    1/43

    Environment Impact Assessment for

    Highways

  • 7/29/2019 EIA Compiled

    2/43

    EIA- Highways

    Damage to eco-systems

    Soil erosion

    Interference with wild-life Loss of agricultural land

    Resettlement of people

    Disruption of local economic activities

  • 7/29/2019 EIA Compiled

    3/43

    A Category

    New National highways

    & Expansion of National

    Highways greater than

    30 km, involving

    additional right of waygreater than 20m

    involving land

    acquisition and passing

    through more than one

    state

    General Condition

    Any project or activity

    specified in Category B

    will be treated as

    category A, if located in

    whole or in part within10 km from the

    boundary of:

    (i) Protected area

    notified under the

    Wildlife Act, 1972.

    (ii) Critically polluted

    areas as notified by

    the Central Pollution

    Control Board

    All state highway

    projects, State highway

    expansion projects in

    hilly terrain or

    ecologically sensitiveareas

    Highway Projects : Categories

    B Category

  • 7/29/2019 EIA Compiled

    4/43

    ECP- Stages

    Screening Scoping

    Public Consultation

    Appraisal

  • 7/29/2019 EIA Compiled

    5/43

    Category -A

  • 7/29/2019 EIA Compiled

    6/43

    Category -B

  • 7/29/2019 EIA Compiled

    7/43

    Generic Structure of EIA Document

    1. Introduction

    2. Project Description3. Analysis of Alternatives (Technology and Site)

    4. Description of the Environment

    5. Anticipated Environmental Impact & Mitigation

    Measures6. Environmental Monitoring Program

    7. Additional Studies

    8. Project Benefits

    9. Environmental Cost Benefit Analysis

    10. Environmental Management Plan

    11. Summary & Conclusion

    12. Disclosure of Consultants engaged

  • 7/29/2019 EIA Compiled

    8/43

    PROJECT DESCRIPTION

    GENERAL

    Project coverage, master plan, phasing and scope

    Relevance of the project in the light of the existing development

    plans of the region /state /nation

    Description of all alternative alignments considered avoiding the

    ethnic minorities living in the proposed right-of-way Procedures and criteria adopted for selection of the alignment of

    right of way, alternative alignments considered, if any, details of

    land acquisition involved, rehabilitation of villages/ communities if

    any, proposed methods there of etc.,

    Overall suitability of the identified alignment and the proposed

    activity in the light of the existing environmental acts and serious

    deviations.

  • 7/29/2019 EIA Compiled

    9/43

    BROADER DETAILS OF PROJECT & LOCATION

    Description of the alignment, broad geology, topography, connectivity,demographic aspects, socio, cultural and economic aspects, villages,

    settlements

    Details of environmentally sensitive places, land acquisition,

    rehabilitation of communities/ villages and present status

    Historical data such as climatic conditions, rainfall, history of cyclones,

    earthquakes

    Technologies involved for design and construction

  • 7/29/2019 EIA Compiled

    10/43

  • 7/29/2019 EIA Compiled

    11/43

    NATURAL RESOURCES REQUIREMENT

  • 7/29/2019 EIA Compiled

    12/43

    3. Analysis of Alternatives

    Consideration of Alternatives:

    Types of Alternatives

    Alternative solution to thetransportation problem

    Alternative Design for theselected project

  • 7/29/2019 EIA Compiled

    13/43

    The four characteristics are:

    Spatial requirements

    Natural resources consumption

    Human resource benefits and costs and

    Waste production during the construction and

    operation/maintenance periods

    These details shall comprise of:

    Description of various alternatives

    Description of each alternative

    Summary of adverse and positive impact of each alternative

    Selection of the alternative which is the best with respect to use

    of resources and adverse environmental impact

  • 7/29/2019 EIA Compiled

    14/43

    4.Description of the environment

    Environmental components in relation to the highwayprojects:

    (a) land

    (b) water(c) air and meteorological

    (d) Biological

    (e) noise

    (f) solid waste management

    (g) Socio economic and health environment.

  • 7/29/2019 EIA Compiled

    15/43

    Study Area:

    Primary Data: The area falling the right way as well asfalling within 500 meters on either side of right of the

    way.

    Secondary Data: Within 15 km aerial distance.

  • 7/29/2019 EIA Compiled

    16/43

    Land Environment:

    Areas protected under international conventions, national or local

    legislation for their ecological, landscape, cultural or other related value

    Areas which are important or sensitive for ecological reasons.

    Areas used by protected, flora or fauna.

    Inland, coastal, marine or underground waters

    State, national boundaries

  • 7/29/2019 EIA Compiled

    17/43

    Routes or facilities used by the public for access to recreation

    or other tourist, pilgrim areas

    Defense installations

    Densely populated or built-up area

    Areas occupied by sensitive man-made land uses.

    Areas containing important, high quality or scarce resources.

    Areas already subjected to pollution or environmental

    damage.

    Areas susceptible to natural hazard, which could cause the

    project to present environmental problems.

  • 7/29/2019 EIA Compiled

    18/43

    The details of demographic profile should be

    collated.

    Data of the proposed land and its availability is to be

    ascertained from local authorities, revenue records

    etc.

  • 7/29/2019 EIA Compiled

    19/43

    Description of theexisting situation of

    the land.

    f

  • 7/29/2019 EIA Compiled

    20/43

    Details of the alignment passing through CRZ area.

    Identification of major and minor irrigation tanks,

    with in 2 kms on the upstream side of alignment.

    The details of identified quarries and borrow areas

    should be given as per the tables:

  • 7/29/2019 EIA Compiled

    21/43

    Geology

    Soil Data

  • 7/29/2019 EIA Compiled

    22/43

    Water Environment

  • 7/29/2019 EIA Compiled

    23/43

  • 7/29/2019 EIA Compiled

    24/43

    Air Environment

    Metrological Data

    Ambient Air Data

  • 7/29/2019 EIA Compiled

    25/43

    Noise Environment

    Bi l i l E i t

  • 7/29/2019 EIA Compiled

    26/43

    Biological Environment:

    Details on secondary data on the existing flora and

    fauna in the study area. The list of endangered and

    endemic species should be given as:

    If th d j t it i l b di

  • 7/29/2019 EIA Compiled

    27/43

    If the proposed project site involves any breeding or

    nesting ground.

    If the proposed route requires cutting of trees.

    Location of national parks, sanctuary, and biosphere

    reserve, tiger reserve, elephant reserve and wildlife

    migratory routes with in aerial distance of 10 km

    either side of proposed alignment should be

    furnished

    S i E i d

  • 7/29/2019 EIA Compiled

    28/43

    Socio Economic and

    Health Environment:

    Baseline data in the study area

    particularly on human

    settlements, health status of

    the communities, existing

    infrastructure facilities should

    be collected through secondary

    sources.

    Present employment,

    livelihood and awareness of the

    population about the project

    should be collected.

  • 7/29/2019 EIA Compiled

    29/43

    Analysis of Potential Environmental

    Impact & Mitigation measures

  • 7/29/2019 EIA Compiled

    30/43

    Environmental Impact

    Environmental Impact should be considered not only pertaining to the road

    Right of Way but also to the sites associated with the road project .

    Environmental Impact should consider:

    1) Land Environment

    2) Water Environment3) Air Environment

    4) Noise Environment

    5) Biological Environment

    6) Socio-economic and Health Environment

    7) Solid Waste Management

  • 7/29/2019 EIA Compiled

    31/43

    Land Environment

    Anticipated impact:

    Highway projects require large quantum of land and causes disturbance to

    the existing land usage

    Impact due to removal of top soil during highway construction and from

    storing stockyards, workers camp etc

    Impact due to destabilization of slopes

    Impact due to diversion of natural surface water flows

    Impact due to construction of bridges across nallahs, streams, rivers and

    water bodies

    Mitigation measures:a) While selecting road alignment , attention must be paid to avoid areas

    prone to land slides, soil erosion, fertile agricultural lands etc

    b) Drainage improvements to avoid water logging and flooding due to

    disturbance of natural drainage pattern

  • 7/29/2019 EIA Compiled

    32/43

    Water Environment

    Anticipated impact:

    Road construction activities that intersect drainage basins, generally

    modify the natural flow of water which may increase the speed of flow

    resulting in flooding and soil erosion.

    Impact due to spillages and accidents of the vehicles carrying chemicals

    should be assessed especially if drinking water bodies are located within

    500 meters

    Impact on water facilities such as wells, hand pumps, tube wells etc along

    the highway should be assessed

    Impact due to wastewater generated from the temporary project offices

    Mitigation measures:

    a) Labour camps should not be located near to water bodies

    b) In dry areas road drainage can be designed to retain water in small dams

    or maintain a high water table, which increases the availability of water

  • 7/29/2019 EIA Compiled

    33/43

    Air Environment

    Anticipated impact:

    Impact due to dust generation from excavation of soil, cutting of

    embankment near to habitation, hospitals, schools, sanctuaries etc

    Impact due to movement of heavy vehicles carrying construction materials

    Impact due to stone quarrying Impact due to wastewater generated from the temporary project offices

    Impact due to dust generation from material handling, storage, operation

    of crushers and hot mix plants, movement of construction vehicles

    Impact due to vehicular emissions from vehicles used for construction

    Mitigation measures:

    a) Selecting road alignment,which avoids passing close to houses, schools etc

    b) Planting tall leafy vegetation between roads and human settlement

  • 7/29/2019 EIA Compiled

    34/43

    Noise Environment

    Anticipated impact:

    Impact of noise during construction activity during operation of

    equipments

    Impact of noise on wildlife from crossing road corridors and becoming the

    highway corridor a barrier to regular wild life travel routes.

    Prediction of noise levels should be done using mathematical modelling

    Impact of vibrations during blasting activity

    Mitigation measures:

    a) Provision for stationary machines and equipment with acoustic enclosures

    and silencers during the construction stageb) Planting tall leafy and dense vegetation between roads and noise sensitive

    areas

  • 7/29/2019 EIA Compiled

    35/43

    Biological Environment

    Anticipated impact:

    Impact on forest resources, economically important plants including

    medicinal plants and threat to endangered species

    Impact on wildlife habitat and biodiversity due to change in land use

    Impact due to fragmentation of wildlife habitat and territories Impact due to changes in water quality, soil profile, noise, light and air

    pollution, which may affect the nature and character of habitats

    Increased chances of animals encountering collision with vehicles

    Mitigation measures:

    a) Identification of sensitive natural environments in the early planning stageso that alternative routes can be examined

    b) Compensate the loss of forest coverage by appropriate plantation

    programme

  • 7/29/2019 EIA Compiled

    36/43

    Socio-economic and Health

    EnvironmentAnticipated impact:

    Displacement of human settlement from proposed sites. Impact on

    livelihood and loss of properties

    Impact on community resources such as grazing land religious places and

    panchayat meeting place etc

    Impact due to accelerated urbanization

    Employment opportunities and access to other amenities such as primary

    education and health care facilities for local people

    Mitigation measures:

    a) Rehabilitation plan for displaces personsb) Training of local people for employing them in the proposed project

    c) Mechanism for providing effective guidance in financial planning to

    affected people

  • 7/29/2019 EIA Compiled

    37/43

    Solid Waste Management

    Anticipated impact:

    Waste generated during construction may impact soil, agriculture ans water

    quality

    Waste generated from worker camps may impact surface and ground water

    quality and agriculture

    Impact due to oil spillage/leakage from machines and vehicles

    Mitigation measures:

    a) Road design and alignment should be finalized to minimize waste

    generation through balancing of cut and fill operations and minimizingexcess cuts requiring disposal

    b) Suitable top soil management

  • 7/29/2019 EIA Compiled

    38/43

    Chapter 7 of Manual

    Apart from the TOR, the other issues which proponent wants tohighlight are attached in the report through this chapter. The EIAreport and EMP should therefore address such issues also.

    In such cases the proponent shall include such issues as additionalstudies under TOR and pursue them in the EIAstudy after the

    regulatory authority approves TOR. Even Regulator , stake holders, can highlight project specific issues

    through this chapter.

    R & R Action Plans

    R&R plan with data on the existing socio-economic status of thepopulation in the study area and broad plan for resettlement of thedisplaced population

    Road Safety Management System

  • 7/29/2019 EIA Compiled

    39/43

    Chapter 8 and 9 of Manual

    This chapter shall include benefits accruing to thelocality, neighborhood, region and nation as a whole.It should bring out details of benefits such as:

    Improvements in the physical infrastructure and road

    access Improvement in social services by quicker and safe

    transport mode

    Development of tourism in specific areas

    Reduced pollution, vehicle maintenance, fuel savingdue to better quality of roads

    Over all development in economy and improved lifestyle

  • 7/29/2019 EIA Compiled

    40/43

    Continued

    Chapter 9ENVIRONMENTAL COST BENEFIT ANALYSIS

    Cost-Benefit Analysis (CBA)

    It is a technique that compares the monetary value of

    benefits with the monetary value of costs in order toevaluate and prioritize issues. The effect of time (i.e. thetime it takes for the benefits of a change to repay its costs)is taken into consideration by calculating a paybackperiod. In its simple form, CBA uses only financial costs and

    financial benefits (e.g. a simple CBA of a road schemewould measure the cost of building the road, and subtractthis from the economic benefit of improving transportlinks).

  • 7/29/2019 EIA Compiled

    41/43

    Chapter 10 of Manual

    ENVIRONMENT MANAGEMENT PLAN

    An EMP is a site-specific plan developed to ensure thatall necessary measures are identified and implementedin order to protect the environment and comply withenvironmental legislation.

    A site-specific EMP must be prepared for all projects. Itprovides the answers to the following importantquestions:

    What are the likely environmental issues for your site?

    What likely harm these issues can cause to thesurrounding environment?

    How will you manage these issues to minimize harm tothe environment?

  • 7/29/2019 EIA Compiled

    42/43

    Chapter 11 of Manual

    SUMMARY AND CONCLUSIONS Summary of EIA shall be a summary of the full EIA report

    condensed to ten A-4 size pages at the maximum. It shouldnecessarily cover in brief the following chapters of the full EIAreport.

    Introduction

    Project description Description of the environment

    Anticipated environmental impact & mitigation measures

    Additional studies

    Project benefits

    Important Aspects of the Environmental Management Plan and Important Aspects of the Environmental Monitoring Programme

    Disclosure of consultants engaged

  • 7/29/2019 EIA Compiled

    43/43

    THANK YOU