university of stuttgart fib th - unile.itfibtg45.dii.unile.it/minutes of the meetings/minutes oct...
TRANSCRIPT
University of StuttgartInstitute of Construction Materials
Behavior and Design of Post-Installed Rebar Connections
fib Task Group 4.5 „Bond Models“– 6th Meeting, October 15 - 16, 2004, Edinburgh, UK –
Isabelle SimonsInstitute of Construction Materials,University of Stuttgart, Germany
University of StuttgartInstitute of Construction Materials
����������������
lv
Connecting new and existing buildings usingpost-installed rebars
Strengthening with post-installed rebar connections
New building
Existing BuildingPost-installedrebars
Adding new columns Thicken columns
Applications with Post-Installed Rebar Connections
Source: 1) (Hilti)
1)
1)
University of StuttgartInstitute of Construction Materials
Cast-in-place Post-installedrebar mortar concreterebar concrete
Source: 1) Kunz, Cook, Fuchs, Spieth(1998)
1)
Load Transfer Mechanism
University of StuttgartInstitute of Construction Materials
Experimental Studies – Influencing Parameters
Geometry • Embedment Depth (hef=10ds, hef>20ds)• Concrete Cover / Edge Distance• Bar Spacing• Bar Diameter• Drilling Diameter in Relation to Bar Diameter
Material • Mortar (Hybrid, Epoxy, Cement)• Concrete• Cracks in Concrete
Environment • Temperature / Fire• Chemical Influences• Freeze-Thaw Cycles
Application • Injection• Drilling• Installation at Extreme Temperatures• Curing Time
Load • Static• Fatigue Loading• Monotonic Loading• Cyclic Loading
University of StuttgartInstitute of Construction Materials
Experimental Studies – Influencing Parameters
Geometry • Embedment Depth (hef=10ds, hef>20ds)• Concrete Cover / Edge Distance• Bar Spacing• Bar Diameter• Drilling Diameter in Relation to Bar Diameter
Material • Mortar (Hybrid, Epoxy, Cement)• Concrete• Cracks in Concrete
Environment • Temperature / Fire• Chemical Influences• Freeze-Thaw Cycles
Application • Injection• Drilling• Installation at Extreme Temperatures• Curing Time
Load • Static• Fatigue Loading• Monotonic Loading• Cyclic Loading
???
University of StuttgartInstitute of Construction Materials
The influencing parameters were examined in the laboratory at the University of Stuttgart and are illustrated in the followingslides.
Is the cement system suitable for post-installed rebars?
The cement is delivered in a 25kg sack. Therefore the cement must be mixed on-site using a special mixerand the components must be carefully weighed!!
The following points must be taken into account according to themanufacturers instructions:
- the borehole must be cleaned- the borehole must be moist; watering at least 6h.- the mixture contains 12% water- the mixture must be agitated at least 5min.
Test Program – Cement System
University of StuttgartInstitute of Construction Materials
Installation Procedure of Cement Systems
Mixing Pour Compaction Installation
Cleaning (hand) Cleaning (machine) Pre-wetting
The process excludes horizontal and over head installations!The installation process is time consuming and complex.
University of StuttgartInstitute of Construction Materials
Experimental Results – Cement Systems – Cleaning Method
0
5
10
15
20
25
30
0 1 2 3 4 5 6 7 8 9 10Verschiebung v [mm]
Ver
bund
span
nung
τ [N
/mm
²]
Reinigung H1
Reinigung H2
Reinigung M1
Bohrlochbewäs. 6h cc , s
τu
τu
τu
Displacement [mm]
Bon
d St
ress
[N/m
m²]
3xblowing, 3xbrushing, 3xblowing (Machine)
1xblowing (Hand)
1xblowing, 1xbrushing, 1xblowing (Hand)
1. Cleaning2. Moisture 6h3. Installation
C20/25ds=20 mmhef=200 mm
University of StuttgartInstitute of Construction Materials
Experimental Results – Cement Systems – Moisture
0
2
4
6
8
10
12
14
16
18
20
0 2 4 6 8 10
Verschiebung [mm]
Verb
unds
pann
ung
[N/m
m2 ]
Bef.: trocken
Bef.: ~ 6h
Bef.: ~24h
Displacement [mm]
Bon
d St
ress
[N/m
m²]
1. Cleaning (1xblowing (Hand))2. Moisture 6h3. Installation
dry concrete
6h
24h
Installation of rebars in dry concrete not realisable.
C20/25ds=20 mmhef=200 mm
University of StuttgartInstitute of Construction Materials
0
2
4
6
8
10
12
14
0 1 2 3 4 5 6 7 8 9 10Verschiebung v [mm]
Ver
bund
span
nung
τ [N
/mm
²]
tcure = 2h tcure = 6h tcure = 18h
Reinigung H1 13% H2O
Reibungsanteil
Haftanteil
Displacement [mm]
Bon
d St
ress
[N/m
m²]
Experimental Results – Cement Systems – Curing Time
1. Cleaning (1xblowing (Hand))2. Moisture 6h3. Installation
Bond
Friction
The system is highly influenced by the curing time. Curing time according to manufacturers instructions is 3 h!!
University of StuttgartInstitute of Construction Materials
0
2
4
6
8
10
12
14
16
0 1 2 3 4 5 6 7 8 9 10Verschiebung v [mm]
Ver
bund
span
nung
τ [N
/mm
²]
12% H2O ; tcure = 20h 30min
13% H2O ; tcure = 18h 30min
Reinigung H1
Displacement [mm]
Bon
d St
ress
[N/m
m²]
Experimental Results – Cement Systems – Mixture Process
The amount of water in the mixture process influences thebond stress (and the mixture process).
1. Cleaning (1xblowing (Hand))2. Moisture 6h3. Installation
University of StuttgartInstitute of Construction Materials
Experimental Studies – Influencing Parameters
Geometry • Embedment Depth (hef=10ds, hef>20ds)• Concrete Cover / Edge Distance• Bar Spacing• Bar Diameter• Drilling Diameter in Relation to Bar Diameter
Material • Mortar (Hybrid, Epoxy, Cement)• Concrete• Cracks in Concrete
Environment • Temperature / Fire• Chemical Influences• Freeze-Thaw Cycles
Application • Injection• Drilling• Installation at Extreme Temperatures• Curing Time
Load • Static• Fatigue Loading• Monotonic Loading• Cyclic Loading
???
University of StuttgartInstitute of Construction Materials
Montage
Post-installed rebars
1. Hairline
2. Drilling
3. Rebar Installation
4. Crack Opening
1.
2. 3. 4.
Experimental Investigations – Installation Cracked Concrete
3.
University of StuttgartInstitute of Construction Materials
Experimental Investigations – Cracked Concrete
crack
crackconcrete
rebar
Crack
Destroys bondbetween
mortar and concrete
Reduction of bond strength (~50%)
University of StuttgartInstitute of Construction Materials
Hydraulikzylinder
Kugelkalotte
Stahlplatte Teflon
Prüfkörper
Beton-würfel
Wegaufnehmer
Rissaufnehmer
Stahlkeil
Kraftmessdose
Hydraulikzylinder
Kugelkalotte
Stahlplatte Teflon
Prüfkörper
Beton-würfel
Wegaufnehmer
Rissaufnehmer
Stahlkeil
Kraftmessdose
Experimental Investigations – Cracked Concrete
CalloteLoad cell
Hydrauliccylinder
LVDT
Steel Plate
Concrete Block
Slab
wedge
Crack measurementdevice
University of StuttgartInstitute of Construction Materials
Failure Mode Pullout – Influence of Cracked Concrete
0,00
0,25
0,50
0,75
1,00
1,25
0,0 0,2 0,4 0,6
M8M12M16
Rissbreite [mm]
Nu (gerissen) / Nu (ungerissen) [-]
0,00
0,25
0,50
0,75
1,00
1,25
0 0,2 0,4 0,6
hef = 100 mmhef = 200 mm
Rissbreite [mm]
ßw = 35 - 37 N/mm2
ds = 16 mm
Nu(gerissen) / Nu(ungerissen) [-]
Bonded anchorsMeszaros (2002)
Cast-in-placeEibl/Idda/Lucero-Climas (1997)
Crack Width [mm] Crack Width [mm]
Nu (cracked) / Nu (uncracked) [-] Nu (cracked) / Nu (uncracked) [-]
University of StuttgartInstitute of Construction Materials
0
5
10
15
20
-0,1 0 0,1 0,2 0,3 0,4 0,5 0,6 0,7 0,8 0,9
Rissbreite w [mm]
Ver
bund
fest
igke
it τ u
[N/m
m²]
Pagel V2/10
fcc = 60,9 N/mm²
fcc = 37-39,3 N/mm²
Crack Width [mm]
Bon
d St
reng
th[N
/mm
²]
Experimental Results – Cement Systems - Cracked Concrete
3xblowing, 3xbrushing, 3xblowing
University of StuttgartInstitute of Construction Materials
0
2
4
6
8
10
12
14
16
18
20
0 1 2 3 4 5 6 7 8 9 10Verschiebung v [mm]
Ver
bund
span
nung
τ [N
/mm
²]
w = 0,0 mm
w = 0,1 mm
w = 0,3 mm
w = 0,5 mm
fcc = 37-39,3 N/mm² lv = 200 mm
Bon
d St
ress
[N/m
m²]
Reduction of bond strength ~50% independent of crack width(w=0,1mm; 0,3mm, 0,5 mm)
Displacement [mm]
Experimental Results – Cement Systems - Cracked Concrete
University of StuttgartInstitute of Construction Materials
Experimental Studies – Influencing Parameters
Geometry • Embedment Depth (hef=10ds, hef>20ds)• Concrete Cover / Edge Distance• Bar Spacing• Bar Diameter• Drilling Diameter in Relation to Bar Diameter
Material • Mortar (Hybrid, Epoxy, Cement)• Concrete• Cracks in Concrete (Hybrid, Epoxy)
Environment • Temperature / Fire• Chemical Influences• Freeze-Thaw Cycles
Application • Injection• Drilling• Installation at Extreme Temperatures• Curing Time
Load • Static• Fatigue Loading• Monotonic Loading• Cyclic Loading
???
University of StuttgartInstitute of Construction Materials
Suitability of Post-installed Rebar Systems
Bond behavior of post-installed rebars should be comparable to cast-in-place rebars taking into account influence of
- sensitivity to installation
- concrete cracking parallel to bars
- temperature
- durability of mortar
Mortar should ensure corrosion resistance of reinforcing bars
Suitability of post-installed rebar systems should be checkedby tests at independent institutes
University of StuttgartInstitute of Construction Materials
Design Concept for Post-Installed Rebar Connections
Simplified Design Concept: Design according to the rules for cast-in-place deformed rebars based on standards for reinforced concrete(e.g. Eurocode 2)
Restrictions:
Larger minimum concrete cover (depending on drilling method)
Larger minimum clear bar spacing (depending on drilling method)
Special requirements for fire safety (depending on system)
Limited design compression strength (depending on system)
Installation by skilled (certified) workers
University of StuttgartInstitute of Construction Materials
Summary
• With suitable injection systems the bond behavior of post-installedrebars is similar to cast-in-place rebars.
• Connections with post-installed rebars are allowed when they areallowed for straight cast-in-place rebars.
• With suitable injection systems the design of connections with post-installed rebars can be done as for deformed cast-in-place rebarsaccording to codes for reinforced concrete (e.g. EC 2).
• The suitability of an injection system should be checked by an independent institute.
• Test criteria and acceptance criteria are required