future technologies in power systems - 大阪大学 · central research institute of electric...
TRANSCRIPT
Central Research Institute of Electric Power Industry
Future Technologiesin Power Systems
Vice President
2016
INTERNATIONAL WORKSHOP ONConstruction of Low-Carbon Society Using Superconducting
and Cryogenics TechnologyMarch 8, 2016
Dr. Shirabe Akita
1
2
What is Future Power System Technologies in
“Construction of Low-Carbon Society”
● Selection of Primary Energy► Solar ► Wind on Shore / off Shore► Hydro► Biomass► Geothermal► Nuclear
2016
2016 3
4
and Several Key New Technologies● Superconducting Technology
► SC Power Cable Including DC► SC Generator with Low Reactance► SC Wind Generator
● Semiconductor Power Device► SiC
● Energy Storage Technology► Li- Ion Batteries ► SMES
● Advanced Thermal Power Generation► Fast Response► Low Minimum Load
2016
Location & spec・Asahi S/S, Yokohama, TEPCO’s network・66 kVrms-1.75 kArms / 200 MVA, 240 m
Check items for the system・Reliable and stable operation over 1 year・Cooling controllability at heat load fluctuation・Maintenance without system shutdown
First ‘in real-grid’ HTS Cable demonstration in JapanLocation & spec・Asahi S/S, Yokohama, TEPCO’s network・66 kVrms-1.75 kArms / 200 MVA, 240 m
Host Power Company
HTS cable system design, manufacture and installationCooling system design,manufacture and installationRefrigerator developmentProject funding and management
Refrigerator development
Project overview
Tokyo
Site
2016 5
“3-in-One” Type HTS CableThree cores are housed in one cryostat.Copper Stranded Former
Electrical Insulation(PPLP+LN2)
LN2 flow channel
Superconducting Shield(BSCCO tapes in 2 layers)
Superconducting conductor(BSCCO tapes in 4 layers)
Thermal insulation pipe (Cryostat)
HTS cables will be key technology for next-generation grid“Large capacity” : equivalent to conventional cables “Compact size” : installed within existing conduits“Low loss” : less than 1/2 of conventional cables
Characteristics and structure
2016 6
Trans154/66kV200MVA
Monitoringhouse
Joint
CB
CH
LS1
CB1
CH
LS10
CB2
T2 T1
P
Ref
Site office
LS2
~250 meter HTS cable
Terminations
Cooling systemhouse
Trans154/66kV200MVA
Monitoringhouse
Joint
CB
CH
LS1
CB1
CH
LS10
CB2
T2 T1
P
Ref
Site office
LS2
~250 meter HTS cable
Terminations
Cooling systemhouse HTS cable
Cooling system house
HTS cable terminations
System Layout
2016 7
Current status of SiC technologySiC semiconductors as a power saving technology for wide range applications
Production of 6-inch wafers is started.1200V class SiC SBDs, MOSFETS and equipment installing SBDs are on the market.SBD-equipped trains are running on the rail.
www.infineon.com
1200V SBDs 1200V MOSFETs
www.cree.com www.mitsubishielectric.co.jp www.nissan.co.jp
www.mitsubishielectric.co.jp
1700V-1200ASiC-SBD/Si-IGBT power module
electric train(Ginza-line)
>10 kV SiC bipolar devices are expectedin power transmission/distribution system
(still need basic material research)
15% reduction of the converter loss
30% reduction of the total system loss
2016 8
Inductioncoil
Susceptor(φ175 mm)
Hot wallSiC substrate
H2+SiH4+C3H8(10-50 Torr)
Quartztube
1650 °C, 15 Torr, H2 70slm
250 µm/h @1650°C
SiC crystal for low-loss >10 kV devices(i) >100 µm thick epitaxial growth(ii) 1014 cm-3 range doping control(iii) >10 µs carrier lifetimes
Very thick, high-quality SiC epitaxial layers are requested
Achievement of very high growth rates in the original CVD reactor by CRIEPI
n- drift
p+ layerp+ buffer
n layer
Cross-sectional view of SiC-IGBT
n buffer
CRIEPI: Appl. Phys. Express 1, 015001 (2008)
2016 9
Vertical gas-flow
High-speed rotation
Planer heaterUniform heating
High growth rate
Uniform gas distribution
NFT: Si industrial reactor
Large diameter waferHigh throughput (high-T wafer loading, quick heating & cooling)
Rotation
SiC wafer
Source gasDevelopment of6-inch SiC epitaxialgrowth process
High quality SiC epitaxy for
car applications
H2+SiH4+C3H8+HCl
150 mmφSiC wafer~1650ºC
upper heater
lower heater
1000rpm
high-speed rotationCRIEPI: Appl. Phys. Express 7, 015502 (2014), ICSCRM20142016 10
(a)Okinawa(Na/S:4MW,LIB:100kW)
(FY2010-16)
(b)Hokuriku(LIB:100 kWh)(FY2010-11)
(d)Kyusyu(LIB:4MW)(FY2012-16)
(i) Hokkaido(RF:15MW)(FY2013-18)
(h) Tohoku(LIB:40MW) × 2(FY2013-18)
(f)Kansai(LIB:100kW)(FY2013-15)
(c)Tokyo(LIB:900kW)(FY2010-14)
(e)Chubu(LIB:250kW)(FY2012-15)
11
(g)Chugoku(Na/S:4.2MW,LIB:2MW)(FY2015-17)
Mainly Lithium-ion Battery(LIB) only, except (a),(g),(j): Na/S Battery,(i):Redox-Flow(RF) Battery
Field Tests of BES by Electric Power Companies in Japan
2016
(j) Kyusyu(Na/S : 50MW)(FY2015-19 )
Actual Installation in Tohoku Power Grid (1)
Introduction of power control equipments (SVR,SVC etc.)*Introduction of Battery**
*SVR: Step Voltage RegulatorSVC:Static Var Compensator
Nishi-Sendai Substation,Tohoku Electric Power Company
12
20MWh/40MW Lithium-ion battery system
Construction started on Nov., 2013
All construction work completed by Feb., 2015
Planned 3-years Demonstration by Mar., 2018
**Ref. Tohoku Electric Power Company, Press Release, 20/Feb./2015.
2016
Actual Installation in Tohoku Power Grid (2)
40MWh/40MW Lithium-ion Battery Systemat Minami-Souma Substation
132016
Ref. Tohoku Electric Power Company, Press Release, 26/Feb./2016.
+-
SEI*
Degraded+-
SEI*Irreversible consumption of lithium on anode
Inactivation of cathode materials
New
SEI*:Solid Electrolyte Interface
Li+Li+
Capacity Fading Model of Lithium-ion Cells
2016 14
Cell voltage = Cathode voltage – Anode voltageCell capacity = Overlap region between cathode and anode
Discharge capacity (mAh g-1)
Initial dislocation
Vd
Volta
ge (
V)
Cell capacity
Cathode
Anode
Discharge capacity (mAh g-1)
Vd
Volta
ge (
V)Cell capacity
Anode
B: Inactivation of cathode materials
Cathode
Anode material degradation=> No contribution to cell capacity
Rising of Vd andcathode SOC
Vd0 Vd0
A: Dislocation increase
Initial dislocation
SEI:Solid Electrolyte Interface
Analysis of Each Electrode Capacities Using “Nico-ichi” Cells*
DegradedNew
*Ref. K. Shono, et al., CRIEPI Report, Q13006 (2014). 2016 15
【Control System】
【Test Cell】
Test Cell10 Ah~100 Ah Class
C/D system5V-(100A~300A)×100ch
Large Battery Test System
20162016 16
Actual Installation in Hokkaido Power Grid
60MWh/15MW Redox-Flow(RF) Batteryat Minami-Hayakita Substation
172016
•
http://www.sei.co.jp/company/press/2015/12/prs098.html
Actual Installation in Kyusyu Power Grid
300MWh/50MW NaS Batteryat Buzen Power Substation
182016
•http://www.shimbun.denki.or.jp/news/energy/20160304_01.html
http://www.mitsubishielectric.co.jp/news/2015/0622-b.html
19
Advanced Thermal Power Generation
NEDO Feasibility Studies(2015 Feb. – 2016 Feb.)
“Research and Development of Advanced Gas Turbinefor Firming Grid in Renewable Energy Age”
R&D Organization
Central Research Institute of Electric Power Industry (CRIEP) National Institute of Advanced Industrial Science and Technology (AIST) Mitsubishi Heavy Industries, Ltd. (MHI) Mitsubishi Hitachi Power Systems, Ltd. (MHPS) TOSHIBA CORPORATION Kawasaki Heavy Industries, Ltd. (KHI) IHI Corporation
2016
20
Research and Development of Advanced Gas Turbine for Firming Grid in Renewable Energy Age
・The object of this theme is to clarify the targets to research anddevelop advanced gas turbine for firming grid in the age when a largeamount of renewable energy is introduced.
・We research and investigate technologies and problems to improveflexibility of gas turbine systems.
R&D Themes and Objectives
R&D Background
・ Introducing a large amount of renewable energy into powergeneration is one of effective alternatives to reduce CO2 emissions.
・The advanced technology of gas turbine systems to achieve highflexibility is important for firming electric power grid.
2016
21
Research and Development of Advanced Gas Turbine for Firming Grid in Renewable Energy Age
Demand side
Renewable energy power generationAdvanced gas turbine systems
for firming grid
Time
Power demandPower supply
and demand
Based power
Renewable energy power
Advanced GT power
Image
2016
22
Research and Development of Advanced Gas Turbine for Firming Grid in Renewable Energy Age
1. Analysis of effects of rapid load change on gas turbine
2. Technology for rapid response and margin increase to loadchange
3. Rapid load following and rapid start-up technology
4. Technology to adjust power output by predicting load
5. Technology to suppress material degradation resultingfrom thermal transient response and cyclic stresses
R&D Items
20162016
23
Research and Development of Advanced Gas Turbine for Firming Grid in Renewable Energy Age
Targets of Development
Example of results
The Report will be uploaded on NEDO web site… coming soon
Gas Turbine size ~10MW 10~100MW 100MW~
Output change rate 40%/min 50%/min 50%/min
Minimum load ------- 10% 10%
Start-up time 5min 6min10min
(GTCC)
Maximum efficiency 36%(LHV) 58%(LHV) 63%(LHV)
2016
24
Low-Carbon Society
will be realized by
Many Future Key Power Technologies !
2016