Duration: 3 hrs Max. Marks: 60 Date: 10/11/2014 Time: 2:00 pm to 5:00pm
Section A (Each Question carries 1 Mark)
1 of 30
WBS structure provides a _____________ view of the project.
Structural
Functional
Graphical
All the options are correct
2 of 30
Where do we define constraints (Basic date)?
WBS
Project definition
Network activity
All the options are correct
3 of 30
During the planning phase, we entered ---------------- for WBS elements.
Actual date
Basic date
Forecast date
Latest date
4 of 30
We can enter confirmation for internal activity by
CATS
Individual Confirmation
Collective Confirmation
All the options are correct
5 of 30
We can user CATS to enter confirmations for production orders. State whether the statement is true or false.
True
False
Page 1
6 of 30
What are the main features of WBS structure?
Planning
Budgeting
Execution (Actual Data)
All the options are correct
7 of 30
Confirmation is entered for
External Activity
Internal Activity
Cost Activity
Service Activity
8 of 30
The relationship between WBS and Activities is
1: N
N: 1
1: 1
None of the options are correct
9 of 30
General Cost activity has control key
PS01
PS02
PS03
PS04
10 of 30
Can we create Good Receipt for the material whose WBS is not Released? Yes or no.
Yes
No
11 of 30
Page 2
Billing plan can be maintained for
SD document
WBS element
Both SD document and WBS element
None of the options are correct
12 of 30
Revenue element for billing plan is mentioned in ________.
Planning profile
Budget profile
Network profile
Investment profile
13 of 30
Can we assign Account assignment to Project definition? Yes or no.
Yes
No
14 of 30
In project profile, we define
Network profile
Parameter for network profile
WBS scheduling profile
All the options are correct
15 of 30
______________is used to budget the investment project, and the budget values are then distributed within the project.
The investment program
Project profile
Planning profile
Page 3
Budget profile
16 of 30
What Operative indicators of WBS are flagged for Post of Revenue?
Planning Element
Account Assignment Element
Billing Element
All the options are correct
17 of 30
We can define budgeting currency in
Controlling area currency
Transition currency
Object currency
All the options are correct
18 of 30
Commitments are created through
Purchase order
Good receipts
Invoice receipts
Purchase requisition
19 of 30
For Preliminary procurement, we must use item category
L
N
M P
20 of 30
If we choose direct procurement with item category N, we can choose between two procurement types. They are:
Purchase requisition for the network
Purchase requisition for WBS
Third-party requisition for the network
Purchase requisition for external activity
Page 4
21 of 30
In work force planning, we can assign person to activity from
Work center
The project team
HR
All the options are correct
22 of 30
When we confirm activity
Capacity requirement increases
Reduce Capacity requirement, update actual date, and actual cost
Increases Capacity requirement, update actual dates, and actual cost
None of the options are correct
23 of 30
When you create a controlling area, the system automatically creates a plan ---------- for planned / actual value.
Version 0
Version 1
Both Version 0 and Version 1
None of the options are correct
24 of 30
How many settlement rules can be maintained for a WBS?
3 1 4 Any number
25 of 30
The link from various business transitions to the WBS element / activity are established by
Account assignment
Item category
Item group
Requirement class
26 of 30
Page 5
To stipulate that network activities are scheduled without taking account of WBS basic dates, you use
Profile for WBS scheduling
Profile for Network scheduling
Free scheduling
All the options are correct
27 of 30
Asset under construction is created automatically when WBS is released by setting ‘Manage Asset Under Construction’ indicator in
Settlement profile
Project profile
Investment Profile
Network profile
28 of 30
To create Purchase requisition with account assignment category Q
The assigned WBS in purchase requisition is always required to be defined as account assignment in the operative indicator of respective WBS
The assigned WBS need not be defined as account assignment in the operative indicator of respective WBS
The assigned WBS in purchase requisition is always required to be defined as planning as the operative indicator of respective WBS
None of the options are correct
29 of 30
Related to System and User status:
We can perform transition even if system status prohibits and user status allows
Both system and user status should allow, only then can we do the transition
We can perform the transition if system status allows even if user status prohibits
None of the options are correct
30 of 30
We can book actual cost at Project Definition Level
Page 6
Yes
No
Section B (Each Question carries 3 Marks, Answer any 10)
What is the organizational structure of PS module? Explain.
Page 7
32 How would you integrate SAP Project System with other SAP Modules? Explain.
MM:Purchasing: Purchase order, goods receipt for materials and services. Inventory Management: goods issue for reservationsSD: Delivery from Project, Milestone BillingPP: Reservation Generated from PS for independent Requirements (Reservations) can be met through Production order.CO: Internal activity allocation, assigned Internal orders, Settlement to CO ObjectFI: Down payments, payments and Settlement to assets , HR: Entry of work for persons, and posting as activity confirmation
33 Explain the following:a. Settlement Rules
Experience has shown that manual settlement rule maintenance for very complex project hierarchy structures is very time-consuming and brings with it the risk of inconsistent characteristics in settlement of customer projects to the profitability segment. The system uses automatic generation to create the settlement rule and parameters, in accordance with the strategy defined in the IMG. The type of planning decides which strategy applies to which object:Planning elementAccount assignment elementBilling elementWBS element with change of organization re the superior
WBS element
b. Relationship
Relationships determine the chronological sequence of the individual activities in a network (or standard network). You can enter additional data (such as a time interval or factory calendar) on the detail screen of each relationship.
In the network structure graphic, you can display relationships "time dependently", in order to illustrate the logical sequence of events. By default, all relationships are displayed as FS relationships in the network structure graphic.
FS SS FF SF
c. Milestone Billing
Milestones are an event with a special meaning. It can be used in a project to designate significant events or the completion of a project phase.
Page 9
These are used in the Project System:
For progress analysis
As release stop indicators
To trigger predefined functions and workflow tasks
Function
In milestone billing, the following functions are carried out at item level:
Determining billing document value on a percentage basis
Dates at header level are copied from all item billing plans assigned to that header. When you make changes at header level (e.g. new billing dates or changes to percentage rates), the related items are automatically changed accordingly. The system does not allow you to make changes at item level.
34 Explain the following operative indicatorsa. Acct. Assignment Element
In assembly processing the cost object is either the sales order or the project (WBS element). In most cases you use the project as the cost object. However, if you do not want to work with projects, but want to use networks, you can use the sales order as the cost object.
b. Planning Element
This indicator controls whether a cost planning is possible only in those WBS elements which were defined as planning elements.If you do not set this indicator, you can carry out cost planning in any WBS element.If you check this indicator in the planning profile system will allow you to do planning only for the WBS elements that have the Planning Element indicator ticked.Even the F1 help for the Planning Element indicator in a WBS element states the same. Do revert if you come across something different.
c. Billing Element
Element on which Revenues can be planned and posted.
35 Explain the Following:a. Internally Processed Activity
You must enter work data for an activity so that the system can plan capacities for a project and calculate costs for activities. You need to specify the amount of work involved and the work center that is to perform the work.
Work is the output to be provided by machines or personnel in order to complete an activity.
Page 10
b. Externally Processed Activity
You can create externally processed activities in your network - for example, if you award the contract for designing a machine to an external design agency.
The system takes the data in the activity and creates a purchase requisition which is processed by the purchasing department. For external processing purposes, you can refer to data from the purchasing department - for example, to a purchasing info record. This contains the prices and delivery times applying to external processing.
c. Service Activity
A service activity triggers a purchasing process similar to the kind triggered by an externally processed activity, but can also contain a hierarchy of planned services to be purchased from the vendor and value limits for unplanned services.
The "goods receipt" of services involves two steps:
Entry of services performed
Acceptance of services performed.
For service activities, you can maintain service specifications for various services to be provided by the service provider (planned services). You can use value limits to restrict services that the service provider has not planned.
You can create the link to the MM Service component (MM-SRV) by means of service activities.
36 Write short notea. Project Planning Board
The project planning board has a central position in the Project System. It simplifies planning and controlling projects. The project planning board allows integrated processing of your project, giving you a graphic overview of the project objects. In the graphic interface you can create, edit and evaluate all the data for a project. You can change the appearance of the project planning board to suit your individual needs and taste.
With the project planning board You obtain an overview about the hierarchy and progress of
your project You can see interrelationships in the organization and the
schedule. You can access all the important data in your project, and
for example
Page 11
b. Capacity Planning
The economic use of resources is an objective for many areas of a company. The component "Capacity Planning" is available in the R/3 System for this purpose.Capacity planning supports planning in all its phases:
long-term rough-cut planning medium-term planning short-term detailed planning
c. Scheduling
In the project system you can plan various date types, such as basic dates and forecast dates. In this process, you plan basic dates only. To do this, you copy the scheduled dates of the activities into the dates of the WBS elements.
To carry out the scheduling, you call up the planning board from the Project Builder. The project planning board provides you with an overview of the hierarchy and the sequence of your project.It is subdivided into two areas:A table area with information about the objects (left side)A graphical representation of the scheduling situation
(right side)You can change the size of the individual areas by dragging the separator lines.
37 Which parameters to be configured under project profile?38 What is settlement?
Costs and revenues are collected in projects only temporarily. They are settled to one or more receivers as part of period-end processing.You use settlement to:
Capitalize the balance from results analysis which is capable of capitalization in the balance sheet.
Obtain detailed data in results analysis for enterprise controlling. In capital-investment measures, to settle the charge to assets under
construction which can or must be capitalized. Include actual costs from the project in actual price calculation in Cost
Center Accounting.IntegrationYou cannot transfer settlement rules to simulation versions or maintain them there.You use the settlement profile to define the following for actual costs:
Must be settled in full Can be settled Must not be settled
Page 12
Depending on the settings in the settlement profile, you must settle the costs of an object in full before you can archive it.
39 Which parameters we configure under settlement profile?40 What is RRB? Explain with example
Any company who bills there customer according to resources consumed
41 What is scheduling?
In the project system you can plan various date types, such as basic dates and forecast dates. In this process, you plan basic dates only. To do this, you copy the scheduled dates of the activities into the dates of the WBS elements.
To carry out the scheduling, you call up the planning board from the Project Builder. The project planning board provides you with an overview of the hierarchy and the sequence of your project.It is subdivided into two areas:A table area with information about the objects (left side)A graphical representation of the scheduling situation
(right side)You can change the size of the individual areas by dragging the separator lines.
42 Explain difference between Budgeting and Planning?
Page 13
43 What are the types of cost planning?
Planning-1) Easy cost planning
2) Manual Cost Planning (WBS)- a)Detailed planning
b)Unit cost
c) hierarchial cost planning
3) Automatic costing in Network/Activities
Easy Cost Planning
The Easy Cost Planning tool enables you to plan costs at WBS level, based on quantities and characteristics. ECP can also be used for Internal Orders & Appropriation Requests.
You use it to create quantity structures (possibly temporary) for the cost calculation, starting from the project structure. The system valuates your entries using the prices and rates defined in the system, then distributes the costs in line with the basic dates for the respective WBS elements.
Unit Costing
The Easy Cost Planning tool enables you to plan costs at WBS level, based on quantities and characteristics. ECP can also be used for Internal Orders & Appropriation Requests.
You use it to create quantity structures (possibly temporary) for the cost calculation, starting from the project structure. The system valuates your entries using the prices and rates defined in the system, then distributes the costs in line with the basic dates for the respective WBS elements.
44 What is difference between Project System and product?45 Explain the project phases?