REKAPITULASI RENCANA ANGGARAN BI PEKERJAAN UTILITAS & FINISHING RUMAH TOKO DAN R NO URAIAN PEKERJAAN A. PEKERJAAN UTILITAS & FINISHING RUMAH TOKO B. PEKERJAAN UTILITAS & FINISHING RUMAH SEWA TOTAL JUMLAH HARGA PEKERJAAN DIBULATKAN Terbilang : "Tiga miliar sembilan ratus tiga puluh empat juta empat ratus dua pu

Upload: hakiki-saputra

Post on 28-Oct-2015

69 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: RAB Rumah Kos Dan Ruko for WY

REKAPITULASI RENCANA ANGGARAN BIAYA

PEKERJAAN UTILITAS & FINISHING RUMAH TOKO DAN RUMAH SEWA

NO URAIAN PEKERJAAN JUMLAH HARGA

( Rp )

A. PEKERJAAN UTILITAS & FINISHING RUMAH TOKO 1,254,838,000.00

B. PEKERJAAN UTILITAS & FINISHING RUMAH SEWA 2,679,582,000.00

TOTAL JUMLAH HARGA PEKERJAAN 3,934,420,000.00

TOTAL JUMLAH HARGA PEKERJAANDIBULATKAN 3,934,420,000.00

Terbilang : "Tiga miliar sembilan ratus tiga puluh empat juta empat ratus dua puluh dua ribu rupiah"

Page 2: RAB Rumah Kos Dan Ruko for WY

REKAPITULASI RENCANA ANGGARAN BIAYA

PEKERJAAN UTILITAS & FINISHING RUMAH TOKO

NO URAIAN PEKERJAAN JUMLAH HARGA

( Rp )

I. PEKERJAAN LANTAI DAN DINDING 312,241,700.00

II. PEKERJAAN KUSEN, DAUN PINTU DAN JENDELA 134,386,300.00

III. PEKERJAAN ATAP 109,034,100.00

IV. PEKERJAAN PENGECATAN 60,995,100.00

V. PEKERJAAN ELEKTRIKAL 21,311,900.00

VI. PEKERJAAN PLUMBING DAN SANITASI 48,618,300.00

VII. PEKERJAAN FURNITURE DAN PERLENGKAPAN 568,250,000.00

TOTAL JUMLAH HARGA PEKERJAAN 1,254,837,400.00

TOTAL JUMLAH HARGA PEKERJAANDIBULATKAN 1,254,838,000.00

Page 3: RAB Rumah Kos Dan Ruko for WY

REKAPITULASI RENCANA ANGGARAN BIAYA

PEKERJAAN UTILITAS & FINISHING RUMAH SEWA

NO URAIAN PEKERJAAN JUMLAH HARGA

( Rp )

I. PEKERJAAN LANTAI DAN DINDING 502,355,700.00

II. PEKERJAAN KUSEN, DAUN PINTU DAN JENDELA 419,486,400.00

III. PEKERJAAN ATAP 171,264,100.00

IV. PEKERJAAN PENGECATAN 95,276,800.00

V. PEKERJAAN ELEKTRIKAL 77,816,300.00

VI. PEKERJAAN PLUMBING DAN SANITASI 265,882,400.00

VII. PEKERJAAN FURNITURE DAN PERLENGKAPAN 1,147,500,000.00

TOTAL JUMLAH HARGA PEKERJAAN 2,679,581,700.00

TOTAL JUMLAH HARGA PEKERJAANDIBULATKAN 2,679,582,000.00

Page 4: RAB Rumah Kos Dan Ruko for WY

RENCANA ANGGARAN BIAYAPEKERJAAN UTILITAS & FINISHING RUMAH TOKO

NO. PEKERJAAN VOL. SAT.

HARGA SUB TOTAL JUMLAH

SATUAN HARGA HARGA

(Rp.) (Rp.) (Rp.)

I. PEKERJAAN LANTAI DAN DINDING 312,241,700

1.1. Pasang Granito Lantai Ukuran 40x40 cm 148.50 M2 281,430 41,792,400

1.2. Pasang Keramik Lantai Ukuran 40x40 cm 385.00 M2 220,430 84,865,600

1.3. Pasang Keramik Lantai Ukuran 20x20 cm 17.50 M2 110,560 1,934,800

1.4. Pasang Keramik Dinding Ukuran 20x25 cm 85.00 M2 166,520 14,154,200

1.5. Pasang Plint Keramik Ukuran 20x40 cm 43.00 M1 70,350 3,025,100

1.6. Pasang Plint Keramik Ukuran 15x30 cm 67.00 M1 39,270 2,631,100

1.7. Pasang Bon bon Keramik 14.00 M1 20,120 281,700

1.8. Pasang Batu Alam Lantai Ukuran 30x30 cm 120.00 M2 232,710 27,925,200

1.9. Pasang Batu Alam Dindingi Ukuran 30x30 cm 520.00 M2 260,830 135,631,600

II. PEKERJAAN KUSEN, DAUN PINTU DAN JENDELA 134,386,300

2.1. Kusen, Daun Pintu (P-1) 4.00 Unit 13,763,750 55,055,000

2.2. Kusen, Daun Pintu (P-2) 6.00 Unit 1,511,250 9,067,500

2.3. Kusen, Daun Jendela (J-1) 6.00 Unit 6,290,625 37,743,800

2.4. Kusen, Daun Jendela (V-1) 6.00 Unit 5,420,000 32,520,000

III. PEKERJAAN ATAP 109,034,100

3.1. Pasang Plafond Gypsum Board 9mm + Rangka 429.00 M2 233,300 100,085,700

3.2. List Profil Plafond Gypsum 120.00 M1 74,570 8,948,400

IV. PEKERJAAN PENGECATAN 60,995,100

4.1. Pengecatan Dinding 3 lapis + Plamur 870.00 M2 23,370 20,331,900

4.2. Pengecatan Plafon 3 lapis 945.00 M2 28,800 27,216,000

4.3. Pengecatan Kayu Melamin 120.00 M2 112,060 13,447,200

V. PEKERJAAN ELEKTRIKAL 21,311,900

5.1. Pemasukan Daya Listrik 2.00 Unit 2,100,000 4,200,000

5.2. Box Panel Distribusi 2.00 Unit 315,000 630,000

5.3. Instalasi Titik Lampu 30.00 Ttk 189,500 5,685,000

5.4. Instalasi Stop Kontak 30.00 Ttk 35,440 1,063,200

5.5. Stop Kontak 36.00 Ttk 23,630 850,700

5.6. Saklar Tunggal 110.00 Unit 31,500 3,465,000

5.7. Lampu pijar 25 - 40W 6.00 Unit 63,000 378,000

5.8. Lampu TL Bamboo 40 Watt 24.00 Bh 210,000 5,040,000

Page 5: RAB Rumah Kos Dan Ruko for WY

RENCANA ANGGARAN BIAYAPEKERJAAN UTILITAS & FINISHING RUMAH TOKO

NO. PEKERJAAN VOL. SAT.

HARGA SUB TOTAL JUMLAH

SATUAN HARGA HARGA

(Rp.) (Rp.) (Rp.)

VI. PEKERJAAN PLUMBING DAN SANITASI 48,618,300

6.1. Pipa Air Bersih (PVC 1/2") 6.00 Titik 29,720 178,300

6.2. Kran Air 6.00 Unit 302,500 1,815,000

6.3. Closet Duduk 6.00 Unit 6,187,500 37,125,000

6.4. Pompa Air 2.00 Unit 2,000,000 4,000,000

6.5. Tanki Air 500 L 2.00 Unit 2,750,000 5,500,000

VI. PEKERJAAN FURNITURE DAN PERLENGKAPAN 568,250,000

7.1. Meja Meting 2.00 Unit 20,000,000 40,000,000

7.2. Meja Kerja 20.00 Unit 2,000,000 40,000,000

7.3. Kursi Kantor 100.00 Unit 700,000 70,000,000

7.4. Lemari Buku Kantor 2.00 Unit 32,000,000 64,000,000

7.5. Partisi Dinding 850.00 M2 355,000 301,750,000

7.6. AC 3/4 PK 15.00 Unit 3,500,000 52,500,000

J U M L A H 1,254,837,400

Page 6: RAB Rumah Kos Dan Ruko for WY

RENCANA ANGGARAN BIAYAPEKERJAAN UTILITAS & FINISHING RUMAH SEWA

NO. PEKERJAAN VOL. SAT.

HARGA SUB TOTAL JUMLAH

SATUAN HARGA HARGA

(Rp.) (Rp.) (Rp.)

I. PEKERJAAN LANTAI DAN DINDING 502,355,700

1.1. Pasang Granito Lantai Ukuran 40x40 cm 272.00 M2 281,430 76,549,000

1.2. Pasang Keramik Lantai Ukuran 40x40 cm 144.39 M2 220,430 31,827,900

1.3. Pasang Keramik Lantai Ukuran 30x30 cm 222.00 M2 209,140 46,429,100

1.4. Pasang Keramik Lantai Ukuran 20x20 cm 54.00 M2 110,560 5,970,200

1.5. Pasang Keramik Dinding Ukuran 20x25 cm 305.65 M2 166,520 50,897,200

1.6. Pasang Plint Keramik Ukuran 20x40 cm 340.00 M1 70,350 23,919,000

1.7. Pasang Plint Keramik Ukuran 15x30 cm 150.00 M1 39,270 5,890,500

1.8. Pasang Bon bon Keramik 93.30 M1 20,120 1,877,200

1.9. Pasang Batu Alam Lantai Ukuran 30x30 cm 85.00 M2 232,710 19,780,400

1.10. Pasang Batu Alam Dindingi Ukuran 30x30 cm 250.00 M2 260,830 65,207,500

1.11. Pasang Wallpaper Dinding 310.00 M2 561,315 174,007,700

II. PEKERJAAN KUSEN, DAUN PINTU DAN JENDELA 419,486,400

2.1. Kusen, Daun Pintu dan Jendela (PJ-1) 17.00 Unit 13,763,750 233,983,800

2.2. Kusen, Daun Pintu (P-1) 17.00 Unit 6,045,000 102,765,000

2.3. Kusen, Daun Pintu (P-2) 2.00 Unit 5,420,000 10,840,000

2.4. Kusen, Daun Pintu (P-3) 3.00 Unit 5,745,000 17,235,000

2.5. Kusen, Daun Jendela (J-1) 1.00 Unit 4,193,750 4,193,800

2.6. Kusen, Daun Jendela (V-1) 17.00 Unit 2,968,750 50,468,800

III. PEKERJAAN ATAP 171,264,100

3.1. Pasang Plafond Gypsum Board 9mm + Rangka 565.84 M2 233,300 132,010,500

3.2. List Profil Plafond Gypsum 526.40 M1 74,570 39,253,600

IV. PEKERJAAN PENGECATAN 95,276,800

4.1. Pengecatan Dinding 3 lapis + Plamur 1,017.00 M2 23,370 23,767,300

4.2. Pengecatan Plafon 3 lapis 848.76 M2 28,800 24,444,300

4.3. Pengecatan Kayu Melamin 420.00 M2 112,060 47,065,200

V. PEKERJAAN ELEKTRIKAL 77,816,300

5.1. Pemasukan Daya Listrik 17.00 Unit 2,100,000 35,700,000

5.2. Box Panel Distribusi 17.00 Unit 315,000 5,355,000

5.3. Instalasi Titik Lampu 106.00 Ttk 189,500 20,087,000

5.4. Instalasi Stop Kontak 40.00 Ttk 35,440 1,417,600

5.5. Stop Kontak 36.00 Ttk 23,630 850,700

5.6. Saklar Tunggal 110.00 Unit 31,500 3,465,000

5.7. Lampu pijar 25 - 40W 77.00 Unit 63,000 4,851,000

5.8. Lampu TL Bamboo 40 Watt 29.00 Bh 210,000 6,090,000

Page 7: RAB Rumah Kos Dan Ruko for WY

RENCANA ANGGARAN BIAYAPEKERJAAN UTILITAS & FINISHING RUMAH SEWA

NO. PEKERJAAN VOL. SAT.

HARGA SUB TOTAL JUMLAH

SATUAN HARGA HARGA

(Rp.) (Rp.) (Rp.)

VI. PEKERJAAN PLUMBING DAN SANITASI 265,882,400

6.1. Pipa Air Bersih (PVC 3/4") 255.00 M1 29,720 7,578,600

6.2. Pipa Air Bersih Galvanis (PVC 3/4") 52.00 M1 89,160 4,636,300

6.3. Kran Air 20.00 Unit 302,500 6,050,000

6.4. Shower 17.00 Unit 2,002,500 34,042,500

6.5. Wastafel 17.00 Unit 2,037,500 34,637,500

6.6. Closet Duduk 17.00 Unit 6,187,500 105,187,500

6.7. Hanger Anduk + Tempat Sabun 17.00 Unit 500,000 8,500,000

6.8. Pompa Air 1.00 Unit 2,000,000 2,000,000

6.9. Tanki Air !000 L 1.00 Unit 3,750,000 3,750,000

6.10. Water Heater 17.00 Unit 3,500,000 59,500,000

VI. PEKERJAAN FURNITURE DAN PERLENGKAPAN 1,147,500,000

7.1. Lemari Pakaian + Meja Kerja + Tempat Tidur+ Kursi 17.00 Unit 57,500,000 977,500,000

7.2. Spring Bed 17.00 Unit 1,000,000 17,000,000

7.3. AC 3/4 PK 17.00 Unit 3,500,000 59,500,000

7.4. TV 23 inc 17.00 Unit 3,500,000 59,500,000

7.5. Kulkas 17.00 Unit 2,000,000 34,000,000

J U M L A H 2,679,581,700

Page 8: RAB Rumah Kos Dan Ruko for WY

DAFTAR HARGA SATUAN PEKERJAAN

NO. ID URAIAN HARGA SATUAN (Rp.)

MATERIAL UPAH JUMLAH

1. An. G.72 S 1 M2 Ubin Granito 40 x 40 cm Pas 1:4 242,520 38,910 281,430

2. An. G.72e 1 M2 Ubin Keramik 40 x 40 cm Pas 1:4 181,520 38,910 220,430

3. An. G.72d 1 M2 Ubin Keramik 30 x 30 cm Pas 1:4 169,520 39,620 209,140

4. An. G.72c 1 M2 Ubin Keramik 20 x 20 cm Pas 1:3 68,110 42,450 110,560

5. An. G. 141 1 M2 Pemasangan Keramik Dinding 20 x 25 cm Pas 1:3 116,990 49,530 166,520

6. An. SNI 1 M1 Pasang Plint 20x40 Pas 1:4 61,860 8,490 70,350

03-2835-2002S

7. An. SNI 1 M1 Pasang Plint 15x30 Pas 1:4 30,780 8,490 39,270

03-2835-2002

8. An. G.70 1 M1 Pasangan bon-bon keramik 15,680 4,440 20,120

9. An. G.72cS 1 M2 Batu Alam Candi Lantai 30 x 30 cm Pas 1:3 176,110 56,600 232,710

10. An. G. 141S 1 M2 Batu Alam Andesit Dinding 30 x 30 cm Pas 1:3 183,000 77,830 260,830

11. An. S1 1 M2 Pasang Wall Paper Dinding 500,250 61,065 561,315

12. Supl-5 1 Unit Pintu dan Jendela PJ-1 13,160,000 603,750 13,763,750

13. Supl-6 1 Unit Pintu P-1 5,620,000 425,000 6,045,000

14. Supl-7 1 Unit Pintu P-2 5,120,000 300,000 5,420,000

15. Supl-8 1 Unit Pintu P-3 5,320,000 425,000 5,745,000

16. Supl-9 1 Unit Jendela J-1 3,790,000 403,750 4,193,750

17. Supl-10 1 Unit Jendela V-1 2,540,000 428,750 2,968,750

18. An. H.80d 1 M2 Pekerjaan Plafond Gypsum + Rangka 203,750 29,550 233,300

19. An. H.80c 1 M1 Pekerjaan Les profil Plafond Gypsum 67,500 7,070 74,570

20. An. K23.aS 1 M2 Pengecatan dgn Cat Tembok 2xPlamir&Finish. 10,640 12,730 23,370

21. An. K23.c 1 M2 Pengecatan Plafond 2xPlamir&Finish. 13,530 15,270 28,800

22. An. K23.b 1 M2 Pengecatan dengan Cat Kayu 3x 12,880 35,000 47,880

23. Suplement 1 M2 Pengecatan Lapis Melamine Duco 62,370 49,690 112,060

24. Supl-12 1 M2 Pengecatan dengan Cat Besi 3x 30,660 42,000 72,660

25. Pemasukan Daya Listrik 1300 W 2,000,000 100,000 2,100,000

26. Pasang Panel Distribusi 300,000 15,000 315,000

27. An. R.21 1 titik Pekerjaan jaringan lampu 89,500 100,000 189,500

28. Pasang Stop Kontak 33,750 1,690 35,440

29. Pasang Saklar Tunggal 22,500 1,130 23,630

30. Pasang Stop Kontak Double 30,000 1,500 31,500

31. Pasang Lampu Pijar 60,000 3,000 63,000

32. Pasang Lampu TL 200,000 10,000 210,000

33. An. P.11.b 1 M1 Pekerjaan Instalasi Pipa PVC Ø 3/4" 21,080 8,640 29,720

34. 1 M1 Pekerjaan Instalasi Pipa Galvanis PVC Ø 3/4" 63,240 25,920 89,160

35. 1 Unit upah & material pemasangan Kran Air 300,000 2,500 302,500

36. 1 Unit upah & material pemasangan Shower 2,000,000 2,500 2,002,500

37. 1 Unit upah & material pemasangan Floor Drain 150,000 2,500 152,500

38. 1 Unit upah & material pemasangan Closet Jongkok 250,000 25,000 275,000

39. 1 Unit upah & material pemasangan Washtafel 2,000,000 37,500 2,037,500

40. 1 Unit upah & material pemasangan Closet Duduk 6,150,000 37,500 6,187,500

41. 1 M2 Pasang Partisi Kayu 320,000 35,000 355,000