1 Plate 8mm (4415mm x 1415mm) 1.400,00 kg 11.000 15.400.000
2 Plate Bahan hollo (8mmx 70mm x 140mm) x 4415mm 388,80 kg 11.000 4.276.800
Plate Bahan hollo (8mmx 70mm x 140mm) x 1270mm 147,39 kg 11.000 1.621.280
3 Pek.UNP (65x 42x 5 mm) 260,77 kg 11.000 2.868.507
24.166.587
B JASA POTONG DAN BENDING
Plate Bahan hollo (8mmx 70mm x 140mm) x 4415mm 388,80 kg 3.000 1.166.400
Plate Bahan hollo (8mmx 70mm x 140mm) x 1270mm 147,39 kg 3.000 442.167
1.608.567
C JASA LAS
1 Plate 8mm (4415mm x 1415mm) 1.400,00 kg 3.500 4.900.000
2 Plate Bahan hollo (8mmx 70mm x 140mm) x 4415mm 388,80 kg 3.500 1.360.800
Plate Bahan hollo (8mmx 70mm x 140mm) x 1270mm 147,39 kg 3.500 515.862
3 Pek.UNP (65x 42x 5 mm) 260,77 kg 3.500 912.707
7.689.368
D MATERIAL PEMBANTU
Peralatan & bahan tambahan (Oksigen,solar, kawat las
listrik dll)2.196,96 LOT 1.800 3.954.532
3.954.532
37.419.055
E BAHAN
1 Plate 8mm 1.400,00 kg 11.000 15.400.000
2 Plate 6mm 1.050,00 kg 11.000 11.550.000
3 Besi AS 4,00 kg 25000 100.000
4 Besi Ass Kotak 14,00 m 25000 350.000
27.400.000
F JASA POTONG DAN BENDING
1 Pek.Plate 8mm 1.400,00 kg 3.000 4.200.000
2 Pek.Plate 6mm 1.050,00 kg 3.000 3.150.000
7.350.000
G JASA LAS
1 Plate 8mm 1.400,00 kg 3.500 4.900.000
2 Plate 6mm 1.050,00 kg 3.500 3.675.000
3 Besi AS 4,00 kg 3.500 14.000
4 Besi Ass Kotak 14,00 m 3.500 49.000
8.638.000
H MATERIAL PEMBANTU
Peralatan & bahan tambahan (Oksigen,solar, kawat las
listrik dll)2.468,00 LOT 1.800 4.442.400
4.442.400
I Mobilisasi 1,00 ls 7.500.000
55.330.400
92.749.455
1,415 4,415 0,008 0,0499778 7850 392,32573 431,56 1 431,56
0,42 4,415 0,008 0,0148344 7850 116,45004 128,10 2 256,19
0,42 1,27 0,008 0,0042672 7850 33,49752 36,85 2 73,69
11,37