pv experience
TRANSCRIPT
Projects References Page 1
ELECNOR GROUP
SOLAR PV REFERENCES
GROUND AND ROOF PLANTS
Projects References Page 2
INDEX
1. PV PROJECTS WORLD MAP LOCATION ........................................................................ 3 2. PV PROJECTS INFORMATION ........................................................................................ 4 3. PV PROJECTS LOCATIONS MAPS. ................................................................................ 61 PV PROJECTS IN SPAIN. LARGE SCALE ............................................................................. 61 INTERNATIONAL PV PROJECTS - EUROPE ........................................................................ 62 INTERNATIONAL PV PROJECTS – SOUTH AMERICA ....................................................... 63 INTERNATIONAL PV PROJECTS – NORTH AMERICA ....................................................... 64 INTERNATIONAL PV PROJECTS – AFRICA ........................................................................ 65 INTERNATIONAL PV PROJECTS – MIDDLE EAST ............................................................. 66 INTERNATIONAL PV PROJECTS – AUSTRALIA ................................................................. 67
Projects References Page 3
1. PV PROJECTS WORLD MAP LOCATION
USA: 58 MW
Argentina 23 MW
Abu Dhabi: 0,5 MW
AUSTRALIA: 56 MW
Jordan: 2 MW
Spain: 209 MW
Italy: 14 MW
Portugal: 7 MW
France: 22 MW
Mauritania: 3 MW
Total: 392 MW
Projects References Page 4
2. PV PROJECTS INFORMATION
PROJECT NAME GUERNSEY
LOCATION California (USA)
POWER INSTALLED 25.000 kWp 20.000 kW
TRACKING TECHNOLOGY Single Axis
ESTIMATED ENERGY PRODUCED 63.000 MWh/y
ACREAGE 146 Ac
PROMOTER PG&E
EPC ELECNOR
INVESTMENT 65.500.000 USD
FINANCIAL ENTITY PRIVATE FUNDS
CONSTRUCTION PERIOD AUG 2012 TO JULY 2013
Projects References Page 5
PROJECT NAME Broookhaven National Laboratory Solar Farm
LOCATION MANORVILLE, Long island, NY
POWER INSTALLED 38,400 kWp 32.000kW
TRACKING TECHNOLOGY Fixed tilt racking
ESTIMATED ENERGY PRODUCED 67,200 MWh/y
ACREAGE 200 acres
PROMOTER Long Island Solar Farm, LLC (BP Solar & MetLife)
CONSTRUCTION COMPANY HAWKEYE
INVESTMENT 53,000,000 USD
FINANCIAL ENTITY PRIVATE FUNDS
CONSTRUCTION PERIOD Fall 2010 - Fall 2011
Projects References Page 6
PROJECT NAME KAISER PERMANENTE PARKING STRUCTURE
LOCATION California (USA)
POWER INSTALLED 850 kWp 800 kW
TRACKING TECHNOLOGY Carport System
ESTIMATED ENERGY PRODUCED 1,200 kWh/y
ACREAGE 2,000,000 sqf
PROMOTER Kaiser
EPC ELECNOR
INVESTMENT 2,700,000 USD
FINANCIAL ENTITY PRIVATE FUNDS
CONSTRUCTION PERIOD Oct 2013 TO May 2014
Projects References Page 7
PROJECT NAME VENTURA NAVAL BASE
LOCATION California (USA)
POWER INSTALLED 50 kWp 45 kW
TRACKING TECHNOLOGY Carport System
ESTIMATED ENERGY PRODUCED 80,000 kWh/y
ACREAGE 7,000 sqf
PROMOTER Ventura Naval Base
EPC ELECNOR-PDE
INVESTMENT 250,000 USD
FINANCIAL ENTITY PRIVATE FUNDS
CONSTRUCTION PERIOD Feb-15 to Jun-15
Projects References Page 8
PROJECT NAME LOS ANGELES FEDERACL COURTHOUSE PV
LOCATION LOS ANGELES, CA.
POWER INSTALLED 280 KWdc 200 kW
TRACKING TECHNOLOGY Fixed Tilt System
ESTIMATED ENERGY PRODUCED 448 MWh/y
ACREAGE 200,000 sqf
PROMOTER MSF
EPC ELECNOR
INVESTMENT 900,000 USD
FINANCIAL ENTITY USA Goverment
CONSTRUCTION PERIOD 3 Months
Projects References Page 9
PROJECT NAME MSF
LOCATION Moree (Australia)
POWER INSTALLED 70.00 MWp 56.00 MW
TRACKING TECHNOLOGY One Axis Horizontal Tracker
ESTIMATED ENERGY PRODUCED 155.000 MWh/y
ACREAGE 210 Ha
PROMOTER MSF
EPC ELECNOR
INVESTMENT 95,000,000 €
FINANCIAL ENTITY ARENA - CEFC
CONSTRUCTION PERIOD 19 Months
Projects References Page 10
PROJECT NAME La Magascona y Magasquilla
LOCATION Trujillo (Cáceres-Spain)
POWER INSTALLED 34,56 MWp 30 MW
TRACKING TECHNOLOGY One axis horizontal
ESTIMATED ENERGY PRODUCED 60,00 MWh/y
ACREAGE 312 Ac
PROMOTER FOTOWATIO
TURN KEY CONSTRUCTOR ELECNOR
INVESTMENT 215.000.000 €
FINANCIAL ENTITY BANCO SANTANDER
CONSTRUCTION PERIOD 16 months
Projects References Page 11
PROJECT NAME Hoya de los Vicentes
LOCATION Jumilla (Murcia-Spain)
POWER INSTALLED 23,04 MWp 20 MW
TRACKING TECHNOLOGY One axis horizontal
ESTIMATED ENERGY PRODUCED 40,00 MWh/y
ACREAGE 180 Ac
PROMOTER LUZENTIA PROMOCIÓN Y MANTENIMIENTO RENOVABLE, S.A.
TURN KEY CONSTRUCTOR ELECNOR
INVESTMENT 145.000.000 €
FINANCIAL ENTITY WEST LB - DEXIA
CONSTRUCTION PERIOD 10 months
Projects References Page 12
PROJECT NAME EGM – Olmedilla
LOCATION Olmedilla (Cuenca-Spain)
POWER INSTALLED 11,52 MWp 10 MW
TRACKING TECHNOLOGY Fix structure
ESTIMATED ENERGY PRODUCED 16,50 MWh/y
ACREAGE 62 Ac
PROMOTER EGM PROYECTOS Y SISTEMAS ENERGÉTICOS, S.L
TURN KEY CONSTRUCTOR ELECNOR
INVESTMENT 63.000.000 €
FINANCIAL ENTITY ROYAL BANK OF SCOTHLAND
CONSTRUCTION PERIOD 7 months
Projects References Page 13
PROJECT NAME Argasol
LOCATION Almodovar del Campo (Ciudad Real-Spain)
POWER INSTALLED 11,52 MWp 10 MW
TRACKING TECHNOLOGY One axis horizontal
ESTIMATED ENERGY PRODUCED 20,00 MWh/y
ACREAGE 90 Ac
PROMOTER ARGASOL, S.L.
TURN KEY CONSTRUCTOR ELECNOR
INVESTMENT 71.000.000 €
FINANCIAL ENTITY WEST LB
CONSTRUCTION PERIOD 7 months
Projects References Page 14
PROJECT NAME Arroyo de San Serván
LOCATION Arroyo de San Serván (Badajoz-Spain)
POWER INSTALLED 11,52 MWp 10 MW
TRACKING TECHNOLOGY Fix structure
ESTIMATED ENERGY PRODUCED 16,50 MWh/y
ACREAGE 70 Ac
PROMOTER ALUMBRA SOLAR, S.L.
TURN KEY CONSTRUCTOR ELECNOR
INVESTMENT 60.000.000 €
FINANCIAL ENTITY BANCO SANTANDER
CONSTRUCTION PERIOD 7 months
Projects References Page 15
PROJECT NAME Zuera
LOCATION Zuera (Zaragoza-Spain)
POWER INSTALLED 9,94 MWp 9 MW
TRACKING TECHNOLOGY Polar (one axis + tilt)
ESTIMATED ENERGY PRODUCED 14,85 MWh/y
ACREAGE 80 Ac
PROMOTER TRATAMIENTO Y GENERACION DE ENERGÍA, S.L.
TURN KEY CONSTRUCTOR ELECNOR
INVESTMENT 62.000.000 €
FINANCIAL ENTITY CAJA DE AHORROS DE LA INMACULADA DE ARAGÓN
CONSTRUCTION PERIOD 6 months
Projects References Page 16
PROJECT NAME Zuera II
LOCATION Zuera (Zaragoza-Spain)
POWER INSTALLED 11.51 MWp 9.90 MW
TRACKING TECHNOLOGY One axis horizontal
ESTIMATED ENERGY PRODUCED 20,680 MWh/y
ACREAGE 41 Ac
PROMOTER DESARROLLOS AGRONÓMICOS INDUSTRIALES, S.L.
TURN KEY CONSTRUCTOR Elecnor
INVESTMENT 17,065,000 €
FINANCIAL ENTITY BBVA
CONSTRUCTION PERIOD 6 months
Projects References Page 17
PROJECT NAME Campos Solares Lorca I
LOCATION Lorca (Murcia-Spain)
POWER INSTALLED 7,37 MWp 6,40 MW
TRACKING TECHNOLOGY One axis horizontal
ESTIMATED ENERGY PRODUCED 28,050 MWh/y
ACREAGE 100 Ac
PROMOTER PARQUES SOLARES DE TORREALVILLA, A.I.E.
TURN KEY CONSTRUCTOR ELECNOR
INVESTMENT 97.000.000 €
FINANCIAL ENTITY WEST LB
CONSTRUCTION PERIOD 6 months
Projects References Page 18
PROJECT NAME Guadarranque
LOCATION Guadarranque (Cádiz-Spain)
POWER INSTALLED 13,53 MWp 12,30 MW
TRACKING TECHNOLOGY One axis horizontal
ESTIMATED ENERGY PRODUCED 24,30 MWh/y
ACREAGE 130 Ac
PROMOTER ENDESA GENERACIÓN, S.A.
TURN KEY CONSTRUCTOR ELECNOR (BOS supplier)
INVESTMENT 27.000.000 €
FINANCIAL ENTITY --
CONSTRUCTION PERIOD 9 months
Projects References Page 19
PROJECT NAME Campos Solares Lorca II
LOCATION Lorca (Murcia-Spain)
POWER INSTALLED 7,83 MWp 6,80 MW
TRACKING TECHNOLOGY One axis horizontal
ESTIMATED ENERGY PRODUCED 12,87 MWh/y
ACREAGE 48 Ac
PROMOTER PARQUES SOLARES DE MIRAS, A.I.E.
TURN KEY CONSTRUCTOR ELECNOR
INVESTMENT 46.000.000 €
FINANCIAL ENTITY WEST LB
CONSTRUCTION PERIOD 6 months
Projects References Page 20
PROJECT NAME Plasencia de Jalón
LOCATION Plasencia de Jalón (Zaragoza-Spain)
POWER INSTALLED 5 MWp 4 MW
TRACKING TECHNOLOGY Fixed Structure
ESTIMATED ENERGY PRODUCED 6,96 MWh/y
ACREAGE 35 Ac
PROMOTER TRATAMIENTO Y GENERACION DE ENERGÍA, S.L.
TURN KEY CONSTRUCTOR ELECNOR
INVESTMENT 14.000.000 €
FINANCIAL ENTITY CAJA DE AHORROS DE LA INMACULADA DE ARAGÓN
CONSTRUCTION PERIOD 5 months
Projects References Page 21
PROJECT NAME Siberia Solar
LOCATION Valdecaballeros (Badajoz-Spain)
POWER INSTALLED 11,82 MWp 10 MW
TRACKING TECHNOLOGY Fixed Structure
ESTIMATED ENERGY PRODUCED 16,6 MWh/y
ACREAGE 100 acres
PROMOTER ELECNOR SA
TURN KEY CONSTRUCTOR ELECNOR
INVESTMENT 33.670.000 €
FINANCIAL ENTITY ELECNOR
CONSTRUCTION PERIOD 8 months
Projects References Page 22
PROJECT NAME Malpartida
LOCATION Malpartida (Cáceres-Spain)
POWER INSTALLED 11,82 MWp 10 MW
TRACKING TECHNOLOGY Fixed Structure
ESTIMATED ENERGY PRODUCED 18,380 MWh/y
ACREAGE 110 acres
PROMOTER ELECNOR SA
TURN KEY CONSTRUCTOR ELECNOR
INVESTMENT 32.000.000 €
FINANCIAL ENTITY BANCO SANTANDER
CONSTRUCTION PERIOD 8,5 months
PROJECT NAME ALGINET
Projects References Page 23
LOCATION Alginet (Valencia – Spain)
POWER INSTALLED 1,96 kWp 1,8 kW
TRACKING TECHNOLOGY On roof
ESTIMATED ENERGY PRODUCED 2, 57 MWh/y
ACREAGE 7 Ac
PROMOTER CELEO
TURN KEY CONSTRUCTOR ELECNOR
INVESTMENT 5.195.000 €
FINANCIAL ENTITY -
CONSTRUCTION PERIOD 4 months
Projects References Page 24
PROJECT NAME ARQUITECTOS IV
LOCATION Huercal Overa (Almería)
POWER INSTALLED 0,96 MWp 0,80 MW
TRACKING TECHNOLOGY One axis tracker
ESTIMATED ENERGY PRODUCED 1,37 MWh/y
ACREAGE 10 Ac
PROMOTER CLAVE ARQUITECTURA
TURN KEY CONSTRUCTOR ATERSA
INVESTMENT 5.787.000 €
FINANCIAL ENTITY --
CONSTRUCTION PERIOD From January 2008 to June 2008
Projects References Page 25
PROJECT NAME CLAVE ARQUITECTURA I
LOCATION Huercal Overa (Almería)
POWER INSTALLED 0,82 MWp 0,7 MW
TRACKING TECHNOLOGY One Axis (Powerligth)
ESTIMATED ENERGY PRODUCED 1,249 MWh/y
ACREAGE 8.3 Ac
PROMOTER CLAVE ARQUITECTURA
TURN KEY CONSTRUCTOR ATERSA
INVESTMENT 4,874,000 €
FINANCIAL ENTITY --
CONSTRUCTION PERIOD From September 2005 to February 2007
Projects References Page 26
PROJECT NAME CLAVE ARQUITECTURA II
LOCATION Huercal Overa (Almería)
POWER INSTALLED 0,63 MWp 0,50 MW
TRACKING TECHNOLOGY One Axis (Powerligth)
ESTIMATED ENERGY PRODUCED 0,962 MWh/y
ACREAGE 5,6 Ac
PROMOTER CLAVE ARQUITECTURA
TURN KEY CONSTRUCTOR ATERSA
INVESTMENT 3.740.000 €
FINANCIAL ENTITY --
CONSTRUCTION PERIOD From April 2006 to May 2007
Projects References Page 27
PROJECT NAME Carrascosa
LOCATION El Pozuelo (Cuenca)
POWER INSTALLED 1,18 MWp 1 MW
TRACKING TECHNOLOGY Fixed
ESTIMATED ENERGY PRODUCED 1,39 MWh/y
ACREAGE Ac
PROMOTER NAVARRO GENERACIÓN
TURN KEY CONSTRUCTOR ATERSA
INVESTMENT 6.400.000 €
FINANCIAL ENTITY Banesto
CONSTRUCTION PERIOD From August 2007 to March 2008
Projects References Page 28
PROJECT NAME Carrascosa
LOCATION Carrascosa de la Sierra (Cuenca)
POWER INSTALLED 1,18 MWp 1 MW
TRACKING TECHNOLOGY Fixed
ESTIMATED ENERGY PRODUCED 1,391 MWh/y
ACREAGE 7,4 Ac
PROMOTER NAVARRO GENERACIÓN
TURN KEY CONSTRUCTOR ATERSA
INVESTMENT 6.400.000 €
FINANCIAL ENTITY Banesto
CONSTRUCTION PERIOD From August 2007 to March 2008
Projects References Page 29
PROJECT NAME ABADÍAS
LOCATION Montearagón (Toledo)
POWER INSTALLED 1,40 MWp 1,20 MW
TRACKING TECHNOLOGY Fixed
ESTIMATED ENERGY PRODUCED 1,02 MWh/y
ACREAGE 8.8 Ac
PROMOTER ABADÍAS 3
TURN KEY CONSTRUCTOR Atersa
INVESTMENT 7.600.000 €
FINANCIAL ENTITY BBVA
CONSTRUCTION PERIOD December 2007 to March 2008
Projects References Page 30
PROJECT NAME AFA
LOCATION Cieza (Murcia)
POWER INSTALLED 3,11 MWp 2,70 MW
TRACKING TECHNOLOGY Fixed
ESTIMATED ENERGY PRODUCED 4,05 MWh/y
ACREAGE 22,9 Ac
PROMOTER FLEXO ESTUDIO
TURN KEY CONSTRUCTOR ATERSA
INVESTMENT 17.696.000 €
FINANCIAL ENTITY Caja Círculo
CONSTRUCTION PERIOD From November 2005 to September 2007
Projects References Page 31
PROJECT NAME DUMAR
LOCATION Torralba de Oropesa (Toledo)
POWER INSTALLED 0,70 MWp 0,63 MW
TRACKING TECHNOLOGY Fixed
ESTIMATED ENERGY PRODUCED 0,847 MWh/y
ACREAGE 4,4 Ac
PROMOTER Aralba Solar II
TURN KEY CONSTRUCTOR ATERSA
INVESTMENT 3.828.000 €
FINANCIAL ENTITY Bancaja
CONSTRUCTION PERIOD July 2007 to February 2008
Projects References Page 32
PROJECT NAME ESPARTOSA I y II
LOCATION Cieza (Murcia)
POWER INSTALLED 5,40 MWp 4,68 MW
TRACKING TECHNOLOGY Fixed
ESTIMATED ENERGY PRODUCED 7,45 MWh/y
ACREAGE 29 Ac
PROMOTER IGS
TURN KEY CONSTRUCTOR ATERSA
INVESTMENT 29.700.000 €
FINANCIAL ENTITY Banco Santander
CONSTRUCTION PERIOD From December 2007 to June 2008
Projects References Page 33
PROJECT NAME GEYPROMAN
LOCATION Alcázar de San Juan (Ciudad Real)
POWER INSTALLED 0,24 MWp 0,20 MW
TRACKING TECHNOLOGY Fixed
ESTIMATED ENERGY PRODUCED 0,305 MWh/y
ACREAGE 1,5 Ac
PROMOTER GEIPROMÁN & SOC. de TRANSFORMACIONES AGRARIAS S. JOSÉ
TURN KEY CONSTRUCTOR ATERSA
INVESTMENT 1.250.000 €
FINANCIAL ENTITY Caja Castilla La Mancha
CONSTRUCTION PERIOD From January 2008 to June 2008
Projects References Page 34
PROJECT NAME IGS
LOCATION Cieza (Murcia)
POWER INSTALLED 7,27 MWp 5,85 MW
TRACKING TECHNOLOGY Fixed
ESTIMATED ENERGY PRODUCED 10,07 MWh/y
ACREAGE 37 Ac
PROMOTER IGS
TURN KEY CONSTRUCTOR ATERSA
INVESTMENT 40.000.000 €
FINANCIAL ENTITY Caja Murcia
CONSTRUCTION PERIOD From March 2007 to June 2008
Projects References Page 35
PROJECT NAME LA LOSA I Y II
LOCATION Casas de Benítez (Cuenca)
POWER INSTALLED 0,24 MWp 0,20 MW
TRACKING TECHNOLOGY One axis (La Losa I)& Fixed La Losa II
ESTIMATED ENERGY PRODUCED 301 MWh/y
ACREAGE 1,93 Ac
PROMOTER NAVARRO GENERACIÓN
TURN KEY CONSTRUCTOR ATERSA
INVESTMENT 1.200.000 €
FINANCIAL ENTITY Private Found
CONSTRUCTION PERIOD From February 2005 to December 2007
Projects References Page 36
PROJECT NAME Mercabio
LOCATION Almanzora (Almería)
POWER INSTALLED 0,13 MWp 0,10 MW
TRACKING TECHNOLOGY Fixed
ESTIMATED ENERGY PRODUCED 0,191 MWh/y
ACREAGE 0,74 Ac
PROMOTER MERCABIO SOCIEDAD COOPERATIVA
TURN KEY CONSTRUCTOR ATERSA
INVESTMENT 740.000 €
FINANCIAL ENTITY Cajamar
CONSTRUCTION PERIOD From November 2006 to January 2007
Projects References Page 37
PROJECT NAME Montiel
LOCATION Montiel (Ciudad Real)
POWER INSTALLED 0,83 MWp 0,70 MW
TRACKING TECHNOLOGY Fixed
ESTIMATED ENERGY PRODUCED 1,02 MWh/y
ACREAGE 5,8 Ac
PROMOTER INVERSIONES EUROPEAS
TURN KEY CONSTRUCTOR ATERSA
INVESTMENT 4.500.000 €
FINANCIAL ENTITY Banca March
CONSTRUCTION PERIOD From January 2008 to June 2008
Projects References Page 38
PROJECT NAME Rusticas
LOCATION Añover de Tajo (Toledo)
POWER INSTALLED 2,50 MWp 2 MW
TRACKING TECHNOLOGY One Axis (Powerligth)
ESTIMATED ENERGY PRODUCED 3,56 MWh/y
ACREAGE 24 Ac
PROMOTER RUSTICAS
TURN KEY CONSTRUCTOR ATERSA
INVESTMENT 14.956.000 €
FINANCIAL ENTITY Barclays
CONSTRUCTION PERIOD February 2006 to February 2008
Projects References Page 39
PROJECT NAME SERRANA II
LOCATION Cieza (Murcia)
POWER INSTALLED 2,39 MWp 2,07 MW
TRACKING TECHNOLOGY Fixed
ESTIMATED ENERGY PRODUCED 3,30 MWh/y
ACREAGE 12 Ac
PROMOTER IGS
TURN KEY CONSTRUCTOR ATERSA
INVESTMENT 13.100.000 €
FINANCIAL ENTITY Caja Murcia
CONSTRUCTION PERIOD From December 2007 to June 2008
Projects References Page 40
PROJECT NAME SOLIVAR MORATALLA
LOCATION Moratalla (Murcia)
POWER INSTALLED 2,22 MWp 1,71 MW
TRACKING TECHNOLOGY Fixed
ESTIMATED ENERGY PRODUCED 3,03 MWh/y
ACREAGE 11 Ac
PROMOTER SOLIVAR MORATALLA
TURN KEY CONSTRUCTOR ATERSA
INVESTMENT 12.200.000 €
FINANCIAL ENTITY Caja Círculo
CONSTRUCTION PERIOD From February 2007 to June 2008
Projects References Page 41
PROJECT NAME Fotonova & Solgomar
LOCATION Onda (Castellón)
POWER INSTALLED 0,84 MWp 0,70 MW
TRACKING TECHNOLOGY Fixed
ESTIMATED ENERGY PRODUCED 1,11 MWh/y
ACREAGE 5,18 Ac
PROMOTER FOTONOVA & SOLGOMAR
TURN KEY CONSTRUCTOR ATERSA
INVESTMENT 5.000.000 €
FINANCIAL ENTITY Caixanova
CONSTRUCTION PERIOD From January 2006 To October 2007
Projects References Page 42
PROJECT NAME CENTRAL FOTOVOLTAICA DO MARL
LOCATION Lisboa (Portugal)
POWER INSTALLED 6,69 MWp 5,9 MW
TRACKING TECHNOLOGY Fixed Structure
ESTIMATED ENERGY PRODUCED 10,62 MWh/y
ACREAGE 20 Ac
PROMOTER MARL ENERGIA
TURN KEY CONSTRUCTOR ELECNOR
INVESTMENT 31.000.000 €
FINANCIAL ENTITY Foment Invest/Caixa Capital
CONSTRUCTION PERIOD 7 months
Projects References Page 43
PROJECT NAME CARTOCETO
LOCATION Cartoceto (PU - Marche - Italia)
POWER INSTALLED 910,8 kWp 900 kW
TRACKING TECHNOLOGY Fixed Structure
ESTIMATED ENERGY PRODUCED 1,02 MWh/y
ACREAGE 6 Ac
PROMOTER NOVAPOWER
TURN KEY CONSTRUCTOR ELECNOR
INVESTMENT 3.050.000 €
FINANCIAL ENTITY Credit Agricole Leaseing Italia
CONSTRUCTION PERIOD 3 months
Projects References Page 44
PROJECT NAME FOSSOMBRONE A
LOCATION Fossombrone (PU – Marche - Italia)
POWER INSTALLED 598,00 kWp 500 kW
TRACKING TECHNOLOGY Fixed Structure
ESTIMATED ENERGY PRODUCED 0,66 MWh/y
ACREAGE 3,7 Ac
PROMOTER NOVAPOWER
TURN KEY CONSTRUCTOR ELECNOR
INVESTMENT 1.990.000 €
FINANCIAL ENTITY LEASINT
CONSTRUCTION PERIOD 2 months
Projects References Page 45
PROJECT NAME FOSSOMBRONE B
LOCATION Fossombrone (PU – Marche - Italia)
POWER INSTALLED 910,8 kWp 900 kW
TRACKING TECHNOLOGY Fixed Structure
ESTIMATED ENERGY PRODUCED 1,01 MWh/y
ACREAGE 6 Ac
PROMOTER NOVAPOWER
TURN KEY CONSTRUCTOR ELECNOR
INVESTMENT 3.100.000 €
FINANCIAL ENTITY LEASINT
CONSTRUCTION PERIOD 3 months
Projects References Page 46
PROJECT NAME AGUGLIANO
LOCATION Agugliano (AN – Marche - Italia)
POWER INSTALLED 1.495 kWp 1.400 kW
TRACKING TECHNOLOGY Fixed Structure
ESTIMATED ENERGY PRODUCED 1,76 MWh/y
ACREAGE 11 Ac
PROMOTER NOVAPOWER
TURN KEY CONSTRUCTOR ELECNOR
INVESTMENT 4.990.000 €
FINANCIAL ENTITY LEASINT
CONSTRUCTION PERIOD 4 months
Projects References Page 47
PROJECT NAME FANO
LOCATION Fano (PU - Marche - Italia)
POWER INSTALLED 999,52 kWp 900 kW
TRACKING TECHNOLOGY Fixed Structure
ESTIMATED ENERGY PRODUCED 1,14 MWh/y
ACREAGE 8,5 Ac
PROMOTER NOVAPOWER
TURN KEY CONSTRUCTOR ELECNOR
INVESTMENT 3.350.000 €
FINANCIAL ENTITY CARIFANO
CONSTRUCTION PERIOD 3 months
Projects References Page 48
PROJECT NAME BARCHI 2
LOCATION Barchi (PU – Marche - Italia)
POWER INSTALLED 908,80 kWp 900 kW
TRACKING TECHNOLOGY Fixed Structure
ESTIMATED ENERGY PRODUCED 1,11 MWh/y
ACREAGE 7,5 Ac
PROMOTER NOVAPOWER
TURN KEY CONSTRUCTOR ELECNOR
INVESTMENT 3.230.000 €
FINANCIAL ENTITY CARIFANO
CONSTRUCTION PERIOD 4 months
Projects References Page 49
PROJECT NAME SAN GIORGIO DI PESARO 1
LOCATION San Giorgio di Pesaro (AN - Marche - Italia)
POWER INSTALLED 999,52 kWp 900 kW
TRACKING TECHNOLOGY Fixed Structure
ESTIMATED ENERGY PRODUCED 1,09 MWh/y
ACREAGE 11 Ac
PROMOTER NOVAPOWER
TURN KEY CONSTRUCTOR ELECNOR
INVESTMENT 3.550.000 €
FINANCIAL ENTITY CARIFANO
CONSTRUCTION PERIOD 4 months
Projects References Page 50
PROJECT NAME CASTELLEONE DI SUASA
LOCATION Castelleone di Suasa (AN – Marche - Italia)
POWER INSTALLED 680,8 kWp 600 kW
TRACKING TECHNOLOGY Fixed Structure
ESTIMATED ENERGY PRODUCED 0,78 MWh/y
ACREAGE 6,5 Ac
PROMOTER NOVAPOWER
TURN KEY CONSTRUCTOR ELECNOR
INVESTMENT 2.420.000 €
FINANCIAL ENTITY LEASINT
CONSTRUCTION PERIOD 3 months
Projects References Page 51
PROJECT NAME SAN LORENZO IN CAMPO 3
LOCATION San Lorenzo in Campo (PU – Marche - Italia)
POWER INSTALLED 980,8 kWp 900 kW
TRACKING TECHNOLOGY Fixed Structure
ESTIMATED ENERGY PRODUCED 1,04 MWh/y
ACREAGE 9,1 Ac
PROMOTER NOVAPOWER
TURN KEY CONSTRUCTOR ELECNOR
INVESTMENT 3.230.000 €
FINANCIAL ENTITY LEASINT
CONSTRUCTION PERIOD 3 months
Projects References Page 52
PROJECT NAME SAN SEVERINO MARCHE
LOCATION San Severino Marche (MC – Marche - Italia)
POWER INSTALLED 2.316 kWp 2.000 kW
TRACKING TECHNOLOGY Fixed Structure
ESTIMATED ENERGY PRODUCED 2,69 MWh/y
ACREAGE 11 Ac
PROMOTER NOVAPOWER
TURN KEY CONSTRUCTOR ELECNOR
INVESTMENT 8.200.000 €
FINANCIAL ENTITY LEASINT
CONSTRUCTION PERIOD 4 months
Projects References Page 53
PROJECT NAME PERGOLA
LOCATION Pergola (PU - Marche - Italia)
POWER INSTALLED 996,84 kWp 900 kW
TRACKING TECHNOLOGY Fixed Structure
ESTIMATED ENERGY PRODUCED 1,2 MWh/y
ACREAGE 7,6 Ac
PROMOTER NOVAPOWER
TURN KEY CONSTRUCTOR ELECNOR
INVESTMENT 3.100.000 €
FINANCIAL ENTITY BNP PARIBAS LEASE GROUP
CONSTRUCTION PERIOD 3 months
Projects References Page 54
PROJECT NAME FOSSOMBRONE TETTO
LOCATION Fossombrone (PU – Marche - Italia)
POWER INSTALLED 910,70 kWp 900 kW
TRACKING TECHNOLOGY On Roof
ESTIMATED ENERGY PRODUCED 1,12 MWh/y
ACREAGE 3,7 Ac
PROMOTER NOVAPOWER
TURN KEY CONSTRUCTOR ELECNOR
INVESTMENT 3.353.000 €
FINANCIAL ENTITY BNP PARIBAS LEASE GROUP
CONSTRUCTION PERIOD 4 months
Projects References Page 55
PROJECT NAME CORRIDONIA
LOCATION Corridonia (MC – Marche - Italia)
POWER INSTALLED 4.641,84 kWp 4.392 kW
TRACKING TECHNOLOGY Fixed Structure
ESTIMATED ENERGY PRODUCED 6,87 MWh/y
ACREAGE 26,9 Ac
PROMOTER NOVAPOWER
TURN KEY CONSTRUCTOR ELECNOR
INVESTMENT 10.443.000 €
FINANCIAL ENTITY -
CONSTRUCTION PERIOD From May to August 2011 (COD: 08/2011)
Projects References Page 56
PROJECT NAME CAÑADA HONDA
LOCATION SAN JUAN – Argentina
POWER INSTALLED 22.393 kWp 20.000 kW
TRACKING TECHNOLOGY Fixed Structure and one-horizontal single axis tracker
ESTIMATED ENERGY PRODUCED 42.500 MWh/y
ACREAGE 75 Ac
PROMOTER EMGASUD
TURN KEY CONSTRUCTOR ELECNOR
INVESTMENT 80.000.000 USD
FINANCIAL ENTITY BICE
CONSTRUCTION PERIOD 18 months (UNDER CONSTRUCTION)
Projects References Page 57
PROJECT NAME SANDOUVILLE
LOCATION ROUEN – France
POWER INSTALLED 10.442 kWp 9.206 kW
TRACKING TECHNOLOGY Fixed Structure
ESTIMATED ENERGY PRODUCED 10.715 MWh/y
ACREAGE 28 Ac
PROMOTER GESTAMP RENEWABLES
BOS CONSTRUCTOR ELECNOR
INVESTMENT 12.000.000 USD
FINANCIAL ENTITY DEUTCHE BANK
CONSTRUCTION PERIOD MAY 2012 TO NOV 2012
Projects References Page 58
PROJECT NAME FLINS
LOCATION PARIS – France
POWER INSTALLED 11.393 kWp 9.200 kW
TRACKING TECHNOLOGY Fixed Structure
ESTIMATED ENERGY PRODUCED 10.262 MWh/y
ACREAGE 30 Ac
PROMOTER GESTAMP RENEWABLES
BOS CONSTRUCTOR ELECNOR
INVESTMENT 12.500.000 USD
FINANCIAL ENTITY DEUTCHE BANK
CONSTRUCTION PERIOD MAY 2012 TO NOV 2012
Projects References Page 59
PROJECT NAME ZOUERATE
LOCATION Mauritania
POWER INSTALLED 3.000 kWp 2.500 kW
TRACKING TECHNOLOGY Fixed structure
ESTIMATED ENERGY PRODUCED 4.800 MWh/y
ACREAGE 7.2 Ha
PROMOTER SNIM
EPC ELECNOR
INVESTMENT 5.500.000 EUR
FINANCIAL ENTITY Multilateral Funding
CONSTRUCTION PERIOD MAR 2013 TO AUG 2013
Projects References Page 60
PROJECT NAME AZRAQ
LOCATION Azraq (Jordan)
POWER INSTALLED 2.177 kWp 2.000 kW
TRACKING TECHNOLOGY 1MW Fixed structure; 1MW Axis Horizontal Tracker
ESTIMATED ENERGY PRODUCED 4.096 MWh/y
ACREAGE 5.39 Ha
PROMOTER Ministry of Energy and Mineral ResourcesS (MEMR)
EPC ATERSA (ELECNOR GROUP)
INVESTMENT 3.500.000 JD (Jordan Dinar)
FINANCIAL ENTITY Debt Swap Program between Jordan and Spain
CONSTRUCTION PERIOD 6 Months
Projects References Page 61
3. PV PROJECTS LOCATIONS MAPS.
PV PROJECTS IN SPAIN. LARGE SCALE
Projects References Page 62
INTERNATIONAL PV PROJECTS - EUROPE
Projects References Page 63
INTERNATIONAL PV PROJECTS – SOUTH AMERICA
Pendiente de conexión
En operación
CAPACIDAD TOTAL: 23 MW
En construcción
PROYECTOS INTERNACIONALES EN SUDAMERICA
Cañada Honda 23 MW
Projects References Page 64
INTERNATIONAL PV PROJECTS – NORTH AMERICA
TOTAL CAPACITY: 25 MW
NORTH AMERICA PV PROJECTS
Under Construction
Operation
Projects References Page 65
Zouerate 3 MW
INTERNATIONAL PV PROJECTS – AFRICA
Operation Under construction
Projects References Page 66
INTERNATIONAL PV PROJECTS – MIDDLE EAST
Azraq 2 MW
Operation Under construction
Projects References Page 67
INTERNATIONAL PV PROJECTS – AUSTRALIA
Moree 56 MW
Operation Under construction