project management an electric utility perspective michael jackovich president and owner project...
TRANSCRIPT
Project ManagementProject ManagementAn Electric Utility PerspectiveAn Electric Utility Perspective
Michael JackovichPresident and Owner
Project Management Plus, Inc.May 18, 2009
Copyright 2009 Project Management Plus, Inc. All rights reserved.
IntroductionIntroduction
Focus on substation, transmission and distribution (T&D)
Project manager (PM) rather than lead engineer is now the responsible individual
Effective PM requires insight– Technical aspects– Work practices
AgendaAgenda
Inception and categories of substation, transmission and distribution projects
Composition and interaction of a typical electric utility project team
Case histories Keys to success
Project CategoriesProject Categories
Regulatory– EPA– NERC
Public Improvement New Business
Project CategoriesProject Categories
Reliability– Tree trimming– Cable replacement
Capacity (“Summer Critical”)
Budgeting and PrioritizationBudgeting and Prioritization
Budget set by upper management Priority system for projects using
proven metrics Projects are “racked and stacked”
Project Team Project Team PM needs to pull the team together Knowledge of work flow process
Environmental
Testing
OperationsProcurement
Construction
Engineering
Real EstatePlanning
Network
At the ForefrontAt the Forefront
Planners (analysts)– Review load data– Recommend changes based on planning
criteria Customer support
– Involved if new business– Liaison between customer and utility
Project controls– Schedulers– Work planners
Design StageDesign Stage Engineering
– Substation, transmission or distribution Real Estate
– Easements, Right of Ways, Surveying Environmental
– Wetland permits, endangered species Procurement
– Acquire major equipment Stores
– Reserve material (cable, conduit, etc.)
Construction StageConstruction Stage
Construction– Substation, transmission or distribution
Operations– Outage and switching plans
Network - IT– SCADA, communications
Testing– Set protective relays, equipment check-out
Unraveling the Underground MazeUnraveling the Underground Maze
Overview– Install 5 miles of 138kV underground
transmission through the streets of a large city.
– Need “signoffs” from 24 city and private entities
– 12 designers and 4 engineers assigned to project team
– Inexperienced with city permit process
Unraveling the Underground MazeUnraveling the Underground Maze Action Plan
– Need to locate a firm familiar with Underground facilities Permitting process
– A subsurface utility engineering (SUE) firm was identified and interviewed
Unraveling the Underground MazeUnraveling the Underground Maze
Results– SUE firm was approved as a subcontractor– Designers reduced from 12 to 6– Received critical advice and support during
the permitting process
The Mystery of the Missing Control The Mystery of the Missing Control BuildingBuilding
Overview– Substation control building – critical path– The building’s subcontractor schedule was
“fluid”– Client facing a substantial penalty if the
project was not completed on time
The Mystery of the Missing Control The Mystery of the Missing Control BuildingBuilding
Action Plan– Visit the subcontractor’s plant– “All hands” meeting at the
plant– Added shift and personnel– Metric to measure progress– Corrective actions
implemented
The Mystery of the Missing Control The Mystery of the Missing Control BuildingBuilding
Results– Control building shipped in 3 weeks– Entire project completed on schedule– Penalty clause not invoked
The Secret of Conceptual The Secret of Conceptual DrawingsDrawings Overview
– 3 projects, 2 were “summer critical”– The 3rd project was a “public
improvement”– All 3 in the same geographic area– Goal was to complete summer critical
projects without any “rework” later– Internal construction resources unavailable– Detailed design and easement acquisition
not complete
The Secret of Conceptual The Secret of Conceptual DrawingsDrawings Action Plan
– Develop a construction bid package using Conceptual drawings Unit prices
– Estimated total of almost 23,000 feet of conduit and 6 underground vaults
– Design and easement acquisition proceeds during bid process
The Secret of Conceptual The Secret of Conceptual DrawingsDrawings Results
– Bid package release and award on time– Design released to construction in phases as
easements were obtained– Summer critical projects completed on
schedule– Contract “extras” resolved via unit prices
Keys to SuccessKeys to Success
Safety Understand the workflow Beware of hand-offs and interfaces Meetings – agenda and action items Communicate
– Field forces– Operations– Governmental entities
Compliment excellent performance
Questions?Questions?
Michael JackovichPresident and Owner
Project Management Plus, Inc.May 18, 2009
Copyright 2009 Project Management Plus, Inc. All rights reserved.