treatment facility condition assessment facility... · • 80 delivery points ... components...
TRANSCRIPT
Treatment Facility Condition Assessment
PRESENTED BY: SCOTT COLE, P.E.YANBO LI, P.E.
WEAT NORTH TEXAS SECTION SEMINAR
FEBRUARY 10, 2011
Acknowledgments
• Theo Chan, P.E., Freese and Nichols
• David Sloan PE Freese and Nichols• David Sloan, P.E., Freese and Nichols
• Angellia Points, EIT, Freese and Nichols
R b t M C th N th T M i i l W t Di t i t• Robert McCarthy, North Texas Municipal Water District
• NTMWD Planning Staff
• NTMWD Operations Department
• NTMWD Maintenance Department
• NTMWD Engineering Department
• NTMWD Executives
2
Agenda
• Background
• Overview of Asset Management Components• Overview of Asset Management Components
• Water Treatment Plant Assessment
W t T t t Pl t Pi i A t• Water Treatment Plant Piping Assessment
• Capital Improvement Program Development
3
Overview of System• Initially established in the 1950s
• Serves approximately 1.6 million people
• 80 delivery points
• Pipelines 12” – 96”
• 19 pump stations
• 2010 Average Day = 278 MGD
• 2010 Maximum Day = 548 MGD
4
Wylie Water Treatment Plant
Plant 3
Plant 4
• Current capacity = 770 MGD Plant 2
• Future capacity = 840 MGD
Plant 2
6
Plant 1
Project Drivers
• Aging Infrastructure
• Refine Asset Management Approach• Refine Asset Management Approach
• Desire to Incorporate System Renewal into CIP
B i A h i Ri k M t i• Business Approach using Risk Management in Infrastructure Renewal
7
Agenda
• Background
• Overview of Asset Management Components• Overview of Asset Management Components
• Water Treatment Plant Assessment
W t T t t Pl t Pi i A t• Water Treatment Plant Piping Assessment
• Capital Improvement Program Development
8
Overview of Asset Management Components
Data Inventory & Management
Continuous Improvement
Process
What is ?
“A set of processes to minimize infrastructure
Capacity Analysis
Prioritized CIP
life cycle costs at an acceptable amount of risk, while delivering an
ConditionRisk
risk, while delivering an established level of service”
Condition Assessment
Criticality
Management
Assessment
9
Risk Based Assessment Planning Process
Review and Inventory of Various Data Sources
GIS SCADA W k O d D t St ffGIS ‐ SCADA ‐Work Order Data – Staff Interviews – Maintenance Records
RISK BASED PRIORITIZED CAPITAL
O
Develop CIP Prioritization
Scoring
ConditionAnalysisSite Visits/
Field Investigations IMPROVEMENT PLANScoring
Criteria Criticality Analysis
Investigations
10
Risk Based Concept for Infrastructure Renewal Prioritization
Risk = ƒ (Criticality x Condition)ƒ ( y )
What is the Consequence of Asset Failure?
•Loss of service
What is the Likelihood of Asset Failure?
•Asset age•Loss of service•Redundancy•Difficulty of repair
•Asset age•Asset material•Performance of assety p
•Damage to property•Public image
•Annual maintenance costs
11
Risk Based Matrix
Very Good Good Fair Poor Very PoorPriority
Condition
Very Good Good Fair Poor Very Poor
Low Impact
ity
Medium Impact
Crit
ical
i
High Impact
Very High
Impact
12
Impact
Agenda
• Background
• Overview of Asset Management Components• Overview of Asset Management Components
• Water Treatment Plant Assessment
W t T t t Pl t Pi i A t• Water Treatment Plant Piping Assessment
• Capital Improvement Program Development
13
Components Evaluated
• Rapid Mix
• Flocculation Basins• Flocculation Basins
• Sedimentation Basins
Filt• Filters
• Filter Backwash System
h l• Chemical Feed
• Sludge Handling
• Plant Water System
14
Condition Scoring GuidelinesCondition Rating
Description
0 New, perfect condition
25Good condition, no improvements recommended to maintain function
50Fair condition, improvements recommended to improve performance or efficiency
75Poor condition, improvements recommended to maintain reliability
100 Imminent failure, rehabilitation or replacement required
0 2 0000New Bulk
Storage Tanks
75 Aging
Infrastructure
25Paint
Stripping
100 Inoperable, No
Replacement Parts
50Small Cracks,
Spalling
Condition of Facilities
• Determine the total condition score for each asset and group into five general categories:g p g g
CONDITION ASSESSMENT SCORING DEFINITION
Very Good Sound physical condition. Total Score ≤ 25
GoodGood Acceptable physical condition. 25 < Total Score ≤ 50
Fair Normal wear and tear. 50 < Total Score ≤ 75
Poor F il lik l i h t t di t 75 T t l S ≤ 85Poor Failure likely in short to medium term. 75 < Total Score ≤ 85Very Poor
Failed or near failure. Total Score > 85Major work or replacement required urgently.
18
Criticality Scoring and Parameter Weighting
Capacity Affected (30%) Process Impact (50%)
Based on Percent of Total Capacity (100 MGD) LostBased on Treatment Process
EffectivenessEffectiveness
≤ 13 MGD (≤13%)Capacity Lost = 10 Mild = 20
14 ‐ 25 MGD (14 – 25%) Capacity Lost = 30 Moderate = 55
26 ‐ 50 MGD (26 – 50%) Capacity Lost = 50 Severe = 10026 50 MGD (26 50%) Capacity Lost 50 Severe 100
51 ‐ 85 MGD (51 – 85%) Capacity Lost = 70
≥ 86 MGD (≥86%) Capacity Lost = 100
Outage Duration (20%)Based on Discussion with Field Crew and Response Time
< 2 Days = 10< 2 Days = 10
3 ‐ 15 Days = 40
16 ‐ 29 Days = 70
≥ 30 Days = 100≥ 30 Days = 100
Risk Based Assessment Matrix
Very Good Good Fair Poor Very PoorPlant 2
Condition
Low Impact
Medium Impact
ality
All Flocculators All Rapid Mix
High Impact
Sed Basins 3 & 4
Crit
ica
Filters 6-20 Lime
Polymer Sed Basins 5,6,8
Filters 1-5 Filters 21-40 Sed Basin 1
Very High
Sodium Chlorite
Ferric Sulfate Filter Backwash
Caustic Soda
Ammonia Sludge Handling
Plant Water
SHORT TERM CRITICAL NEEDS 21
Impact Fluoride Plant Water
Agenda
• Background
• Overview of Asset Management Components• Overview of Asset Management Components
• Water Treatment Plant Assessment
W t T t t Pl t Pi i A t• Water Treatment Plant Piping Assessment
• Capital Improvement Program Development
22
Condition Scoring & Parameter Weighting
Pipe Age (30%) Pipe Repairs (55%)Year Installed Based on # of Repairs in Last 10 Years
1950 – 1959 = 100 More than 6 repairs = 100
1960 – 1969 = 80 4 ‐ 6 repairs = 60
1970 – 1979 = 60 2‐ 3 Repairs = 30
1980 – 1989 = 40 No Repairs = 0
1990 – 1999 = 20
2000 – 2009 = 0
Pipe Material (15%)
Non Cylinder Water Pipe = 90
Ductile Iron = 40
Pre‐stressed Concrete Cylinder Pipe (PCCP) = 40
Reinforced Concrete Pipe (RCP) = 40
Mortar Coated Steel (MCS) = 40
23
Mortar Coated Steel (MCS) = 40
Bar‐wrapped Concrete Cylinder Pipe (BWCCP/RCCP) = 40
Polyurethane Coated Steel (PCS) = 40
Criticality Scoring & Parameter Weighting
Capacity Affected (40%) Redundancy (30%)
Based on Percent of Total Capacity (770 MGD) LostBased on Capacity Lost to the
Receiving BasinReceiving Basin≤ 35 MGD (≤ 4.5 %) Capacity Lost = 10
35 ‐ 69 MGD (4.6 ‐ 8.9%) Capacity Lost = 30 ≤ 25% Capacity Lost = 10
70 ‐ 139 MGD (9 ‐ 18%) Capacity Lost = 50 26 – 49% Capacity Lost = 40
140 ‐ 279 MGD (18.1% ‐ 36.2%) Capacity Lost = 70 50 – 74% Capacity Lost = 70
≥ 280 MGD (≥ 36.3%) Capacity Lost = 100 ≥ 75% Capacity Lost = 100
Outage Duration (30%)d i i i h i ld C d iBased on Discussion with Field Crew and Response Time
≤ 8 hours = 10
8 – 16 hours = 40
17 – 24 hours = 70
24
≥ 24 hours = 100
Criticality and Condition Results
Condition Rating Min Maxd
Plant 2
Yard Pipe Condition CriticalityCondition Rating
Criticality Rating
Risk
72" Interconnect Very Good 0 25Good 26 50Fair 51 75Poor 76 85
Between WTP-2 Tank #3 and WTP-2 Tank #2
24 62 Very Good
High Impact Low
72" Interconnect Between WTP-2 Tank #3 and WTP-
24 62 Very Good
High Impact Low
Very Poor 86 100 2 Tank #4p
60" Interconnect Between WTP‐2 Tank #2 and WTP‐2 Tank #4
18 79 Very GoodVery High Impact
Medium
60" Filt d W t
Criticality Rating Min MaxLow Impact 0 30Medium Impact 31 50
60" Filtered Water from Filters to WTP‐2 Tank #2
24 62 Very GoodHigh Impact
Low
72" Interconnect between WTP‐2 Tank #3 and 60" Line
6 50 Very GoodMedium Impact
Low pHigh Impact 51 70Very High Impact 71 100
from WTP‐1 Tank #3
84" From WTP‐2 Tank #4 to HSPS 2‐2
18 88 Very GoodVery High Impact
Medium
72" From Filters to HSPS 2‐3
6 53 Very GoodHigh Impact
Low
"
26
36" From WTP‐2 Tank #1 to Wylie/Rockwall/Farmersville Pump Station
24 72 Very GoodVery High Impact
Medium
Agenda
• Background
• Overview of Asset Management Components• Overview of Asset Management Components
• Water Treatment Plant Assessment
W t T t t Pl t Pi i A t• Water Treatment Plant Piping Assessment
• Capital Improvement Program Development
27
CIP Prioritization Methodology
Very Good Good Fair Poor Very PoorPriority
Condition
Low Impact K G
No
calit
y
Medium Impact L H DProjects
I E BCrit
ic
High Impact M
AVery High
Impact N J F C
28
SHORT TERM CRITICAL NEEDS
Capital Improvement Program Prioritization
Priority Bin
Priority Rank
Plant Project
1 2 Sedimentation Basins 3 and 4 ‐ SMP2 1 All ClariflocculatorsB
Priority Bin
Project
High Risk 30" Cast Iron Pipe
FACILITIES PIPELINES
2 1 All Clariflocculators3 1 Rapid Mix Basin
4 2 Ammonia5 2 Sludge Handling6 1&2 Plant Water7 1 Ammonia
B
8" Cast Iron Pipe12" Cast Iron Pipe
24" Reinforced Concrete Pipe30" Reinforced Concrete Pipe" f d7 1 Ammonia
8 1 Filter Backwash9 3 Chlorine10 3 Ammonia11 3 Plant Water12 3 Fluoride
F
33" Reinforced Concrete Pipe36" Reinforced Concrete Pipe42" Reinforced Concrete Pipe54" Reinforced Concrete Pipe60" Reinforced Concrete Pipe
13 3 Sludge Handling14 3 Ferric Sulfate
15 3 Filter Backwash
16 2 Filters 6‐2017 2 Filter Influent Gallery
72" Reinforced Concrete Pipe60" Mortar Coated Steel Pipe
18"/30" Pre‐Stressed Concrete Cylinder Pipe24" Pre‐Stressed Concrete Cylinder Pipe36" Pre‐Stressed Concrete Cylinder Pipe
Medium Risk
17 2 Filter Influent Gallery18 2 Filter Effluent Gallery19 2 Lime
20 2EIC ‐ Rapid Mix, Flocculators, and
Sedimentation Basins21 2 Sedimentation Basins 5, 6, 8 ‐ SMP
42" Pre‐Stressed Concrete Cylinder Pipe48" Pre‐Stressed Concrete Cylinder Pipe60" Pre‐Stressed Concrete Cylinder Pipe72" Pre‐Stressed Concrete Cylinder Pipe84" Pre‐Stressed Concrete Cylinder Pipe
29
22 1 & 2 Polymer23 1& 2 S di Chl it
I 90" Pre‐Stressed Concrete Cylinder Pipe96" P St d C t C li d Pi
*Scores of “100” included as a project under the associated process unit regardless of overall facility score
Next Steps
• Finalize cost estimates
• Finalize reportFinali e report
• Determine impact on Water System CIP
• Re‐evaluate Risk Based Assessment periodically asRe evaluate Risk Based Assessment periodically as system ages and new facilities come on‐line
30
Questions?
Contact Information:
Scott Cole, [email protected](817)735 7255
Yanbo Li, [email protected](972) 442 5405(817)735‐7255
4055 International Plaza, Suite 200Fort Worth, TX 76109
(972) 442‐5405505 East Brown StWylie, Texas 75098
31