مشروع المساحة2
DESCRIPTION
bookTRANSCRIPT
The Islamic university _ Gaza
College of Engineering
Department of Civil Engineering
Surveying (2)
Project:-
Vertical Design Of
Ahmed Abdel Aziz Street
Designed By:-
1- Osama Kh. Abu Eltayf 2- Mohammed H. Shehada 3- Omar A. Falyona 4- Mustafa El Dalo
Submitted to:-
Eng. Ramy El-Faqawe
(2011 ــــ 2010)
1- Introduction :
Route surveying is comprised of all survey operations required for design and construction of engineering works such as highways, pipelines, canals, or railroads. At Caltrans a route surveying system is generally associated with highway design and construction.
A route surveying system usually contains four separate but interrelated processes:
• Reconnaissance and planning
• Works design
• Right of way acquisition
• Construction of works
HORIZONTAL AND VERTICAL CURVES
The center line of a road consists of series of straight lines interconnected by curves
that are used to change the alignment, direction, or slope of the road. Those curves
that change the alignment or direction are known as horizontal curves, and those
that change the slope are vertical curves.
HORIZONTAL CURVES
When a highway changes horizontal direction, making the point where it changes
direction a point of intersection between two straight lines is not feasible. The
change in direction would be too abrupt for the safety of modem, high-speed
vehicles. It is therefore necessary to interpose a curve between the straight lines.
The straight lines of a road are called tangents because the lines are tangent to the
curves used to change direction.
In practically all modem highways, the curves are circular curves; that is, curves that
form circular arcs. The smaller the radius of a circular curve, the sharper the curve.
For modern, high-speed highways, the curves must be flat, rather than sharp. That
means they must be large-radius curves.
In highway work, the curves needed for the location or improvement of small
secondary roads may be worked out in the field. Usually, however, the horizontal
curves are computed after the route has been selected, the field surveys have been
done, and the survey base line and necessary topographic features have been
plotted. In urban work, the curves of streets are designed as an integral part of the
Preliminary and final layouts, which are usually done on a topographic map. In
highway work, the road itself is the end result and the purpose of the design. But in
urban work, the streets and their curves are of secondary importance; the best use
of the building sites is of primary importance.
VERTICAL CURVES
In addition to horizontal curves that go to the right or left, roads also have vertical curves that go up or down. Vertical curves at a crest or the top of a hill are called summit curves, or over verticals. Vertical curves at the bottom of a hill or dip are called sag curves, or under verticals.
GRADES
Vertical curves are used to connect stretches of road that go up or down at a constant slope. These lines of constant slope are called grade tangents The rate of slope is called the gradient, or simply the grade. (Do not confuse this use of the term grade with other meanings, such as the design elevation of a finished surface at a given point or the actual elevation of the existing ground at a given point.) Grades that ascend in the direction of the stationing are designated as plus; those that descend in the direction of the stationing are designated as minus. Grades are measured in terms of percent; that is, the number of feet of rise or fall in a 100-foot horizontal stretch of the road.
After the location of a road has been determined and the necessary fieldwork has been obtained, the engineer designs or fixes (sets) the grades. A number of factors are considered, including the intended use and importance of the road and the existing topography. If a road is too steep, the comfort and safety of the users and fuel consumption of the vehicles will be adversely affected; therefore, the design criteria will specify maximum grades. Typical maximum grades are a 4-percent desired maximum and a 6-percent absolute maximum for a primary road. (The 6 percent means, as indicated before, a 6-foot rise for each 100 feet ahead on the road.) For a secondary road or a major street, the maximum grades might be a 5-percent desired and an 8-percent absolute maximum; and for a tertiary road or a secondary street, an 8-percent desired and a 10-percent (or perhaps a 12-percent) absolute maximum. Conditions may sometimes demand that grades or ramps, driveways, or short access streets go as high as 20 percent. The engineer must also consider minimum grades. A Street with curb and gutter must have enough falls so that the storm water will drain to the inlets; 0.5 percent is a typical minimum grade for curb and gutter (that is, 1/2 foot minimum fall for each 100 feet ahead). For roads with side ditches, the desired minimum grade might be 1 percent; but since ditches may slope at a grade different from the pavement, a road may be designed with a zero-percent grade. Zero-percent grades are not unusual, particularly through plains or tidewater areas. Another factor considered in designing the finished profile of a road is the earthwork balance; that is, the grades should be set so that all the soil cut off of the hills may be economically hauled to fill in the low areas. In the design of urban streets, the best use of the building sites next to the street will generally be more important than seeking an earthwork balance.
2- Methodology: 1. First of all to make a longitudinal section you must marking all the points
which needed to be studied , by opening the tape for a fixed distance(20 m) then mark the point "it is recommended that the distance between the points be equal each other to make the calculation easier ".
2. After marking the points, setup the level in a suitable place "covers number of points".
3. After leveling the level, take the reading of the staff to each point and tabulate the readings.
4. If the level did not cover all of the points you must move it to another station and continue taking the reading (Remark:- the first reading taken at every instrument station called back sight (BS),the last reading taken at every instrument station is called foresight(FS) , the point which take the two reading is called turning point).
5. After we take all the measurements we make a table and calculate the elevation of the points by rise and fall methods or by HI method.
A. Collection Data's
Checks:-
- 4)=(4 FS #.of = BS #.of
- 45.1 FirstLast RLRLFallRiseFSBS
Notes RL Fall Rise FS IS BS Distance Station
START 21.45
3.77 0 1
21.56
0.11
3.66
20 2
21.66
0.1
3.56
40 3
21.76
0.1
3.46
60 4
21.94
0.18
3.28
80 5
22.31
0.37
2.91
100 6
23.05
0.74
2.17
120 7
23.46
0.41
1.76
140 8
23.7
0.24
1.52
160 9
23.67 0.03
1.55
180 10
23.76
0.09
1.46
200 11
TB 24.47
0.71 0.75
3.21 220 12
25.4
0.93
2.28
240 13
26.2
0.8
1.48
260 14
26.69
0.49
0.99
280 15
TB/ISP 26.98
0.29 0.7
2.54 300 16
27.78
0.8
1.74
320 17
27.7 0.08
1.82
340 18
27.16 0.54
2.36
360 19
TB 26.24 0.92
3.28
0.41 380 20
25.31 0.93
1.34
400 21
BM 25 0.31
1.65
24.79 0.21
1.86
420 22
24.01 0.78
2.64
440 23
23.46 0.55
3.19
460 24
END 22.9 0.56
3.75
480 25
4.91 6.36 8.48
9.93
SUM
B. Draw the profile The drawing of profile is attached in the end of the project
C. Slope Calculation:
%5.3%100150
81.2756.223
%76.2%100150
67.2381.272
%26.1%100180
21.45-23.67 = 1 Slope
Slope
Slope
D. Design Level : - Calculations
m
SgDLDLpo
m
SgDLDLpo
m
SgDLDLpo
exampleFor
SgDLDL poane
36.25)70035.0(81.27
)5(int
33.25)600276.0(67.23
)12(int
66.22)1000126.0(4.21
)5(int
:
320
212
15
int
)(13.066.2479.24)21(int
)(35.066.2231.22)5(int
)(
)(
CutmPo
FillmPo
ExampleFor
FILLDLGL
CUTDLGL
E. Design of vertical curve:
1- Calculate the side distance (S) = )(2
2
ifg
vtv
Where:
V= design velocity = 70 km/hr. = 19.44m/s
t= perception and reaction time = 2.5 s
g = gravity = 9.81 m/s
f = coefficient of friction of road surface = 0.35
I = gradient = positive upwards or negative downwards
2- After knowing the length of the curve we calculate the distance between VPI and mid –
point of the curve
mh
CurveSummitFor
mh
CurveSagFor
LAh
313.08
400626.0
:
075.08
40015.0
:
8
)(40
)(395.26405.105.10626.
229.1992.
)(98.29505.105.12
29.1990626.0.
22.
2.
29.199)0276.035.0(81.92
44.195.244.192
400
333.149015.0
204035.22.12042.
)(67.74204035.22.1
204015.0.
035.22.12.
035.22.1.
204)0126.35.0(81.92
44.195.244.192
2
2
2
2
2
2
2
min
2
2
2
edapproximatisdatasTheaccuratenotnscalculatioTheBecausemLLet
wrongmLLSb
wrongmLLSa
hhA
SLLSb
hh
SALLSacurveofLength
mS
CurveSummitFor
mLSomL
mLLSb
wrongmLLSa
A
SSLLSb
S
SALLSacurveofLength
mS
CurveSagFor
oe
oe
Form similarity of triangles we can find the other point of the vertical curve
VPT VPI Sag curve VPC
20m 20m
Y X
075.020
YX
0.01875 5
0.0375 10
0.05625 15
0.075 20
Remark: we apply the points on both sides of the vertical curve
VPTVPIsametheandVPIVPC
VPI Summit curve VPT VPC
20m 20m
Y X
313.020
YX
0.07825 5
0.1565 10
0.23475 15
0.313 20
Remark: we apply the points on both sides of the vertical curve
VPTVPIsametheandVPIVPC
3- Design Criteria:
Min slope =0.5% Max slope = 7% Difference between any tow successive gradient >0.5 , (g2-g1) >0.5:
mfillorcut
mFillCut
slopes
1maxmax
5.0
max,min
Types of gradients:
Falling Gradients Rising Gradients
-g +g
4- Results and Tables:
8 7 6 5 4 3 2 1 0 Station
160 140 120 100 80 60 40 20 0 Distance
23.7 23.46 23.05 22.31 21.94 21.76 21.66 21.56 21.45 GL
23.42 23.17 22.91 22.66 22.41 22.16 21.91 21.65 21.4 DL
0.28 0.29 0.14 0 0 0 0 0 0.05 Cut
0 0 0 0.35 0.47 0.4 0.25 0.09 0 Fill
24 23 22 21 20 19 18 17
480 460 440 420 400 380 360 340
22.9 23.46 24.01 24.79 25.31 26.24 27.16 27.7
22.56 23.26 23.96 24.66 25.36 26.06 26.76 27.46
0.34 0.2 0.05 0.13 0 0.18 0.4 0.24
0 0 0 0 0.05 0 0 0
mFillCut
mFill
mCut
83.037.22.3
37.2
2.3
5- Comments:
The length of the vertical curves (Sag & Summit) can not be measured from the
equations, the answers is not accepted because the design velocity we taken and other
factors not accurate, so we assume the length of curves (Sag & Summit) equal 40m as
the supervisor engineering. Other calculation approximately accurate.
6- Recommendations:
We should take the data's accurate such that (Design velocity, Friction coefficient of
road surface) in order to achieve the correct results and corrected design.
7- Maps:
The drawing is attached in the end of the project
16 15 14 13 12 11 10 9
320 300 280 260 240 220 200 180
27.78 26.98 26.69 26.2 25.4 24.47 23.76 23.67
27.53 26.98 26.43 25.88 25.33 24.77 24.22 23.67
0.25 0 0.26 0.32 0.07 0 0 0
0 0 0 0 0 0.3 0.46 0