spcc ptm p ts 001 rev b

Upload: dan-morgan

Post on 03-Jun-2018

221 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/12/2019 Spcc Ptm p Ts 001 Rev b

    1/27

    Tia Maria Project

    ______Specification

    Rev. APage 1of 27

    SOUTHERN COPPER CORPORATION

    Tia Mara Project

    TECHNICAL SPECIFICATION

    SPCC-PTM-P-TS-001

    INSTALLATION FIELD PIPING SYSTEMS

    REV DATE BY CHK APPROVAL DESCRIPTION

    B 10/12/07 EB JVR Issued for biddin

    DISTRIBUTION A B C 0 1 2 3 4 5 6 7 8 9 10

  • 8/12/2019 Spcc Ptm p Ts 001 Rev b

    2/27

    Tia Maria Project

    ______Specification

    Rev. APage 2of 27

    CONTENTS

    1.0 GENERAL 03

    2.0 REFERENCES : Standards and Codes. 03

    3.0

    4.0

    FABRICATION

    INSTALLATION

    05

    06

    5.0 WELDING FOR STEEL PIPING 13

    6.0 BRONZE AND TIN WELDS 17

    7.0 ELECTRICAL HEATING 17

    8.0 CLEANING, FLUSHING AND PROTECTION 17

    9.0

    10.0

    PAINTING

    QUALITY CONTROL

    21

    21

    11.0 INSPECTION 22

    12.0

    13.0

    14.0

    IDENTIFICATION

    GENERAL PROCEDURES FOR PRESSURE TESTING

    ATTACHMENTS

    ANEXO 1.- PIPING IDENTIFICATION LEGEND

    ANEXO 2.- FLUSHING/CHEMICAL CLEANING

    ANEXO 3.- PRESURE TEST RECORD

    22

    22

    25

    26

    27

  • 8/12/2019 Spcc Ptm p Ts 001 Rev b

    3/27

    Tia Maria Project

    ______Specification

    Rev. APage 3of 27

    1.0 GENERAL

    1.1 Scope

    This specification covers the general requirements for the installation of Steel,

    PVC and HDPE piping systems for the Tia Maria Project for Southern Peru.

    1.2 Work included

    Minor materials requirements.

    Installation

    Cleaning and flushing

    Supports

    Services identification

    Inspection and testing ( QC ).

    Painting and identification

    1.3 Work excluded

    Material purchase

    Unloading and storage

    1.4 Requirements

    The process and service pipelines must be prepared and installed according to

    the reference standards, the drawings of the project, the class and the materials

    of the pipes according to the design and requirements established in thisdocument.

    All installations must be executed following good industrial practices, in

    compliance with procedures verified by the Quality Control of the installer,

    conveniently recorded and filed.

    In the event of a conflict between the aforementioned documents, this

    Specification shall prevail, except where another legal provision is otherwise

    applicable.

    2.0 REFERENCES

    2.1 Standards

    Unless otherwise specifically indicated, all the work must be carried out

    according to the requirements of the latest reviews of the applicable codes and

    regulations, which must include but not be limited to the following:

  • 8/12/2019 Spcc Ptm p Ts 001 Rev b

    4/27

    Tia Maria Project

    ______Specification

    Rev. APage 4of 27

    ANSI American National Standards Institute

    API American Petroleum Institute Standards

    ASME American Society of Mechanical EngineersASNT American Society for Non-Destructive Testing

    ASTM American Society for Testing and Materials

    AWWA American Water Works Association

    AWS American Welding Society

    FM Factory Mutual Engineering Division Recommended Practices

    HI Hydraulic Institute

    MSHA Mine Safety and Health Administration

    MSS Manufacturers Standardization Society of the Valve and Fittings

    Industry

    NFPA National Fire Protection Association

    OSHA Occupational Safety & Health Administration

    UL Underwriters Laboratories Inc.

    2.2 Codes

    When the regulations, laws and statutes of the local codes have priority over the

    ASTM or ANSI standards, such regulations, laws, statutes or codes must prevail

    and this fact shall be indicated in the project drawings.

    Materials, installation, tests and inspection should be in agreement with the last

    edition of the following codes

    ANSI B31.3 Code for Chemical Plant and Petroleum Refinery Piping.

    AWWA C200 Code for Steel Water Pipe.

    Whenever other codes apply such as the fire, refrigeration or health protection

    codes, these shall be indicated in the drawings of the Project.

    The installation, tests and inspection of the reinforced plastic fiberglass (FRP),

    the high density polyethylene (HDPE) and polyvinyl chloride (PVC) and other

    thermoplastic pipe materials must be manufactured according to ANSI B31.3.

    2.3 In addition to the standards and their referential specifications, the following

    specifications must be considered in its last revisions..

    25329-220-3DR-G01L-0001 General Site Conditions

    SPCC-PTM-P-DC-001 Piping Design Criteria

    Line List.

    SPCC-PTM-C-TS-006 Painting Specification

    SPCC-PTM-P-TS-003 G. S. for fusion welding at field & Shops

    Of HDPE pipelines.

  • 8/12/2019 Spcc Ptm p Ts 001 Rev b

    5/27

  • 8/12/2019 Spcc Ptm p Ts 001 Rev b

    6/27

    Tia Maria Project

    ______Specification

    Rev. APage 6of 27

    SERVICE NDE

    Service Lines ( Up to and including 150# ) 5 % spot RT ( CD as necessary )

    Process Lines 10% spot RT (CD as necessary)Highly toxic, highly flammable or highly 20% spot RT (CD as necessary)

    explosive lines.

    RT : Radiographic testing

    UT : Ultrasonic testing.

    CD: Magnetic Particle and/or Dye Penetrant.

    4.0 INSTALLATION

    4.1 General

    Coordinates, dimensions and elevations are indicated in the drawings.All the installation drawings must be signed and approved for

    CONSTRUCTION and the installer is responsible for keeping the latest version

    at the site.

    Prior to the mounting of the pipes, the installer must inspect the route indicated

    in the drawings and confirm the feasibility of the installation. The pipes must be

    installed as shown in the project drawings, however any interference or

    discrepancy, regardless of its nature or origin, must be settled by the installer.

    Any amendments required to solve such inconveniences must be made by the

    installer and approved by the authorized representative of Southern Peru.

    If the routing and layout of the pipes of less than 1 are not fully detailed or

    shown in the projects drawings, these must be determined onsite following the

    requirements of the P & ID and in accordance with the authorized representative

    of Southern Peru.

    The installer is responsible for the suitable storage at the project site of the pipes

    waiting to be installed. The ends of the referred pipes must remain sealed until

    the moment prior to their installation to prevent the contamination of their

    internal walls.

    PVC pipes can not drag across rocks or roads which could cause scratches and

    gouges. Do not install underground piping when the soil is wet.

    Do not backfill PVC pipelines with rocks or coarse fill. Provide a 300 mm coverof clean fill over PVC piping prior to any coarse back fill material.

    The actuator of valves may be rotated by the contractor only with prior

    authorization from Southern Peru authorized representative.

  • 8/12/2019 Spcc Ptm p Ts 001 Rev b

    7/27

    Tia Maria Project

    ______Specification

    Rev. APage 7of 27

    Pipe supports shall be in accordance with specification No SPCC-PTM-P-TS-

    002and drawings for installation.

    When construction pipeline crossings of roads, maintain safety precautions such

    as signs, lights and guards in the interest of public safety. A temporary bypass

    must be provided.

    Install culverts at road crossings as shown on the piping drawings . Allowable

    loads shall be according to AASHTO standards.

    4.2 Vents and Drains

    Vents in high points and drainages in low points must be provided to facilitate

    hydrostatic testing, cleaning, maintenance and operation of the system, as

    outlined in the drawings and the P&ID of the Project.

    The drainage points of the equipment and pipes located up to 1,5 meters from

    the floor slab shall not require drainage pipes unless specifically shown in the

    projects drawings. All drainage points above 1,5 meters must be equipped with

    pipes to discharge the floor drains or in the catch basin. Valves for the vents and

    drains must be installed according to the drawings developed by the Detailed

    Engineering.

    4.3 Inspection before mounting

    All the pipe spools and loose pipes must be inspected before mounting to

    make sure that they are damage free, with no dirt or any foreign substance. The

    damaged items must be reported in writing to the authorized representative of

    Southern Peru.

    The prefabricated spools must be examined to verify that the identity of each

    piece is correct according to the approved installation drawings.

    4.4 Pipe expansion

    The expansion joints must be anchored and installed according to the

    manufacturers instructions to make sure that their free play is not damaged

    during maximum expansions and contractions. The expansion joints must be

    removed prior to the hydrostatic test.The pipes must be installed to prevent interferences due to the expansion or

    contraction of the adjacent pipes.

  • 8/12/2019 Spcc Ptm p Ts 001 Rev b

    8/27

    Tia Maria Project

    ______Specification

    Rev. APage 8of 27

    4.5 Equipment and pump connections

    All equipment and pump connections must be installed without exercising stresson the line, taking into account all the contractions due to welding or

    constructive misalignments. The cold spring coupling of the pipes or forcing

    the interconnecting pipes to make them connect shall not be allowed.

    If the nozzles or the alignment of the equipment and pumps are impaired due to

    a faulty or deficient installation, the installer shall be responsible for all the

    actions taken to solve the problem. In flanged connections, the pipes must be

    installed and supported in such a manner so as to achieve an exact alignment of

    the holes for the bolts and an even contact without exercising stress over the

    total area of the packing. The pipes must not be supported from the flanges of

    the equipment during construction. The pipe supports must be suitably located

    to prevent overloading in the lines and equipment.Under no circumstance must the ground connection be welded in the base plates

    of the mechanical equipment nor shall the ground connection be made through

    the equipment. The brazing tongs must be as close as possible to the point where

    the welding is being performed.

    4.6 Insulation for galvanic corrosion

    Insulation flanges must be installed in the flanged connections between the

    cathode protected surface pipes and the underground pipes. In the case of the

    steel pipes on the surface coupled with cast iron underground pipes, the

    transition must consist of a non-conductor pipe adaptor. Only when the cast iron

    pipes have a molded elastic packing installed in the plant can it be directly

    coupled to the steel pipe.

    Special care must be taken upon installing the insulation kit to avoid damaging

    the sleeves of the bolts, the packings and the washers. Having completed the

    coupling it must be tested with the Megger, DVOM, or a similar device to

    secure electrical isolation. The required reading must exceed 10.000 Ohms.

    The ground connections of the weldings must not be installed using isolation

    flanges.

    4.7 Pipe threaded connections

    The threaded connections must be sealed with 13mm wide by 0.08mm/0.1mm

    thick Teflon tape or a similar component, unless the connection is sealed by

    welding. For temperatures above 260 C, use Armite N 250, lead plate,

  • 8/12/2019 Spcc Ptm p Ts 001 Rev b

    9/27

    Tia Maria Project

    ______Specification

    Rev. APage 9of 27

    Molycote G or similar component, unless the connection is otherwise weld-

    sealed.

    The machine oil to make the thread of the pipes or to cut must be eliminated

    with solvent before applying the tape or the sealing component.

    4.8 Seal welding for threaded connections

    When the specifications of pipe materials stipulate that the threaded carbon steel

    and stainless steel connections must be sealed by welding, the referred welding

    shall be penetration groove welding. Special care must be taken to make sure

    that a minimum of master wire (hilo macho) is left exposed in the adjustments.

    Compounds for sealing thread or tape must not be used. No tape or thread must

    be left exposed after soldering. Welding in malleable iron shall not be allowed.

    4.9 Coupling of pipe with grooved ends

    The Victaulic pipe must be installed according to the Victaulic connection

    manufacturers assembly instructions.

    Couplings Style Number 77 : the separation between the ends of the pipes and

    the maximum admissible movement between pipe ends provides a relation

    between the coupling and the rear end of the pipes groove. In order to achieve

    an equal contraction and expansion, the visible space on either side of the

    coupling must allow for of the maximum admissible movement at the end of

    the pipe for a total separation of pipes of of the maximum admissible

    movement.

    Couplings Style Number 07 Zero-Flex : this coupling is rigid and does not allow

    the pipe to accommodate to the expansion or contraction. The separation

    between pipes cannot be adjusted onsite. Its installation shall be carried out

    according to the instructions of the manufacturer.

    Victaulic Flanges Style 741, 742, 742SF : These elements are designed to rest

    against a regular and hard surface. A metal washer must be inserted between the

    Vic-Flange and the accompanying flange for the following applications:

    a) when the Vic-Flange is connected against an irregular flange (in other words,cast steel gate, globe or check valves). The washer and a packing must be placed

    between the referred washer and the irregular flange.

    b) when the Vic-Flange is connected to a rubber cased flange, the washer must

    be installed but in this case additional packing is not required.

  • 8/12/2019 Spcc Ptm p Ts 001 Rev b

    10/27

    Tia Maria Project

    ______Specification

    Rev. APage 10of 27

    4.10 FRP, PVC, HDPE and casing pipes

    The fiberglass reinforced pipes (FRP) must be handled, stored and installedaccording to the installation instructions of the manufacturer. All the parts must

    be eye-inspected for possible damages. The damaged parts must be cut or

    repaired. The protection seals of the ends of the pipe must not be removed until

    the moment of fabrication.

    The polyvinyl chloride pipes (PVC) with cemented socket joints must be

    installed according to the manufacturers instructions. The solvent cement must

    not be used beyond its date of used recommended by the manufacturer.

    The high density polyethylene pipes (HDPE) must be welded/soldered according

    to the General Specification for Workshop and Onsite Fusion Welding N

    SPCC-PTM-P-TS-003 The installation and the welding must be carried out byqualified staff with experience in work with HDPE pipe materials.

    Thermal expansion and contraction must be controlled as follows:

    a) Ideally, the HDPE pipe must be installed at a temperature ranging

    between 5 C and 7C design temperature indicated in the list of lines,

    considering the season and time of day. The temperature can be adjusted

    by circulating hot or cold air through the pipes to obtain the required

    temperature. This is particularly important in the case of connections

    between two fixed points.

    b) Supports must be provided to prevent overloading on adjacent points of

    connection.

    c) The HDPE pipes installed on the surface or buried must be undulated and

    anchored, as necessary, so that the heat expansion and contraction can be

    controlled by lateral deflection. The level of undulation required for the

    buried pipes shall be smaller than that required for the exposed pipes on

    the surface, due to the smaller changes in temperature and in the thermal

    mass of the ground. The buried pipes shall also require less anchoring

    due to the natural anchoring power provided by the contact with the

    ground.

    d) To install an HDPE pipe on the surface between two fixed connection

    points, sufficient pipe length must be added to allow for the contraction.

    The extra length is calculated using the following formula:

    L = 0,00017 L (t1 - t2)

    L = extra length, in meters, to be added to L

    L = length, in meters, at room temperature at the time of installation

  • 8/12/2019 Spcc Ptm p Ts 001 Rev b

    11/27

    Tia Maria Project

    ______Specification

    Rev. APage 11of 27

    t1 = room temperature at the time of installation

    t2 = lowest temperature of the season in the area

    Anchoring must be provided to prevent excess stress on the end of the HDPE

    pipe and the on the connection to adjacent fixed tanks, equipment or piping.

    Care must be taken to avoid damages to the casings and linings upon installing

    the cased, lined pipes or rubber hoses.

    4.11 Access and open/unobstructed spaces

    The pipes must not interfere with the access to the valves or the equipment and

    must not obstruct aisles or walkways. When access is required, the minimum

    open/unobstructed spaces must meet the requirements contained in the General

    Specification for Installation of field piping Systems No SPCC-PTM-P-TS-001for this project.

    .

    Pipe installations that fail to meet these limits require the approval of the

    authorized representative of SOUTHERN PERU. Furthermore, they must be

    supplemented by suitable onsite security signs and markings.

    4.12 Passage of pipes through walls

    Penetrations in surfaces, walls and partitions to accommodate the pipes must be

    carried out according to the instructions container in the drawings. The pasajes

    must be sealed and covered after the installation with suitable materials existing

    in the market, similar or equal to the HILTY products.

    4.13 Specialties

    The installation of special complementary items, such as, filters, special

    couplings, valves, etc, must meet the manufacturers specifications with due

    provision for access to operation, maintenance and removal.

    4.14 Flanged joint

    Flanged joints must be installed and anchored to obtain the exact alignment of

    the holes for the bolts and an even, stress free contact with the total area of thepacking.

    Forcing the pipe in order to tighten the joints shall not be allowed. The bolts for

    the steel and cast iron flanges shall be tightened with a torque recommended by

    the manufacturers of the packing used in the connection.

  • 8/12/2019 Spcc Ptm p Ts 001 Rev b

    12/27

    Tia Maria Project

    ______Specification

    Rev. APage 12of 27

    The bolts for the valve flanges and special pieces made of FRP or plastic shall

    be tightened strictly in accordance with the instructions of the manufacturers.

    Inspect the gasket material for possible defects such as bents or creases.

    Use logical sequence of bolt tightening to ensure even gasket compression, as

    indicated in ASME B16.5, or by suppliers recommendations.

    Prior to bolt-up, examine flange faces. Flange faces shall be in as-new condition,

    and shall be wiped clean of any debris, excess oil, grease, and dirt. Do not

    perform weld repairs on flange faces or flanges unless previously authorized by

    Southern Peru authorized representative.

    Inspect the studs and nuts. They should be of dirt and corrosion. The studs

    should be straight and the threats free from nicks, burrs and chips.

    Do not use washers or spacers to make up bolt length. Bolt lengths are specified

    to prevent over sizing.

    The calibration of torque wrenches and tensioners shall be checked against the

    manufacturers specifications upon receipt. Any tools that are out of calibration

    shall be rejected. A recheck f the calibration shall be made on a regular basis.

    Any tool found to be out of calibration shall immediately be taken out of service

    for repair. Frequency of calibration shall be recommended by the tensioner

    manufacturer. All flanged joints secured with tools found to be defective shall be

    rechecked with a properly functioning tool.

    4.15 Valves

    The valves, except for the valves of instruments, vents and drains must be

    accessible for operation from the operating platforms. When indicated in the

    project drawings, or where the installation of manual valves in inaccessible

    places is necessary and practical, the valves must be supplied with extension

    stems/rods or with hand-wheels with chains.

    When extension rods are installed in valves subject to linear displacements by

    heat expansion or contraction, these must include universal joints.

    The primary isolation valves for the connection of manometers, etc. must be

    installed as shown in the projects drawings.

    The rods of the valves shall not be tipped/inclined below the horizontal position

    unless otherwise specifically indicated in the project drawings.

  • 8/12/2019 Spcc Ptm p Ts 001 Rev b

    13/27

    Tia Maria Project

    ______Specification

    Rev. APage 13of 27

    The globe valves must be installed with a line pressure under the seat. In the

    vacuum service, the negative pressure must be on top of the seat.

    The cone valves lined with soft rubber must be directed according to Attachment

    1 to this Specification to prevent the accumulation of solids that may restrict the

    movement of the cone.

    All unidirectional valves must be installed with the flow arrow marked on the

    body of the valve corresponding to the direction of the flow.

    All the valves must be examined prior to their installation to check that they

    meet the technical specifications.

    4.16 Service stations, emergency showers and eyewash basins

    The indoor and outdoor service stations, emergency showers and eyewash basins

    must be installed according to detail drawing of the project.

    4.17 As built drawings

    A full and accurate record of all the unmet specifications container in the

    projects drawings shall be marked in a reproducible set of documents that must

    be kept both clearly and cleanly.

    Modifications due to interferences must be approved prior to the installation and

    recorded in the drawings. The routing pipe in the field and the pipe supports

    must also be recorded as built by the installer.

    The as built drawings must be submitted for the approval and acceptance of

    the authorized representative of Southern Peru prior to their final issue.

    5.0 WELDING FOR STEEL PIPING

    5.1 Revision of procedures

    Before beginning the work, all the welding procedures must be issued for review

    and must include the records of the suitable qualification testing procedure

    (PQR). The records of the qualification of welders must be available for theauthorized representative of Southern Peru at his convenience. The welding

    work shall only be started when the representative has approved and authorized

    their application in the project works.

    Welder operators shall be tested by installer QC inspector to assure that his

    welds will meet the requirements of specification.

  • 8/12/2019 Spcc Ptm p Ts 001 Rev b

    14/27

    Tia Maria Project

    ______Specification

    Rev. APage 14of 27

    All tests shall be in strict accordance with the provisions of ANSI B 31.3 for in-

    plant piping or API standard 1104 for long distance pipeline as applicable.

    Two copies of welding procedures with copies of the Record of Qualification

    Test Report shall be submitted to Southern Per representative prior to start of

    welding.

    The repair procedures that use welding must be issued for review.

    The repair procedures must include:

    a) The method to establish the type and size of the defect.

    b) The methods used to eliminate the defect and the test performed to make

    sure that the defect has been corrected.

    c) The welding procedure used to re-solder and the non-destructiveexamination methods (NDE) carried out to inspect the weld repair area

    after performing the welding.

    5.2 Welding processes

    The welding processes listed below can be used, subject to the following

    limitations:

    Gas Arc Welding (GMAW)

    The range of transference due to short circuiting must be limited to:

    1) Ferrous materials that do not exceed a nominal thickness of 7 mm

    (1/4) and to austenitic steel and nickel based materials with a

    nominal thickness of up to and including 5 mm (3/16).

    2) Pipes butt welded on one side only, in flat or rotating positions

    regardless of the thickness of the material.

    3) Non-structural inserts when the welded material does not exceed

    a nominal thickness of 7 mm(1/4 inches).

    4) Welding of points, temporary inserts, couplings welded on both

    sides and other applications in which the metal welding deposited

    by the GMAW short-circuiting process is subsequently

    eliminated.

    5.3 Welding electrodes

    The welding materials must be selected in such a manner that the deposited

    welding metal is not significantly harder or more resistant than the base material.

    Welding for couplings made of uneven ferrous material must match the

  • 8/12/2019 Spcc Ptm p Ts 001 Rev b

    15/27

    Tia Maria Project

    ______Specification

    Rev. APage 15of 27

    resistance of the material of the lowest P-number groups contained in

    Appendix A of Standard ASME/ANSI B31.3, Table A-1 Basic Allowance

    Stresses in Tension for Metals.

    The detailed engineering drawings shall indicate the electrode and type of

    welding to be employed whenever welded joints/connections are required.

    However, the installer must bear in mind that all the arc welded metals must be

    welded using low hydrogen type electrodes in any of the following conditions:

    a) In steels with a specified carbon content of over 0.30% or steels with a

    resistance to tension of over 482650 Kpa (70.000 psi), or in ferrous steel

    smelting repairs with SMAW welding.

    b) For the materials of steel piping in group P-1 that require the use oflow hydrogen electrodes, only the butt can be soldered with AWS E6010

    and E7010-A1 electrodes, respectively.

    c) If the base material has been impact tested, the electrodes classified

    under E6012, E6013, E7014 and E7024 must not be used to pressure

    weld parts. However, these electrodes can be used in fillet welds in parts

    without pressure of materials in group P-1. The storage, heating and

    drying of coated electrodes, flux-coated electrodes and fluxes must meet

    the recommendations of the manufacturer.

    5.4 Welding requirements

    All welding works must be protected from the wind, rain and other adverse

    weather conditions that may affect the quality of the weld.

    The surfaces to be welded must be free of incrustations, oil, grease, dust, paint,

    galvanizing and other pollutants.

    The passage of all the butt welds must be inspected by applying penetrating die.

    The QC inspector of the installer shall be the person in charge of qualifying the

    result of the test and shall authorize that welding be continued if the result is

    correct. Otherwise, he shall order the work to be redone.

    The thickness of each layer of individual welding, for all processes, must not

    exceed 13 mm (1/2) for materials with a thickness of 32 mm (1-1/4) and more,

    and 10 mm (3/8) for materials with a thickness of 32 mm (1-1/4) and less.

    Welds that retain pressure must have two layers at least. The slag/clinker must

    be fully eliminated before proceeding with the next layer.

  • 8/12/2019 Spcc Ptm p Ts 001 Rev b

    16/27

    Tia Maria Project

    ______Specification

    Rev. APage 16of 27

    When double groove welding is used, the first step must be chiseled, sanded or

    cleaned with the arc until the metal is totally clean before soldering a secondtime.

    After cleaning with the arc, an inspection for magnetic particles shall be carried

    out at the request of the authorized representative of Southern Peru.

    Welding without beveling is prohibited. The procedures and good building

    practices must be applied.

    5.5 Preheating

    The preheating temperature must meet the applicable codes, except for the

    recommended minimum preheating temperatures which must be consideredmandatory. The preheating requirements must also be applied to the spot

    welding and to the welding of temporary inserts. The preheating requirements

    must also be applied to arc cleaning and to the cutting operations, except for the

    steels of group P-1.

    In addition to the requirements of the applicable code, the steels in group P-1

    must have a minimum preheating temperature of 80C, for thicknesses that

    exceed 38 mm (1-1/2).

    Preheating must be established with fusion thermometers, contact pyrometers or

    other appropriate equivalent means.

    5.6 Labor, visual examination of quality and inspection

    The welding layer must be even and without slag sediments, porosity and

    damaging undercuts. Cracks and lack of fusion and/or penetration are forbidden.

    In addition, the final welding layer must be basically free of rough formations,

    uneven seams, high peaks or depressions. The marks left by the blows of the arc

    at the beginning and at the end of the welds must be re-smelted with welding or

    eliminated with emery. Welding with cracks must not be locally repaired. The

    total length of the weld must be eliminated and the groove must be prepared

    once again for new welding application.

    The socket weld must have a light of 2 mm (1/16) minimum to 3 mm (1/8)

    maximum, approximately, between the bottom of the socket to the end of the

    pipe, prior to execution.

  • 8/12/2019 Spcc Ptm p Ts 001 Rev b

    17/27

    Tia Maria Project

    ______Specification

    Rev. APage 17of 27

    The misalignment of the pipe couplings that were butt welded on one side only

    must not exceed 2 mm (1/16) unless otherwise expressly approved by the

    representative of Southern Peru solely for lines with a high flow speed.

    6.0 BRONZE AND TIN WELDS

    Bronze and tin welds must be carried out by qualified staff according to the

    recommendations of the manufacturer for the materials that are being welded.

    The welding procedures must be issued and forwarded to the authorized

    representative of Southern Peru for his review and approval prior to their

    execution.

    7.0 ELECTRICAL HEATING

    The electrical heating requirements will be appliance according design

    specifications and drawings for steel piping..

    8.0 CLEANING, FLUSHING AND PROTECTION

    The installer must prepare and present to the representative of Southern Peru for

    approval thereof, of the cleaning procedures for each pipeline as relevant and

    according to the design specifications to this effect. The installer is responsible

    for the execution of these actions and the necessary equipment.

    The pipes must be dry, totally clean and free of dust, slag and other loose foreign

    material, before being mounted. The spools can be placed face down and banged

    to remove the dust and other waste prior to the final thorough cleaning

    procedure.

    Solvents shall be used to eliminate grease, oil or other foreign material. The

    recommended solvents are acetone and trichloretane. Solvents with chlorine

    used to clean stainless steel pipes must be immediately eliminated after cleaning

    with potable water, rinsing oil, hydraulic or transmission oil.

    The installer shall be responsible for the disposal of chemicals, washing water,

    flushing oil, containers and the like.

    The stainless steel pipes shall be brushed with clean stainless steel brushes that

    have not been previously used in materials other than stainless steel.

    The hot-rolled bends must be hand cleaned to fully remove the adhered sand.

    Following chemical clearing and inspection, cleaned piping subject to prolonged

    periods of storage, prior to installation, shall have all openings tightly sealed to

  • 8/12/2019 Spcc Ptm p Ts 001 Rev b

    18/27

    Tia Maria Project

    ______Specification

    Rev. APage 18of 27

    protect against the possible entry of foreign matter, moisture, etc. until the entire

    system is ready for operation. Flanged ends shall be sealed using tape and

    polyethylene sheeting . Threaded or socket weld connections and butt weld endsshall be tightly sealed with polyethylene or plastic plugs ( or cans) secured with

    tape. Tape used for securing covers shall be of a vinyl waterproof type.

    The method for the discharge of chemical products, rinse water, flushing oil,

    containers and similar elements, must be issued and forwarded to the authorized

    Representative of Southern Peru for approval thereof. Under no circumstance

    shall the waste be discharged in the plant.

    For PVC piping lines cleaning and flushing shall be according fabricator

    recommendations.

    8.1 Flushing of Steel pipelines

    8.1.1. General Requirements

    a) As an initial stage, all the pipe systems, including the lines for the

    transportation of sulfuric acid, must be cleaned inside with air or steam

    to remove the waste and other foreign matters.

    b) For those systems that require flushing, they shall be flushed at speeds

    that must not fall below the design speeds. The long vertical pipes must

    be cleaned downwards. The main distribution heads must be washed

    separately before washing the branch pipes. Flushing with water must be

    carried out with clean water using the water spray of the hydrostatic test

    whenever possible. The transmission and hydraulic oil pipes must be

    cleaned with flushing oil.

    c) The pipes upstream from the pumps or compressors must be washed

    before the downstream pipes.

    d) The downstream pipes, subject to the approval of the authorized

    Representative of Southern Peru, can be washed or flushed using the

    installed pumps or compressors. This equipment can be protected by

    temporary suction filters during the cleaning process and the initial tests

    if the conditions so require.

    e) The flushing of any element of the system shall be considered completed

    when the eye-inspection of a sample of one quarter of a gallon of

    flushing water appears to be clean and with no suspended material.

  • 8/12/2019 Spcc Ptm p Ts 001 Rev b

    19/27

    Tia Maria Project

    ______Specification

    Rev. APage 19of 27

    The pipes must not be connected to the equipment until flushing has

    been completed.

    The use of fresh water obtained from the ground shall require the

    approval of the authorized Representative of Southern Peru. The

    Installer must schedule the date and time prior to the execution of the

    works to make the necessary arrangements.

    8.1.2 Suction pipes of compressors and vacuum pumps

    a) The suction pipes of compressors and vacuum pumps must be carefully

    cleaned to remove incrustations and all kinds of foreign material.

    Depending on the conditions, suction filters may be required.

    b) The suction pipes of the centrifugal compressors must be blown orcleaned by hand until they are completely clean prior to attaching them

    to the respective machine.

    8.1.3 Drinking water supply pipes

    a) All the drinking water supply pipes must be flushed and chemically

    disinfected according to AWWA C-601.

    8.1.4 Lubricant, hydraulic and transmission oil pipes

    Prior to the referred cleaning or flushing process, all the pipes of these

    systems must undergo a pickling (chemical wash) according to the

    following procedure:

    -Degrease to fully remove the protective coating. -Clean with sulfuric acid at 5% to remove all foreign substances inside

    the pipe.

    -Neutralize, rinse and fully remove the Pickling solution. -Dry carefully. -Protect the interior of the pipe with a corrosion-resistant protector

    approved by the authorized Representative of Southern Peru.

    a) The stainless steel pipes for lubricating, hydraulic and transmission oil

    systems must be cleaned with a mildew inhibitor washing oil until thereare no particles of dirt, metal or any other type of material. Washing

    must be carried out for at least one hour or until no waste is observed in a

    filtering cloth of 30 nominal microns.

    b) After cleaning, the system must be pressure tested, using flushing oil as a

    test fluid.

  • 8/12/2019 Spcc Ptm p Ts 001 Rev b

    20/27

    Tia Maria Project

    ______Specification

    Rev. APage 20of 27

    c) The flushing oil must be emptied and all the equipment, catch basins,

    filter, etc., cleaned.

    d) Immediately after emptying, the operating oil must be circulated in the

    system until all traces of flushing oil have disappeared.

    e) The circulated oil must be emptied and the system must be immediately

    filled with fresh operating oil. The system must be sealed ready to

    begin.

    f) Disposal of chemicals: the Installer shall be responsible for the safe

    storage and disposal of all the flushing oils, chemical washes and

    containers. In these cases, the counseling of the Department of

    Environmental Services shall be provided through the authorizedRepresentative of Southern Peru.

    8.1.5. Pipes for sulfuric acid

    After the initial cleaning stage, the pipes of the sulfuric acid system shall be

    flushed with water prior to their installation. Once they have been installed they

    shall be hydrostatically tested. Upon completion of the hydrostatic test, the

    entire system shall be dried with dry air.

    8.1.6. Control vales and instruments

    The control valves and instruments must be flushed or removed as follows:

    a) Control valves with gate and bypass valves: Remove the valve, open the

    bypass valve, close the gate valves and wash. Open the gate valve

    upstream and wash. Close the gate valve downstream and wash for five

    minutes.

    b) Control valve without a gate or bypass valve: remove the valve. Install a

    spool and wash.

    c) Magnetic Flow Gages: wash them completely.

    d) Positive displacement gages: Remove the gages. Clean as in point b).

    e) Rotameters, flow regulators, solenoid valves, pinch valves: remove the

    instrument. Wash as in point b).

  • 8/12/2019 Spcc Ptm p Ts 001 Rev b

    21/27

    Tia Maria Project

    ______Specification

    Rev. APage 21of 27

    8.2 Procedures for approval

    a) The proposed sector to be washed and the flushing or cleaningprocedures must be communicated to the authorized Representative of

    Southern Peru for approval prior to proceeding thereon.

    b) The records of the washing and rinsing procedures carried out must be

    inspected by the QC of the installer and approved and signed, after which

    they shall be filed.

    8.3 Evacuation of cleaning agents and chemical products.

    The Installer is responsible for the safe elimination of flushing oils, chemical

    cleaning products (pickling solutions) and containers thereof. The Department

    of Environmental Services shall provide counseling through the authorized

    Representative of Southern Peru.

    9.0 PAINTING

    The carbon steel pipes that have no thermal isolation shall be painted and

    according to specification No SPCC-PTM-C-TS-006 Shop priming and

    painting the stainless steel pipes and plastic pipes shall not be painted.

    10.0 QUALITY CONTROL

    10.1 General

    The installer contractor shall have in effect at all times, a quality control

    program, which clearly establishes the authority and responsibility of those

    responsible for the quality system. Persons performing quality control functions

    shall have sufficient and well-defined authority to enforce quality requirements

    that initiate, identify, recommended, and provide solutions to quality problems

    and verify the effectiveness of the corrective action.

    A copy of the installer contractor quality control program shall be submitted for

    Southern Peru review and approval prior to work starting.

    The quality control program shall include procedures, instructions, and QA

    systems to ensure that assigned field construction, fabrication, assembly,

    installation, field purchased materials and services, field engineering,workmanship, and other related services conform with the specified codes,

    approved design engineering specifications, design drawings, and other

    contractual, jurisdictional, and legal requirements.

    Southern Peru shall examine and inspect the final product to ensure that installer

    contractor quality criteria have been met.

  • 8/12/2019 Spcc Ptm p Ts 001 Rev b

    22/27

    Tia Maria Project

    ______Specification

    Rev. APage 22of 27

    11.0 INSPECTION

    Prior to inspection, the installer must remove all the provisional installations,

    scaffolding, frameworks, wedges, belts and other materials used in the assembly,

    maintaining only the minimum required to allow access for the inspection.

    The finished systems of pipes must be eye-inspected to check that they have

    been completed finished: the installation of the packing, the proper installation

    of the valves, suitable supports, the control valves and instruments have been

    correctly installed, etc. To this effect, the P&ID drawings of the project, as

    issued for the construction, must be used.

    The QC of the installer shall have the updated QC documents readily available

    of all the applications during the construction process (mounting andinstallation).

    12.0 IDENTIFICATION

    The pipes shall be identified based on Specification N SPCC-PTM-C-TS-006

    Shop priming and painting to this effect.

    The carbon steel pipes without exception must be fully painted and signaled

    according to the color code and name of the fluid that identifies them. In

    addition, arrows indicating the direction of the flow must be painted every 6m or

    the most convenient length according to their plant layout.

    Colored painted rings must be placed at intervals of no less than 6m or more

    than 15 m, depending on the position and configuration and in all the changes of

    direction, including the branches.

    The identifying color painted rings must be 50mm wide with a spacing of 50mm

    between the bands for multiple band codes.

    13.0 GENERAL PROCEDURES FOR PRESSURE TESTING.

    The following procedure outlines the method to be used in testing all process,

    service and utility pipe installations. Al piping systems shall be tested inaccordance with these requirements.

    A complete pressure test shall be performed on all lines and equipment upon

    completion of construction work but before insulation is applied.

  • 8/12/2019 Spcc Ptm p Ts 001 Rev b

    23/27

    Tia Maria Project

    ______Specification

    Rev. APage 23of 27

    The test pressure on any section of the line shall be limited to the test pressures

    permitted on any exchanger, separator, strainer, expansion joint or other

    appurtenance and equipment installed in the line.

    No lines shall be hydrostatically tested to less than 50 psig. Except sanitary lines

    and drains. Sewer and drain lines shall be tested a minimum hydrostatic head of

    10 feet.

    The following lines may be tested pneumatically

    Instrument air lines

    Compressed air lines for general service

    Nitrogen gas lines .

    The above lines shall be tested with air at pressure equal to at least 110 percentof the operating pressure.

    The pneumatic test pressure shall not exceed 150 psig. Lines being

    pneumatically tested shall be brought up to final test pressure in easy stages to

    avoid vibration . All joints shall be swabbed with a leak detecting compound.

    Personnel responsible for testing shall record the test pressure applied to each

    line using the attached form Pressure Test Record witnessed and signed bay

    QC constructor.

    Closed valves may be used at the extremities of the systems to be tested at the

    discretion of constructor.

    Line test pressures, established in accordance with the specification No SPCC-

    PTM-P-TS-001 or Piping Line Lists, shall not include any major equipment.

    However, it is preferred to test exchangers and/or vessels simultaneously with

    connected piping, provided the test pressure used is not higher than that

    permitted for the equipment.

    Orifice plates, which interfere with filling, venting and draining, shall be

    removed prior to testing. Where expansion joints are used in piping, they shall

    no be subjected to test pressures higher than their design test pressure. Other

    pieces of equipment, such as flame arrestors, filters, and instruments, which donot have test pressures indicated, shall not be included in the tests.

    Pressure parts of instruments together with piping connecting to main pipe lines

    or equipment shall be tested at the same test pressures as the main piping or

    equipment.

  • 8/12/2019 Spcc Ptm p Ts 001 Rev b

    24/27

    Tia Maria Project

    ______Specification

    Rev. APage 24of 27

    Pressure gauges shall not be subject to pressures in excess of their scale ranges.

    Where lines to which they are connected receive a higher hydrostatic test

    pressure, the gauges shall be removed and their connections plugged. After thetest, pressure gauges shall be reinstalled.

    Prior to filling a system for testing, all pipe lines shall be cleaned thoroughly.

    Lines shall be purged of air before the hydrostatic test pressure is applied. Vents

    shall be open when draining the systems.

    Care shall be exercised in testing so the applied pressure is limited to that

    portion of the system being tested.

    Pressure relief and thermal expansion relief valves shall be excluded from the

    pressure tests. Blinds shall be installed adjacent to their inlet and/or outletflanges during tests. Screwed relief valves shall be removed and the connections

    plugged during the test.

    Lines containing check valves shall have the source of pressure located upstream

    from the check valve so the pressure is applied under the seat. If this is not

    possible, the check valves shall be removed, blanked off, or the discs popped

    open.

    Control valves shall be set in the wide open position.

    Hydrostatic test pressures shall be maintained for a sufficient length of time (30

    minutes minimum) to permit close visual or hand wiping inspection of all joints.

    Care shall be exercised in order to prevent concentration of excessive loads on

    the support structure.

    Retesting of lines, after repair, shall be done at the pressure originally specified

    for the test.

    After completion of hydrostatic testing, temporary blanks and blinds shall be

    removed and lines shall be completely drained. Valves, orifice plates, expansion

    joints, etc. shall be reinstalled. After the lines have been drained, temporary

    supports shall be removed.

    Lines pneumatically tested shall be kept under test pressure for not less than one

    hour, without a 5 % loss in pressure. If loss exceeds 5 % in one hour leaks shall

    be repaired. After repairing leaks, retest the line at the pressure originally

    specified for the test.

  • 8/12/2019 Spcc Ptm p Ts 001 Rev b

    25/27

    Tia Maria Project

    ______Specification

    Rev. APage 25of 27

    14.0 ATTACHMENTS

    ANNEX 1

  • 8/12/2019 Spcc Ptm p Ts 001 Rev b

    26/27

    Tia Maria Project

    ______Specification

    Rev. APage 26of 27

    ANNEX 2

    FLUSHING / CHEMICAL CLEANING

    DATE_________

    EQUIPMENT NUMBER ________________________AREA_________________________

    SYSTEM DESCRIPTION________________________________________________________

    _____________________________________________________________________________

    _____________________________________________________________________________

    _____________________________________________________________________________

    _____________________________________________________________________________

    FLUSHING MEDIA____________________________________________________________

    PRESURE________________________________FLOW RATE_________________________

    TEMPERATURE___________TIME START______________TIME FINISH______________

    SCREEN SIZE______________________FILTER SIZE_______________________________

    SPECIAL CONDITIONS________________________________________________________

    _____________________________________________________________________________

    COMENTS___________________________________________________________________

    _____________________________________________________________________________

    _____________________________________________________________________________

    PERFORMED BY_________________________STARTUP ENGINEER_________________

    WITNESSED BY___________________________________________

    DATE _____________________________

  • 8/12/2019 Spcc Ptm p Ts 001 Rev b

    27/27

    Tia Maria Project

    ______Specification

    Rev. A

    ANNEX 3

    PRESSURE TEST RECORD

    DATE_________

    AREA___________________________________SYSTEM____________________________

    TYPE TEST : PNEUMATIC________________________

    STATIC ________________________

    HYDROSTATIC_____________________

    DRAWING NUMBER ATTACHED ______________________________________________

    TEST DESCRIPTION __________________________________________________________

    _____________________________________________________________________________

    __ __ __ __ ___ __ __ __ __ __ __ ___ __ __ __ __ __ __ ___ __ __ __ __ __ __ ___ __ __ __ __ ___ __ __ ___ __ __ __ __ ___ __ _

    OPERATION PRESSURE________________ TEST PRESSURE______________________

    TIME START__________________________ TIME FINISH _________________________

    TEMP START ________________________- TEMP FINISH _________________________

    LEAK RATE _________________________ FINAL TEST PRESSURE _______________

    COMMENTS

    __________________________________________________________________

    _____________________________________________________________________________

    ____________________________________________________________________________

    PERFORMED BY _____________________STARTUP ENG___________________________

    WITNESSED/ACCEPTED FOR OWNER __________________________________________

    DATE__________________________