profil centennial coal

Upload: indra

Post on 24-Feb-2018

224 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/25/2019 Profil Centennial Coal

    1/92

    Northern Coal Services

    Coal Logistics Project

    Briefing Paper

    February 2012

  • 7/25/2019 Profil Centennial Coal

    2/92

  • 7/25/2019 Profil Centennial Coal

    3/92

    NORTHERN COAL SERVICES COAL LOGISTICS PROJECT

    Page i

    TABLE OF CONTENTS

    1.0 INTRODUCTION ............................................................................................................... 1

    1.1 BACKGROUND................................................................................................................. 1

    1.2 PROJECT

    OVERVIEW

    ....................................................................................................... 11.3 BRIEFING PAPER ............................................................................................................ 5

    1.4 THEAPPLICANT.............................................................................................................. 5

    2.0 SITE DESCRIPTION ......................................................................................................... 6

    2.1 SITE LOCALITY AND EXISTING LAND USES....................................................................... 6

    2.1.1 Newstan Colliery..................................................................................................... 6

    2.1.2 Mandalong Mine Cooranbong Entry Site ............................................................. 6

    2.2 LANDFORMS AND TOPOGRAPHY...................................................................................... 6

    2.2.1 Newstan Colliery..................................................................................................... 6

    2.2.2 Mandalong Mine Cooranbong Entry Site ............................................................. 6

    2.3 LAND OWNERSHIP .......................................................................................................... 7

    2.3.1 Newstan Colliery..................................................................................................... 7

    2.3.2 Mandalong Mine Cooranbong Entry Site ........................................................... 10

    3.0 CURRENT APPROVED OPERATIONS ......................................................................... 13

    3.1 NEWSTAN COLLIERY..................................................................................................... 13

    3.2 MANDALONG MINE........................................................................................................ 133.3 INFRASTRUCTURE......................................................................................................... 14

    3.3.1 Newstan Colliery................................................................................................... 14

    3.3.2 Mandalong mine Cooranbong Entry Site ........................................................... 15

    3.4 COAL HANDLING AND TRANSPORT................................................................................. 16

    3.4.1 Domestic Coal Transportation Newstan Colliery .................................................. 16

    3.4.2 Domestic Coal Transportation Mandalong Mine .................................................. 17

    3.4.3 Export Coal Transportation Newstan Colliery ....................................................... 17

    3.4.4 Export Coal Transportation Mandalong Mine ....................................................... 17

    3.5 REJECT MANAGEMENTNEWSTAN COLLIERY............................................................... 17

    3.6 REJECT MANAGEMENTMANDALONG MINE.................................................................. 18

    3.7 WATER MANAGEMENT .................................................................................................. 20

    3.8 CONSENTS,LEASES AND LICENCES............................................................................... 23

    3.8.1 Newstan Colliery Development Consents ............................................................ 23

    3.8.2 Mandalong Mine Development Consents ............................................................. 24

  • 7/25/2019 Profil Centennial Coal

    4/92

    NORTHERN COAL SERVICES COAL LOGISTICS PROJECT

    Page ii

    3.8.3 Centennial Newstan Mining Leases ..................................................................... 26

    3.8.4 Centennial Mandalong Mining Leases ................................................................. 29

    3.8.5 Environmental Protection Licences ...................................................................... 29

    3.9 ENVIRONMENTAL MANAGEMENT SYSTEM...................................................................... 30

    4.0 PROPOSED PROJECT .................................................................................................. 32

    4.1 BACKGROUND............................................................................................................... 32

    4.2 PROJECTAREA............................................................................................................. 33

    4.3 COAL HANDLING........................................................................................................... 33

    4.4 REJECT MANAGEMENT.................................................................................................. 34

    4.5 INFRASTRUCTURE......................................................................................................... 36

    4.6 WATER MANAGEMENT .................................................................................................. 36

    4.7 HOURS OF OPERATION AND PERSONNEL....................................................................... 37

    4.8 ADDITIONAL LICENCES ANDAPPROVALS........................................................................ 37

    4.9 ENVIRONMENTAL MANAGEMENT SYSTEM...................................................................... 37

    5.0 PLANNING CONSIDERATIONS .................................................................................... 38

    5.1 INTRODUCTION ............................................................................................................. 38

    5.2 COMMONWEALTH LEGISLATION..................................................................................... 38

    5.2.1 Environment Protection and Biodiversity Conservation Act 1999 ........................ 38

    5.2.2

    National Greenhouse and Energy Reporting Act 2007 ........................................ 38

    5.2.3 Native Title Act 1994 ............................................................................................ 39

    5.3 NEW SOUTH WALES LEGISLATION................................................................................. 39

    5.3.1 Environmental Planning and Assessment Act 1979 ............................................. 39

    5.3.2 Other NSW State Legislation................................................................................ 40

    5.3.3 State Environmental Planning Policies ................................................................. 42

    5.4 LOCALENVIRONMENTPLANS ................................................................................ 42

    5.4.1 Lake Macquarie Local Environment Plan ............................................................. 42

    6.0 KEY ENVIRONMENTAL ISSUES .................................................................................. 44

    6.1 IDENTIFICATION OF ENVIRONMENTAL ISSUES................................................................. 44

    6.1.1 Pre-Project Risk Assessment ............................................................................... 44

    6.2 IDENTIFIED ENVIRONMENTAL ISSUES............................................................................. 46

    6.2.1 Flora and Fauna ................................................................................................... 46

    6.2.2 Surface Water....................................................................................................... 47

    6.2.3 Greenhouse Gas .................................................................................................. 47

  • 7/25/2019 Profil Centennial Coal

    5/92

    NORTHERN COAL SERVICES COAL LOGISTICS PROJECT

    Page iii

    6.2.4 Air Quality ............................................................................................................. 48

    6.2.5 Noise .................................................................................................................... 48

    6.2.6 Heritage (Aboriginal and European) ..................................................................... 49

    6.2.7 Social/Community ................................................................................................. 49

    6.2.8 Waste Management ............................................................................................. 49

    6.2.9 Visual .................................................................................................................... 50

    7.0 STAKEHOLDER AND COMMUNITY CONSULTATION ............................................... 50

    8.0 PROJECT JUSTIFICATION ........................................................................................... 51

    9.0 CONCLUSION ................................................................................................................ 52

  • 7/25/2019 Profil Centennial Coal

    6/92

    NORTHERN COAL SERVICES COAL LOGISTICS PROJECT

    Page iv

    FIGURES

    FIGURE 1NORTHERN COAL SERVICESCOAL LOGISTICS PROJECTAREA.................. 4

    FIGURE 2NEWSTAN COLLIERY SURFACE SITE LAND OWNERSHIP................................ 9

    FIGURE 3MANDALONG MINECOORANBONG ENTRY SITE LAND OWNERSHIP........... 12FIGURE 4CURRENTAPPROVED COAL HANDLING AND TRANSPORT SYSTEM.............. 19

    FIGURE 5NEWSTAN COLLIERY SURFACE WATER MANAGEMENT SYSTEM.................. 21

    FIGURE 6MANDALONG MINECOORANBONG ENTRY SITE SURFACE WATERMANAGEMENT SYSTEM......................................................................................... 21

    FIGURE 7CENTENNIAL NEWSTAN MINING LEASES.................................................... 28

    FIGURE 8PROPOSED COAL HANDLING AND TRANSPORT SYSTEM.............................. 35

    TABLES

    TABLE 1LIST OF LAND TITLES FOR THE NEWSTAN COLLIERY SURFACE SITE................ 7

    TABLE 2LIST OF LAND TITLES FOR THE MANDALONG MINECOORANBONG ENTRY SITE

    ............................................................................................................................ 10

    TABLE 3NEWSTAN COLLIERY DEVELOPMENT CONSENTS.......................................... 21

    TABLE 4MANDALONG MINE DEVELOPMENT CONSENTS............................................. 26

    TABLE 5CENTENNIAL NEWSTAN MINING LEASES...................................................... 26

    TABLE 6CENTENNIAL MANDALONG MINING LEASES.................................................. 29

    TABLE 7-SUMMARY OF NSWLEGISLATION RELEVANT TO THE PROJECT..................... 41

    APPENDICES

    APPENDIX 1ENVIRONMENT AND COMMUNITY BROAD BRUSH RISKASSESSMENT

    APPENDIX 2SCHEDULE OF LAND

    APPENDIX 3QUANTITY SURVEYORS CERTIFICATE

  • 7/25/2019 Profil Centennial Coal

    7/92

    NORTHERN COAL SERVICES COAL LOGISTICS PROJECT

    Page v

    ABBREVIATIONS

    AHD Australian Height Datum

    AHIMS Aboriginal Heritage Information Management System

    Banpu Banpu Public Company Limited

    BOM Bureau of Meteorology

    CCC Community Consultative Committee

    CPP Coal Preparation Plant

    Centennial Centennial Coal Company

    Centennial Newstan Centennial Newstan Pty Ltd

    DA 73-11-98 Development Application 73-11-98

    EARs Environmental Assessment Requirements

    EIS Environmental Impact Statement

    DP&I Department of Planning and Infrastructure

    DTIRIS Department of Trade and Investment, Regional

    Infrastructure and Services

    EMS Environmental Management System

    EP&A Act Environmental Planning and Assessment Act 1979

    EPBC Act Environment Protection and Biodiversity Conservation

    Act 1999

    EPL Environment Protection Licence

    Heritage Act Heritage Act 1977

    ILUA Indigenous Land Use Agreement

    LALC Local Aboriginal Land Council

    LEP Local Environmental Plan

    LGA Local Government Area

    LMCC Lake Macquarie City Council

    MNES Matters of National Environmental Significance

  • 7/25/2019 Profil Centennial Coal

    8/92

    NORTHERN COAL SERVICES COAL LOGISTICS PROJECT

    Page vi

    Mtpa Million tonnes per annum

    Newstan EIS Newstan Colliery Life Extension Project Environmental

    Impact Statement

    NREA Northern Reject Emplacement Area

    NGER Act National Greenhouse and Energy Reporting Act 2007

    NOW NSW Office of Water

    NPW Act National Parks and Wildlife Act 1974

    OEH Office of Environment and Heritage

    POEO Act Protection of the Environment Operations Act 1997

    Project Coal Logistics Project

    ROM Run of Mine

    RWMP Revised Water Management Plan

    SEPP State Environmental Planning Policies

    SREA Southern Reject Emplacement Area

    TSC Act Threatened Species Conservation Act 1995

    WMA Water Management Act 2000

    WSP Water Sharing Plan

  • 7/25/2019 Profil Centennial Coal

    9/92

    NORTHERN COAL SERVICES COAL LOGISTICS PROJECT

    Page vii

    Definitions

    Newstan Colliery

    Newstan Colliery encompasses the Newstan Colliery Surface Site including rejectemplacement areas, the extent of existing and approved underground mine workings

    and the extent of mining leases and exploration licences held by Centennial

    Newstan.

    Newstan Colliery Surface Site

    The Newstan Colliery Surface Site encompasses the surface facilities located off

    Miller Road, Fassifern and includes all buildings, coal handling infrastructure, menand materials access, mine ventilation fans and a water management system.

    Mandalong Mine

    Mandalong Mine encompasses the extent of existing mining leases, underground

    mine workings, the Mandalong Mine Surface Site located near Morisset, the

    Cooranbong Colliery workings, the Mandalong Mine Cooranbong Entry Site at Dora

    Creek, the Delta Entry and coal delivery system near Wyee and the Mandalong Mine

    private haul road.

    Mandalong Mine Surface Site

    The Mandalong Mine Surface Site is located adjacent to the F3 Freeway interchange

    at Morisset and includes administration buildings, a workshop, a men and materials

    drift, ventilation fans and infrastructure for greenhouse gas abatement.

    Mandalong Mine Cooranbong Entry Site

    The Mandalong Mine Cooranbong Entry Site is located at Dora Creek and includes

    administration buildings, workshops, coal stockpiles, coal handling infrastructure and

    a water management system.

  • 7/25/2019 Profil Centennial Coal

    10/92

    NORTHERN COAL SERVICES COAL LOGISTICS PROJECT

    Page viii

    Mandalong Mine Haul Road

    The Mandalong Mine haul road is a privately owned haul road linking the Mandalong

    Mine - Cooranbong Entry Site to the Newstan Colliery via the Newstan-Eraring

    private haul road.

  • 7/25/2019 Profil Centennial Coal

    11/92

    NORTHERN COAL SERVICES COAL LOGISTICS PROJECT

    Page 1

    1.0 INTRODUCTION

    1.1 Background

    Centennial Coal Company (Centennial) is a coal mining and marketing company

    supplying thermal and coking coal to the domestic and export markets. Centennial is

    a major fuel supplier to the New South Wales energy industry, fuelling approximately

    46% of the States coal-fired electricity. Centennial sells approximately one third of its

    coal to export market customers including power stations and steel mills in Japan,

    Korea and Europe. Centennial exports its coal through the ports of Newcastle and

    Port Kembla.

    Centennial operates twelve coal mines in NSW, making Centennial one of the largest

    underground coal producers in NSW and now, as part of Banpu, a member of thelargest independent pan-Asian coal group. Centennials operations include Awaba,

    Mandalong, Mannering, Myuna and Newstan located in the northern region around

    Lake Macquarie. The surface facilities of the Newstan Colliery and former

    Cooranbong Colliery are integral to the ongoing processing, handling and transport of

    coal from the Newstan Colliery and Mandalong Mine operations into the export

    market. These services are managed by the Northern Coal Services business unit

    within Centennial.

    1.2 Project Overview

    Centennials Northern Coal Services is seeking approval for the Coal Logistics Project

    (the Project) under Part 4 Division 4.1 of the Environmental Planning and

    Assessment Act 1979 (EP&A Act). Specifically the Project proposes to:

    Transport up to 4 Million tonnes per annum (Mtpa) of coal from the

    Mandalong Mine Cooranbong Entry Site to the Newstan Colliery Surface

    Site by truck using the existing Mandalong Mine and Newstan-Eraring private

    haul roads;

    Upgrade the surface infrastructure of the Newstan Colliery to enable the

    handling and processing of up to 8 Mtpa of Run of Mine (ROM) consisting of

    up to 4.5 Mtpa from the Newstan Colliery and up to 4 Mtpa from the

  • 7/25/2019 Profil Centennial Coal

    12/92

    NORTHERN COAL SERVICES COAL LOGISTICS PROJECT

    Page 2

    Mandalong Mine through the Newstan Colliery Coal Preparation Plant (CPP)

    and coal handling infrastructure;

    Increase the coal stockpile capacity at the Newstan Colliery Surface Site;

    Transport up to 8 Mtpa of coal from the Newstan CPP or coal handling

    infrastructure through the Newstan Colliery rail loading facilities by train to the

    Port of Newcastle or Port Kembla;

    Operate coal handling facilities at Cooranbong;

    Transport up to 4.5 Mtpa of coal product from the Newstan Colliery to the

    Eraring Power Station or the Mandalong Mine - Cooranbong Entry Site by

    truck using the existing Newstan-Eraring and/or Mandalong Mine private haul

    roads;

    Transport up to 4 Mtpa of coal from the Mandalong Mine Cooranbong Entry

    Site to the Eraring Power Station via a dedicated overland conveyor owned

    and operated by Eraring Energy;

    Transport reject material to the Newstan Colliery Northern Reject

    Emplacement Area (NREA), the Newstan Colliery Southern Reject

    Emplacement Area (SREA) or the Lake Macquarie City Council (LMCC)

    owned Hawkmount Quarry via private haul roads;

    Construct and operate a coal crushing facility at the Mandalong Mine -

    Cooranbong Entry Site that has previously been approved but not yet

    constructed;

    Manage surface water at the Newstan Colliery Surface Site, the Mandalong

    Mine Cooranbong Entry Site, the Mandalong Mine private haul and the

    LMCC owned Hawkmount Quarry;

    Transfer water between the Newstan Colliery, the Awaba Colliery, the

    Hawkmount Quarry and the Mandalong Mine water management system;

    Undertake locomotive refuelling and servicing on site;

    Continue the construction of the Newstan Colliery SREA to RL60;

    Progressively rehabilitate disturbed areas;

    Provide employment for up to 100 personnel; and

  • 7/25/2019 Profil Centennial Coal

    13/92

    NORTHERN COAL SERVICES COAL LOGISTICS PROJECT

    Page 3

    Continue to operate the coal handling activities 24 hours per day seven days

    per week.

    The proposed Northern Coal Services - Coal Logistics Project area as shown in

    Figure 1includes:

    The Newstan Colliery Surface Site (including reject emplacement areas);

    The Mandalong Mine Cooranbong Entry Site;

    The existing Newstan-Eraring and Mandalong Mine private haul roads; and

    The LMCC owned Hawkmount Quarry.

  • 7/25/2019 Profil Centennial Coal

    14/92

    NORTHERN COAL SERVICES COAL LOGISTICS PROJECT

    Page 4

    Figure 1 Northern Coal Services Coal Logistics Project Area

  • 7/25/2019 Profil Centennial Coal

    15/92

    NORTHERN COAL SERVICES COAL LOGISTICS PROJECT

    Page 5

    1.3 Briefing Paper

    This Briefing Paper has been prepared by Centennials Northern Coal Services to:

    Provide the Department of Planning and Infrastructure (DP&I) and other

    relevant regulators with a description of the Project; and

    Identify likely key social and environmental issues associated with the Project.

    This Briefing Paper is intended to enable the Director-General to issue Environmental

    Assessment Requirements (EARs) to assist Centennial in the preparation of the

    Environmental Impact Statement (EIS) required to support the Project Application.

    The Briefing Paper is generally structured as follows:

    Section 1:provides an introduction to the Project;

    Section 2: provides a description of the site and an overview of the existing

    environment;

    Section 3: provides an overview of the existing and approved operations of

    the Newstan Colliery, the Awaba Colliery and the Mandalong Mine;

    Section 4:provides a description of the Project;

    Section 5:summarises the legislation relevant to the Project;

    Section 6: provides an overview of the preliminary environmental risks

    associated with the Project and the proposed assessment methodology for all

    key environmental issues identified in the preliminary environmental risk

    assessment for the Project;

    Section 7:describes the stakeholder consultation program to be undertaken

    to ensure all interested parties are consulted with regards to the Project; and

    Section 8:provides a justification for the Project.

    1.4 The Appl icant

    Centennials Northern Coal Services Pty Limited is the applicant for this proposed

    Project. Northern Coal Services Pty Limited is a wholly owned subsidiary of

    Centennial Coal Company (Centennial), which is a wholly owned subsidiary of Banpu

    Public Company Limited (Banpu).

  • 7/25/2019 Profil Centennial Coal

    16/92

    NORTHERN COAL SERVICES COAL LOGISTICS PROJECT

    Page 6

    2.0 SITE DESCRIPTION

    2.1 Site Locali ty and Existing Land Uses

    2.1.1 Newstan Colliery

    Newstan Colliery is regionally located approximately 25 kilometres south-west of

    Newcastle and 140 kilometres north of Sydney within the Lake Macquarie Local

    Government Area (LGA). The Newstan Colliery Surface Site is located in Fassifern

    approximately four kilometres north of the township of Toronto.

    2.1.2 Mandalong Mine Cooranbong Entry Site

    The Mandalong Mine Cooranbong Entry Site is situated approximately

    90 kilometres north-east of Sydney on the western side of Lake Macquarie and within

    the Lake Macquarie LGA. The Mandalong Mine Cooranbong Entry Site is located

    approximately 2.6 kilometres north of the township of Dora Creek.

    A 3.4 kilometre private haul road owned by Centennial Mandalong links the

    Mandalong Mine Cooranbong Entry Site to the Newstan Colliery via the existing

    Newstan-Eraring private haul road. The Newstan-Eraring private haul road is ownedby Eraring Energy, is approximately 13 kilometres long and links to the Newstan

    Colliery to the Eraring Power Station.

    2.2 Landforms and Topography

    2.2.1 Newstan Colliery

    The Newstan Colliery is located in gently undulating terrain bordered by vegetation.

    The site has an approximate elevation of 30 metres AHD at Surface Site and an

    approximate elevation of 72 metres AHD (highest point) at the SREA.

    2.2.2 Mandalong Mine Cooranbong Entry Site

    The Mandalong Mine Cooranbong Entry Site typically has an elevation of 10

    metres to 14 metres AHD. The site has been excavated into the floor of a small

  • 7/25/2019 Profil Centennial Coal

    17/92

    NORTHERN COAL SERVICES COAL LOGISTICS PROJECT

    Page 7

    valley and is surrounded to the south, west and north by ridges with elevations of

    typically 40 to 50 metres AHD.

    2.3 Land Ownership

    2.3.1 Newstan Colliery

    The Newstan Colliery Surface Site occupies mainly freehold land. The remainder of

    the land is Crown land. Land title descriptions and ownership associated with the

    Newstan Colliery Surface Site is listed in Table 1 and shown in Figure 2 below.

    Table 1 List of Land Titles for the Newstan Colliery Surface Site

    Lot DP Owner

    C 381399 Centennial Fassifern Pty Limited

    441 583057 Fassifern Colliery Pty Limited

    442 583057 Fassifern Colliery Pty Limited

    443 583057 Fassifern Colliery Pty Limited

    148 728974 Centennial Fassifern Pty Limited

    390 1064199 Centennial Fassifern Pty Limited

    64 755207 Fassifern Colliery Pty Limited

    1 121470 Fassifern Colliery Pty Limited

    630 816256 Crown Land

    631 816256 Crown Land

    11 1031778 Fassifern Colliery Pty Limited

    13 1031778 Fassifern Colliery Pty Limited

    100 1149240 Fassifern Colliery Pty Limited

  • 7/25/2019 Profil Centennial Coal

    18/92

    NORTHERN COAL SERVICES COAL LOGISTICS PROJECT

    Page 8

    103 1149241 Fassifern Colliery Pty Limited

    104 1149241 Fassifern Colliery Pty Limited

    15 1031778 Fassifern Colliery Pty Limited

    17 1031778 Fassifern Colliery Pty Limited

    18 1031778 Fassifern Colliery Pty Limited

    20 1031778 Fassifern Colliery Pty Limited

    27 755207 Fassifern Colliery Pty Limited

    66 755207 Fassifern Colliery Pty Limited

    100 1127677 Croft Bros. Pty Limited

    591 607932 Nicholas & Robert Croft

    234 755207 Crown Land

    5 46737 Crown Land

    6 46737 Crown Land

  • 7/25/2019 Profil Centennial Coal

    19/92

    NORTHERN COAL SERVICES COAL LOGISTICS PROJECT

    Page 9

    Figure 2 Newstan Colliery Surface Site Land Ownership

  • 7/25/2019 Profil Centennial Coal

    20/92

    NORTHERN COAL SERVICES COAL LOGISTICS PROJECT

    Page 10

    2.3.2 Mandalong Mine Cooranbong Entry Site

    Land at the Mandalong Mine Cooranbong Entry Site is largely Crown land or land

    owned by Centennial Fassifern Pty Limited. Land title descriptions and ownership

    associated with the Mandalong Mine Cooranbong Entry Site is listed in Table 2 andshown in Figure 3 below.

    Table 2 List o f Land Titles for the Mandalong Mine Cooranbong Entry Site

    Lot DP Owner

    7306 1164232 Crown Land

    11 1050120 Eraring Energy

    211 702166 Centennial Fassifern Pty Limited

    210

    755218 Gregory James Agius and Rebbekah

    Josephine Atkinson

    221 702167 Centennial Fassifern Pty Limited

    23 264502 Centennial Fassifern Pty Limited

    24 264502 Centennial Fassifern Pty Limited

    1 960790 Centennial Fassifern Pty Limited

    97 755218 Crown land

    10 1050120 Crown land

    186 755218 Centennial Fassifern Pty Limited

    187 755218 Crown land

    170 755218 Centennial Fassifern Pty Limited

    179 755218 Centennial Fassifern Pty Limited

  • 7/25/2019 Profil Centennial Coal

    21/92

    NORTHERN COAL SERVICES COAL LOGISTICS PROJECT

    Page 11

    173 755218 Crown land

    169 755218 Centennial Fassifern Pty Limited

    1 6747 Centennial Fassifern Pty Limited

    2 6747 Centennial Fassifern Pty Limited

    171 755218 Crown land

  • 7/25/2019 Profil Centennial Coal

    22/92

    NORTHERN COAL SERVICES COAL LOGISTICS PROJECT

    Page 12

    Figure 3 Mandalong Mine Cooranbong Entry Site Land Ownership

  • 7/25/2019 Profil Centennial Coal

    23/92

    NORTHERN COAL SERVICES COAL LOGISTICS PROJECT

    Page 13

    3.0 CURRENT APPROVED OPERATIONS

    3.1 Newstan Colliery

    Newstan Colliery was granted Development Consent DA 73-11-98 by the then

    Minister for Urban Affairs and Planning on 14 May 1999 under Part 4 of the EP&A

    Act. Centennial Newstan is approved under DA 73-11-98 to undertake the following

    activities:

    Extraction of up to 4 Mtpa of ROM coal from within the Newstan Colliery Life

    Extension Area;

    Process up to 4 Mtpa of ROM coal through the Newstan Colliery CPP;

    Export up to 3 Mtpa of coal through the Newstan Colliery rail loading facilitiesby train;

    Transport up to 2 Mtpa of coal by truck to the Eraring Power Station using the

    existing Newstan-Eraring private haul road;

    Receive ROM coal from the Mandalong Mine by truck;

    Receive up to 880,000 tpa of coal from the Awaba Colliery by truck;

    Transport reject material from the Newstan Colliery CPP to the Northern

    Reject Emplacement Area;

    Transport reject material from the Newstan Colliery CPP to the Southern

    Reject Emplacement Area;

    Construction of the SREA to RL60; and

    Operate activities 24 hours per day 7 days a week.

    3.2 Mandalong Mine

    Mandalong Mine was granted Development Consent DA 97/800 by the then Minister

    for Urban Affairs and Planning on 14 October 1998 under Part 4 of the EP&A Act.

    Mandalong Mine is an extension of the old Cooranbong Colliery. After obtaining

    Development Consent in 1998, construction commenced on the Mandalong Mine

    Surface Site and decline tunnel to access the Mandalong underground mining area.

    Coal produced by the Mandalong Mine is either transported to the Delta Entry Site or

  • 7/25/2019 Profil Centennial Coal

    24/92

    NORTHERN COAL SERVICES COAL LOGISTICS PROJECT

    Page 14

    the Mandalong Mine Cooranbong Entry Site where it is either transported to the

    Eraring Power Station or the Newstan Colliery Surface Site for further processing and

    transport into the export market.

    Approved activities for the Mandalong Mine - Cooranbong Entry Site include:

    Receipt of up to 4 Mtpa of ROM coal from the Mandalong Mine underground

    workings;

    Construction and operation of coal handling infrastructure including a coal

    preparation plant;

    Coal stockpiling;

    Construction and operation of a private haul road linking the Mandalong Mine

    Cooranbong Entry site to the Newstan Colliery Surface Site;

    Delivery of up to 2 Mtpa of coal to the Eraring Power Station via a dedicated

    overland conveyor owned and operated by Eraring Energy;

    Delivery of up to 2 Mtpa of ROM coal to the Newstan Colliery surface site by

    truck via the Mandalong Mine and Newstan-Eraring private haul roads;

    Delivery of stone material by truck using the existing Mandalong Mine and

    Newstan-Eraring private haul roads to the Newstan Colliery emplacement

    areas;

    Delivery of reject material to the LMCC owned Hawkmount Quarry for

    emplacement;

    Pumping of tailings into the underground workings of the Mandalong Mine;

    Operation of a water management system; and

    Operate activities 24 hours per day 7 days a week.

    3.3 Infrastructure

    3.3.1 Newstan Colliery

    The existing Newstan Colliery Surface Site is located adjacent to Miller Road, near

    the township of Fassifern. The Newstan Colliery surface infrastructure incudes:

  • 7/25/2019 Profil Centennial Coal

    25/92

    NORTHERN COAL SERVICES COAL LOGISTICS PROJECT

    Page 15

    An administration building;

    A bathhouse with adequate facilities and services for up to 350 people;

    A CPP and coal storage bins with a design capacity in excess of 4 million

    tonnes per annum;

    Various workshops, service buildings and material storage sheds;

    Visitor and employee parking areas;

    A men and materials drift winder for access to underground workings;

    A coal conveyor drift and coal conveyor drive house to transport coal from the

    underground workings to the surface;

    Ventilation fans;

    A ballast borehole at Awaba;

    Coal stockpile areas;

    A rail loop;

    Reject emplacement areas; and

    A comprehensive water management control system and associated

    infrastructure.

    The Newstan Colliery also operates a range of ancillary surface infrastructure for the

    provision of water, electricity, ventilation and communications to the site and removal

    of gas from the underground workings.

    3.3.2 Mandalong mine Cooranbong Entry Site

    Infrastructure at the existing Mandalong Mine Cooranbong Entry Site consists of:

    An administration building and bath house;

    Car parking;

    A material storage facility;

    A workshop;

    Personnel and materials access drift;

  • 7/25/2019 Profil Centennial Coal

    26/92

    NORTHERN COAL SERVICES COAL LOGISTICS PROJECT

    Page 16

    A twin centrifugal fan upcast air shaft;

    A compressor building;

    An emergency services helipad;

    Equipment and materials storage sheds;

    Water management and associated infrastructure; and

    Coal handling plant and stockpiles.

    Coal handling plant infrastructure includes conveyors leading from the South Drift, a

    rotary breaker and sizer, conveyor drive head units, storage bins, coal stockpile

    areas and a haul road linking the Cooranbong Services Site to the Newstan-Eraring

    private haul road. The majority of the site is paved with runoff from the site beingdirected into a controlled water management system. The Mandalong Mine has

    approval for upgrades to the coal handling system at the Cooranbong Entry Site to

    include additional washing and processing infrastructure. These upgrades have not

    yet been constructed.

    3.4 Coal Handling and Transport

    The current approved coal handling and transport operations across the NewstanColliery and the Mandalong Mine are detailed below and shown in Figure 4.

    3.4.1 Domestic Coal Transportation Newstan Colliery

    Domestic coal at the Newstan Colliery is delivered by conveyor from the Newstan

    CPP to the 2000 tonne truck loading bin prior to being loaded onto trucks and

    transported to Eraring Power Station via the Newstan-Eraring private haul road.

    Domestic coal may also be stockpiled within the Newstan rail loop before it is loaded

    onto trains by front end loaders. The coal is then transported by rail to the Vales

    Point Power Station.

  • 7/25/2019 Profil Centennial Coal

    27/92

    NORTHERN COAL SERVICES COAL LOGISTICS PROJECT

    Page 17

    3.4.2 Domestic Coal Transportation Mandalong Mine

    Domestic coal delivered from the Mandalong Mine to the Mandalong Mine

    Cooranbong Entry Site is transported directly to the Eraring Power Station via the

    Eraring Energy owned enclosed overland conveyor.

    3.4.3 Export Coal Transportation Newstan Colliery

    Export quality coal produced by the Newstan Colliery CPP is transported by truck

    from the 2000 tonne truck loading bin and stockpiled within the central portion of the

    existing rail loop. Coal is then loaded by front end loaders onto the trains for

    transportation along the Main Northern Railway to the port of Newcastle or Port

    Kembla.

    3.4.4 Export Coal Transportation Mandalong Mine

    Export quality coal produced by the Mandalong Mine and delivered to the Mandalong

    Mine Cooranbong Entry Site is transported by truck using the Mandalong Mine

    private haul road to the Newstan Colliery Surface Site. Mandalong Mine coal is then

    processed and handled in accordance with the approved coal handling operations of

    the Newstan Colliery before being loaded onto trains and transported to the port of

    Newcastle or Port Kembla.

    3.5 Reject Management Newstan Coll iery

    Fine reject material (tailings), produced from the washing of coal through the

    Newstan CPP is pumped to the approved Newstan Colliery SREA. The SREA has an

    approved development area of 75 hectares, which equates to an emplacement

    volume of approximately 12.3 million cubic metres. The SREA has been designed to

    be developed in a series of stages to minimise the land area that needs to be cleared

    at any time. This sequential development also allows a free-draining and stable final

    landform to be readily achieved if emplacement in this area ceases at any stage of

    the development. A filter wall and bore are strategically located within the confines of

    the tailings dam which allows excess water to be decanted from the tailings dam into

  • 7/25/2019 Profil Centennial Coal

    28/92

    NORTHERN COAL SERVICES COAL LOGISTICS PROJECT

    Page 18

    underground workings. The decanted water is recycled for reuse in the mine and the

    CPP.

    Coarse reject material is transported by truck from the Newstan Colliery CPP to the

    SREA for emplacement or use in the construction of the dam wall. Some coarsereject material is transported to the NREA where it is used as a capping material in

    the rehabilitation process.

    3.6 Reject Management Mandalong Mine

    Currently, approximately 7800 tonnes per year of stone material produced from the

    processing of coal at the Mandalong Mine - Cooranbong Entry Site is transported by

    truck, using the existing Mandalong Mine and Newstan-Eraring private haul roads, to

    the Newstan Colliery for use in rehabilitation or emplacement within the Newstan

    Colliery reject emplacement areas. Mandalong Mine has an existing approval to

    transport coarse reject material produced from the approved but not yet constructed

    wash plant to the Hawkmount Quarry for emplacement and dispose of fine reject

    material (tailings) underground into disused workings of the Cooranbong Colliery.

    Stone material from the Mandalong Mine that is processed at the Newstan Colliery

    Surface Site is managed in accordance with the approved Newstan Colliery reject

    management system.

  • 7/25/2019 Profil Centennial Coal

    29/92

    NORTHERN COAL SERVICES COAL LOGISTICS PROJECT

    Page 19

    Figure 4 Current Approved Coal Handling and Transport System

  • 7/25/2019 Profil Centennial Coal

    30/92

    NORTHERN COAL SERVICES COAL LOGISTICS PROJECT

    Page 20

    3.7 Water Management

    The water management system at the Newstan Colliery and the Mandalong Mine

    Cooranbong Entry Site is comprised of both surface and underground water and is a

    complex system that has been progressively developed over the life of theoperations. The water management system for all sites has been designed to:

    Maximise the separation of clean and dirty water;

    Manage water discharge from site, in terms of volume and quality, to a level

    that is acceptable for environmental management;

    Minimise water discharges from the premises by maximising, where

    practicable available water storages; and

    Minimise discharges of dirty water from the premises.

    Figure 5 and Figure 6 depict the surface water management system at both the

    Newstan Colliery Surface Site and the Mandalong Mine Cooranbong Entry Site

    respectively.

  • 7/25/2019 Profil Centennial Coal

    31/92

    NORTHERN COAL SERVICES COAL LOGISTICS PROJECT

    Page 21

    Figure 5 Newstan Colliery Surface Water Management System

  • 7/25/2019 Profil Centennial Coal

    32/92

    NORTHERN COAL SERVICES COAL LOGISTICS PROJECT

    Page 22

    Figure 6 Mandalong Mine Cooranbong Entry Site Surface Water

    Management System

  • 7/25/2019 Profil Centennial Coal

    33/92

    NORTHERN COAL SERVICES COAL LOGISTICS PROJECT

    Page 23

    3.8 Consents, Leases and Licences

    3.8.1 Newstan Colliery Development Consents

    Newstan Colliery was granted Development Consent by the (then) Minister for Urban

    Affairs and Planning on the 14 May 1999 for the range of activities detailed and

    assessed within the Newstan Colliery Life Extension Project Environmental Impact

    Statement (Newstan EIS). Modifications to DA 73-11-98 include:

    Approval to allow for the continuation of underground mining within longwall

    panel 24 and the relocation of an approved, however not yet constructed,

    ventilation shaft and associated service corridors granted on 23 September

    2007;

    Approval to wash coal from the Centennial Mandalong Mine at Newstan

    Colliery granted on 27 November 2009; and

    Approval to wash coal from the Centennial Awaba Colliery at Newstan

    Colliery, the acceptance of stone reject material from the Centennial

    Mandalong Mine at Newstan Colliery and the establishment of a 30,000 tonne

    emergency coal stockpile granted on 26 November 2010.

    In 2011, Centennial Newstan submitted an application to DP&I to modify DA 73-11-

    98 to allow for the recommencement of mining using bord and pillar mining methodswithin an area referred to as Main West. At the time of submitting this document,

    approval for the Main West Mining Project has not yet been obtained. Table 3

    contains a list of the consents relevant to the Newstan Colliery operation.

  • 7/25/2019 Profil Centennial Coal

    34/92

    NORTHERN COAL SERVICES COAL LOGISTICS PROJECT

    Page 24

    Table 3 Newstan Colliery Development Consents

    Reference Descript ion Expiry date

    DA 73-11-98

    Approves the extension of Newstan underground

    coalmine and upgrade of associated surface facilities on

    May 14 1999 (modified in 2007, 2009 and 2010).

    6/07/2020

    DA 83/877

    Authorises the transport of coal via the NewstanEraring

    private haul road to Eraring and to the Newstan CHPP

    from Awaba Colliery surface facilities.

    N/A

    DA 93/00080Allows the development of coal storage and a rail loading

    area.N/A

    DA 88/0645Permits the establishment of a coal storage area and

    water management facilities adjacent to rail loop.N/A

    DA

    99/02806/1N

    Permits the establishment of an emergency egress and

    bulk materials delivery facility.N/A

    DA 95/00152 For addition to lease area for land under ML 1380. N/A

    The Newstan-Eraring private haul road is owned by Eraring Energy with whom

    Centennial Newstan has an agreement with for its use. The road is located on Crown

    land used under Permissive Occupancy #16313 held by Eraring Energy. A small

    section of the haul road access from the Awaba Colliery stockpile area to the junction

    with the main haul road is owned by Centennial Newstan. The road is constructed on

    Crown land leased by Centennial Newstan.

    3.8.2 Mandalong Mine Development Consents

    Mandalong Mine was granted Development Consent DA 97/800 in 1998 for the

    extension to underground mining activities at the Cooranbong Services Site and

    development of the Mandalong Mine Surface Facilities Area. Development Consent

    97/800 is supported by the Cooranbong Colliery Life Extension Project -

  • 7/25/2019 Profil Centennial Coal

    35/92

    NORTHERN COAL SERVICES COAL LOGISTICS PROJECT

    Page 25

    Environmental Impact Statement (Umwelt, 1997). Seven modifications to the original

    Development Consent have since been approved, as follows:

    Development Consent DA 97/800 was first modified in 2001 under section

    96(1A) of the EP&A Act to allow for minor changes to conditions of consentrelating to the preparation of property subsidence management plans,

    longwall subsidence management plans and notification of landholder

    requirements;

    In 2005 a modification was approved under section 96(2) of the EP&A Act for

    the installation of methane drainage plant and the transport of 1,000 tonnes of

    coal from the Mine by road. Centennial Mandalong has since constructed and

    commenced operation of the methane drainage plant;

    Condition 60a(iii) of the 2005 modification included a requirement for

    Centennial Mandalong to submit a report on the progress towards

    implementing greenhouse gas abatement. In accordance with this condition,

    a report dated 24th June 2005 and a subsequent application was submitted to

    modify DA 97/800 to allow for the installation and operation of enclosed

    methane gas flare units for high purity methane drainage gas. This

    modification was approved in 2006; and

    In 2009 three modifications to the consent were approved for the:

    o Construction and operation of gas engines to produce up to 12 Mega

    Watts (MW) of electricity using high purity methane drainage gas, an

    increase in the rate of ROM production to 6 Mtpa, relocation of the

    approved ballast borehole, and an update of subsidence conditions to

    make them consistent with the current Subsidence Management Plan

    (SMP) process;

    o Temporary increase in the amount of coal product transported by

    conveyor from Mandalong Mine to the Eraring Power Station

    stockpiles, and processing of Mandalong coal at the Newstan Colliery;

    and

    o Modifications to the heights and locations of already approved but not

    yet constructed coal handling infrastructure at the Cooranbong

    Services Site.

  • 7/25/2019 Profil Centennial Coal

    36/92

    NORTHERN COAL SERVICES COAL LOGISTICS PROJECT

    Page 26

    In 2011, approval was granted for the installation and ongoing operation of

    new technology known as a ventilation air methane regenerative after burner

    (VAMRAB) to demonstrate the ability of the technology to capture and abate

    ventilation air methane from the mine.

    In addition to DA 97/800, Development Consent DA 35/2/2004 was granted in July

    2004 by the Minister for Planning, approving the construction and operation of the

    coal handling and clearance system at the Delta Entry Site. Table 4 details the

    Development Consents held by Centennial Mandalong.

    Table 4 Mandalong Mine Development Consents

    Reference Descr ipt ion Expiry Date

    DA 97/800 Development Consent for Mandalong Mine 14/10/2019

    DA 35/2/2004

    Development Consent for the construction

    and use of the Mandalong Coal Delivery

    System (Delta Link Project)

    04/07/2021

    3.8.3 Centennial Newstan Mining Leases

    Centennial Newstan holds a number of mining leases which are detailed in Table 5

    and Figure 7below.

    Table 5 Centennial Newstan Mining Leases

    Lease Expiry Date

    CCL727 11/08/27

    CCL746 31/12/28

    CCL763 09/06/22

    CCL764 18/05/21

    ML1380 18/09/16

  • 7/25/2019 Profil Centennial Coal

    37/92

    NORTHERN COAL SERVICES COAL LOGISTICS PROJECT

    Page 27

    Newstan Colliery has eleven benefiting unregistered subleases with adjoining mining

    lease holders to mine various coal seams. Recent changes to the Mining Act 1992

    have resulted in all the subleases held by Centennial Newstan being deregistered.

    Newstan Colliery is in the process of making application to have the various

    subleases reregistered.

    ML1452 06/07/20

    ML1480 20/07/23

    ML1587 23/10/27

    MPL304 25/03/14

    MPL305 25/03/14

    MPL327 05/08/15

    MPL328 05/08/15

    PLL497 24/08/17

  • 7/25/2019 Profil Centennial Coal

    38/92

    NORTHERN COAL SERVICES COAL LOGISTICS PROJECT

    Page 28

    Figure 7 Centennial Newstan Mining Leases

  • 7/25/2019 Profil Centennial Coal

    39/92

    NORTHERN COAL SERVICES COAL LOGISTICS PROJECT

    Page 29

    3.8.4 Centennial Mandalong Mining Leases

    Table 6lists the mining leases relevant to the Centennial Mandalong operations. The

    Mandalong Mine - Cooranbong Entry site is located within CCL 762 held by

    Centennial Mandalong. The Mandalong Mine private haul road is located withinCCL746 held by Centennial Newstan. Centennial Newstan holds Licence Number

    LI432152 with the Land and Property Management Authority for the construction and

    operation of the Mandalong Mine private haul road.

    Table 6 Centennial Mandalong Mining Leases

    3.8.5 Environmental Protection Licences

    Newstan Colliery currently holds EPL 395. Mandalong Mine holds EPL 365 which

    covers the Mandalong Mine Cooranbong Entry Site.

    Lease Expiry Date

    CCL 762 13/10/2022

    CCL746 31/12/2028

    ML 1443 01/03/2020

    ML 1431 27/05/2019

    ML1543 25/11/2024

    ML1553 07/09/2025

    MPL 191 24/02/2023

    MPL 329 04/08/2015

  • 7/25/2019 Profil Centennial Coal

    40/92

    NORTHERN COAL SERVICES COAL LOGISTICS PROJECT

    Page 30

    3.9 Environmental Management System

    The Mandalong Mine and the Newstan Colliery have an established Environmental

    Management System (EMS) that has been developed in accordance with the

    Centennial Coal Environmental Management System Framework (October 2011).

    The EMS for both sites has been developed and implemented to ensure the effective

    management of environmental issues and compliance with all regulatory

    requirements while providing a means for continued improvement in the

    environmental performance of the sites. The major components of the EMS include:

    Centennial Coals Environmental Policy;

    Various management plans, management documents and environmental

    monitoring programmes; and

    An Environmental Management Strategy.

    The existing environmental management plans in place the Newstan Colliery include:

    Noise Management;

    Dust Management Plan;

    Flora & Fauna Management Plan;

    Water Management Plan;

    Wetland Management Plan;

    Archaeology & Cultural Heritage Plan;

    Landscape Management Plan;

    Fine Rejects Management Plan;

    Erosion & Sediment Control Plan;

    Land Management Plan;

    Soil Stripping Management Plan; and

    Bush Fire Management Plan.

    The environmental management plans in place at the Mandalong Mine, relevant to

    the Mandalong Mine Cooranbong Entry Site include:

  • 7/25/2019 Profil Centennial Coal

    41/92

    NORTHERN COAL SERVICES COAL LOGISTICS PROJECT

    Page 31

    Underground Mining Environmental Management Plan;

    Surface Environmental Management Plan;

    Stakeholder Engagement Plan;

    Emergency Plan;

    Wetland Management Plan;

    Energy Savings Action Plan; and

    Cooranbong Haul Road Environmental Management Plans.

  • 7/25/2019 Profil Centennial Coal

    42/92

    NORTHERN COAL SERVICES COAL LOGISTICS PROJECT

    Page 32

    4.0 PROPOSED PROJECT

    4.1 Background

    Centennials Northern Coal Services is seeking approval for the Coal Logistics Project

    under Part 4 Division 4.1 of the EP&A Act. Specifically the Project proposes to:

    Transport up to 4 Million tonnes per annum (Mtpa) of coal from the

    Mandalong Mine Cooranbong Entry Site to the Newstan Colliery Surface

    Site by truck using the existing Mandalong Mine and Newstan-Eraring private

    haul roads;

    Upgrade the surface infrastructure of the Newstan Colliery to enable the

    handling and processing of up to 8 Mtpa of Run of Mine (ROM) consisting of

    up to 4.5 Mtpa from the Newstan Colliery and up to 4 Mtpa from the

    Mandalong Mine through the Newstan Colliery Coal Preparation Plant (CPP)

    and coal handling infrastructure;

    Increase the coal stockpile capacity at the Newstan Colliery Surface Site;

    Transport up to 8 Mtpa of coal from the Newstan CPP or coal handling

    infrastructure through the Newstan Colliery rail loading facilities by train to the

    Port of Newcastle or Port Kembla;

    Operate coal handling facilities at Cooranbong;

    Transport up to 4.5 Mtpa of coal product from the Newstan Colliery to the

    Eraring Power Station or the Mandalong Mine - Cooranbong Entry Site by

    truck using the existing Newstan-Eraring and/or Mandalong Mine private haul

    roads;

    Transport up to 4 Mtpa of coal from the Mandalong Mine Cooranbong Entry

    Site to the Eraring Power Station via a dedicated overland conveyor owned

    and operated by Eraring Energy;

    Transport reject material to the Newstan Colliery Northern Reject

    Emplacement Area (NREA), the Newstan Colliery Southern Reject

    Emplacement Area (SREA) or the Lake Macquarie City Council (LMCC)

    owned Hawkmount Quarry via private haul roads;

  • 7/25/2019 Profil Centennial Coal

    43/92

    NORTHERN COAL SERVICES COAL LOGISTICS PROJECT

    Page 33

    Construct and operate a coal crushing facility at the Mandalong Mine -

    Cooranbong Entry Site that has previously been approved but not yet

    constructed;

    Manage surface water at the Newstan Colliery Surface Site, the MandalongMine Cooranbong Entry Site, the Mandalong Mine private haul and the

    LMCC owned Hawkmount Quarry;

    Transfer water between the Newstan Colliery, the Awaba Colliery, the

    Hawkmount Quarry and the Mandalong Mine water management system;

    Undertake locomotive refuelling and servicing on site;

    Continue the construction of the Newstan Colliery SREA to RL60;

    Progressively rehabilitate disturbed areas;

    Provide employment for up to 100 personnel; and

    Continue to operate the coal handling activities 24 hours per day seven days

    per week.

    4.2 Project Area

    The Northern Coal Services Coal Logistics Project Area as shown in Figure 1

    includes:

    The Newstan Colliery Surface Site (including reject emplacement areas);

    The Mandalong Mine Cooranbong Entry Site;

    The existing Newstan-Eraring and Mandalong Mine private haul roads; and

    The LMCC owned Hawkmount Quarry.

    4.3 Coal Handling

    The Project will allow for the flexible processing and handling of coal from both the

    Newstan Colliery and Mandalong Mine. ROM coal produced by the Newstan Colliery

    will be delivered to and processed by the Newstan Colliery CPP before being

    transported to the domestic or export markets. Coal from the Mandalong Mine will be

  • 7/25/2019 Profil Centennial Coal

    44/92

    NORTHERN COAL SERVICES COAL LOGISTICS PROJECT

    Page 34

    either transported from the Mandalong Mine - Cooranbong Entry Site to the Newstan

    Colliery Surface Site by truck using the Mandalong Mine and Newstan-Eraring

    private haul roads or transported directly from the Mandalong Mine Cooranbong

    Entry Site to the Eraring Power Station using the existing Eraring Energy owned

    overland conveyor. Coal transportation to the Newstan Colliery Surface Site will be at

    a rate of up to 4 Mtpa or the Eraring Power Station at a rate of up to 4 Mtpa.

    Mandalong Mine coal will either be processed through the Newstan CPP or

    transported directly into the export market through the Newstan Colliery rail loading

    facility.

    The Newstan Colliery coal handling infrastructure and CPP will be upgraded to allow

    up to 8 Mtpa to be processed and handled at the Newstan Colliery Surface Site. Up

    to 8 Mtpa of either Newstan or Mandalong Mine coal will be transported into theexport market through the Newstan Colliery rail loading facilities.

    Up to 4.5 Mtpa of coal will be transported from the Newstan Colliery Surface Site to

    the Eraring power Station via the Newstan-Eraring private haul road.

    Figure 8 depicts the coal handling and transport system propsed for the Northern

    Coal Services Coal Logistics Project.

    4.4 Reject Management

    Coarse reject material produced form the processing of coal through the Newstan or

    Cooranbong Colliery CPPs will be either transported to the Newstan Colliery NREA

    for use in capping and rehabilitation of the site or SREA for use in the construction of

    the dam wall or emplacement. Coarse reject material will also be transported by truck

    using the existing Newstan-Eraring and Mandalong Mine private haul roads for

    emplacement at the LMCC owned Hawkmount Quarry.

    Fine rejects (tailings) will continue to be pumped from the Newstan Colliery CPP to

    the SREA for emplacement.

  • 7/25/2019 Profil Centennial Coal

    45/92

    NORTHERN COAL SERVICES COAL LOGISTICS PROJECT

    Page 35

    Figure 8 Proposed Coal Handling and Transport System

  • 7/25/2019 Profil Centennial Coal

    46/92

    NORTHERN COAL SERVICES COAL LOGISTICS PROJECT

    Page 36

    4.5 Infrastructure

    The proposed Project will utilise the existing infrastructure of the Newstan Colliery

    and the Mandalong Mine Cooranbong Entry Site, including existing private haul

    roads and rail loading facilities. The Project proposes upgrades to the NewstanColliery CPP and coal handling infrastructure to allow for the handling and

    processing of up to 8 Mtpa of ROM coal from either the Newstan Colliery or

    Mandalong Mine. The Project will also require the construction and operation of an

    automatic train loading facility at the Newstan Colliery to facilitate the transport of up

    to 8 Mtpa through the Newstan Colliery rail loading facility into the export market.

    The Newstan Colliery Extension of Mining Project currently being considered by

    Centennial proposes upgrades to the infrastructure at the Awaba Colliery Surface

    Site to accommodate for the proposed relocation of the Centennial Newstan

    workforce. Once the Centennial Newstan workforce has relocated to the Awaba

    Colliery Surface Site, the existing infrastructure at the Newstan Colliery Surface Site,

    including administration buildings, workshops and storage areas will continue to be

    utilised by the Coal Logistics Project Team. Minor upgrades to this infrastructure may

    be required.

    Additional infrastructure including support buildings and infrastructure for electrical

    reticulation, water reticulation, water management, communications, hydrocarbonstorage and management and other services may also be required.

    An additional coal crushing facility at the Mandalong Mine Cooranbong Entry Site

    currently approved for construction by the Mandalong Mine Development Consent

    DA 97/800 will be constructed and operated as part of the Coal Logistics Project.

    4.6 Water Management

    The Project will continue to operate and manage the surface water management

    systems of the Newstan Colliery, the Mandalong Mine - Cooranbong Entry Site, the

    Mandalong Mine private haul road and the LMCC owned Hawkmount Quarry.

    Surface water management includes the supply of potable water and the

    management of all licenced discharge points at these sites. Upgrades to the water

    management systems may be required at all sites and will be discussed in detail in

    the EIS. Centenial are currently investigating water management options at a

  • 7/25/2019 Profil Centennial Coal

    47/92

    NORTHERN COAL SERVICES COAL LOGISTICS PROJECT

    Page 37

    regional level across its operations and options to manage water quality at both the

    Newstan Colliery Surface Site and the Mandalong mine Cooranbong Entry Site.

    These investigations involve ongoing discussions with the Office of Environment and

    Heritage and will be further detailed within the EIS.

    Additional water management infrastructure will be required to be constructed at the

    Hawkmount Quarry to manage surface water at the site. Detailed water management

    requirements for the Hawkmount Quarry will also be discussed in the EIS.

    4.7 Hours of Operation and Personnel

    The coal handling, processing and transport operations associated with this Project

    will be undertaken 24 hours a day, seven days a week. The project will require

    approximately 100 full time personnel to be engaged to manage the Project. These

    100 personnel will be spread across the Newstan Colliery Surface Sites and the

    Mandalong Mine Cooranbong Entry Site and will utilise existing buildings and car

    parking facilities.

    4.8 Additional Licences and Approvals

    A new EPL will be required to support the Project incorporating existing Newstan

    Colliery and Mandalong Mine Cooranbong Entry Site Licenced Discharge Points. A

    review of all additional licences or approvals required to support the Project will be

    undertaken as part of the preparation of the EIS.

    4.9 Environmental Management System

    If the Project is approved, the EMS of the Newstan Colliery and the Mandalong Mine

    will be revised to develop a single EMS to cover the activities associate with the

    Northern Coal Services - coal logistics operations. The EMS will be developed, taking

    into consideration the results of specialist studies undertaken as part of the

    development of the EIS.

  • 7/25/2019 Profil Centennial Coal

    48/92

    NORTHERN COAL SERVICES COAL LOGISTICS PROJECT

    Page 38

    5.0 PLANNING CONSIDERATIONS

    5.1 Introduction

    The Project will be assessed in full consideration of the applicable statutory planning

    instruments of the Commonwealth and State, as well as associated planning and

    environmental frameworks. This section describes the statutory planning instruments

    relevant to the Project, and assesses their implications in relation to the required

    approval process.

    5.2 Commonwealth Legislation

    5.2.1 Environment Protection and Biodiversity Conservation Act 1999

    The Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act)

    came into effect on 16 July 2000 and is administered by the Commonwealth

    Department of the Sustainability, Environment, Water, Population and Communities

    (SEWPaC). Part 3 of the EPBC Act states that an action that has, will have or is likely

    to have a significant impact on a Matter of National Environmental Significance

    (MNES), may not be undertaken without prior approval of the Minister for SEWPaC.

    An assessment of whether the Project will have a significant impact on these MNES

    will be undertaken as part of the environmental assessment process. If required, a

    referral will be submitted to SEWPaC to determine if the Project is a controlled action

    under the EPBC Act.

    5.2.2 National Greenhouse and Energy Reporting Act 2007

    The National Greenhouse and Energy Reporting Act 2007 (NGER Act) provides a

    single National framework for the reporting and dissemination of information

    regarding greenhouse gas emissions, greenhouse gas projects and energy use, and

    production by corporations. The NGER Act mandates registration and reporting by

    corporations whose energy production or use, or greenhouse gas emissions meet

    specified thresholds. Centennial reports emissions from the corporation which

    includes emissions from the Newstan Colliery, the Awaba Colliery and the

    Mandalong Mine.

  • 7/25/2019 Profil Centennial Coal

    49/92

    NORTHERN COAL SERVICES COAL LOGISTICS PROJECT

    Page 39

    5.2.3 Native Title Act 1994

    The Native Title Act 1994 recognises that Aboriginal people have rights and interests

    to land which derives from their traditional laws and customs. Native title rights can

    include rights to: live on the land, access the land for traditional purposes, protectimportant places and sites, collect food and medicinal resources from native plants,

    hunt and fish, teach traditional law and customs, and to have input into land use

    practices and development planning. Native title can be negotiated in two ways;

    through a Native Title Claim (applications and determinations), or through an

    Indigenous Land Use Agreement (ILUA).

    An ILUA is an agreement between a native title group and other parties who use or

    manage the land and waters. The ILUA process allows for negotiation between

    indigenous groups and other parties over the use and management of land and water

    resources, and the ability to establish a formal agreement. An ILUA is binding once it

    has been registered on the Native Title Tribunals Register of Indigenous Land Use

    Agreements.

    The land within the mining leases and exploration licences currently held by

    Centennial Newstan are covered by an ILUA (NIA2000/001) which was entered into

    on 28 May 1999 by Wonnarua Nation Aboriginal Corporation and Powercoal Pty Ltd

    (since acquired by Centennial). As such, Centennial is bound by the terms of theILUA.

    5.3 New South Wales Legislation

    5.3.1 Environmental Planning and Assessment Act 1979

    The development assessment and approval system in NSW is set out in Parts 4 and

    5 of the EP&A Act. A Planning and Assessment Commission determines applications

    for State significant development. Schedule 1 of SEPP (State and Regional

    Development) 2011 identifies development which is classified as State significant.

    The Project is a State significant development listed under Schedule 1 of SEPP

    (State and Regional Development) 2011 as it is development for the purpose of

    mining related works and has a capital investment value greater than $30 Million. As

    such Part 4 Division 4.1 of the EP&A Act applies.

  • 7/25/2019 Profil Centennial Coal

    50/92

    NORTHERN COAL SERVICES COAL LOGISTICS PROJECT

    Page 40

    5.3.2 Other NSW State Legislation

    The provisions and requirements of additional NSW legislation will be considered and

    addressed within the EIA. A summary of potentially relevant Acts is included in Table

    7.

  • 7/25/2019 Profil Centennial Coal

    51/92

    NORTHERN COAL SERVICES COAL LOGISTICS PROJECT

    Page 41

    Table 7 - Summary of NSW Legislation Relevant to the Project

    Act Relevance to the Project

    Protection of theEnvironment Operations

    Act 1997 (POEO Act)

    The POEO Act is administered by the OEH and requireslicensing for environmental protection, including waste

    generation and disposal, water, air and noise pollution.

    Under the POEO Act, an EPL is required for premises at

    which a scheduled activity is conducted. Schedule 1 of the

    POEO Act lists activities that are scheduled activities for the

    purposes of the Act. The proposed Project is a scheduled

    activity and will require a new EPL to support the Project.

    Mining Act 1992 Centennial Newstan and Centennial Mandalong currently

    hold mining leases over the Project Area. No new mining

    leases are required to support the Project.

    Water Act 1912 The Water Act 1912 is administered by the NSW Office of

    Water (NoW) and contains approval requirements for some

    developments to protect watercourses from any adverse

    effects resulting from works within or in proximity of these

    watercourses.

    National Parks and

    Wildlife Act 1974 (NPW

    Act)

    The National Parks and Wildlife Act 1974 (NPW Act) is

    administered by the National Parks and Wildlife Service

    (NPWS) and provides for the establishment, care, control,

    and management of National Parks, historic sites, nature

    reserves, State conservation areas, Aboriginal areas, and

    State game reserves. An archaeological assessment will

    be conducted as part of the EIS, which will identify the

    presence of any known Aboriginal sites, as well as

    strategies for the management and mitigation of any

    identified impacts on such sites.

    Heritage Act 1977 The purpose of the Heritage Act 1977 (Heritage Act) is to

    protect and conserve non-indigenous cultural heritage,

  • 7/25/2019 Profil Centennial Coal

    52/92

    NORTHERN COAL SERVICES COAL LOGISTICS PROJECT

    Page 42

    including scheduled heritage items, sites, and relics. The

    Heritage Act is administered by the Heritage Branch within

    the OEH.

    The archaeological assessment will be undertaken as partof the EIS and will identify any items of heritage significance

    in the Project Area and recommend appropriate

    management strategies if and where required.

    Threatened Species

    Conservation Act 1995

    The Threatened Species Conservation Act 1995 (TSC Act)

    provides for the conservation of threatened species,

    populations, and ecological communities. The EIS will

    identify any threatened species, populations and ecological

    communities within the Project Area, as well as strategies

    for the management and mitigation of impacts where

    required.

    5.3.3 State Environmental Planning Polic ies

    The following State Environmental Planning Policies (SEPPs) will be considered as

    part of the EIS for the Northern Coal Services - Coal Logistics Project:

    SEPP (State and Regional Development) 2011;

    SEPP (Mining, Petroleum Production and Extractive Industries) 2007;

    SEPP 33 Hazardous and Offensive Development; and

    SEPP 44 Koala Habitat Protection.

    5.4 LOCAL ENVIRONMENT PLANS

    5.4.1 Lake Macquarie Local Environment Plan

    The Newstan Colliery surface site is located on land zoned 4(1) Industrial (Core)

    and 9 Natural Resources. The Awaba Colliery surface site is located on land zoned

    9 Natural Resources. The Mandalong Mine Cooranbong Entry Site is located on

    land zoned 4(1) Industrial (Core), 7(2) Conservation Secondary and 9 Natural

  • 7/25/2019 Profil Centennial Coal

    53/92

    NORTHERN COAL SERVICES COAL LOGISTICS PROJECT

    Page 43

    Resources. The Mandalong Mine private haul road and the LMCC owned

    Hawkmount Quarry located on land owned 9 Natural Resources.

    Development for the purposes of a mine is permissible with development consent

    under the Lake Macquarie LEP 2004 within zones 1(1), 4(1) and 9 however isprohibited within all other zones. Despite the Lake Macquarie LEP 2004 prohibiting

    mining within certain zones, the Mining SEPP prevails over the Lake Macquarie LEP

    2004 to the event of any inconsistency. Any zoning provision in the LEP that would

    otherwise operate to prohibit the project therefore has no effect in this case.

  • 7/25/2019 Profil Centennial Coal

    54/92

    NORTHERN COAL SERVICES COAL LOGISTICS PROJECT

    Page 44

    6.0 KEY ENVIRONMENTAL ISSUES

    6.1 Identification of Environmental Issues

    The key project-related issues warranting detailed assessment in the EIS will be

    identified through:

    The existing environmental context of the Project Areas and surrounding

    locality;

    The legislative framework applicable to the Project (discussed in Section 5.0);

    A preliminary environmental risk assessment, which has already been

    completed (see Section 6.1.1);

    The outcomes of consultation to be undertaken with government agencies

    and other relevant stakeholders; and

    Specialist studies completed as part of the preparation of the EIA.

    6.1.1 Pre-Project Risk Assessment

    A preliminary environmental risk assessment was conducted by Northern Coal

    Services in accordance with the Centennial risk management process, with the aim

    of:

    Identifying those issues relating to the Project that represent the greatest risk

    to the business, environment and community; and

    Assisting in setting the level of assessment required to address each

    identified risk within the EIS.

    The issues that were specifically assessed in the risk assessment include:

    Flora and fauna

    Surface water

    Water management

    Greenhouse gas

    Air quality

    Noise

    European heritage

    Aboriginal heritage

    Social and community issues

    Visual impacts

  • 7/25/2019 Profil Centennial Coal

    55/92

    NORTHERN COAL SERVICES COAL LOGISTICS PROJECT

    Page 45

    A Risk Assessment report, including a risk register, was prepared to document the

    outcomes of the risk assessment, and is attached asAppendix 1.

    The risk assessment did not identify any extreme or high environmental issues

    relating to the Project.

    Two significant issues were identified, relating to the Project including:

    Community or social issues as a result of the continued operation and

    expansion of coal handling operations or inadequate community consultation

    being undertaken; and

    Impacts to creeks (creek geomorphology or ecological receptors) or impacts

    to water quality above ANZECC or EPL criteria as a result of operating the

    surface water management systems at both the Newstan Colliery SurfaceSite and the Mandalong Mine - Cooranbong Entry Site.

    Moderate risks relating to the Project identified during the risk assessment included:

    Impacts to Aboriginal heritage sites as a result of land clearing required for

    the construction of additional surface infrastructure;

    Exceedence of noise criteria, air quality criteria or community complaints

    regarding noise or air quality as a result of the construction of new

    infrastructure at either the Newstan Colliery Surface Site or the Mandalong

    Mine - Cooranbong Entry Site; and

    Exceedence of noise criteria, air quality criteria or issues with vibration as a

    result of coal transportation or the operation of surface infrastructure at the

    Newstan Colliery Surface Site or the Mandalong Mine Cooranbong Entry

    Site.

    A number of low risks were identified including:

    Impacts to EECs, threatened flora, threatened fauna or threatened fauna

    habitat as a result of land clearing required for the construction of additional

    surface infrastructure;

    Impacts to European heritage sites as a result of land clearing required for the

    construction of additional surface infrastructure;

  • 7/25/2019 Profil Centennial Coal

    56/92

    NORTHERN COAL SERVICES COAL LOGISTICS PROJECT

    Page 46

    Impacts to creeks or water quality as a result of land clearing required for the

    construction of additional surface infrastructure;

    Exceedence of noise and air quality criteria or community complaints

    regarding noise or air quality as a result of the construction of additionalinfrastructure at the LMCC owned Hawkmount Quarry;

    Visual impacts or complaints regarding impacts to visual amenity as a result

    of the construction of additional surface infrastructure;

    Greenhouse gas emissions as a result of coal stockpiling and coal handling

    operations contributing to sea level rise and global warming; and

    Traffic impacts as a result of increased train movements on the Main Northern

    Railway.

    6.2 Identified Environmental Issues

    The environmental issues identified during the environmental risk assessment, and

    how they will be assessed in the EIS is discussed in the sections below.

    6.2.1 Flora and Fauna

    A terrestrial ecological impact assessment will be undertaken as part of the EIS. The

    assessment will involve:

    A review of previous ecological investigations undertaken in proximity to the

    Project Application Area in addition to database searches within the locality;

    Vegetation community survey and mapping;

    Targeted seasonal threatened flora surveys;

    Fauna Surveys; and

    Identification of mitigation or management measures as required.

  • 7/25/2019 Profil Centennial Coal

    57/92

    NORTHERN COAL SERVICES COAL LOGISTICS PROJECT

    Page 47

    6.2.2 Surface Water

    A surface water impact assessment will be undertaken as part of the EIS and will

    include:

    Collection and review of background data;

    Assessment of impacts to creeks which could be impacted by the proposed

    Project;

    Development of a site water balance which includes analysis of any water

    quality data to determine the median, 80th and 20th percentile values for

    each parameter. The background water quality will be compared to the

    ANZECC water quality guidelines;

    Analysis of the water quality data to determine any mine water quality and the

    potential contaminants associated with any discharge requirements;

    Review and update existing monitoring program as required (including any

    licensing requirements); and

    Determine mitigation or management measures as required.

    6.2.3 Greenhouse Gas

    A greenhouse gas assessment will be undertaken as part of the EIS. The

    greenhouse gas assessment will:

    Calculate Scope 1, 2 and 3 greenhouse gas estimations for the activities

    associated with the Project in accordance with the requirements of the NGER

    Act, and by applying all relevant emission factors and methods including

    those documented in the relevant NGERs guidelines;

    Assess the significance of greenhouse gas emissions for the Project in

    relation to national greenhouse gas objectives, and report on the Projects

    greenhouse gas implications in terms of Commonwealth and State

    Government policies and protocols; and

    Determine mitigation or management measures as required.

  • 7/25/2019 Profil Centennial Coal

    58/92

    NORTHERN COAL SERVICES COAL LOGISTICS PROJECT

    Page 48

    6.2.4 Air Quality

    An air quality assessment will be undertaken as part of the EIS to assess potential

    impacts on nearby sensitive receptors. This assessment will include:

    Identification of an appropriate meteorological data set to utilise for the

    Project;

    Identification of sensitive receptors;

    Identification of all likely dust generating sources (depositional dust, PM10,

    PM2.5 and Total Suspended Particulates (TSP));

    Establishment of background air quality levels and air quality goals for all

    relevant air quality emissions in accordance with relevant guidelines;

    Estimation of emission rates primarily using emission inventory data.

    Dispersion modelling to predict PM10, PM2.5, TSP and deposition rates at

    the closest sensitive receptors; and

    Recommendations on mitigation and management strategies.

    6.2.5 Noise

    A noise impact assessment will be undertaken as part of the EIS and will include:

    Installation of noise loggers, where required, at locations representing the

    nearest affected residential premises to determine existing background noise

    levels and contributors for a period of at least seven days;

    Noise measurements to determine sound power levels of all acoustically

    significant plant and equipment associated with the Project.

    Analysis of noise data with reference to local weather conditions andcumulative impacts;

    Impact assessment of the proposed Projects contribution to the noise

    environment at the nearest sensitive receptors for day, evening and night time

    periods under calm and prevailing meteorological conditions; and

    Identification of noise management strategies and mitigation measures, as

    required.

  • 7/25/2019 Profil Centennial Coal

    59/92

    NORTHERN COAL SERVICES COAL LOGISTICS PROJECT

    Page 49

    6.2.6 Heritage (Aboriginal and European)

    An Aboriginal and European heritage impact assessment will be undertaken as part

    of the EIS and will include:

    Background research, including:

    o Identify statutory requirements relevant to the proposed Project;

    o Consultation with the Aboriginal community and other interested

    stakeholders in accordance with the Aboriginal Cultural Heritage

    Consultation Requirements for Proponents 2010 (OEH, 2010);

    o Literature review of previous archaeological studies relevant to the

    Project Application Area;

    o Search of the Aboriginal Heritage Information Management System

    (AHIMS) database;

    o Assessment of Aboriginal and European archaeological and cultural

    heritage items identified within the Project areas; and

    o Baseline inventory of all Aboriginal heritage sites inside the Project

    areas.

    Field surveys over the Project area; and

    Identification of mitigation and management strategies to minimise the

    impacts to identified Aboriginal and/or European heritage sites.

    6.2.7 Social/Community

    A social impact assessment will be undertaken as part of the EIS to identify impacts

    of the Project on the community and identify mitigation and management measures

    as required.

    6.2.8 Waste Management

    The EIS will include an assessment of waste management across the site including

    management of reject material.

  • 7/25/2019 Profil Centennial Coal

    60/92

    NORTHERN COAL SERVICES COAL LOGISTICS PROJECT

    Page 50

    6.2.9 Visual

    A visual impact assessment will be undertaken as part of the EIS.

    7.0 STAKEHOLDER AND COMMUNITY CONSULTATION

    Centennial will lead the stakeholder and community consultation for the Project. A

    detailed stakeholder consultation plan will be developed for the Project, and will

    provide a framework to identify and appropriately consult with stakeholders that may

    be influenced by or have an interest in the Project. Key stakeholders include:

    Government (Commonwealth, State and Local);

    Community; and

    Mine staff and employees.

    Centennial has undertaken extensive consultation with the Office of Environment and

    Heritage regarding water management across its operations which will continue

    throughout the preparation of the EIS. A stakeholder consultation log will be

    maintained as a record of the consultation activities undertaken, and the contents of

    this log will be summarised in the EIS.

    Consultation to be undertaken as part of the Project will include:

    Updates to the Newstan and Mandalong Mine Community Consultative

    Committees;

    Updates to the LT Creek Sustainable Neighbourhood Group;

    Letters informing people of the project;

    Project updates provided on the Centennial Coal website;

    Project updates provided in the Lakes Mail;

    Media releases;

    Information sessions where required;

    Face to face meetings with landowners and other regulatory and industry

    stakeholders where required; and

  • 7/25/2019 Profil Centennial Coal

    61/92

    NORTHERN COAL SERVICES COAL LOGISTICS PROJECT

    Page 51

    A briefing session with relevant government agencies.

    Centennial Newstan and Centennial Mandalong maintain a community complaints

    and enquiries line which will also be made available to the community for people to

    obtain up to date and factual information or make complaints regarding the Project.

    8.0 PROJECT JUSTIFICATION

    The Northern Coal Services Coal Logistics Project, if approved, will allow for

    flexible coal handling arrangements and improved surface water management across

    the Newstan Colliery and the Mandalong Mine Cooranbong Entry Sites. The

    Project provides an opportunity for Centennial to produce and deliver a range of coal

    products suitable for both the domestic and export markets.

    Both the surface facilities of the Newstan Colliery and the Mandalong Mine -

    Cooranbong Entry Site are located in close proximity to the existing Power station.

    Newstan Colliery is directly linked to the Eraring Power Station by private haul road

    and the Mandalong Mine Cooranbong Entry Site is linked to the Eraring power

    Station by an overland conveyor. The existing infrastructure in place at the Newstan

    Colliery and the Mandalong mine Cooranbong Entry Site provides an ongoing

    stable supply of coal while reducing the energy demands that would be required forcoal to be supplied from other NSW mining operations. In addition, the ability for

    Centennial Newstan to handle and process coal from other Centennial Coal

    operations at the Newstan Colliery Surface Site provides a unique opportunity for

    Centennial to blend different coal qualities in order to meet supply demands for

    different coal products.

  • 7/25/2019 Profil Centennial Coal

    62/92

    NORTHERN COAL SERVICES COAL LOGISTICS PROJECT

    Page 52

    9.0 CONCLUSION

    Centennials Northern Coal Services is seeking approval under Part 4 Division 4.1 of

    the EP&A Act to undertake and continue a range of coal handling and surface water

    management activities across Centennials Newstan Colliery, the Awaba Colliery and

    the Mandalong Mine Cooranbong Entry site as outlined within this Briefing Paper. A

    detailed assessment of infrastructure requirements, impacts and management

    measures required for the Project will be undertaken during the preparation of the

    EIS.

    This Briefing Paper has been prepared by Northern Coal Services to accompany and

    is intended to provide the DP&I, other relevant regulators and the community with a

    description of the Project and identify likely key social and environmental issues

    associated with the Project to enable the Director-General to issue EARs. The EARs

    will be considered during the preparation of the EIS.

  • 7/25/2019 Profil Centennial Coal

    63/92

    NORTHERN COAL SERVICES COAL LOGISTICS PROJECT

    Appendix 1 Environment and Communi ty Broad Brush Risk Assessment

  • 7/25/2019 Profil Centennial Coal

    64/92

  • 7/25/2019 Profil Centennial Coal

    65/92

    Coal Logistics Project Enviro

    1 of 15

    DyademStatureforRiskManagement:

    Risk Assessment Title: Coal Logistics Project - Environment and Community Broad Brushed Risk Assessment

    Version: 1

    Region: North

    Stature Risk Assessment No.: 1000074014

  • 7/25/2019 Profil Centennial Coal

    66/92

  • 7/25/2019 Profil Centennial Coal

    67/92

    Coal Logistics Project Enviro

    3 of 15

    Objectives

    The objectives of this Risk Assessment is to identify the environment and community risks associated with the proposeProject and to identify knowledge gaps where further information and/or assessment will be required to support an Environm

  • 7/25/2019 Profil Centennial Coal

    68/92

    Coal Logistics Project Enviro

    4 of 15

    Potential Hazards

    The potential hazards for the proposed Northern Coal Services Logistics Project include:

    Vegetation clearing required to support additional infrastructure or upgrades to existing infrastructure;

    Impacts to water quality;

    Noise impacts; Air quality impacts;

    Impacts to Archaeological sites;

    Impacts from GHG emissions;

    Traffic/rail impacts;

    Impacts to the existing water management system;

    Community/social impacts; and

    Visual impacts.

  • 7/25/2019 Profil Centennial Coal

    69/92

    Coal Logistics Project Enviro

    5 of 15

    Scope

    This Risk Assessment is a preliminary Risk Assessment aimed to identify knowledge gaps and areas where further asseenvironmental risks associated with this project will not be understood until further and more detailed investigations havshould be reviewed following the completion of the detailed investigations to ensure all environmental risks associatunderstood and are at an acceptable level for the company.

  • 7/25/2019 Profil Centennial Coal

    70/92

    Coal Logistics Project Enviro

    6 of 15

    Risk Assessment Method

    Yes/No Method

    Yes Workplace Risk Assessment and Control (WRAC)

    No Fault Tree Analysis (FTA)

    No Safety Integrity Level Analysis t