the republic of uganda - office of the auditor · pdf file1.3 audit objectives ... storm water...
TRANSCRIPT
The Republic of Uganda
VALUE FOR MONEY AUDIT REPORT ON THE MANAGEMENT OF ACCOMMODATION BY THE UGANDA POLICE FORCE
Prepared by Office of the Auditor General
P.O. Box 7083 Kampala
FEBRUARY, 2012
i
i
TABLE OF CONTENTS
LIST OF TABLES……………………………………………………………………………………………………………ii
LIST OF FIGURES ………………………………………………………………………………………………ii
LIST OF PICTURES…………………………………………………………………………………………….iii
LIST OF
ABBREVIATIONS ............................................................................................................... iv
EXECUTIVE SUMMARY ....................................................................................................... v
CHAPTER ONE ................................................................................................................... 1
INTRODUCTION ................................................................................................................ 1
1.1 Motivation ............................................................................................................... 1
1.2 Description of the Audit area .................................................................................... 1
1.3 Audit Objectives ...................................................................................................... 3
1.4 Audit Scope ............................................................................................................. 4
CHAPTER TWO .................................................................................................................. 5
METHODOLOGY ................................................................................................................. 5
2.1 Sampling ................................................................................................................. 5
2.2 Document Review .................................................................................................... 5
2.3 Interviews ............................................................................................................... 5
2.4 Observation/Field Inspections ................................................................................... 6
CHAPTER THREE ............................................................................................................... 7
SYSTEMS AND PROCESSES DESCRIPTION .......................................................................... 7
3.1 Roles and Responsibilities of Key Players ................................................................... 7
3.2 Process Description .................................................................................................. 9
CHAPTER FOUR ............................................................................................................... 11
FINDINGS CONCLUSIONS AND RECOMMENDATIONS ........................................................ 11
4.1 Allocation of Accommodation in the Police Barracks ................................................. 11
4.2 Gazetted Officers Staying in the Barracks ................................................................ 19
4.3 Maintenance of Police Buildings .............................................................................. 21
4.4 Inspection of Barracks Quarters .............................................................................. 30
GLOSSARY OF TERMS: ..................................................................................................... 35
ii
ii
LIST OF APPENDICES
Appendix (i) Organisation Chart
Appendix (ii) List of Documents obtained and reviewed during audit
Appendix (iii) Interviews conducted
List of Tables Page
Table 1: UPF Funding for the period 2008/09 to 2010/11 3
Table 2: UPF Renovation work for the period 2008/09 to 2010/11 29
List of Figures
Figure 1: Number of Police officers and available housing units by region 11
Figure 2: Number of Gazetted officers staying in the barracks 19
iii
iii
List of Pictures: Page:
Picture 1: Mattresses on the floor in Ntinda barracks 12
Picture 2: Storm Water inside the dormitory in Ntinda barracks. 12
Picture 3: Slab where a dormitory had been constructed but blown by wind. 13
Picture 4: Poorly constructed dormitory destroyed by wind. 13
Picture 5: Materials for 35 uniports in Arua Police Station meant for 7 outposts 14
Picture 6: Materials for uniports in Lira barracks. 14
Picture 7: One of the cracks on the veranda of one of the renovated houses. 15
Picture 8: Self-help houses in Luwero. 17
Picture 9: Some of the “Self-help” latrines in Ntinda barracks. 17
Picture 10: One of the housing units built under the Hydra-Form in Kitgum. 18
Picture 11: Stones holding the roof of one of the houses in Tororo barracks. 22
Picture 12: Roof in Arua barracks. 22
Picture 13: Cracks in one of the houses in Bushenyi. 23
Picture 14: Cracks and worn out plaster on one of the houses in Luwero 23
Picture 15: One of the hanging verandas in Fort-Portal barracks. 23
Picture 16: Rotten windows in Arua barracks. 24
Picture 17: Broken door at Bushenyi Police block. 24
Picture 18: Overflowing sewerage in Ntinda barracks. 25
Picture 19: Leakage of water in Nsambya barracks. 25
Picture 20: Blocked sewerage system in Tororo barracks. 25
Picture 21: Blocked sewerage system in Nsambya barracks plastic materials 25
Picture 22: Exposed electrical wires in Masindi barracks. 26
Picture 23: Uniport with exposed electrical wires in Tororo barracks. 26
Picture 24: Old Sewerage pipes that were removed but not replaced 27
Picture 25: Plants growing on the wall of one of the flats in Nsambya barracks 28
Picture 26: Plants growing on one of the buildings in Masindi barracks. 28
Picture 27: Cooking in one of the dormitories in Ntinda police Barracks. 31
Picture 28: Solid Waste in Ntinda barracks 32
Picture 29: Solid Waste in Arua barracks. 32
Picture 30: Turkeys in Ntinda barracks. 32
Picture 31: Ducks and Chicken in Arua barracks 32
Picture 32: One of the Cows in Tororo barracks 33
Picture 33: Goats in Nsambya barracks 33
iv
iv
ABBREVIATIONS
AIDS Acquired Immune Deficiency Syndrome
ASP Assistant Superintendent of Police
CID Criminal Investigations Department
CP Commissioner of Police
DPC District Police Commander
FY Financial Year
HIV Human Immunodeficiency Virus
IGP Inspector General of Police
JLOS Justice Law and Order Sector
LC Letter of Credit
OAG Office of the Auditor General
OC Officer in Charge
PTS Police Training School
Ug Shs Uganda Shillings
UPF Uganda Police Force
v
v
EXECUTIVE SUMMARY
The welfare of Police officers in the Uganda Police Force (UPF) continues to
pose a challenge. Among the key welfare concerns, is the question of
insufficient residential and office accommodation for the Police staff. For
example, a stock of 4360 available housing units accommodate about 9,331
police officers, representing only 24% of the entitled officers, at a ratio of 1
house accommodating 2 police officers. In some barracks, most families are
sharing small rooms in housing units, including uniports, which are in most
cases dilapidated. The hygienic conditions in most of the places of
accommodation are deplorable.
The police barracks are characterised by old faulty sewerage and water
systems, and absence of a systematic garbage disposal mechanism. Old water
and sewerage pipes contribute to huge utility bills through leakages and bursts.
Poor electrical installations in the UPF barracks also escalate utility bills, and
accidents through electrocution and death of people in the barracks.
Government and development partners have increased funds invested in the
UPF from Ug Shs 142 billion (bn) in 2008/09 to Ug Shs 206bn in 2009/10 and
319.4bn in 2010/11. Of these funds, buildings received Ug Shs 3.8bn (2.7%),
Ug Shs 6.9bn (3.3%) and Ug Shs 5.5bn (1.7%) in 2008/09, 2009/10 and
2010/11, respectively.
Audit Findings
The Office of the Auditor General conducted a Value for Money (VFM) audit on
the management of accommodation by the Uganda Police Force and the
following audit observations were made:
Allocation of Accommodation in the Police Barracks
It was found that only 25% of the police officers entitled to accommodation
were provided with accommodation.
Inadequate accommodation is caused by failure to match recruitment and
transfer of staff with housing requirements, poor workmanship of some
vi
vi
construction projects, delayed construction works, cost overruns and variations
which erode the available resources meant for construction work and impair
the achievement of construction targets.
Lack of accommodation has led to congestion in the barracks, lack of privacy,
promiscuity, defilement, misunderstandings between the different families, and
theft. The HIV/AIDS policy has also recognized the challenges of
accommodation in the police as one of the factors contributing to the spread of
HIV/AIDS. It has also led to the construction of un-planned structures by
individual police officers in barracks.
Gazetted Officers Staying in the Barracks
It was noted that gazetted officers at the rank of Assistant Inspectors and
above were staying in the barracks and efforts to evict them have been futile.
It was also observed that those required to pay rent had either not been
paying rent or the deductions were not consistent and accountability for the
money deducted from staff was not obtained. This is caused by conflicting
guidelines regarding gazetted officers staying out of the barracks, which
requires them to sign tenancy agreements and pay rent and at the same time
allows officers on operation command to stay in the barracks.
Allowing gazetted officers to stay in the barracks deprives entitled police
officers accommodation. Furthermore, failure by gazetted officers to pay rent
denies the UPF rental income. It should also be noted that officers’ salaries
were consolidated by the Ministry of Public Service to include housing
allowance. Selective deduction causes disharmony on the part of those paying
rent, while poor accountability and recording of rent can lead to
misappropriation of these funds.
Maintenance of Police Buildings
Police buildings are very old and in a state of disrepair. No systematic plan was
in place for maintaining the barracks in form of routine, periodic and
emergency maintenance work. The roofs were old, broken and leaking; the
walls had not been painted for several years, the cracks had not been repaired;
the verandas and sub-structure were affected by erosion; doors and windows
vii
vii
were broken; water and sewerage pipes were old and characterised by
leakages, bursts and blockages; electrical installations and systems were
substandard, illegal and dangerous to the people living in the barracks.
This was mainly attributed to lack of clear systems of reporting and handling
repairs, lack of maintenance manuals to guide staff, poor maintenance culture,
and lack of an up-to-date inventory of all UPF buildings showing location, size,
age, and condition. Roof leakages create discomfort to the house occupants,
destroy property, damage roofing timber, weaken the walls and create
dampness in the houses, ultimately weakening the entire building. Asbestos
sheets also pose other health risks like cancer. Exposed verandas create a
conducive atmosphere for water absorption which leads to mould and rot and
rapid deterioration of buildings. Weak and damaged doors and windows
compromise the privacy of the people staying in the barracks and the security
of the property. Poor electrical and water systems contribute to high utility
bills.
Inspection of Barracks Quarters
UPF carries out inspections to ascertain the level of cleanliness, occupants in
the barracks, hygiene, and condition of buildings. It was noted that the UPF
does not have a standard time frame in which these inspections should be
done. As a result, some stations carry out weekly inspections while others carry
it out on a monthly or quarterly basis. Congestion, weak enforcement of rules
and the practice of converting kitchens into accommodation rooms also cause a
strain on achieving the desired objective of keeping the barracks clean at all
times.
The level of cleanliness in the barracks was not satisfactory. Cooking in un-
authorised places, solid waste disposal/management, keeping of poultry and
animals in the barracks were still a big challenge.
Recommendations
Allocation of Accommodation in the Police Barracks
Management should ensure that plans to recruit new officers and transferring
existing staff to other stations is matched with provision of accommodation.
viii
viii
Management should ensure that construction projects are executed according
to agreed plans to avoid delays, cost-overruns and discourage variations as
much as possible, since they partly depict poor planning.
Gazetted Officers staying in the Barracks:
All rent deductions made from the officers should be reconciled and properly
accounted for to avoid loss of funds.
Management should streamline and harmonise the policies regulating the
occupancy of all police houses.
Maintenance of Police Buildings:
Management should assess the benefits of carrying out regular maintenance
against the costs and wastage resulting from inflated utility bills, gross wear
and tear of buildings and costs of entirely losing a building or even loss of lives.
Asbestos sheets should be phased out to reduce the health related risks to
human beings.
Management should institute a clear system of reporting and handling repairs;
further, a system to handle complaints and ensure a follow-up mechanism
should be put in place to monitor, report, assess and carry out repairs in a
timely manner.
Maintenance manuals and/or guidelines should be designed to guide staff
when carrying out maintenance work and ensuring that the minimum
standards of maintenance are achieved.
The UPF management should put in place and regularly update an appropriate
inventory/record of all its institutional buildings, site installations and land with
basic data relating to location, size, age, condition or construction materials
used.
Inspection of Barracks Quarters
The UPF management should establish a standard time frame for inspections
and sensitise all residents in the barracks about the dangers of cooking inside
houses and keeping animals in the barracks.
Efforts should be made to ensure that waste is disposed of properly and as
soon as possible to avoid outbreaks of diseases in the barracks.
1
1
CHAPTER ONE
INTRODUCTION
1.1 Motivation
The welfare of Police officers in the Uganda Police Force (UPF) continues to pose a
challenge. Among the key welfare concerns, is the question of insufficient residential
and office accommodation for the Police staff. For example, a stock of 4360 available
housing units accommodate about 9,331 police officers, representing only 24% of the
entitled officers, at a ratio of 1 house accommodating 2 police officers. In some
barracks, most families are sharing small rooms in housing units, including uniports,
which are in most cases dilapidated. The hygienic conditions in most of the places of
accommodation are deplorable.
The police barracks are characterised by old, faulty water and sewerage systems, and
absence of a systematic garbage disposal mechanism. Old water and sewerage pipes
contribute to huge utility bills through leakages and bursts. Poor electrical installations in
the UPF barracks also escalate utility bills, and accidents through electrocution and
death of people in the barracks.
Government and development partners have increased funds invested in the UPF from
Ug Shs 142 billion (bn) in 2008/09 to Ug Shs 206bn in 2009/10 and 319.4bn in 2010/11.
Of these funds, recurrent budget represented 90% in 2008/09, 82% in 2009/10 and
78% in 2010/11. Specifically, buildings received Ug Shs 3.8bn (2.7%), Ug Shs 6.9bn
(3.3%) and Ug Shs 5.5bn (1.7%) of the total funds for the respective years.
1.2 Description of the Audit area
The Uganda Police Force is established by Article 211(1) of the 1995 Constitution of the
Republic of Uganda under Chapter 12 and Section 2 of the Police Act Cap 303. The
Headquarters are situated at Parliamentary Avenue in Kampala.
Administratively the set up of the police is divided into 17 regions, 122 policing
districts/divisions and 213 stations/barracks. Other barracks not in the regional set up
2
2
include Railways, Fire, Police Training School (PTS) Kampala, PTS Kabalye, Nsambya,
Ntinda, MPPU (Mobile Police Patrol Unit), Naguru, and Kireka.
1.2.1 Statutory Mandate
The Mandate of the Uganda Police as stated in Article 212 (a), (b), (c), (d) of the 1995
Constitution of the Republic of Uganda is to protect life and property, preserve law and
order, prevent and detect crime and to co-operate with the civilian authority and other
security organs established under the Constitution.
1.2.2 Vision, Mission Statement and Major Activities
The Vision, mission, and activities related to accommodation in the Uganda Police Force
are:
Vision
The Vision of Uganda Police Force is re-defined as “a Crime Free Society.”
Mission
“To secure life and property in partnership with the public in a committed and
professional manner in order to promote development.
1.2.3 Major activities of the Directorate of Logistics and Engineering
The Directorate of Logistics and Engineering in Uganda Police Force was created to
perform the following welfare functions:-
Develop effective systems for management of utilities.
Advise on plans for construction and maintenance of UPF infrastructure.
Ensure effective supervision and monitoring for UPF construction projects.
Initiate and develop policies and regulations on the use and maintenance of vehicles
and accommodation for the UPF.
Provide proper accommodation for the personnel in the UPF.
Undertake physical construction and maintenance of UPF buildings.
1.2.4 Organizational Structure
The Police Authority is the top decision and policy organ of the UPF with the Minister for
Internal Affairs as its chairperson. Other members of the Authority include the Attorney
General, Inspector General of Police (IGP), Deputy Inspector General of Police (D/IGP),
3
3
Permanent Secretary Ministry of Public Service, a senior officer in charge of
Administration at UPF headquarters and three other persons appointed by the President.
Below the Authority is a team of top management charged with day to day management
of the UPF headed by the IGP who is the Chief Executive of the organization.
Specifically, the Department of Engineering in the Directorate of Logistics and
Engineering is headed by a Commissioner of Police who reports to the Deputy Director
(at the rank of Senior Commissioner of Police) and the Director Logistics and
Engineering (at the rank of Assistant Inspector General of Police). An organization chart
showing the above relationships is attached as Appendix (i).
1.2.5 Funding of the Police Force
The activities and operations of UPF are funded by the Government of Uganda and
development partners. From FY 2008/09 to 2010/11, Ug Shs. 678.1 billion was released
to the force as summarized in the table below.
Table 1: UPF Funding for the period 2008/09 to 2010/11.
Financial Year 2008/09
(Ug Shs in bn)
2009/10
(Ug Shs in bn)
2010/11
(Ug Shs in bn)
Recurrent 132.8 174.1 250.6
Development 14.1 37.7 68.8
Total Funding 146.9 211.8 319.4
Source: UPF audited Accounts FY 2008/09, 2009/10 and 2010/11.
1.3 Audit Objectives
The overall objective of the audit was to assess UPF’s efforts in implementing policies,
programmes and strategies aimed at improving accommodation in the UPF.
The specific objectives included:
To establish whether entitled police officers are provided with accommodation.
To ascertain whether the police stations and barracks are regularly maintained and
properly furnished.
To verify whether the barracks are subjected to regular inspections and kept clean
at all times.
4
4
1.4 Audit Scope
The audit was conducted at Uganda Police Force Headquarters and covered Police
stations in the four regions of Uganda. The study covered three financial years from July
2008 to June 2011.
5
5
CHAPTER TWO
METHODOLOGY
The audit was conducted in accordance with International Organization of Supreme
Audit Institutions (INTOSAI) Auditing Standards and OAG VFM Audit Manual. Those
Standards require that a VFM audit should be planned in a manner which ensures that
an audit of high quality is carried out in an economic, efficient and effective way and in
a timely manner. In collecting data from the field, the team reviewed documents,
carried out interviews and physical inspection/observation of the facilities.
2.1 Sampling
Stratified sampling was used to select the regions: Northern, Central, Eastern and
Western. From these regions, simple random sampling was used to select specific
stations as follows: Arua and Gulu in Northern region; Kampala, Mityana, and Luwero in
Central region; Tororo and Jinja in Eastern region; and Masindi and Bushenyi in Western
region.
2.2 Document Review
The team obtained and reviewed documents to obtain information relating to financing,
mandate, planned construction/maintenance outputs, the police strength, and progress
reports of works on the various construction and maintenance projects. Correspondence
on fire reports, barracks allocation/accommodation, rent deductions,
construction/maintenance contracts were also reviewed. The team also reviewed
registers of residents and population at the specific barracks. A list of documents
reviewed is attached as Appendix (ii).
2.3 Interviews
The team conducted interviews at Police headquarters, Kampala Metropolitan (Ntinda
and Nsambya barracks), Arua, Gulu, Mityana, Luwero, Tororo, Jinja, Masindi and
Bushenyi barracks/stations in order to establish: the allocation of accommodation to
police officers, reporting and execution of maintenance work, staff numbers in the
barracks, and the accommodation challenges experienced. Interviews were conducted
6
6
with officers at UPF headquarters and upcountry police stations as shown in Appendix
(iii).
2.4 Observation/Field Inspections
Field visits were carried out in Kampala Metropolitan (Ntinda and Nsambya barracks),
Arua, Gulu, Mityana, Luwero, Tororo, Jinja, Masindi and Bushenyi barracks to ascertain:
the state, and extent of damage on residential facilities in the barracks, garbage disposal
management in the barracks, and the state of office equipment, furniture and utilities
provided by the Uganda Police Force.
7
7
CHAPTER THREE
SYSTEMS AND PROCESSES DESCRIPTION
3.1 Roles and Responsibilities of Key Players
3.1.1 The Police Authority
This is the supreme governing body of the UPF chaired by the Minister of Internal Affairs
and consists of the following members: the Attorney General, the Inspector General of
Police, the Deputy Inspector General of Police, a senior officer in charge of
administration at the UPF Headquarters and three other persons appointed by the
President. The Authority plays two major roles of advising the Government on policy
matters relating to the management, development and administration of the Police
Force; and also advising the President on the appointment of the top managers of the
force.
3.1.2 The Police Council
This is the second top most governing body of the UPF chaired by the Inspector General
of Police and consists of the Deputy IGP, Directors, the Regional and Extra Regional
Police Commanders and officers at headquarters of the force responsible for finance
operations, human resource management, human resource development, community
affairs, policy research and planning, inspectorate, legal affairs, traffic and road safety,
communications, force transport, logistics and supplies, force estates, medical services,
operations, mobile police patrol unit, private security organisations, non-human
resource, firearms, criminal investigations administration, identification bureau, collation,
production and private security. The Police Council, among other functions, is
responsible for recommending to the Public Service Commission the recruitment,
appointment and promotion of police officers up to the rank of inspector of police and
may appoint a committee from among its members to assist it in the performance of its
functions under this section and may assign to it such functions subject to such
conditions and restrictions as the minister may deem fit.
8
8
3.1.3 Ministry of Internal Affairs
This is the mother ministry of the UPF and is charged with policy and oversight matters.
The Minister responsible for Internal Affairs chairs the Police Authority, which is the
Supreme governing body of the UPF.
3.1.4 Inspector General of Police
The IGP is responsible for development, implementation, coordination, monitoring and
evaluation of security policies and strategies of the Uganda Police Force to ensure crime
prevention, protection of life and property of citizens and enforcement of law and order.
3.1.5 Deputy Inspector General of Police
The officer is charged with the coordination, management and guidance of police
inspection, finance and office support services to enable the institution to execute its
mandate.
3.1.6 Under Secretary
He/she reports to the Deputy Inspector General of Police and his/her role is to provide
financial support, office supplies and support services to all operational areas of the
Police Force to enable them to achieve their objectives and mandates.
3.1.7 Director Logistics and Engineering
Advises management on effective approaches to logistics, estates and Force transport
management. Develops effective systems for the management of utilities, and
supervises the construction projects in the UPF. The Director also advises on plans for
construction and maintenance of UPF infrastructure.
3.1.8 Justice Law and Order Sector (JLOS)
The Justice Law and Order Sector (JLOS), through a sector wide approach, brings
together the government ministries and departments involved in the justice system, like:
the Ministry of Justice and Constitutional Affairs, Ministry of Internal Affairs, Judiciary,
Uganda Police Force, Uganda Prisons Service, Judicial Service Commission, Uganda Law
Reform Commission and Directorate of Public Prosecution.
9
9
3.1.9 Communities and Local Councils
The police work in partnership with Local Councils and communities to establish some
police units where there is demand for their services. They donate land, provide office
space or residential accommodation and also rent their buildings to the UPF.
3.1.10 Commissioner Barracks Administration
The Commissioner barracks administration is supposed to develop plans, policies and
strategies for effective police barracks administration; coordinate and manage the
operations of the barracks of the Uganda Police Force; and update and keep records of
all residents in a barracks. He/she is also required to offer technical advice on matters
relating to barracks administration; ensure proper and clean environment within the
barracks and the surrounding areas; promote good welfare for the residents of the
barracks; mobilize and sensitize residents about good principles of habitation; and
discipline officers or residents who commit minor crimes and break society norms in the
barracks.
The commissioner prepares work plans and budgets for the barracks administration and
forwards them to relevant authorities.
3.2 Process Description
3.2.1 Accommodation Process
After recruitment and eventual deployment, police officers below the rank of Assistant
Superintendent of Police are entitled to accommodation of a two or three roomed
housing unit, depending on rank. The allocation of housing units is a responsibility of the
Barracks Commandant or any other police staff of the same capacity in the police
barracks.
Gazetted officers above the rank of ASP and children above 18 years are not supposed
to be accommodated in the barracks.
3.2.2 Maintenance Process
The UPF has permanent and temporary buildings. Temporary houses include uniports,
dormitories, and mud and wattle buildings.
10
10
The normal maintenance of all permanent buildings is the responsibility of the Police
Construction Unit. This includes repairs to barracks quarters necessitated by normal
wear and tear. Unit commanders are supposed to regularly inspect all buildings for
which they are responsible and submit necessary requisitions for repairs and
maintenance to their local police construction representative.
Unit commanders will address requests for repairs of any temporary buildings in their
command to their regional commander who will, if necessary, refer the matter to the
IGP.
All barracks quarters will be kept clean at all times and will be subjected to frequent
inspections, with specific attention to cooking places and the keeping of poultry and
animals in the barracks.
11
11
CHAPTER FOUR
FINDINGS CONCLUSIONS AND RECOMMENDATIONS
4.1 Allocation of Accommodation in the Police Barracks
According to the Uganda Police Standing orders, police officers below the rank of
Assistant Superintendent of Police are entitled to accommodation.
A review of the summary of barracks data from the Department of Barracks
Administration revealed that of the 38,460 police officers entitled to accommodation,
only 9,331, representing 24% were provided with accommodation. The analysis of those
provided with accommodation also indicated that the number of housing units was not
matched with the number of police officers in the respective stations. Only 4,503
housing units were available for those officers to share at a ratio of 1 house to 2
officers. A summary of staff against available housing units is shown in figure 1 below.
Source: OAG analysis of data from UPF Barracks Administration Department.
In extreme cases, we noted that some female police officers in Arua and Ntinda were
sharing accommodation with male colleagues in the same house. In some of the
stations, like Nsambya, Ntinda, Tororo and Masindi, kitchens had been converted into
accommodation units and allocated to police officers for accommodation.
12
12
It was noted that the inadequate provision of accommodation was attributed to a
number of causes as explained in the following paragraphs 4.1.1 to 4.1.3:
4.1.1 Standard of Workmanship of some Construction Projects
To alleviate the problem of accommodation and given that uniports were considered to
be more expensive, management constructed dormitories (commonly known as Kibati),
each to accommodate on average 40 policemen on assignments like Public Order
Management and accommodation of newly trained officers. A number of these
structures were built by the Estates Department while others were awarded to
contractors. This was planned to be a temporary arrangement to accommodate officers
in Kampala metropolitan and Entebbe areas. The temporary structures were built at a
cost of Ug Shs 13m each, while semi-permanent (meant to last up to 3 years) cost 30m
each. These have continued to be used even after their planned life span, to
accommodate the increasing numbers of police officers and the continued Public Order
Management activities, especially in Kampala metropolitan area.
We noted, however, that the workmanship on these structures was poor. The slabs for
some of the units constructed were substandard, with exposed aggregate stones
(Picture 1) while others were made of poor quality materials like timber and iron sheets.
Some of the structures built in Ntinda barracks were not occupied because the storm
water flows in the dormitories rendering them unfit for human habitation - Picture 2).
Picture 1: Mattresses on the floor in Ntinda barracks. OAG photo taken on 24th October 2011 at 2.47pm.
Picture 2: Storm Water inside the dormitory in Ntinda barracks. OAG photo taken on 24th October 2011 at 2.37pm.
13
13
In Nsambya barracks where 7 semi-permanent structures were constructed in 2007, site
inspection on 2 of the sites revealed that one of the structures had been completely
brought down by the wind leaving only a poorly constructed slab (Picture 3) while
another one at the same site had also been badly damaged by wind. It also had a poor
slab and weak eucalyptus poles and iron sheets (Picture 4). In total, 4 structures worth
Ug Shs 52m in Nsambya were not occupied. Management explained that the units were
part of the contract worth Ug Shs. 149.8m which were not accepted by UPF. The
contractor was not paid and money was returned to the Consolidated fund.
Picture 3: Slab where a dormitory had been constructed but completely blow away by wind. OAG photo taken on 27th October 2011 at 3.25pm.
Picture 4: Poorly constructed dormitory destroyed by wind. OAG photo taken on 27th October 2011 at 3.27pm.
4.1.2 Failure to Match Recruitment and transfer of staff with housing requirements
The UPF is supposed to recruit 4,000 police officers annually to meet the International
target of 1 police officer to 500 people and address the shortfall which currently stands
at a ratio of 1:1,786.1 The need for growth is also dictated by the creation of new
districts in the country and requests for police services. Interviews with management
revealed that recruitment is not matched with the rate of house construction but is
instead dictated by the available resource envelope.
1 Justice Law and Order Sector Annual Performance Report 2009/10 – page 28
14
14
It was also noted that the practice by staff transferred to other stations of leaving their
families in the barracks also creates shortage of accommodation in the barracks since
they practically occupy two houses in different stations.
4.1.3 Delayed Construction Works
It was also noted that delays in completion of projects, cost overruns and variations
some of them not authorised, erode the available resources meant for construction work
and impair the achievement of construction targets.
Management explained that the delayed completion of construction projects was
attributed to poor roads, especially in Northern and Eastern Uganda; land disputes; and
long bureaucratic payment system, involving several stakeholders and variations,
especially in renovation work, which have to be approved by the contracts committee.
Supply of 847 Uniports A contract for the supply of 847 uniports cost the UPF Ug
Shs 503.8m. Inspection of Lira, Arua and Kapchorwa revealed that the uniport materials
which were meant for outposts mainly at sub-counties were delivered at the main
stations. To-date, these uniports are still kept in the compound of the respective stations
and exposed to extreme weather conditions for over 1½ years. (Pictures 5 and 6).
Picture 5: Materials for 35 uniports in Arua Police Station meant for 7 outposts not yet delivered. OAG photo taken on 1st November 2011 at 11.34am.
Picture 6: Materials for uniports in Lira barracks. OAG photo taken on 27th July 2011 at 3.06pm.
15
15
It will now cost Ug Shs 719.95m to erect these uniports instead of Ug Shs 423.5m when
they were delivered (as it currently requires Ug Shs 850,000 to erect 1 uniport
compared to Ug Shs 500,000 required at the time of delivery). This implies that delays
in delivery and installation of uniports will translate into an additional cost of Ug Shs
296.45m.
It was also noted that uniports have become relatively more expensive over the years.
While uniports used to cost a total of Ug Shs 2.50m, including installation/erection costs,
1½ years ago, it now requires Ug Shs 4.35m to put up a uniport of the same size and
quality. Besides, uniports may not be the best option to alleviate accommodation
problems as they are uncomfortable to stay in, as they are either too hot during a sunny
period or too cold during a rainy season.
Renovation of Gulu Barracks
The renovation of Gulu barracks which was to cost Ug Shs 497.62m, commenced in
October 2010 and was to be completed in March 2011. By the time of the audit
(December 2011), a total of Ug Shs 258.81m had been paid to the contractor. The
completion has been delayed by over 7 months. At the time of inspection, the contractor
had not been on site for over 4 months. We also observed that some of the work
completed, like verandahs, had started cracking, as shown in picture 7 below.
Management has extended the Letter of Credit (LC) more than 3 times and paid the
extension charges.
Picture 7: One of the cracks on the veranda of one of the renovated houses. OAG photo taken on 2nd July
16
16
2011 at 9.38am.
Management Response
When works had just started there arose a need for change in the scope of
works which necessitated a change in the bills of quantities and hence the
requirement to get approval from the contracts committee. This had to take
some time before approval.
At the time of the inspection, the contractor was not on site while awaiting
approval of the variations but these have been approved and the works
resumed.
Renovation of Lira Barracks
The renovation of Lira barracks commenced in October 2010 and was to take 6 months
at a cost of Ug Shs 551.63m. To-date, the completion has delayed by 8 months. At the
time of audit (December 2011), the work had stalled and the contractor had abandoned
the site because the company had internal problems. The UPF management informed us
that the police legal department has taken over the case with the view of terminating
the contract. The delays, termination process and re-tendering is likely to increase the
cost far above the initial cost of Ug Shs 551.63m. Already, the UPF management has
had to extend the LC and pay the attendant LC management costs more than 3 times.
Management response
The contractor resumed the works recently and work is scheduled to be
completed by the end of January 2012 without any variations arising out of
delayed completion by the contractor.
Through interviews, it was noted that lack of accommodation has led to lack of privacy,
promiscuity, defilement, misunderstandings between the different families, and thefts.
The HIV/AIDS policy has also recognized the challenges of accommodation in the police
as one of the factors contributing to the spread of HIV/AIDS.
Failure to provide accommodation has led to the construction of un-planned structures
by individual police officers in barracks (commonly known as self-help as shown in
Pictures 8 and 9). Some police officers having been transferred, rent them out or in
some cases ask for compensation for their effort.
17
17
Picture 8: Self-help houses in Luwero. OAG photo taken on 31st October 2011 at 10.33am.
Picture 9: Some of the “Self-help” latrines in Ntinda barracks. OAG photo taken on 24th October 2011 at 1.09pm.
Recruiting officers without corresponding provision of accommodation deprives the
officers of their right to accommodation and demoralises them. It also worsens the
already acute accommodation challenge in the UPF.
Management Response
Management further explained that in order to improve its operational
effectiveness, and upgrade the working and residential accommodation;
training facilities and other services; plans are underway to construct 7,300
police barracks and 24 police stations in 13 divisions of the Kampala
metropolitan area and a Police Training College in Kabalye, Masindi district
under the Public Private Partnership (PPP) arrangement in a period of three
years, where a private investor will design, finance, build and provide vital
maintenance of buildings. The signing of this agreement is expected to take
place in April 2012.
Another intervention the UPF management has taken to increase
accommodation in the UPF is through the Hydra-Form project where a total of
32 housing units and 4 police stations were constructed in Panyandoli
(Kiryandongo District), Nebbi and Kitgum in 2011 alone, while another 8
housing units and 5 police stations will be completed in 2012 in Busia, Nyero
(Kumi District), Kapeeka (Nakaseke District), Maracha, Awach (Gulu District)
and Sheema.
18
18
Picture 10: One of the housing units built under the Hydra-Form in Kitgum. UPF courtesy photo.
Future plans under the Hyrda-Form project will include construction of more
accommodation blocks and police posts in Lamo, Maracha, Arua, Nyero,
Busia, Butaleja, Zombo, Sironko, Pakwach, Kamdini, Otuboi and the armory at
the Police Training School, Kabalye.
The implementation of this initiative, however, is hampered by lack of
adequate equipment, like excavators, mixers, vibrators, water tank vehicles,
water pumps, mobile generators for welding, lighting systems and mounted
trucks. The UPF also has challenges of inadequate skilled manpower,
bureaucracy in the procurement process, lack of timely supervision, price
fluctuations of construction materials and inadequate funds.
Conclusion
Absence of a workable plan to match the accommodation facilities with the growing
police staff numbers has deprived entitled police officers of decent accommodation thus
posing a challenge to the welfare and motivation of the force.
Failure by the UPF to ensure standard construction works by contractors on the various
police housing projects like Kibati dormitories and fully implementing the housing
19
19
interventions like uniport installation has greatly and will continue to aggravate the
accommodation problem.
Recommendation
Management should ensure that plans to recruit new officers and transferring existing
staff to other stations is matched with provision of accommodation.
Management should ensure that construction projects are executed according to agreed
plans to avoid delays, cost-overruns and discourage variations as much as possible since
they partly depict poor planning.
4.2 Gazetted Officers Staying in the Barracks
All officers of and above the rank of Assistant Superintendant of Police are not supposed
to stay in the barracks. However, Paragraph 67(a) of Chapter 9 of the Police Standing
Orders requires such officers to be charged rent at laid down public service standing
orders. Occupancy of any Government housing shall be governed by a tenancy
agreement between the two parties detailing the terms and conditions of the tenancy.2
During audit, we found that there were gazetted officers of and above the rank of
Assistant Inspectors staying in the barracks and efforts by management to evict them
have been futile. Figure 2 below shows the number of gazetted officers staying in the
barracks in the respective stations.
Management indicated that they had taken measures to evict the officers from the
barracks as directed by the Police Council in October 2006. The eviction exercise was,
2 The Uganda Public Services Standing Orders (H-b) (1)
20
20
however, rejected by the officers who instead opted to take the case to the Uganda
Human Rights Commission (UHRC) court arguing that their human rights had been
violated. The case was concluded in favour of UPF.
Regarding the payment of rent, management was deducting rent for the period under
review at the rate of 15% of the basic salary.
Management indicated that from 2003 to 2009 when the Police Council resolved to stop
deductions, Ug Shs 1.08bn had been collected as rent from the officers residing in the
barracks and out of this amount, Ug Shs 778.8m had been utilised to procure and install
uniports.
Evidence obtained during audit, however, indicated that to-date, recoveries of rent were
still being effected from some of the officers, more than 2 years after the Police Council
directive. It was noted, however, that the deduction policy is not applied consistently as
deductions were not being made from all the gazetted officers staying in the barracks.
The money was banked on the general expenditure account without ledgers of income
of expenditure for the rent received, making it difficult to account and verify such
transactions.
This is caused by conflicting guidelines regarding gazetted officers staying out of the
barracks, requiring them to sign tenancy agreements or a Memorandum of
understanding and pay rent and at the same time allowing officers on operation
command to stay in the barracks.
Allowing gazetted officers to stay in the barracks deprives entitled police officers of
accommodation. Furthermore, failure by gazetted officers to pay rent denies the UPF
rental income. Selective deduction causes disharmony on the part of those paying rent,
while poor accountability and recording of rent can lead to misappropriation of these
funds.
Conclusion
Gazetted officers were staying in the barracks without paying rent further increasing the
challenge of inadequate accommodation in the UPF. Rent deducted is not properly
21
21
accounted for as required by the Public Service Standing Orders and the Treasury
Accounting Instructions.
Recommendation
Management should ensure that the recommendations of the Police Council and the
UHRC court ruling are implemented so as to provide more accommodation space for
the entitled policemen.
All rental deductions made should be reconciled and properly accounted for to avoid
loss of funds.
Management should streamline and harmonise policies regulating occupancy of all
police houses and properly invest rental income from police houses.
4.3 Maintenance of Police Buildings
The normal maintenance of all permanent buildings in the Force is the responsibility of
the Police Construction Unit. This includes repairs to barracks quarters necessitated by
wear and tear. 3 Unit commanders should address requests for repairs of any temporary
buildings in their command to their regional commander who will if necessary refer the
matter to the IGP.
Most of the police buildings were built during the colonial period (between 1920’s and
1960’s) and are very old and in a state of disrepair. There is no systematic plan for
maintaining the housing units in the police stations and the barracks in form of routine,
periodic and emergency maintenance work. The Directorate of Logistics and Engineering
does not carry out the maintenance of buildings. The interviews conducted revealed that
even when requests are sent to the Directorate, they are not honoured. Individual
officers carry out repairs that they can afford and the repair of offices is neglected.
During audit, attention was given to maintenance issues related to roofing, walling, and
veranda, doors/windows, water and sewerage systems and electrical installations as
summarised below:
3 Uganda Uganda Police Standing Orders 7th Edition Volume 1 Chapter 10(33).
22
22
4.3.1 Roofing
Most of the houses in 6 of the 8 areas inspected are roofed with asbestos sheets. We
observed that the roofs were old, broken and leaking. The occupants of these houses
were improvising by using polythene sheets or supporting them in place with stones or
old car tyres (picture 11). This poses another risk of accidents in case these stones fall.
Concrete ceilings in Arua, Nsambya and Ntinda barracks had cracks and were leaking
(Picture 12).
Picture 11: Stones holding the roof of one of the houses in Tororo barracks. OAG photo taken on 3rd November 2011 at 9.33am.
Picture 12: Roof in Arua barracks. OAG photo taken 1st November 2011 at 11.36am.
The World Health Organisation (WHO) estimates indicate that more than 107,000
people die each year from asbestos related lung cancer and other diseases because of
continued exposure to asbestos both at work and at home (all forms of asbestos are
carcinogenic to humans with potential of causing mesothelioma and cancer of the lungs,
larynx and ovary)4. Continued leakage of houses creates discomfort to the occupants,
destroys property, damages roofing timber, weakens the walls and creates dampness in
the houses, ultimately weakening the entire building.
4.3.2 Walling
The walls of the houses in the barracks and some of the office buildings were poorly
maintained. The stations had not been painted for several years. There was no effort
made to have the cracks repaired, some of which were 3cm wide, rendering the houses
4 World Health Organisation – Media Centre (http//www.who.int/mediacentre/factsheets/).
23
23
unsuitable for human habitation yet people were still occupying such houses as shown in
Pictures 13 and 14.
Picture 13: Cracks in one of the houses in Bushenyi. OAG photo taken on 4th November 2011 at 1.23pm.
Picture 14: Cracks and worn-out plaster on one of the houses in Luwero 31st October 2011 at 10.26am.
4.3.3 Verandas and Substructure
The verandas and the sub-structures were worn out and exposed leaving some of the
houses “hanging”. The soils had been washed away by continued erosion and failure to
control storm water as shown in Picture 15.
24
24
Picture 15: One of the hanging verandas in Fort-Portal barracks. OAG photo taken on 1st August 2011 at 5.13pm.
Exposed verandas create a conducive atmosphere for water absorption which leads to
mould and rot and rapid deterioration of buildings.
4.3.4 Doors and Windows
All barracks and offices inspected revealed that windows and doors were old and not
maintained. Window panes were broken while wooden doors and windows had rotted
away (Picture 16 and 17) or were badly damaged by termites.
Picture 16: Rotten windows in Arua barracks. OAG photo taken on 1st November 2011 at 11.48am.
Picture 17: Broken door at Bushenyi Police block. OAG photo taken on 4th November at 1.04pm.
Weak and damaged doors and windows compromise the privacy of people staying in the
barracks and the security of the property.
4.3.5 Water and Sewerage Systems
The water, plumbing and sewerage systems were laid over 50 years ago. The water
pipes were leaking, and the sewerage pipes were blocked leading to overflow of
sewerage (pictures 18 and 19).
25
25
Picture 18: Overflowing sewerage in Ntinda barracks. OAG Photo taken on 24th October 2011 at 2:06pm.
Picture 19: Leakage of water in Nsambya barracks. OAG photo taken on 27th October 2011 at 3:59pm.
In some cases, it was noted that sewerage systems were blocked (pictures 20 and 21)
due to poor disposal methods of waste disposal like throwing of polythene bags, sanitary
pads and failure to use soft tissues like toilet paper. There was no evidence that
management was paying attention to the leakages and blockages.
Picture 20: Blocked sewerage system in Tororo barracks. OAG photo taken on 3rd November 2011 at 9.45am.
Picture 21: Blocked sewerage system in Nsambya
barracks plastic materials OAG photo taken on 27th October 2011 at 3.58pm.
It was also evident that response time to address faults was too long. In Nsambya
barracks, for example, it had taken the Estates Department more than a year to fix a
burst on a 3 inch pipe on the Gaaba road main reservoir tank serving the entire
barracks. At the time of inspection, the leakage had not been repaired. Management
26
26
explained that delays were due to lack of the necessary materials, like pipes, to address
such repairs as and when they occur. Repair materials have to be requisitioned and
purchased from the open market.
Officers at the stations attributed the delays and failure to address maintenance and
repair work to lack of facilitation, as each station receives only Ug Shs 0.8m quarterly to
handle all office operations. Poorly maintained water and sewerage pipes lead to
wastage of water which translates into increased water bills and contamination.
4.3.6 Electrical Installations
The electrical installations and wiring system in the barracks inspected was sub-standard
and, in some cases, individual occupants illegally connected electricity from one house
to another without regard to safety measures. Some of the wires were not insulated,
while others were covered with polythene sheets. Other live wires were exposed and too
close to entrances or on metallic uniports as shown in picture 22 and 23.
Picture 22: Exposed electrical wires in Masindi barracks. OAG Photo taken on 31st October 2011 at 3:47pm.
Picture 23: Uniport with exposed electrical wires in Tororo barracks. OAG photo taken on 3rd November 2011 at 9:54am.
The current electrical wiring in the UPF also exposes the occupants of these houses to
the risk of electrocution. In one of the uniports in Nsambya barracks, for example, a
child and the mother were electrocuted in 2008 and the child died as a result. Another
child was also electrocuted and died in October 2009 in Tororo barracks.
27
27
Poorly connected electrical installations and old electric wires cause much resistance and
energy loss, consequently leading to increased electricity bills.
4.3.7 Other Maintenance Works - Overhaul of Tororo Water and Sewerage Systems
The renovation of Tororo water and sewerage systems commenced in October 2011 at a
cost of Ug Shs 312.83m. The project was expected to take a period of 7 months and the
scope of works was to repair works on 12 existing structures, plumbing and sanitary
works and construction of 2 septic tanks. The inspection carried out at Tororo barracks
revealed that the old sewerage pipes were removed by the contractor but not replaced.
There was no evidence that the old water system was overhauled. Instead new toilets
which were not part of the initial agreement were constructed leaving the old ones
incomplete (Picture 24). The new ones did not cover the entire barracks where the old
pipes were removed. We also observed that the toilets were blocked or the PVC pipes
were broken and leaking.
Picture 24: Old Sewerage pipes that were removed but not replaced in Tororo barracks. OAG photo taken on 3rd November 2011 at 10.05am.
Management indicated that inadequate provision of the funds required for repair and
maintenance works is the major reason for the backlog in the maintenance of police
buildings.
28
28
We also noted that the Estates Department does not have staff at the barracks and at
the regional level to carry out routine inspection, receive and handle complaints, carry
out assessments and repair work at the barracks or at the regional level as and when
reported.
There was no maintenance manual to guide staff in their work and no master plan
showing overall maintenance requirements. We also noted that where works are
undertaken, projects are characterized by delays and cost overruns.
The poor maintenance culture in the UPF also contributes to the poor state of the
buildings in the barracks and offices. Simple tasks like removing plants from the walls
and roofs of buildings which may not require any money were not being done. This
leads to cracks in the walls or rotting of buildings (pictures 25 and 26).
Picture 25: Plants growing on the wall of one of the flats in Nsambya police barracks. Photo taken by OAG.
Picture 26: Plants growing on one of the buildings in
Masindi barracks. Photo taken by OAG.
UPF does not have an up-to-date register of its housing stock in the country. Planning
for maintenance without an accurate account of all buildings, their location, age or
condition becomes difficult.
Management Response
In the past three financial years, UPF has carried out maintenance projects
worth Shs 2.99bn as shown in Table 2 below. Funds permitting, UPF plans to
overhaul, on a case by case basis, a particular barracks where the roofs will
29
29
be replaced and painting done to create a more visible impact rather than
spreading of the little resources over a wider area.
Table 2: UPF Renovation work for the period 2008/09 to 2010/11.
Financial Year Project Name Amount (Shs)
2008/09 Old Kampala Police Barracks 250.0m
Iganga Barracks 200.0m
2009/10 Mubende Police Barracks 250.0m
Atyak Police Barracks 192.8m
2010/11 Nsambya Barracks (Maternity) 74.4m
Lira Police Barracks 551.6m
Gulu Police Barracks 478.9m
Mechanical Workshop Kampala 486.2m
Nsambya Police Canteen 289.7m
Naguru Armory 211.4m
Total 2,985m
Source: UPF Management
However some of the buildings in Naguru, Ntinda, Nsambya, Jinja, Mbale,
Masaka, Mbarara, Tororo, Lira and Gulu were built between 1928 to 1962 and
are beyond renovation.
Conclusion
Absence of a maintenance policy has greatly contributed to the accommodation problem
where the few available housing units have not been maintained at all leading to their
deterioration in quality and in some cases total collapse.
Recommendation
Management should assess the benefits of carrying out regular maintenance against
the costs and wastage resulting from inflated utility bills, gross wear and tear of
buildings and costs of entirely losing a building or even loss of lives.
Asbestos sheets should be phased out to reduce the health related risks on human
beings.
30
30
Management should institute a clear system of reporting and handling of repairs to
handle complaints and ensuring that a follow-up mechanism is put in place to
monitor, report, assess and carry out repairs in a timely manner.
Manuals and or maintenance guidelines should be designed to guide staff when
carrying out maintenance work and ensuring that the minimum standards of
maintenance are achieved.
UPF management should put in place and regularly update an appropriate
inventory/record of all institutional buildings, site installations and land making up
their building stock with basic data relating to location, size, age, condition or
construction materials used.
4.4 Inspection of Barracks Quarters
All barracks quarters should be kept clean at all times and should be subjected to
frequent inspections. The lighting of fires and cooking of food should be in specially
constructed places. Poultry may not be kept in Police barracks unless properly penned
in enclosures which should be out of sight, and at the back of the barracks and in an
area approved by the unit commander. No other animals will be kept in any police
barracks.5
In all the barracks visited, we noted that UPF carried out inspections to ascertain the
level of cleanliness, occupants in the barracks, hygiene, condition of building and to
settle misunderstandings and domestic quarrels. However, there was no standard time
frame or reporting requirements as to when the exercise should be carried out. While
UPF carried out weekly inspections in 80% of the stations visited, 14% of the stations
were inspected on a monthly basis while 6% were being inspected on a quarterly basis.
The inspections carried out during audit revealed that the level of cleanliness in the
barracks was not satisfactory. Cooking in un-authorised places, management of
wastewater, solid waste disposal/management, keeping of poultry and animals in the
barracks were still a big challenge.
5 Uganda Police Standing Orders 7th Edition Volume 1 Chapter 10 (41) (a) and (c).
31
31
4.4.1 Cooking in Unauthorised Places
Inspections revealed that some of the officers were cooking inside the dormitories
instead of the designated kitchen/cooking areas as shown in Picture 27 below.
Picture 27: Cooking in one of the dormitories in Ntinda police Barracks. OAG Photo taken on 12 October
2011 at 3.25pm.
Electrical coils and charcoal stoves were being used inside their houses or on verandas
and not in the designated cooking areas/kitchens. The charcoal stoves generate much
soot which soils the walls and the entire house.
We noted that officers partition dormitories with cardboards, ply-wood and paper
packaging material for privacy. These initiatives increase the risk of fire in the barracks
and risk the lives of the people. In Ntinda barracks, one of the dormitories was burnt
down in June 2010 where a 2 year old child died in the inferno and property of 14
families were destroyed, while another house in Nsambya also caught fire in November
2008 destroying household items, cash and documents for 7 families. These losses could
have been minimized if there was no congestion.
4.4.2 Solid Waste Disposal
Disposal of garbage in the barracks has had challenges. In some of the stations
inspected, heaps of decomposing garbage were stretching to verandahs or very close to
entrances with a foul smell and attracting flies. Some of the heaps had stayed for more
32
32
than 5 years, creating huge mounds. (Pictures 28 and 29). While the respective urban
Councils were facilitating the collection of solid waste from the barracks in upcountry
stations, UPF trucks were responsible for the Kampala Metropolitan area. The trucks
were characterized by frequent breakdown or lacked fuel to take the garbage to the
dumping site.
Picture 28: Solid Waste in Ntinda barracks. OAG Photo taken on 24th October 2011 at 1.28pm.
Picture 29 Solid Waste in Arua barracks. OAG Photo taken on 1st November 2011 at 11.51am.
Poor waste management and disposal also exposes the residents to water-borne
diseases and also harbours vectors/rodents that transmit diseases to humans like flies,
mosquitoes and rats.
4.4.3 Keeping of Poultry and Animals in the Barracks
We established that police officers were keeping poultry in all the stations visited
including chicken, ducks and turkeys and these were not being kept in special penned
houses, but left to move freely in the barracks as shown in pictures 30 and 31.
33
33
Picture 30: Turkeys in Ntinda barracks. OAG photo taken on 24th October 2011 at 12.53pm.
Picture 31: Ducks and Chicken in Arua barracks. OAG photo taken on 1st November 2011 at 11.51am.
The rearing of animals like goats, sheep, dogs, and, to a small extent, cows, was also
practised (pictures 32 and 33). Some of the goats were tied near houses or the
verandas.
Picture 32: One of the cows in Tororo barracks. OAG photo taken on 3rd November 2011 at 10.38am.
Picture 33: Goats in Nsambya barracks. OAG photo taken on 27th October 2011 at 4.04pm.
Management explained that animals were reared in the barracks by individuals or at
communal level to boost their livelihoods and supplement their household incomes. In
some cases, these animals were reared on the pretext that they were in transit or meant
to be slaughtered during festive days.
34
34
Free range rearing of poultry and animals can also be a potential source of diseases in
the barracks, generate misunderstandings amongst neighbours, especially where these
animals cross compound boundaries, thus exacerbating the already existing congestion
in the barracks. Animals are also a source of wear and tear of buildings as they tend to
scratch the walls and floors in search of shelter or insects.
Conclusion
Inspection of barracks in the UPF has not achieved the intended purpose. Rearing of
poultry, keeping of animals and cooking in unauthorised places in the barracks continue
to take place. The objective of ensuring that the premises are kept clean at all times has
not been achieved.
Recommendation
The UPF management should establish a standard time frame for inspections and
sensitise all residents in the barracks about the dangers of cooking inside houses
and keeping of animals in the barracks.
Efforts should be made to ensure that waste is disposed of properly as soon as
possible to avoid outbreak of diseases in the barracks.
John F. S. Muwanga AUDITOR GENERAL
KAMPALA
27th February, 2012
35
35
GLOSSARY OF TERMS:
Term Definition
Asbestos: The term asbestos designates a group of naturally occurring
fibrous minerals with current or historical commercial usefulness
due to their extraordinary tensile strength, poor heat conduction,
and relative resistance to chemical attack.
Barracks A building or group of buildings where members of the police
force live.
1
APPENDIX (i) UPF ORGANISATION STRUCTURE
Police Council
IGP
Deputy IGP
Poli
tica
l C
om
mis
sar
Dir
ecto
r of
Info
rmat
ion a
nd
Com
munic
atio
ns
Tec
hnolo
gy
Dir
ecto
r H
um
an R
esourc
e
Dev
elopm
ent
and
Man
agem
ent
Dir
ecto
r C
ID
Dir
ecto
r C
ounte
r T
erro
rism
Dir
ecto
r of
Oper
atio
ns
Dir
ecto
r L
ogis
tics
and
Engin
eeri
ng
Dir
ecto
r R
esea
rch,
Pla
nnin
g a
nd D
evel
opm
ent
Dir
ecto
r In
terp
ol
and P
eace
Su
pport
Oper
atio
ns
Dir
ecto
r P
oli
ce O
per
atio
ns
Inspectorate Department
Finance and Office Support Services
Professional Standards Unit
Legal Services Public Relations /Police Spokesperson
Government Security
Police Authority
2
Appendix (ii) List of Documents Reviewed
Document Purpose
Ministerial Policy Statements – Ministry of
Internal Affairs 2008/09, 2009/10 and
20010/11
Obtain plans, funding, force strength and
performance for the UPF
Police Department Reports and Financial
Statements FY’s 2008/09, 2009/10 and
2010/11
To establish funding for the UPF for the 3
years under review.
Justice Law and Order Sector Annual
Performance Report 2009/10
To get an overview of UPF performance in
the sector
Uganda Police Standing Orders (7th Edition)
Volume 1
Obtain standards of performance for the UPF
Approved Structure for Uganda Police Establish the staff structure of the UPF
Compendium of Laws 2008 (Police Act) Obtain mandate of UPF, functions of Police
Council
Contracts Establish agreed amount and scope of works
for civil works in the UPF
Minutes of Police Council To obtain decisions reached by Council on
accommodation of gazetted police officers
Summary of Barracks Data To establish the number of housing units and
officers accommodated by the UPF
Mwangaza UPF magazine Challenges of accommodation in the UPF
3
Appendix (iii) Interviews Conducted
Section Officer(s) Purpose of the interview(s)
UPF
Headquarters
The Deputy Inspector
General of Police.
To obtain understanding of the operations and
structure of the Uganda Police Force.
UPF
Headquarters
The Under Secretary To obtain information about the planning,
budgeting, releases, accounting and
monitoring of the various UPF activities.
UPF
Headquarters
Commissioner; Barracks
administration
To obtain clarification on who is entitled to
barracks accommodation and administration of
barracks.
Directorate of
Logistics and
Engineering
Jinja Road.
Director; Logistics and
Engineering.
Obtain an understanding of the structure of
the Directorate of Logistics and Engineering
and the major activities of the directorate.
Directorate of
Logistics and
Engineering
Jinja Road.
Deputy Director;
Logistics and
Engineering.
Ascertain the Directorate’s plans of increasing
accommodation facilities to match the
recruitment of police personnel.
Barracks
Administration
Barracks Commandant;
Ntinda-Naguru-Kireka.
To establish the nature of houses in the
barracks, how they are allocated, the
population of police staff accommodated and
the challenge encountered.
Barracks
Administration
Barracks Commandant
Nsambya.
To establish the nature of houses in the
barracks, how they are allocated, the
population of police staff accommodated and
the challenge encountered.
Barracks
Administration
DPC/ OC Barracks Gulu To establish the nature of houses in the
barracks, how they are allocated, the
population of police staff accommodated and
the challenge encountered.
4
Barracks
Administration
OC CID/CLO/OC
Barracks Luwero
To establish the nature of houses in the
barracks, how they are allocated, the
population of police staff accommodated and
the challenge encountered.
Barracks
Administration
DPC/OC station/OC
Barracks Arua
To establish the nature of houses in the
barracks, how they are allocated, the
population of police staff accommodated and
the challenge encountered.
Barracks
Administration
DPC/OC Barracks Tororo To establish the nature of houses in the
barracks, how they are allocated, the
population of police staff accommodated and
the challenge encountered.
Barracks
Administration
OC Barracks; Jinja Main
Police Barracks
To establish the nature of houses in the
barracks, how they are allocated, the
population of police staff accommodated and
the challenge encountered.
Barracks
Administration
DPC/OC Barracks
Bushenyi
To establish the nature of houses in the
barracks, how they are allocated, the
population of police staff accommodated and
the challenge encountered.
Barracks
Administration
DPC/OC CID/ OC
Barracks Masindi
Establish the nature of houses in the barracks,
how they are allocated, the population of
police staff accommodated and the challenge
encountered.