectives

    Defined in the charter

    Project complete when the objectives are

    accomplished

    Quality activities should be designed to increase

    chances of achieving objectives

    Risk management activities designed to increase

    chances of achieving objectives (all management plans)

  • 5/19/2018 PMI Framework Processes Presentation

    3/17

    PMI FrameworkOrganization Structures

    One of the main influences on project success

    Functional (silo)

    Projectized (no home)

    Matrix (multi-reporting)

    o

    Strong (power with project manager)oWeak (power with functional manager)

  • 5/19/2018 PMI Framework Processes Presentation

    4/17

    PMI FrameworkLife-CycleProduct Life-Cycle

    From conception to retirement

    May spawn many projects over its life-cycle

    Project Life-Cycle

    Depends on industry (e.g. softwaredesign, develop,test, deploy)

    Run through initiation, planning, execution, monitor &

    control and closing for each life-cycle step

  • 5/19/2018 PMI Framework Processes Presentation

    5/17

    PMI FrameworkLessons Learned

    Required for all projects

    Collected throughout the project, finalized during

    project closing

  • 5/19/2018 PMI Framework Processes Presentation

    6/17

    PMI FrameworkExam Questions

    Question 3, chapter 2In a projectized organization, the

    project team:

    a) Reports to many bosses.

    b) Has no loyalty to the project.

    c) Reports to the functional manager.

    d) Will not always have a home.

  • 5/19/2018 PMI Framework Processes Presentation

    7/17

    PMI FrameworkExam Questions

    Question 4, chapter 2A project manager is trying to

    complete a software development project, but cannot

    get enough attention for the project. Resources are

    focused on completing process-related work and the

    project manager has little authority to properly assign

    resources. What form of organization must the project

    manager be working in?

    a) Functional.b) Matrix.

    c) Expeditor.

    d) Coordinator.

  • 5/19/2018 PMI Framework Processes Presentation

    8/17

    PMI FrameworkExam Questions

    Question 5, chapter 2A project manager has very little

    project experience, but he has been assigned as the

    project manager of a new project. Because he will be

    working in a matrix organization to complete his project,

    he can expect communications to be:

    a) Simple.

    b) Open and accurate.

    c) Complex.d) Hard to automate.

  • 5/19/2018 PMI Framework Processes Presentation

    9/17

    PMI FrameworkExam Questions

    Question 10, chapter 2A manager and head ofengineering discuss a change to a major work package.

    After the meeting, the manager contacts you and tells

    you to complete the paperwork to make the change.

    This is an example of:

    a) Management attention to scope management.

    b) Management planning.

    c) A project expeditor position.d) A change control system.

  • 5/19/2018 PMI Framework Processes Presentation

    10/17

    PMI FrameworkExam Questions

    Question 17, chapter 2A project team is working onmanufacturing a new product, but they are having

    difficulty creating a project charter. What is the BEST

    description of the real problem?

    a) They have not identified project objectives.

    b) They are working on a process and not a project.

    c) The end date has not been set.

    d) They have not identified the product of the project.

  • 5/19/2018 PMI Framework Processes Presentation

    11/17

    PMI Processes

    Describes what you need to do to manage a project(see page 43 for process chart)

    Discuss study approach for exam (page 42)

    Includes:

    oInitiatingoPlanning

    oExecuting

    oMonitoring & Controlling

    oClosing(See page 98 for an example of how the

    integration knowledge area crosses processes)

  • 5/19/2018 PMI Framework Processes Presentation

    12/17

    PMI ProcessesExam Questions

    Question 2, chapter 3The project charter is created inwhich project management process group?

    a) Executing.

    b) Planning.

    c) Closing.

    d) Initiating.

  • 5/19/2018 PMI Framework Processes Presentation

    13/17

    PMI ProcessesExam Questions

    Question 4, chapter 3A detailed project schedule canbe created only after creating the:

    a) Project budget.

    b) Work breakdown structure.

    c) Project management plan.

    d) Detailed risk assessment.

  • 5/19/2018 PMI Framework Processes Presentation

    14/17

    PMI ProcessesExam Questions

    Question 6, chapter 3Which of the following is NOT aninput to the initiating process group?

    a) Company processes.

    b) Company culture.

    c) Historical WBSs.

    d) Project scope statement.

  • 5/19/2018 PMI Framework Processes Presentation

    15/17

    PMI ProcessesExam Questions

    Question 7, chapter 3The project sponsor just signedthe project charter. What is the NEXT thing to do?

    a) Begin to complete the work packages.

    b) Verify scope.

    c) Start integrated change control.

    d) Start to create management plans.

  • 5/19/2018 PMI Framework Processes Presentation

    16/17

    PMI ProcessesExam Questions

    Question 14, chapter 3During a team meeting, a teammember asks about the measurements that will be used

    on the project to judge performance. The team member

    feels that some of the measures related to activities

    assigned him are not valid measurements. The project is

    BEST considered in what part of the project

    management process?

    a) Closing.b) Monitoring & Controlling.

    c) Executing.

    d) Initiating.

  • 5/19/2018 PMI Framework Processes Presentation

    17/17

    Agenda for Next Class

    - PMI Integration ManagementChapter 4