north shore connector tunnels and station shell light rail project
TRANSCRIPT
NORTH SHORE CONNECTORNORTH SHORE CONNECTOR
TUNNELS AND STATION SHELLTUNNELS AND STATION SHELLTUNNELS AND STATION SHELLTUNNELS AND STATION SHELLLIGHT RAIL PROJECTLIGHT RAIL PROJECT
PAUL ZICK, PE
NORTH SHORE CONSTRUCTORS JV
North Shore Connector Alignment
•• 7300 lf 7300 lf Extension to existing 25 mile systemExtension to existing 25 mile system
•• 18 Contracts18 Contracts
• $435 Million$435 Million
Project Location006006007007
Future- to Airport North ShoreNorth Shore
003003
006006007007
Airport North Shore North Shore Connector Connector Light Rail Light Rail E iE iExpansionExpansion
004 New Gateway Station004 New Gateway Station
Existing
EXISTING GATEWAY EXISTING GATEWAY STATIONSTATION
Existing Light Rail System
Project Team• Owner
–– Port Authority of Allegheny CountyPort Authority of Allegheny County
• Construction ManagerTriGoldTriGold–– TriGoldTriGold
• Jacobs Civil
• HDR
• Kwame
Project Team• Design Engineer
–– DMJMDMJM
• ContractorNorth Shore Constructors JVNorth Shore Constructors JV–– North Shore Constructors JVNorth Shore Constructors JV
• Obayashi Corp.
• Trumbull Corp.
What we are building
• Two Contracts
• Combined Contract Value - $156 500 000Combined Contract Value $156,500,000
• Time ––– NTPNTP Oct 2, 2006Oct 2, 2006
–– 003 Tunnels 003 Tunnels 1243 days1243 days Feb 26, 2010Feb 26, 2010
–– 006 Station / C&C006 Station / C&C 870 days870 days Feb 18, 2009Feb 18, 2009
Four Major Structure Types
• Boat Section – 340 lf–– SOE SOE -- Steel Soldier Piles and Wood LaggingSteel Soldier Piles and Wood LaggingSOSO Stee So d e es a d ood agg gStee So d e es a d ood agg g
• Cut and Cover – 1200 lfSOESOE C t D S il Mi i W ll (CDSM)C t D S il Mi i W ll (CDSM)–– SOE SOE -- Cement Deep Soil Mixing Wall (CDSM)Cement Deep Soil Mixing Wall (CDSM)
–– SOE SOE –– Cement Bentonite Wall (CB)Cement Bentonite Wall (CB)
• Top Down Construction - Station–– SOE SOE -- Slurry WallSlurry Wallyy
• Bored Tunnel – 2240 lfSOESOE P t C t S t l Li iP t C t S t l Li i–– SOE SOE -- Precast Concrete Segmental LiningPrecast Concrete Segmental Lining
Boat Section – Soldier pile and lagging• Excavation – 0 to 35 feet
• Soldier Piles and Wood Lagging
• Above or at the water table
• Deep Wells
Walls and Waterproofing
EXISTING SOILSEXISTING SOILS
Boat Section - SOE - Soldier Piles & Lagging
Soldier Piles andSoldier Piles andSoldier Piles and Soldier Piles and LaggingLagging
Cut & Cover / Launch Pit - CDSM WALLSI l il i d ithIn place soils mixed with Bentonite Slurry going down
Cement Slurry mixed going up
Insert Steel Soldier Piles
Cut & Cover – InstrumentationInstruments
Stain gauges
Weather
Tilt MetersTilt Meters
MotorizedMotorized Total Station
North Shore Station – Slurry WallsDESANDING
P iP iP i
DESANDING
Excavate Slot Primary Panel
Primary Panel
Primary Panel
SecondarySecondary Panel
North Side Station – Slurry walls
Concrete P iP iP iConcrete Primary Panel
Primary Panel
Primary Panel
Secondary Secondary
Rebar
Tremie pipeSecondary
PanelSecondary
Panel
Rebar
Excavate to Concourse
BackfillRoof Slab
Soldier Piles installed by building Soldier Piles installed by building contractorcontractor
CONCOURSE
Roof Slabcontractorcontractor
ROCK
Ground Improvement - Jet Grout
75% COVERAGE
Receiving Pit
100%
100% Coverage
6’ Around Tunnel6 Around Tunnel
Ground Improvement - Jet Grout – 75%HORNE BLGHORNE BLG.
MinimizeMinimize Angular Distortion due t dto ground loss
Bored Tunnels
Tunnel Tunnel Boring Boring M hiM hiMachine Machine Launch PitLaunch Pit
TBM Tunnels – 2200 lfNORTH SHORENORTH SHORE
Receiving Pit
SOUTH SHORESOUTH SHORE
Bored Tunnel SectionPRECASTPRECAST SEGMENTLININGLINING
Segment Lining 20’ inside diameter
CAST IN PLACEPLACE INVERT
TBM TunnelsSl P B l TBM (SPBTBM)• Slurry Pressure Balance TBM (SPBTBM)
–– Mixed Shield (Soft Ground and Rock)Mixed Shield (Soft Ground and Rock)
–– Working Pressure 3 barWorking Pressure 3 bar
Slurry TBM – 22’- 9” dia (6.92 m)24 17 i h t i• 24 -17 inch twin disk cutters
• 20 - Scrapers20 Scrapers
• Bucket lips
• 3 - Wear• 3 - Wear detection devices
• 0-2.7 rpm
• Left or Right
Cutter Head Drive
• Motors - 8 – 101 hp
• Total - 808 hp18
2Total 808 hp
• Variable Frequency Drive (VFD)
7
Drive (VFD)
• 480 v AC 4
3
5
6
• 0-2.7 rpm (l or r)
• Main bearing 8 5 ft
45
• Main bearing – 8.5 ft
TBM – Rear of Middle Shield• Propel Cylinders - 24
• Piston Diameter - 260 mm
• Rod Diameter - 220 mm
• Max Stroke - 1750 mmMax Stroke 1750 mm
• Advance force - 38227 kN (4,296 tn)
TBM Operation
Excavation Chamber
Working Chamber
Hydrostatic and Soil
Slurry In
and Soil Pressure
Slurry OutSlurry Out
Segment ErectorH d li l iH d li l i•• Hydraulic telescopic arm type Hydraulic telescopic arm type
•• 6 ranges of movement6 ranges of movement
•• TelescopeTelescope
R t tiR t ti•• RotationRotation
•• TravelTravel
•• Independent Independent Roll & YawRoll & Yaw–– Roll & YawRoll & Yaw
•• Controlled by joy stickControlled by joy stick
TBM Mining – Start North SideNORTH SHORESOUTH SHORE
Equitable
NORTH SHORESOUTH SHORE
Equitable Resources
Building
Soft Ground
Fluvioglacial Material• Gravel 40% - 57%
• Sand 50% - 38%
• Fines 10% - 5%
• Cobbles - up to 2’Cobbles up to 2
TBM Mining - River CrossingNORTH SHORESOUTH SHORE
Equitable
NORTH SHORESOUTH SHORE
Equitable Resources
Building
Mixed Face
River CrossingNORTH SHORESOUTH SHORE
Equitable
NORTH SHORESOUTH SHORE
Equitable Resources
Building
Rock
River Crossing
25 feet ALLEGHENY RIVER
RIVER SILTS (ALLUVIAL)22 feet
Top of Rock FLUVIOGLACIAL
( )22 feet
SILTY SHALE (5,400 SILTY SHALE (5,400 –– 11,800 psi)11,800 psi)
CLAYSTONE (200CLAYSTONE (200 4 400 psi)4 400 psi)COALCOAL
10 feet
CLAYSTONE (200CLAYSTONE (200-- 4,400 psi)4,400 psi)
SILTSTONE (3 400SILTSTONE (3 400--11 000 psi)11 000 psi)SILTSTONE (3,400SILTSTONE (3,400--11,000 psi)11,000 psi)
River CrossingNORTH SHORESOUTH SHORE
Equitable
NORTH SHORESOUTH SHORE
Equitable Resources
Building
Well Horne Blg.
Soft GroundJet Grout
Mixed Face
TBM Guidance System – VMT
Total StationTotal Station Operator’s DisplayOperator’s Display
80 mm
TargetTarget
Precast Segments – Universal RingSix pieces + Key4’ – Long
20’ ID
4 Long
Bolted
Two tapers 2-3/8 & 1-5/8
Segment Finishing Line•• Rotate Segments Rotate Segments ––
curve upcurve up
•• Repair SurfacesRepair Surfaces
•• Add GasketAdd Gasket
•• Add Joint PackingAdd Joint Packing
•• Stack in reverse order Stack in reverse order of installationof installation
Tunnel Infrastructure
50,000 CFM Ventilation50,000 CFM VentilationTemporary Temporary LightingLighting
2 - 4” water
8” Discharge
Walkwayy