Page 1: HDB-Supervision Guide for Electrical Engineering Works

Supervision Guide for Electrical Engineering

Works

Page 2: HDB-Supervision Guide for Electrical Engineering Works

Introduction

To develop quality management system and checklists / forms for supervising Electrical Engineering Works

Page 3: HDB-Supervision Guide for Electrical Engineering Works

Quality Control

Material

Timber mock up

Trades Demonstration

Sample units

In-process checking

Delivery and storage

Testing & commissioning

Handover inspection

Page 4: HDB-Supervision Guide for Electrical Engineering Works

Specific Requirement

No Drill Zone

150mm “bandwidth” to the left, right, above and below w.r.t. all conceal electrical accessory and also below ceiling

Page 5: HDB-Supervision Guide for Electrical Engineering Works

Specific Requirement

Lightning Protection System

HDB use aluminium lightning tape on the roof top and run the aluminium down conductor on surface of external wall/column.

The aluminum down conductor is connect to copper tape using bi-metallic aluminum/copper connector at a height of 2.5m. The copper tape shall be properly concealed or embedded to prevent it from being removed

Page 6: HDB-Supervision Guide for Electrical Engineering Works

Specific Requirement

TV System

All distribution amplifiers are to be properly secured with locking device and engrossed with Serial number. All Tee units in the Telecom Riser and distribution amplifiers are to be spray painted

Page 7: HDB-Supervision Guide for Electrical Engineering Works

Submission

Services coordination drawings

First Storey trunking route and penetration

Page 8: HDB-Supervision Guide for Electrical Engineering Works

Good Practices/ Common Defects

Page 9: HDB-Supervision Guide for Electrical Engineering Works

Good Practices/Common Defects

Electrical Installation

Conceal conduits should be gradually bent and has no more than 2 nos. of 90 degree bend between two points and the crossing of conduits should be kept to a minimum so that the covering of the conduit should be sufficient

Page 10: HDB-Supervision Guide for Electrical Engineering Works

Good Practices/Common Defects

Electrical Installation

Proper conduit accessories are to be used

Location of conceal conduit w.r.t. the precast component must be checked

Page 11: HDB-Supervision Guide for Electrical Engineering Works

Good Practices/Common Defects

Electrical Installation

Conceal conduit running outside the no drill zone

X

Page 12: HDB-Supervision Guide for Electrical Engineering Works

Good Practices/Common Defects

Electrical Installation

The Consultant can consider casting the socket outlets separately to ensure that the socket outlets are in level position and also reduce the need to hack the brick wall later for the installation of conduits.

For those socket outlets to be installed at the brick wall

Page 13: HDB-Supervision Guide for Electrical Engineering Works

Good Practices/Common Defects

Electrical Installation

No cable should be exposed without the protection of a conduit, trunking or some other form of protection

X

Page 14: HDB-Supervision Guide for Electrical Engineering Works

Good Practices/Common Defects

Electrical Installation

The Consultant should inspect and paid attention on the running of the conceal conduit in block walls.

In this case, metal conduit should be used

X

X

Page 15: HDB-Supervision Guide for Electrical Engineering Works

Good Practices/Common Defects

Electrical Installation

In instances where two residential units share one common riser duct, PowerGrid meter boxes should be placed logically for identification

Page 16: HDB-Supervision Guide for Electrical Engineering Works

Good Practices/Common Defects

Electrical Installation

The Consultant should check to ensure that the main door does not hit the CCU when fully opened.

X

Page 17: HDB-Supervision Guide for Electrical Engineering Works

Good Practices/Common Defects

Earth System

The Consultant should ensure all necessary information of the earth system engraved on a durable identification tag to be fixed onto the inside top of the earth pit

Page 18: HDB-Supervision Guide for Electrical Engineering Works

Good Practices/Common Defects

ELV Installation

Proper separations between Switched socket outlet box and TV outlet box

X

Page 19: HDB-Supervision Guide for Electrical Engineering Works

Good Practices/Common Defects

Lightning Protection System

Location of the aluminium air terminal should be check and relocated appropriately with consideration of the ladder or railing installed at the roof

X

Page 20: HDB-Supervision Guide for Electrical Engineering Works

Good Practices/Common Defects

Lightning Protection System

Re-entrant loop should be avoided

Page 21: HDB-Supervision Guide for Electrical Engineering Works

CONQUAS

Finishes must be even, level, align & consistent

No stain marks and visible damages / defects

Page 22: HDB-Supervision Guide for Electrical Engineering Works

Thank You

Page 23: HDB-Supervision Guide for Electrical Engineering Works

Timber Mock Up

The Consultant should inspect and verify the position of all electrical provision, esp at toilet and balcony

- heater point at toilet

- power point for the washing machine

Page 24: HDB-Supervision Guide for Electrical Engineering Works

In Process Checking

The Consultant should verify that the Electrical Sub-contractor is

- BCA registered contractor of at least L2 grade

- Registered with Qualified Electrical Contractors Registry maintained by IES/ACES