The Design, Construction, Testing & Commissioning of Strategic Reservoirs

(Phase III) Faisaliah - Jeddah

Letter of Award: 8/1/2014Site Hand Over Date : 22/06/2014Completion Date: 23/04/2016Contract Period: 18 monthTime Extension : 9 monthsContract Value: 451,800,000 SR

Project location: Jeddah City - Reservoirs area of FAISALAH

Project location:

Site

PROJECT SITUATION

• Finish the soil improvement work for both tanks 1&3• Finish of installation and commissioning for the batch plant by the

attendance of the Consultant and receive approval for the submitted calibration report.

• Finish the design for the tower crane location, casting 1 crane foundation and finish reinforcement for 3 other cranes foundation and ready to cast , finish assembly for 2 tower crane and ready for installation.

• Delivery for 4 tower cranes to the site.• Excavation is running in area of tank #1 and finish about

50%.• Submit the recovery time schedule by the new dates after notice of

proceeding the work of the project.• Delivery for the formwork for the wall, Post tensioning material, pipes

material.• Finish 95 % of site mobilization.• Finish the first path of rerouting the fiber optic and delivered the Lab to

NWC, Working is running to finish the second path to delivered the training center.

Work Situation:

Construction ..1:

Excavation is running in area of tank #1

Complete removal for the existing pipe in

area of tank #4

Construction ..2:

Start assembly

for the wall

formwork

Internal

External

Construction ..3:

Finish assembly for 2 tower

cranes

Tower crane #1

Tower crane #2

Construction ..4:

Start dewatering activity

Construction ..5:

Finish the soil improvement work for tank #3

Construction ..6:

After approval for the soil improvement for tanks 2 & 4 to be

“Stone Column” technique – as shown in the photos below

(1)(2)(3)

Construction ..7:

Finish of installation and

commissioning for the batch plant by the attendance of

the Consultant

Construction ..8:

Implementation for protection trench

Construction ..9:

Start rebar & formwork forming

Construction ..10:

Finish new offices for DNGO

site engineers and main

subcontractors

Construction ..11:

Material delivery

Material delivery

for formwork and post tension material

Material Delivery ..1:

Delivery for pipes 8”

Material Delivery ..2:

Design

Soil improvement work:• Receive approval for the design report for tank #1.• Pressure meter test is running to submit the final report for tank #3.• Receive APPROVAL FOR THE NEW SOIL IMPROVEMENT TECHNIQUE

“Stone Column” for tanks 2 & 4.Foundation design:• Submit the foundation design (under revision)Wall design:• Receive approval for the wall design.Piping design:• Receive approval for the “GRP PIPING SPECIFICATIONS UNDER TANK”• Receive approval for the submitted method statement for pipe

installation and hydro test.• Receive approval for the method statement for the dewatering system.• Received some information for the hydraulic and electrical

design, still some minor information is missing to complete the required design.

التصميم أع�مال :موقف

Project Resources

• In hand 394 manpower, 76 equipment.

• Manpower are available under the sponsorship of the company to complete the work on the project.