Sector Gas Pipeline Project Type Natural Gas Transmission & Distribution Pipeline Project Title Project Management Consultancy (PMC) for Gas Transmission and Distribution Project Location From South Sumatera District to West Java District, Republic of Indonesia Client Pt. Perusahaan Gas Negara/ Japan International Cooperation Agency Project Period 2004 – 2010 Gas pipe line in between South Sumatera and West Java districts Problems addressed by the Project The domestic demand of energy in Indonesia had been drastically increased since 1986 and reached double in 1997. In order to stabilize the energy balance, Indonesian government set principal objectives in energy sector to minimize the domestic consumption of tradable fuels by substituting non-tradable alternatives such as surplus coal, geothermal energy, and natural gas. In the above circumstance, Indonesian government decided to utilize the natural gas from comparatively small size and scattered in South Sumatera to Java Island. The Indonesian government has requested Japanese government to provide financial aid for Gas Transmission Pipeline Project to install gas pipeline from South Sumatera to West Java by applying JICA ODA loans. Total length of gas pipe line is approximately 500 km from Sumatra to Jakarta across Selat Sunda having high ocean current speed. OC Global as a member of the consultant has been engaged with Pt. Perusahaan Gas Negara to provide project management consulting (PMC) services. Since the Project contains various fields of services, the knowledge of PMC is one of the key for smooth implementation. Also, the knowledge and experience of various steps as ruled by the guidelines for procurement under JICA ODA Loan was important. Service Provided Project Management Overall Project Management Engineering including design development, cost estimation and preparation of bid documents Procurement Assistance Construction Supervision Environmental Management and Monitoring Actual Project Works South Sumatera Onshore Transmission Pipeline: 32" x 270 km Sunda Strait Offshore Transmission Pipeline: 32" x 105 km West Java Onshore Transmission Pipeline: 24" x 129 km West Java Distribution Pipeline: 16" x 50 km and 8" x 1 km)

Upload: nguyentruc

Post on 12-Apr-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

Sector Gas Pipeline

Project Type Natural Gas Transmission & Distribution Pipeline

Project Title Project Management Consultancy (PMC) for Gas Transmission and Distribution Project

Location From South Sumatera District to West Java District, Republic of Indonesia

Client Pt. Perusahaan Gas Negara/ Japan International Cooperation Agency

Project Period 2004 – 2010

Gas pipe line in between South Sumatera and West Java districts

Problems addressed by the Project

The domestic demand of energy in Indonesia had been drastically increased since 1986 and reached double in 1997.

In order to stabilize the energy balance, Indonesian government set principal objectives in energy sector to minimize the domestic consumption of tradable fuels by substituting non-tradable alternatives such as surplus coal, geothermal energy, and natural gas.

In the above circumstance, Indonesian government decided to utilize the natural gas from comparatively small size and scattered in South Sumatera to Java Island. The Indonesian government has requested Japanese government to provide financial aid for Gas Transmission Pipeline Project to install gas pipeline from South Sumatera to West Java by applying JICA ODA loans.

Total length of gas pipe line is approximately 500 km from Sumatra to Jakarta across Selat Sunda having high ocean current speed.

OC Global as a member of the consultant has been engaged with Pt. Perusahaan Gas Negara to provide project management consulting (PMC) services. Since the Project contains various fields of services, the knowledge of PMC is one of the key for smooth implementation. Also, the knowledge and experience of various steps as ruled by the guidelines for procurement under JICA ODA Loan was important.

Service Provided

Project Management

Overall Project Management Engineering including design development, cost estimation and preparation of bid documents Procurement Assistance Construction Supervision Environmental Management and Monitoring

Actual Project Works

South Sumatera Onshore Transmission Pipeline: 32" x 270 km Sunda Strait Offshore Transmission Pipeline: 32" x 105 km West Java Onshore Transmission Pipeline: 24" x 129 km West Java Distribution Pipeline: 16" x 50 km and 8" x 1 km)