  • S10 Pgina 1

    PresupuestoREPARACION Y HABILITACION DE PLANTA Y CAMPAMENTOS UM CONTONGA0902001PresupuestoALTERNATIVA N 02001Subpresupuesto

    CLIENTE PRIVADO 12/01/2016Costo alClienteLugar JUNIN - YAULI - LA OROYA

    Precio S/. Parcial S/.Item Descripcin Und. Metrado

    OBRAS PROVISIONALES01 1,500.00

    1,500.00 1.00 ALMACEN PROVISIONAL DE OBRA GLB01.01 1,500.00

    TRABAJOS PRELIMINARES02 2,489.47

    1,443.17 450.99 LIMPIEZA DE TERRENO MANUAL m202.01 3.20

    1,046.30 450.99 TRAZO DE NIVELES Y REPLANTEO m202.02 2.32

    MOVIMIENTO DE TIERRAS03 1,761.19

    589.01 15.57 EXCAVACION MANUAL m303.01 37.83

    1,041.79 450.99 REFINE, NIVELACION Y COMPACTACION m203.02 2.31

    130.39 18.68 ELIMINACION DE DESMONTE DE CORTE DE TERRENO (CON MAQUINARIA) m303.03 6.98

    OBRAS DE CONCRETO SIMPLE04 19,398.36

    9,930.55 31.14 CIMIENTOS CORRIDOS 1:10 + 30% PG m304.01 318.90

    5,206.30 15.57 SOBRECIMIENTO MEZCLA 1:8 CEMENTO-HORMIGON 25% PIEDRA MEDIANA m304.02 334.38

    4,261.51 155.70 ENCOFRADO Y DESENCOFRADO SOBRECIMIENTO HASTA 0.80 M m204.03 27.37

    CARPINTERIA METALICA05 47,738.01

    1,481.30 38.06 COLUMNETA DE 4X4 INCL PLACA DE ANCLAJE EMPERNADO Y PINTURA m05.01 38.92

    908.73 24.22 CORREAS DE 2"X4"X3MM INCL PINTURA m05.02 37.52

    4,314.64 4.00 TIJERALES DE 2"X4"X3MM INCL PINTURA und05.03 1,078.66

    223.38 6.92 TUBO REDONDO DE 3" INCL PINTURA m05.04 32.28

    8,274.15 194.64 MALLA ELECTROSOLDADA m05.05 42.51

    3,676.11 181.00 CANAL "C" 6"x2"x3.0 EN CORREAS INCL PINTURA kg05.06 20.31

    8,205.24 404.00 CANAL "C" 6"x2"x3.0 EN TIJERALES INCL PINTURA kg05.07 20.31

    20,271.99 631.92 MARCO DE TUBOS 1 1/2" INCL PINTURA m05.08 32.08

    382.47 57.00 FIERRO CORRUGADO EN ARRIOSTRES kg05.09 6.71

    TECHO METALICO06 5,757.17

    5,757.17 57.96 COBERTURA DE TECHO CON CALAMINON Al- 106 m206.01 99.33

    SEGURIDAD Y SALUD07 4,000.00

    2,000.00 1.00 POLIZA DE SEGURO Y PENSION GLB07.01 2,000.00

    2,000.00 1.00 EQUIPOS DE PROTECCION GLB07.02 2,000.00

    VARIOS08 9,500.00

    4,500.00 1.00 FLETE TERRESTRE GLB08.01 4,500.00

    3,500.00 1.00 MOVILIDAD GLB08.02 3,500.00

    1,500.00 1.00 HOSPEDAJE Y ALIMENTACION GLB08.03 1,500.00

    Costo Directo 92,144.20

    UTILIDAD 8% 7,371.54

    GASTOS GENERALES 10% 9,214.42

    ------------------------------------------------------------------------------------------------

    SUB TOTAL 108,730.16

    IGV 18% 19,571.43

    ------------------------------------------------------------------------------------------------

    TOTAL DE OBRA 128,301.59

    SON : NOVENTIDOS MIL CIENTO CUARENTICUATRO Y 20/100 NUEVOS SOLES