  • Internal Only

    TK Service Department

    Jan 31st, 2011

    Site Engineer Training Course

    Site Acquisition

  • Internal Only

    2011-5-19 2

    Learning Objectives

    2011-5-19 2

    From this course you will learn:

    All the actions by the site engineer in the site

    acquisition process;

    Basic process and key actions of site acquisition;

    Key points of each action;

    Input and output reports;

    Final deliverables and standards.

  • Internal Only

    Site Acquisition - Action List for Site Engineers

    Site Acquisition Plan & Preparation

    Initial Site Survey (SA)

    Lease Agreement & Permits

    Content

  • Internal Only

    No. Site Engineer Action Illustration

    1 Hand over SA

    2Review engineering requirement

    & plan

    3 SA kick-off meeting

    4 SA training

    5 Review initial site survey

    6 Prioritize identified candidates

    7 Review SA negotiation results

    8 SA & documents filing

    Site Engineer Action List

    Illustration

    CP

    KCP

    100%on-site check

    10%on-site check

    Document check

  • Internal Only

    Frequently Used Abbreviations

    Abbreviation

    Key Control Point

    Civil Work Site EngineerCSE

    SUB

    LOS

    PR

    PO

    SA

    CP

    KCP

    Subcontractor

    Line of Sight

    Purchase Request

    Site Acquisition

    Control Point

    Purchase Order

    CER

    SAR

    Candidate Site Evaluation Report

    Site Acquisition Report

    LA

    BP

    Lease Agreement

    Building Permits

  • Internal Only

    Site Acquisition - Action List for Site Engineers

    Site Acquisition Plan & Preparation

    Action 1: SA Handover Meeting

    Action 2: Review Engineering Requirement & Plan

    Action 3: SA Kick-off Meeting

    Initial Site Survey (SA)

    Lease Agreement & Permits

    Content

  • Internal Only

    Site acquisition plan &

    preparation

    SA Plan & Preparation

    From

    Half a day Half a day 1day Half a day Half a day

    Develop

    SA planSA Handover

    meeting

    Members/vehicles/

    tools preparation

    Develop SA

    detailed plan

    Review engineering

    requirement & planSA kick-

    off meeting

    Action 1 Action 2 Action 3

    Blue: Site Engineer

    Orange: Subcontractor

    CP KCP

    Level 4

    Level 5Site acquisition plan &

    preparation Initial site survey (SA) Lease agreement &

    permits

    Site

    acquisit

    ion

    Site

    surveySite

    design

    Material

    delivery

    Civil

    work

    TE installat

    ion

    Site integra

    tion

    Network

    optimiza

    tion

    PATNetwork

    planning

  • Internal Only

    Output - All kinds of template

    1. Meeting attended by SA Manager, CSE, PDT and SA subcontractors.

    2. The meeting shall determine SOW, workflow, cooperation requirements, document template,

    lease agreement template, etc.

    3. CSE should control the availability of SA subcontractor , focus on the meeting content, define all

    workflows and document templates.

    Key action Documents & key points Work day

    SA handover

    meeting

    Relative documents: 1. SA Report Template;

    2. Lease Agreement Template;

    3. Candidate Site Evaluation Report Template;

    4. Building Permits Template;

    5. Lease LOI Template

    Key Points:1. SOW;

    2. Cooperation requirements;

    3. Work flow clarification.

    0.5

    Input - All kinds of templates draft

    Action 1: KCP SA Handover Meeting

  • Internal Only

    Action 2: Review Engineering Requirement & Plan

    Action No. Action Name Executor Work Day

    CSE-02 Review Engineering Requirement & Plan CSE 0.5

    ATTENTION

    CSE should review the

    engineering requirement & plan

    submitted by SA subcontractor,

    and focus on time, scope,

    participants, vehicle, tool s ,

    progress and cost.

    Develop detailed

    SA design

    Staff/vehicle/

    tool preparation

    Review engineering requirement & plan Pass

    No

    Yes

    SA kick-off

    meeting

  • Internal Only

    Action 3: SA Kick-off Meeting

    Action No. Action Name Executor Work Day

    CSE-03 SA Kick-off Meeting CSE, SAS 0.5

    ATTENTION

    CSE shall call SA

    subcontractor to attend SA

    Kick-off Meeting, and output

    Minutes of Kick off Meeting

    Work out detailed

    SA design

    Staff/vehicle/

    tool preparation

    Review engineering

    requirement & planPass

    No

    Yes

    SA kick-off meeting

  • Internal Only

    Site Acquisition - Action List for Site Engineers

    Site Acquisition Plan &Preparation

    Initial Site Survey (SA)

    Action 4: SA Training

    Action 5: Review Site Survey Report

    Action 6: Prioritize identified Sites

    Lease Agreement & Permits

    Content

  • Internal Only

    Initial Site Survey (SA)

    3days 1day Half a day 1day

    Develop SA

    principle

    SAtraining

    Map/GPS

    preparation

    Locate the

    planned site

    Search

    candidate

    site

    Arrange dates

    for

    site access

    Action 4

    Survey tools/

    material

    preparation

    To be

    continued

    Initial Site Survey (SA)

    Level 4

    Level 5Site Acquisition Plan &

    Preparation Initial Site Survey (SA) Lease Agreement &

    Permits

    Site

    Acquisit

    ion

    Site

    SurveySite

    Design

    Material

    Delivery

    Civil

    Work

    TE Installat

    ion

    Site Integra

    tion

    Network

    Optimiza

    tion

    PATNetwork

    Planning

    Blue: Site Engineer

    Orange: Subcontractor and other

    CP KCP

  • Internal Only

    Initial Site Survey (SA)

    1day 1day 1day 1day 3days

    Negotiation

    with owner

    Complete

    SA report

    Review sitesurvey report

    Prioritize identified sites

    Provide

    selected

    candidate info

    Review site

    information

    Action 5Complete

    initial site

    survey report

    On-site

    initial site

    survey

    Action 6

    Blue: Site Engineer

    Orange: Subcontractor and other

    CP KCP

    Initial Site Survey (SA)

    Level 4

    Level 5Site Acquisition Plan &

    Preparation Initial Site Survey (SA) Lease Agreement &

    Permits

    Site

    Acquisit

    ion

    Site

    SurveySite

    Design

    Material

    Delivery

    Civil

    Work

    TE Installat

    ion

    Site Integra

    tion

    Network

    Optimiza

    tion

    PATNetwork

    Planning

  • Internal Only

    Key action Documents & Key Points Work day

    SA training Relative Documents:Candidate Site Evaluation Report, etc

    Action Points:1. Focus on training content

    1Candidate site location info; 2Local culture and customs; 3Government relationship; 4Ownership info; 5Residents interference; 6Water / AC power/ road; 7Local laws

    2. SOW &workflow;

    3. The ranking is based on the following factors: site acquisition

    time, site rental fee, site construction difficulty, site technical

    assessment;

    4. Make sure that all documents are accurate and complete.

    1

    Action 4: CP SA Training

    1. CSE shall call SA subcontractors to attend the SA training , and invite engineers from technical

    departments to share the SA experiences.

    2. CSE shall make record of subcontractor attendance, test result, training evaluation, etc.

    3 .CSE shall submit the training results to regional project manger.

    Input All Kinds of Templates

    Output - SA Training Record

  • Internal Only

    Output - CER and Site List Info

    1. Civil Work Site Engineers and Site Survey Engineers shall review Candidate Site Evaluation

    Report and Site Survey Report together;

    2. All documentation should be reviewed and 10% of these should be checked on site.

    Key action Documents & Key Points Work day

    10% on-site

    check

    Key points1. Ownership documents

    2. Owners will;3. Citizens interference;4. Water and electricity usage;

    5. Road connection;

    6. Subcontractors Competence;

    1

    Input - CER and Site List Info

    Action 5 KCP Review Site Survey Reports (1)

    Work out site

    survey reportSearch

    for new

    candidates

    OK

    No

    Yes

    Review site

    survey reports

    Work out

    SA report

    Prioritize

    identified

    candidate

  • Internal Only

    Output - CER and Site List Info

    1. Civil Work Site Engineers and Site Survey Engineers shall review Candidate Site

    Evaluation Report and Site Survey Report together;

    2. All documentation should be reviewed and 10% of these should be checked on site.

    Key action Documents & Key Points Work day

    100%

    review

    of

    reports

    Relative documentsCER, Site List Info

    Action Points:1. Assessment of Ownership documents

    2. Government requirements

    3. Owners will;

    4. Local law;

    5. Citizens interference;

    6. Water and electricity usage;

    7. Road connection;

    1

    Input - CER and Site List Info

    Action 5 KCP Review Site Survey Reports (2)

  • Internal Only

    Output - CER and Site List Info

    1 SA Manager calls PDT, CSE, DSE to prioritize identified candidates in order.

    2 If SA cannot decide the prioritization, they should ask PDT for technical support, and PDT will

    make the decision.

    3 CSE submit the best site info to SA Manager, and receives feedback from the Customer.

    Key action Documents & key points Work day

    Prioritize

    identified

    candidat

    es

    Relative documentsCER and Site List Info (draft)

    The ranking is based on the following factors:1. Site acquisition time;

    2. Site rental fee;

    3. Site construction difficulty;

    4. Site technical assessment;

    1

    Input - CER and Site List Info

    Action 6CP Prioritize Identified Candidates

    Prioritize identified

    candidates

    Feedback

    the best

    site Info

    Review site

    information

    Review site

    survey reports

  • Internal Only

    Site Acquisition - Action List for Site Engineers

    Site Acquisition Plan & Preparation

    Initial Site Survey (SA)

    Lease Agreement & Permits

    Action 7: Review SA Negotiation Results

    Action 8: SA & Documents Filing

    Content

  • Internal Only

    Lease Agreement & Permits

    9days 1day 1day 10 days ???Site price

    negotiations

    based

    on priority

    Audit SA negotiation

    results

    Signing of

    lease

    agreement

    Building

    permits

    acquisition

    Action 7

    1day

    SA & documents filing

    Action 8

    Lease

    Agreement &

    Permits

    Level 4

    Level 5Site Acquisition Plan &

    Preparation Initial Site Survey (SA) Lease Agreement &

    Permits

    Site

    Acquisit

    ion

    Site

    SurveySite

    Design

    Material

    Delivery

    Civil

    Work

    TE Installat

    ion

    Site Integra

    tion

    Network

    Optimiza

    tion

    PATNetwork

    Planning

    Blue: Site Engineer

    Orange: Subcontractor

    CP KCP

  • Internal Only

    Output Signed Lease Agreement

    Key action Documents & Key Points Roles Work day

    SA

    &documents

    filing

    Key action pointsCivil work site engineers should review

    result of site rent after getting LOI

    submitted by subcontractor, paying

    attention to the whole process of lease

    agreement signing between the

    customer and the owner.

    CSE 1

    Input - Lease Agreement Template

    Action 7 CP Audit SA Negotiation Results

    Lease

    renegotiation

    Audit SA

    negotiation

    results

    OK

    No

    yes

    Site price

    negotiations

    based

    on priority

    Signing of lease

    agreement

  • Internal Only

    Output - Filling of complete SA Documentation

    Key action Documents & key points Roles Work day

    SA & documents filing

    Relative documents1. Candidate Evaluation Report;

    2. Ownership Certification; 3. Lease Agreement;4. Building Permits;

    5. Initial Site Survey Report; 6. Government documentation7. Others

    Key pointsTo ensure the timeliness, effectiveness,

    accuracy, completeness of all

    documents.

    Customers, SA

    subcontractors and owners.

    1

    Input Site Acquisition Documentation

    Action 8 CP SA & Documents Filing

  • Internal Only

    Training Course Review

    1 What are the CPs/KCPs for a CSE

    2 What are each key points for each

    action?

    3 What are the extra CPs/KCPs

    needed to be examined?

  • Proprietary Confidential