issued for construction foothills landfill … cell 6...issued for construction foothills landfill...
TRANSCRIPT
Foothills Regional Service Commission
Issued For Construction
Foothills
Landfill Expansion – Cell 6
January 2018
Contract
Specifications
Ú±±¬¸·´´ λ¹·±²¿´ Í»®ª·½» ݱ³³··±² Í»½¬·±² ððððë
Ú±±¬¸·´´ Ô¿²¼º·´´ Û¨°¿²·±² ó Ý»´´ ê ÝÛÎÌ×Ú×ÝßÌ×ÑÒ ÐßÙÛ
îðïèóðïñîðïéóíêëðòðîð п¹» ï ±º ï
ÐæÄîðïéíêëðÄðîÁÝ»´́ êÁÛ¨°ÄÛ²¹·²»»®·²¹ÄðéòððÁݱ²¬®¿½¬Áܱ½ÁЮ»°Äððððëò¼±½æ Ö¿²«¿®§ îçô îðïè
Ú±±¬¸·´´ λ¹·±²¿´ Í»®ª·½» ݱ³³··±²
Ú±±¬¸·´´
Ô¿²¼º·´´ Û¨°¿²·±² � Ý»´´ ê
Ю»°¿®»¼ ¾§ ÒÔÎñßÛ Ý±²«´¬¿²¬
ÛÒÜ ÑÚ ÍÛÝÌ×ÑÒ
Foothills Regional Services Commission Section 00010
Foothills Landfill Expansion - Cell 6 TABLE OF CONTENTS
2018-01/2017-3650.020 Page 1 of 1
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00010.doc: January 29, 2018
TABLE OF CONTENTS PAGES
DIVISION 00 - BIDDING REQUIREMENTS
Section 00005 - Certification Page 1
Section 00010 - Table of Contents 1
Section 00015 - List of Drawings 1
Section 00200 - Instructions to Bidders 7
Section 00300 - Information for Bidders 1
Section 00410 - Bid Form 8
Section 00436 - Substitution List 1
Section 00437 - Subcontractor List 1
Section 00441 - Contract Time 1
Section 00442 - Construction Schedule 2
Section 00451 - Bidder's Qualifications 2
Section 00520 - Contract Agreement 4
Section 00611 - Consent of Surety Company 1
Section 00612 - Certificate of Recognition 1
Section 00614 - Performance Bond 1
Section 00615 - Labour and Material Payment Bond 1
Section 00623 - Certificate of Insurance 1
Section 00700 - General Conditions 66
Section 00710 - Insurance 2
Section 00800 - Supplementary Conditions 5
DIVISION 01 - GENERAL REQUIREMENTS
Section 01001 - General Requirements 15
Section 01270 - Measurement and Payment 12
Section 01450 - Quality Control 6
DIVISION 02 - SITE CONSTRUCTION
Section 02073 - Geomembranes 12
Section 02113 - Stripping 3
Section 02210 - Common Excavating and Grading 7
Section 02215 - Clay Liner 5
Section 02411 - Leachate Collection System 9
Section 02415 - Subdrain System 5
Section 02484 - Topsoil and Finish Grading 3
Section 02485 - Seeding 3
Section 02594 - Geosynthetic Clay Liner 7
Section 02690 - Miscellaneous Work 2
END OF DOCUMENT
Foothills Regional Services Commission Section 00015
Foothills Landfill Expansion - Cell 6 LIST OF DRAWINGS
2018-01/2017-3650.020 Page 1 of 1
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00015.doc: January 29, 2018
SEE APPENDIX FOR DRAWINGS
FOOTHILLS LANDFILL EXPANSION – CELL 6
Drawing No. Title
3650-02-0000 Cover Page
3650-02-1001 Overall Site Plan/Key Plan
3650-02-1002 Stripping Limits/Stockpile Layout Plan
3650-02-1003 Cell 6 Development Plan
3650-02-1004 Cell 6 Development Sections
3650-02-1005 Details Sheet 1 of 4
3650-02-1006 Details Sheet 2 of 4
3650-02-1007 Details Sheet 3 of 4
3650-02-1008 Details Sheet 4 of 4
END OF SECTION
Foothills Regional Services Commission Section 00200
Foothills Landfill Expansion - Cell 6 INSTRUCTIONS TO BIDDERS
2018-01/2017-3650.020 Page 1 of 7
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00200.doc: January 29, 2018
1 General
1.1 DEFINITIONS
.1 Definitions:
.1 “Bid Closing Time” means the time and date stipulated for receipt of bids in
Article 1.3.1.1 of this Section as may be amended by addendum.
.2 “Bid Documents” means the bid documents obtained in accordance with
Article 1.3.1.1 of these Instructions to Bidders and comprising all of the document
sections and drawings listed in the Table of Contents thereof, and any addenda that
may be issued thereto.
.3 “Bid Form” means Section 00410 of the Bid Documents and the supplements
thereto.
.4 “Bidder” means any holder of Bid Documents.
.5 “Total Bid” means the amount entered by the Bidder into the Bid Form as may be
adjusted as provided for by Articles 1.9.7.1 and 1.9.7.4 of this Section.
.2 Additional Definitions:
.1 The definitions set out in Section 00700 - General Conditions are incorporated
into and form part of this Section 00200 - Instructions to Bidders.
1.2 LIMITATION OF LIABILITY.1 The Bidder agrees that the Owner’s sole obligation, in return for the Bidder’s
preparation and submission of its bid, is to give consideration to the bid in accordance
with the Contract Documents. The Bidder hereby waives any claim for damages or
costs of any nature against the Owner and the Engineer (including, without limitation,
the cost of preparing and submitting the Tender, and any anticipated profits and
contributions to overhead) arising out of the Owner’s use of its discretion under the
Contract Documents and the Engineer’s advice to the Owner.
1.3 INVITATION
.1 Bid Call:
.1 Sealed bids marked “Bid for Foothills Regional Services Commission,Foothills Landfill Expansion - Cell 6” will be received by NLR/AE Consultants
located at Associated Engineering’s office at #400, 600 Crowfoot Crescent NW,
Calgary, AB T3G 0B4 on or before 2:00 pm Mountain Time on March 29, 2018:
.1 Offers will be opened in public, immediately after the time of receipt of bids.
.2 Faxed or e-mailed bid submissions will not be opened.
Foothills Regional Services Commission Section 00200
Foothills Landfill Expansion - Cell 6 INSTRUCTIONS TO BIDDERS
2018-01/2017-3650.020 Page 2 of 7
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00200.doc: January 29, 2018
.2 Pre-Tender Meeting:
.1 A pre-tender meeting will be held at the Foothills Regional Landfill & Resource
Recovery Centre on March 09, 2018 at 2:00 p.m. Mountain Time. Bidders and
attendees are required to wear the proper PPE; hard hat, steel toe boots, safety glasses.
Attendees must sign in at the scale office.
.2 Pre-tender meeting attendance is recommended for all Bidders. Failure to attend
the pre-tender meeting may result in rejection of the Bidder’s tender.
.3 The Bidder is directed to contact the Engineer at the following phone number in order
to arrange a site visit: Stan Reimer, P.Eng., Project Manager, Associated Engineering:
403-262-4500.
.4 The Bidder may arrange to do their own test-pitting investigation if they so choose.
1.4 INTENT.1 The intent of this bid process is to obtain an offer to perform work to construct a
Class II Landfill Cell at the Foothills Regional Landfill & Resource Centre, for a Unit
Price contract, in accordance with the Contract Documents. Refer to Section 01001 –
General Requirements for a description of work required and conditions under which
work will be carried out.
1.5 CONTRACT/BID DOCUMENTS
.1 Availability:
.1 Bid Documents may be obtained at the office of NLR/AE Consultants (the
Engineer) located at Associated Engineering’s office at #400, 600 Crowfoot
Crescent NW, Calgary, AB T3G 0B4.
.2 A refundable deposit of $100.00 per set in the form of cash or certified cheque
payable to Associated Engineering Alberta Ltd. is required to obtain bid documents.
.3 Alternatively, the Bid Documents can be downloaded from Merx or Alberta
Purchasing Connection (APC) at no charges to their members. Please be aware that it
is the Bidder’s responsibility to obtain any and all Addenda from the respective online
site that the original contract documents are obtained from.
.4 Subcontractors and suppliers can obtain additional Bid Documents upon request
from the Engineer listed in the RFP.
.5 Bid Documents are made available only for the purpose of obtaining offers for
this project. Their use does not confer a license or grant for other purposes.
.6 Refer to Section 00300 - Information for Bidders for identification of information
available to Bidders.
.2 Examination:
.1 Upon receipt of Bid Documents verify that documents are complete; notify
Engineer should the documents be incomplete.
.2 Immediately notify Engineer upon finding discrepancies or omissions in the Bid
Documents.
Foothills Regional Services Commission Section 00200
Foothills Landfill Expansion - Cell 6 INSTRUCTIONS TO BIDDERS
2018-01/2017-3650.020 Page 3 of 7
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00200.doc: January 29, 2018
.3 Queries/Addenda:
.1 Direct questions to: Stan Reimer, P.Eng., NLR/AE Consultants (403-262-4500)
listed in the RFP.
.2 Addenda may be issued during the bidding period. All addenda become part of
the Contract Documents. Include addenda requirements in the schedule of costs.
.3 Verbal answers are only binding when confirmed by written addenda.
.4 Clarifications requested by Bidders must be in writing not less than five (5)
working days before date set for receipt of bids. The reply will be in the form of an
addendum, a copy of which will be forwarded to Bidders no later than three (3)
working days before receipt of bids.
.4 Proposed Substitutions:
.1 Base Total Bid on use of specified products.
.2 Products other than those specified will be considered only if information is
provided on the Document 00436 - Substitution List in the Supplements to Bid Form.
.3 The submission shall provide sufficient information to enable the Engineer to
determine acceptability of such products.
.4 Provide complete information on required revisions to other work to
accommodate each substitution. The dollar amount of additions to or reductions from
the Total Bid, including revisions to other work, is to be shown on the Substitution
List.
.5 Unless substitutions are submitted in this manner and subsequently accepted,
provide products as specified.
.6 Approval to submit substitutions prior to submission of bids is not required.
.7 No ruling on a proposed substitution will be made prior to bid submission.
.8 Submit additional documentation supporting the proposed substitution(s) within
twenty-four (24) hours of a request to do so.
1.6 SITE ASSESSMENT.1 Site Examination:
.1 Visit the Project Site and surrounding area before submitting a bid.
.2 See Section 1.3.
1.7 QUALIFICATIONS.1 Bidder’s Qualifications:
.1 Submit completed Section 00451 – Bidder’s Qualification form with the Bid
Form.
.2 Indicate the OHS Act Certificate of Registration number. Refer to Section 00800 -
Supplementary Conditions.
.2 Subcontractors:
.1 Indicate on Section 00437 - Subcontractor List in the Supplements to Bid Form
the names of all subcontractor's proposed to be employed on the work.
Foothills Regional Services Commission Section 00200
Foothills Landfill Expansion - Cell 6 INSTRUCTIONS TO BIDDERS
2018-01/2017-3650.020 Page 4 of 7
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00200.doc: January 29, 2018
.2 A pre-qualified geosynthetic installation Subcontractor is to be used. Pre-qualified
Subcontractors are listed below:
.1 Primary Systems Ltd.
.2 Western Tank and Lining Ltd.
.3 Layfield Canada Ltd.
.4 Titan Environmental Containment Ltd.
.5 Nilex Construction Inc.
.3 Owner reserves the right to object to any of the subcontractors listed in
Section 0437 – Subcontractor List and such objection may be valid cause for rejection
of the bid. If Owner objects to a listed subcontractor then Owner will permit Bidder,
within five (5) days of such Notice, to propose a substitute subcontractor acceptable to
Owner provided that there is no resulting adjustment in the Total Bid or the Contract
Time. Bidder is not required to make such a substitution and, if Owner objects to a
listed subcontractor, rather than propose a substitute subcontractor, Bidder may by
Notice request that Owner rejects its bid and Owner will agree to that request.
1.8 BID SUBMISSION.1 Bid Ineligibility:
.1 Bids that are unsigned, improperly signed or sealed, conditional, illegible,
obscure, contain unbalanced prices, arithmetical errors, or irregularities of any kind,
may, at the discretion of Owner, be declared informal. If so declared, the bid will be
rejected.
.2 Bids with Bid Form, Supplements to Bid Form, or enclosures which are
improperly prepared may, at the discretion of Owner, be declared informal. If so
declared, the bid will be rejected.
.3 Bids that fail to include bonding or insurance requirements may be declared
informal. If so declared, the bid will be rejected.
.4 Bids are by invitation only from selected Bidders. Bids from unsolicited Bidders
will be returned.
.2 Submissions:
.1 Bidders shall be solely responsible for the delivery of their bids in the manner and
time prescribed.
.2 Submit one (1) copy of the executed offer on the Bid Form provided, signed and
corporate sealed together with the required supplements to the Bid Form to the
Engineer listed in the Bid Documents in a closed opaque envelope, clearly identified
with Bidder’s name, project name and Owner’s name. Retain a copy of the completed
Bid Form for Bidder’s records.
.3 Do not submit Bid Documents with Bid Form.
.4 A Bid Bond is not required.
.3 Bid Modifications:
.1 Amendments to the submitted bid will be permitted if received in hard copy at the
office where bids are being opened prior to Bid Closing Time, provided that bid
Foothills Regional Services Commission Section 00200
Foothills Landfill Expansion - Cell 6 INSTRUCTIONS TO BIDDERS
2018-01/2017-3650.020 Page 5 of 7
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00200.doc: January 29, 2018
amendments are endorsed by the same party or parties who signed and sealed the
offer.
.2 The onus is on Bidder to ensure timely receipt of bid modifications. To be
considered, bid modifications must be received in full prior to Bid Closing Time.
.4 Bid Withdrawal:
.1 Bidder shall be permitted to withdraw bid without prejudice, provided a request,
in writing, signed by the same person or persons who signed the Bid Form, is received
at the office designated in the Bid Documents before Bid Closing Time. Error on the
part of Bidder in preparing the bid confers no right to the withdrawal of the bid after it
has been opened.
1.9 BID ENCLOSURES/REQUIREMENTS.1 Consent of Surety:
.1 Submit with the Bid Form, a surety company’s letter of consent, stating that the
surety company is willing to supply the required Performance and Labour and
Materials Payment Bonds.
.2 Surety Company:
.1 Consent of Surety must be issued by a surety company licensed to conduct
business in the province or territory where the work is located.
.3 Performance Assurance:
.1 The accepted Bidder shall provide Performance and Labour and Materials
Payment Bonds as described in the Section 00700 - General Conditions.
.4 Cost of Bonds:
.1 Include the cost of bonds in the Total Bid.
.5 Certificate of Recognition:
.1 Submit with the Bid Form a Certificate of Recognition (COR) or a Temporary
Letter of Certification (TLC).
.6 Bid Form Requirements:
.1 Fill in unit prices where indicated in the Schedule of Quantities and Prices of
Section 00410 – Bid Form. Extend unit prices in accordance with quantities shown.
Insert extensions in spaces provided.
.2 Quantities shown against items listed in the Schedule of Quantities and Prices are
estimates and serve only to provide a basis for comparing bids. Payment in respect of
these items will be in accordance with the Contract Documents.
.3 Fill in prices where indicated on Bid Form.
.4 In the event of a discrepancy between unit prices and extension, unit prices will
govern and Engineer will correct extensions accordingly.
.5 In the event of a discrepancy between the sum of prices and extensions and Total
Bid, prices and extensions will govern and the Engineer will correct Total Bid
accordingly.
Foothills Regional Services Commission Section 00200
Foothills Landfill Expansion - Cell 6 INSTRUCTIONS TO BIDDERS
2018-01/2017-3650.020 Page 6 of 7
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00200.doc: January 29, 2018
.6 Include in price(s) bid supply of all materials except those specified to be supplied
by others, all supervision, labour and equipment, and a provision for sales taxes, duties
overhead and profit. Total Bid shall represent the entire cost to Owner for the
completed works as specified and shown on the Drawings, exclusive only of GST
payable by Owner.
.7 The amount of GST payable by Owner on goods and services provided under this
Contract is in addition to the Total Bid and is to be shown on a separate line on the Bid
Form.
.8 Bid analysis will be based on the Total Bid price, exclusive of GST.
.7 Bid Signing:
.1 The Bid Form shall be executed by Bidder as follows:
.1 Sole Proprietorship: signature of sole proprietor in the presence of a witness
who will also sign. Insert the words "Sole Proprietor" under the signature.
.2 Partnership: signature of all partners in the presence of a witness who will
also sign. Insert the word partner under each signature.
.3 Limited Company: signature of a duly authorized signing officer(s) in their
normal signatures. Insert the officer's capacity in which the signing officer acts,
under each signature. Affix the corporate seal.
.4 Joint Venture: each party of the joint venture shall execute the bid under their
respective seals in a manner appropriate to such party as described above, similar
to the requirements of a Partnership.
.8 Supplements to Bid Form to be submitted with Bid:
.1 See Section 00410 – Supplements to Bid Form.
.9 Supplements to Bid Form for post-bid Submission:
.1 See Section 00410 – Supplements to Bid Form.
1.10 OFFER ACCEPTANCE/REJECTION.1 Duration of Offer:
.1 Bids shall remain open to acceptance and shall be irrevocable for a period of
sixty (60) days after the bid closing date.
.2 Acceptance of Offer:
.1 Owner reserves the right to accept any offer, waive defects in any offer, or reject
any or all offers.
.2 After acceptance of an offer by the Owner, the Engineer, on behalf of Owner, will
issue a written Notice of Award to accepted Bidder.
Foothills Regional Services Commission Section 00200
Foothills Landfill Expansion - Cell 6 INSTRUCTIONS TO BIDDERS
2018-01/2017-3650.020 Page 7 of 7
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00200.doc: January 29, 2018
.3 Award Conditions:
.1 The following conditions must be satisfied before Owner can make the award
decision:
.1 Approval of the project by the regulatory authorities.
2 Products
Not Used.
3 Execution
Not Used.
END OF SECTION
Foothills Regional Services Commission Section 00300
Foothills Landfill Expansion - Cell 6 INFORMATION FOR BIDDERS
2018-01/2017-3650.020 Page 1 of 1
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00300.doc: January 29, 2018
1 General
1.1 GEOTECHNICAL REPORT
.1 The geotechnical report is available upon request. This report has been prepared for
the Owner by an independent specialist consultant. While the data contained therein is
believed to be accurate, any opinions or recommendations are solely those of the
authors of the geotechnical report. Bidders must form their own conclusions from the
data and shall make no claim at any time that any opinion or recommendation is
incorrect or misleading. Neither the Owner nor the Engineer accepts responsibility for
the contents of this report nor for the suggestions or recommendations contained
therein. In making this disclaimer the Owner will be deemed to be acting as the
Trustee for the Engineer.
END OF SECTION
Foothills Regional Services Commission Section 00410
Foothills Landfill Expansion - Cell 6 BID FORM
2018-01/2017-3650.020 Page 1 of 8
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00410.doc: January 29, 2018
Foothills Regional Services Commission
Foothills
Landfill Expansion – Cell 6
TO: Joe Angevine
Foothills Regional Services Commission
309 Macleod Trail, Box 5606
High River, AB
T1V 1M7
The undersigned Bidder, having carefully examined the Contract Documents and locality of the
proposed work, and having full knowledge of the work required and the materials to be furnished
and used, hereby agrees to provide all necessary materials, supervision, labour and equipment
and perform and complete all work, and fulfill everything as set forth and in strict accordance
with the Contract Documents and Addenda numbered 1__________ for the prices stated in the
Schedule of Quantities and Prices.
1 Bidder to fill in each Addendum No. received, e.g., 1, 2, 3, etc. as applicable.
Foothills Regional Services Commission Section 00410
Foothills Landfill Expansion - Cell 6 BID FORM
2018-01/2017-3650.020 Page 2 of 8
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00410.doc: January 29, 2018
The undersigned also agrees:
1 That Owner is in no way obligated to accept this bid.
2 That, if the Bid Form is improperly completed or incomplete, Owner shall have the right
to disqualify and/or reject this bid.
3 That this bid is made without knowledge of the bid prices to be submitted for this work
by any other company, firm, or person.
4 That this bid is made without any connection or arrangement with any other company,
firm, or person submitting a bid for this work.
5 That this bid is made without any undisclosed connection or arrangement with any other
company, firm, or person having an interest in this bid or in the proposed Contract.
6 That this bid is irrevocable for sixty (60) days after the closing date for receipt of bids
and that the Owner may, at any time within such period, accept this bid whether any other
bid has previously been accepted or not and whether Notice of Award of a contract has
been given or not.
7 To deposit with Owner a Performance Bond and Labour and Material Payment Bond on
the forms provided in these documents and for the amount specified in the General
Conditions and the specified insurance endorsement certificates and execute the Contract
Agreement in accordance with the time periods specified in the General Conditions, such
time periods being extended only on the written approval of Owner.
8 To commence and proceed actively with the work promptly following receipt of the
Notice to Proceed, and to complete all work under the Contract within a period of
_______ calendar days from Notice of Award, subject to the provisions of the General
Conditions for extension of Contract Time.
9 To compensate Owner in accordance with the Contract Documents if the work is not
completed within the Contract Time.
10 To do all extra work not reasonably inferable from the specifications or drawings, but
called for in writing by Engineer and to accept as full compensation therefor payment in
accordance with the provisions of the General Conditions.
11 That estimates of quantities shown in the Bid Form serve only to provide a basis for
comparing bids and that no representations have been made by either Owner or Engineer
that the actual quantities will even approximately correspond therewith, and further, that
Owner has the right to increase or decrease the quantities in any or all items and to
eliminate items entirely from the work.
Foothills Regional Services Commission Section 00410
Foothills Landfill Expansion - Cell 6 BID FORM
2018-01/2017-3650.020 Page 3 of 8
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00410.doc: January 29, 2018
12 That payment for the work done will be made on the basis of the quantities measured by
Engineer and at the prices shown in the Bid Form which shall be compensation in full for
the work done under the terms of the Contract, exclusive of GST payable by Owner.
13 That, in preparing this bid, the Bidder has drawn their own conclusions from the data
contained in the geotechnical report bound with these and has not relied on the opinions
or the recommendations of the authors of the geotechnical report.
Foothills Regional Services Commission Section 00410
Foothills Landfill Expansion - Cell 6 BID FORM
2018-01/2017-3650.020 Page 4 of 8
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00410.doc: January 29, 2018
SCHEDULE OF QUANTITIES AND PRICES
The following are our prices, exclusive of GST payable by the Owner, for the cost of work for
each item as outlined in the respective payment clauses in the Specifications.
Item Description Unit Estimated Quantity Unit Rates Estimated
Amount PART A - GENERAL REQUIREMENTS 1.0 Mobilization and
Demobilization L.S. 1
2.0 Layout and Record Survey L.S. 1
3.0 Safety L.S. 1
Part A Sub-Total
PART B - LANDFILL DEVELOPMENT 4.0 Stripping Hauled to
Stockpiles:
4.1 Topsoil and Subsoil
Stripping m3 13,750
5.0 Common Excavation:
5.1 Common Excavation to
Berm Embankment m3 4,900
5.2 Common Excavation to
Stockpiles m3 69,600
6.0 Compacted Clay Liner m2 29,100
7.0 Geosynthetic Clay Liner:
7.1 Supply Geosynthetic Clay
Liner m2 3,700
7.2 Install Geosynthetic Clay
Liner m2 3,700
8.0 60 mil HDPE Liner:
8.1 Supply 60 mil HDPE Liner m2 32,400
8.2 Install 60 mil HDPE Liner m2 32,400
9.0 Leachate Collection System:
9.1 Perimeter and Interior
(Type 1) Leachate Trench l.m. 337
9.2 Install Owner Supplied Tire
Shred m3 12,000
9.3 Riser - Leachate ea 1
10.0 Groundwater Subdrain
System:
10.1 Subdrain Trench l.m. 340
10.2 Riser - Subdrain L.S. 1
Foothills Regional Services Commission Section 00410
Foothills Landfill Expansion - Cell 6 BID FORM
2018-01/2017-3650.020 Page 5 of 8
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00410.doc: January 29, 2018
11.0 2-Sided Geocomposite:
11.1 Supply 2-Sided
Geocomposite m2 900
11.2 Install 2-Sided
Geocomposite m2 900
12.0 Light Geotextile:
12.1 Supply Light Geotextile m2 1,300
12.2 Install Light Geotextile m2 1,300
13.0 Heavy Geotextile:
13.1 Supply Heavy Geotextile m2 30,000
13.2 Install Heavy Geotextile m2 30,000
14.0 Sand Tubes:
14.1 Supply Sand Tubes ea 60
14.2 Install Sand Tubes ea 60
15.0 Barricades and Markers:
15.1 Supply Lock Blocks ea 15
15.2 Install Lock Blocks ea 15
Part B Sub-Total
PART C - LANDFILL INFRASTRUCTURE 16.0 Topsoil Hauled from
Stockpile, Placement and
Finished Grading m2 6,300
17.0 Seeding of Disturbed Areas,
Ditches and Stockpiles m2 32,900
Part C Sub-Total
PART D - PROVISIONAL ITEMS 18.0 Provisional Groundwater
Subdrain:
18.1 Supply 2-Sided
Geocomposite m2 400
18.2 Install 2-Sided
Geocomposite m2 400
19.0 Rock Excavation:
19.1 Solid Rock Excavation m3 3,500
Part D Sub-Total
Foothills Regional Services Commission Section 00410
Foothills Landfill Expansion - Cell 6 BID FORM
2018-01/2017-3650.020 Page 6 of 8
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00410.doc: January 29, 2018
BID SUMMARY
TOTAL A - GENERAL REQUIREMENTS: $
TOTAL B - LANDFILL DEVELOPMENT: $
TOTAL C - LANDFILL INFRASTRUCTURE: $
TOTAL D - PROVISIONAL ITEMS: $
TOTAL BID: (excluding GST) $
Goods and Services Tax: $
Foothills Regional Services Commission Section 00410
Foothills Landfill Expansion - Cell 6 BID FORM
2018-01/2017-3650.020 Page 7 of 8
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00410.doc: January 29, 2018
SUPPLEMENTS TO BID FORM
The following Supplements to Bid Form are included with and form a part of our Bid. We
understand that the information provided on these forms will be used by the Owner during Bid
analysis.
00436 - Substitution List
00437 - Subcontractor List
00441 - Contract Time
00451 - Bidder's Qualifications
00611 - Consent of Surety Company
00612 - Certificate of Recognition
00623 - Certificate of Insurance
Following bid submission, upon request from the Engineer, Bidders under consideration for
contract award are required to complete the following Supplements to Bid Form within two (2)
Business Days of receipt of the request, or as directed by the Engineer:
00442 - Construction Schedule (in Gantt format)
Foothills Regional Services Commission Section 00410
Foothills Landfill Expansion - Cell 6 BID FORM
2018-01/2017-3650.020 Page 8 of 8
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00410.doc: January 29, 2018
This bid is executed under seal at _______________________________________________ this
day of ________________________________, 20___.
Name of Firm
Address
For Individual or Partnership: SIGNED, SEALED AND DELIVERED by:
Bidder (please print) Signature
in the presence of:
Title
Name
Address
City/Province/PC
Seal
Occupation
For Limited Company or Corporation:
The Corporate Seal of:
Bidder (please print)
was hereunto affixed in the presence of:
Authorized Signing Officer Title Seal
Authorized Signing Officer Title
NOTE: If the bid is by joint venture, add additional forms of execution for each member
of the joint venture in the appropriate form or forms as above.
END OF SECTION
Foothills Regional Services Commission Section 00436
Foothills Landfill Expansion - Cell 6 SUBSTITUTION LIST
2018-01/2017-3650.020 Page 1 of 1
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00436.doc: January 29, 2018
Supplement to Bid Form
We propose using the following equipment and/or materials as substitutes for those specified and
shown on the drawings. Should any of these proposed substitutes be accepted, we will adjust our
Total Bid in accordance with the price variations shown below. These prices will represent the
total cost difference to the Owner for supply and installation of the proposed substitute products
in lieu of those specified.
Item Product Brand Name orManufacturer Supplier Price
Variation
END OF SECTION
Foothills Regional Services Commission Section 00437
Foothills Landfill Expansion - Cell 6 SUBCONTRACTOR LIST
2018-01/2017-3650.020 Page 1 of 1
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00437.doc: January 29, 2018
Trade/Supplier Name of Subcontractor Full Time/Part Time
Geomembrane Supplier
Geomembrane Installer
GCL Supplier
GCL Installer
Aggregate Supplier
Geocomposite Supplier
Geocomposite Installer
Geotextile Supplier
Geotextile Installer
PVC Pipe Supplier
PE Pipe Supplier
Survey Services
All subcontractors have reviewed specific submittal and QC requirements related to their scope of
Work? YES/NO.
END OF SECTION
Foothills Regional Services Commission Section 00441
Foothills Landfill Expansion - Cell 6 CONTRACT TIME
2018-01/2017-3650.020 Page 1 of 1
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00441.doc: January 29, 2018
CONTRACT PERIOD - TOTAL NUMBER OF CALENDAR DAYS
1. The Bidder shall indicate the total number of Calendar Days required to complete the
Work.
2. The Bidder agrees to complete all the Work herein on or before the total number of
Calendar Days.
3. The total number of Calendar Days required to complete the Work under the terms and
conditions of this Contract, as indicated below, shall exclude the time required by the
Geosynthetics Installation Contractor to complete their specific scope of Work.
Total number of Calendar Days required to complete the Work ______________________.
END OF SECTION
Foothills Regional Services Commission Section 00442
Foothills Landfill Expansion - Cell 6 CONSTRUCTION SCHEDULE
2018-01/2017-3650.020 Page 1 of 2
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00442.doc: January 29, 2018
1 General
1.1 CONSTRUCTION SCHEDULE REQUIREMENTS
.1 The Bidder shall, as part of the tender submission requirements, submit a construction
schedule for the Owner’s review and comments.
.2 The construction schedule will be reviewed and analysed by the Owner and Engineer
and will be considered as part of the Bidder’s tender. The acceptability of the
information given on the construction schedule will be an integral component in the
Owner’s selection of the successful Bidder.
.3 It is the responsibility of the Bidder to prepare a construction schedule that reflects the
Bidder’s own timeline for completing the Work according to the Bidder’s total number
of Calendar Days required to complete the Work. The Bidder shall exclude the time
required by the Geosynthetics Installation Contractor to complete their specific scope
of Work.
.4 Preference will be given to bidders whose construction schedule indicated the least
total number of Calendar Days required to complete the Work.
.5 The Owner and/or Engineer may review the schedule with the Bidder prior to award of
the Contract and request revisions be made to the schedule as a condition of award of
the Contract. If such revisions are requested, the Bidder shall make any and all such
revisions to the schedule and re-submit the revised schedule as specified in Item 1.2.4,
at the Bidder’s expense.
.6 The finalized form of the construction schedule, that is acceptable to the Owner, shall
form part of the Contract documents.
1.2 FORM OF SCHEDULE
.1 The construction schedule shall be in the form of a Gantt chart in pdf format.
.2 The construction schedule shall be set up for ease of tracking, on a weekly basis, of the
items of Work listed in the schedule.
.3 The items of Work listed in the construction schedule shall consist of the items of
Work given in Section 00410 - Bid Form. The construction schedule shall incorporate
parts A, B and C (exclude Part D - Provisional Items).
.4 The construction schedule submission shall consist of one (1) hard copy in the tender
package. Electronic copies, either on CD or a Microsoft Excel spreadsheet, shall be
submitted to the Engineer on the day following the tender closing date.
.5 The time line of the construction schedule shall commence from the date of notice to
proceed to the end of the total number of Calendar Days required to complete the
Foothills Regional Services Commission Section 00442
Foothills Landfill Expansion - Cell 6 CONSTRUCTION SCHEDULE
2018-01/2017-3650.020 Page 2 of 2
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00442.doc: January 29, 2018
Work, as stated by the contractor in the bid documents. The time line shall be divided
into seven (7) day (weekly) periods; each subdivided into days.
.6 The construction schedule shall make allowances for possible weather and/or other
delays and shall indicate “float” time allowance(s) to make up for any progress delays.
.7 The schedule, in the form of footnotes, shall specify the following:
.1 Number of days per Work week for the Bidder’s own forces and those of the
sub-contractors.
.2 Number of working hours per day for the Bidder’s own forces and those of the
sub-contractors.
.3 Location of materials and average estimated delivery duration to site.
.4 Average daily Work force for the Bidder’s own forces and those of the
sub-contractors that will be maintained on the project.
END OF SECTION
Foothills Regional Services Commission Section 00451
Foothills Landfill Expansion - Cell 6 BIDDER'S QUALIFICATIONS
2018-01/2017-3650.020 Page 1 of 2
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00451.doc: January 29, 2018
1 General
1.1 PROVIDE THE QUALIFICATIONS OF THE PERSONNEL SPECIFIED INTHE TABLE BELOW FOR BOTH THE BIDDER’S OWN FORCES AND ALLSUBCONTRACTORS AND SUB-TRADES.
Person Position Years ofExperience Previous Similar Projects
A. Bidder’s Own Forces(Project Manager, Site Superintendent, Foreman, QC Coordinator)
Project Manager
Site Superintendent
Quality Control Inspector
Foreman
Safety Coordinator
Geosynthetics Installation
Coordinator
B. Subcontractors(Survey, Geosynthetics)
Survey Crew Chief
Geosynthetics Foreman
C. Sub-Trades
Foothills Regional Services Commission Section 00451
Foothills Landfill Expansion - Cell 6 BIDDER'S QUALIFICATIONS
2018-01/2017-3650.020 Page 2 of 2
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00451.doc: January 29, 2018
1.2 PROVIDE THE FOLLOWING INFORMATION IN ORDER THAT THEOWNER MAY JUDGE THE BIDDER’S ABILITY TO FULFIL THECONTRACT REQUIREMENTS.
.1 The Bidder has completed a quality control plan in the past? Yes/No
.2 The Bidder’s proposed shift required to perform the Work detailed is ______
hours/day _____ days/week.
.3 The average number of workers the Bidder will employ and maintain on the project is
________.
.4 Include the resume of the Site Superintendent proposed to Work on the project and his
previous experience on this type of construction.
.5 Include the resume of the Foreman proposed to Work on the project and his previous
experience on this type of construction.
.6 Include the resume of the person responsible for completing the quality control
inspection of the Works (if other than the Site Superintendent or Foreman)
____________________.
.7 Include the resume of the Safety Coordinator (if other than the Site Superintendent or
Foreman).
.8 Include the resume of the Geosynthetics Installation Coordinator (if other than the Site
Superintendent or Foreman).
END OF SECTION
Foothills Regional Services Commission Section 00520
Foothills Landfill Expansion - Cell 6 CONTRACT AGREEMENT
2018-01/2017-3650.020 Page 1 of 4
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00520.doc: January 29, 2018
THIS AGREEMENT made this _______________________ day of _____________________
in the year 20___ by and between Foothills Regional Services Commission, herein called
"Owner," and ___________________________________, herein called "Contractor".
WITNESSETH: That Contractor and Owner undertake and agree as follows:
ARTICLE 1.
Contractor shall:
1. Provide all necessary materials, labour, supervision and equipment, and perform all work
and fulfill everything as set forth and in strict accordance with the Contract Documents
and Addenda numbered ___ for the project entitled “Foothills Regional Services
Commission Landfill Expansion – Cell 6” which have been prepared by NLR/AE
Consultants, acting as and hereby entitled Engineer; and
2. Commence to proceed actively with the work of the Contract promptly following receipt
of the Notice to Proceed, and achieve Total Performance of the Work within a period of
______ calendar days from the date of the Notice of Award, subject to the provisions for
the extension of Contract Time stipulated in the General Conditions.
ARTICLE 2.
Owner will pay to Contractor, as full compensation for the performance and fulfilment of this
Contract, the sum or sums of money specified herein in the manner and at the times specified in
the Contract Documents.
ARTICLE 3.
All of the Contract Documents, including but not limited to the Instructions to Bidders,
Information Available to Bidders, Bid Form, Supplements to Bid Form, Novation Agreement,
Bonds, Insurance, General Conditions, Supplementary Conditions, Special Provisions, Addenda,
Appendices, Specifications and Drawings, whether annexed hereto or contained in a separate
volume, are incorporated herein and form a part of this Agreement as fully to all intents and
purposes as though recited in full herein, and the whole shall constitute the Contract between the
parties, and it shall enure to the benefit of and be binding upon them and their successors,
executors, administrators, and assigns.
ARTICLE 4.
No implied contract of any kind whatsoever, by or on behalf of Owner, shall arise or be implied
from anything contained in this Contract or from any position or situation of the parties at any
time, it being understood and agreed that the express contracts, covenants, and agreements
contained herein and made by the parties hereto are and shall be the only contracts, covenants,
and agreements on which any rights against Owner may be founded.
Foothills Regional Services Commission Section 00520
Foothills Landfill Expansion - Cell 6 CONTRACT AGREEMENT
2018-01/2017-3650.020 Page 2 of 4
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00520.doc: January 29, 2018
ARTICLE 5.
Subject to Article 3, this Agreement shall supersede all communications, negotiations, and
agreements, either written or verbal, made between the parties hereto in respect of matters
pertaining to this Agreement prior to the execution and delivery hereof.
ARTICLE 6.
Any Notice to be given by either Party pursuant to this Agreement, or Engineer, shall be in
writing and delivered personally, by commercial courier or transmitted by fax to the following
addresses and fax numbers, as applicable:
Contractor at:
Address:
Fax: Email:
Owner at: Foothills Regional Services Commission
Address: 309 Macleod Trail, Box 5606, High River, Alberta T1V 1M7
Fax: Email: [email protected]
Engineer at: Associated Engineering Alberta Ltd.
Address: #400, 600 Crowfoot Crescent NW, Calgary, AB T3G 0B4
Fax: 403.269.7640 Email: [email protected]
A Notice shall be deemed to have been given and received on the date on which it was delivered
or transmitted, if delivered or transmitted on a Business Day during the regular business hours of
the recipient. If it is delivered or transmitted on a day that is not a Business Day or outside the
regular business hours of the recipient, the Notice shall be deemed to have been delivered or
transmitted on the following Business Day.
A Party may change its address for receipt of Notices at any time by giving Notice of the change
to the other Party and Engineer in accordance with this provision. Engineer may change its
address for receipt of Notices at any time by giving Notice of the change to the Parties in
accordance with this provision. Such changed address for receipt of Notices will be effective
five (5) Business Days after receipt of the Notice by the recipient.
Email may be used for day-to-day communication between the Parties and others working on the
Project, but email shall not be used for the delivery of a Notice which is required to be given by
this Agreement.
Foothills Regional Services Commission Section 00520
Foothills Landfill Expansion - Cell 6 CONTRACT AGREEMENT
2018-01/2017-3650.020 Page 3 of 4
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00520.doc: January 29, 2018
IN WITNESS WHEREOF the parties hereto have executed this Agreement the day and year
above first written.
For Individual or Partnership:SIGNED, SEALED AND DELIVERED by:
Contractor (please print) Signature
in the presence of:
Title
Name
Address
City/Prov/PC
Seal
Occupation
For Limited Company:The Corporate Seal of:
Contractor (please print)
was hereunto affixed in the presence of:
Authorized Signing Officer Title
Seal
Authorized Signing Officer Title
NOTE: If Contractor is a joint venture, add additional forms of execution for each
member of the joint venture in the appropriate form or forms as above.
Foothills Regional Services Commission Section 00520
Foothills Landfill Expansion - Cell 6 CONTRACT AGREEMENT
2018-01/2017-3650.020 Page 4 of 4
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00520.doc: January 29, 2018
For Corporate Owner:
The Corporate Seal of:
Foothills Regional Services Commission
Owner (please print full corporate name)
was hereunto affixed in the presence of:
Authorized Signing Officer Title
Seal
Authorized Signing Officer Title
END OF SECTION
Foothills Regional Services Commission Section 00611
Foothills Landfill Expansion - Cell 6 CONSENT OF SURETY COMPANY
2018-01/2017-3650.020 Page 1 of 1
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00611.doc: January 29, 2018
END OF SECTION
Foothills Regional Services Commission Section 00612
Foothills Landfill Expansion - Cell 6 CERTIFICATE OF RECOGNITION
2018-01/2017-3650.020 Page 1 of 1
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00612.doc: January 29, 2018
END OF SECTION
Foothills Regional Services Commission Section 00614
Foothills Landfill Expansion - Cell 6 PERFORMANCE BOND
2018-01/2017-3650.020 Page 1 of 1
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00614.doc: January 29, 2018
END OF SECTION
Foothills Regional Services Commission Section 00615
Foothills Landfill Expansion - Cell 6 LABOUR AND MATERIAL PAYMENT BOND
2018-01/2017-3650.020 Page 1 of 1
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00615.doc: January 29, 2018
END OF SECTION
Foothills Regional Services Commission Section 00623
Foothills Landfill Expansion - Cell 6 CERTIFICATE OF INSURANCE
2018-01/2017-3650.020 Page 1 of 1
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00623.doc: January 29, 2018
END OF SECTION
Foothills Regional Services Commission Section 00700
Foothills Landfill Expansion - Cell 6 GENERAL CONDITIONS TABLE OF CONTENTS
2018-01/2017-3650.020 Page i of iii
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00700.doc: January 29, 2018
PART 1 CONTRACT DOCUMENTS 1
GC 1. DEFINITIONS 1
GC 2. INTERPRETATION AND GENERAL PROVISIONS 7
GC 3. LAW OF THE CONTRACT AND ATTORNMENT 8
GC 4. PRECEDENCE OF DOCUMENT FOR INTERPRETATION 8
GC 5. USE OF THE CONTRACT DOCUMENTS 9
GC 6. NO WAIVER 10
GC 7. NO ASSIGNMENT WITHOUT CONSENT 10
GC 8. SURVIVAL 10
PART 2 INSURANCE, WORKERS’ COMPENSATION AND BONDS 11
GC 9. INSURANCE 11
GC 10. WORKERS’ COMPENSATION 11
GC 11. BONDS 12
PART 3 GENERAL PROVISIONS 12
GC 12. EXECUTION OF THE CONTRACT AGREEMENT 12
GC 13. CONDUCT OF THE WORK 13
GC 14. ACTIVITIES 14
PART 4 ADMINISTRATION OF THE CONTRACT 15
GC 15. AUTHORITY OF THE ENGINEER 15
GC 16. ROLE AND RESPONSIBILITY OF THE ENGINEER 15
GC 17. REVIEW AND INSPECTION OF THE WORK 17
GC 18. DEFICIENCIES 19
PART 5 EXECUTION OF THE WORK 19
GC 19. CONTROL OF THE WORK 19
GC 20. ELECTRONIC INFORMATION 20
GC 21. LAYOUT OF THE WORK 20
GC 22. CONSTRUCTION BY THE OWNER OR OTHER CONTRACTORS 21
GC 23. SUSPENSION OF WORK BY OWNER 22
GC 24. TEMPORARY SUPPORTS, STRUCTURES AND FACILITIES 23
GC 25. CONSTRUCTION SCHEDULE 24
GC 26. SAFETY 25
Foothills Regional Services Commission Section 00700
Foothills Landfill Expansion - Cell 6 GENERAL CONDITIONS TABLE OF CONTENTS
2018-01/2017-3650.020 Page ii of iii
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00700.doc: January 29, 2018
GC 27. SUPERINTENDENT AND KEY PERSONNEL 26
GC 28. SUBCONTRACTORS 26
GC 29. LABOUR AND MATERIALS 27
GC 30. DOCUMENTS AT THE SITE 28
GC 31. SHOP DRAWINGS 28
GC 32. STEWARDSHIP OF THE PROJECT SITE 30
PART 6 PROTECTION OF PERSONS AND PROPERTY AND TOXIC ORHAZARDOUS SUBSTANCES 31
GC 33. PROTECTION OF WORK AND PROPERTY 31
GC 34. TOXIC OR HAZARDOUS SUBSTANCES 32
PART 7 PAYMENT AND ALLOWANCES 34
GC 35. GENERAL PROVISIONS RELATING TO PAYMENT 34
GC 36. FINANCIAL INFORMATION REQUIRED OF THE CONTRACTOR 34
GC 37. PROGRESS PAYMENTS 34
GC 38. PROGRESS PAYMENT HOLDBACKS 36
GC 39. QUANTITIES 37
GC 40. SUBSTANTIAL PERFORMANCE OF THE WORK 38
GC 41. RELEASE OF MAJOR LIEN FUND HOLDBACK 39
GC 42. TOTAL PERFORMANCE OF THE WORK AND FINAL PAYMENT 39
GC 43. RELEASE OF MINOR LIEN FUND HOLDBACK 41
GC 44. WITHHOLDING OF PAYMENT AND SET OFF 41
GC 45. PROGRESSIVE RELEASE OF HOLDBACK TO SUBCONTRACTORS AND
SUPPLIERS 42
PART 8 TAXES AND DUTIES 43
GC 46. RESPONSIBILITY FOR TAXES AND DUTIES 43
PART 9 TIMELY CONSTRUCTION 43
GC 47. DELAY 43
GC 48. LATE COMPLETION 46
PART 10 TERMINATION 46
GC 49. OWNER’S RIGHT TO TERMINATE FOR DEFAULT 46
GC 50. CONTRACTOR’S RIGHT TO TERMINATE FOR DEFAULT 48
GC 51. TERMINATION FOR CONVENIENCE 49
Foothills Regional Services Commission Section 00700
Foothills Landfill Expansion - Cell 6 GENERAL CONDITIONS TABLE OF CONTENTS
2018-01/2017-3650.020 Page iii of iii
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00700.doc: January 29, 2018
GC 52. OBLIGATIONS ON TERMINATION 49
PART 11 CHANGES AND CONCEALED OR UNKNOWN CONDITIONS 50
GC 53. CHANGES 50
GC 54. CONTEMPLATED CHANGE NOTICES AND CHANGE ORDERS 51
GC 55. CHANGE DIRECTIVES 53
GC 56. FORCE ACCOUNT WORK 53
GC 57. CONCEALED OR UNKNOWN CONDITIONS 55
PART 12 DISPUTE RESOLUTION 56
GC 58. CLAIMS 56
GC 59. APPLICABLE TO ALL DISPUTES 56
GC 60. NEGOTIATION 57
GC 61. MEDIATION 58
PART 13 INDEMNIFICATIONS AND WARRANTY 58
GC 62. INDEMNIFICATIONS 58
GC 63. WARRANTY 60
PART 14 CONFIDENTIALITY AND FREEDOM OF INFORMATION 61
GC 64. CONFIDENTIALITY 61
PART 15 INTELLECTUAL PROPERTY AND TITLE TO THE WORK 62
GC 65. INTELLECTUAL PROPERTY 62
GC 66. BUILDERS LIENS AND TITLE TO THE WORK 62
GC 67. RECORDS 63
Foothills Regional Services Commission Section 00700
Foothills Landfill Expansion - Cell 6 GENERAL CONDITIONS
2018-01/2017-3650.020 Page 1 of 63
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00700.doc: January 29, 2018
PART 1 CONTRACT DOCUMENTS
GC 1. DEFINITIONS
In this Contract, the following definitions shall apply:
“Abnormal Weather” means adverse temperature, precipitation, wind or other adverse weather
condition which, in any two (2) week period, differs from the statistical average for that
condition in that period by more than one standard deviation, calculated based on relevant data
available from Environment Canada, covering the twenty (20) year period immediately
preceding the Notice of Award.
“Business Day” means any day other than a Saturday, Sunday or statutory holiday recognized in
the province or territory wherein the Project Site is located.
“Certificate of Insurance” means a document issued by an insurance company or authorised
broker to certify the extent, period and limits of insurance coverage under specific conditions
granted to listed Persons.
“Certificate of Substantial Performance” means a certificate issued by the Engineer stating
that Substantial Performance of the Work has been achieved.
“Certificate of Total Performance” means a certificate issued by the Engineer stating that Total
Performance of the Work has been achieved.
“Change” means an increase or addition to, a reduction or deletion from or an extension of the
Work or the Construction Schedule, or the replacement of a proposed subcontractor or supplier,
which results in a material change to the Contract Time or Contract Price.
“Change Directive” means a written instruction signed by the Owner and issued by the Engineer
to the Contractor directing the Contractor to proceed with a Change despite the absence of an
agreement as to adjustment of the Contract Price or Contract Time, or both, as applicable.
“Change Order” means a written record of a Change prepared by the Engineer and signed by
the Owner, the Engineer and the Contractor stating their agreement to a Change, and setting out a
description of the Work covered by the Change Order, the price or method of valuation of the
Work and the change in the Contract Price or adjustment of the Contract Time, or both, as
applicable.
“Claim” means a written demand for adjustment of the Contract Price or Contract Time made by
either Party against the other Party.
“Confidential Information” means all information that is acquired by, or becomes known to,
the Contractor or any of its Personnel, or Subcontractors as a result of, directly or indirectly,
performing the Work, or otherwise being involved in the Project and which is in the nature of
one of the following categories of information:
Foothills Regional Services Commission Section 00700
Foothills Landfill Expansion - Cell 6 GENERAL CONDITIONS
2018-01/2017-3650.020 Page 2 of 63
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00700.doc: January 29, 2018
(a) all information with respect to the Owner’s operations, the Project and this Contract; or
(b) all personal information as defined in the Freedom of Information and Protection of
Privacy legislation in the jurisdiction in which the Work is performed.
“Consequential Damages” means all damages except direct damages, including any one or
more of: loss of profits or anticipated profits, loss of business opportunity, loss of revenue and
loss of reputation.
“Construction Equipment” means all tools, machinery and equipment whether operated or not
operated, which are required for preparing, fabricating, conveying, erecting or otherwise
performing the Work but are not incorporated into the Work.
“Construction Schedule” means the schedule for the Work which is prepared by the Contractor
and approved by the Owner and the Engineer in accordance with GC 25 CONSTRUCTION
SCHEDULE.
“Construction Safety Plan” means the plan developed by the Contractor to address safety on
the Project Site, and anywhere else that the Work is performed.
“Contemplated Change Notice” means a written notification authorized and issued by or on
behalf of the Owner, providing Notice and Specifications or Drawings, or both, to the Contractor
and others of a contemplated Change and requesting a quotation for adjustments of Contract
Price and Contract Time that would result from the Change.
“Contract Documents” or “Contract” means the complete set of documents, Specifications,
Drawings, and addenda incorporated therein, as listed in the “Table of Contents” of the Contract
and any amendments thereto agreed upon between the Parties, including all Site Instructions,
Specifications, Drawings, Change Orders and Change Directives.
"Contract Price" means, if the Contract is on the basis of a stipulated or lump sum, the lump
sum price stated in Section 00410 – Bid Form, as may be adjusted by Change Orders or Change
Directives. If the Contract calls for payments on a unit price basis whether including lump sums
or not, Contract Price shall mean the product of the units of Work actually performed and the
appropriate unit prices plus the total of the lump sums prices all as stated in Section 410 – Bid
Form, and all as may be adjusted by Change Orders or Change Directives.
“Contract Time” means the time stipulated in Article 1 of Section 00520 - Contract Agreement
as the period between the date of the Notice of Award and achievement of Total Performance of
the Work, as may be adjusted by Change Orders or Change Directives.
“Contractor” means the Contractor named in Section 00520 - Contract Agreement.
“Deficiencies” means one or more defects or deficiencies in the Work or Materials, including
Work omitted or not performed as provided for in this Contract.
Foothills Regional Services Commission Section 00700
Foothills Landfill Expansion - Cell 6 GENERAL CONDITIONS
2018-01/2017-3650.020 Page 3 of 63
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00700.doc: January 29, 2018
“Dispute” means any difference between the Contractor and the Owner as to the interpretation,
application or administration of the Contract or any failure by the Owner and the Contractor to
agree where the Contract Documents call for agreement.
“Drawings” means the graphic and pictorial drawings, sketches and representations, whether
electronic or paper-based, prepared to represent the Work and issued by the Engineer, including
plans, elevations, sections, details, schedules, and diagrams.
“Engineer” means Associated Engineering acting through a delegate duly appointed to act on its
behalf, or such other engineer, architect or Person as may from time to time be duly authorized
and appointed in writing by the Owner.
“Field Instruction” means a written directive by the Engineer for immediate action by the
Contractor to correct or remedy observed deficiencies in compliance with the safety or
environmental requirements of the Contract.
“Force Account” means the method of calculating payment the Contractor shall receive for the
Work performed as set out in GC 56 FORCE ACCOUNT WORK.
“Governmental Authority” means any federal, provincial, first nation or municipal
government, official, administrative, regulatory, or legislative authority, commission, tribunal or
court or any of the respective agencies or departments thereof having jurisdiction over any aspect
of the Project, the Work, this Contract, or any matters arising thereunder.
“Law” means the common law and all applicable decrees, statutes, laws, by-laws, rules, orders,
codes, directives and regulations in effect from time to time and made or issued by any
Governmental Authority having jurisdiction over any aspect of the Project, the Work, this
Contract, the Owner, the Contractor and the Subcontractors, and includes any applicable
replacement, amendment or supplementary legislation, and any applicable regulations, and
further includes the OH&S Legislation.
“Lien Act” means the applicable provincial or territorial lien legislation, including regulations
enacted pursuant to that lien statute, at the Project Site, current at the date of the Notice to
Proceed and as may be revised during the Contract Time.
“Materials” means materials, supplies, machinery, equipment and fixtures which are or which
are to be permanently incorporated into the Work, but excludes Construction Equipment.
“Major Lien Fund Holdback” means the total of lien holdbacks from progress payments for
Work performed before Substantial Performance of the Work.
“Milestone Date” means any date or dates specified in the Contract Documents for completion
of specified portions of the Work, including the dates of Substantial Performance of the Work
and Total Performance of the Work.
“Minor Lien Fund Holdback” means the total of lien holdbacks from progress payments for
Work performed after Substantial Performance of the Work.
Foothills Regional Services Commission Section 00700
Foothills Landfill Expansion - Cell 6 GENERAL CONDITIONS
2018-01/2017-3650.020 Page 4 of 63
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00700.doc: January 29, 2018
“Notice” means a notice made in writing and delivered to one of the Parties or the Engineer at
the address, or any replacement address, stipulated for and in the method required for, delivery as
set out in Article 6 of Section 00520 - Contract Agreement.
“Notice of Award” has the meaning set out in Section 00410 - Bid Form.
“Notice to Proceed” has the meaning set out in Section 00410 - Bid Form.
“OH&S Legislation” means, collectively, all of the applicable decrees, statutes, laws, by-laws,
rules, orders, codes, directives and regulations concerning occupational health and safety, which
may be in force, from time to time at the Project Site.
“Other Contractors” means any other contractors or consultants which are retained directly by
the Owner for other work at the Project Site, other than the Contractor, and includes the Owner’s
own forces.
“Owner” means the Person identified as such in Section 00520 - Contract Agreement and
includes any authorized representative of the Owner.
“Party” means one of the parties to this Contract and Parties means the Owner and the
Contractor, collectively, as the case may be.
“Payment Certificate” has the meaning set out in GC 37 PROGRESS PAYMENTS.
“Person” means any one of an individual, partnership, limited liability partnership, limited
liability company, corporation, sole proprietorship, trust, unincorporated organization,
association, society, or Governmental authority.
“Personnel” means, without limitation:
(a) in relation to any Party and its affiliates, elected officials, directors, officers, employees,
contract personnel, non-employed representatives, contractors, consultants and agents,
including those who are assigned or seconded to the Project; and
(b) in relation to any other Person, each of their respective elected officials, directors,
officers, employees, contract personnel, non-employed representatives, contractors,
consultants and agents, including those who are assigned or seconded to the Project.
“Pre-contractual Statement” means any communication or correspondence, including any
agreement, undertaking, representation, warranty, promise, assurance, arrangement or draft of
any nature whatsoever, whether or not in writing, relating to the subject matter of the Contract
and which is not repeated in the Contract, made by any Person at any time before the date of the
Contract Agreement.
“Prime Contractor For Safety” means “Prime Contractor”, “Constructor”, “Principal
Contractor”, or such other position of similar import as the case may be according to the location
of the Project Site, as is defined in the OH&S Legislation.
Foothills Regional Services Commission Section 00700
Foothills Landfill Expansion - Cell 6 GENERAL CONDITIONS
2018-01/2017-3650.020 Page 5 of 63
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00700.doc: January 29, 2018
“Project” means the project identified in Article 1 of Section 00520 - Contract Agreement.
“Project Record Drawings” means a dedicated set of Drawings reserved and annotated by the
Contractor on an ongoing basis during the performance of the Work for the purpose of recording
differences between the built Work and Drawings.
“Project Site” means the designated location of the Work on the Project as identified in the
Contract Documents, or, if not identified in the Contract Documents, as identified by the Owner
by Notice to the Contractor, from time to time.
“Project Takeover” means the turnover by the Contractor and the takeover by the Owner of
part, or all of, the Project, which may occur in phases, or not, as determined in the sole discretion
of the Owner, and which shall occur when all of the prerequisites identified in this Contract have
been completed by the Contractor, certified by the Engineer and accepted in writing by the
Owner.
“Project Takeover Date” means the date that Project Takeover occurs in relation to a part, or
all, of the Project.
“Quantities” means the quantities for the Work performed, measured in accordance with
GC 39 QUANTITIES.
“Records” means the records of the Contractor and its Subcontractors relating to the Contract,
the Project or the performance of the Work, and which include, paper and electronic copies, as
the case may be, of:
(a) original invoices and accounts;
(b) records of account for all Work performed, itemizing the names and positions of
Personnel, the hours worked by each, the type of services performed and the hourly rate
charged, together with copies of all subcontracts and invoices for expenses;
(c) records of account for all amounts claimed related to termination or suspension, itemizing
the names and positions of Personnel, the hours worked by each, the type of services
performed and the hourly rate charged, together with copies of all subcontracts; and
(d) correspondence, minutes of meetings, notes, reports, incident reports and all other
documentation including information relating to the Contractor’s compliance with the
Law and the Contract and the use of Confidential Information.
“Shop Drawings” means one or more Drawings, diagrams, illustrations, photographs, schedules,
performance charts, technical brochures, samples, models and other data which are to be
provided by or through the Contractor or the Subcontractors to illustrate details of a portion of
the Work.
Foothills Regional Services Commission Section 00700
Foothills Landfill Expansion - Cell 6 GENERAL CONDITIONS
2018-01/2017-3650.020 Page 6 of 63
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00700.doc: January 29, 2018
“Site Instruction” means an instruction, not involving any adjustment to the Contract Price or
Contract Time, in the form of Specifications, Drawings, schedules, samples, models or written
instructions issued by the Engineer to supplement the Contract Documents as required for the
performance of the Work.
“Specifications” means those documents, whenever issued by the Engineer, setting out the
requirements and standards for Materials, equipment, systems, workmanship and the services
necessary for the proper performance of the Work or any part thereof.
“Subcontractor” means a Person who performs part of the Work, including the Supply of
Materials, and either: (a) has a direct contract with the Contractor or (b) has no direct contract
with the Contractor but is at any tier below the Contractor.
“Substantial Performance of the Work” means that the Work is substantially complete or
substantially performed as defined in the Lien Act, the Work or a substantial part of it is ready
for use or is being used in the way that was intended for the purpose intended, and the Engineer
has issued a certificate verifying that, in the opinion of the Engineer, Substantial Performance of
the Work has been achieved.
“Superintendent” means the Contractor’s senior representative at the Project Site.
“Supplier” means a Person having a direct contract with the Contractor to Supply Materials not
worked to a special design for the Work.
“Supply” means supply and pay for.
“Surety” means the Person who has supplied the performance and labour and material bonds for
the Contract.
“Temporary Work” means temporary supports, structures, facilities, services and other
temporary items, excluding Construction Equipment that is required for performing the Work but
is not incorporated into the Work.
“Total Performance of the Work ” means the Work, with the exception of Warranty Work, has
been fully completed, including rectification of all known Deficiencies, and the Engineer has
issued a certificate verifying that, in the opinion of the Engineer, Total Performance of the Work
has been achieved.
“Toxic or Hazardous Substances” means any solid, liquid, gaseous, thermal or electromagnetic
irritant or contaminant and includes all pollutants and hazardous substances or wastes whether or
not defined in any Law.
“Warranty Period” means that period of time set out in GC 63 WARRANTY during which the
Contractor is obligated to warrant the Work.
“Warranty Work” means the Work to remedy, correct or rectify any Deficiencies, including
any Work required to access the Deficiencies and any Work required to make good the
Deficiencies and any other Work or work performed by Other Contractors that is destroyed,
Foothills Regional Services Commission Section 00700
Foothills Landfill Expansion - Cell 6 GENERAL CONDITIONS
2018-01/2017-3650.020 Page 7 of 63
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00700.doc: January 29, 2018
disturbed or negatively affected by the performance of the Work to remedy, correct or rectify any
Deficiencies, which shall be performed by the Contractor.
“Work” means and includes anything and everything required to be done for the fulfilment and
completion of the Contract.
“Workers Compensation Legislation” means the applicable workers compensation legislation
at the Project Site, current at the date of the Notice to Proceed and as may be revised during the
Contract Time.
“Working Day” means any day that there is construction activity at the Project Site or any
Business Day that construction activity is reasonably possible.
GC 2. INTERPRETATION AND GENERAL PROVISIONS.1 Wherever this Contract requires an action to be performed or an obligation to be
undertaken, unless otherwise specified, such action or obligation shall be performed in a
prompt and commercially reasonable manner by the Party taking the action or fulfilling
its obligation.
.2 This Contract supersedes all prior negotiations and Pre-contractual Statements, relating in
any manner to the subject matter of this Contract, including any bid documents that are
not expressly listed in the Table of Contents of the Contract Documents.
.3 A Party shall have no right of action against any other Party arising out of or in
connection with any Pre-contractual Statement except to the extent that it is repeated in
the Contract.
.4 This Contract may only be amended by a document in writing signed by the Parties.
.5 Wherever the term “including” is used, or any derivative thereof, it shall be read to mean
“including, but not limited to” or an equivalent phrase for a derivative, as the case may
be, if the context so permits such a construction.
.6 Wherever the singular or masculine or neuter is used it will be interpreted as meaning the
plural or feminine or body politic or corporate, and vice versa, as the context requires.
.7 Documents comprising this Contract are complementary, and what is required by any one
shall be as binding as if required by all.
.8 Words and abbreviations that have customary technical or trade meanings are used in this
Contract in accordance with such recognized meanings.
.9 All amounts referred to in this Contract are in Canadian dollars, unless otherwise
indicated.
Foothills Regional Services Commission Section 00700
Foothills Landfill Expansion - Cell 6 GENERAL CONDITIONS
2018-01/2017-3650.020 Page 8 of 63
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00700.doc: January 29, 2018
.10 In the calculation of time, the first day shall be excluded and the last day shall be
included.
.11 If a court of competent jurisdiction determines that any provision of this Contract is
invalid or unenforceable, such determination shall not affect the validity or enforceability
of the remaining provisions of this Contract.
.12 The Parties have each had the opportunity of obtaining legal advice and accordingly any
rule of construction to the effect that any ambiguity is to be resolved against the drafting
Party shall not apply in the interpretation of this Contract.
GC 3. LAW OF THE CONTRACT AND ATTORNMENT
.1 This Contract shall be governed by the Laws of the Province or Territory where the
Project Site is located and the Parties agree to attorn to the exclusive jurisdiction of the
Courts of that Province or Territory.
GC 4. PRECEDENCE OF DOCUMENT FOR INTERPRETATION
.1 In case of any inconsistency or conflict between the provisions of the Contract
Documents, the provisions of such documents and addenda thereto shall take precedence
and govern in the following order:
1. Contract Agreement
2. Supplementary Conditions
3. General Conditions
4. Specifications
5. Drawings
6. Executed Bid Form
7. Instructions to Bidders
8. Invitation to Bid
9. All other documents
.2 Figured dimensions on a Drawing take precedence over measurements scaled from the
Drawing.
.3 Large-scale Drawings take precedence over those of smaller scale.
.4 Supplementary Drawings and Specifications supersede their antecedents.
.5 In case of conflict between figured dimensions on a Drawing and the dimensions of a
specified product, the dimensions of the specified product shall govern.
Foothills Regional Services Commission Section 00700
Foothills Landfill Expansion - Cell 6 GENERAL CONDITIONS
2018-01/2017-3650.020 Page 9 of 63
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00700.doc: January 29, 2018
.6 If compliance with two or more standards or specifications is specified and the standards
or specifications establish different or conflicting requirements, the Contractor shall
comply with the most stringent requirement.
.7 Documents of a later date shall govern over a similar type of document of an earlier date.
GC 5. USE OF THE CONTRACT DOCUMENTS
.1 The intent of the Contract Documents is that the Contractor shall Supply, directly or
through a Subcontractor, all labour, Materials, related services, equipment or other
matters or things necessary for the Contractor to perform the Work.
.2 All Work described in the Specifications and not shown on the Drawings and all Work
shown on the Drawings and not described in the Specifications shall be performed by the
Contractor as if included in both.
.3 The Contractor shall review the Contract Documents provided by the Owner or the
Engineer and shall promptly provide Notice to the Engineer of any of the following that
the Contractor discovers or becomes aware of:
(a) any errors, inconsistencies, omissions or ambiguities in the Contract Documents;
(b) doubt as to the meaning or intent of any part of the Contract Documents;
(c) any variance between the content of the Contract Documents and the Law; or
(d) modifications required to be made to the Contract Documents as a result of
revisions made to the Law.
.4 If the Contractor does discover any conditions described in GC 5.3, the Contractor shall
not proceed with the Work affected until the Contractor has received clarification of or
revisions to the Contract Documents from the Engineer.
.5 If Notice is given by the Contractor in accordance with GC 5.3 and clarifications or
revisions to the Contract Documents are required, the Engineer shall revise the Contract
Documents and any Change shall be dealt with in accordance with PART 11 CHANGES
AND CONCEALED OR UNKNOWN CONDITIONS.
.6 If the Contractor fails to provide Notice as required in GC 5.3 or proceeds with the Work
before receiving clarification of or revisions to the Contract Documents from the
Engineer as provided for in GC 5.5, the Contractor shall be responsible for and shall bear
the costs, expenses, and damages attributable to any such failure, or of proceeding in such
manner.
Foothills Regional Services Commission Section 00700
Foothills Landfill Expansion - Cell 6 GENERAL CONDITIONS
2018-01/2017-3650.020 Page 10 of 63
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00700.doc: January 29, 2018
.7 Unless otherwise expressly agreed to in writing by the Owner, nothing contained in the
Contract Documents shall create any contractual relationship between:
(a) the Owner or its Personnel and any Subcontractor or its Personnel, or other
Persons engaged in the performance of the Work; or
(b) the Engineer or its Personnel and the Contractor, or any Subcontractor, or their
respective Personnel, or other Persons engaged by them in the performance of the
Work.
GC 6. NO WAIVER
.1 No action or failure to act by the Owner, the Engineer or the Contractor shall constitute a
waiver of any right or duty afforded or imposed on any of them under this Contract, and
such action or failure to act shall not constitute an approval of, or acquiescence in, any
breach of this Contract, except as may be expressly provided for or required by this
Contract or otherwise agreed in writing by the Parties.
GC 7. NO ASSIGNMENT WITHOUT CONSENT
.1 Neither Party to this Contract shall assign their respective rights or responsibilities, or any
portion thereof, without the prior written consent of the other Party.
GC 8. SURVIVAL
.1 Any provision of this Contract which expressly states or naturally implies that it survives
the termination, cancellation, completion, suspension or expiration of this Contract,
including any other provision that is necessary for the interpretation or enforcement of
the same, shall continue as valid and enforceable notwithstanding any such termination,
cancellation, completion, suspension or expiration.
Foothills Regional Services Commission Section 00700
Foothills Landfill Expansion - Cell 6 GENERAL CONDITIONS
2018-01/2017-3650.020 Page 11 of 63
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00700.doc: January 29, 2018
PART 2 INSURANCE, WORKERS’ COMPENSATION AND BONDS
GC 9. INSURANCE
.1 The Contractor shall obtain and continuously carry, while the Work is being performed
and while any remedial or Warranty Work is being undertaken, at the Contractor’s own
expense and cost, the insurance coverage as specified in Section 710 – Insurance, unless
otherwise indicated in writing by the Owner. The Owner reserves the right to supplement
or add insurance coverage from time to time as may be required, by Change Order.
.2 The insurance maintained by the Owner or the Contractor shall in no manner limit the
Contractor’s obligations to indemnify or otherwise perform the obligations required of it
pursuant to the terms of this Contract.
.3 Prior to commencing the Work, the Contractor shall provide the Owner with Certificates
of Insurance in a form acceptable to the Owner and evidence the insurance coverage is in
accordance with the requirements of the Contract.
.4 Deductibles, if any, which are applicable to the specified insurance, shall be borne by the
Contractor.
GC 10. WORKERS’ COMPENSATION
.1 The Contractor shall ensure all of its and the Subcontractors’ respective Personnel,
agents, representatives and visitors attending at the Project Site are registered for
workers’ compensation coverage. The Contractor shall indemnify and save harmless the
Owner for any and all claims incurred by the Owner as a result of the Contractor failing
to comply with GC 10.
.2 The Contractor shall at all times pay or cause to be paid any assessment or contribution
required to be paid pursuant to the Workers Compensation Legislation applicable to the
Project Site. If the Contractor fails to do so, the Owner, in addition to any of its other
rights under this Contract, may retain the amount of the assessment or contribution from
any payment then due, or to become due, to the Contractor under this Contract.
.3 At any time during the term of this Contract, when requested by the Owner, the
Contractor shall provide evidence of compliance by the Contractor and Subcontractors
with the obligations under GC 10. As minimum, the Contractor shall provide evidence,
satisfactory to the Engineer, of compliance with the requirements of the Workers
Compensation Legislation including payments due thereunder at the following times:
(a) prior to commencing the Work;
(b) as a condition of receiving a Certificate of Substantial Performance ; and
Foothills Regional Services Commission Section 00700
Foothills Landfill Expansion - Cell 6 GENERAL CONDITIONS
2018-01/2017-3650.020 Page 12 of 63
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00700.doc: January 29, 2018
(c) as a condition of receiving a Certificate of Total Performance.
.4 If at any time the performance of the Work is stopped because the Contractor
unreasonably fails or refuses to comply with a regulation or order issued pursuant to the
Workers Compensation Legislation, then such failure or refusal shall be considered a
default under this Contract and the provisions of GC 49 OWNER’S RIGHT TO
TERMINATE FOR DEFAULT shall apply.
GC 11. BONDS
.1 The Contractor shall, prior to commencement of the Work, pay for and provide to the
Owner:
(a) a performance bond, in the amount of 50% of Contract Price, covering the
performance of this Contract, including any warranty requirements; and
(b) a labour and material payment bond, in the amount of 50% of Contract Price.
.2 The Owner shall not be obligated to make any payment to the Contractor until such time
as the bonds specified in GC 11.1 have been delivered to the Owner by the Contractor.
.3 The bonds specified in GC 11.1 shall be:
(a) in the form which is in accordance with the latest edition of the CCDC approved
bond forms;
(b) issued by a duly licensed surety company authorized to transact the business of
suretyship in the province or territory of the Project Site;
(c) acceptable to the Owner; and
(d) maintained in good standing until the fulfillment of the Contract.
PART 3 GENERAL PROVISIONS
GC 12. EXECUTION OF THE CONTRACT AGREEMENT
.1 The Contractor shall deliver the following documents to the Engineer within ten (10)
Business Days of the date of the Notice of Award:
(a) Certificates of Insurance in accordance with GC 9 INSURANCE;
(b) evidence of compliance with the requirements of the Workers Compensation
Legislation including payments due thereunder in accordance with GC 10
WORKERS’ COMPENSATION;
Foothills Regional Services Commission Section 00700
Foothills Landfill Expansion - Cell 6 GENERAL CONDITIONS
2018-01/2017-3650.020 Page 13 of 63
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00700.doc: January 29, 2018
(c) bonds in accordance with GC 11 BONDS; and
(d) draft Construction Schedule in accordance with GC 25 CONSTRUCTION
SCHEDULE.
.2 The Engineer shall deliver the Contract Documents, in a form ready for signing, and the
Notice to Proceed to the Contractor within five (5) Business Days after receipt of the
documents from the Contractor provided for in GC12.1 that are satisfactory and in strict
compliance with the Contract Documents.
.3 The Contractor shall sign the Contract Documents and return them to the Engineer within
five (5) Business Days after receiving them and the Engineer shall forward them to the
Owner for signing.
.4 The Owner shall sign the Contract Documents and return them to the Engineer within
fifteen (15) Business Days after receiving them and the Engineer shall deliver the
Contractor’s copies to the Contractor.
GC 13. CONDUCT OF THE WORK
.1 The Contractor shall perform the Work in strict accordance with the Contract Documents
and in a professional, competent and safe manner with good workmanship which
performance meets or exceeds the standards for construction on projects of a similar
nature and locality.
.2 The Contractor shall perform the Work diligently and take all measures necessary to
ensure that the Construction Schedule is met.
.3 The Contractor represents that it is highly knowledgeable and experienced in the type of
work described in the Contract Documents. The Contractor is being retained by the
Owner specifically because of its knowledge and expertise in that regard.
.4 The Contractor shall in all respects be an independent contractor.
.5 The Contractor shall not, in the performance of the Work, engage in practices which
conflict with the Owner’s interest including, without limitation, disclosing information
about the Owner’s business or operations; withholding information that could adversely
affect the business interests or operations of the Owner; accepting gifts from or offering
gifts to the Owner’s Personnel that may lead to a perceived obligation; or engaging in any
activity that would contravene any Law. The Contractor shall inform the Owner,
immediately and in writing, of any potential conflict of interest that may arise.
.6 The Contractor shall cooperate and work with any Other Contractors, who are appointed
by the Owner from time to time.
Foothills Regional Services Commission Section 00700
Foothills Landfill Expansion - Cell 6 GENERAL CONDITIONS
2018-01/2017-3650.020 Page 14 of 63
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00700.doc: January 29, 2018
.7 The Contractor shall perform the Work in such manner as to cause a minimum of
interference with the Owner’s operations and the operations of Other Contractors. The
Contractor and the Owner shall cooperate fully with each other, Other Contractors and all
other parties with whom the Contractor and the Owner may be involved during the
performance of the Work.
GC 14. ACTIVITIES
.1 The Owner will provide the Project Site. Where Work is to be performed on lands
owned by others, the Owner will obtain the necessary easements or rights-of-way. Delay
in providing the Project Site, or in obtaining easements or rights-of-way which, in the
opinion of the Engineer, delays the Work will be deemed cause for extension of the
Contract Time and the provisions of GC 47 DELAY shall apply.
.2 The Contractor shall not enter on the Project Site until the Owner or the Engineer has
issued the Notice to Proceed.
.3 The Contractor shall ensure that all permits, licenses and building occupancy permits for
the Project which are required by the Contract Documents to be obtained by the
Contractor are obtained in a timely manner and in accordance with the Construction
Schedule.
.4 The Contractor shall, by personal inspection, examination, calculations or tests, or by any
other means, satisfy himself with respect to the local conditions to be encountered and the
Quantities, quality, and practicability of the Work and of his methods of procedure.
.5 The Contractor shall be responsible for all ordering, scheduling and planning required to
complete the Work in a timely manner. Without prejudice to Contractor’s obligation to
perform on time, the Contractor shall give the Engineer prompt Notice in writing if any
delay is foreseen for any reason.
.6 The Contractor shall monitor its progress in performing the Work and report regularly to
the Engineer in a format acceptable to the Engineer, which shall include:
(a) actual progress reports, with itemization of Work complete, in progress and
scheduled for the next period and the Materials delivered to the Project Site;
(b) forecasts for progress and labour deployment;
(c) identification of any portions of the Work which have, or have the potential to be,
delayed and the mitigation efforts being deployed by the Contractor to address
such delay or potential delay;
(d) lost time incident reports; and
(e) other reports which may be requested by the Engineer from time to time.
Foothills Regional Services Commission Section 00700
Foothills Landfill Expansion - Cell 6 GENERAL CONDITIONS
2018-01/2017-3650.020 Page 15 of 63
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00700.doc: January 29, 2018
.7 The Owner shall make reasonable efforts to provide the Contractor with the necessary
information regarding the Project which the Owner has available. It shall be the
Contractor’s responsibility to:
(a) advise the Engineer if any further or additional information is required; and
(b) obtain and assemble adequate information to permit the Work to be completed in
a proper and expeditious manner as required by and in accordance with the
Contract Documents and the Construction Schedule.
PART 4 ADMINISTRATION OF THE CONTRACT
GC 15. AUTHORITY OF THE ENGINEER
.1 The Engineer shall have authority to act on behalf of the Owner only to the extent
provided for in this Contract or as the Owner may authorize, from time to time, but only
to the extent that such authorization is communicated to the Contractor by Notice from
the Owner.
.2 The duties, responsibilities, and limitations of authority of the Engineer shall only be
modified or extended by a Notice issued by the Owner to the Contractor.
GC 16. ROLE AND RESPONSIBILITY OF THE ENGINEER
.1 The Engineer shall, to the extent specifically provided for in this Contract, be a
representative of the Owner during the performance of the Work until the date of the
Total Performance of the Work and the completion of the Warranty Work. The
Engineer’s instructions to the Contractor shall be forwarded directly from the Engineer,
or alternatively through the Owner, as may be determined appropriate by the Owner from
time to time.
.2 The Engineer shall visit the Project Site at intervals appropriate to the progress of the
Work to observe the progress and quality of the Work and to determine if the Work is
proceeding in general conformity with this Contract.
.3 The Engineer may provide at the Project Site one or more Personnel to assist in carrying
out the Engineer’s responsibilities.
.4 Based upon the Engineer’s observations and evaluation of the Contractor’s applications
for payment, the Engineer shall make an assessment as to the amounts owing to the
Contractor under this Contract and shall issue Payment Certificates as provided for in
PART 7 PAYMENT AND ALLOWANCES.
Foothills Regional Services Commission Section 00700
Foothills Landfill Expansion - Cell 6 GENERAL CONDITIONS
2018-01/2017-3650.020 Page 16 of 63
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00700.doc: January 29, 2018
.5 The Engineer shall not be responsible for, and shall not have control, charge, or
supervision of construction means, methods, techniques, sequences, or procedures,
quality assurance or safety or environmental protection programs and other programs
required in connection with the Work in accordance with applicable Law or general
construction practice.
.6 The Engineer shall not be responsible for the Contractor’s failure to carry out its
obligations in accordance with the Contract Documents. The Engineer shall not have
control over, charge of, or be responsible for the acts or omissions of the Contractor or
any Person for whom the Contractor is responsible at Law.
.7 The Engineer shall be, in the first instance, the interpreter of the requirements of this
Contract and shall make determinations as to the performance under the Contract by the
Owner and the Contractor and the Subcontractors. Interpretations and determinations of
the Engineer shall be consistent with the intent of the Contract Documents.
.8 Claims, Disputes, and other matters in question relating to the performance of the Work
or the interpretation of the Contract Documents, shall be referred initially by Notice to
the Engineer for the Engineer’s interpretation and determination. The Engineer’s
interpretation and determinations shall be given by Notice to both the Owner and the
Contractor.
.9 The Engineer shall have authority to reject work which, in the Engineer’s opinion, does
not conform to the requirements of this Contract. Whenever the Engineer considers it
necessary or advisable, the Engineer shall have authority to require inspection or testing
of Work, whether or not such Work is fabricated, installed or completed. However,
neither the authority of the Engineer to act, nor any decision either to exercise or not
exercise such authority, shall give rise to any duty or responsibility of the Engineer to the
Contractor.
.10 During the progress of the Work, the Engineer may issue Site Instructions to the
Contractor. The Contractor shall comply with the Site Instructions with reasonable
promptness or in accordance with a schedule for implementation of such Site Instructions
agreed to by the Engineer and the Contractor.
.11 The Engineer may issue Field Instructions requiring the Contractor’s immediate action to
effect, maintain or restore compliance of the Work with the safety or environmental
requirements of the Contract.
.12 The Engineer shall review and take appropriate action upon the Contractor’s submittals
such as Shop Drawings and samples, as provided in the GC31 SHOP DRAWINGS.
.13 The Engineer shall prepare Change Orders, Change Directives, Contemplated Change
Notices and Site Instructions as provided in PART 11 CHANGES AND CONCEALED
OR UNKNOWN CONDITIONS. Neither a Change Order nor a Change Directive shall
constitute a Change unless signed by the Owner.
Foothills Regional Services Commission Section 00700
Foothills Landfill Expansion - Cell 6 GENERAL CONDITIONS
2018-01/2017-3650.020 Page 17 of 63
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00700.doc: January 29, 2018
.14 The Engineer shall conduct reviews of the Work to verify Substantial Performance of the
Work and Total Performance of the Work as provided in GC 40 SUBSTANTIAL
PERFORMANCE OF THE WORK and GC 42 TOTAL PERFORMANCE OF THE
WORK AND FINAL PAYMENT.
.15 The Engineer shall make reasonable efforts to promptly review and take appropriate
action with respect to documents submitted by the Contractor, including written
warranties and related documents, and upon the Owner’s request, shall establish a process
for the Owner’s review of some or all such documents.
.16 In the event that the Contractor believes that the Engineer is not promptly reviewing or
taking appropriate action with respect to any samples or documents submitted by the
Contractor, the Contractor shall, within five (5) Business Days of such event occurring,
provide Notice to the Engineer and the Owner setting out which samples or documents
have not been promptly reviewed or in relation to which the Engineer has not taken
appropriate action and the effect of such conduct. If the Contractor does not provide such
Notice within the specified time, the Contractor shall have no Claim against the Owner
for any reason relating to the conduct of the Engineer with respect to the review of
samples or documents submitted by the Contractor.
GC 17. REVIEW AND INSPECTION OF THE WORK
.1 The Owner and the Engineer shall have access to the Work at all times provided they
follow the Contractor’s safety requirements.
.2 The Contractor shall Supply sufficient, safe, and proper facilities at all times for the
review and inspection of the Work by the Owner, the Engineer and Governmental
Authorities. If parts of the Work are in preparation at locations other than the Project
Site, the Owner and the Engineer shall be given access to such parts of the Work.
.3 The Owner may review the Project Site at any time to observe whether the Contractor is
fulfilling its responsibilities as Prime Contractor for Safety and under the OH&S
Legislation. Reviews may include: Project Site conditions, work processes, procedures
and documentation of Project Site safety related activities. Observed infractions or
possible infractions will be reported to the Engineer and the Contractor for further
investigation and action by the Contractor.
.4 If any portion of the Work is designated for tests, inspections or approvals in the Contract
Documents, or by the Engineer, or by Law, the Contractor shall give the Engineer Notice
of not less than two (2) Business Days of when the Work will be ready for review and
inspection. The Contractor shall arrange for, and shall give the Engineer reasonable
Notice of, the date and time of inspections by all Governmental Authorities.
.5 The Contractor shall promptly deliver to the Engineer two copies of any certificates and
inspection reports relating to the Work, or any portion thereof.
Foothills Regional Services Commission Section 00700
Foothills Landfill Expansion - Cell 6 GENERAL CONDITIONS
2018-01/2017-3650.020 Page 18 of 63
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00700.doc: January 29, 2018
.6 Within ten (10) Business Days of the commencement of the Work, the Owner and the
Engineer, in conjunction with the Contractor, shall jointly develop a schedule of items of
Work which are designated for special tests, inspections, or approvals.
.7 If the Contractor covers or permits to be covered, Work that has been designated for
special tests, inspections, or approvals before such special tests, inspections, or approvals
are made, given or completed, the Contractor shall, if so directed, uncover such Work,
have the inspections or tests satisfactorily completed, and re-perform all covering Work,
all at the Contractor’s expense, regardless of the outcome of the tests.
.8 The Engineer may order any portion or portions of the Work to be examined to confirm
the Work is in accordance with the requirements of this Contract. If the Engineer
provides Notice to the Contractor that the Work is not in accordance with the
requirements of this Contract, the Contractor shall correct the Work and pay the cost of
examination, correction and restoration. If, on such examination, the Work has been
completed in accordance with the requirements of this Contract, the Owner shall be
responsible for the cost of examination and restoration, except as provided for in
GC 17.7.
.9 Neither the failure of the Engineer, or an inspection agency appointed by the Owner or
the Engineer, to carry out any reviews or inspections, nor errors or omissions in the
performance of such reviews and inspections by the Engineer, or an appointed inspection
agency, shall relieve the Contractor from responsibility that the Work, or any portion
thereof, is performed in accordance with this Contract.
.10 The Contractor shall continuously monitor and inspect the Work of the Subcontractors
for Deficiencies and ensure that all such Deficiencies are promptly corrected.
.11 The Contractor shall implement and follow a quality assurance program with respect to
the performance of the Work, and shall ensure the compliance of the Subcontractors with
its quality assurance program, to ensure that the quality of the Work meets or exceeds the
standards of performance and quality required by this Contract.
Foothills Regional Services Commission Section 00700
Foothills Landfill Expansion - Cell 6 GENERAL CONDITIONS
2018-01/2017-3650.020 Page 19 of 63
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00700.doc: January 29, 2018
GC 18. DEFICIENCIES
.1 At all times during the performance of the Work, the Contractor shall promptly remedy,
correct and rectify any Deficiencies, whether or not the Deficiencies have been
incorporated in the Work, and whether or not the Deficiencies are the result of poor
workmanship, use of defective Materials, or vandalism, theft or damage through
carelessness, negligence, inadequate security or protection or other act or omission of the
Contractor or any Person for whom the Contractor is responsible at Law.
.2 The Contractor shall remedy, correct and rectify, as required to ensure the timely
performance of the Work in accordance with the Construction Schedule, any and all:
(a) Deficiencies in a manner acceptable to the Engineer and the Owner; and
(b) Work, or other work, that is destroyed or damaged as a result of the Deficiencies
or the remedying or correction thereof.
.3 If, in the opinion of the Owner, it is not expedient to correct any Deficiency as provided
for in this Contract, after consultation with the Engineer and Contractor, the Owner may
require the Contractor to deduct from the amount otherwise due to the Contractor the
difference in value between the Work as performed and that called for by this Contract.
If the Owner and the Contractor do not agree on the difference in value, they shall refer
the matter for determination in accordance with PART 12 DISPUTE RESOLUTION.
.4 In the event that the Contractor does not remedy, correct or rectify the Deficiencies as
required herein, the Owner may, upon expiry of ten (10) Business Days after giving
Notice to the Contractor, take such steps as may be necessary to remedy, correct or
rectify the Deficiencies in the Work or other work which is damaged or destroyed as a
result of the Deficiencies or the remedying or correction thereof. In such event, the
Contractor shall promptly pay the Owner for costs incurred by the Owner for remedying,
correction or rectification of those Deficiencies, including both the Work or other work,
if any, destroyed or damaged, or any alterations necessitated by the Contractor failing to
remedy, correct or rectify the Deficiencies and any claims incurred by the Owner in so
doing may be set-off against any monies due from the Owner to the Contractor.
PART 5 EXECUTION OF THE WORK
GC 19. CONTROL OF THE WORK
.1 The Contractor shall have total control of the Work and shall effectively control, direct
and supervise the Work so as to ensure conformity with the Contract Documents and
compliance with all Law.
.2 The Contractor shall be solely responsible for construction means, methods, techniques,
sequences, procedures and safety and coordination of the various parts of the Work.
Foothills Regional Services Commission Section 00700
Foothills Landfill Expansion - Cell 6 GENERAL CONDITIONS
2018-01/2017-3650.020 Page 20 of 63
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00700.doc: January 29, 2018
.3 Without limiting the generality of the foregoing, the Contractor is responsible for the
coordination of the various parts of the Work so that no part is left in an unfinished or
incomplete condition, unless otherwise required or specified by the Engineer to be
unfinished or uncompleted.
.4 Prior to commencing any of the Work, the Contractor shall verify all measurements,
dimensions, and levels necessary for the proper, timely and complete performance of all
aspects of the Work. Where measurements, dimensions or levels are not included in the
Contract Documents or exact locations or requirements are not apparent, the Contractor
shall immediately provide Notice to the Engineer identifying the lack of information and
shall obtain instructions from the Engineer prior to proceeding with any part of the Work
affected thereby.
GC 20. ELECTRONIC INFORMATION
.1 At the Contractor’s request and at the Owner’s option, the Engineer may provide the
Contractor with electronic copies of the Drawings, design digital terrain model, building
information model or other such information.
.2 If the Engineer does provide such information, it is provided "as is" and at the
Contractor's request, without warranty of any kind, whether express or implied. All
implied warranties, including, without limitation, implied warranties of accuracy,
completeness, merchantability, fitness for a particular purpose, and non-infringement, are
hereby expressly disclaimed.
.3 Under no circumstances will the Owner or the Engineer be liable to any Person for any
direct, indirect, special, incidental, or other damages including Consequential Damages
and, without limitation, any loss of programs or information, based on any use of this
information or any information referenced therein, even if the Owner or the Engineer has
been specifically advised of the possibility of such damages.
GC 21. LAYOUT OF THE WORK
.1 The Engineer shall establish reference points for construction which are necessary for the
Contractor to proceed with the Work.
.2 The Contractor shall preserve and protect the established reference points and shall not
modify or relocate the established reference points without the approval of the Engineer.
Foothills Regional Services Commission Section 00700
Foothills Landfill Expansion - Cell 6 GENERAL CONDITIONS
2018-01/2017-3650.020 Page 21 of 63
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00700.doc: January 29, 2018
.3 Unless otherwise stated in the Contract Documents, the Contractor shall be responsible
for:
(a) laying out the Work;
(b) Supply of stakes, markers and related tools and equipment.
.4 Regardless of the layout methodology, the Contractor shall verify the accuracy of the
proposed location of the elements of the Work as indicated by the layout, prior to their
construction, by measurements to legal property lines and existing physical features at the
Project Site.
GC 22. CONSTRUCTION BY THE OWNER OR OTHER CONTRACTORS
.1 The Owner reserves the right to award separate contracts for work at the Project Site to
Other Contractors and to perform work with its own forces.
.2 The Contractor shall cooperate and work with any Other Contractors, who are appointed
by the Owner from time to time.
.3 When separate contracts are awarded by the Owner to Other Contractors for work at the
Project Site, the Owner shall:
(a) provide for the coordination of the activities and work of Other Contractors with
the Work;
(b) provide Notice to the Contractor as to whether the Contractor will be Prime
Contractor for Safety in relation to some, or all of the work that is performed by
Other Contractors; and
(c) where the Contractor is Prime Contractor for Safety for the area of the Project Site
where work is to be performed by Other Contractors, contractually require that
those Other Contractors adhere to the work rules and procedures established by
the Contractor to ensure safety and the protection of Persons and the Work.
.4 When separate contracts are awarded for work at the Project Site or when work is
performed at the Project Site by the Owner’s own forces, the Contractor shall:
(a) provide the Other Contractors with a reasonable opportunity to bring onto the
Project Site and store their respective materials and to use their construction
equipment and temporary work to execute their respective work;
(b) coordinate and schedule the Work with the work of Other Contractors;
(c) connect such other work with the Work as specified or shown in the Contract
Documents;
Foothills Regional Services Commission Section 00700
Foothills Landfill Expansion - Cell 6 GENERAL CONDITIONS
2018-01/2017-3650.020 Page 22 of 63
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00700.doc: January 29, 2018
(d) participate and assist with Other Contractors and the Owner in reviewing and
coordinating the construction schedules of those Other Contractors; and
(e) where part of the Work is affected by, or depends upon for its proper execution,
the work of Other Contractors, promptly provide Notice to the Engineer, prior to
proceeding with that part of the Work, of any apparent deficiencies in such work.
Failure by the Contractor to promptly provide Notice will invalidate any Claims
of the Contractor against the Owner by reason of the deficiencies in the work of
Other Contractors.
.5 When a Change is required as a result of :
(a) assignment of Prime Contractor for Safety status by the Owner with respect to
Other Contractors; or
(b) coordination of, interference or damage to the work of Other Contractors; or
(c) connection of the work of Other Contractors with the Work,
the Changes will be dealt with in accordance with PART 11 CHANGES AND
CONCEALED OR UNKNOWN CONDITIONS.
GC 23. SUSPENSION OF WORK BY OWNER
.1 The Owner may at any time suspend the Work or delay commencement thereof, or any
portion thereof, provided he gives the Contractor ten (10) Business Days’ Notice of
suspension or delayed commencement. The Contractor shall resume Work upon Notice
from the Owner within ten (10) Business Days after the date set forth in such Notice to
resume Work.
.2 In the event that the Owner chooses to delay the commencement of the Work or any
portion thereof or implement a temporary suspension:
(a) the Contract Time shall be adjusted by the Owner to account for the period of
delay or suspension affecting the Work and any seasonal impact on the Work
directly resulting from the delay or suspension; and
(b) the Owner shall reimburse the Contractor for direct and provable costs and
expenses incurred by the Contractor necessitated by such delay or suspension of
the Work or portion thereof, but the Contractor shall not recover from the Owner
payment for any loss of profits or any other form of damages.
.3 If the delay or suspension of the Work lasts more than forty-five (45) Business Days, the
Contractor may, at its option and on ten (10) Business Days’ Notice, terminate the
Contract as provided for in GC 50 CONTRACTOR’S RIGHT TO TERMINATE FOR
Foothills Regional Services Commission Section 00700
Foothills Landfill Expansion - Cell 6 GENERAL CONDITIONS
2018-01/2017-3650.020 Page 23 of 63
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00700.doc: January 29, 2018
DEFAULT. The Contractor shall not be permitted to terminate the Contract when only a
portion of the Work is delayed or suspended.
.4 A suspension of the Work because of seasonal climatic conditions, whether ordered by
the Owner or the Engineer or not, shall not be deemed to be a suspension of the Work
within the meaning of GC 23.
.5 Except as provided by GC 23, the Owner shall not be liable in any way to the Contractor
in relation to a suspension or delayed commencement of the Work, or any portion of the
Work, and under no circumstances shall the Owner be liable for Consequential Damages
as a result of suspension or delayed commencement of the Work pursuant to GC 23.
GC 24. TEMPORARY SUPPORTS, STRUCTURES AND FACILITIES
.1 The Contractor shall have the sole responsibility for the design, erection, operation,
maintenance and removal of Temporary Work and the design and execution of
construction methods required in its use.
.2 The Contractor shall engage and pay for professional engineer(s) registered and in good
standing in the Province or Territory where the Project Site is located and skilled in the
appropriate disciplines to perform those functions referred to in GC 24.1 where:
(a) required by the Law or by the Contract Documents; and
(b) in all cases where such Temporary Work and its method of construction are of
such a nature that professional engineering skill is required to produce safe and
satisfactory results.
.3 Despite any other provision of this Contract, where the Contract Documents include
designs for Temporary Work or specify a method of construction in whole or in part,
such Temporary Work shall be considered to be part of the design of the Work and the
Contractor shall not be held responsible for that part of the design or the specified method
of construction. The Contractor shall, however, be responsible for the execution of such
design or specified method of construction in the same manner as for the execution of the
Work.
.4 At least fifteen (15) Business Days before construction or location of Temporary Work
the Contractor shall submit representative designs and sketches of Temporary Work to
the Engineer as provided for in GC 31 SHOP DRAWINGS. The Engineer shall review
the Temporary Work drawings and sketches for compatibility with the Work and for
possibilities of impediments to the operations of Other Contractors and the safe passage
of the public.
Foothills Regional Services Commission Section 00700
Foothills Landfill Expansion - Cell 6 GENERAL CONDITIONS
2018-01/2017-3650.020 Page 24 of 63
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00700.doc: January 29, 2018
GC 25. CONSTRUCTION SCHEDULE
.1 The Contractor shall:
(a) within ten (10) Business Days of award of this Contract, prepare a draft
Construction Schedule including all of the construction phases of the Work that
shall incorporate:
(i) the sequence and timing of the required major Project decisions;
(ii) the timing of major activities of the Work and sufficient detail of the
critical events and their inter-relationship to demonstrate that the Work
will be performed in conformity with the Contract Time; and
(b) within the time referred to in GC 25.1(a) deliver to the Engineer the draft
Construction Schedule and:
(i) at a time agreed to by the Engineer, make a presentation of the draft
Construction schedule to the Engineer;
(ii) where the draft Construction Schedule cannot be approved by the
Engineer without revision, the Contractor shall promptly revise the draft
Construction Schedule and deliver and re-present it to the Engineer
repeating the process until the draft Construction Schedule is approved
and becomes the Construction Schedule;
(iii) break-down the Construction Schedule into phases of the Work and show
the Milestone Dates for the various phases;
(iv) use the Construction Schedule as the baseline schedule which will be
identified and compared to all subsequent schedule revisions and updates;
(v) at least monthly, or as more frequently requested by the Engineer:
1. provide proposed updates to the Construction Schedule, which
updates shall include:
a. a twenty (20) Business Day forecast of the planned progress of
the Work;
b. adjustments resulting from Change Orders and Change
Directives; and
c. identification of potential variances between the Construction
Schedule and probable completion dates for all elements of the
Work;
2. review all schedules for Work not started or completed and when
required prepare and plan for mitigation measures and submit the
mitigation plan in writing to the Engineer for review.
.2 Approval by the Engineer of the Construction Schedule shall not diminish or lessen the
Contractor’s obligations and responsibilities under this Contract, including the obligation
to meet the Milestone Dates and achieve the Total Performance of the Work within the
Contract Time.
.3 The time for performance of the Work shall commence on the date specified in the
Notice to Proceed, or if not so specified, on the date that the Notice to Proceed is issued.
Foothills Regional Services Commission Section 00700
Foothills Landfill Expansion - Cell 6 GENERAL CONDITIONS
2018-01/2017-3650.020 Page 25 of 63
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00700.doc: January 29, 2018
GC 26. SAFETY
.1 Unless expressly directed otherwise pursuant to GC 22 CONSTRUCTION BY THE
OWNER OR OTHER CONTRACTORS, the Contractor shall be solely responsible for
construction safety at the Project Site and in performing the Work, and for the
Contractor’s compliance and that of the Subcontractors with all Law and practices
relating to health and safety. The Contractor shall be responsible for initiating,
maintaining and supervising all safety programs, including the preparation of applicable
hazard assessments, in connection with the performance of the Work.
.2 The Owner delegates and the Contractor accept the role and responsibilities of the Prime
Contractor for Safety for the entire Project Site until the Project Takeover Date of the
entire Work. A partial takeover of the Project by the Owner shall not affect this
delegation, unless Notice of a Change in the designation of the Contractor as Prime
Contractor for Safety is provided by the Owner to the Contractor, in which case, the
Contractor shall follow the directions of the Owner as set out in the Notice.
.3 In the event of any occurrence, circumstance or condition that caused, or has the potential
to cause, injury or damage to any Person, property, reputation, security or the
environment, the Contractor shall:
(a) immediately verbally notify the Owner and the Engineer of the same and follow
up with prompt Notice providing details of the occurrence, circumstance or
condition;
(b) keep the Owner and the Engineer informed and provide copies of all relevant
documentation to the Owner and the Engineer of all developments, including
medical status and anticipated recovery of any individuals involved,
investigations by any Governmental Authority, reports prepared by or submitted
by the Contractor or any Subcontractor and the laying of any charges;
(c) cooperate and ensure the cooperation of all Subcontractors with investigations,
whether instigated by the Owner or any Governmental Authority, and provide
copies of any investigations undertaken by the Contractor to the Owner; and
(d) prepare a corrective action plan in a time period agreed to by the Owner and the
Engineer and provide a copy to the Owner and the Engineer.
.4 The Owner may, acting reasonably but at its sole and absolute discretion, for reasons of
health and safety, cause parts of, or all of, the Work or Project to be stopped, or the
Contractor or any of the Subcontractors to be removed or excluded from the Project Site.
Such action shall not relieve the Contractor from its obligations under this Contract or
otherwise affect the Contract Price, the Contract Time or give rise to any Claim by the
Contractor against the Owner.
Foothills Regional Services Commission Section 00700
Foothills Landfill Expansion - Cell 6 GENERAL CONDITIONS
2018-01/2017-3650.020 Page 26 of 63
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00700.doc: January 29, 2018
GC 27. SUPERINTENDENT AND KEY PERSONNEL
.1 The Contractor shall assign to the Project the Superintendent identified in Section 00451
– Bidder’s Qualifications. The Superintendent shall remain assigned to the Project up to
and including the achievement of Substantial Performance of the Work and shall dedicate
substantially all of their full working time and attention to the Project. The Contractor
shall ensure that the Superintendent is available at no additional cost for consultation and
to provide direction during the correction of Deficiencies and performance of any
Warranty Work. The Superintendent shall not be removed, re-assigned to another project
or have their role changed on the Project without the prior written consent of the
Engineer, unless such individual leaves the employment of the Contractor.
.2 The Superintendent shall represent the Contractor at the Project Site until all Deficiencies
noted at the time of Substantial Performance of the Work have been corrected to the
satisfaction of the Engineer. Notices and Site Instructions given to the Superintendent
shall be held to have been received by the Contractor.
.3 The Engineer, may, with reasonable cause at any time during the performance of the
Work, by Notice to the Contractor, require the replacement of the Superintendent
identified in Section 00451 – BIDDER’S QUALIFICATIONS or other supervisory
Personnel assigned to the Work. Upon receipt of the Notice, the Contractor shall
immediately make arrangements to appoint a replacement acceptable to the Engineer.
GC 28. SUBCONTRACTORS
.1 The Contractor shall:
(a) enter into written subcontracts with Subcontractors to require them to perform
their Work as provided in the Contract Documents;
(b) ensure that the relevant portions of this Contract are incorporated into and form
part of, the subcontracts entered into between the Contractor and its
Subcontractors, including:
(i) provisions equivalent to those set out in PART 10 TERMINATION so
that in the event of any kind of termination or delay the Contractor is only
required to pay its Subcontractors for those types of costs and expenses
that the Owner is required to pay the Contractor and the Contractor shall
indemnify the Owner from any other claim by any of its Subcontractors;
and
(ii) an obligation for Subcontractors to protect the Work, the Owner’s
property, property on or adjacent to the Project Site and Materials stored
off the Project Site on terms equal to, or more favourable, than the terms
set out in PART 6 PROTECTION OF PERSONS AND PROPERTY
AND TOXIC OR HAZARDOUS SUBSTANCES.
Foothills Regional Services Commission Section 00700
Foothills Landfill Expansion - Cell 6 GENERAL CONDITIONS
2018-01/2017-3650.020 Page 27 of 63
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00700.doc: January 29, 2018
.2 The Contractor shall employ only those Subcontractors listed in Section 00437 –
Subcontract List or others as approved in writing by the Engineer and shall not change or
employ additional Subcontractors without the approval of the Engineer and the Owner,
which approval shall not be unreasonably withheld. Such changes in Subcontractors
shall not result in an adjustment to the Contract Price or Contract Time.
.3 The Owner, through the Engineer, may at any time during the performance of the Work
object to the use of a Subcontractor and give Notice to the Contractor to employ a
different Subcontractor that is satisfactory to the Owner.
.4 If the Owner requires the Contractor to change a proposed Subcontractor or Supplier
pursuant to GC 28.3 for any reason other than reasonable cause, the Contract Price or
Contract Time, or both as the case may be, shall be adjusted by the differences, if any,
occasioned by such required Change.
.5 Unless a Subcontractor is specified in the Contract Documents, the Contractor shall not
be required to engage as a Subcontractor, a Person to whom the Contractor reasonably
objects.
.6 If a Subcontractor provides the Engineer with a copy of the relevant executed subcontract
agreement, then the Owner, through the Engineer, may provide to a Subcontractor
information as to the percentage of the Subcontractor’s Work which has been certified for
payment. The Owner and the Engineer shall inform the Contractor of any such
communications.
GC 29. LABOUR AND MATERIALS
.1 The Contractor shall Supply all services, labour, Materials, tools, Construction
Equipment, Temporary Work, water, heat, light, power, transportation, and other
facilities and services, including temporary access, access roads, parking areas, laydown
areas and utilities, necessary for the performance of the Work.
.2 Materials Supplied shall be new, fit for the purposes intended by the Owner and
otherwise of the quality as depicted in and required by the Contract Documents.
Materials that are not specified shall be of a quality consistent with those specified and
their use confirmed in advance as being acceptable to the Engineer.
.3 Materials that are used in the performance of the Work, for construction or incorporation
into parts of the Work that will be in contact with partially treated or potable water,
including water retaining structures and piping, shall be compatible with potable water in
accordance with all applicable health and environmental regulations. This shall include,
but not be limited to, all sealants, waterproofing agents, form release agents, concrete
accessories, and valve and pipe coatings and linings.
Foothills Regional Services Commission Section 00700
Foothills Landfill Expansion - Cell 6 GENERAL CONDITIONS
2018-01/2017-3650.020 Page 28 of 63
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00700.doc: January 29, 2018
.4 Until such time as the Materials are incorporated into the Work, the Contractor shall be
responsible for the safe and secure storage and preservation of Materials on the Project
Site, or elsewhere if located off of the Project Site, so as to avoid damage, destruction,
contamination, alteration, waste or spoilage to the Materials, injury to Persons, damage or
destruction to property or delay to the Project resulting from such Materials.
.5 The Contractor shall maintain good order and discipline among the Contractor’s
Personnel, and the Subcontractor’s Personnel engaged in the performance of the Work,
and shall not employ, or permit to be employed, any Subcontractor not skilled in the tasks
assigned.
GC 30. DOCUMENTS AT THE SITE
.1 The Contractor shall keep at least two (2) copies of current Contract Documents, permits,
licenses, authorizations, submittals, reports, the Construction Safety Plan, together with
documentation applicable to safety procedures and compliance with the OH&S
Legislation and Workers Compensation Legislation, and minutes of meetings for the
Work at the Project Site, in good order and available for review by the Owner and the
Engineer.
.2 The Contractor shall ensure that record Drawings, Project Record Drawings, maintenance
manuals, operating instructions, and such similar construction documents, are properly
completed and handed over to the Engineer in a timely manner, or as otherwise required
by the Owner. The Contractor shall not achieve Total Performance of the Work until all
record Drawings, Project Record Drawings, maintenance manuals, operating instructions
and such similar construction documents are complete and delivered to the Engineer.
.3 The Contractor shall ensure that all manufacturers’ maintenance manuals, service
agreements, warranties and guarantees are in order, and shall prepare a register of the
same and deliver the register and the documents to the Engineer in a timely manner, or as
otherwise required by the Owner, and in any event, before Total Performance of the
Work.
GC 31. SHOP DRAWINGS
.1 In consultation with the Engineer, the Contractor shall establish and implement
procedures for timely receipt, processing and review of Shop Drawings and samples.
Upon request of the Engineer, the Contractor shall prepare a target schedule of dates for
submission, review and return of Shop Drawings for the consideration of the Engineer.
.2 The Contractor shall Supply Shop Drawings as described in the Contract Documents or
as the Engineer may reasonably request.
.3 The Contractor shall review all Shop Drawings prior to submission to the Engineer and
shall represent by its review that:
Foothills Regional Services Commission Section 00700
Foothills Landfill Expansion - Cell 6 GENERAL CONDITIONS
2018-01/2017-3650.020 Page 29 of 63
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00700.doc: January 29, 2018
(a) the Contractor has determined and verified all field measurements and field
construction conditions and shall ensure that any Subcontractor submitting Shop
Drawings has also determined and verified all field measurements and field
construction conditions, Material requirements, catalogue numbers, and similar
data; and
(b) the Contractor and the Subcontractor have checked and coordinated all Shop
Drawings with the requirements of the Work and the requirements of the Contract
Documents.
.4 The Contractor shall confirm this review of each of the Shop Drawings by stamp, date,
and signature of the individual responsible. Shop Drawings not reviewed, stamped and
signed by the Contractor may be rejected by the Engineer.
.5 The Contractor shall submit Shop Drawings to the Engineer to review in an orderly
sequence, in accordance with any schedule that may be agreed to for the submission of
Shop Drawings and sufficiently in advance of the need for reviewed Shop Drawings, so
as not to cause any delay to the Construction Schedule or to the work of Other
Contractors. At the time of submission, the Contractor shall provide Notice to the
Engineer of any deviations in the Shop Drawings from the requirements of the Contract
Documents.
.6 Upon the Engineer’s request, the Contractor shall revise and resubmit Shop Drawings
which the Engineer rejects as inconsistent with the Contract Documents. The Contractor
shall provide Notice to the Engineer of any revisions made to resubmitted Drawings other
than those requested by the Engineer.
.7 If the Contractor Supplies the Shop Drawings in accordance with the schedule agreed
upon, the Engineer shall review and return Shop Drawings in accordance with the
schedule agreed upon, or otherwise with reasonable promptness. In the event that the
Contractor believes that the Engineer is not promptly reviewing Shop Drawings
submitted by the Contractor, the Contractor shall, within five (5) Business Days of such
event occurring, provide Notice to the Engineer and the Owner setting out which Shop
Drawings have not been promptly reviewed and the effect of such conduct. If the
Contractor does not provide such Notice within the specified time, the Contractor shall
have no Claim against the Owner for any reason relating to the conduct of the Engineer
with respect to review of Shop Drawings.
.8 The Engineer’s review of Shop Drawings is for general conformity to the design concept,
and for general arrangement only, and shall not relieve the Contractor of responsibility
for errors or omissions in the Shop Drawings or for meeting all requirements of this
Contract.
.9 The Engineer’s authority to review Shop Drawings shall be for the benefit of the Owner
and such authority shall not give rise to any duty or responsibility of the Engineer or the
Foothills Regional Services Commission Section 00700
Foothills Landfill Expansion - Cell 6 GENERAL CONDITIONS
2018-01/2017-3650.020 Page 30 of 63
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00700.doc: January 29, 2018
Owner to the Contractor, Subcontractors or their Personnel or other Persons performing
any of the Work.
.10 Shop Drawings that require approval of any Governmental Authority shall be submitted
to such Governmental Authority by the Contractor for approval, prior to submission to
the Engineer, so as not to adversely impact the Construction Schedule.
GC 32. STEWARDSHIP OF THE PROJECT SITE
.1 The Contractor shall confine Construction Equipment, Temporary Work, storage of
Materials, waste products and debris and operations of Personnel and Subcontractors to
limits indicated by Law, ordinances, permits or the Contract Documents, as applicable,
and shall not unreasonably encumber or obstruct the Work or the Project Site.
.2 The Contractor shall not load, or permit to be loaded, any part of the Work with a weight
or force or in any other manner that will endanger the safety of the Work or any Persons.
.3 The Contractor shall maintain the Work and the Project Site in a tidy condition free from
the accumulation of waste products and debris, other than that resulting from the
operations of the Owner or Other Contractors.
.4 The Contractor shall remove waste products and debris, other than that resulting from the
operations of the Owner or Other Contractors, and shall leave the Work and the Project
Site clean and suitable for occupancy on each applicable Project Takeover Date. The
Contractor shall remove tools, Construction Equipment, and equipment not required for
the performance of the remaining Work.
.5 In the event that any products or debris resulting from the operations of the Owner or
Other Contractors affects the Work or safety on the Project Site, the Contractor shall
immediately verbally inform the Engineer and the Owner and provide Notice to the same
of such condition within one (1) Business Day thereafter.
.6 Prior to application for the final Payment Certificate, the Contractor shall remove tools,
Construction Equipment, Temporary Work, and waste products and debris, other than
that resulting from the work undertaken by the Owner or the Other Contractors.
Foothills Regional Services Commission Section 00700
Foothills Landfill Expansion - Cell 6 GENERAL CONDITIONS
2018-01/2017-3650.020 Page 31 of 63
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00700.doc: January 29, 2018
PART 6 PROTECTION OF PERSONS AND PROPERTY AND TOXIC OR HAZARDOUS
SUBSTANCES
GC 33. PROTECTION OF WORK AND PROPERTY
.1 In performing the Work the Contractor shall protect the Work and the Owner’s property
and any other Person’s property from damage. The Contractor shall at the Contractor’s
own expense make good any such damage which arises as the result of the Contractor’s
operations.
.2 At no additional cost to the Owner and as part of the Work, the Contractor shall provide
all safety devices, signage and supervision at the Project Site that are necessary to protect
Personnel and the public.
.3 Before commencing any Work at the Project Site the Contractor shall:
(a) expose and determine conclusively the location in the field of all underground
utilities and structures indicated on the Contract Documents as being at the
Project Site;
(b) consult with all utility corporations that provide electricity, communication, gas or
other utility services in the area of the Project Site, to expose and conclusively
determine the location of all underground utilities;
(c) expose and conclusively determine the location of any other utilities or
underground structures that are reasonably apparent or inferable in an inspection
of the Project Site; and
(d) survey and record the location, in three dimensions, of underground structures
exposed in accordance with GC 33.3; and
(e) provide the information obtained under GC 33.3 (d) to the Engineer.
.4 If any underground utility or structure located under GC 33.3 is in conflict with the Work
as indicated on the Drawings, immediately provide Notice to the Engineer. If the
resolution of the conflict requires a Change that increases or decreases the Contract Price
or the Contract Time, then the provisions of GC 57 CONCEALED OR UNKNOWN
CONDITIONS shall apply.
.5 The Contractor shall pay the costs to repair any underground utility or structure that the
Contractor damages in the performance of the Work which the Contractor was required
to locate under GC 33.3.
.6 If, in the performance of the Work the Contractor causes damage to an underground
utility or structure:
Foothills Regional Services Commission Section 00700
Foothills Landfill Expansion - Cell 6 GENERAL CONDITIONS
2018-01/2017-3650.020 Page 32 of 63
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00700.doc: January 29, 2018
(a) which was unknown or unforeseeable to the Contractor at the time of the damage;
and
(b) that the Contractor was not required to locate pursuant to GC 33.3,
then such event may be considered a concealed or unknown condition and the provisions
of GC 57 CONCEALED OR UNKNOWN CONDITIONS shall apply.
.7 Unless the Owner provides Notice to the Contractor stating otherwise, in the event of a
shutdown or suspension of the Work, the Contractor shall continue to be responsible for
the care, protection, security and maintenance of the Work during the period of the
shutdown or suspension.
.8 The Contractor shall provide, at no additional cost to the Owner, adequate site security at
all times during the performance of the Work. The Owner shall not be responsible for the
costs of any theft, damage, alteration, loss or replacement.
GC 34. TOXIC OR HAZARDOUS SUBSTANCES
.1 Unless otherwise specified in the Contract Documents the Contractor shall assume that
the Owner has elected not to conduct tests or investigations for Toxic or Hazardous
Substances at the Project Site.
.2 Subject to the provisions of GC 34, the Owner bears the risk that the Contractor will
encounter Toxic or Hazardous Substances at the Project Site.
.3 The Contractor has no obligation or duty to conduct tests or investigations for Toxic or
Hazardous Substances at the Project Site unless the Engineer gives written directions
regarding Toxic or Hazardous Substances that are discovered or suspected at the Project
Site.
.4 If, in the performance of the Work the Contractor encounters any materials at the Project
Site that the Contractor knows or suspects may be Toxic or Hazardous Substances then
the Contractor shall immediately:
(a) stop the Work, or portion of the Work, and take such steps as required so that
such materials are contained and not disturbed; and
(b) give written Notice to the Engineer, the Owner and all other parties as required by
Law.
.5 If the Engineer observes any materials at the Project Site that the Engineer knows or
suspects may be Toxic or Hazardous Substances then the Engineer shall immediately
give written Notice to the Owner and the Contractor, and the Contractor shall
immediately stop the Work or portion of the Work as required by GC 34.4.
Foothills Regional Services Commission Section 00700
Foothills Landfill Expansion - Cell 6 GENERAL CONDITIONS
2018-01/2017-3650.020 Page 33 of 63
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00700.doc: January 29, 2018
.6 If materials are encountered that are or are suspected to be Toxic or Hazardous
Substances and Notice is given either by the Contractor pursuant to GC 34.4, or by the
Engineer pursuant to GC 34.5, then the Engineer shall after consulting with the
Contractor give the Contractor written directions specifying what, if any, measures are to
be taken on account of such materials so as to reasonably permit the Contractor to
proceed with the Work. The Contractor shall strictly comply with any such directions.
.7 The Work shall be performed in full compliance with all Laws applicable to any Toxic or
Hazardous Substances encountered at the Project Site.
.8 Any adjustment that the Contractor is required to make to the performance of the Work
on account of suspected or confirmed Toxic or Hazardous Substances encountered by the
Contractor at the Project Site and that were not identified in the Contract Documents shall
be considered a concealed or unknown condition and the provisions of GC 57
CONCEALED OR UNKNOWN CONDITIONS shall apply.
.9 Unless stated otherwise in the Contract Documents, the remediation, treatment or
removal of any Toxic or Hazardous Substances shall be a Change and the provisions of
Part 11 CHANGES AND CONCEALED OR UNKNOWN CONDITIONS shall apply.
.10 Provided that the Contractor strictly complies with the requirements of GC 34 then the
Owner shall indemnify the Contractor against any costs, expenses and damages that the
Contractor is required by Law to pay to any third party (excluding Subcontractors) as a
direct result of encountering any Toxic or Hazardous Substances in the performance of
the Work at the Project Site.
.11 If the Contractor fails to notice any materials that a competent contractor reasonably
experienced in the Work would have noticed were Toxic or Hazardous Substances, or
fails to comply with a direction given by the Engineer pursuant to GC 34.5, then the
Contractor shall:
(a) pay all reasonable additional costs the Owner is required by Law to incur to deal
with any Toxic or Hazardous Substances that have been disturbed or permitted to
escape as a direct result of such failure; and
(b) indemnify the Owner from any and all additional costs, expenses and damages
that the Owner is required by Law to pay to any third party as a direct result of
such failure.
.12 The Contractor shall not bring to the Project Site any Toxic or Hazardous Substances and
the Contractor shall indemnify the Owner from any costs, expenses and damages the
Owner is required by Law to pay as a result of the Contractor bringing any Toxic or
Hazardous Substances to the Project Site.
.13 Nothing in GC 34 shall be interpreted to prohibit or prevent the Contractor from bringing
to the Project Site any Toxic or Hazardous Substances such as fuel oil, or other materials
Foothills Regional Services Commission Section 00700
Foothills Landfill Expansion - Cell 6 GENERAL CONDITIONS
2018-01/2017-3650.020 Page 34 of 63
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00700.doc: January 29, 2018
that the Contractor is specifically, or by necessary and reasonable implication, permitted
or required to bring onto the Project Site in order to perform the Work as required by the
Contract Documents.
.14 In the event that Toxic or Hazardous Substances are used or placed in the Work or onto
the Project Site by the Contractor, or any Person for whom the Contractor is responsible
at Law, the Contractor shall take the necessary steps to ensure that no Person suffers
injury, sickness, or death, and that no property is damaged or destroyed as a result of
exposure to, or the presence of, such Toxic or Hazardous Substances.
PART 7 PAYMENT AND ALLOWANCES
GC 35. GENERAL PROVISIONS RELATING TO PAYMENT
.1 Payments shall be made to the Contractor in accordance with this PART 7 PAYMENT
AND ALLOWANCES and, as applicable, Section 00520 - Contract Agreement.
.2 No payment by the Owner under this Contract, or partial or entire use or occupancy of
the Work by the Owner shall constitute an acceptance of any portion of the Work which
is not in accordance with the requirements of the Contract.
GC 36. FINANCIAL INFORMATION REQUIRED OF THE CONTRACTOR
.1 At the request of the Owner, from time to time, the Contractor shall provide to the
Owner, in writing, such financial or corporate information as may be reasonably required
by the Owner, to establish or confirm the ability of the Contractor to perform its
obligations pursuant to this Contract.
.2 The Contractor shall keep the Owner apprised of any material or significant changes in
the ownership or financial position of the Contractor which take place or are to take place
during the term of this Contract or which may in any manner adversely impact on the
Contractor’s ability to perform its obligations in a timely, competent or complete manner.
GC 37. PROGRESS PAYMENTS
.1 Within five (5) Business Days after the end of a calendar month the Engineer shall
prepare and issue to the Owner a Payment Certificate for the period ending the last
calendar day of the month.
.2 The Payment Certificate shall set out as of the end of last calendar day of the preceding
month:
(a) the total value of the Work completed and the Materials incorporated into the
Work;
Foothills Regional Services Commission Section 00700
Foothills Landfill Expansion - Cell 6 GENERAL CONDITIONS
2018-01/2017-3650.020 Page 35 of 63
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00700.doc: January 29, 2018
(b) the total Quantities, or the percent complete for each pay item;
(c) all holdback amounts if any;
(d) the total amount owing by the Owner to the Contractor;
(e) any liquidated damages or other deductions; and
(f) set offs permitted by the Contract Documents.
.3 The Engineer shall not finalize a Payment Certificate without consulting with the
Superintendent about the Quantities and amounts to be included in a Payment Certificate.
.4 The period referred to in GC 37.1 for the issuance of the Payment Certificate may be
extended by any time that the Contractor takes to provide the consultation to the
Engineer, or to provide any supporting documentation the Engineer requires to finalize
the Payment Certificate.
.5 If the Engineer does not agree with the Superintendent regarding any aspect of the
Payment Certificate then the Engineer shall without delay:
(a) prior to issuing the Payment Certificate, fully advise the Superintendent of the
reasons for the disagreement; and then
(b) issue the Payment Certificate to the Owner, with a copy to the Contractor, in the
amounts the Engineer determines are correct.
.6 The Contractor shall provide to the Engineer all documentation as required by the
Contract Documents in support of the completed portion of the Work and Materials
covered by the Payment Certificate including inspection reports, invoices, weigh tickets
and daily Force Account records.
.7 If requested in writing by the Engineer the Contractor shall, as a precondition to the
issuance of the Payment Certificate, provide a sworn declaration in a form acceptable to
the Engineer that all amounts relating to the Work, due and owing to third parties,
including all Subcontractors and Suppliers, as of the end of the month previous to that
covered by the Payment Certificate, have been paid.
.8 Except for materials or products which are identified in the Contract Documents as being
“Supply Only”, payments shall not be made for materials or products purchased by the
Contractor but not fully incorporated into the Work at the Project Site.
.9 Subject to GC 44 WITHHOLDING OF PAYMENT AND SET OFF, the Owner shall
make payment to the Contractor of amounts due by the Owner no later than twenty (20)
Business Days after the receipt by the Owner of the Payment Certificate as issued by the
Engineer.
Foothills Regional Services Commission Section 00700
Foothills Landfill Expansion - Cell 6 GENERAL CONDITIONS
2018-01/2017-3650.020 Page 36 of 63
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00700.doc: January 29, 2018
.10 All Payment Certificates issued by the Engineer shall be to the best of the Engineer’s
knowledge, information, and belief.
.11 The monthly progress Payment Certificates shall not bind the Owner or Engineer in any
manner in the preparation of subsequent Payment Certificates or the final progress
Payment Certificate, but shall be construed and held to be approximate only. By issuing
any Payment Certificate, the Engineer does not assume any of the responsibility of the
Contractor with respect to the correctness or completeness of the Work, including the
Contractor’s responsibility to ensure that the Work has been completed in accordance
with the Contract Documents.
GC 38. PROGRESS PAYMENT HOLDBACKS
.1 The Owner shall:
(a) hold back 10%, or other percentage as required by the Lien Act, of any amounts
net of value-added taxes due to the Contractor, including those amounts due for
payment for Work performed after Substantial Performance of the Work; and
(b) if the Project Site is a highway, Indian reserve or other lands that cannot be
liened, then, notwithstanding that a lien cannot be registered against the Project
Site, hold back the percentage that would have been required if the Lien Act did
apply of any amounts due to the Contractor as a lien holdback, on the same
conditions as though such holdback was a requirement of the Lien Act, including
making payment from such holdback directly to Subcontractors.
.2 In addition to other holdbacks as provided by the Contract Documents, the Owner may
hold back from payments otherwise due to the Contractor amounts as determined by the
Engineer pursuant to GC 44 WITHHOLDING OF PAYMENT AND SET OFF, on
account of deficient or defective Work already paid for. This holdback may be held,
without interest, until such deficiency or defect is remedied.
.3 If after Substantial Performance of the Work is achieved the Contractor is unable to
complete any portion of the Work because of climatic or other conditions beyond the
Contractor’s reasonable control then the Owner may hold back from payments otherwise
due to the Contractor the amount, as estimated by the Engineer, by which the cost to have
others complete the Work exceeds the Contract Prices for such completion work.
.4 The Contractor shall assist the Owner to establish a holdback account pursuant to the
Lien Act, if required to be established under the Lien Act, at a savings institution
acceptable to the Owner, including preparing and completing any and all documents and
forms as the savings institution may require. Any Notice issued by the Contractor upon
the Owner’s failure to pay into the holdback account the amount the Owner is required to
retain under the Lien Act shall be given in writing to the Engineer.
Foothills Regional Services Commission Section 00700
Foothills Landfill Expansion - Cell 6 GENERAL CONDITIONS
2018-01/2017-3650.020 Page 37 of 63
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00700.doc: January 29, 2018
GC 39. QUANTITIES
.1 The estimate of Quantities shown in the Section 00410 - Bid Form serves only to provide
a basis for comparing bids and no representations have been made by either Owner or
Engineer that the actual Quantities will even approximately correspond therewith.
.2 The Owner has the right to increase or decrease the Quantities in any or all items and to
eliminate items entirely from the Work.
.3 Where there is a discrepancy between the measurement or calculations made by or for the
Contractor to establish the Quantities and the measurement or calculations made by the
Engineer to establish the Quantities, the Quantities shall be deemed to be the
measurement made by the Engineer.
.4 Where the Quantities are disputed by the Contractor, upon request of the Contractor, the
Parties will exchange their data, surveys and other information as the same relates to the
measurements and calculations.
.5 If after reviewing the Engineer’s data, surveys and other information the Contractor still
disputes the Quantities, the Contractor may dispute the Quantities by providing Notice to
the Engineer, within ten (10) Business Days of the Engineer providing its data, surveys
and other information to the Contractor, stating:
(a) that it disagrees with the Quantities; and
(b) its measurements and calculation of the Quantities.
.6 If Notice is provided by the Contractor as set out in GC 39.5, the Parties shall take the
necessary steps to have the Dispute resolved in accordance with PART 12 DISPUTE
RESOLUTION. In the event that the Contractor does not provide Notice to the Engineer
as set out in GC 39.5, the Contractor shall be deemed to have waived all of its rights to
dispute the Quantities.
Foothills Regional Services Commission Section 00700
Foothills Landfill Expansion - Cell 6 GENERAL CONDITIONS
2018-01/2017-3650.020 Page 38 of 63
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00700.doc: January 29, 2018
GC 40. SUBSTANTIAL PERFORMANCE OF THE WORK
.1 The Engineer shall be the payment certifier responsible for payment certification as
required by the Lien Act for the Contractor. The Contractor shall be the Person
responsible for payment certification as required by the Lien Act for all Subcontractors.
.2 When the Contractor considers that it has achieved Substantial Performance of the Work,
the Contractor shall prepare and submit to the Engineer:
(a) a written application from the Contractor for a Certificate of Substantial
Performance; and
(b) written confirmation that upon payment in the amount applied for, that the
Contractor has no further Claim against the Owner for the Work, for any reason,
except to the extent of any Claims for which the Contractor has previously
provided Notice to the Owner and the Engineer.
.3 The Engineer will, no later than six (6) Business Days after the receipt of a written
application from the Contractor for a Certificate of Substantial Performance make an
inspection and assessment of the Work to verify the validity of the application. The
Engineer will prepare and issue a comprehensive list of items to be completed or
corrected, and either:
(a) issue the Certificate of Substantial Performance, or
(b) if the Engineer determines that Substantial Performance of the Work has not been
achieved, consult with the Contractor and advise the Contractor of the Work
required to achieve Substantial Performance of the Work.
.4 Failure to include an item on the comprehensive list of items described in GC 40.3 does
not alter the responsibility of the Contractor to complete the Work or remedy, correct or
rectify any Deficiencies.
.5 If the Engineer determines that Substantial Performance of the Work has not been
achieved, the Owner may deduct the cost of the inspection and assessment by the
Engineer from payments otherwise due to the Contractor.
.6 The Contractor may, after performing the required Work, re-apply for the Certificate of
Substantial Performance, and the provisions of GC 40 shall apply to the re-application.
.7 The Engineer shall include the date of Substantial Performance of the Work in the
Certificate of Substantial Performance.
.8 The Contractor shall promptly post a copy of the Certificate of Substantial Performance
at a prominent and visible location at the Project Site.
Foothills Regional Services Commission Section 00700
Foothills Landfill Expansion - Cell 6 GENERAL CONDITIONS
2018-01/2017-3650.020 Page 39 of 63
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00700.doc: January 29, 2018
GC 41. RELEASE OF MAJOR LIEN FUND HOLDBACK
.1 Upon the expiry of the statutory time for filing liens under the Lien Act, the Contractor
shall submit the following documents to the Engineer:
(a) an application for payment of the holdback amount;
(b) a sworn declaration in a form acceptable to the Engineer to state that all accounts
for labour, subcontracts, Materials, Construction Equipment, and other
indebtedness which may have been incurred by the Contractor in the Substantial
Performance of the Work and for which the Owner might in any way be held
responsible have been paid in full, except for amounts properly retained as a
holdback or as an identified amount in dispute; and
(c) documents satisfactory to the Engineer showing compliance with the applicable
Workers Compensation Legislation at the Project Site including payments due
thereunder.
.2 After the receipt of an application for payment from the Contractor and the
accompanying documents as provided in GC 41.1, the Engineer will issue a Payment
Certificate for payment of the holdback amount.
.3 The Owner shall pay any lien holdback as required by the Lien Act, or on such other date
as required by Law, but the Owner may set off from the holdback payment the amounts
for any Deficiencies or filed liens as provided in GC 44 WITHHOLDING OF
PAYMENT AND SET OFF.
GC 42. TOTAL PERFORMANCE OF THE WORK AND FINAL PAYMENT
.1 When the Contractor considers that it has achieved Total Performance of the Work, the
Contractor shall prepare and submit to the Engineer:
(a) a written application from the Contractor for a Certificate of Total Performance;
and
(b) written confirmation that upon payment in the amount applied for, that the
Contractor has no further Claim against the Owner for the Work, for any reason,
except to the extent of any Claims for which the Contractor has previously
provided Notice to the Owner and the Engineer.
.2 The Engineer will, no later than six (6) Business Days after the receipt of a written
application from the Contractor for a Certificate of Total Performance make an inspection
and assessment of the Work to verify the validity of the application, and either:
Foothills Regional Services Commission Section 00700
Foothills Landfill Expansion - Cell 6 GENERAL CONDITIONS
2018-01/2017-3650.020 Page 40 of 63
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00700.doc: January 29, 2018
(a) issue the Certificate of Total Performance, or
(b) if the Engineer determines that Total Performance of the Work has not been
achieved, the Engineer will prepare and issue a comprehensive list of items to be
completed or corrected to achieve Total Performance of the Work.
.3 Failure to include an item on the comprehensive list of items described in GC 42.2(b)
does not alter the responsibility of the Contractor to complete the Work or remedy,
correct or rectify any Deficiencies.
.4 If the Engineer determines that Total Performance of the Work has not been achieved, the
Owner may deduct the cost of the inspection and assessment by the Engineer from
payments otherwise due to the Contractor.
.5 The Contractor may, after performing the required Work, re-apply for the Certificate of
Total Performance, and the provisions of GC 42 shall apply to the re-application.
.6 The Engineer shall include the date of Total Performance of the Work in the Certificate
of Total Performance.
.7 No later than ten (10) Business Days after issuance of the Certificate of Total
Performance, the Engineer shall issue to the Contractor, a draft Payment Certificate for
final payment, for the Contractor’s review and agreement. If after reviewing the
Engineer’s Payment Certificate the Contractor disputes the Quantities or the payment
amount, the provisions of GC 39 QUANTITIES will apply.
.8 If after reviewing the Engineer’s Payment Certificate the Contractor agrees with the
Quantities and the payment amount, then no later than five (5) Business Days after
receipt from the Contractor of Notice that the Contractor agrees with the Payment
Certificate for final payment, the Engineer shall issue to the Owner, a Payment
Certificate for final payment in the amount that the Engineer determines to be properly
due.
.9 Subject to GC 44 WITHHOLDING OF PAYMENT AND SET OFF, the Owner shall
make payment to the Contractor of amounts certified as due by the Engineer, no later
than twenty (20) Business Days after receipt of the Engineer’s Payment Certificate for
final payment and attainment of all of the following conditions:
(a) Total Performance of the Work has been achieved by the Contractor, verified by
the Engineer and approved by the Owner;
(b) the period designated for the release of holdback pursuant to the Lien Act from
the date of Substantial Performance of the Work has expired;
(c) no liens have been registered arising from the Work;
Foothills Regional Services Commission Section 00700
Foothills Landfill Expansion - Cell 6 GENERAL CONDITIONS
2018-01/2017-3650.020 Page 41 of 63
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00700.doc: January 29, 2018
(d) there are no claims that have been made against the Owner by any Person other
than the Contractor, arising from the performance of the Work.
GC 43. RELEASE OF MINOR LIEN FUND HOLDBACK
.1 Upon the expiry of the statutory time for filing liens under the Lien Act, the Contractor
shall submit the following documents to the Engineer:
(a) an application for payment of the holdback amount;
(b) a sworn declaration in a form acceptable to the Engineer to state that all accounts
for labour, subcontracts, Materials, Construction Equipment, and other
indebtedness which may have been incurred by the Contractor in the Total
Performance of the Work and for which the Owner might in any way be held
responsible have been paid in full, except for amounts properly retained as a
holdback or as an identified amount in dispute; and
(c) documents satisfactory to the Engineer showing compliance with the applicable
Workers Compensation Legislation at the Project Site including payments due
thereunder.
.2 After the receipt of an application for payment from the Contractor and the
accompanying documents as provided in GC 43.1, the Engineer will issue a Payment
Certificate for payment of the holdback amount.
.3 The Owner shall pay any lien holdback as required by the Lien Act, or on such other date
as required by Law, but the Owner may set off from the holdback payment the amounts
for any Deficiencies or filed liens as provided in GC 44 WITHHOLDING OF
PAYMENT AND SET OFF.
GC 44. WITHHOLDING OF PAYMENT AND SET OFF
.1 Subject to GC 44.2, if for any reason there are any Deficiencies, any portion of the Work
that is not performed or there is any claim by a third party made against the Owner
arising from the Work, the Owner may withhold from payment to the Contractor such
amounts as the Engineer determines are sufficient and reasonable to cover the cost of
rectification, completion or resolution, until the Deficiencies are rectified, the Work is
completed or such claim is resolved.
.2 The cost of rectifying Deficiencies or completing Work not performed shall be estimated
by the Engineer and a value equivalent to twice that amount shall be withheld from any
payment. Subject to any other right the Owner may have, the holdback amount shall be
paid to the Contractor after proper rectification of all the Deficiencies and completion of
all Work.
Foothills Regional Services Commission Section 00700
Foothills Landfill Expansion - Cell 6 GENERAL CONDITIONS
2018-01/2017-3650.020 Page 42 of 63
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00700.doc: January 29, 2018
.3 In preparing the estimate referred to in GC 44.2, the Engineer shall not be bound by the
Contractor’s unit prices and shall estimate the cost of rectifying Deficiencies or
completing Work using his sole judgement of the influence of prevailing circumstances.
.4 Notwithstanding any other provision of this Contract, the Owner shall be entitled to
withhold and set-off against any monies otherwise due and payable to the Contractor
under this Contract, any sums which the Owner is permitted to withhold either pursuant
to this Contract or to any other agreement between the Owner and the Contractor,
howsoever arising.
GC 45. PROGRESSIVE RELEASE OF HOLDBACK TO SUBCONTRACTORS ANDSUPPLIERS
.1 Where provided by the Lien Act and if the Contractor has certified that the work of a
Subcontractor or Supplier is substantially or totally performed, upon application by the
Contractor accompanied by the documents listed in GC 45.2 and expiry of the statutory
time for filing liens under the Lien Act the Owner shall pay the Contractor the holdback
amount retained for such subcontract work, or for the Materials supplied by such
Supplier.
.2 Applications to the Engineer by the Contractor for progressive release of holdback to
Subcontractors or Suppliers shall be accompanied by the following documents:
(a) A Certificate of Substantial or Total Performance of the subcontract work or
supply contract, as the case may be, prepared by the Contractor in a form
acceptable to the Engineer;
(b) a sworn declaration in a form acceptable to the Engineer to state that all accounts
for labour, subcontracts, Materials, Construction Equipment, and other
indebtedness which may have been incurred by the Subcontractor or Supplier, as
the case may be, in the Substantial or Total Performance of the subcontract work,
or the supply contract, as the case may be, and for which the Owner or Contractor
might in any way be held responsible, have been paid in full, except for amounts
properly retained as a holdback or as an identified amount in dispute;
(c) documents satisfactory to the Engineer showing compliance by the Subcontractor
or Supplier, as the case may be, with the applicable Workers Compensation
Legislation at the Project Site including payments due thereunder; and
(d) written confirmation that upon payment in the amount applied for, that the
Subcontractor or Supplier, as the case may be, has no further Claim against the
Contractor for subcontract work or Materials for any reason, except to the extent
of any claims for which the Subcontractor or Supplier has previously provided
Notice to the Contractor.
Foothills Regional Services Commission Section 00700
Foothills Landfill Expansion - Cell 6 GENERAL CONDITIONS
2018-01/2017-3650.020 Page 43 of 63
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00700.doc: January 29, 2018
.3 After the receipt of an application for payment from the Contractor and the
accompanying documents as provided in GC 45.2, the Engineer will issue a Payment
Certificate for payment of the holdback amount.
.4 The Owner shall pay any lien holdback as required by the Lien Act, or on such other date
as required by Law, or thirty (30) Business Days after receipt of the documents listed in
GC 45.2 that are satisfactory to the Engineer, whichever is the latest.
.5 Progressive release of holdback to Subcontractors and Suppliers as provided for in GC 45
shall not affect the Warranty Period. The Warranty Period for the Work shall commence
as provided for in GC 63 WARRANTY.
PART 8 TAXES AND DUTIES
GC 46. RESPONSIBILITY FOR TAXES AND DUTIES
.1 The Contract Price includes all customs duties and taxes, except Goods and Services Tax
(GST) or Harmonized Sales Tax (HST), in effect at the time of the execution of this Contract.
.2 The Contractor shall be responsible to pay all taxes.
.3 The amount of GST or HST payable by the Owner on goods and services provided under
this Contract is in addition to the Contract Price and is to be shown on a separate line on
Payment Certificates.
.4 If the Owner is exempt from GST or HST, a Certificate of Exemption will be issued to
the Contractor following issuance of the Notice of Award.
.5 The Contract Price shall include any tax rebates which may be applicable under current
legislation. Upon request by the Contractor, the Owner shall provide certificates, in
support of the Contractor's rebate submission to a Governmental Authority. The Owner
shall not be liable to compensate the Contractor for any tax rebates that are denied by
Governmental Authorities.
.6 In the event that new or additional duties or taxes in respect of the Work are applicable or
required by the Law after this Contract is executed, the Contract Price shall be adjusted to
include such new or additional taxes and duties, if applicable.
PART 9 TIMELY CONSTRUCTION
GC 47. DELAY
.1 Subject to the limitations and requirements expressly stated in GC 47, and the
Contractor’s obligation to mitigate the impact of any delay, if the Contractor is delayed in
the performance of the Work:
Foothills Regional Services Commission Section 00700
Foothills Landfill Expansion - Cell 6 GENERAL CONDITIONS
2018-01/2017-3650.020 Page 44 of 63
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00700.doc: January 29, 2018
(a) due to an action or omission of the Owner, the Engineer or any Person for whom
the Owner is responsible at Law;
(b) by a “stop work” or similar order issued by a court or Governmental Authority,
and providing that such order was not issued as the result of an act or fault of the
Contractor or any Person for whom the Contractor is responsible at Law;
(c) where Changes to the Work are made as provided for in PART 11 CHANGES
AND CONCEALED OR UNKNOWN CONDITIONS;
(d) where the Work is suspended or delayed in commencement as provided for in GC
23 SUSPENSION OF WORK BY OWNER;
(e) where the Work is delayed on account of the Owner not providing the Project
Site, or not obtaining easements or rights-of-way;
(f) where the Work is delayed on account of conditions which could not have been
foreseen or which were beyond the control of the Contractor and which were not
the result of fault or negligence of the Contractor or any Person for whom the
Contractor is responsible at Law;
(g) where the Work is delayed on account of Abnormal Weather;
(h) where the Engineer causes delay in providing Drawings or necessary information;
(i) where, in the opinion of the Engineer, the Contractor is entitled to an extension of
Contract Time;
(j) where strikes, lockouts, or labour disputes prevent or substantially interfere with
the progress of the Work,
then provided the Engineer determines that there is no parallel delay that has been caused
by the Contractor or any Person for whom the Contractor is responsible at Law, the
Contract Time shall be extended for such reasonable time as is appropriate to account for
the delay directly associated with the causes set out above, but not including parallel
delays caused by the Contractor or any Person for whom the Contractor is responsible at
Law, as the Engineer, in the first instance, determines, or as may be subsequently
determined in accordance with PART 12 DISPUTE RESOLUTION.
.2 No extension of the Contract Time shall be made and no adjustment in the Contract Price
shall be made for any delay except for a delay described in GC 47.1 and then only if the
Contractor provides Notice, in accordance with GC 47.4, of such a Claim to the Engineer
within five (5) Business Days after the occurrence of the event which has caused the
delay.
Foothills Regional Services Commission Section 00700
Foothills Landfill Expansion - Cell 6 GENERAL CONDITIONS
2018-01/2017-3650.020 Page 45 of 63
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00700.doc: January 29, 2018
.3 Except as expressly provided within these General Conditions, the granting of an
extension of Contract Time pursuant to GC 47 shall not give the Contractor grounds to
make any Claims whatsoever for additional payment, except on the grounds set out in GC
47.1 items (b), (c), (d) or (e).
.4 The Notice prescribed by GC 47.2 must:
(a) contain sufficient detail to provide the Engineer with the opportunity to identify
the cause of the delay and to take steps to mitigate the impact of such delay;
(b) be provided by the Contractor to the Engineer with respect to each and every
event of delay; and
(c) be provided as a separate Notice.
.5 Knowledge by the Owner or the Engineer of any delay, or the impact of any delay, shall
not constitute a waiver of the requirement for the Contractor to provide Notice in
accordance with GC 47.2.
.6 The failure to provide separate express Notice in strict compliance with GC 47 shall be
deemed to be prejudicial to the Owner and shall prohibit the Contractor from claiming, or
being entitled to, any Claim for adjustment to the Contract Time or Contract Price with
respect to such delay or any impact of such delay.
.7 In the event of a delay the Contractor shall take all reasonable measures to minimize the
effects and the costs of the delay and this obligation shall be taken into account in the
determination of the Contractor’s entitlement to an extension of the Contract Time and
reimbursement of delay costs, if any.
.8 The Owner shall not be liable for any penalties or claims by third parties incurred or
suffered by the Contractor and under no circumstances shall the Owner be liable for
Consequential Damages, as a result of delay pursuant to GC 47.
.9 If the Contractor is delayed in the performance of the Work by its own acts or omissions
or those of its Personnel or Subcontractors, then the Contractor will not be entitled to any
time extension or additional payment as a result of such delay.
Foothills Regional Services Commission Section 00700
Foothills Landfill Expansion - Cell 6 GENERAL CONDITIONS
2018-01/2017-3650.020 Page 46 of 63
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00700.doc: January 29, 2018
GC 48. LATE COMPLETION
.1 The Contractor acknowledges that if the Contractor fails to complete the Work within the
Contract Time or fails to meet a specified Milestone Date for any part of the Work, the
Owner will incur additional administrative and overhead costs and will be required to pay
additional compensation to the Engineer (collectively “Additional Overhead”). The
Contractor agrees that in the event the Contractor fails to complete the Work within the
Contract Time or fails to meet a specified Milestone Date for any part of the Work, the
Owner may deduct from any monies owing to the Contractor for the Work, as a genuine
pre-estimate of the Owner’s Additional Overhead, the amount specified in the
Supplementary General Conditions for each Working Day the Work or any portion of the
Work remains incomplete after the applicable Contract Time or Milestone Date.
.2 The rights set out in GC 48.1 are in addition to any other rights the Owner may have and
are in no way exclusive.
.3 No bonus will be allowed by the Owner for completion of the Work in less than the
Contract Time.
PART 10 TERMINATION
GC 49. OWNER’S RIGHT TO TERMINATE FOR DEFAULT
.1 If the Contractor is unable to pay its lawful debts as they come due, is adjudged bankrupt,
makes a proposal pursuant to the Companies’ Creditors Arrangement Act, commits or
threatens to do any act of bankruptcy, commits or seeks to liquidate or is involved in any
similar action under any Law relating to bankruptcy or insolvency, the Owner may,
without prejudice to any other right or remedy it has, terminate this Contract by giving
the Contractor, trustee, monitor or receiver Notice that this Contract will be terminated
immediately and that the applicable provisions of GC 49 apply.
.2 If the Contractor neglects to proceed with, undertake or complete any aspect of the Work
promptly or properly, or otherwise fails to comply with the requirements of this Contract,
the Owner may, without prejudice to any other right or remedy the Owner may have, give
Notice to the Contractor that the Contractor is in default of the Contractor’s contractual
obligations and instruct the Contractor to correct the default within five (5) Business
Days immediately following the receipt of the Notice.
.3 If the default cannot be corrected within the five (5) Business Days specified, the
Contractor shall be in compliance with the Owner’s instructions if the Contractor:
(a) commences the correction of the default in a manner acceptable to the Owner,
within a different time agreed to by the Owner;
(b) provides the Owner with a written plan and schedule acceptable to the Owner for
such correction; and
Foothills Regional Services Commission Section 00700
Foothills Landfill Expansion - Cell 6 GENERAL CONDITIONS
2018-01/2017-3650.020 Page 47 of 63
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00700.doc: January 29, 2018
(c) corrects the default in accordance with such schedule.
.4 If the Contractor fails to correct the default in accordance with GC 49.2 or as
subsequently agreed upon pursuant to GC 49.3, without prejudice to any other right or
remedy the Owner may have, the Owner may, without further Notice to the Contractor,
do one or both of the following:
(a) immediately correct such default and deduct the cost thereof, including any costs
incurred by the Owner, from any payment then or thereafter due to the Contractor,
provided that the Engineer has certified such cost as due to the Owner; or
(b) immediately terminate the Work, in whole or in part, or terminate this Contract, in
whole or in part.
.5 In the event of default under GC 49, the Owner shall have the option, to be exercised in
its absolute discretion, to terminate the right of the Contractor to perform all or any part
or parts of the Work and permit the Contractor to continue to perform the rest of the
Work.
.6 If the Owner terminates the Work, in whole or in part, or terminates this Contract, in
whole or in part, whether pursuant to GC 49.1, GC 49.4 or GC 49.5, or otherwise:
(a) the Owner shall be entitled to take possession of the Work and Materials, and use
the Construction Equipment and Temporary Work at the Project Site, subject to
the rights of third parties, and finish the Work by whatever method the Owner
may consider proper or expedient;
(b) the Owner shall be entitled to withhold further payment to the Contractor until the
total cost of construction of the Work and all backcharges to the Contractor are
known; and
(c) in addition to any other amount that may be owing under this Contract, the
Contractor shall be liable to the Owner for the amount by which the following
items added together exceed the Contract Price:
(i) the total cost of construction of the Work;
(ii) a reasonable allowance or amount, as determined by the Engineer, to
cover the cost of Warranty Work;
(iii) a reasonable allowance or amount, as determined by the Engineer, to
compensate the Engineer;
(iv) the costs and expenses both external and internal and including actual
legal fees, disbursements and taxes incurred by the Owner for its
additional services related to the termination of the Work, in whole or in
part, or termination of this Contract, in whole or in part.
Foothills Regional Services Commission Section 00700
Foothills Landfill Expansion - Cell 6 GENERAL CONDITIONS
2018-01/2017-3650.020 Page 48 of 63
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00700.doc: January 29, 2018
.7 In the event that the Owner terminates the Work in part or terminates this Contract in
part, the Owner shall be entitled to apply GC 49.6 with an appropriate adjustment for the
portion of the Work involved and the portion of the Contract Price attributable to that
portion of the Work.
.8 The Owner shall not be liable for those costs incurred by the Contractor as a result of the
termination.
.9 The Owner shall not be liable for any penalties or claims by third parties incurred or
suffered by the Contractor and under no circumstances shall be liable for Consequential
Damages as a result of termination pursuant to GC 49 and the Contractor shall indemnify
and hold the Owner and its Personnel, including the Engineer, harmless from and against
any such penalties or claims.
GC 50. CONTRACTOR’S RIGHT TO TERMINATE FOR DEFAULT
.1 If the Owner is adjudged bankrupt, makes a proposal pursuant to the Companies’Creditors Arrangement Act, commits or threatens to do any act of bankruptcy, commits
or seeks to liquidate or is involved in any similar action under any Law relating to
bankruptcy or insolvency, the Contractor may, without prejudice to any other right or
remedy it has, terminate this Contract by giving the Owner, trustee, monitor or receiver
Notice that this Contract will be terminated immediately and that the applicable
provisions of GC 50 apply.
.2 If the Work is stopped or otherwise delayed for a period of forty-five (45) Business Days
or more as provided for in GC 23 SUSPENSION OF WORK BY OWNER or under an
order or decision of a court or decision of another Governmental Authority, and
providing that such order was not issued as the result of an act or fault of the Contractor
or any Person for whom the Contractor is responsible at Law, the Contractor may
terminate the Work without prejudice to any other right or remedy the Contractor may
have, by giving the Owner Notice five (5) Business Days prior to such termination. The
Contractor shall not be permitted to terminate the Contract when only a portion of the
Work that is incomplete is delayed or suspended until forty-five (45) Business days after
the Work, except for that portion which is suspended or delayed, is substantially
completed.
.3 The Contractor shall provide Notice to the Owner, with a copy to the Engineer, if the
Owner is in default of its contractual obligations to pay the Contractor when due the
amounts certified by the Engineer or awarded by a court of competent jurisdiction. The
Notice shall state that if the default is not corrected in the thirty (30) Business Days
immediately following the receipt of the Notice, the Contractor may, without prejudice to
any other right or remedy it may have, stop the Work or terminate this Contract.
.4 If the Contractor terminates this Contract under the conditions set out in GC 50.1 or GC
50.2, the Contractor shall be entitled to be paid for all of the Work that has been properly
Foothills Regional Services Commission Section 00700
Foothills Landfill Expansion - Cell 6 GENERAL CONDITIONS
2018-01/2017-3650.020 Page 49 of 63
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00700.doc: January 29, 2018
performed in accordance with this Contract to the date of termination and which has not
been paid for or reimbursed to that date, and such other costs and expenses that the
Contractor may have sustained as a direct result of the Owner’s default which the
Engineer considers to be reasonable and which are supported by auditable
documentation, but shall not be entitled to any claims for Consequential Damages.
.5 The Owner shall not be liable for any penalties or claims incurred or suffered by the
Contractor and under no circumstances shall be liable for Consequential Damages as a
result of termination pursuant to GC 50 and the Contractor shall indemnify and hold the
Owner and its Personnel, including the Engineer, harmless from and against any such
penalties or claims.
GC 51. TERMINATION FOR CONVENIENCE
.1 The Owner, in its sole discretion, shall have the right, which may be exercised at any
time, to terminate all or a portion of the Work or this Contract, without reason or cause,
by giving not less than twenty (20) Business Days’ Notice to the Contractor.
.2 If the Work or this Contract is terminated by the Owner pursuant to GC 51.1, the
Contractor shall be entitled to:
(a) the portion of the Contract Price owed but unpaid to the date of termination,
computed in accordance with this Contract; and
(b) reasonable costs incurred by the Contractor in terminating the Work or this
Contract, including the cost of materials that cannot reasonably be returned to
their Supplier and any return-to-supplier costs.
.3 If the Work or this Contract is terminated by the Owner pursuant to GC 51, the Owner
shall not be liable to the Contractor for any claims or Consequential Damages or any
amounts other than as stated in GC 51.2, as applicable, except as expressly provided for
herein, and the Contractor shall indemnify and hold harmless the Owner, its Personnel,
including the Engineer, from any such claims for amounts not provided for in GC 51.
GC 52. OBLIGATIONS ON TERMINATION
.1 If the Owner terminates the Work, in whole or in part, or terminates this Contract, in whole
or in part, whether pursuant to GC 49.1, GC 49.4 or GC 49.5 OWNER’S RIGHT TO
TERMINATE FOR DEFAULT, or otherwise, the Contractor shall:
(a) subject always to considerations of safety and of the environment, immediately
discontinue performance of the Work, except to the extent as may be necessary to
carry out such discontinuance, and ensure that its operations and activities are
brought to an orderly conclusion and that demobilization occurs in a proper and
Foothills Regional Services Commission Section 00700
Foothills Landfill Expansion - Cell 6 GENERAL CONDITIONS
2018-01/2017-3650.020 Page 50 of 63
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00700.doc: January 29, 2018
careful fashion with due attention being given to public safety and the protection
of the Project and the Work;
(b) comply in full with the Owner’s instructions regarding the termination;
(c) take such steps as may be necessary or desirable to minimize the costs to the
Owner associated with the termination;
(d) promptly deliver to the Owner all of the deliverables and the Owner’s
Confidential Information and intellectual property, including the originals and all
copies and all other documents required by the Owner;
(e) take all steps required by the Owner, to assign to and fully vest in the Owner the
rights and benefits of the Contractor under all subcontracts with its Subcontractors
and any licenses, warranties or guarantees for the Project; and
(f) assign to the Owner, or its nominee, as directed, rights and titles relating to all
Materials for which the Contractor has been paid or will be paid through the
termination process.
.2 The Contractor’s obligations as to quality, correction, and warranty of the Work
performed by the Contractor up to the date of termination shall continue in force after
such termination. If Substantial Performance of the Work has not been reached by the
date of termination, the Warranty Period shall nevertheless be deemed to commence from
the date of Substantial Performance of the Work.
.3 Notwithstanding any other provision of this Contract, termination of this Contract in any
manner by the Owner shall not limit, affect or invalidate in any manner:
(a) those provisions of this Contract for the benefit of the Owner which, expressly or
by implication, are to operate or have effect after termination;
(b) any right of action the Owner may have as at the date of termination; or
(c) any other right or remedy the Owner may have as a consequence of the
Contractor’s default and the resulting termination of this Contract.
PART 11 CHANGES AND CONCEALED OR UNKNOWN CONDITIONS
GC 53. CHANGES
.1 The Owner, through the Engineer, without invalidating this Contract, may make Changes
at any time.
.2 The Contractor shall not perform a Change without a written Change Order or Change
Directive signed by the Owner and issued by the Engineer.
Foothills Regional Services Commission Section 00700
Foothills Landfill Expansion - Cell 6 GENERAL CONDITIONS
2018-01/2017-3650.020 Page 51 of 63
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00700.doc: January 29, 2018
.3 The Contractor shall advise the Engineer of the effect a Contemplated Change Notice
will have on the Contract Price and the Contract Time within five (5) Business Days of
receipt of the Contemplated Change Notice, or within such other time period as may be
agreed by the Parties.
.4 Where both additions and deletions are involved in a Change Order all calculations for
profits and overhead shall be determined on a net basis for that Change Order.
.5 The Owner shall make the final determination as to whether any Change is to be
implemented.
.6 It is intended in all matters related to Changes that the Owner, the Engineer and the
Contractor shall act promptly so as not to adversely impact the Construction Schedule.
GC 54. CONTEMPLATED CHANGE NOTICES AND CHANGE ORDERS
.1 When a Change is proposed or required, the Engineer shall provide a Contemplated
Change Notice describing the proposed Change to the Contractor. If, due to exceptional
circumstances, a Contemplated Change Notice cannot be issued by the Engineer, the
Owner or the Engineer may issue a Change Directive as provided by GC 55 CHANGE
DIRECTIVES.
.2 The method of determining the value of a Change shall be decided by the Engineer. The
value of the Change shall be determined by one or more of the following methods:
(a) by unit prices or combinations of unit prices found in the “Schedule of Quantities
and Prices” in Section 00410 - Bid Form;
(b) by unit prices submitted by the Contractor and accepted by the Owner;
(c) by lump sum submitted by the Contractor and accepted by the Owner; and
(d) on a Force Account basis as specified in GC 56 FORCE ACCOUNT WORK.
.3 Within five (5) Business Days of receipt of the Contemplated Change Notice, or within
such other time period as may be agreed by the Parties, the Contractor shall present, in a
form acceptable to the Engineer, a method of proposed adjustment or an amount of
proposed adjustment to the Contract Price, if any, and the adjustment in Contract Time, if
any, for the proposed Change.
.4 Any written quotation for a Change submitted by the Contractor shall be interpreted:
(a) to represent the total adjustment to the Contract Price;
(b) to represent the total adjustment to the Contract Time;
Foothills Regional Services Commission Section 00700
Foothills Landfill Expansion - Cell 6 GENERAL CONDITIONS
2018-01/2017-3650.020 Page 52 of 63
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00700.doc: January 29, 2018
(c) to include compensation for all costs related to the Change, including but not
limited to costs for direct, indirect, office, overhead, surety, insurance and all
other costs, mark-ups and profits; and
(d) to have considered all effects on the Contract Time and if there is no mention of
Contract Time adjustment in the quotation to mean that the Contractor will
implement and complete the Change without any adjustment to the Contract
Time, in which case the Change will not extend the Contract Time or entitle the
Contractor to additional compensation or damages of any nature whatsoever for
any scheduling issues or acceleration.
.5 In the case of Changes proposed to be paid for in whole or in part by lump sum, the
Contractor shall include a cost breakdown to substantiate or justify the Contract Price
adjustment, in addition to any other documentation the Engineer or the Owner may
require.
.6 In the case of Changes to be paid for in whole or in part by unit rates or Force Account
plus a fixed or percentage fee, the form of presentation of costs and methods of
measurement shall be agreed to by the Engineer and the Contractor before proceeding
with the Change. The Contractor shall keep accurate documentation of Quantities and
costs for Changes, and present an account of the cost of the Change to the Engineer.
.7 When the Engineer and the Owner agree to adjustments to the Contract Price or the
Contract Time, or both, and the method to be used to determine the adjustments, a
Change Order signed by the Engineer, the Owner and the Contractor shall be issued
revising the Contract Price or the Contract Time, or both, as applicable. The value of
Work performed as the result of a Change Order shall be included in Payment Certificate.
.8 Administration of Changes to be paid for in whole or in part by Force Account plus a
fixed or percentage fee, shall be in the manner set out in GC 56 FORCE ACCOUNT.
.9 The Owner reserves the right to withdraw any Contemplated Change Notice without
additional compensation to the Contractor if such withdrawal occurs prior to issuance of
the Change Order.
Foothills Regional Services Commission Section 00700
Foothills Landfill Expansion - Cell 6 GENERAL CONDITIONS
2018-01/2017-3650.020 Page 53 of 63
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00700.doc: January 29, 2018
GC 55. CHANGE DIRECTIVES
.1 If the Owner requires the Contractor to proceed with a Change prior to the Owner and the
Contractor agreeing upon the adjustment in Contract Price and Contract Time, the
Owner, through the Engineer, may issue a Change Directive.
.2 Upon receipt of a Change Directive, the Contractor shall proceed promptly with the
Change and, in the case of an emergency identified in a Change Directive, proceed
immediately with the Change.
.3 An adjustment in the Contract Price for a Change carried out by way of a Change
Directive shall be determined on the basis of Force Account in accordance with GC 56
FORCE ACCOUNT WORK.
.4 If the method of valuation, measurement or corresponding increase or decrease in the
Contract Price and Contract Time cannot be promptly agreed upon then, the Engineer in
the first instance, shall determine the method of valuation, measurement and
corresponding increase or decrease in the Contract Price and the Contract Time subject to
final determination in the manner set out in PART 12 DISPUTE RESOLUTION.
.5 In the case of a Dispute in the valuation of a Change Directive, and pending final
determination of such value, the Engineer shall certify the value of Work performed in
relation to the Change Directive in accordance with the Engineer’s evaluation of the
Change Directive, and shall include that amount in a progress Payment Certificate.
.6 If, at any time after the start of the Work directed by a Change Directive, the Owner and
the Contractor reach agreement on the adjustment to the Contract Price and to the
Contract Time, such agreement shall be recorded in a Change Order.
GC 56. FORCE ACCOUNT WORK
.1 Compensation for Work done on a Force Account basis, authorized by a Change Order or
Change Directive issued by the Engineer, shall be calculated as follows:
(a) Labour - All classifications of labour not priced separately in the Bid Form will be
paid for at rates actually paid by the Contractor. A payroll assessment of thirty
percent (30%) of the hourly wage will be allowed to cover all costs including
pension, holiday pay, payroll administration, insurance and similar benefits.
Small tool allowance will be at the rate of four percent (4%) of gross cost of
labour. The Contractor will be allowed a further ten percent (10%) mark-up on
the total of the foregoing as the allowance for overhead and a further ten percent
(10%) mark-up on the resulting subtotal as allowance for profit.
Foothills Regional Services Commission Section 00700
Foothills Landfill Expansion - Cell 6 GENERAL CONDITIONS
2018-01/2017-3650.020 Page 54 of 63
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00700.doc: January 29, 2018
(b) Construction Equipment - The rates for equipment, vehicles and power tools shall
include operator's wages, all maintenance and operating costs and Contractor's
profit. No additional mark-up of Construction Equipment charges shall be
allowed.
(c) Materials supplied by the Contractor shall be paid for at Supplier's invoice price
plus an additional payment of ten percent (10%) of cost to cover handling and
indirect overhead costs, plus ten percent (10%) of all costs including indirect
overhead as profit.
(d) Construction Equipment rentals - The allowance to the Contractor for profit,
superintendence, and all other expense related shall be ten percent (10%) of the
rental agency's invoice to the Contractor for the rental of tools and miscellaneous
equipment.
(e) For subcontract Work, the allowance to the Contractor for profit, superintendence,
and all other expenses shall be ten percent (10%) of the Subcontractor's invoice
for such Work performed.
.2 In the event that, in its sole discretion, Engineer deems that, any or all prices and rates for
Force Account that are included in the Bid Form are not fair and reasonable compared
with normal industry standards, Engineer may order recalculation of any or all prices and
rates based on the Contractor’s actual costs, as provided for in GC 56.1 items (a) and (b).
.3 For the purposes of calculating Force Account rates as provided for in GC 56.1 items (a)
to (e), upon request by Engineer, Contractor shall submit a detailed and verifiable
statement of actual cost of labour, Construction Equipment, Materials and subcontracted
Work. Pending receipt of such statements, Engineer shall apply normal industry-standard
Force Account rates discounted by 20% to facilitate inclusion of interim payments for
Force Account in Payment Certificates, on an ongoing basis.
.4 Subcontractor's Force Account invoices to the Contractor shall be calculated and
submitted for review as described in GC 56.1 items (a) to (e), unless otherwise instructed
by the Engineer.
.5 On a daily basis, the Contractor shall keep an accurate, complete and up-to-date record in
a form satisfactory to the Engineer, showing on a shift-by-shift basis, all Contractor and
Subcontractor labour, Construction Equipment and Materials to be paid by Force
Account. Daily Force Account records shall be submitted by the Contractor to the
Engineer for review within one (1) Business Day of the subject Work being performed.
The submission to the Engineer or countersignature by the Engineer of daily Force
Account records shall not at any time be deemed to be an admission that the Work is
properly chargeable to Force Account.
.6 The Owner shall not be liable to pay for any Work based on Force Account for which the
daily Force Account records were not prepared and submitted in accordance with
GC 56.5.
Foothills Regional Services Commission Section 00700
Foothills Landfill Expansion - Cell 6 GENERAL CONDITIONS
2018-01/2017-3650.020 Page 55 of 63
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00700.doc: January 29, 2018
GC 57. CONCEALED OR UNKNOWN CONDITIONS
.1 Subject to GC 57.2, should one Party discover conditions at the Project Site which:
(a) are subsurface or otherwise inaccessible and concealed physical conditions, which
existed before the commencement of the Work, and which differ materially from
those reasonably inferable from or indicated in the Contract Documents or
studies, reports and other site data referenced therein; and
(b) materially affect the cost of the Work or the time required to perform the Work, then the
discovering Party shall provide Notice to the other Party within one (1) Business Day of
discovering such conditions and, in any case, before such conditions are disturbed.
.2 Physical conditions which are not visible but which are a logical extension, or part of a
visible physical condition, and physical conditions which can be reasonably accessed for
observation, shall not be considered as concealed for the purposes of GC 57.
.3 The Engineer shall promptly investigate and make a determination as to whether the
conditions fit within the parameters described in GC 57.1.
.4 If the determination is that the conditions:
(a) fit within the parameters described in GC 57.1 and the performance of the Work
with such conditions being present requires a Change that increases or decreases
the Contract Price or the Contract Time, or both, then a Change Order or a
Change Directive, as applicable, shall be issued to deal with the consequences of
the conditions; or
(b) do not fit within the parameters described in GC 57.1 or do fit within the
parameters described in GC 57.1 but do not cause an increase or decrease in the
Contract Price or Contract Time, or both, the Engineer shall provide Notice of
such determination to both the Owner and the Contractor.
.5 If either Party wishes to make a Claim that the Contract Time or Contract Price should be
adjusted because of concealed or unknown conditions then such Party shall give the other
Party and the Engineer Notice of such Claim immediately after that Party first becomes
aware of the concealed or unknown condition. No adjustment of Contract Price or
Contract Time shall be allowed for any Work undertaken prior to the delivery of such
Notice.
.6 If either Party gives Notice of concealed or unknown conditions pursuant to GC 57.1,
then as part of the Work the Contractor shall keep daily records in accordance with the
requirements of GC 58 CLAIMS.
Foothills Regional Services Commission Section 00700
Foothills Landfill Expansion - Cell 6 GENERAL CONDITIONS
2018-01/2017-3650.020 Page 56 of 63
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00700.doc: January 29, 2018
PART 12 DISPUTE RESOLUTION
GC 58. CLAIMS
.1 If the Contractor intends to make a Claim for an extension of Contract Time or for an
increase to the Contract Price, or if the Owner intends to make a Claim against the
Contractor for a credit to the Contract Price, the Party that intends to make the Claim
shall give timely Notice in writing of intent to Claim to the other Party and to the
Engineer.
.2 Upon commencement of the event or series of events giving rise to a Claim, the Party
intending to make the Claim shall:
(a) take all reasonable measures to mitigate any delay, loss or expense which may be
incurred as a result of such event or series of events, and
(b) keep such records as may be necessary to support the Claim.
.3 The Party giving Notice of intent to make a Claim shall submit to the Engineer a detailed
account of the amount claimed and the grounds upon which the Claim is based, within a
reasonable time.
.4 Where the event or series of events giving rise to the Claim has a continuing effect, the
detailed account submitted pursuant to GC 58.3 shall be considered to be an interim
account and the Party making the Claim shall, at such intervals as the Engineer may
reasonably require, submit further interim accounts giving the accumulated amount of the
Claim and any further grounds upon which it is based. The Party making the Claim shall
submit a final account after the end of the effects resulting from the event or series of
events.
.5 The Engineer’s findings, with respect to a Claim made by either Party, will be given by
Notice in writing to both Parties within thirty (30) Business Days after receipt of the
Claim by the Engineer, or within such other time period as may be agreed by the Parties.
.6 If such finding is not acceptable to either Party, the Claim shall be settled in accordance
with this PART 12 DISPUTE RESOLUTION.
GC 59. APPLICABLE TO ALL DISPUTES
.1 In the event of a Dispute, the Contractor shall abide by the Engineer’s decision with
respect to the Dispute, proceed diligently with the Work without prejudice to the
Contractor’s right to advance any Claim it may wish to assert with respect to the Dispute
and track all costs and impacts associated therewith.
Foothills Regional Services Commission Section 00700
Foothills Landfill Expansion - Cell 6 GENERAL CONDITIONS
2018-01/2017-3650.020 Page 57 of 63
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00700.doc: January 29, 2018
.2 The Contractor shall not delay the Work or any portion of the Work, nor shall there be
any extension of Contract Time solely on account of any Dispute Resolution pursuant to
this PART 12 – DISPUTE RESOLUTION.
.3 Disputes between the Parties relating to or arising out of the Contract shall be settled in
accordance with PART 12 DISPUTE RESOLUTION. No legal action shall be taken or
maintained without these provisions having been complied with, except to the extent that
such legal action is necessary to:
(a) preserve a right or commence a Claim that would otherwise be barred by statute
or another agreement if such legal action is not commenced or maintained; or
(b) obtain injunctive relief.
GC 60. NEGOTIATION
.1 A Party seeking resolution of a Dispute shall commence the negotiation process by
serving a Notice requiring negotiation of the Dispute on the other Party and the Engineer.
The date of delivery, or deemed date of delivery, as the case may be, is referred to in
PART 12 DISPUTE RESOLUTION as the “Negotiation Notice Date”. The Notice shall
describe the Dispute and reference any time or money claimed and reference all of the
provisions of the Contract that are relied on in relation to the Dispute.
.2 The Parties shall meet in person for the purpose of negotiating a resolution of the Dispute
within fifteen (15) Business Days of the Negotiation Notice Date. Failure to meet within
this time period means that, subject to the Parties otherwise agreeing, the negotiation will
be deemed complete and either Party can immediately commence mediation in
accordance with GC 61 MEDIATION.
.3 Each of the Parties shall discuss the Dispute in a professional and amicable manner and
negotiate in good faith. The Parties agree to use all reasonable efforts to resolve any
Dispute, whether arising during the existence of this Contract or at any time after the
expiration or termination of this Contract, which touches upon the validity, construction,
meaning, performance or effect of this Contract or the rights or liabilities of the Parties or
any matter arising out of, or in connection with this Contract.
.4 Disputes that are resolved by negotiation shall be formally concluded with a binding
agreement between the Owner and the Contractor, executed within thirty (30) Business
Days of the Negotiation Notice Date, stating the details of the resolution. Disputes that
are not fully concluded in this manner will proceed to mediation, or otherwise, pursuant
to GC 60.6.
.5 All meetings and communications during the negotiation are without prejudice and
cannot be used in evidence in any proceeding. The Parties shall treat the negotiation as
confidential and neither of the Parties shall disclose any part of the negotiation to any
third party, except for the sole purpose of dealing with the Dispute.
Foothills Regional Services Commission Section 00700
Foothills Landfill Expansion - Cell 6 GENERAL CONDITIONS
2018-01/2017-3650.020 Page 58 of 63
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00700.doc: January 29, 2018
.6 In the event that the Parties cannot resolve the Dispute within thirty (30) Business Days
of the Negotiation Notice Date, then, subject to the Parties otherwise agreeing, the Parties
shall participate in mediation in accordance with GC 61 MEDIATION.
GC 61. MEDIATION
.1 If the negotiation process provided for in GC 60 NEGOTIATION is initiated but a
Dispute is not resolved within thirty (30) Business Days from the Negotiation Notice
Date or the negotiation is deemed complete pursuant to GC 60.2 NEGOTIATION either
Party is entitled by Notice to the other Party to call for the appointment of an individual
to act as a mediator. The date of delivery, or deemed date of delivery, as the case may
be, is referred to in GC 61 as the “Mediation Notice Date”.
.2 Within fifteen (15) Business Days of the Mediation Notice Date, the Parties shall jointly
nominate a mediator. The cost of the mediator shall be shared equally between the
Parties. The mediator will be instructed to render invoices at monthly intervals. The
Owner shall fully pay the mediator for services rendered upon presentation of an invoice
by the mediator and deduct the Contractor’s share from payments otherwise due to the
Contractor. In the event that there are no payments due to the Contractor, the Owner shall
invoice the Contractor for the Contractor’s share of the cost of the mediator.
.3 The Parties shall submit their positions relating to the Dispute in writing to the mediator
and afford to the mediator access to all Records, documents and information the mediator
may reasonably request. The Parties shall meet with the mediator at such reasonable
times as may be required and shall, as facilitated by the mediator, negotiate in good faith
to resolve the Dispute. All meetings and communications with or involving the mediator
are without prejudice and cannot be used in evidence in any proceeding. The Parties
shall treat the mediation as confidential and neither of the Parties shall disclose any part
of the mediation to any third party, except for the sole purpose of dealing with the
Dispute.
.4 If the Dispute has not been resolved within forty (40) Business Days of the Mediation
Notice Date then, subject to the Parties otherwise agreeing, the mediation shall be
deemed to have been concluded.
.5 Once the mediation is concluded, or deemed to be concluded, any Dispute not settled
may be litigated in accordance with the Law.
PART 13 INDEMNIFICATIONS AND WARRANTY
GC 62. INDEMNIFICATIONS
.1 The Contractor shall at all times and without limitation, be fully liable for, and shall
indemnify and save harmless the Owner and its Personnel, including the Engineer, from
Foothills Regional Services Commission Section 00700
Foothills Landfill Expansion - Cell 6 GENERAL CONDITIONS
2018-01/2017-3650.020 Page 59 of 63
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00700.doc: January 29, 2018
and against all liabilities, losses, injuries, costs, damages, legal fees, disbursements, fines,
penalties, expenses, all manner of actions, causes of action, claims, demands and
proceedings, all of whatever nature and kind, which any of the Owner and its Personnel
may sustain, pay or incur or which may be brought or made against all or any of them,
and whether or not incurred, in connection with any action or other proceedings or claims
or demands made by third parties, relating to, or resulting from or arising out of all or any
of the following:
(a) the misconduct, negligent action or negligent failure to act, as the case may be, of
the Contractor or any of those Persons for whom the Contractor is responsible at
Law (including, without limitation, any of its Personnel or Subcontractors);
(b) the costs of repairs, clean-up or restoration paid by the Owner and any fines
levied against the Owner or the Contractor;
(c) any breach, violation or non-performance of any representation, warranty,
obligation, covenant, condition or agreement in this Contract set forth and
contained on the part of the Contractor to be fulfilled, kept, observed or
performed, as the case may be;
(d) any damages to third parties caused by, resulting at any time from, arising out of
or in consequence of the misconduct, negligent action or failure to act of the
Contractor or any of those Persons for whom the Contractor is responsible at Law
(including, without limitation, any of its Personnel or Subcontractors);
(e) any damages, costs, fines, expenses and penalties that the Owner is required to
pay on account of the Contractor performing the Work in breach of any Workers
Compensation Legislation order or regulation; or
(f) any damages, costs, fines, expenses and penalties arising out of or as a result of
the Contractor’s failure, or the failure of any Person for whom the Contractor is
responsible at Law, to comply with the requirements of GC 34 TOXIC OR
HAZARDOUS SUBSTANCES.
.2 The provisions in GC 62 are in addition to and shall not prejudice any other rights of the
Owner at Law or in equity.
.3 The Owner shall indemnify and hold harmless the Contractor and its Personnel from and
against claims, demands, losses, costs, damages, actions, suits, or proceedings arising out
of the Contractor’s performance of the Contract which are attributable to a lack of or
defect in title to the Project Site.
.4 If the Owner performs work at the Project Site at the same time as the Contactor is
performing the Work, then the Owner shall indemnify and hold harmless the Contractor
and its Personnel from and against claims, demands, losses, costs, damages, actions, suits
or proceedings by third parties that arise out of or are attributable to, any act or omission
Foothills Regional Services Commission Section 00700
Foothills Landfill Expansion - Cell 6 GENERAL CONDITIONS
2018-01/2017-3650.020 Page 60 of 63
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00700.doc: January 29, 2018
or alleged act or omission of the Owner and its Personnel in the performance of that
work.
GC 63. WARRANTY
.1 The Contractor warrants that the Work, including all workmanship, labour, Materials and
equipment supplied by the Contractor, either directly or indirectly, and incorporated into
the Work, shall comply in all respects with this Contract and shall be free from
Deficiencies.
.2 Subject to GC 63.3, the Warranty Period with regard to the Work shall be the longer of:
(a) one year from the date of Substantial Performance of the Work, for any Materials
or portions of the Work which are supplied or completed before Substantial
Performance of the Work is attained, unless a longer period is specified in the
Contract Documents for such Materials or portions of the Work;
(b) one year from the date of Total Performance of the Work, for any Materials or
portions of the Work which are supplied or completed after Substantial
Performance of the Work is attained, unless a longer period is specified in the
Contract Documents for such Materials or portions of the Work;
(c) one year from the date of Total Performance of the Work if some Work is
excluded from the Substantial Performance of the Work assessment, where
permitted by the Lien Act in effect at the Project Site, because a portion of the
Work cannot be completed expeditiously for reasons beyond the control of the
Contractor; and
(d) where a period longer than that described in GC 63.2(a) or GC 63.2(b) is specified
in the Contract Documents, then that period specified in the Contract Documents
shall apply from the date specified in the Contract Documents or, if no date is
specified, from the date of Total Performance of the Work.
.3 Where Warranty Work is performed, regardless of the initial Warranty Period, the
Warranty Period shall recommence for that Warranty Work for the same period as
initially contemplated commencing on the date of completion of the Warranty Work.
.4 The Contractor shall promptly perform the Warranty Work, at the Contractor’s expense,
for all Deficiencies which appear prior to and during the Warranty Period for which the
Contractor is provided Notice by the Owner or the Engineer no later than thirty (30)
Business Days after the end of the Warranty Period.
.5 All Warranty Work carried out by the Contractor shall be performed during periods of
time acceptable to the Owner.
Foothills Regional Services Commission Section 00700
Foothills Landfill Expansion - Cell 6 GENERAL CONDITIONS
2018-01/2017-3650.020 Page 61 of 63
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00700.doc: January 29, 2018
.6 The Contractor shall ensure that any Warranty Work which is of an emergency nature, as
reasonably determined by the Owner, is performed immediately upon receipt of Notice
from the Owner or the Engineer.
PART 14 CONFIDENTIALITY AND FREEDOM OF INFORMATION
GC 64. CONFIDENTIALITY
.1 The Contractor shall:
(a) hold, and shall take all reasonable steps to ensure that any Person employed,
engaged or contracted by it holds all Confidential Information in strict
confidence;
(b) not use, and shall take reasonable steps to ensure that any Person employed,
engaged or contracted by it does not use any Confidential Information other than
to perform the Work;
(c) not disclose, and shall take reasonable steps to ensure that any Person employed,
engaged or contracted by it does not disclose, any Confidential Information to
anyone other than those Persons engaged to perform the Work and then only to
the extent that such Confidential Information is directly required to be disclosed
in order to properly perform the Work; and
(d) not disclose, and shall take reasonable steps to ensure that any Person employed,
engaged or contracted by it does not disclose any Confidential Information to any
third party at any time during or subsequent to the duration of this Contract.
.2 The obligations set forth in GC 64.1 apply to any and all Confidential Information except
that which:
(a) is required to be disclosed by applicable Law; or
(b) subject to the applicable Law, is in the public domain or is provided to its
financial and legal advisors in confidence.
.3 The Contractor agrees that it shall not include any reference to the Owner, the Work or
the Project in any advertisement, public announcement or statement, or promotional
materials without the prior written consent being obtained from the Owner.
Foothills Regional Services Commission Section 00700
Foothills Landfill Expansion - Cell 6 GENERAL CONDITIONS
2018-01/2017-3650.020 Page 62 of 63
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00700.doc: January 29, 2018
PART 15 INTELLECTUAL PROPERTY AND TITLE TO THE WORK
GC 65. INTELLECTUAL PROPERTY
.1 The Contract Documents and models provided by the Engineer in any format are to be
used only with respect to the Project and are not to be used for other work and are not to
be copied or altered in any manner without the prior written authorization of the Engineer
and the Owner.
.2 The Contractor shall indemnify and hold harmless the Owner, its Personnel, agents and
consultants, including the Engineer, from any and all claims arising out of or as a result
of an infringement or an alleged infringement of a copyright, or a trademark, patent or
invention used or incorporated into the Work by the Contractor, the Subcontractors, or
any Person for whom the Contractor is responsible for at Law.
.3 Subject to any limitations of liability expressly provided for in this Contract and any
Law, the Owner shall, to the extent it can provide an indemnity in accordance with the
Law, indemnify the Contractor against claims arising out of or as a result of an
infringement or an alleged infringement of a patent relating to a model, plan, equipment
or design which was provided to the Contractor by the Owner as part of the Contract
Documents.
GC 66. BUILDERS LIENS AND TITLE TO THE WORK
.1 The Contractor shall remove or cause to be removed all affidavits of claim of lien, claims
of lien or liens filed or registered against the lands and premises on which the Work is
being performed or has been performed which claim of lien or liens arise out of anything
done or to be done under the Contract. Such removal shall be effected by the Contractor
forthwith upon demand by the Owner or the Engineer. Upon receiving satisfactory
security for its costs and a suitable indemnity, the Owner will authorize the Contractor to
apply to the Court in the name of the Owner to have the affidavits of claim of lien, claims
of lien or liens removed from the title to the lands upon payment into Court.
.2 Notwithstanding anything elsewhere contained in the Contract Documents, the
Contractor shall indemnify and hold harmless the Owner against and from all demands,
damages, costs, losses and actions arising in any way out of claims of lien or liens which
arise out of anything done or to be done under the Contract.
.3 The obligations imposed on the Contractor by the provisions of GC 66 shall not extend to
claims of lien or liens properly filed by the Contractor himself.
.4 The Contractor warrants that title to all of the Work and other matters or things produced
for the benefit of the Owner shall be free of all claims.
Foothills Regional Services Commission Section 00700
Foothills Landfill Expansion - Cell 6 GENERAL CONDITIONS
2018-01/2017-3650.020 Page 63 of 63
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00700.doc: January 29, 2018
.5 Title to all Materials shall, unless otherwise agreed in writing, vest in the Owner
absolutely upon delivery to the Project Site or upon payment therefore, whichever shall
first happen. All Materials shall remain at the risk of the Contractor until incorporated in
the Work and Total Performance of the Work is achieved. Title to any Materials which
are rejected by the Engineer or are ordered by him to be removed from the Project Site
for any reason shall revest in the Contractor immediately upon receipt of Notice of
rejection or order for removal.
.6 The Contractor warrants that Materials delivered to the Project Site shall:
(a) not be removed from the Project Site or changed except with the prior written
authorization of the Owner; and
(b) at all times be kept secure.
GC 67. RECORDS.1 The Contractor shall:
(a) maintain full Records of the estimated and actual costs of the Work together with
all tender calls, quotations, contracts, correspondence, invoices, receipts and
vouchers relating thereto. The Contractor shall maintain daily Records of the
time, materials and equipment employed on the Work. Daily Records shall
allocate the time, materials and equipment spent on each activity performed in a
day to a description of that activity;
(b) preserve the Records for the Work during the term of the Contract and for a
period of at least 3 years after Total Performance of the Work;
(c) make all Records and material referred to in GC 67.1(a) available to audit and
inspection by the Owner and by Persons acting on behalf of the Owner when
requested;
(d) allow any of the Persons referred to in GC 67.1(c) to make copies of and to take
extracts from any of the Records and material referred to in GC 67.1(a); and
(e) provide any Person referred to in GC 67.1(c) with information that may be
required from time to time in connection with such Records and material.
END OF SECTION
Foothills Regional Services Commission Section 00710
Foothills Landfill Expansion - Cell 6 INSURANCE
2018-01/2017-3650.020 Page 1 of 2
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00710.doc: January 29, 2018
Without limiting any of Contractor’s obligations or liabilities under the Contract Documents,
Contractor shall, and shall cause its Subcontractors to, obtain and continuously carry, while
Work is being performed and while any remedial or warranty work is being undertaken, at
Contractor’s own expense and cost, the following insurance coverage with minimum limits not
less than those stated:
Liability Insurance
General Liability Insurance, in a form acceptable to Owner, with limits of not less than
$5,000,000.00 inclusive per occurrence for bodily injury, death and damage to property,
including loss of use thereof. Such coverage shall be endorsed to include Products and
Completed Operations hazards, Contractual Liability (including liability assumed under
this Contract), and Owners and Contractors Protective Liability coverages, and shall
cover liability arising out of this Contract and all operations necessary or incidental
thereto.
The liability insurance shall include Owner and Engineer as additional insureds with
respect to this contract and contain a cross liability clause.
Automobile Insurance (Owned and Non-Owned)
Automobile Liability Insurance with respect to licensed vehicles, with coverage limits of
not less than $2,000,000.00 inclusive per occurrence for bodily injury, death and damage
to property, covering all licensed vehicles owned, leased, rented or used by Contractor.
Contractors’ Equipment Insurance
“All-Risk” Contractors’ Equipment Insurance to the full insurable value of construction
machinery and equipment used by Contractor in the performance of Work, including
boiler insurance for temporary boilers and pressure vessels as applicable.
Builders Risk Insurance
“All-Risks” Course of Construction Insurance in the joint names of Contractor, Owner
and Engineer, with the subcontractors as unnamed insureds, insuring not less than one
hundred and ten percent (110%) of the sum of the amount of the Contract Price and the
full value of materials provided by the Owner for incorporation into Work, with a
deductible not exceeding $5000.00. Such coverage to contain sublimits for materials in
transit and materials stored at unnamed locations.
Foothills Regional Services Commission Section 00710
Foothills Landfill Expansion - Cell 6 INSURANCE
2018-01/2017-3650.020 Page 2 of 2
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00710.doc: January 29, 2018
Aircraft and Watercraft Liability Insurance
Aircraft and Watercraft Liability Insurance with respect to owned and non-owned aircraft
and watercraft, if used directly or indirectly in the performance of Work, with coverage
limits of not less than $3,000,000.00 inclusive per occurrence for bodily injury, death and
damage to property, including loss of use thereof and limits of not less than $3,000,000
for aircraft passenger hazard.
All policies of insurance shall be in a form acceptable to Owner and shall not allow subrogation
claims by the insurer against Owner or Engineer.
All policies of insurance shall provide that at least thirty (30) days prior written notice be given
to Owner in the event of cancellation or amendment restricting coverage.
Prior to commencing Work, Contractor shall provide Owner with Certificates of Insurance in a
form acceptable to Owner, and with a letter from the insurer stating that the insurance provided
complies with the requirements of the Contract.
Deductibles, if any, which are applicable to the insurance specified herein, shall be borne by
Contractor.
The specified limits of insurance and coverages in no way define or limit the obligation of
Contractor to indemnify Owner in the event of loss.
Owner makes no representation or warranty with respect to the extent or adequacy of the
insurance protection afforded by the insurance policies that are specified in this section.
Contractor shall be fully responsible to determine additional insurance coverages that may be
necessary and advisable for protection of Contractor or to fulfil Contractor’s obligations under
this Contract.
END OF SECTION
Foothills Regional Services Commission Section 00800
Foothills Landfill Expansion - Cell 6 SUPPLEMENTARY CONDITIONS
2018-01/2017-3650.020 Page 1 of 5
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00800.doc: January 29, 2018
MODIFICATIONS TO GENERAL CONDITIONS
The General Conditions are hereby revised as follows:
GC 1. DEFINITIONS
Delete “Engineer” in its entirety and replace with;
“Engineer” shall mean NLR/AE Consultants, acting through a delegate duly appointed to act on
its behalf, or such other engineer, architect or person as may be from time to time be duly
authorized and appointed in writing by the Owner.
Add “Geosynthetics Installation Contractor” as follows;
“Geosynthetics Installation Contractor” shall mean the company(s) contracted by the
Contractor as its subcontractor(s) for the supply and installation of the geosynthetic components
of the Work.
GC 18. DEFICIENCIES
Delete GC 18.1 in its entirety and replace with:
.1 Upon failure of the Contractor to perform the work in accordance with the Contract
Documents, and after ten (10) days written notice to the Contractor, or without notice if
an emergency or danger to the work or public exists, the Owner may, without prejudice
to any other remedy the Owner may have, or correct such deficiencies. The cost of work
certified by the Engineer as having been performed by the Owner in correcting
deficiencies shall be paid by the Contractor, or may be deducted by the Owner from any
payment then or thereafter due to the Contractor.
GC 23. SUSPENSION OF WORK BY OWNER
Delete GC 23. in its entirety and replace with:
.1 The Owner may at any time suspend the Work or delay commencement thereof, or any
portion thereof, provided he gives the Contractor five (5) Days’ Notice of suspension or
delayed commencement. The Contractor shall resume Work upon Notice from the
Owner within ten (10) Days after the date set forth in such Notice to resume Work.
.2 In the event that the Owner chooses to delay the commencement of the Work or any
portion thereof or implement a temporary suspension:
(a) the Contract Time shall be adjusted by the Owner to account for the period of
delay or suspension affecting the Work and any seasonal impact on the Work
directly resulting from the delay or suspension; and
Foothills Regional Services Commission Section 00800
Foothills Landfill Expansion - Cell 6 SUPPLEMENTARY CONDITIONS
2018-01/2017-3650.020 Page 2 of 5
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00800.doc: January 29, 2018
(b) the Owner shall reimburse the Contractor for direct and provable costs and
expenses incurred by the Contractor necessitated by such delay or suspension of
the Work or portion thereof, but the Contractor shall not recover from the Owner
payment for any loss of profits or any other form of damages.
.3 If the delay or suspension of the Work lasts more than ninety (90) Days, the Contractor
may, at its option and on ten (10) Days’ Notice, terminate the Contract as provided for in
GC 50. CONTRACTOR’S RIGHT TO TERMINATE FOR DEFAULT. The Contractor
shall not be permitted to terminate the Contract when only a portion of the Work is
delayed or suspended.
.4 A suspension of the Work because of seasonal climatic conditions, whether ordered by
the Owner or the Engineer or not, shall not be deemed to be a suspension of the Work
within the meaning of GC 23.
.5 Except as provided by GC 23., the Owner shall not be liable in any way to the Contractor
in relation to a suspension or delayed commencement of the Work, or any portion of the
Work, and under no circumstances shall the Owner be liable for Consequential Damages
as a result of suspension or delayed commencement of the Work pursuant to GC 23.
GC 34. TOXIC OR HAZARDOUS SUBSTANCES
Remove GC 34. in its entirety.
GC 37. PROGRESS PAYMENTS
Remove GC 37. in its entirety and replace with:
.1 The Owner and Contractor shall agree to a payment date at the start of the project. The
Engineer shall prepare and issue to the Owner a Payment Certificate for the period ending
with the agreed to payment date once a month.
.2 The Payment Certificate shall be set out as up to and including the day of submission:
(a) the total value of the Work completed and the Materials incorporated into the
Work;
(b) the total Quantities, or the percent complete for each pay item;
(c) all holdback amounts if any;
(d) the total amount owing by the Owner to the Contractor;
(e) any liquidated damages or other deductions; and
(f) set offs permitted by the Contract Documents.
.3 The Engineer shall not finalize a Payment Certificate without consulting with the
Superintendent about the Quantities and amounts to be included in a Payment Certificate.
Foothills Regional Services Commission Section 00800
Foothills Landfill Expansion - Cell 6 SUPPLEMENTARY CONDITIONS
2018-01/2017-3650.020 Page 3 of 5
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00800.doc: January 29, 2018
.4 If accepted by the Owner, the period referred to in GC 37.1 for the issuance of the
Payment Certificate may be extended by any time that the Contractor takes to provide the
consultation to the Engineer, or to provide any supporting documentation the Engineer
requires to finalize the Payment Certificate.
.5 If the Engineer does not agree with the Superintendent regarding any aspect of the
Payment Certificate then the Engineer shall without delay:
(a) prior to issuing the Payment Certificate, fully advise the Superintendent of the
reasons for the disagreement; and then
(b) issue the Payment Certificate to the Owner, with a copy to the Contractor, in the
amounts the Engineer determines are correct.
.6 The Contractor shall provide to the Engineer all documentation as required by the
Contract Documents in support of the completed portion of the Work and Materials
covered by the Payment Certificate including inspection reports, invoices, weigh tickets
and daily Force Account records.
.7 If requested in writing by the Engineer the Contractor shall, as a precondition to the
issuance of the Payment Certificate, provide a sworn declaration in a form acceptable to
the Engineer that all amounts relating to the Work, due and owing to third parties,
including all Subcontractors and Suppliers, as of the agreed to payment date previous to
that covered by the Payment Certificate, have been paid.
.8 Except for materials or products which are identified in the Contract Documents as being
“Supply Only”, payments shall not be made for materials or products purchased by the
Contractor but not fully incorporated into the Work at the Project Site.
.9 Subject to GC 44. WITHHOLDING OF PAYMENT AND SET OFF, the Owner shall
make payment to the Contractor of amounts due by the Owner no later than
thirty (30) Days after the receipt by the Owner of the Payment Certificate as issued by the
Engineer.
.10 All Payment Certificates issued by the Engineer shall be to the best of the Engineer’s
knowledge, information, and belief.
.11 The monthly progress Payment Certificates shall not bind the Owner or Engineer in any
manner in the preparation of subsequent Payment Certificates or the final progress
Payment Certificate, but shall be construed and held to be approximate only. By issuing
any Payment Certificate, the Engineer does not assume any of the responsibility of the
Contractor with respect to the correctness or completeness of the Work, including the
Contractor’s responsibility to ensure that the Work has been completed in accordance
with the Contract Documents.
Foothills Regional Services Commission Section 00800
Foothills Landfill Expansion - Cell 6 SUPPLEMENTARY CONDITIONS
2018-01/2017-3650.020 Page 4 of 5
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00800.doc: January 29, 2018
GC 48. LATE COMPLETION
Add GC 48.4 as follows:
.4 The pre-estimate of the Owner’s additional costs pursuant to GC 48.1 shall be $2,000 per
working day.
GC 50. CONTRACTOR’S RIGHT TO TERMINATE FOR DEFAULT
Delete GC 50.2 in its entirety and replace with:
.2 If the Work is stopped or otherwise delayed for a period of forty-five (45) Days or more
as provided for in GC 23. SUSPENSION OF WORK BY OWNER or under an order or
decision of a court or decision of another Governmental Authority, and providing that
such order was not issued as the result of an act or fault of the Contractor or any Person
for whom the Contractor is responsible at Law, the Contractor may terminate the Work
without prejudice to any other right or remedy the Contractor may have, by giving the
Owner Notice five (5) Business Days prior to such termination. The Contractor shall not
be permitted to terminate the Contract when only a portion of the Work that is incomplete
is delayed or suspended until ninety (90) days after the Work, except for that portion
which is suspended or delayed, is substantially completed.
ADDITIONAL GENERAL CONDITIONS
The following General Conditions are hereby added:
GC 68. OCCUPATIONAL HEALTH AND SAFETY
1. Contractor shall comply with the provisions of the Occupational Health and Safety Act,
R.S.A. 1980, Chapter 0-2, and amendments thereto and regulations thereunder or any
successive legislation, and shall at all times ensure that all subcontractors at the Site shall
comply with the requirements of the said Act and regulations thereunder. Contractor shall be
the general representative and agent to Owner for the purposes of insuring compliance with
safety regulations for both itself and subcontractors. Contractor shall bring to the attention of
subcontractors the provisions of the Occupational health and Safety Act and regulations
thereunder.
2. For the purposes of the project, Contractor is assigned the role of Prime Contractor for the
Site and is responsible for ensuring compliance with the Occupational Health and Safety Act
by all employers and employees on the Site.
3. Contractor shall have either full certification in the Alberta Labour approved “Certificate of
Recognition” (C.O.R.) Program appropriate to their industry or a Temporary Letter of
Certification (T.L.C.) issued by the Alberta Construction Safety Association or other
appropriate industry association.
Foothills Regional Services Commission Section 00800
Foothills Landfill Expansion - Cell 6 SUPPLEMENTARY CONDITIONS
2018-01/2017-3650.020 Page 5 of 5
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\00800.doc: January 29, 2018
GC 69. HISTORICAL RESOURCES ACT
1. The Contractor shall comply, and shall ensure that its sub-consultants comply, with the
Historical Resources Act of Alberta.
2. Where, in the course of Work under the Contract, suspected archaeological or historical
artifacts are unearthed, the Contractor shall immediately:
a) Suspend all operations in the vicinity of the find,
b) Notify the Engineer of the location of the find and the nature of the materials, structures
or artifacts found and,
c) Ensure that the site is preserved until its significance can be assessed.
3. Delays caused through compliance with this Act will result in a time existing only for
performance of Contract and the Owner shall not be obliged to pay any additional amount
because of such delay.
END OF SECTION
Foothills Regional Services Commission Section 01001
Foothills Landfill Expansion - Cell 6 GENERAL REQUIREMENTS
2018-01/2017-3650.020 Page 1 of 15
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\01001.doc: January 29, 2018
1 General
1.1 SUMMARY OF WORK
.1 Work Included:
.1 The Work under this Contract consists of construction of a Class II Landfill Cell
for Foothills Regional Services Commission, hereinafter called the Owner.
.2 The following work is included, but not limited to:
.1 Test pit operations.
.2 Strip the landfill cell footprint and common excavation and designated stockpile
areas.
.3 Earthworks related to the landfill development.
.4 Construction of a compacted clay liner.
.5 Supply and installation of leachate collection system.
.6 Supply and installation of a leachate riser.
.7 Supply and installation of a subdrain system, and riser.
.8 Supply and installation of 2-sided geocomposite.
.9 Supply and installation of HDPE liner.
.10 Installation of Owner supplied tire shred over the cell floor.
.11 Supply and installation of non-woven heavy geotextile cushion layer.
.12 Supply and installation of non-woven light geotextile filter layer.
.13 Restoration and topsoiling of disturbed areas and ditches.
.14 Coordination with the Engineer’s geotechnical consultant for all geotechnical
materials testing.
.15 Prepare and compile all required testing and material data.
.16 Control, layout, quantity and record survey requirements.
.17 Maintain dust control on-site as required.
.18 The Work, unless specifically stated otherwise, shall include the furnishing of all
material, product, plant, labour and transportation necessary to complete the Work.
.19 Any minor item of the Work not called for in the Specifications or shown on the
Drawings but clearly required to meet the intent of design and normally provided for
the proper operation of the Work shall be provided as if specifically called for in the
Contract Documents.
.20 Contract method: unit price.
Foothills Regional Services Commission Section 01001
Foothills Landfill Expansion - Cell 6 GENERAL REQUIREMENTS
2018-01/2017-3650.020 Page 2 of 15
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\01001.doc: January 29, 2018
.3 Drawings and Specifications Furnished:
.1 Owner will provide four (4) copies of Drawings and Specifications to Contractor.
.2 Additional copies of Drawings and Specifications are available upon request at an
additional cost.
.3 Maintain at Site one (1) complete set of full size Drawings and Specifications.
Make available to Engineer at any time.
1.2 SITE SAFETY
.1 Owner’s site safety requirements:
.1 The Contractor shall adhere to all requirements of the Owner’s site safety
program.
.2 Minimum PPE requirements identified in the Owner’s site safety program are as
follows:
.1 Steel toed boots.
.2 Safety glasses.
.3 Cotton coveralls with reflective stripping.
.4 Hard hats.
.5 Hearing protection shall be worn in any area where the measured noise level
is greater than or equal to 85 dBA.
.6 All identified PPE shall comply with the appropriate CSA standard.
.3 The Owner site safety program will be available at all times at the request of the
contractor.
.4 Contractor’s safety representative will receive the Owner’s site orientation and
endorsement. The representative will be required to incorporate this orientation into
the Contractor’s site indoctrination and submit employee acknowledgements to the
Plant Manager/Lead Operator.
.2 Required content of the Contractor’s site safety program are as follows:
.1 Site Indoctrination and sign in procedure.
.2 Safe Work permit system.
.3 Hazard identification program and pre-job safety reviews.
.4 Hazard and near-miss reporting system.
.5 Man-hour and equipment time tracking system.
.3 Owner will review the Health and Safety program of the Contractor as well as perform
audits during the project.
Foothills Regional Services Commission Section 01001
Foothills Landfill Expansion - Cell 6 GENERAL REQUIREMENTS
2018-01/2017-3650.020 Page 3 of 15
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\01001.doc: January 29, 2018
.4 The Contractor shall provide MSDS and all applicable labels for all WHMIS
controlled products.
.5 Submit an Incident Report to the Engineer within twelve (12) hours of any
environmental or safety related incident.
.6 All Work performed within the identified operating area of the Owner’s site must take
place under the control of the "Safe Work Permit System".
.7 Contractors are expected to Work within the conditions of the Safe Work Permit and
as discussed and signed off by the Plant Manager/Lead Operator prior to initiating the
agreed Work. The Contractor shall also communicate the conditions of the Safe Work
Permit to their employees.
1.3 QA/QC ADMINISTRATION
.1 Submittal Procedures to be followed by the Contractor:
.1 Procedures for submitting to the Engineer or Inspector:
.1 Step 1: Contractor will collect the required submittals as listed in Table 1-1
and provide to Engineer and/or Inspector as requested.
.2 Step 2: The Engineer or Inspector shall ensure that each submittal document
meets or exceeds the testing standards and minimum requirements outlined in the
Specifications. Submittals not meeting the minimum requirements will be
returned to the Contractor for resubmission.
.3 Step 3: Engineer or Inspector will review, date, sign and record status of each
submittal.
.4 Step 4: The Engineer or Inspector shall retain one (1) duplicate copy in their
Quality Control binder. Contractor to retain original in Contractor’s Quality
Control binder.
.2 Table 1-1:
Item Submittal Submittal Code
1Construction Progress Schedule: Submit to Engineer as
required.01001.1
2Site Safety Meeting Minutes: Submit to Inspector after each
meeting.01001.2
3 SStatistical Summary of OH&S Related Issue: Submit to
Inspector after each progress meeting.01001.3
4Contractor’s Full Size Mark-up Drawings: Submit to Engineer
within seven (7) days of substantial completion.01450.1
Foothills Regional Services Commission Section 01001
Foothills Landfill Expansion - Cell 6 GENERAL REQUIREMENTS
2018-01/2017-3650.020 Page 4 of 15
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\01001.doc: January 29, 2018
Item Submittal Submittal Code
5
Manufacturer’s Material Affidavits for Resin Certification and
Geomembrane Material: Submit to Engineer seven (7) days
before material placement.
02073.1
6
Letter of Certification from Manufacturer stating Geomembrane
Material adheres to the GRI GM13 requirements: Submit to
Engineer seven (7) days before material placement.
02073.2
7Geomembrane Roll Certificates: Submit to Engineer
seven (7) days before material placement.02073.3
8
Geomembrane Proposed Panel Sketch Layout: Installer’s field
superintendent to submit sketch to Inspector before material
placement.
02073.4
9Geomembrane Installer’s QA/QC Program: Submit to
Engineer before material placement.02073.5
10
Names of the Supervisor, Master Seamer and other Personnel
who will complete Geomembrane Installation: Submit to
Engineer before material placement.
02073.6
11
Two (2) Year Geomembrane Installation Warranty: Submit to
Engineer within fourteen (14) days of final inspection of
installed geomembrane.
02073.7
12
As-built Record of Geomembrane Panel Layout, Seam
Locations, Seam Details and Liner Penetration Details:
Submit to Engineer within fourteen (14) days of final
inspection of installed geomembrane.
02073.8
13
Geomembrane Installation Report: Submit to Engineer within
fourteen (14) days of final inspection of installed
geomembrane. Report is to include copies of all installation
quality control test results taken in accordance with this
Specification.
02073.9
14Sub-grade Acceptance Certificate: Submit to Inspector within
forty-eight (48) hours of sub-grade inspection.02073.10
15Destructive Liner Samples: Submit to Inspector within
forty-eight (48) hours of geomembrane final inspection.02073.11
Foothills Regional Services Commission Section 01001
Foothills Landfill Expansion - Cell 6 GENERAL REQUIREMENTS
2018-01/2017-3650.020 Page 5 of 15
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\01001.doc: January 29, 2018
Item Submittal Submittal Code
16
Survey of Stripped Area (pre and post stripping survey):
Provide to Engineer within seven (7) days of stripping
completion.
02113.1
17
Survey of all Common Excavation and Finished Subgrade
Work (exterior landfill cell subgrade survey): Submit to
Engineer within seven (7) days of excavation and subgrade
completion.
02210.1
18
Survey of Bottom of Clay Liner: Submit to Engineer and
Inspector within forty-eight (48) hours of completing subgrade
preparation.
02215.1
19
Survey of Top of Clay Liner: Submit to Engineer and
Inspector within forty-eight (48) hours of completing top of
clay liner.
02215.2
20PVC and PE Pipe Data: Submit to Inspector before pipe
installation.02411.1
21
Two (2) Year Geosynthetics Installation Warranty: Submit to
Engineer within fourteen (14) days of final inspection of
installed geomembrane.
02411.2
22Manufacturer’s Material Affidavits for Light and Heavy
Geotextile: Submit to Engineer before material placement.02411.3
23Manufacturer’s Material Affidavits for Double-Sided
Geocomposite: Submit to Engineer before material placement.02411.4
24Light and Heavy Geotextile Roll Certificates: Submit to
Engineer before material placement.02411.5
25Double-sided Geocomposite Roll Certifications: Submit to
Engineer before material placement.02411.6
26Pipe Jointing Installation Procedures: Submit to Inspector
before installing pipe.02411.7
27Hydraulic Conductivity Test Results for Drainage Gravel:
Submit to Engineer and Inspector before material placement.02411.8
Foothills Regional Services Commission Section 01001
Foothills Landfill Expansion - Cell 6 GENERAL REQUIREMENTS
2018-01/2017-3650.020 Page 6 of 15
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\01001.doc: January 29, 2018
Item Submittal Submittal Code
28Sieve Analysis Test Results for Drainage Gravel Media:
Submit to Engineer and Inspector before material placement.02411.9
29Manufacturer’s Material Affidavits for Geosynthetics: Submit
to Engineer before material placement.02415.1
30Geosynthetics Roll Certificates: Submit to Engineer before
material placement.02415.2
31Perforated PVC Pipe Data: Submit to Inspector before pipe
installation.02415.3
32Survey of Subdrain Pipe: Submit to Engineer within
seven (7) days of installation of subdrain pipe.02415.4
33Survey of the Topsoiled Areas: Submit to Engineer withinseven (7) days of topsoil completion.
02484.1
34Seed Purity and Germination Test Results: Submit to Engineerseven (7) days before seeding. 02485.1
35Confirmation of Seed Mixture (seed certificate): Submit toEngineer seven (7) days before seeding. 02485.2
36Survey of the Seeded Areas: Submit to Engineer within
seven (7) days of seeding completion.02485.3
37Manufacturer’s Material Affidavit for GCL: Submit toEngineer before material placement.
02594.1
38GCL Roll Certificates: Submit to Engineer before material
placement.02594.2
39GCL Raw Material Certification for Bentonite and Geotextile:
Submit to Engineer before material placement.02594.3
40
GCL Proposed Panel Sketch Layout: Installer’s field
superintendent to submit sketch to Inspector before material
placement.
02594.4
41GCL Material Installer’s QA/QC Program: Submit to
Engineer before material placement.02594.5
42Two (2) Year GCL Installation Warranty: Submit to Engineer
before applying for substantial completion.02594.6
Foothills Regional Services Commission Section 01001
Foothills Landfill Expansion - Cell 6 GENERAL REQUIREMENTS
2018-01/2017-3650.020 Page 7 of 15
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\01001.doc: January 29, 2018
Item Submittal Submittal Code
43As-built Record of GCL Panel Layout: Submit to Engineer
within seven (7) days of final inspection of installed GCL.02594.7
44GCL Installation Report: Submit to Engineer within
seven (7) days of final inspection of installed GCL.02594.8
45Manufacturer Certification (1 million m2 production): Submit
to Engineer seven (7) days before material placement.02594.9
46
GCL Installer’s Field Superintendent Certification of
Experience five (5) projects > 50,000 m2: Submit to Engineer
seven (7) days before material placement.02594.10
47Sub-grade Acceptance Certificate: Submit to Inspector within
forty-eight (48) hours of sub-grade inspection.02594.11
1.4 FIELD ENGINEERING
.1 Survey Requirements:
.1 Provide qualified surveyor, acceptable to Owner.
.2 Locate, confirm and protect control points prior to starting site Work. Preserve
permanent reference points during construction.
.3 Establish at least two (2) permanent control points on site, referenced to establish
control points by survey control points. Record locations, with horizontal and vertical
data in project record documents.
.4 Establish lines and levels, locate and layout, by instrumentation.
.5 Maintain a complete, accurate log of control and survey Work. A maximum
25 m x 25 m layout and record grid is required.
.6 At the end of each stage in construction turn over survey data in digital and paper
format to Engineer.
.2 Geotechnical Testing Services:
.1 The Contractor shall coordinate the geotechnical testing requirements with the
Engineer’s representative.
.2 The Contractor is to provide a minimum of forty-eight (48) hours notice for any
geotechnical testing requirements.
.3 In the event the Contractor requires geotechnical services for his own construction
purposes while completing the Work, the Contractor shall supply his own geotechnical
forces and equipment at the Contractor’s cost.
Foothills Regional Services Commission Section 01001
Foothills Landfill Expansion - Cell 6 GENERAL REQUIREMENTS
2018-01/2017-3650.020 Page 8 of 15
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\01001.doc: January 29, 2018
.4 The Contractor shall provide equipment and operator to support Engineer’s
Geotechnical Testing Representative in performing test pit operations.
.3 Subsurface Conditions:
.1 Promptly notify Engineer in writing if subsurface conditions at place of the Work
differ materially from those indicated in Contract Documents, or reasonable
assumption of probable conditions based thereon.
.2 After prompt investigation, should Engineer determine that conditions do differ
materially, instructions will be issued for changes in the Work as provided in the
Contract procedures for changes in the Work.
1.5 SCHEDULE
.1 Schedules Required:
.1 Construction Schedule.
.2 Schedule Format:
.1 Prepare schedule in form of a Gantt chart in pdf format.
.2 Provide separate bar for each operation.
.3 Provide horizontal time scale identifying first workday of each week.
.3 Submission:
.1 Submit to Engineer as part of the tender requirements.
.2 Engineer will return schedule and may request revisions be made.
.3 Resubmit finalized schedule within three (3) days after return of reviewed copy.
.4 Schedule Updates:
.1 In the event of any changes to the Contractor’s workflow, an updated
schedule shall be provided to the Engineer.
1.6 INSPECTION
.1 Owner and Engineer shall have access to the Work at all times during construction.
.2 Give timely notice requesting inspection if Work is designated for special inspections
by Engineer.
.3 If Contractor covers or permits to be covered Work that has been designated for
special tests, inspections or approvals before such is made, uncover such Work, have
inspections or tests satisfactorily completed and make good such Work.
1.7 PROJECT MEETINGS
.1 The following meetings will be scheduled and administrated by the Engineer:
Foothills Regional Services Commission Section 01001
Foothills Landfill Expansion - Cell 6 GENERAL REQUIREMENTS
2018-01/2017-3650.020 Page 9 of 15
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\01001.doc: January 29, 2018
.1 Pre-construction meeting: meeting will be conducted on site to discuss
administrative procedures, responsibilities, safety, and QA/QC.
.2 Progress meetings: meetings will be held as required to discuss schedule,
QA/QC, administrative issues, and issues requiring resolution.
1.8 CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS
.1 Installation/Removal:
.1 Provide construction facilities and temporary controls in order to execute Work
expeditiously.
.2 Remove from site all such Work after use.
.2 Water Control:
.1 Water existing prior to starting Work shall be managed and controlled by
Contractor as required.
.2 Protect open excavations and laydown area against flooding and damage due to
surface runoff and/or pond water seepage. Provide temporary drainage and pumping
facilities to keep excavation and site free from standing water.
.3 Keep excavations, pits, subgrade and laydown area free of water at all times
during the course of the Work. Provide all necessary pumps and other suitable
equipment, and any necessary temporary drainage system to meet this requirement.
.4 Use extreme caution in positioning pumps or other dewatering equipment, and the
discharge from same, to ensure that damage does not occur to existing structures and
to Works under construction.
.5 Dispose of water in a manner not detrimental to public health, environment,
public and private property, other Contractors, or any portion of the Work completed
or under construction. Water collected from excavation and all areas of site shall not
be released to surrounding areas prior to Engineer’s review and acceptance of
discharge plan.
.6 Provide dewatering plan at request of Engineer, outlining methods, equipment,
approval requirements and overall environmental issues.
.7 Contractor shall determine the amount of surface water and seepage water to be
encountered and to allow for handling of such water. Any additional excavation to
control water shall be considered as unauthorized over-excavation.
.8 Contractor to control surface water during geosynthetic installation, and provide
surface water discharge plan at the Engineer’s request.
.9 The release of surface water shall be completed in accordance with the
requirements of the approval.
Foothills Regional Services Commission Section 01001
Foothills Landfill Expansion - Cell 6 GENERAL REQUIREMENTS
2018-01/2017-3650.020 Page 10 of 15
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\01001.doc: January 29, 2018
.3 Erosion and Sediment Control:
.1 The Work is to be executed by methods to control surface drainage from common
excavation, stockpiles and all other Work areas. Contractor is responsible for
prevention of erosion and sedimentation control.
.2 The Contractor is to provide and maintain any temporary measures such as
ditches, drains, berms, terracing, rip-rap, sedimentation basins, dikes and any other
construction to prevent erosion and migration of silt, mud, sediment and other debris
off Site or to other areas of Site where damage could result.
.3 The Contractor is required to install silt fencing or straw bales to control erosion
as required or as directed by the Engineer. All silt fencing and/or straw bale material
supply and Work shall be considered as incidental to the Contract.
.4 Dust Control:
.1 Provide dust control as required to areas of the active construction to prevent
health and safety concerns.
.5 Sanitary Facilities:
.1 Provide sufficient sanitary facilities for workers in accordance with local health
authorities.
.2 Maintain in clean condition.
.6 Water Supply:
.1 Provide a continuous supply of potable water for construction and sanitary use.
.7 Temporary Telephone:
.1 Provide and pay (including monthly rental costs) for temporary telephones, fax
and high-speed internet (if available) necessary for Contractor, Engineer and
emergency use.
.8 Field Office:
.1 Provide temporary office for Engineer use and for Contractor administrative
responsibilities. Provide the Engineer’s field office with light, heat, air conditioning
and power.
.2 Inside dimensions minimum 5.5 m long x 3 m wide x 2.4 m high with
four (4) windows and one (1) lockable door.
.3 Equip office with the following:
.1 One (1) standard double pedestal lockable desk and chair.
.2 Eight (8) stackable chairs.
.3 One (1) drawing table with stool.
.4 One (1) standard 3-drawer legal size filing cabinet.
Foothills Regional Services Commission Section 01001
Foothills Landfill Expansion - Cell 6 GENERAL REQUIREMENTS
2018-01/2017-3650.020 Page 11 of 15
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\01001.doc: January 29, 2018
.5 One (1) shelf.
.6 One (1) conference table capable of seating eight (8) persons.
.7 Clean office prior to all site meetings and at request of Engineer.
.8 Provide MSDS and all applicable labels for controlled products.
.9 Fire Protection:
.1 Provide fire protection equipment required by regulation. Orient all site personnel
on location and operation of fire protection equipment.
.10 Site Security:
.1 Contractor’s Site Security to comply with Owner or the Engineer, and site security
requirements.
.2 Security of all contracted equipment, personnel, materials and belongings,
including those of Subcontractors is the responsibility of the respective Contractors for
the entire duration of the Works.
.11 Equipment/Tool/Materials Storage:
.1 Provide and maintain, in clean and orderly condition, lockable weatherproof sheds
for storage of tools, equipment and materials.
.2 Locate materials not required to be stored in weatherproof sheds on site in manner
to cause least interference with Work activities.
.12 Access Roads:
.1 Construct and maintain all temporary site access roads required to perform and
access the Work.
.2 Remove temporary access roads and reclaim affected areas following completion
of the Work.
.3 Any areas under temporary haul roads must be stripped of topsoil and subsoil
prior to construction and replaced to original condition post construction.
.13 Project Cleanliness:
.1 Maintain the Work in tidy condition, free from accumulation of waste products
and debris.
.2 Remove waste material and debris from site at end of each working day.
.3 Clean all areas prior to start of finish Work, maintain areas and remove all
contaminants during finishing operations.
Foothills Regional Services Commission Section 01001
Foothills Landfill Expansion - Cell 6 GENERAL REQUIREMENTS
2018-01/2017-3650.020 Page 12 of 15
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\01001.doc: January 29, 2018
.14 Existing Facilities:
.1 Existing facilities in use by the Owner are not designated for use by the Contractor
or his personnel. This includes as a minimum, telephone, shop, tools, fax and
washrooms.
.2 Protect existing monitoring wells from damage. Costs resulting from damage to
wells will be deducted from final Contract payment.
.3 Protect existing survey control points. Costs resulting from damage to control
points will be deducted from final Contract payment.
1.9 SHOP DRAWINGS AND PRODUCT DATA
.1 Shop Drawings and Product Data:
.1 The term "Shop Drawings" means Drawings, diagrams, illustrations, schedules,
performance charts, brochures, test data and other data which are to be provided by
Contractor to illustrate details of a portion of the Work.
.2 Indicate materials, methods of construction and attachment or anchorage,
connection, explanatory notes and other information necessary for completion of
Work.
.3 Make changes in Shop Drawings as Engineer may require.
.4 Contractor's responsibility for errors and omissions in submission is not relieved
by Engineer's review of submittals.
.5 Contractor's responsibility for deviations in submission from requirements of
Contract Documents is not relieved by Engineer's review.
.6 Keep one (1) reviewed copy of each submission on Site.
.7 Detail all Shop Drawings using the metric system. Prepare to a drafting standard
equivalent to that of the Contract Drawings.
.8 Submit Shop Drawings to the Engineer for review with a Transmittal Form as
provided by the Engineer. This Transmittal Form is a multi-part form. Type or print
the appropriate information on the form to fully describe the submittal being sent for
review. Retain one (1) copy of the form for filing and record purposes before
Drawings are sent to the Engineer.
.9 Submit one (1) copy of product data sheets, test data or brochures for
requirements requested in the Specifications and as the Engineer may reasonably
request where Shop Drawings will not be prepared due to standardized manufacture of
product.
.10 Submit one (1) print of Shop Drawings for each requirement requested in the
Specifications and as the Engineer may reasonably request.
Foothills Regional Services Commission Section 01001
Foothills Landfill Expansion - Cell 6 GENERAL REQUIREMENTS
2018-01/2017-3650.020 Page 13 of 15
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\01001.doc: January 29, 2018
.11 During review, Engineer will mark Drawings to indicate review status:
.1 "REVIEWED" - Make and distribute additional copies as required for
execution of the Work.
.2 "REVISE & RESUBMIT" - Make the necessary revisions and resubmit
revised Drawings for review. Show the Drawing number of the first such revised
Drawing and show the latest revision number applicable to the Drawing by adding
a suffix to the Drawing number as - "REV. 1", "REV. 2", etc.
.3 "NOT REVIEWED" - This notation indicates when the Engineer has not
reviewed the Drawing. It may also be used in combination with the notation to
revise and resubmit the Drawing where the Engineer lacks sufficient information
to complete the review and requires resubmission of the Drawing for review after
revision.
.4 Drawings will be marked "REVIEWED" together with the notation to
"REVISE & RESUBMIT" when the Engineer requires resubmission of a revised
Drawing showing corrections made as a result of the Engineer's notations on the
Shop Drawings. This procedure will not relieve the Contractor of responsibility
for errors or omissions in the Shop Drawings or of responsibility for meeting all
requirements of the Contract.
.12 Where Shop Drawings are submitted to the Engineer use only those Shop
Drawings on the Work that bear the "REVIEWED" notation.
.13 Do not revise Shop Drawings marked "REVIEWED" unless resubmitted to the
Engineer for further review.
.14 Determine which Shop Drawings have, in addition to those Drawings specifically
mentioned in the Contract, design elements requiring the seal of a Professional
Engineer registered in the Province or Territory where the Work is located, in
accordance with the applicable provincial or federal engineering acts or other
governing legislation. Seal such Drawings before submitting them for review. Submit
for review engineering calculations signed by the registered Professional Engineer
responsible for the shop Drawing design elements.
.15 Review by the Engineer is for the sole purpose of ascertaining conformance with
the general design concept. This review does not mean that the Engineer approves the
detail design inherent in the Shop Drawings, responsibility for which remains with the
Contractor, and such review does not relieve the Contractor of his responsibility for
errors or omissions in the Shop Drawings or of his responsibility for meeting all
requirements of the Contract Documents. The Contractor is responsible for
dimensions to be confirmed and correlated at the job-site, for information that pertains
solely to fabrication processes or to techniques of construction and installation and for
coordination of the Work of all sub-trades.
Foothills Regional Services Commission Section 01001
Foothills Landfill Expansion - Cell 6 GENERAL REQUIREMENTS
2018-01/2017-3650.020 Page 14 of 15
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\01001.doc: January 29, 2018
1.10 MATERIAL AND EQUIPMENT
.1 Product and Material Quality:
.1 Products, materials, equipment and articles (referred to as Products throughout
Specifications) incorporated in Work shall be new, not damaged or defective, and
conforming with Specifications for purpose intended. If requested, furnish evidence as
to type, source and quality of Products provided.
.2 Defective Products will be rejected regardless of previous inspections. Inspection
does not relieve responsibility, but is a precaution against oversight or error. Remove
and replace defective Products at own expense and be responsible for delays and
expenses caused by rejection.
.2 Storage, Handling and Protection:
.1 Handle and store Products in manner to prevent damage, adulteration,
deterioration and soiling and in accordance with manufacturer's instructions when
applicable.
.2 Store packaged or bundled Products in original and undamaged condition with
manufacturer's seals and labels intact.
.3 Store products subject to damage from weather in weatherproof enclosures.
.3 Manufacturer's Instructions:
.1 Unless otherwise indicated in Specifications, install or erect Products in
accordance with manufacturer's instructions. Do not rely on labels or enclosures
provided with Products. Obtain written instructions directly from manufacturers.
.2 Notify Engineer in writing of conflicts between Specifications and manufacturer's
instructions, so that Engineer may establish course of action.
.3 Improper installation of erection of Products, due to failure in complying with
these requirements, authorizes Engineer to require removal and reinstallation at no
increase in Contract Amount.
.4 Workmanship:
.1 Execute Work by workers experienced and skilled in respective duties for which
they are employed. Immediately notify Engineer if required Work is such as to make it
impractical to produce required results.
.2 Do not employ any unfit person or anyone unskilled in their required duties. The
Engineer reserves the right to require the dismissal from site of workers deemed
incompetent, careless, insubordinate or otherwise objectionable.
Foothills Regional Services Commission Section 01001
Foothills Landfill Expansion - Cell 6 GENERAL REQUIREMENTS
2018-01/2017-3650.020 Page 15 of 15
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\01001.doc: January 29, 2018
1.11 PROJECT CLOSEOUT
.1 Final Cleaning:
.1 When the Work is Substantially Performed, remove surplus products, tools,
construction machinery and equipment not required for performance of remaining
Work.
.2 Remove waste materials and debris from site at regularly scheduled times or
dispose of as directed by Engineer. Do not burn waste materials on site, unless
approved by Engineer.
.2 Documents:
.1 Collect reviewed submittals and assemble documents executed by Subcontractors,
suppliers, and manufacturers.
.2 Submit all submittal information prior to final Application for Payment.
.3 Inspection/Takeover Procedures:
.1 Prior to application for Certificate of Substantial Performance, carefully inspect
the Work and ensure it is complete, that major and minor construction deficiencies are
complete, defects are corrected, and the work site is clean and in condition for
operational use. Notify Engineer in writing, of satisfactory completion of the Work
and request an inspection.
.2 During Engineer inspection, a list of deficiencies and defects will be tabulated.
Correct same.
.3 When Engineer considers deficiencies and defects have been corrected and it
appears requirements of Contract have been performed, make application for
Certificate of Substantial Performance. Refer to General Conditions for specifics of
application.
END OF SECTION
Foothills Regional Services Commission Section 01270
Foothills Landfill Expansion - Cell 6 MEASUREMENT AND PAYMENT
2018-01/2017-3650.020 Page 1 of 12
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\01270.doc: January 29, 2018
1 General
1.1 PAYMENT
.1 Payments will be made on the basis of the unit prices bid in the Tender.
.2 The prices bid for various items of work, unless specifically noted otherwise, shall
include the supply of all labour, material, plant and equipment necessary to construct
the Work in accordance with the Specifications and Drawings; and all incidental work
for which separate prices are not specified in the Schedule of Quantities and Prices.
.3 The prices bid for supply and installation of materials shall be full compensation of
supplying, hauling, installing, cleaning, testing, and placing in service together with all
other work subsidiary and incidental thereto for which separate payment is not
provided elsewhere.
.4 The method of measurement of the quantities for payment and the basis for payment
will be in accordance with the following items of this Section. All measurement will
be performed by the Contractor supplied survey forces using generally accepted field
survey methods. Stationing interval for volume calculations shall not exceed 25 m.
.5 Where the Tender shows separate items for supply and installation, the unit prices or
lump sum prices bid for supplying, delivering, loading, unloading and all allowances
for handling, storage, breakage and waste shall be included in the bid price. Payment
will be made only for materials actually installed.
.6 Survey data and volume calculations shall be provided to the Engineer for verification
and review. For each individual pay item, data to be supplied in .csv format (point,
northing, easting, elevation, description) and in .dwg format with survey points (3D)
superimposed over cell base plan with named descriptors, point number and
elevations, all on individual unique layers. Coordinate system to match that specified
by Engineer (i.e., grid on the plan). Drawings submitted for square metre pay items to
include perimeter line indicating limits of survey for that item. Drawings submitted
for cubic metre pay items to include all surfaces used to calculate volumes on
individual, unique layers. A volume summary sheet is required. For final quantities, a
complete list of all quantities following the Schedule of Quantities and Prices must be
provided.
.7 All materials on site, whether existing structures, vegetation, topsoil, gravel, sand or
other excavated or piled materials, are the property of the Owner or the Owner of the
land on which the Work is located. Only those materials specifically noted in the
Specification or on the Drawings as belonging to the Contractor shall become the
Contractor’s property.
Foothills Regional Services Commission Section 01270
Foothills Landfill Expansion - Cell 6 MEASUREMENT AND PAYMENT
2018-01/2017-3650.020 Page 2 of 12
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\01270.doc: January 29, 2018
.8 When there are excess excavated materials or unsuitable materials of any kind that are
excavated but not used in the Work, such materials are not the property of the
Contractor unless authorized in writing by the Engineer or specified to be disposed of
by the Contractor.
.9 Refer to additional Sections as appropriate for general, product and execution
information.
2 Measurement and Payment Clauses
PART A - GENERAL REQUIREMENTS
2.1 MOBILIZATION AND DEMOBILIZATION
.1 Mobilization and demobilization shall include the Contractor’s costs of mobilization at
the beginning of the project; and the costs of demobilization at the end of the project.
.2 Included in mobilization are such items as bonding, insurance, permits, moving
personnel, materials and equipment to the site, site office trailer, setting up temporary
facilities and all preparation for performing the Work.
.3 Included in demobilization are removal of all personnel, materials and equipment, and
cleanup of the site of the Work.
.4 The lump sum price bid for this Work shall be relative to the costs involved, but shall
not exceed 10% of the Tender Price.
.5 Payment will be made as follows; as approved by the Engineer:
.1 50% of the lump sum price bid will be included in the first progress payment
certificate.
.2 50% of the lump sum price bid will be included in the final progress payment
certificate.
.3 The costs of other items specified under General Requirements shall be
considered as incidental to the Work and separate payment will not be made for any
other items of General Requirements.
2.2 LAYOUT AND RECORD SURVEY
.1 The layout and record survey includes all layout and construction surveys as required
to complete the work according to the Specifications and Drawings, data submittals to
the Engineer, quantity surveys, final as-built (record) surveys and all submittals as
specified in the Contract Documents.
Foothills Regional Services Commission Section 01270
Foothills Landfill Expansion - Cell 6 MEASUREMENT AND PAYMENT
2018-01/2017-3650.020 Page 3 of 12
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\01270.doc: January 29, 2018
.1 Measurement: N/A
.2 Payment: Lump sum bid for this item of work. Payment schedule shall be as
follows:
.1 30% of the lump sum bid amount upon confirmation of turnover of the
post-stripping survey data, documents and Drawings.
.2 20% of the lump sum bid amount upon confirmation of the compacted clay
liner (CCL) subgrade and embankment survey data, documents and Drawings.
.3 20% of the lump sum bid amount upon confirmation of turnover of the CCL
and embankment completions survey data, CCL thickness data, documents and
Drawings.
.4 30% upon confirmation of turnover of the final site as-built survey and all
data, submittals and Drawings in the format acceptable to the Engineer.
2.3 SAFETY
.1 Payment for safety includes the requirements by the Contractor to provide full-time
safety personnel on site as required by the Specifications, and all other safety related
requirements required by Foothills Regional Services Commission; includes all
reporting required.
.1 Measurement: N/A
.2 Payment: Lump sum bid for this item of work. Payment schedule shall be as
follows:
.1 30% of the lump sum bid amount after the first thirty (30) Calendar Days.
.2 30% of the lump sum bid amount after sixty (60) Calendar Days.
.3 40% upon confirmation of turnover of all submittals in the format acceptable
to the Engineer.
PART B - LANDFILL DEVELOPMENT
All unit prices bid for earthworks items under PART B - LANDFILL DEVELOPMENT shall
include all handling (double or otherwise) of the earthworks quantities and materials necessary to
construct the Works intended in the Contract Documents and Specifications. No separate
payment shall be made by the Owner in the event that additional earthworks handling is required
by the Contractor to execute the Work as specified and intended by the Contract.
2.4 STRIPPING HAULED TO STOCKPILES
.1 Topsoil and Subsoil Stripping: This work includes stripping topsoil and subsoil
material from the areas specified on the Drawings; loading, transporting and placement
in stockpile; separation of topsoil and subsoil stockpiles; stripping topsoil over subsoil
stockpile area; stripping topsoil and subsoil over common stockpile area; and loading,
transporting and stockpiling on the site as specified on the Drawings; and all incidental
Foothills Regional Services Commission Section 01270
Foothills Landfill Expansion - Cell 6 MEASUREMENT AND PAYMENT
2018-01/2017-3650.020 Page 4 of 12
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\01270.doc: January 29, 2018
work necessary to complete the function for which separate payment is not specified
elsewhere in the Schedule of Quantities and Prices.
.1 Measurement: Survey of pre-strip versus post-strip.
.2 Payment: Unit price bid per cubic metre.
2.5 COMMON EXCAVATION
.1 Common Excavation to Berm Embankment: This work includes the common
excavation, load, haul and placement of the common excavated material to the
designated embankment areas for the construction of all perimeter and intermediate
berm embankments, common excavation from stockpiles, roads, berms, ditches,
sub-drain and leachate collection trenches, and liner anchor trenches. Included in the
work of this item is the moisture conditioning, compaction and grading of the
embankment areas, roads, berms, trenches, ditches, and liner anchor trenches; and all
handling of the common excavated materials as may be required to execute the work;
includes coordination of Work with the Engineer’s Geotechnical Subconsultant; and
all incidental work for which separate prices are not specified in the Schedule of
Quantities and Prices.
.1 Measurement: Common excavation to berm embankment shall be paid based on
the post stripping survey versus top of clay liner survey and exterior landfill cell
finished subgrade survey. Other components of common excavation to stockpile and
clay liner construction paid elsewhere.
.2 Payment: Unit price bid per cubic metre.
.2 Common Excavation to Stockpiles: Work of this item includes the excavation, load,
haul and placement of the common excavated material that is in excess of the
embankment common excavation construction requirements, to stockpile. Also
included is the finished grading of the stockpile, drainage ditch construction and
clean-up and grading of stockpile areas; included is all handling of the common
materials as required to complete the work; and all incidental work for which separate
prices are not specified in the Schedule of Quantities and Prices.
.1 Measurement: Common excavation to stockpiles shall be paid based on the post
stripping survey versus top of clay liner survey and exterior landfill cell finished
subgrade survey.
.2 Payment: Unit price bid per cubic metre.
2.6 COMPACTED CLAY LINER
.1 Includes excavation to clay liner sub-grade elevation, scarification, compaction,
moisture conditioning, clay liner sub-grade preparation, all handling of clay liner
materials as required to execute the clay liner construction, clay liner material
placement, spreading, watering or drying as required, and compaction of clay material
to achieve the permeability and in-place moisture/density as specified, and to the lines
and levels as specified on the Drawings; includes coordination of Work with the
Foothills Regional Services Commission Section 01270
Foothills Landfill Expansion - Cell 6 MEASUREMENT AND PAYMENT
2018-01/2017-3650.020 Page 5 of 12
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\01270.doc: January 29, 2018
Engineer’s Geotechnical Subconsultant; and all incidental work for which separate
prices are not specified in the Schedule of Quantities and Prices.
.1 Measurement: Survey measurements of completed clay liner area.
.2 Payment: Unit price bid per square metre.
2.7 GEOSYNTHETIC CLAY LINER (GCL)
.1 Supply Geosynthetic Clay Liner: All materials costs, freight to site, taxes, insurance,
equipment, overhead and profit for supply only of geosynthetic clay liner materials.
Includes all material necessary to complete the full structure and QA requirements;
and all incidental work for which separate prices are not specified in the Schedule of
Quantities and Prices.
Note: Estimated quantities are 3D coverage area based on design lines and levels.
Additional material for all overlaps, jointing, anchor trenches, and wastage are to
be supplied and included in pricing.
.1 Measurement: As per request for quotation.
.2 Payment: Unit price bid per square metre. Payment as follows (based on
submission of required measurement data, all payments made available following
progress payment):
.1 10% of extension after receipt and acceptance of roll certification by
Engineer.
.2 90% of extension after complete delivery of all GCL materials.
.2 Install Geosynthetic Clay Liner: Work includes the installation of GCL as specified
and shown on the Drawings. Installation includes labour, and subsistence, and all
incidentals for which separate prices are not specified in the Schedule of Quantities
and Prices.
.1 Measurement: Completed area of GCL coverage based on design lines and levels.
.2 Payment: Unit price bid per square metre. Payment as follows (based on
submission of required measurement data, all payments made available following
progress payment):
.1 30% of unit price bid per square metre after complete mobilization of
geosynthetic installation crew and start of installation.
.2 50% of unit price bid per square metre installed and tested.
.3 20% of unit price bid per square metre on submission of complete QC
package.
Foothills Regional Services Commission Section 01270
Foothills Landfill Expansion - Cell 6 MEASUREMENT AND PAYMENT
2018-01/2017-3650.020 Page 6 of 12
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\01270.doc: January 29, 2018
2.8 60 MIL HDPE LINER - 2-SIDED TEXTURED
.1 Supply 60 mil HDPE Liner: All material costs, freight to site, taxes, insurance,equipment, overhead and profit for supply only of 60 mil HDPE materials. Includes allmaterial necessary to complete the full structure and QA requirements; and allincidental work for which separate prices are not specified in the Schedule ofQuantities and Prices.
Note: Estimated quantities are 3D coverage area based on design lines and levels.Additional material for all overlaps, jointing, anchor trenches, and wastage are tobe supplied and included in pricing.
.1 Measurement: As per request for quotation.
.2 Payment: Unit price bid per square metre. Payment as follows (based onsubmission of required measurement data, all payments made available followingprogress payment):
.1 10% of extension after receipt and acceptance of roll certification byEngineer.
.2 90% of extension after complete delivery of all 60 mil HDPE materials.
.2 Install 60 mil HDPE: Work includes the installation of all liner material as specifiedand shown on the Drawings. Installation includes placement of liner, tie-in to existingliner, field seaming, jointing and QA/QC requirements according to the ContractSpecifications including liner inspections, repairs and testing. Also included is anylabour, subsistence and all incidental work for which separate prices are not specifiedin the Schedule of Quantities and Prices.
.1 Measurement: Completed area of 60 mil HDPE liner based on design lines andlevels.
.2 Payment: Unit price bid per square metre. Payment as follows (based onsubmission of required measurement data, all payments made available followingprogress payment):
.1 30% of unit price bid per square metre after complete mobilization ofgeosynthetics installation crew and start of installation.
.2 50% of unit price bid per square metre installed and tested.
.3 20% of unit price bid per square metre on submission of complete QCpackage.
2.9 LEACHATE COLLECTION SYSTEM
.1 Perimeter and Interior (Type 1) Leachate Trench: Leachate trench includes the supplyand placement of drainage rock within the perimeter trench excavation; supply andinstallation of perforated leachate collection piping and fittings as shown on theDrawings; and all incidental work for which separate prices are not specified in theSchedule of Quantities and Prices.
.1 Measurement: Survey of the centerline length of pipe installed.
.2 Payment: Unit price bid per lineal metre.
Foothills Regional Services Commission Section 01270
Foothills Landfill Expansion - Cell 6 MEASUREMENT AND PAYMENT
2018-01/2017-3650.020 Page 7 of 12
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\01270.doc: January 29, 2018
.2 Install Owner Supplied Tire Shred: Work includes the haul and placement of tireshred drainage material over the landfill base as per the Contract drawings andspecifications, spreading to the required lines and levels, and all incidental Work forwhich separate payment is not specified in the Schedule of Quantities and Prices.
.1 Measurement: Design lines and levels.
.2 Payment: Unit price bid per cubic metre.
.3 Riser - Leachate: Work includes the supply and installation of a complete 300 mmdiameter DR11 PE riser pipe assembly as shown on the Drawings. All materials andmanpower required to completely install the riser shall be supplied including tools,equipment, clean-out riser, Fernco coupling adapter, IPS to PVC transition fitting, pipeblind flange and backup ring, and all necessary fittings. Reaming of all Interior PEconnections. All necessary testing shall be completed as per the manufacturer’ssupplied installation instructions. All incidental work for which separate prices are notspecified in the Schedule of Quantities and Prices shall be completed by the Contractorat no extra cost to the Owner.
.1 Measurement: Survey of each riser installed.
.2 Payment: Unit price per each location installed.
2.10 GROUNDWATER SUBDRAIN SYSTEM
.1 Subdrain Trench: Work included in subdrain system includes excavation, load, haul,and handling of materials; supply and placement of drainage gravel, and supply andinstallation of perforated PVC pipe and fittings as shown on the Drawings; and allincidental work for which separate prices are not specified in the Schedule ofQuantities and Prices.
.1 Measurement: Survey of the centerline length of pipe installed.
.2 Payment: Unit price bid per lineal metre.
.2 Riser - Subdrain: Work includes the excavation of all materials for the subdrain riser,supply and placement of all subdrain riser components, supply and installation of thePVC subdrain riser pipe; backfilling and compaction; and supply of all materials asshown on the Drawings; and all work for which separate prices are not specified in theSchedule of Quantities and Prices.
.1 Measurement: Survey of each riser installed.
.2 Payment: Unit price per each location installed.
Foothills Regional Services Commission Section 01270
Foothills Landfill Expansion - Cell 6 MEASUREMENT AND PAYMENT
2018-01/2017-3650.020 Page 8 of 12
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\01270.doc: January 29, 2018
2.11 2-SIDED GEOCOMPOSITE
.1 Supply 2-Sided Geocomposite: All material costs, freight to site, taxes, insurance,equipment, overhead and profit for supply only of 2-sided geocomposite materials.Includes all material necessary to complete the full structure and QA requirements;and all incidental work for which separate prices are not specified in the Schedule ofQuantities and Prices.
Note: Estimated quantities are 3D coverage area based on design lines and levels.Additional material for all overlaps, jointing, anchor trenches, and wastage are tobe supplied and included in pricing.
.1 Measurement: As per request for quotation.
.2 Payment: Unit price bid per square metre. Payment as follows (based onsubmission of required measurement data, all payments made available followingprogress payment):
.1 10% of extension after receipt and acceptance of roll certification byEngineer.
.2 90% of extension after complete delivery of all 2-sided geocompositematerials.
.2 Install 2-Sided Geocomposite: Work includes the installation of all geocomposite
material as specified and shown on the Drawings. Installation includes placement of
geocomposite, overlapping, jointing and QA/QC requirements according to the
Contract Specifications including inspections, repairs and testing. Also included is any
labour, subsistence and all incidental work for which separate prices are not specified
in the Schedule of Quantities and Prices.
.1 Measurement: Completed area of 2-sided geocomposite based on design lines
and levels.
.2 Payment: Unit price bid per square metre. Payment as follows (based on
submission of required measurement data, all payments made available following
progress payment):
.1 30% of unit price bid per square metre after complete mobilization of
geosynthetics installation crew and start of installation.
.2 50% of unit price bid per square metre installed and tested.
.3 20% of unit price bid per square metre on submission of complete QC
package.
2.12 LIGHT GEOTEXTILE
.1 Supply Light Geotextile: All materials costs, freight to site, taxes, insurance,
equipment, labour, subsistence, overhead and profit for supply only of light geotextile
material. Includes all material necessary to complete all overlaps, jointing, wastage
and QA requirements.
Foothills Regional Services Commission Section 01270
Foothills Landfill Expansion - Cell 6 MEASUREMENT AND PAYMENT
2018-01/2017-3650.020 Page 9 of 12
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\01270.doc: January 29, 2018
.1 Measurement: Completed area of light geotextile coverage based on design lines
and levels.
.2 Payment: Unit price bid per square metre. Payment as follows (based on
submission of required measurement data, all payments made available following
progress payment):
.1 10% of extension after receipt and acceptance of roll certification by
Engineer.
.2 90% of extension after complete delivery of all light geotextile materials.
.2 Install Light Geotextile: Work includes the installation of light non-woven geotextile
filter fabric as specified and shown on the Drawings. Includes all material necessary to
complete overlaps, jointing, wastage, anchorage, and QA/QC requirements; and all
incidental work for which separate prices are not specified in the Schedule of
Quantities and Prices.
.1 Measurement: Completed area of light geotextile coverage based on design lines
and levels.
.2 Payment: Unit price bid per square metre.
2.13 HEAVY GEOTEXTILE
.1 Supply Heavy Geotextile: All materials costs, freight to site, taxes, insurance,
equipment, labour, subsistence, overhead, and profit for supply of heavy geotextile
material only.
.1 Measurement: As per request for quotation.
.2 Payment: Unit price bid per square metre. Payment as follows (based on
submission of required measurement data, all payments made available following
progress payment):
.1 10% of extension after receipt and acceptance of roll certification by
Engineer.
.2 90% of extension after complete delivery of all heavy geotextile materials.
.2 Install Heavy Geotextile: Work includes the installation of the heavy non-woven
geotextile filter fabric as specified and shown on the Drawings. Includes all material
necessary to complete overlaps, jointing, wastage, anchorage, and QA/QC
requirements; and all incidental work for which separate prices are not specified in the
Schedule of Quantities and Prices.
.1 Measurement: Completed area of heavy geotextile based on design lines and
levels.
.2 Payment: Unit price bid per square metre.
Foothills Regional Services Commission Section 01270
Foothills Landfill Expansion - Cell 6 MEASUREMENT AND PAYMENT
2018-01/2017-3650.020 Page 10 of 12
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\01270.doc: January 29, 2018
2.14 SAND TUBES
.1 Supply Sand Tubes: All material costs, freight to site, taxes, insurance, equipment,overhead and profit for supply only of sand tube materials. Sand tubes to beconstructed with 12 mil RPE tubes and tied with wire ties. Includes all materialnecessary to complete the full structure; sand bags and sand paid elsewhere; and allincidental work for which separate prices are not specified in the Schedule ofQuantities and Prices.
Note: Estimated quantities for each sand tube based on design lines and levels.
.1 Measurement: As per design lines and levels of sand tube alignment divided byspacing of sand tubes.
.2 Payment: Per sand tube based on design lines and levels. Payment as follows(based on submission of required measurement data, all payments made availablefollowing progress payment):
.1 10% of extension after receipt and acceptance of roll certification byEngineer.
.2 90% of extension after complete delivery of all sand tube materials.
.2 Install Sand Tubes: Work includes the installation of all sand tubes as shown on theDrawings with a 6 m spacing. Work includes supply and installation of sand; sandbag; filling, tying and placing of the sand tubes; and QA/QC requirements according tothe Contract Specifications including inspections, and repairs. Also included is anylabour, subsistence and all incidental work for which separate prices are not specifiedin the Schedule of Quantities and Prices.
.1 Measurement: Survey of sand tube alignment divided by spacing of sand tubes.
.2 Payment: Unit price bid per sand tube. Payment as follows (based on submissionof required measurement data, all payments made available following progresspayment):
.1 30% of unit price bid per alignment per metre after complete mobilizationand start of installation.
.2 50% of unit price bid per alignment per metre installed.
.3 20% of unit price bid on submission of complete QC package.
2.15 BARRICADES AND MARKERS
.1 Supply Lock Blocks: All material costs, freight to site, taxes, insurance, equipment,overhead and profit for supply only of standard/full sized lock blocks. Includes allincidental work for which separate payment is not specified in the Schedule ofQuantities and Prices.
.1 Measurement: As per request for quotation.
.2 Payment: Unit price bid for each lock block supplied.
Foothills Regional Services Commission Section 01270
Foothills Landfill Expansion - Cell 6 MEASUREMENT AND PAYMENT
2018-01/2017-3650.020 Page 11 of 12
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\01270.doc: January 29, 2018
.2 Install Lock Blocks: Work includes the installation of lock blocks as specified and
shown on the Drawings. Also included is any labour, subsistence and all incidental
work for which separate prices are not specified in the Schedule of Quantities and
Prices.
.1 Measurement: Survey of center point of installed lock blocks.
.2 Payment: Unit price bid for each lock block installed.
PART C - LANDFILL INFRASTRUCTURE
2.16 TOPSOIL HAULED FROM STOCKPILE, PLACEMENT AND FINISHEDGRADING
.1 Work includes loading, hauling and placement of topsoil from stockpiles on all
disturbed areas to the stripping limits shown on Drawings excluding stockpiles, and
interior of landfill cell; spreading and grading of the topsoil to the specified depth,
seed bed preparation of the areas to be seeded; and all incidental work for which prices
are not specified in the Schedule of Quantities and Prices.
.1 Measurement: Survey of the area topsoiled.
.2 Payment: Unit price bid per square metre.
2.17 SEEDING OF DISTURBED AREAS, DITCHES AND STOCKPILES
.1 Includes supply of seed mix and seeding of all topsoiled areas and topsoil, subsoil, and
common stockpiles. All incidental work for which prices are not specified in the
Schedule of Quantities and Prices is also included in this item.
.1 Measurement: Survey of the seeded stockpiles and survey of the area topsoiled.
.2 Payment: Unit price bid per square metre.
PART D - PROVISIONAL ITEMS
The provisional items are items of work for which unit prices are requested from the Bidder’s but
the items of work may or may not be incorporated into the Work. The purpose of the provisional
items is to solicit unit prices for each provisional item of work using the representative estimated
quantities as a basis for establishing a representative unit rate for each item of work in the event
that such items of work may be incorporated into the work of the Contract. No payment shall be
made to the Contractor if any or all of the provisional items of work are not used. Conversely, no
claims shall be levied against the Contract for the deletion of the provisional items in whole or in
part.
Foothills Regional Services Commission Section 01270
Foothills Landfill Expansion - Cell 6 MEASUREMENT AND PAYMENT
2018-01/2017-3650.020 Page 12 of 12
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\01270.doc: January 29, 2018
2.18 PROVISIONAL GROUNDWATER SUBDRAIN
.1 Supply 2-Sided Geocomposite: All material costs, freight to site, taxes, insurance,
equipment, overhead and profit for supply only of 2-sided geocomposite materials.
Includes all material necessary to complete the full structure and QA requirements;
and all incidental work for which separate prices are not specified in the Schedule of
Quantities and Prices.
Note: Estimated quantities are 3D coverage area based on design lines and levels.
Additional material for all overlaps, jointing, anchor trenches, and wastage are to
be supplied and included in pricing.
.1 Measurement: Survey of area of provisional 2-sided geocomposite installed.
.2 Payment: Unit price per square metre
.2 Install 2-Sided Geocomposite: Work includes the installation of all geocomposite
material as specified and shown on the Drawings. Installation includes placement of
geocomposite, overlapping, jointing and QA/QC requirements according to the
Contract Specifications including inspections, repairs and testing. Also included is any
labour, subsistence and all incidental work for which separate prices are not specified
in the Schedule of Quantities and Prices.
.1 Measurement: Survey of area of provisional 2-sided geocomposite installed.
.2 Payment: Unit price per square metre.
2.19 ROCK EXCAVATION
.1 Solid Rock Excavation: This work includes the excavation, load, haul and disposal in
stockpile of any excavated material classified as solid rock by the Engineer, and
excavated to the lines and elevations determined by the Engineer; and all incidental
work for which separate payment is not specified elsewhere.
.1 Measurement: Survey of volume of solid rock in the stockpile.
.2 Payment: Unit price bid per cubic metre.
END OF SECTION
Foothills Regional Services Commission Section 01450
Foothills Landfill Expansion - Cell 6 QUALITY CONTROL
2018-01/2017-3650.020 Page 1 of 6
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\01450.doc: January 29, 2018
1 General
1.1 WORK INCLUDED
.1 The following work is included, but not limited to:
.1 Requirements for the completion and submission of all required testing,
measurements, observations, procedures, inspections, submittals and quality control
for the construction of the Work.
.2 The Quality Control program for the Work consists of the following documents.
.1 The requirements of this Section 01450.
.2 The Quality Control requirements as specified in other Sections of the
documents.
1.2 RELATED WORK - DIVISION 1 AND DIVISION 2
1.3 SUBMITTALS
.1 Submittals - refer to Section 01001 - General Requirements.
1.4 TESTS
.1 General:
.1 Testing shall be in accordance with applicable codes and regulations, and with the
standards of the American Society for Testing and Materials (ASTM), Canadian
Standards Association (CSA), and Geosynthetics Research Institute (GRI).
.2 Testing of materials, products and the Work shall only be conducted by agencies
named in the Contract documents and accepted by the Engineer and Owner. The
Owner reserves the right to test product, material and the Work by the Owner’s or
Engineer’s testing agency not named in the Contract Documents.
.2 Contractor:
.1 Copies of reports resulting from inspections and tests shall be submitted by the
Contractor to the Engineer.
.2 The Contractor shall promptly process and distribute all required copies of test
reports, test information and related instructions to all subcontractors and suppliers to
ensure that all necessary retesting and replacement of non-compliant Work can
proceed without delay.
.3 Inspections and tests required by codes or ordinances, or by an authority having
jurisdiction, shall be the responsibility of the Contractor, at the Contractor’s expense.
Foothills Regional Services Commission Section 01450
Foothills Landfill Expansion - Cell 6 QUALITY CONTROL
2018-01/2017-3650.020 Page 2 of 6
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\01450.doc: January 29, 2018
.4 When tests on product, material or completed portions of the Work, carried out by
the Contractor or approved testing agency, yield results not in compliance with the
requirements of the Contract Documents, the Contractor, in addition to carrying out
remedial Work or replacement of the product or material, shall provide for retesting of
the remedied Work and the replacement product and material at the Contractor’s
expense.
.5 Retesting by the Owner’s testing agency shall be at the Owner’s expense.
.6 In every case where the Contractor has submitted test results failing to comply
with the requirements of the Contract Documents, the Contractor shall submit, within
ten (10) days, results of a retest showing that the defective works are in compliance
with the Specifications of the Contract Documents.
.7 If the Contractor fails to perform remedial Work or replace unacceptable material
or product, the Owner shall employ whatever means necessary to make good the
non-compliant Work. All costs incurred by the Owner for the performance of the
remedial Work shall be deducted from payments to the Contractor.
1.5 QA/QC RESPONSIBILITIES
.1 Contractor:
.1 The Contractor is totally responsible for the quality of materials and products
provided and incorporated into the Work. The Contractor, at any time, may have their
own testing agency perform additional tests at the Contractor’s cost.
.2 The Contractor shall ensure conformity of materials to the design and
manufacturer’s specification. The Contractor shall be responsible for quality control
and shall perform inspections and tests as are necessary to ensure that the Work
conforms to the Specifications and Drawings.
.3 Minimum requirements regarding quality control are specified in various sections
of the Specifications; however, the Contractor shall perform as many inspections and
tests as are necessary to ensure that the Work conforms to the requirements and
Specifications of the Contract Documents.
.4 Product testing, mill tests and laboratory reports shall demonstrate that product
and material supplied by the Contractor meet the Specifications specified in various
Sections of the Contract Documents.
.5 Contractor to cooperate fully with, and provide reasonable facilities and
equipment for, the Owner’s testing agency to access all portions of the Work,
manufacturing and fabrication plants.
.2 Engineer:
.1 The Engineer’s testing agency and the Engineer may inspect and test material,
product and the Work for conformance with the requirements of the Contract
Documents; however, they do not undertake to check the quality of the Work on behalf
of the Contractor, nor to provide quality control.
Foothills Regional Services Commission Section 01450
Foothills Landfill Expansion - Cell 6 QUALITY CONTROL
2018-01/2017-3650.020 Page 3 of 6
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\01450.doc: January 29, 2018
.2 Inspections and tests by the Engineer’s testing agency and by the Engineer do not
relieve the Contractor of his responsibility to supply material and product and to
perform the Work in accordance with the requirements and Specifications of the
Contract Documents.
.3 The Engineer, at his discretion, may order or perform any additional inspections
and tests for purposes of his own or for purposes of the Owner.
.4 The Engineer shall direct the quality assurance inspection review.
.3 Quality Assurance Inspection:
.1 The Construction Quality Assurance (CQA) Inspector shall be under the direction
of the Engineer.
.2 The CQA Inspector shall be permitted to review the Work performed by the
Contractor at any time during the course of the Contract period.
.3 The Owner may retain and pay for the services of an independent testing agency
for testing, for quality assurance, or for the Owner’s purposes at the Owner’s expense.
.4 The CQA Inspector shall review quality control documentation against the Work
performed and materials supplied by the Contractor as required in the various Sections
of the Contract Documents.
2 Products
Not Used.
3 Execution
3.1 COMMON EXCAVATION AND GRADING MATERIALS
.1 Material Supply:
.1 The Contractor shall provide the Engineer with a list of sources of materials.
.2 The Owner’s testing agency shall provide the following:
.1 Provide sufficient samples, tests, and reports for the Engineer’s review, to
show that materials supplied meet the Specifications.
.2 Furnish moisture-density curves (Standard Proctor in accordance with
ASTM D698) for each classification of native soil material to be used or imported
material to be supplied.
.3 Preliminary approval of material does not constitute general acceptance.
Acceptance depends upon satisfactory field test results and performance in place.
.2 Material Placement:
.1 Field density tests shall be done in accordance with ASTM D2922 Standard Test
Method for Density of Soil and Soil-Aggregate in Place by Nuclear Methods (Shallow
Depth).
Foothills Regional Services Commission Section 01450
Foothills Landfill Expansion - Cell 6 QUALITY CONTROL
2018-01/2017-3650.020 Page 4 of 6
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\01450.doc: January 29, 2018
.2 Field moisture tests shall be in accordance with ASTM D3017 Standard Test
Method for Water Content of Soil and Rock in Place by Nuclear Methods (Shallow
Depth).
.3 The Engineer may order additional field density tests or other tests at his
discretion, if there is concern about the adequacy of the Contractor’s testing program,
procedures or results, at the Contractor’s cost.
.4 Field Tests: minimum field tests to be achieved for each structure shall be as
follows.
.1 Embankment fills (from excavated material) - one (1) of each 500 m3 of
compacted layers for field density tests.
.2 Road sub-grade preparation - one (1) for every 500 m3 of compacted layer for
field density tests.
.3 Landfill sub-grade preparation - one (1) for every 2500 m2 of landfill
sub-grade for field density tests.
.4 Embankment fills and sub-grade preparation - one (1) per each day of
construction for field moisture tests.
.5 Anchor trench fill - one (1) per 200 m of anchor trench per lift for field
density tests.
3.2 CLAY LINER MATERIALS
.1 Observation and testing of the clay liner materials shall be in accordance with the
following test methods and minimum frequencies identified in Table 1.
.1 Table 1 - Observations and Tests of Liner Material at the Borrow Source
Test ASTM Test Method Specific Minimums
Water Content D2216One (1) test per 4000 m3 of liner materials, or with each
change in material types [minimum of four (4)]
Atterberg Limits D4318One (1) test per 4000 m3 or with each change in material
types [minimum of four (4)]
Particle Size Distribution D422One (1) test per 4000 m3 or with each change in material
types [minimum of four (4)]
Moisture Density D698 or D1557One (1) test per 4000 m3 or with each change in material
types [minimum of four (4)]
Remoulded Permeability D5084One (1) test per 10,000 m3 or with each change in
material types [minimum of two (2)]
Changes in Borrow Materials Observation Continuous
Foothills Regional Services Commission Section 01450
Foothills Landfill Expansion - Cell 6 QUALITY CONTROL
2018-01/2017-3650.020 Page 5 of 6
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\01450.doc: January 29, 2018
.2 Observation and testing shall be conducted during the construction of a compacted
clay liner according to the test methods and minimum frequencies provided in Table 2.
The results of observations and testing shall be documented and maintained in the
landfill construction record.
.1 Table 2 - Observations and Testing Frequency During Construction
Test ASTM Test Method Specified Minimums
Construction Procedures Observation Continuous
Number of Passes ofCompaction Equipment
Observation Continuous
Pulverization of Clods Observation Continuous
Moisture/Density WaterContent (nuclear)
D3017 13/ha/lift
Density (nuclear) D2922 13/ha/lift
Water Content (oven) D2216 One (1) per each day of construction
Hydraulic ConductivityTests of UndisturbedSamples or EquivalentInsitu Tests
ASTM D5084 or othertest as determined
acceptableOne (1) per 10,000 m3 [minimum of four (4)]
Liner Thickness Survey Controls 20 m x 20 m survey grid
Liner Grade andUniformity
Survey Controls andObservations
20 m x 20 m survey grid
3.3 DRAINAGE GRAVEL MEDIA
.1 Testing shall conform to the following table:
.1 Table 1 - Observations and Testing Frequency of Material at the Source of Supply
Test ASTM Test Method Test Frequency
Grain Size D422 One (1) Test
Hydraulic Conductivity D2434 One (1) Test
.2 Table 2 - Observations and Testing Frequency During Construction
Test ASTM Test Method Test Frequency
Grain Size Source Confirmation Continuous
Material Continuity Observation Continuous
Construction Procedures Observation Continuous
Foothills Regional Services Commission Section 01450
Foothills Landfill Expansion - Cell 6 QUALITY CONTROL
2018-01/2017-3650.020 Page 6 of 6
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\01450.doc: January 29, 2018
.3 Table 3 - Observations and Testing Frequency After Placement
Test ASTM Test Method Test Frequency
Thickness Survey Controls 15 m x 15 m grid
Grade and Uniformity Observation Continuous
.2 The drainage gravel shall be capable of obtaining a minimum hydraulic conductivity of
1 x 10-2 m/s based on ASTM D2434 test method.
END OF SECTION
Foothills Regional Services Commission Section 02073
Foothills Landfill Expansion - Cell 6 GEOMEMBRANES
2018-01/2017-3650.020 Page 1 of 12
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\02073.doc: January 29, 2018
1 General
1.1 WORK INCLUDED
.1 The following Work is included, but not limited to:
.1 Supply and installation of HDPE geomembrane.
1.2 RELATED WORK
.1 Common Excavating and Grading - refer to Section 02210.
.2 Clay Liner - refer to Section 02215.
.3 Leachate Collection System - refer to Section 02411.
.4 Geosynthetic Clay Liner - refer to Section 02594.
1.3 QUALITY CONTROL
.1 Quality Control - refer to Section 01450 for general information.
.2 The materials supplied shall be in accordance with the Specifications. Any proposed
variance or deviation shall be requested in writing prior to the commencement of
installation.
.3 The Contractor shall submit certificates of compliance with the requirements of
standards and testing methods; and affidavits that materials meet the requirements of
the Specifications in every respect.
.4 Product Quality Control - refer to Clause 2 of this section.
.5 Installation Quality Control - refer to Clause 3 of this section.
.6 Identification:
.1 Rolls must be tagged to identify the thickness of the material, the length and width
of the roll, batch and roll number and the name of the manufacturer.
.7 The manufacturer shall have at least two (2) years continuous experience in the
manufacture of HDPE geomembranes.
1.4 SUBMITTALS
.1 Submittals - refer to Section 01001 - General Requirements.
Foothills Regional Services Commission Section 02073
Foothills Landfill Expansion - Cell 6 GEOMEMBRANES
2018-01/2017-3650.020 Page 2 of 12
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\02073.doc: January 29, 2018
1.5 GEOMEMBRANE INSTALLATION WARRANTY PERIOD
.1 The Contractor shall warranty against geomembrane installation defects for a period of
two (2) years from date of issue of Contract Completion Certificate. The
geomembrane installation warranty shall originate with and be provided by the
Geosynthetics Installation Contractor. Submit warranty to Engineer on date specified.
1.6 PRODUCT DELIVERY, STORAGE AND HANDLING
.1 Geotextile and geomembranes shall be handled and stored in accordance with the
manufacturer’s recommendations.
.2 Store materials so that they do not come in contact with substances that may affect
their physical or chemical properties.
.3 The integrity and legibility of the product labels shall be preserved during storage,
delivery and handling.
1.7 MEASUREMENT AND PAYMENT
.1 Measurement and Payment - refer to Section 01270.
1.8 DISPOSAL
.1 Remove and dispose of all waste material offsite at Contractor’s expense, unless onsite
disposal is provided by the Owner.
2 Products
2.1 60 MIL GEOMEMBRANE LINER - 2-SIDED TEXTURED
.1 The primary geomembrane shall be premium grade high density polyethylene (HDPE)
geomembrane with a nominal thickness of 1.5 mm (60 mil). Geomembrane shall be
2-sided textured.
.2 The 60 mil HDPE geomembrane liner material shall adhere to the GRI GM13 (Current
Version) testing standards and requirements including the following ASTM tests:
Foothills Regional Services Commission Section 02073
Foothills Landfill Expansion - Cell 6 GEOMEMBRANES
2018-01/2017-3650.020 Page 3 of 12
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\02073.doc: January 29, 2018
Property ASTM Test Methods Certificate Required
Thickness D5994 Manufacturer Test
Density D1505/D792 Manufacturer Test
Tensile Properties D6693 Type IV Manufacturer Test
Tear Resistance D1004 Manufacturer Test
Puncture Resistance D4833 Manufacturer Test
Stress Crack Resistance D5397“Letter of Certification” or
Manufacturer Test
Accelerated Heat Aging D5721 Manufacturer Test
Carbon Black Content D4218 or D1603 Manufacturer Test
Carbon Black Dispersion D5596 Manufacturer Test
Melt Flow Index D1238 Manufacturer Test
Oxidative Induction Time D5885 or D3895“Letter of Certification” or
Manufacturer Test
Oven Aging D5721 or D5885 or D3895“Letter of Certification” or
Manufacturer Test
UV ResistanceD7238 or D5885 or D3895
“Letter of Certification” or
Manufacturer Test
*ASTM tests that have been revised or superseded by ASTM shall be permissible.
.3 The Geosynthetic Installation Contractor shall retain a “Letter of Certification” from
the 60 mil HDPE geomembrane manufacturer certifying the specified additional
ASTM testing properties above.
.4 The primary geomembrane shall be suitable for the intended purpose at the site
ambient temperature range.
.5 Width - 6.7 m minimum.
.6 60 mil HDPE geomembrane shall be manufactured from the same resin source.
Provide resin lot numbers issued by the manufacturer to the Engineer seven (7) days
prior to deployment.
.7 60 mil HDPE geomembranes shall be used as the primary (upper) component of the
landfill composite liner system.
Foothills Regional Services Commission Section 02073
Foothills Landfill Expansion - Cell 6 GEOMEMBRANES
2018-01/2017-3650.020 Page 4 of 12
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\02073.doc: January 29, 2018
2.2 EXTRUDATE ROD OR BEAD
.1 Extrudate material shall be made from same type of resin as the HDPE liner.
.2 Extrudate material shall be free of contamination by moisture or foreign matter.
3 Execution
3.1 INSTALLATION CONTRACTOR
.1 The Geosynthetics Installation Contractor shall be an approved contractor trained and
licensed to install the manufacturer’s membrane.
.2 Installation shall be performed under the constant supervision of an experienced
geomembrane Supervisor, who shall direct the laying and seaming of the liner.
Seaming shall be done by an experienced seamer, experienced in seaming HDPE using
the type of equipment being used on this project.
.3 The Geosynthetics Installation Contractor shall provide a written report on the
completed installation which shall certify that the liner is installed in accordance with
the requirements of the Specifications, is ready for operation, and that the warranty is
in effect as of the date of the Final Completion Certificate.
.4 Provide information regarding the Geosynthetics Installation Contractor Field
Installation Quality Control Program and qualifications of field personnel.
3.2 INSTALLATION QUALITY CONTROL
.1 The following elements are required of the installation quality control plan:
.1 Visual Inspection:
.1 Sub-grade surface prior to installation.
.2 Geomembrane damage in shipping.
.3 Geomembrane defects, texture.
.4 Seams, anchors, penetrations.
.5 Geomembrane during deployment for imperfections, and mark faulty or
suspect areas.
.2 Qualifying Weld Tests are required:
.1 At the start of each seaming period.
.2 If welding has ceased for four (4) hours or more.
.3 If a new operator or new machine starts welding.
.4 If there is a significant change in weather condition.
Foothills Regional Services Commission Section 02073
Foothills Landfill Expansion - Cell 6 GEOMEMBRANES
2018-01/2017-3650.020 Page 5 of 12
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\02073.doc: January 29, 2018
.3 Qualifying Weld Tests:
.1 Minimum length is 1 m for extrusion welding.
.2 Minimum length is 2 m for hot shoe welding.
.3 Cut 25 mm specimens from each end of the test seam.
.4 Test for shear - ASTM D6392 (minimum of one (1) test).
.5 Test for peel - ASTM D6392 (minimum of four (4) tests).
.4 Production Weld Tests (Destructive Seam Testing):
.1 One (1) destructive test sample properly identified per 500 m of production
weld.
.2 Each destructive test sample shall be cut into ten (10) coupons 25 mm wide.
.3 Test five (5) coupons in the shear mode - Seam Strength ASTM D6392.
.4 Test five (5) coupons in the peel mode - Seam Strength ASTM D6392.
.5 All field welds shall be tested using the applicable pressure or vacuum test.
.6 All extrusion welds shall be vacuum box tested.
3.3 PREPARATION
.1 The Contractor shall be responsible for preparing and maintaining the sub-grade in a
condition suitable for installation of the HDPE liner. The Geosynthetics Installation
Contractor shall prepare a Certificate of Sub-grade Acceptance signed by the
Contractor and Geosynthetics Installation Contractor certifying that sub-grade is
acceptable for geomembrane installation.
.2 Inspect the underlying layer daily before placing HDPE liner.
.3 The underlying layer shall be clean and free from debris, snow, and soil, smooth and
free of cuts, erosion rills, or protrusions.
.4 Installer shall verify weather conditions are suitable for HDPE liner placement each
day of installation prior to deployment.
.5 Ensure adequate sand bags are prepared prior to initial liner deployment.
3.4 METHOD OF PLACEMENT - GEOMEMBRANE
.1 The HDPE liner shall be placed in intimate contact with the compacted clay liner or
geosynthetic clay liner where applicable.
.2 No equipment or tools shall damage the HDPE liner or underlying surfaces by
handling, trafficking, or other means.
Foothills Regional Services Commission Section 02073
Foothills Landfill Expansion - Cell 6 GEOMEMBRANES
2018-01/2017-3650.020 Page 6 of 12
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\02073.doc: January 29, 2018
.3 Place ballast (sand bags) on HDPE liner which will not damage HDPE liner to prevent
uplift.
.4 No personnel working on the HDPE liner shall wear damaging shoes, or engage in
other activities that could damage the geomembrane. Smoking will not be permitted on
the geomembrane.
.5 The method used to unroll the panels shall not cause any damage to the HDPE liner
and shall not damage the supporting soil and/or underlying geosynthetics.
.6 The Geosynthetics Installation Contractor shall submit a panel layout proposal, to the
Engineer for review, prior to the geomembrane placement.
.7 The method used to place the panels shall minimize wrinkles (especially differential
wrinkles between adjacent panels).
.8 Mark and document all defects for repairs. Defects are defined as any abnormalities
that may affect the physical properties of the HDPE liner material.
.9 The Geosynthetics Installation Contractor shall use appropriate mechanical equipment
when deploying the geomembrane panels in order to mitigate the impact and defects
on the installed portions of the geomembrane liner and sub-grade.
.10 If, in the opinion of the Engineer, the mechanical equipment is causing a detrimental
impact to the liner, the Geosynthetics Installation Contractor shall deploy other means
or equipment to place the liner.
3.5 MATERIAL DEPLOYMENT
.1 Incorporation of slack into the liner installation shall be placed differentially with
respect to the base area and the slope areas.
.2 The occurrence of bridging shall be corrected and repaired in order to meet slack
requirements.
.3 If bridging occurs at any time during the two (2) year Geomembrane Installation
Warranty Period, the Geosynthetics Installation Contractor shall make good any such
defects at the Geosynthetics Installation Contractor’s expense.
.4 Deploy HDPE liner completely down the side and across the bottom of the anchor
trench ensuring that there are no sharp projections along the edge of the trench.
.5 When side-slope material is developed for welding on horizontal surfaces, care must
be taken when it is moved to the side slope so that the underside is not excessively
scratched or gouged and that loose flaps adjacent to seams are not penetrated by dirt,
sand or gravel.
Foothills Regional Services Commission Section 02073
Foothills Landfill Expansion - Cell 6 GEOMEMBRANES
2018-01/2017-3650.020 Page 7 of 12
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\02073.doc: January 29, 2018
.6 HDPE liner deployment shall proceed between ambient temperatures of 0°C to 40°C.
Placement can proceed below 0°C only after it has been verified that the material can
be seamed according to the specification and is approved by the Engineer.
Geomembrane seaming shall not be done during any precipitation, in the presence of
excessive moisture (e.g., fog, rain, dew, snow) or in the presence of excessive winds.
.7 At the beginning of each day of liner deployment, Geosynthetics Installation
Contractor shall verify geomembrane has not pulled away from the sub-grade or
anchor trench.
3.6 FIELD SEAMS - GEOMEMBRANE
.1 Orient seams parallel to the line of maximum slope if possible. Minimize the number
of seams, especially those running across the slope.
.2 Base T-Seams shall be at least 2 m from the toe of slope. Repair wrinkles or fish
mouths in seams by relieving them and cap-stripping. Patch if required.
.3 Production seams shall be completed with double track (split) wedge welding
equipment. Extrusion welds may be used for patches, repairs, overlays, and
connections. Solvents shall not be used without prior approval of the Engineer.
.4 Finished panel overlap shall be a minimum of 100 mm for wedge fusion joints and
75 mm for extrusion welding.
.5 If grinding of the surfaces to be seamed is required, the grinding marks shall be
oriented perpendicular to the seam direction and no marks shall extend beyond the
extrudate after placement.
.6 Clean overlapped areas to be seamed and maintain state of cleanliness until the weld is
complete. Inspect panel for flaws and repair as required.
.7 Lap overlap sheets smoothly on each other, avoiding wrinkles, especially differential
wrinkles. Hold sheets in place with sand bags.
.8 The field seams shall meet the Specifications of GRI GM19 “Seam Strength and
Related Properties of Thermally Bonded Polyolefin Geomembranes”.
3.7 FIELD SEAM TESTING - NON-DESTRUCTIVE - GEOMEMBRANE
.1 The Geosynthetics Installation Contractor shall non-destructively test all field seams
over their full length. All test equipment, including but not limited to the following
shall be furnished by the Geosynthetics Installation Contractor.
.2 Vacuum Box Testing - Extrusion Seams:
.1 Test Equipment:
Foothills Regional Services Commission Section 02073
Foothills Landfill Expansion - Cell 6 GEOMEMBRANES
2018-01/2017-3650.020 Page 8 of 12
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\02073.doc: January 29, 2018
.1 A vacuum box assembly consisting of a rigid housing, a transparent viewing
window, a soft rubber gasket attached to the bottom, port hole or valve assembly,
and a vacuum gauge.
.2 A steel vacuum tank and pump assembly equipped with a pressure controller
and pump connections.
.3 A rubber pressure/vacuum hose with fittings and connections.
.4 A 20 L spray bottle.
.5 A soapy solution.
.2 The following procedures shall be followed by the Geosynthetics Installation
Contractor:
.1 Excess sheet overlap shall be trimmed away.
.2 Clean the window, gasket surfaces and check for leaks.
.3 Wet a strip of geomembrane the same size as the vacuum box, with a soapy
solution.
.4 Place the box over the wetted area and compress.
.5 Close the bleed valve and open the vacuum valve.
.6 Ensure that a leak tight seal is created.
.7 Energize the vacuum pump and reduce the tank pressure to approximately
10 kPa.
.8 For a period of approximately ten (10) seconds, examine the geomembrane
through the viewing window for the presence of soap bubbles.
.9 If no bubbles appear after ten (10) seconds, close the vacuum valve and open
the bleed valve, move the box over the next adjoining area with a minimum
75 mm overlap and repeat the process.
.10 All areas where soap bubbles appear shall be marked and repaired and then
re-tested.
.3 The following procedures shall apply to locations where seams cannot be
non-destructively tested:
.1 If the seam is accessible to testing equipment prior to final installation, the
seam shall be non-destructively tested prior to final installation.
.2 If the seam cannot be tested prior to final installation, provide “spark” testing
in the presence of the CQA Inspector or Engineer where appropriate. Review
seaming operations in the presence of the CQA Inspector or Engineer to ensure
uniformity and completeness.
Foothills Regional Services Commission Section 02073
Foothills Landfill Expansion - Cell 6 GEOMEMBRANES
2018-01/2017-3650.020 Page 9 of 12
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\02073.doc: January 29, 2018
.3 Air Pressure Testing (for double wedge seam only)
.1 The following procedures are applicable to those processes which produce a
double wedge seam with an enclosed space:
.1 Equipment:
.1 An air pump equipped with pressure gauge capable of generating and
sustaining a pressure between 240 kPa (35 psi) and 310 kPa (45 psi) for
60 mil liner and mounted on a cushion to protect the geomembrane.
.2 A manometer equipped with a sharp hollow needle, or other approved
pressure feed device.
.2 Procedure:
.1 Seal both ends of the seam to be tested.
.2 Insert needle or other approved pressure feed device into the tunnel
created by the double wedge fusion weld.
.3 For 60 mil liner testing, energize the air pump to a pressure between
240 kPa and 310 kPa (35 to 45 psi), close valve and sustain pressure for a
minimum of five (5) minutes.
.4 After five (5) minutes, if loss of pressure exceeds ten percent (10%) of
the pressure at the start of the test, or pressure does not stabilize, locate faulty
area, repair and re-test.
.5 Remove needle or other approved pressure feed device, release pressure
at opposite end of the seam and seal.
3.8 FIELD SEAMING TESTING - DESTRUCTIVE - GEOMEMBRANE
.1 The Geosynthetics Installation Contractor shall provide a minimum of one (1)
destructive test sample per 500 m of seam length from a location specified by the
Engineer. The Geosynthetics Installation Contractor shall not be informed in advance
of the sample location.
.2 Sampling Procedure:
.1 In order to obtain test results prior to completion of liner installation, samples
shall be cut by the Geosynthetics Installation Contractor as the seaming progresses.
Sampling times shall be taken within twenty-four (24) hours and tested within
forty-eight (48) hours of the completion of production welding. Location of samples
shall be determined by the Engineer. The Engineer must witness the obtainment of all
field test samples with their location, roll, and seam number. The Geosynthetics
Installation Contractor shall also record in written form the date, time, location, roll,
seam number, ambient temperatures, and pass or fail description. A copy of the
information must be attached to each sample portion as well as detailed on each test
data log. All holes in the geomembrane resulting from obtaining the seam samples
shall be immediately repaired. All patches shall be vacuum tested.
Foothills Regional Services Commission Section 02073
Foothills Landfill Expansion - Cell 6 GEOMEMBRANES
2018-01/2017-3650.020 Page 10 of 12
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\02073.doc: January 29, 2018
.3 Size and Disposition of Samples:
.1 The samples shall be 300 mm wide by 600 mm long with the seam centered
lengthwise. The sample shall be cut into two (2) equal length pieces, half to be given
to the Engineer and the other half to be given to the Geosynthetics Installation
Contractor.
.2 Each equal length piece shall be labelled with the date, time, location, roll, seam
number, ambient temperatures, and pass or fail description.
.4 Test Method:
.1 Seam coupons are 25.4 mm wide, grip separation rate is 50.8 mm/min.
.2 Both shear seam strength and peel tests shall be run on five (5) replicate coupons.
A break through the weld or at the weld sheet interface shall be considered a Non-FTB
(failure) in both seams strength (shear) and peel strength tests.
.3 Test Shear Seam Strength to ASTM D6392.
.4 Test Peel Strength to ASTM D6392.
.5 Record ambient temperature and sample surface temperature at testing location.
.5 Procedures for Destructive Test Failure:
.1 One (1) or more of the following procedures shall apply whenever a sample fails
the field destructive test. The Geosynthetics Installation Contractor shall reconstruct
the seam between the failed location and any passed test location.
.1 The Geosynthetics Installation Contractor can retrace the welding path to an
intermediate location (at a minimum of 3 m from the location of the failed test), at
the Engineer’s discretion, and take a small sample for an additional field test. If
this test passes, then the seam shall be reconstructed between that location and the
original failed location. If the test fails, then the process is repeated.
.2 Over the length of seam failure, the Geosynthetics Installation Contractor
shall either cut out the old seam, reposition the panel and reseam or add a cap
strip, as required by the Engineer.
.3 After reseaming, additional destructive field test(s) shall be taken within the
reseamed area. The reseamed sample shall be found acceptable if test results are
approved by the Engineer. If test results are not acceptable, this process shall be
repeated until the reseamed length is judged satisfactory by the Engineer. The
Geosynthetics Installation Contractor shall be responsible for all costs of action
resulting from test failure.
Foothills Regional Services Commission Section 02073
Foothills Landfill Expansion - Cell 6 GEOMEMBRANES
2018-01/2017-3650.020 Page 11 of 12
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\02073.doc: January 29, 2018
.6 Submission of Samples:
.1 All destructive seam samples shall be turned over to the Engineer at the
completion of geomembrane liner installation.
.2 Delivery of samples shall be well organized and to the satisfaction of the
Engineer.
3.9 DEFECTS AND REPAIRS - GEOMEMBRANE
.1 All seams and non-seam area of the geomembrane shall be inspected by the
Geosynthetics Installation Contractor and the Engineer for defects, holes, blisters,
undispersed raw materials, and any sign of contamination by foreign matter. The
geomembrane surface shall be brushed, blown, or washed by the Geosynthetics
Installation Contractor if the amount of dust or mud inhibits inspection. This
inspection should be done immediately after placement of the liner panel and again at
the completion of construction as a minimum.
.2 Evaluation:
.1 Each suspect location in seam and non-seam areas shall be non-destructively
tested as appropriate in the presence of the Engineer. Each location that fails the
non-destructive testing shall be marked, and repaired accordingly.
.3 Repair Procedures:
.1 Defective seams shall be restarted/reseamed as described in these Specifications.
.2 Small holes shall be repaired by extrusion cap welding. If the hole is larger than
6 mm, it shall be patched.
.3 If grinding of the surfaces is required, the grinding marks shall be oriented
perpendicular to the seam direction and no marks shall extend beyond the extrudate
after placement.
.4 Tears shall be repaired by patching. Where the tear is on a slope or an area of
stress and has a sharp end it must be rounded prior to patching.
.5 Blisters, large holes, undispersed raw materials, and contamination by foreign
matter shall be repaired by patches.
.6 Surfaces of HDPE which are to be patched shall be abraded and cleaned no more
than fifteen (15) minutes prior to the repair. No more than 10% of the thickness shall
be removed.
.4 Patches shall be round or oval in shape, made of the same geomembrane, and extend a
minimum of 150 mm beyond the edge of defects. All patches shall be of the same
compound and thickness as the geomembrane specified. All patches shall have their
top (or outside) edge beveled with an angle grinder either prior to or after patch is
placed on the geomembrane. Patches shall be applied using approved methods only.
Foothills Regional Services Commission Section 02073
Foothills Landfill Expansion - Cell 6 GEOMEMBRANES
2018-01/2017-3650.020 Page 12 of 12
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\02073.doc: January 29, 2018
.5 Restart/Reseaming Procedures:
.1 The extrusion welding process shall restart by grinding the existing seam and
rewelding a new seam. Welding shall commence where the grinding started and must
overlap the previous seam by at least 50 mm. Reseaming over an existing seam
without regrinding shall not be permitted.
.6 Verification of Repairs:
.1 Each repair shall be non-destructively tested, except when the Engineer requires a
destructive seam sample obtained from a repaired seam. Repairs that pass the
non-destructive test shall be taken as an indication of an adequate repair. Failed tests
indicate that the repair shall be repeated and re-tested until passing test results are
achieved.
.7 Recording of Results:
.1 Daily documentation of all non-destructive and destructive testing shall be
provided to the Engineer by the Geosynthetics Installation Contractor. This
documentation shall identify all seams that initially failed the test and include evidence
that these seams were repaired and successfully re-tested.
END OF SECTION
Foothills Regional Services Commission Section 02113
Foothills Landfill Expansion - Cell 6 STRIPPING
2018-01/2017-3650.020 Page 1 of 3
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\02113.doc: January 29, 2018
1 General
1.1 WORK INCLUDED
.1 The following work is included, but not limited to:
.1 Stripping and hauling to stockpile.
.2 Stripping and stockpiling for re-use.
.2 Stripping shall be limited to the area shown on the Drawings including: the landfill
cell footprint, roads, ditches and specified stockpile areas.
.3 The Engineer may waive stripping of wetland areas, at his discretion.
1.2 RELATED WORK
.1 Common Excavating and Grading - refer to Section 02210.
.2 Topsoil and Finish Grading - refer to Section 02484.
1.3 PERMITS AND REGULATIONS
.1 Abide by provincial and municipal regulations with regard to diversions or alterations
to drainage patterns and the preservation of reclamation topsoil and subsoil resources.
.2 Burning permit.
1.4 QUALITY CONTROL
.1 Quality Control - refer to Section 01450.
1.5 SUBMITTALS
.1 Submittals - refer to Section 01001 - General Requirements.
2 Products
Not Used.
3 Execution
3.1 NOTIFICATION
.1 The Engineer and the Contractor shall inspect the area to be stripped to establish
specific requirements and to review procedures.
Foothills Regional Services Commission Section 02113
Foothills Landfill Expansion - Cell 6 STRIPPING
2018-01/2017-3650.020 Page 2 of 3
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\02113.doc: January 29, 2018
3.2 STRIPPING
.1 Strip the area of the Work to the lines and/or coordinates indicated on the Drawings.
.2 Do not strip when the stripping area is wet or when there is a risk of cross
contamination between the topsoil and the subsoil.
.3 Strip the topsoil separate from the subsoil. Ensure that a minimum of subsoil material
is incorporated into the topsoil material.
.4 Commence the post stripping survey as soon as an adequately sized stripped area
becomes available.
.5 Maintain positive drainage on the worksite at all times during the stripping operation.
.6 Topsoil shall be defined as surface organic material suitable for seed bed preparation
and seeding.
.7 Subsoil material shall be defined as the non-organic layer between the topsoil and the
sub-grade (clay) material. Engineer shall assist with subsoil determination by
observation method.
.8 Unsuitable material shall be defined by the Engineer and shall generally consist of
material that is neither topsoil nor subsoil and is deemed to be unsuitable for
replacement as seed bed or cover material.
3.3 STOCKPILES AND STOCKPILE AREAS
.1 Prior to commencement of the stripping operation, coordinate with the Engineer those
areas of the stockpile area that shall receive topsoil, sub-soil and unsuitable material.
.2 The area to receive stripped topsoil does not need to be stripped of topsoil.
.3 The area to receive stripped subsoil or unsuitable material shall be stripped of topsoil.
Haul material to the topsoil stockpile.
.4 The area to receive common or unsuitable material shall be stripped of topsoil, subsoil,
and unsuitable material. Haul material to their respective stockpiles.
.5 Maintain a minimum 5 m separation between the toes of slope of the topsoil, subsoil
and common materials stockpiles.
.6 Stockpile the stripped materials in a manner and under conditions that prevent the
cross-contamination of the materials in the stockpiles.
.7 Construct the stockpiles with smooth and even sideslopes, free of excessive
depressions, ridges or piles. Stockpile sideslopes shall be graded at 2H:1V finished
slopes. Stockpile ramps shall be graded between 4H:1V and 5H:1V slopes.
Foothills Regional Services Commission Section 02113
Foothills Landfill Expansion - Cell 6 STRIPPING
2018-01/2017-3650.020 Page 3 of 3
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\02113.doc: January 29, 2018
.8 Upon completion of the stockpiles, blade the tops and sideslopes of the stockpiles to
ensure positive drainage off the stockpiles and for pre-survey preparation.
.9 Provide and maintain for positive drainage from stockpile area and from around the
toes of the individual stockpiles.
.10 After completion of the stockpile(s) survey, do not place additional materials on the
stockpiles without the notification and approval of the Engineer.
END OF SECTION
Foothills Regional Services Commission Section 02210
Foothills Landfill Expansion - Cell 6 COMMON EXCAVATING AND GRADING
2018-01/2017-3650.020 Page 1 of 7
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\02210.doc: January 29, 2018
1 General
1.1 WORK INCLUDED
.1 The following work is included, but not limited to:
.1 Cell excavation and embankment berm construction.
.2 Stockpiling excess excavated material.
.3 General site grading.
.4 All handling of common excavated materials necessary to construct the Work.
.5 Anchor trench excavation and fill.
.6 Construction of on-site drainage ditches.
.7 Excavation of leachate collection trenches.
.8 Excavation of subdrain trenches and excavation for installation of a vertical riser.
1.2 RELATED WORK
.1 Geomembranes - refer to Section 02073.
.2 Stripping - refer to Section 02113.
.3 Clay Liner - refer to Section 02215.
.4 Geosynthetic Clay Liner - refer to Section 02594.
1.3 REFERENCE STANDARDS
.1 Refer to ASTM Sieve Analysis and ASTM Tests for Specifications for aggregates and
soils.
.2 Other materials are specified with reference to CGSB Standards, CSA Standards,
ASTM Standards and AASHTO Standards.
1.4 QUALITY CONTROL
.1 Quality Control - refer to Section 01450.
1.5 SUBMITTALS
.1 Submittals - refer to Section 01001 - General Requirements.
1.6 MEASUREMENT AND PAYMENT
.1 Measurement and Payment - refer to Section 01270.
Foothills Regional Services Commission Section 02210
Foothills Landfill Expansion - Cell 6 COMMON EXCAVATING AND GRADING
2018-01/2017-3650.020 Page 2 of 7
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\02210.doc: January 29, 2018
1.7 DISPOSAL
.1 All materials on site whether stockpiled, stored or excavated are the property of the
Owner, and the Owner reserves the right to keep any part or all of the material.
.2 The Contractor shall dispose of debris, waste, unsuitable material, rock or excess
material under direction of Engineer.
2 Products
2.1 EMBANKMENT MATERIAL
.1 Embankments shall be constructed using suitable clay till material excavated on site.
2.2 COMMON EXCAVATION MATERIALS
.1 Common excavation materials shall be any materials excavated from the site,
consisting of clay till and minor quantities of sand, clay or silty material, gravel, or
organic materials.
.2 Organic material is peat moss, or other organic soil underlying the topsoil, or topsoil
that has not previously been stripped.
.3 Unsuitable materials are materials other than organic material that are in the opinion of
the Engineer, not suitable for use in sub-grade of roads, embankments or fills. Frozen
material is considered unsuitable material.
2.3 ROCK EXCAVATION
.1 Rippable rock excavation shall be defined as weathered rock that can be loaded and
hauled to stockpile using common excavation methods after being ripped by means of
a ripper tooth attached to a crawler tractor or any other piece of equipment. Rippable
rock excavation shall be approved by the Engineer prior to commencement of this type
of excavation. Volume of rippable rock loaded and hauled to stockpile using common
excavation methods shall be measured in stockpile approved by the Engineer.
.2 Loading and hauling of ripped boulders shall be completed by means of a backhoe and
rock trucks to the rock stockpile. Rippable boulders shall have a volume larger than
what typically can be loaded and hauled using motor scrapers or other machinery used
to load and haul common excavated material. Rippable boulder loading and hauling
shall only commence upon the approval of the Engineer. Volume of rippable boulders
loaded and hauled shall be measured in stockpile.
.3 Solid rock is defined as either single boulders, or bedrock with a volume in excess of
0.24 m3 or any material that cannot be removed by D8R Series 300 crawler tractor or
equal with a single ripper tooth and, having a bucket capacity of 0.95 m3 to 1.15 m3
Foothills Regional Services Commission Section 02210
Foothills Landfill Expansion - Cell 6 COMMON EXCAVATING AND GRADING
2018-01/2017-3650.020 Page 3 of 7
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\02210.doc: January 29, 2018
and which requires for its removal, drilling and blasting or breaking up with a power
operated hand tool.
.4 No soft or disintegrated rock which can be ripped with a crawler tractor having a rated
horsepower of 240, no loose or previously blasted rock, or broken stone shall be
classified as solid rock.
.5 Frozen material shall not be classified as solid rock.
.6 If, in the opinion of the Contractor, solid rock is encountered, he shall immediately
notify the Engineer. The Engineer shall make a determination as to whether or not the
material qualifies as solid rock.
.7 If solid rock is encountered, the volume of solid rock excavated shall be measured in
stockpile approved by the Engineer.
.8 The limits of solid rock excavation shall be determined by the Engineer.
.9 Remove rock to a disposal site designated by the Engineer.
3 Execution
3.1 PREPARATION OF SITE
.1 Maintain slopes and adequate drainage during grading.
.2 Dewatering:
.1 It is the responsibility of the Contractor to remove water from trenches and
excavations, regardless of origin.
.2 Provide pumps and other equipment and materials necessary to keep excavations
free of water while work is in progress.
.3 Construction water shall be kept separate from landfill leachate system by use of
berms and/or trenches.
.4 Equipment used for dewatering shall be of a suitable and rugged type to ensure
continuous operation.
.5 Make provision as necessary to prevent flotation or damage to the work in case of
accidental stoppage of dewatering equipment.
.6 Protect excavations against flooding and damage due to surface run-off.
.7 Dispose of the water away from the Work in a manner such that there is no
damage to the Work or other property or persons. Submit dewatering disposal plan at
request of Engineer.
.8 Provide silt fence, silt bags, straw bales or other suitable erosion control devices
as required to minimize erosion of the excavation work.
Foothills Regional Services Commission Section 02210
Foothills Landfill Expansion - Cell 6 COMMON EXCAVATING AND GRADING
2018-01/2017-3650.020 Page 4 of 7
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\02210.doc: January 29, 2018
.3 Excavate and remove all materials to the depths and dimensions necessary for the
construction of the structure and/or piping systems.
.4 Stockpile excavated materials suitable for backfill in designated location. Common
excavated material stockpiles shall be located on areas stripped of topsoil and subsoil.
.5 Minimize disturbance to supporting soil.
.6 Remove debris and trim excavations. If material at the bottom of the excavation has
been disturbed, compact to a density equal to undisturbed soil.
.7 Inspection:
.1 Notify the Engineer for inspection after the excavation is completed.
3.2 DITCHES
.1 Excavate drainage ditches in locations appropriate to maintain drainage on site to
detention ponds. All side slopes to be finished to allow seeding and maintenance of
slopes.
3.3 LANDFILL CELL
.1 Excavate the Landfill Cell to the depth and grade indicated on the Drawings. Stockpile
excavated material in locations indicated on the Drawings.
.2 In cut areas, undercut, soft, compressible soil and otherwise unsuitable soil areas a
minimum 1000 mm or as directed by the Engineer, and replace with suitable clay till
or clayey materials and compact in accordance with the requirements of this
Specification.
.3 In fill areas, scarify the surface prior to placing fill.
.4 Place fill in 150 mm lifts and compact to 95% of maximum density as determined by
the Standard Proctor compaction test and within (+/-) 3% of the optimum moisture
content.
3.4 GRADING PROCEDURES
.1 Excavate to the required sub-grade elevation and to cross-sections shown on the
Drawings.
.2 Excavate organic material and stockpile or place in fills, if approved by the Engineer.
.3 Excavate unsuitable material and haul to disposal areas.
.4 Do not mix organic materials, unsuitable materials or rock with other excavated
materials.
Foothills Regional Services Commission Section 02210
Foothills Landfill Expansion - Cell 6 COMMON EXCAVATING AND GRADING
2018-01/2017-3650.020 Page 5 of 7
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\02210.doc: January 29, 2018
.5 Overexcavate as required and as directed by the Engineer to remove organic, soft,
compressible and otherwise unsuitable material.
.6 Overexcavate to remove organic and unsuitable material, such that there is a 5H:1V
slope between the in-situ material and the material replaced with suitable fill.
.7 Maintain slopes and adequate drainage during grading.
.8 The use of vibratory compaction equipment is not allowed.
3.5 EMBANKMENTS, LAYERS, AND FILLS
.1 Scarify and compact sub-grade to 95% of the maximum Standard Proctor Density.
.2 Uniformly grade areas to be filled before placing material.
.3 Place common excavated materials in embankments, layers, and fills; and in
over-excavated areas if approved by the Engineer.
.4 Construct embankments by depositing, shaping and rolling materials in layers not
exceeding 200 mm thickness.
.5 Where compaction of embankments, layers, and fills is required, place the material in
200 mm lifts and compact to 95% of the maximum Standard Proctor Density.
.6 In the event that the material is too wet to obtain the specified density thoroughly work
the material by blading or other acceptable means, until the optimum moisture content
is reached. If the material is too dry, add water as necessary. Moisture content of the
material being placed in and embankments, layers, and fills shall be controlled to
within (+/-) 3% of the optimum condition.
3.6 LEACHATE TRENCHES
.1 Excavate leachate trenches to the required elevations and slopes as shown on the
Drawings.
.2 Uniformly grade areas to be filled before placing material.
.3 Where common excavated material for leachate trenches is required, place material in
150 mm lifts and compact to 95% of the maximum Standard Proctor Density.
.4 In the event that the material is too wet to obtain the specified density, thoroughly
work the material by blading, or other acceptable means, until the optimum moisture
content is reached. If the material is too dry, add water as necessary. Moisture content
of the material being placed in leachate collection trenches shall be controlled to
within (+/-) 3% of the optimum condition.
Foothills Regional Services Commission Section 02210
Foothills Landfill Expansion - Cell 6 COMMON EXCAVATING AND GRADING
2018-01/2017-3650.020 Page 6 of 7
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\02210.doc: January 29, 2018
3.7 FINISHING
.1 Final surfaces shall be reasonably smooth and uniform, free from lumps, loose earth,stones and debris.
.2 Grades shall be within 30 mm of design grades.
3.8 UTILITIES
.1 Locate, protect and mark all utilities and appurtenances, including groundwatermonitoring wells and benchmarks.
.2 Overhead and buried power and telecommunication lines may exist, so appropriatesafety measures must be taken for equipment and construction.
3.9 ANCHOR TRENCH
.1 A common anchor trench shall be provided for the HDPE geomembrane liner. Refer tothe Drawings for typical detail.
.2 The anchor trenches shall be constructed in coordination with the GeosyntheticsInstallation Contractor.
.3 Slightly rounded corners shall be provided in the trench where the HDPE liner adjoinsthe trench so as to avoid sharp bends in the HDPE liner. No loose soil shall be allowedat the bottom of the trench.
.4 Remove all sandbags prior to backfilling anchor trench. Coordinate removal of sandbags with the Geosynthetics Installation Contractor before proceeding with sandbagremoval.
.5 The anchor trench shall be backfilled and compacted. Trench backfill material shall beplaced in two (2) equal lifts, each not less than 300 mm thick (loose) and compactedby wheel rolling with light, rubber-tired or other light compaction equipment.
.6 Care shall be taken when backfilling the trenches to prevent any damage to thegeomembrane. At no time shall construction equipment come into direct contact withthe geomembrane. If damage occurs, it shall be repaired by the GeosyntheticsInstallation Contractor prior to the completion of backfilling.
.7 Backfilling shall occur when the geomembrane material is at its most contracted stateto avoid potential bridging problems, and shall be coordinated with the GeosyntheticsInstallation Contractor.
.8 Compaction of backfill should be a minimum of 95% of the maximum StandardProctor Density and suitable to the Geosynthetics Installation Contractor.
.9 Anchor trench and anchor trench cap compaction tests shall be taken at one (1) test per200 lm per lift. Test results shall be submitted as part of QC submission requirements.
Foothills Regional Services Commission Section 02210
Foothills Landfill Expansion - Cell 6 COMMON EXCAVATING AND GRADING
2018-01/2017-3650.020 Page 7 of 7
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\02210.doc: January 29, 2018
3.10 STOCKPILES
.1 Provide and maintain for positive drainage from stockpile area and from around the
toes of the stockpile.
.2 Construct the stockpiles with smooth and even sideslopes, free from excess
depressions, ridges or piles. Stockpiles graded at maximum 2H:1V finished slopes.
Stockpile ramps graded to between 4H:1V and 5H:1V slopes.
END OF SECTION
Foothills Regional Services Commission Section 02215
Foothills Landfill Expansion - Cell 6 CLAY LINER
2018-01/2017-3650.020 Page 1 of 5
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\02215.doc: January 29, 2018
1 General
1.1 WORK INCLUDED
.1 The following work is included: Compacted Clay Liner (CCL) for the landfill cell or
any other area shown on the Drawings or designated by the Engineer.
1.2 RELATED WORK
.1 Geomembranes - refer to Section 02073.
.2 Common Excavating and Grading - refer to Section 02210.
.3 Leachate Collection System - refer to Section 02411.
.4 Geosynthetic Clay Liner - refer to Section 02594.
1.3 REFERENCE STANDARDS
.1 The following tests shall be conducted by the Owner’s testing agency:
.1 Moisture density curves: ASTM D698.
.2 Field densities: ASTM D2167 or to ASTM D2922.
.3 Field moisture: ASTM D3017.
.4 Permeability: ASTM D5084.
.5 Atterberg limits: ASTM D4318.
.6 Water content: ASTM D2216 or D4643.
.7 Particle size distribution: ASTM D422.
1.4 QUALITY CONTROL
.1 Quality Control - refer to Section 01450.
.2 Material Supply:
.1 Refer to Clause 2 - Products.
1.5 MATERIAL PLACEMENT
.1 Refer to Clause 3 - Execution for details of individual tests to be carried out.
.2 The use of vibratory compaction equipment is not allowed.
1.6 SUBMITTALS
.1 Submittals - refer to Section 01001 - General Requirements.
Foothills Regional Services Commission Section 02215
Foothills Landfill Expansion - Cell 6 CLAY LINER
2018-01/2017-3650.020 Page 2 of 5
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\02215.doc: January 29, 2018
2 Products
2.1 CLAY MATERIAL
.1 Thickness of Compacted Clay Liner (CCL) is indicated on the Drawings.
.2 The CCL will be constructed using select excavated clay till or suitably plastic clayey
material.
.3 The material shall be clean and free of rocks greater than 100 mm in size, topsoil,
sand, organic material, frozen lumps, debris or other deleterious material.
.4 The material used shall have the following minimum physical characteristics:
Parameter Required Min. Value
Plasticity Index (PI) ≥15
Liquid Limit 30 ≤ LL ≤ 50
Fines (Clay + Silt) Content ≥65%
Clay Content ≥11%
.5 At least one (1) moisture-density (ASTM D698 or D1557) and one (1) Atterberg
Limits (ASTM D4318) will be carried out by Owner’s testing agency for each 4000 m3
of material used for CCL construction or with each change in material type (minimum
of four (4) tests).
.6 At least one (1) water content (ASTM D2216, D4643, D4944, D4959) shall be carried
out by Owner’s testing agency for each 4000 m3 of material used for CCL construction
or with each change in material type. These tests shall be completed immediately after
CCL material has been excavated due to the duration of the test (minimum of
four (4) tests).
.7 At least one (1) particle size distribution (ASTM D422) shall be carried out by
Owner’s testing agency for each 4,000 m3 of material used for CCL construction or
with each change in material type (minimum of four (4) tests).
.8 At least one (1) remoulded hydraulic conductivity test (ASTM D5084) shall be carried
out by Owner’s testing agency for each 10,000 m3 of material used or with each
change in material type (minimum of two (2) tests). Test parameters shall conform to
96% Standard Proctor Density and 2-5% above optimum moisture content.
(Consideration may be given to possible revisions to the allowable moisture content
and related compaction density required, based on results of laboratory remoulded
permeability testing undertaken by the Owner’s testing agency).
Foothills Regional Services Commission Section 02215
Foothills Landfill Expansion - Cell 6 CLAY LINER
2018-01/2017-3650.020 Page 3 of 5
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\02215.doc: January 29, 2018
.9 The material shall be capable of achieving, upon compaction, a hydraulic conductivity
of 1 x 10-9 m/s or less based on remoulded samples using ASTM D5084. The
Contractor is responsible for achieving the specified permeability.
3 Execution
3.1 SUB-GRADE PREPARATION
.1 Examine the surface on which the CCL will be placed.
.2 Scarify the clay base to a depth of 200 mm below CCL grade and compact to 95% of
the maximum density (within +/- 3% of the Optimum Moisture Content) as
determined by the Standard Proctor Compaction test.
.3 Remove rocks and roots and fill depressions with compacted clay material.
.4 All slopes of the landfill sub-grade are to be uniform.
.5 The Contractor shall be responsible for preparing and maintaining the sub-grade in a
condition suitable for installation of the CCL.
.6 Prior to CCL material placement, a survey of the sub-grade shall be performed. Await
Engineer’s approval to commence clay liner material placement.
3.2 CLAY LINER
.1 The compaction of the CCL shall be performed using equipment which will provide
compaction by penetrating through the entire thickness of the clay lift placed.
Compaction equipment to operate at speeds that will provide optimum compaction.
Compaction equipment not to perform sudden braking or sharp turns.
.2 CCL graded shall be within 30 mm (+/-) of design grades.
.3 The clay, when compacted shall have a moisture content of 2-5% over optimum
moisture content.
.4 The Contractor shall moisture condition (dry or wet) the clay material if necessary; and
shall supply and add water as necessary to control the moisture content.
.5 Place select fill materials in thin lifts such that complete mixing of the fill materials is
accomplished and uniform compaction to the specified density of 96% of maximum
standard proctor density is achieved for the full depth of the lift. Under no
circumstances should the lift exceed 150 mm compacted thickness. Sideslopes should
be placed in horizontal lifts keyed into the embankment. The final surface should be
trimmed to the design grades. The width will be dependant on compaction equipment
with minimum thickness perpendicular to the slope.
Foothills Regional Services Commission Section 02215
Foothills Landfill Expansion - Cell 6 CLAY LINER
2018-01/2017-3650.020 Page 4 of 5
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\02215.doc: January 29, 2018
.6 One (1) moisture content test (ASTM D3017) and one (1) density test (ASTM D2922)
shall be completed by the Owner’s testing agency with a frequency of thirteen (13)
tests/ha/lift on all material compacted. One (1) test of water content (ASTM D2216)
shall be completed by the Owner’s testing agency on the CCL each day of
construction.
.7 If the Contractor must place the CCL material thicker than the minimum specified in
order to provide proper operating conditions for construction equipment, the
Contractor shall allow for the thickness in constructing the slopes, and the Contractor
shall bear the cost of providing the extra clay.
.8 CCL acceptance will be based on the in-situ hydraulic conductivity of the CCL
material. One (1) hydraulic conductivity test of undisturbed samples (ASTM D5084)
or equivalent in-situ test shall be completed by the Owner’s testing agency for each
10,000 m3 of material used (minimum four (4) tests). Testing shall confirm that the
CCL achieved a hydraulic conductivity less than 1 x 10-9 m/s. The Contractor is
responsible for achieving the specified permeability.
.9 In the event that the Engineer accepts a revision to the parameters, the Contractor will
still be responsible for attaining the specified hydraulic conductivity of 1 x 10-9 m/s or
less. The unit rate or total amount for the Work shall not change from the Contract
amount.
.10 The top and bottom (subgrade) of the CCL shall be surveyed by the Contractor in a
maximum grid of 20 x 20 m for liner thickness, grade and uniformity. The results shall
be reviewed by the Engineer prior to installation of any layer or material on top of the
CCL, including geomembranes. Await Engineer approval prior to placement of any
layer or material on top of the CCL.
.11 CCL should not be constructed when daytime temperatures are below freezing.
.12 The CCL must be protected from desiccation and freezing.
.13 Submit sub-grade acceptance certificate to Engineer prior to proceeding with
geomembrane placement.
.14 Smooth roll CCL in preparation for HDPE liner installation. Finished surface of CCL
shall be ready to receive HDPE liner as required.
.15 Maintain CCL moisture content, by spraying with water and rolling with a smooth
drum roller during times of dry weather, to eliminate shrinkage cracking prior to
HDPE liner installation.
.16 Ensure that voids in the CCL created from tests, grade stakes, and other penetrations
are repaired.
Foothills Regional Services Commission Section 02215
Foothills Landfill Expansion - Cell 6 CLAY LINER
2018-01/2017-3650.020 Page 5 of 5
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\02215.doc: January 29, 2018
3.3 STATUS REPORTS
.1 A weekly report completed by the Owner’s geotechnical testing agency outlining the
status of remoulded hydraulic conductivity test results and in-situ hydraulic
conductivity test results will be provided to the Contractor.
.2 The weekly report will contain the following information:
.1 Remoulded hydraulic conductivity.
.2 In-Situ hydraulic conductivity.
.3 The Contractor is responsible for reviewing the weekly CCL report and ensuring the
materials used, and the completed CCL, conform to the specified requirements.
3.4 APPROVAL TO PROCEED WITH GEOMEMBRANE INSTALLATION
.1 The geomembrane liner installation shall not commence until the Contractor has
obtained verification from the Engineer that all in-situ hydraulic conductivity tests, in
accordance with Clause 3.2.9, have been completed and have passed the required
standard of 1 x 10-9 m/s.
.2 The Engineer may, at his discretion, allow the geomembrane liner installation to
proceed prior to the completion of the required in-situ hydraulic conductivity testing.
END OF SECTION
Foothills Regional Services Commission Section 02411
Foothills Landfill Expansion - Cell 6 LEACHATE COLLECTION SYSTEM
2018-01/2017-3650.020 Page 1 of 9
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\02411.doc: January 29, 2018
1 General
1.1 WORK INCLUDED
.1 The following work is included, but not limited to:
.1 Supply and installation of drainage gravel for the leachate collection trenches.
.2 Supply and installation of perforated PVC piping and fittings.
.3 Supply and installation of solid HDPE piping and fittings.
.4 Supply and installation of the permanent clean-out infrastructure.
.5 Installation of Owner supplied tire shred.
.6 Supply and installation of light geotextile.
.7 Supply and installation of heavy geotextile.
.8 Supply and installation of 2-sided geocomposite.
.9 Supply and installation of waste limit rope.
.10 Reaming of all interior PE risers and clean-out connections.
1.2 RELATED WORK
.1 Geomembranes - refer to Section 02073.
.2 Common Excavating and Grading - refer to Section 02210.
.3 Geosynthetic Clay Liner - refer to Section 02594.
1.3 QUALITY CONTROL
.1 Quality Control - refer to Section 01450.
.2 Material Supply:
.1 The geosynthetic material supplied shall be in accordance with the Specifications.
Any proposed variance or deviation shall be requested in writing to the Engineer prior
to the commencement of installation.
.2 The Geosynthetics Installation Contractor shall submit certificates of compliance
with the requirements of standards and testing methods; and affidavits that geotextiles
and geocomposite materials meet the requirements of the Specifications in every
respect. Certificates to be provided for each lot supplied.
.3 Manufacturers shall have at least two (2) years continuous experience in the
manufacture of the respective geosynthetic.
.4 The manufacturer shall permit the Engineer to visit the manufacturing plant and
witness geosynthetic manufacture.
Foothills Regional Services Commission Section 02411
Foothills Landfill Expansion - Cell 6 LEACHATE COLLECTION SYSTEM
2018-01/2017-3650.020 Page 2 of 9
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\02411.doc: January 29, 2018
.3 Testing:
.1 Minimum quality control test frequencies specified as follows are the minimum
number required. The Contractor or Geosynthetics Installation Contractor shall
perform as many tests as are necessary to ensure that the work conforms to the
requirements of the Contract regardless of the minimum number required.
.2 The Contractor shall inspect each heat fusion joint made. The inspection shall be
by a person other than the person making the joint.
1.4 SUBMITTALS
.1 Submittals - refer to Section 01001 - General Requirements.
1.5 PRODUCT DELIVERY, STORAGE AND HANDLING
.1 Pipe, geocomposite and geotextile materials shall be handled and stored in accordance
with the manufacturer’s recommendations.
.2 Store pipe, geocomposite and geotextile materials so that they do not come in contact
with substances that may affect their physical or chemical properties. Fuel, equipment
exhausts and petroleum products are potentially hazardous.
.3 The pipe manufacturer shall supply raw materials and manufacture pipe in compliance
with the standards specified in Clause 2 - Products.
.4 The pipe manufacturer shall provide certificates of compliance with the relative CSA,
CGSB and ASTM standards.
.5 Pipe shall be unloaded and handled by the Contractor with care to prevent damage.
.6 Lift pipe with fabric slings or manually.
.7 Do not use hooks in pipe ends.
1.6 MARKING
.1 All pipe should be marked as follows:
.1 Manufacturer name.
.2 Nominal size.
.3 Manufacturing standard reference - CGSB/CSA.
.4 Production code for date of manufacture.
1.7 HEAT (BUTT) FUSION JOINTS
.1 Polyethelene pipe shall be joined by the method of thermal butt fusion (ASTM F2620 -
Heat Joining Polyethylene Pipe and Fittings).
Foothills Regional Services Commission Section 02411
Foothills Landfill Expansion - Cell 6 LEACHATE COLLECTION SYSTEM
2018-01/2017-3650.020 Page 3 of 9
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\02411.doc: January 29, 2018
.2 Butt fusion joining of pipe and fittings shall be performed in accordance with the
procedures recommended by the manufacturer.
.3 Individuals performing heat fusion joining shall have training and experience in the
use of the fusion procedure. Submit proof of training and experience.
.4 Individuals performing heat fusion joining shall make sample joints, according to
approved procedures, that pass the following inspections and tests:
.1 Joints shall be visually examined during and after joining and found to have the
same appearance as control joints or photographs of acceptable joints.
1.8 MEASUREMENT AND PAYMENT
.1 Measurement and Payment - refer to Section 01270.
1.9 DISPOSAL
.1 Remove and dispose of all waste material offsite at Contractor’s expense, unless onsite
disposal is provided by the Owner.
2 Products
2.1 LIGHT GEOTEXTILE
.1 The geotextile material shall be non-woven needle-punched polypropylene. The
geotextile material shall be a minimum weight of 6 oz/yd2. The material Specifications
shall be based on minimum average roll values not typical values.
.2 The geotextile shall exhibit the following properties:
Property Units ASTM Test Method Minimum Value
Grab Tensile kN D4632 0.710
Apparent Opening Size mm D4751 0.212*
Permittivity/Flow Ratesec-1/
L/min/m2 D4491 1.5/4480
UV Resistance % D4355 70
*Maximum Value
.3 The rolls must be tagged to identify lot and batch, unique roll number, roll dimension,
manufacturer and material type. Provide QA testing certificate for each roll delivered.
2.2 HEAVY NON-WOVEN GEOTEXTILE
.1 The geotextile material shall be non-woven needle-punched polypropylene. The
geotextile material shall be a minimum weight of 16 oz/yd2. The material
Specifications shall be based on a minimum average roll values not typical values.
Foothills Regional Services Commission Section 02411
Foothills Landfill Expansion - Cell 6 LEACHATE COLLECTION SYSTEM
2018-01/2017-3650.020 Page 4 of 9
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\02411.doc: January 29, 2018
.2 The geotextile for the protection layer exhibit the properties described in the
GRI GT12 Standards - “Test Methods and Properties for Non-woven Geotextiles used
as Protection (or Cushioning) Materials”.
.3 The rolls must be tagged to identify lot, batch, unique roll number, roll dimensions,
manufacturer and material type. Provide QC testing certificate for each roll delivered,
in accordance with the following required properties:
Property ASTM Test Method Unit MARV
Mass Per Unit Area D5261 oz/yd2 16
Grab Tensile Strength D4632 KN 1.64
Grab Tensile Elongation D4632 % 50
Trap Tear Strength D4533 KN 0.64
Puncture Strength D4833 KN 0.75
UV Resistance D4533 % 70
2.3 PVC PIPE - LEACHATE COLLECTION
.1 PVC Pipe Standards:
.1 To CAN/CSA - B182.2.
.2 200 mm diameter SDR - 35.
.3 Joint Type - Bell and Spigot, gasketed.
.4 Perforated.
.5 Perforations shall be 16 mm diameter, two (2) rows @ 120° spaced at 300 mm on
centre.
.6 End caps shall be PVC.
2.4 SOLID AND PERFORATED HDPE PIPE
.1 Unless otherwise shown, the leachate riser pipe is to be 300 mm (10”) HDPE DR11
with perforations, as shown on the Drawings.
.2 Pipe to be dimensions shown on Contract Drawings.
.3 Pipe to CSA B137.0 - General Requirements and Methods of Testing for
Thermoplastic Pipe.
.4 Pipe to CSA B137.1 - Polyethylene Plastic Pipe (SDR-PR) Based on Controlled
Outside Diameter.
.5 Pipe to ASTM D2837 - Long Term Hydrostatic Strength of 1600 psi.
Foothills Regional Services Commission Section 02411
Foothills Landfill Expansion - Cell 6 LEACHATE COLLECTION SYSTEM
2018-01/2017-3650.020 Page 5 of 9
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\02411.doc: January 29, 2018
.6 To ASTM F714 - Polyethylene (PE) Plastic Pipe (SDR-PR) based on outside diameter.
.7 Raw material designation ASTM D1248 Type III, Class C, Category 5, Grade P34,Polyethylene material PE3408.
.8 Pipe Joint - Thermal Butt Fusion - as per ASTM F2620, Heat Joining PolyethylenePipe and Fittings.
.9 End caps shall be HDPE.
2.5 DRAINAGE GRAVEL
.1 Clean, screened drainage gravel: 50 mm maximum size. The drainage gravel materialconforming to the following or as approved by the Engineer:
Sieve Size Percent Passing
50 mm 100
40 mm 60 - 100
25 mm 10 - 60
16 mm 0 - 5
4.75 mm 0 - 2
.2 The drainage gravel shall be capable of obtaining a minimum hydraulic conductivity of1 x 10-2 m/s based on ASTM D2434 test method.
2.6 GEOCOMPOSITE (2-SIDED)
.1 The double-sided geocomposite shall consist of a geonet with a non-woven geotextilebonded to two sides. The geonet shall consist of two (2) sets of polyethylene strandsextruded to form a bi-planar drainage material. This geonet provides planar leachateflow, which shall be inert to biological attack, naturally encountered chemicals, alkalisand acids and shall be resistant to ultra-violet (UV) light exposure.
.2 The geotextile material shall be a non-woven needle punched polypropylene. Thegeotextile material shall be a minimum weight of 6 oz/yd2. The material specificationshall be based on minimum average roll values, not typical values.
.3 The non-woven geotextile shall exhibit the following properties:
Property UnitsASTM Test
Method
MinimumAverage Roll
Value
Weight oz / sy D5261 5.6
Grab Tensile lbs (kN) D4632 160 (0.712)
Grab Elongation % D4632 50
Permittivity/Flow Rate sec-1 D4491 1.5
Foothills Regional Services Commission Section 02411
Foothills Landfill Expansion - Cell 6 LEACHATE COLLECTION SYSTEM
2018-01/2017-3650.020 Page 6 of 9
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\02411.doc: January 29, 2018
.4 The resulting geocomposite shall exhibit the following Specifications.
Property Units ASTM TestMethod
MinimumAverage Roll
Value
Thickness (net) mils (mm) D5199 300 (7.6)
Density of Polymer g/cm3
D1505 or
D792
Method B
0.94
Carbon Black % D4218 2
Melt Index g/10 min D1238 1 max
Geocomposite Transmissivity* m2/sec D4716 3.0 x 10-3
* Transmissivity should be measured using water at 20 degrees C and with a slope gradient of 0.1. Thetesting should be conducted with the geocomposite between a geomembrane, Ottawa sand, and two (2)steel plates; under a confining pressure of at least 1000 psf and a fifteen (15) minute duration.
2.7 FERNCO COUPLING ADAPTOR
.1 The coupling adaptor used to connect new perforated leachate collection piping toexisting piping shall be a Fernco Series 1056 coupler or approved equal.
.2 The Fernco Series 1056 coupling adaptor shall be sized and selected to suit the outsidediameter (OD) of the existing and new perforated pipes. All hardware to be stainlesssteel.
2.8 WASTE LIMIT ROPE
.1 10 mm diameter yellow nylon rope.
.2 Zip ties.
3 Execution3.1 METHODS OF PLACEMENT - GEOTEXTILE
.1 All geotextiles shall be handled in a manner to ensure they are not damaged. Thefollowing special handling requirements shall be adhered to.
.2 On slopes, the geotextiles shall be anchored in the trench and then rolled down theslope when practical. The geotextiles shall be deployed in a manner to continuallykeep the geotextile sheet in sufficient tension to reduce folds or wrinkles.
.3 All geotextiles shall be weighted with sandbags or the equivalent.
.4 Geotextiles shall be cut using an approved cutter. Special care should be taken toprotect other geosynthetic materials from damage.
.5 Care shall be taken not to entrap stones or excessive dust that could generate cloggingof drains or filters.
Foothills Regional Services Commission Section 02411
Foothills Landfill Expansion - Cell 6 LEACHATE COLLECTION SYSTEM
2018-01/2017-3650.020 Page 7 of 9
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\02411.doc: January 29, 2018
3.2 SEAMS AND OVERLAPS - GEOTEXTILE
.1 Geotextiles shall be seamed by thermal bonding or by sewing. No horizontal seams
shall be allowed on side slopes.
.2 On slopes steeper than 10H:1V, geotextiles shall be overlapped a minimum of 100 mm
prior to sewing as per the manufacturer’s installation requirements.
.3 On bottoms and slopes shallower than 10H:1V, geotextiles shall be sewn as per the
manufacturer’s installation requirements, or thermally bonded. If thermally bonded,
the geotextile shall be overlapped a minimum of 100 mm prior to seaming.
3.3 DEFECTS AND REPAIRS - GEOTEXTILE
.1 Defects in the geotextile shall be repaired as follows:
.1 On slopes: A patch made of the same geotextile shall be seamed into place. If the
hole or tear width across the roll is more than 50% the width of the roll, the damaged
area shall be cut out and the two (2) portions of the geotextile shall be joined.
.2 Horizontal areas: A patch made from the same geotextile shall be spot-seamed in
place with a minimum of 300 mm overlap in all directions.
.3 All defects shall be repaired and documented.
3.4 INSTALLATION - GEOCOMPOSITE
.1 Method of placement: All geocomposite shall be handled in a manner to ensure they
are not damaged. The following special requirements shall be adhered to:
.1 On slopes, the geocomposites shall be secured in the anchor trench and then rolled
down the slope when practical. The geocomposite shall be deployed in a manner to
continually keep the geocomposite sheet in sufficient tension to reduce folds and
wrinkles.
.2 In the presence of high wind, all geocomposite shall be weighted with sandbags or
the equivalent.
.3 The underlying layer shall be clean and free from debris, snow, and soil.
.4 Geocomposite shall be cut using an approved cutter. If material is being cut in
place, special care should be taken to protect other geosynthetic materials from
damage.
.5 Care should be taken not to entrap stones or excessive dust that could damage the
geomembrane, or generate clogging of drains or filters.
.2 Seams and overlaps: Geocomposite shall be seamed by thermal bonding or by sewing.
No horizontal seams shall be allowed on side slopes greater than 4H:1V.
.1 Tying of the geonet shall be with plastic fasteners. Tying devices shall be white
or yellow for easy inspection. Metallic devices are not allowed.
Foothills Regional Services Commission Section 02411
Foothills Landfill Expansion - Cell 6 LEACHATE COLLECTION SYSTEM
2018-01/2017-3650.020 Page 8 of 9
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\02411.doc: January 29, 2018
.2 Tying shall be every 1.5 m across the cell floor, every 1.5 m along the side slopes
and every 750 mm at the top of berms and into anchor trenches. End to end joints on
the cell floor shall be overlapped 600 mm with no tying.
.3 Repairs: The damage shall be observed, and if smaller than 1 m by 1 m, the
geocomposite shall be repaired. If the tear or hole is larger, then the roll shall be cut to
remove the damaged area, fasteners shall be used to attach the geonet with the
geotextile being heat seamed. Minimum overlaps to be as specified.
.1 If the geonet is undamaged, and the geotextile is damaged, a patch of geotextile
shall be placed. The geotextile patch shall be thermally bonded in place with a
minimum of 300 mm overlap in all directions.
.2 If the geonet is damaged, the geonet shall be removed. A section of geonet shall
be cut to replace the removed section. The geonet shall be tied to the existing geonet
using plastic fasteners placed at least every 150 mm. A geotextile patch shall be placed
over the repaired geonet section. The geotextile patch shall be thermally bonded in
place with a minimum of 300 mm overlap in all directions. All defects shall be
repaired and documented.
3.5 DRAINAGE GRAVEL PLACEMENT
.1 Install drainage gravel to the lines and levels shown on the Drawings.
.2 Install at initial depth to protect geomembranes and other geosynthetics from damage.
Do not slide material over geomembranes; such actions may cause wrinkling.
.3 Equipment used to haul and place drainage gravel shall be low ground pressure, rubber
tired or rubber tracked type equipment and shall be approved by Engineer (e.g., skid
steer). The Contractor shall use rubsheets, sacrificial geocomposite materials and other
materials and methods to protect the geomembrane liner from damage. All costs for
such work shall be borne by the Contractor.
.4 Provide the results of the record survey of the completed surface of the drainage gravel
layer based on a maximum 15 m x 15 m grid.
3.6 ALIGNMENT AND GRADE
.1 Lay pipe to the required alignment and grade, with fittings and all other appurtenances
at their required locations.
.2 Provide minimum depth of cover on the pipe as detailed on the Drawings.
.3 Acceptable tolerances are as follows:
.1 Alignment - the centreline of the pipe shall not be more than 100 mm off the
given line.
.2 Grade - the centreline of the pipe shall not be more than +/- 50 mm off the given
line.
Foothills Regional Services Commission Section 02411
Foothills Landfill Expansion - Cell 6 LEACHATE COLLECTION SYSTEM
2018-01/2017-3650.020 Page 9 of 9
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\02411.doc: January 29, 2018
3.7 LOWERING PIPE AND ACCESSORIES INTO TRENCH
.1 Use implements, tools and facilities satisfactory to the Engineer, and use care to
prevent damage to pipe and material. Do not drop pipe or materials into the trench.
.2 Cover pipe ends to keep clean.
3.8 PIPELAYING - GENERAL
.1 Cut pipes where necessary to install fittings. Make cuts in accordance with the
manufacturer’s recommendations using recommended cutting tools. Pipes to be cut
squarely and accurately.
.2 Pipe deflections at joint shall not exceed those specified by the pipe manufacturer.
.3 Install perforated piping in accordance with the manufacturer’s recommended methods
and procedures.
.4 Install perforated piping with perforations oriented downwards as shown on the
Drawings.
.5 Install Fernco Series 1056 coupling adaptor(s) at all new pipe to existing pipe
connections. All hardware to be stainless steel.
3.9 LEACHATE RISER PIPE INSTALLATION
.1 Install a blind flange on the top (upper) end of the Leachate Riser pipe.
.2 Install a reducer and coupler(s) on the bottom (lower) end of the leachate riser pipe to
allow for a “silt tight” joint between the perforated leachate collection piping and the
Leachate Riser.
.3 Install 2-sided drainage geocomposite, drainage gravel, light geotextile, perforated
PVC drainage pipe and Leachate Riser to perforated pipe connection at the locations
and lines and levels indicated on the Drawings.
.4 Ream all interior PE connections.
.5 Install anchor bollards and anchor riser as shown on the Drawings.
3.10 WASTE LIMIT ROPE
.1 Zip ties to be 6 m spacing maximum.
END OF SECTION
Foothills Regional Services Commission Section 02415
Foothills Landfill Expansion - Cell 6 SUBDRAIN SYSTEM
2018-01/2017-3650.020 Page 1 of 5
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\02415.doc: January 29, 2018
1 General1.1 DESCRIPTION
.1 This section specifies requirements for installation of those components of the
subdrain system which are included in this Contract.
.2 The following work is included, but not limited to:
.1 Supply and installation of drainage gravel and non-woven geotextile for the
subdrain trench.
.2 Supply and installation of solid and perforated PVC piping and fittings.
.3 Supply and installation of 2-sided geocomposite.
1.2 RELATED WORK
.1 Common Excavating and Grading - refer to Section 02210.
.2 Clay Liner - refer to Section 02215.
.3 Leachate Collection System - refer to Section 02411.
1.3 QUALITY ASSURANCE
.1 The geotextile materials supplied shall be in accordance with the Specifications. Any
proposed variance or deviation shall be requested in writing prior to the
commencement of installation.
.2 The Contractor shall submit certificates of compliance with the requirements of
standards and testing methods; and affidavits that geotextiles and geocomposite
materials meet the requirements of the Specifications in every respect.
1.4 SUBMITTALS
.1 Submittals - refer to Section 01001 - General Requirements.
1.5 PRODUCT DELIVERY, STORAGE AND HANDLING
.1 Geotextile, pipe and materials shall be handled and stored in accordance with the
manufacturer’s recommendations.
.2 Store geotextile, pipe and materials so that they do not come in contact with
substances that may affect their physical or chemical properties.
1.6 MEASUREMENT AND PAYMENT
.1 Measurement and Payment - refer to Section 01270.
Foothills Regional Services Commission Section 02415
Foothills Landfill Expansion - Cell 6 SUBDRAIN SYSTEM
2018-01/2017-3650.020 Page 2 of 5
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\02415.doc: January 29, 2018
1.7 DISPOSAL
.1 Remove and dispose of all waste material offsite at Contractor’s expense, unless onsite
disposal is provided by the Owner.
2 Products2.1 LIGHT GEOTEXTILE
.1 The geotextile material shall be non-woven needle-punched polypropylene. The
geotextile material shall be a minimum weight of 6 oz/yd2. The material Specifications
shall be based on minimum average roll values, not typical values.
.2 The geotextile shall exhibit the following properties:
Property Units ASTM TestMethod Minimum Value
Grab Tensile kN D4632 0.710
Apparent Opening Size mm D4751 0.212*
Permittivity/Flow Rate Sec-1/L/min/m2 D4491 1.5/4480
UV Resistance % D4355 70
*Maximum Value
.3 The rolls must be tagged to identify lot and batch, unique roll number, roll dimension,
manufacturer and material type.
2.2 DRAINAGE GRAVEL
.1 Clean, screened drainage gravel - 50 mm maximum size. The drainage gravel shall
conform to the following:
Sieve Size Percent Passing
50 mm 100
40 mm 60-100
25 mm 10-60
16 mm 0-5
4.75 mm 0-2
.2 The drainage gravel shall be capable of obtaining a minimum hydraulic conductivity
of 1 x 10-2 m/s based on ASTM D2434 test method.
2.3 PVC SUBDRAIN PIPING
.1 Unless otherwise shown, the subdrain pipe is to be 150 mm (6”) PVC solid wall, with
perforations within the trench as shown on the Drawings.
.2 To CAN/CSA - B182.2.
Foothills Regional Services Commission Section 02415
Foothills Landfill Expansion - Cell 6 SUBDRAIN SYSTEM
2018-01/2017-3650.020 Page 3 of 5
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\02415.doc: January 29, 2018
.3 150 mm diameter SDR - 35.
.4 Joint Type - Bell and Spigot, gasketed.
.5 Perforated.
.6 Perforations shall be 16 mm diameter, two (2) rows at 120° spaced at 300 mm on
centre.
.7 End caps shall be PVC.
2.4 PVC RISER PIPE
.1 Unless otherwise shown, the subdrain riser pipe is to be 150 mm 6” PVC solid wall.
.2 To CAN/CSA - B182.2.
.3 SDR - 35.
.4 Joint Type - Bell and Spigot, gasketed.
.5 Solid.
.6 End caps shall be PVC.
2.5 GEOCOMPOSITE (2-SIDED)
.1 The double-sided geocomposite shall consist of a geonet with a non-woven geotextile
bonded to two (2) sides. The geonet shall consist of two (2) sets of polyethylene
strands extruded to form a bi-planar drainage material. This geonet provides planar
groundwater flow, which shall be inert to biological attack, naturally encountered
chemicals, alkalis and acids and shall be resistant to ultra-violet (UV) light exposure.
.2 The geotextile material shall be a non-woven needle punched polypropylene. The
geotextile material shall be a minimum weight of 6 oz/yd2. The material specification
shall be based on minimum average roll values, not typical values.
.3 The non-woven geotextile shall exhibit the following properties:
Property Units ASTM TestMethod
Minimum AverageRoll Value
Weight oz / sy D5261 5.6
Grab Tensile lbs (kN) D4632 160 (0.712)
Grab Elongation % D4632 50
Permittivity/Flow Rate sec-1 D4491 1.5
Foothills Regional Services Commission Section 02415
Foothills Landfill Expansion - Cell 6 SUBDRAIN SYSTEM
2018-01/2017-3650.020 Page 4 of 5
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\02415.doc: January 29, 2018
.4 The resulting geocomposite shall exhibit the following Specifications.
Property Units ASTM TestMethod
MinimumAverage Roll
Value
Thickness (net) mils (mm) D5199 300 (7.6)
Density of Polymer g/cm3D1505 or
D792 Method B0.94
Carbon Black % D4218 2
Melt Index g/10 min D1238 1 max
Geocomposite Transmissivity* m2/sec D4716 3.0 x 10-3
* Transmissivity should be measured using water at 20 degrees C and with a slope gradient of 0.1. The
testing should be conducted with the geocomposite between a geomembrane, Ottawa sand, and
two (2) steel plates; under a confining pressure of at least 1000 psf and fifteen (15) minute duration.
3 Execution3.1 SUBDRAIN PIPE INSTALLATION
.1 Place geotextile as detailed on the Drawings, overlap of 300 mm at top.
.2 Install perforated and solid PVC pipe and fittings as shown on the Drawings.
.3 Place drainage gravel in the trenches in 200 mm layers.
.4 Backfill and compact the remainder of the excavation with suitable common material.
.5 Compact suitable common material to 95% Standard Proctor Density.
.6 Ensure that all fittings are compatible with solid and perforated piping and riser
materials as specified herein.
3.2 INSTALLATION - GEOCOMPOSITE
.1 Method of placement: Geocomposite shall be handled in a manner to ensure it is not
damaged. The following special requirements shall be adhered to:
.1 On slopes, the geocomposite shall be secured in the anchor trench and then rolled
down the slope when practical. The geocomposite shall be deployed in a manner to
continually keep the geocomposite sheet in sufficient tension to reduce folds and
wrinkles.
.2 In the presence of high wind, all geocomposite shall be weighted with sandbags or
the equivalent.
.3 Geocomposite shall be cut using an approved cutter. If material is being cut in
place, special care should be taken to protect other geosynthetic materials from
damage.
Foothills Regional Services Commission Section 02415
Foothills Landfill Expansion - Cell 6 SUBDRAIN SYSTEM
2018-01/2017-3650.020 Page 5 of 5
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\02415.doc: January 29, 2018
.4 Care should be taken not to entrap stones or excessive dust that could generate
clogging.
.2 Seams and overlaps: Geocomposites shall be seamed by thermal bonding or by
sewing. No horizontal seams shall be allowed on side slopes greater than 4H:1V.
.1 Tying of the geonet shall be with plastic fasteners. Tying devices shall be white
or yellow for easy inspection. Metallic devices are not allowed.
.2 Tying shall be every 1.5 m across the bottom, every 1.5 m along the slope, at the
top of berms and into anchor trenches at least with 750 mm intervals. End to end
joints on the bottom shall be overlapped 600 mm with no tying.
.3 Repairs: The damage shall be observed and if smaller than 1 m by 1 m, the
geocomposite shall be repaired. If the tear or hole is larger, then the roll shall be cut to
remove the damaged area and a butt joint placed to restart the roll utilizing minimum
overlaps as specified.
.1 If the geonet is undamaged, and the geotextile is damaged, a patch of geotextile
shall be placed. The geotextile patch shall be thermally bonded in place with a
minimum of 300 mm overlap in all directions.
.2 If the geonet is damaged, the geonet shall be removed. A section of geonet shall
be cut to replace the removed section. The geonet shall be tied to the existing geonet
using plastic fasteners placed at least every 150 mm. A geotextile patch shall be placed
over the repaired geonet section. The geotextile patch shall be thermally bonded in
place with a minimum of 300 mm overlap in all directions. All defects shall be
repaired and documented.
END OF SECTION
Foothills Regional Services Commission Section 02484
Foothills Landfill Expansion - Cell 6 TOPSOIL AND FINISH GRADING
2018-01/2017-3650.020 Page 1 of 3
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\02484.doc: January 29, 2018
1 General
1.1 WORK INCLUDED
.1 The following work is included, but not limited to:
.1 Load, haul and place topsoil from stockpile(s).
.2 Sub-grade grading, as required.
.3 Sub-grade preparation.
.4 Topsoil placement and final topsoil grading.
.5 Seed bed preparation.
.2 Disturbed areas to the stripping limits shown on the drawings, including exterior berm
slopes and ditches, shall be topsoiled and seeded. Areas not to be topsoiled and seeded
include the interior of the Landfill Cell and graveled areas.
.3 Stockpiles not to be topsoiled.
1.2 RELATED WORK
.1 Common Excavating and Grading - refer to Section 02210.
.2 Seeding - refer to Section 02485.
1.3 QUALITY CONTROL
.1 Quality Control - refer to Section 01450.
1.4 DISPOSAL
.1 All materials on site, whether stockpiled or excavated, are the property of the Owner,
and the Owner reserves the right to keep any part or all of the material.
.2 The Contractor shall dispose of debris, waste, unsuitable material, rock or excess
material in accordance with other Sections of the Contract Specifications.
.3 The Contractor shall dispose of all waste materials offsite at sites to be determined by
the Contractor, unless onsite disposal is provided by the Owner.
1.5 MEASUREMENT AND PAYMENT
.1 Measurement and Payment - refer to Section 01270.
Foothills Regional Services Commission Section 02484
Foothills Landfill Expansion - Cell 6 TOPSOIL AND FINISH GRADING
2018-01/2017-3650.020 Page 2 of 3
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\02484.doc: January 29, 2018
2 Products
2.1 TOPSOIL - FROM STOCKPILES
.1 Topsoil stockpile comprises of material previously stripped and stockpiled, prior to
grading.
.2 Topsoil shall be selected from stockpiles so that only those areas of the stockpile
approved by the Engineer are used.
.3 Selected topsoil shall be free from subsoil, slag, clay, stones, lumps, live plant roots or
other unsuitable material.
2.2 INSPECTION
.1 Obtain the Engineer’s review of the topsoil stockpile and areas to receive topsoil prior
to using any materials, whether onsite or borrow materials, for embankments and
topsoil.
3 Execution
3.1 PROTECTION
.1 Locate and protect existing utilities, structures, groundwater monitoring wells and
survey control points.
.2 Correct any damage to existing structures at Contractor’s expense.
3.2 INSPECTION
.1 Examine the site and existing work prior to landscape preparation and notify the
Engineer of any problems or uncompleted work.
3.3 SUB-GRADE TOLERANCE
.1 Grade so that surfaces are within 50 mm of the design grades, and ensure that there are
no depressions or soft areas.
.2 Make grade changes gradual and blend slopes into level areas with no abrupt changes.
.3 Remove rocks, sticks and all debris.
.4 Scarify the surface slightly before placing topsoil.
3.4 PLACING TOPSOIL
.1 Load, haul and place topsoil to provide a thickness of 150 mm, or as directed by the
Engineer.
Foothills Regional Services Commission Section 02484
Foothills Landfill Expansion - Cell 6 TOPSOIL AND FINISH GRADING
2018-01/2017-3650.020 Page 3 of 3
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\02484.doc: January 29, 2018
.2 Grade and level topsoil to a uniform grade.
.3 Harrow or “float” the surface to a texture free from lumps of soil, stones and other
materials.
.4 Remove stones greater than 75 mm in diameter prior to seeding.
3.5 RUN-OFF CONTROL
.1 Provide silt fencing in areas requested by the Engineer at the Contractor’s cost.
END OF SECTION
Foothills Regional Services Commission Section 02485
Foothills Landfill Expansion - Cell 6 SEEDING
2018-01/2017-3650.020 Page 1 of 3
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\02485.doc: January 29, 2018
1 General
1.1 WORK INCLUDED
.1 The following work is included, but not limited to:
.1 Seeding areas are to be landscaped. Include all disturbed areas, exterior berms,
stockpiles, ditches and other areas as designated by the Engineer.
.2 Areas not to be seeded include the interior of the landfill cell and roads.
1.2 RELATED WORK
.1 Topsoil and Finish Grading - refer to Section 02484.
1.3 QUALITY CONTROL
.1 Quality Control - refer to Section 01450.
1.4 SUBMITTALS
.1 General Requirements - refer to Section 01001.
1.5 MEASUREMENT AND PAYMENT
.1 Measurement and Payment - refer to Section 01270.
2 Products
2.1 SEED - MATERIALS
.1 Refer to the Standard Specifications for Highway Construction for application
specifications (2.20.2 MATERIALS):
http://www.transportation.alberta.ca/Content/docType245/Production/2010_Highway
_Construction.pdf
.1 Supply of Materials.
.2 Grass Seed.
.3 Fertilizer.
.4 Hydro-Mulch.
.5 Tackifier.
.6 Water.
Foothills Regional Services Commission Section 02485
Foothills Landfill Expansion - Cell 6 SEEDING
2018-01/2017-3650.020 Page 2 of 3
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\02485.doc: January 29, 2018
2.2 SEED MIXTURE
.1 Refer to the Alberta Infrastructure and Transportation Design Bulletin No.25 - revised
2005-10-26 for seed mixture specifications.
http://www.transportation.alberta.ca/Content/docType233/Production/DesignBulletin2
5.pdf
2.3 RATE OF APPLICATION
.1 Refer to the Standard Specifications for Highway Construction for application
specifications (2.20.3.7 Application rates).
http://www.transportation.alberta.ca/Content/docType245/Production/2010_Highway_
Construction.pdf
3 Execution
3.1 PREPARATION
.1 Examine the site, verify the grades and check that the topsoil has been placed as
specified.
.2 The Work shall be done in calm weather, during the normal planting season for the
type of seed mixture supplied.
.3 Notify the Engineer prior to the start of seeding operations.
3.2 CONSTRUCTION
.1 Refer to the Standard Specifications for Highway Construction for application
specifications (2.20.3 CONSTRUCTION).
http://www.transportation.alberta.ca/Content/docType245/Production/2010_Highway
_Construction.pdf
.1 Notification of Commencement of Work.
.2 Surface Preparation.
.3 Weather Conditions.
.4 Classes of Seeding.
.5 Slope Texturing.
.6 Harrowing.
.7 Protection.
Foothills Regional Services Commission Section 02485
Foothills Landfill Expansion - Cell 6 SEEDING
2018-01/2017-3650.020 Page 3 of 3
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\02485.doc: January 29, 2018
3.3 WARRANTY
.1 Warranty for seeded areas is one (1) year from date of issue of Completion Certificate.
.2 Areas showing deterioration, bare spots or thin areas shall be re-seeded at the
Contractor’s expense.
3.4 INSPECTION
.1 Final inspection of seeded areas will be made at the end of the warranty period.
.2 At the time of inspection all the areas shall be alive and in a healthy satisfactory
growing condition.
.3 Seeding shall be done in the normal growing season, after May 15 and before
August 15.
.4 Areas seeded after August 15 will not be accepted before June 15 of the following
year.
END OF SECTION
Foothills Regional Services Commission Section 02594
Foothills Landfill Expansion - Cell 6 GEOSYNTHETIC CLAY LINER
2018-01/2017-3650.020 Page 1 of 7
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\02594.doc: January 29, 2018
1 General
1.1 WORK INCLUDED
.1 The following work is included, but not limited to:
.1 Supply and installation and quality control of Geosynthetic Clay Liner (GCL).
1.2 RELATED WORK
.1 Geomembranes - refer to Section 02073.
.2 Common Excavating and Grading - refer to Section 02210.
1.3 QUALITY CONTROL
.1 The materials supplied shall be in accordance with the Specifications. Any proposed
variance or deviation shall be requested in writing prior to the commencement of
installation.
.2 GCL manufacturer must have produced at least one (1) million m2 of GCL, with at
least 800,000 m2 installed.
.3 The GCL installer must either have installed at least 50,000 m2 of GCL, or must
provide to the Engineer satisfactory evidence, through similar experience in the
installation of other types of geosynthetics, that the GCL will be installed in a
competent, professional manner.
.4 The Contractor or GCL installer shall provide a qualified QC Inspector for the GCL
installation. The QC Inspector shall be an individual or company who shall be
responsible for monitoring and documenting activities related to the Construction
Quality Control (CQC) of the GCL throughout installation. The QC Inspector shall
have provided CQC services for the installation of similar GCL for at least five (5)
completed projects totalling not less than 50,000 m2.
1.4 REFERENCE STANDARDS
.1 ASTM D6768 “Test Method for Grab Breaking Load and Elongation of Geotextiles”.
.2 ASTM D5084 “Hydraulic Conductivity of Saturated Porous Material Using a Flexible
Wall Permeameter”.
.3 ASTM D5321 “Determining the Coefficient of Soil and Geosynthetic or Geosynthetic
and Geosynthetic Friction by the Direct Shear Method”.
.4 ASTM D5887 “Test Method for Measurement of Index Flux Through Saturated
Geosynthetic Clay Liner Specimens Using a Flexible Wall Permeameter”.
Foothills Regional Services Commission Section 02594
Foothills Landfill Expansion - Cell 6 GEOSYNTHETIC CLAY LINER
2018-01/2017-3650.020 Page 2 of 7
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\02594.doc: January 29, 2018
.5 ASTM D5890 “Test Method for Swell Index of Clay Mineral Component of
Geosynthetic Clay Liners”.
.6 ASTM D5891 “Test Method for Fluid Loss of Clay component of Geosynthetic Clay
Liners”.
.7 ASTM D5993 “Test Method for Measuring Mass Per Unit of Geosynthetic Clay
Liners”.
.8 ASTM D6102 “Standard Guide for Installation of Geosynthetic Clay Liners”.
1.5 SUBMITTALS
.1 Submittals - refer to Section 01001 - General Requirements.
1.6 INSTALLATION CONTRACTOR
.1 Installation shall be performed under the constant supervision of an experienced GCL
supervisor who shall direct the laying and seaming of the liner.
.2 The GCL installer shall provide a written report on the completed installation which
shall certify that the liner is installed in accordance with the manufacturer’s
recommendations, is ready for operation and that the warranty is in effect from the
date of issue of the Completion Certificate. This report shall be signed by the GCL
installer.
.3 Provide information regarding the installer’s Field Installation Quality Assurance
program.
1.7 MEASUREMENT AND PAYMENT
.1 Measurement and Payment - refer to Section 01270.
1.8 PRODUCT DELIVERY, STORAGE AND HANDLING
.1 GCL rolls and bentonite bags shall be handled and stored in accordance with the
manufacturer’s recommendations.
.2 Supply a spreader bar approved by the manufacturer for the off loading of GCL rolls.
.3 Provision for storage area for GCL rolls shall be the responsibility of the Contractor.
A dedicated storage area shall be provided at the job-site that is away from high traffic
areas and is level, dry and well drained.
.4 Rolls shall be stored in a manner that prevents sliding or rolling from the stacks and
may be accomplished by the use of chock blocks or by use of the dunnage shipped
between rolls. Rolls should be stacked at a height no higher than that at which the
lifting apparatus can be safely handled (typically no higher than four (4)).
Foothills Regional Services Commission Section 02594
Foothills Landfill Expansion - Cell 6 GEOSYNTHETIC CLAY LINER
2018-01/2017-3650.020 Page 3 of 7
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\02594.doc: January 29, 2018
.5 All stored GCL materials and the accessory bentonite must be covered with a plastic
sheet or tarpaulin until installation.
.6 The integrity and legibility of the labels must be preserved during storage.
1.9 DISPOSAL
.1 Remove and dispose of all waste material off site at Contractor’s expense, unless
onsite disposal is provided by the Owner.
2 Products
2.1 DESCRIPTION
.1 The GCL shall consist of a layer of natural or granular sodium bentonite clay
encapsulated between two (2) non-woven geotextiles and shall comply with the
criteria listed in this section.
.2 A reinforced (double needlepunched) GCL must be used as designated by the
Engineer.
.3 Fibres from one (1) layer of the non-woven geotextile shall be needle punched through
the bentonite layer and into the other geotextile and shall be thermally bonded in place.
2.2 GEOSYNTHETIC CLAY LINER
.1 The GCL and their components shall have the properties shown in Section 2.2.2.
.2 GCL Material Properties:
Material Property ASTM TestMethod
M.A.R.V.1Reinforced GCL
Bentonite Swell Index 1 D5890 24 mL/2 g
Bentonite Fluid Loss 1 D5891 18 mL maximum
Bentonite Moisture 1 D4643 12% maximum
Bentonite Mass/Area 2 D5993 0.75 lbs/ft2 (3.6 kg/m2)
GCL Grab Strength 3 D6768 50 lbs/in (88 N/cm)
GCL Index Flux 4 D5887 1 x 10-8 m3/m2/sec maximum
GCL Peel Strength 3 D6496 3.5 lbs/in (6.1 N/cm)
GCL Permeability 4 D5887 5 x 10-9 cm/sec maximum
GCL Hydrated Internal Shear Strength 5 D6243500 psf (24 kPa) typ @
200 psf
Notes:
1. Bentonite property tests performed at a bentonite processing facility before shipment to GCL
production facilities.
2. Bentonite mass/area reported at 0 percent moisture content.
Foothills Regional Services Commission Section 02594
Foothills Landfill Expansion - Cell 6 GEOSYNTHETIC CLAY LINER
2018-01/2017-3650.020 Page 4 of 7
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\02594.doc: January 29, 2018
3. All tensile strength testing is performed in the machine direction using ASTM D 6768. All peel
strength testing is performed using ASTM D 6496. Upon request, tensile and peel results can be
reported per modified ASTM D 4632 using 4 inch grips.
4. Index flux and permeability testing with deaired distilled/deionized water at 80 psi (551kPa) cell
pressure, 77 psi (531 kPa) headwater pressure and 75 psi (517 kPa) tailwater pressure. Reported
value is equivalent to 925 gal/acre/day. This flux value is equivalent to a permeability of 5x10-9
cm/sec for typical GCL thickness. Actual flux values vary with field condition pressures. The
last twenty (20) weekly values prior the end of the production date of the supplied GCL may be
provided.
5. Peak values measured at 200 psf (10 kPa) normal stress for a specimen hydrated for forty-eight
(48) hours. Site-specific materials, GCL products, and test conditions must be used to verify
internal and interface strength of the proposed design.
.3 The minimum acceptable dimensions of full-size GCL panels shall be 4.6 m (15 feet)
in width and 45.7 m (150 feet) in length. Shorter rolls (those manufactured to 25 m
(82 feet), but less than a full length roll) may be supplied at a rate no greater than
two (2) rolls every 3000 m2 of GCL.
.4 A minimum 225 mm overlap guideline shall be imprinted on both edges of the upper
geotextile component of the GCL as a means for providing quality assurance of the
overlap dimension. Lines shall be printed in easily visible, nontoxic ink.
.5 The GCL shall be supplied in rolls with a rigid core whose diameter is sufficient to
facilitate handling. The core should be sufficiently strong to prevent collapse during
transit, handling and storage, etc.
.6 The GCL rolls shall meet the properties outlined in this specification.
.7 GCL material shall meet physical and chemical requirements as specified for the
intended operation.
.8 All rolls shall be labeled and bagged in moisture resistant plastic which is also
resistant to photo degradation by ultraviolet (UV) light.
2.3 PRODUCT QUALITY DOCUMENTATION
.1 The GCL manufacturer shall provide the Engineer or other designated party with
manufacturing QA/QC certifications for each shipment of GCL. The certifications
shall be signed by a responsible party employed by the GCL manufacturer and shall
include:
.1 Certificates of analysis for the bentonite clay used in GCL production
demonstrating compliance with the parameters shown in Section 2.2.2.
.2 Test data for geotextile materials used in GCL production, including at a
minimum, mass/area data and tensile test data demonstrating compliance with the
GCL manufacturer MQC plan.
.3 GCL lot and roll numbers supplied for the project (with corresponding shipping
information). Roll numbers shall include length, width and total weight of each roll.
Foothills Regional Services Commission Section 02594
Foothills Landfill Expansion - Cell 6 GEOSYNTHETIC CLAY LINER
2018-01/2017-3650.020 Page 5 of 7
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\02594.doc: January 29, 2018
.4 Manufacturer’s test data for the finished GCL production, including theparameters of bentonite mass/area, tensile strength and representative permeabilitydata demonstrating compliance with the performance parameters shown inSection 2.2.2.
2.4 ACCESSORY BENTONITE
.1 The granular bentonite or natural bentonite sealing compound used for seaming,penetration sealing and repairs shall be made from the same natural sodium bentoniteas used in the GCL and shall be as recommended by the GCL manufacturer.
.2 Use bentonite where recommended or required by manufacturer.
3 Execution3.1 PREPARATION
.1 The Contractor shall be responsible for preparing and maintaining the sub-grade in acondition suitable for installation of the GCL.
.2 The surface shall be smooth, firm and unyielding and free of:
.1 Vegetation.
.2 Construction debris.
.3 Sticks.
.4 Sharp rocks.
.5 Void spaces.
.6 Ice.
.7 Abrupt elevation changes.
.8 Standing water.
.9 Cracks larger than 6 mm (one-quarter inch) in width.
.10 Any other foreign matter that could contact the GCL.
.3 Immediately prior to GCL deployment, the sub-grade shall be final-graded to fill in allvoids or cracks and then smooth-rolled to provide the best practicable surface for theGCL. At completion of this activity, no wheel ruts, footprints or other irregularitiesshall exist in the sub-grade. Furthermore, all protrusions extending more than 12 mmfrom the surface shall either be removed, crushed or pushed into the surface with asmooth-drum compactor.
.4 At the top of sloped areas of the job-site, an anchor trench for the GCL shall beexcavated in accordance with the drawings. The trench shall be excavated andapproved by the QA Inspector prior to GCL placement. No loose soil shall be allowedat the bottom of the trench and no sharp corner or protrusions shall exist anywherewithin the trench.
Foothills Regional Services Commission Section 02594
Foothills Landfill Expansion - Cell 6 GEOSYNTHETIC CLAY LINER
2018-01/2017-3650.020 Page 6 of 7
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\02594.doc: January 29, 2018
3.2 METHOD OF PLACEMENT
.1 GCL rolls should be delivered to the working area of the site in their original
packaging. Immediately prior to deployment, the packaging should be carefully
removed without damaging the GCL. The orientation of the GCL should be in
accordance with the Engineer’s or manufacturer’s recommendations. The GCL shall
be installed such that the GCL overlap mark lines face up.
.2 Proper equipment, spreader-bar and core-bar assembly and/or a forklift with stinger
attachment shall be used during handling and deployment as per manufacturer’s
recommendations.
.3 Equipment which could damage the GCL shall not be allowed to travel directly on it.
If the installation equipment causes rutting of the sub-grade, the sub-grade must be
restored to its originally accepted condition before placement continues.
.4 Care must be taken to minimize the extent to which the GCL is dragged across the
sub-grade in order to avoid damage to the bottom surface of the GCL. A temporary
geosynthetic sub-grade covering, commonly known as a slip sheet or rub sheet, may be
used to reduce friction damage during placement.
.5 The GCL shall be placed so that seams are parallel to the direction of the slope.
Seams should be located at least 1 m from the toe and crest of slopes steeper than
4H:1V.
.6 Placement shall be from highest elevation to the lowest elevation to facilitate drainage
in the event of precipitation.
.7 All GCL panels should lie flat on the underlying surface, with no wrinkles or folds,
especially at the exposed edges of the panels. Panels shall be placed with non-woven
side up.
.8 Only as much GCL shall be deployed as can be covered with soil, a geomembrane, or
a temporary waterproof tarpaulin at the end of the working day.
.9 The GCL shall be placed in an anchor trench at the top of the slope as per the
drawings. The front edge of the trench should be rounded so as to eliminate any sharp
corners. Loose soil should be removed from the floor of the trench. The GCL should
cover the entire trench floor, but not the rear trench wall.
3.3 FIELD SEAMS
.1 The GCL seams are constructed by overlapping their adjacent edges. Care shall be
taken to ensure that the overlap zone is not contaminated with loose soil or other
debris. Supplemental bentonite is required in the overlap zone.
Foothills Regional Services Commission Section 02594
Foothills Landfill Expansion - Cell 6 GEOSYNTHETIC CLAY LINER
2018-01/2017-3650.020 Page 7 of 7
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\02594.doc: January 29, 2018
.2 The minimum dimension of the longitudinal overlap should be 225 mm. End-of-roll
overlapped seams should be similarly constructed, but the minimum overlap should
measure 600 mm.
.3 Seams at the ends of the panels should be constructed such that they are shingled in the
direction of the grade to prevent the potential for runoff flow to enter the overlap zone.
.4 Where the GCL product requires bentonite-enhanced seams as recommended by the
GCL manufacturer, bentonite-enhanced seams shall be constructed by overlapping
adjacent panels as instructed above, exposing the underlying edge and then applying a
continuous bead of granular sodium bentonite along a zone defined by the edge of the
underlying panel and the 150 mm line. The bentonite shall be applied at a minimum
application rate of 0.4 kg/m. Where bentonite-enhanced seams are not required by the
GCL product as recommended by the GCL manufacturer, GCL installer shall receive
approval from the Engineer.
3.4 DETAIL WORK
.1 The GCL shall be sealed around penetrations and embedded structures in accordance
with the drawings.
.2 Cutting the GCL should be performed using a sharp utility knife. Frequent blade
changes are required to avoid damage to the geotextile components of the GCL during
the cutting process.
3.5 DAMAGE REPAIR
.1 If the GCL is damaged (torn, puncture, perforated, etc.) during installation, it may be
possible to repair it by cutting a patch to fit over the damaged area. The patch shall be
obtained from a new GCL roll and shall be cut to size such that minimum overlap of
300 mm (12 inches) is achieved around all of the damaged area. Dry bentonite or
bentonite mastic should be applied around the damaged area prior to placement of the
patch. It may be desirable to use an adhesive to affix the patch in place so it is not
displaced during cover placement.
.2 Any solvent or adhesive in contact with the GCL must be approved by the
manufacturer.
END OF SECTION
Foothills Regional Services Commission Section 02690
Foothills Landfill Expansion - Cell 6 MISCELLANEOUS WORK
2018-01/2017-3650.020 Page 1 of 2
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\02690.doc: January 29, 2018
1 General1.1 WORK INCLUDED
.1 The following work is included, but not limited to:
.1 Supply and installation of precast concrete lock blocks.
.2 Supply and installation of RPE sand tubes.
1.2 RELATED WORK
.1 Quality Control - refer to Section 01450.
.2 Common Excavating and Grading - refer to Section 02210.
.3 Leachate Collection System - refer to Section 02411.
1.3 QUALITY CONTROL
.1 Quality Control - refer to Section 01450.
1.4 SUBMITTALS
.1 Submittals - refer to Section 01001 - General Requirements.
1.5 MEASUREMENT AND PAYMENT
.1 Measurement and Payment - refer to Section 01270.
2 Products2.1 PRECAST CONCRETE LOCK BLOCK
.1 Inland Concrete, LaFarge North America or as approved by the Engineer.
.2 Model: Standard lock blocks, select best condition possible.
.3 Size: 765 mm (30”) height, 765 mm (30”) width and 1525 mm (60”) length.
2.2 RPE SAND TUBES
.1 The sand tubes shall be premium grade-reinforced polyethylene (RPE) with a nominal
thickness of 0.3 mm (12 mil).
.2 The RPE tubes shall have a diameter of 300 mm.
Foothills Regional Services Commission Section 02690
Foothills Landfill Expansion - Cell 6 MISCELLANEOUS WORK
2018-01/2017-3650.020 Page 2 of 2
P:\20173650\02_Cell6_Exp\Engineering\07.00_Contract_Doc_Prep\02690.doc: January 29, 2018
3 Execution3.1 PRECAST CONCRETE LOCK BLOCKS
.1 Place precast concrete lock blocks as shown on the Drawings and as directed by
Engineer and as per the manufacturer recommendations.
.2 Provide final placement inspection to the QA Inspector’s satisfaction.
.3 The Engineer reserves the right to reject poorly finished or poor quality lock blocks.
3.2 RPE SAND TUBES
.1 Cut sand tubes into 1.5 m lengths.
.2 Fill sand tubes as per Drawings and tie ends closed using wire ties.
.3 Place sand tubes in 6 m intervals in locations as shown on the Drawings.
END OF SECTION