-syngenoperatn
TRANSCRIPT
-
7/29/2019 -Syngenoperatn
1/16
Spring 2002 ELCT 553 Synchronous generator:
Operation
1
Synchronous Generators:Operation
We consider:isolated generator
generator connected in parallelwith a large system
two generators connected inparallel
-
7/29/2019 -Syngenoperatn
2/16
Spring 2002 ELCT 553 Synchronous generator:
Operation
2
Isolated generator
Control prime mover throttle
to control speedspeed governor measures
speed and uses a control loopto regulate it to generate 60 Hz(for example)
average load power met (up tothe system limits)
-
7/29/2019 -Syngenoperatn
3/16
Spring 2002 ELCT 553 Synchronous generator:
Operation
3
Control exciter to controlterminal voltage
voltage regulator measuresarmature voltage and uses a
control loop to regulate it togenerate at rated voltage
the reactive power needs of theload are met (up to systemlimits)
-
7/29/2019 -Syngenoperatn
4/16
Spring 2002 ELCT 553 Synchronous generator:
Operation
4
VAjXS IA Load
EA
IA
VA
EA
jXSIA
-
7/29/2019 -Syngenoperatn
5/16
Spring 2002 ELCT 553 Synchronous generator:
Operation
5
EA
IA
XSIA
VAdq g
EAsin(d)=XSIAcos(q)
q
EAcos(d)-VA=XSIAsin(q)
S
AAA
S
AA
X
)V-)cos((E3VAA
X
)sin(E3V
AA
)sin(IV3Q
)cos(I3VP
d
d
=q=
=q=
-
7/29/2019 -Syngenoperatn
6/16
Spring 2002 ELCT 553 Synchronous generator:
Operation
6
Since the speed and |VA| areregulated:
Load average power (P) increasescause increased values ofd(caused by increased powerinput)
Load reactive power (Q) increases
cause |EA| to increase (byincreased field current)
-
7/29/2019 -Syngenoperatn
7/16
Spring 2002 ELCT 553 Synchronous generator:
Operation
7
EA
IA
XSIA
VA
d
q
g
Increase P at constant Q
-
7/29/2019 -Syngenoperatn
8/16
Spring 2002 ELCT 553 Synchronous generator:
Operation
8
EA
IA
XSIA
VA
dq
g
Increase Q at constant P
-
7/29/2019 -Syngenoperatn
9/16
Spring 2002 ELCT 553 Synchronous generator:
Operation
9
EA
IA
XSIA
VAdq g
Increase |S| at constant pf
-
7/29/2019 -Syngenoperatn
10/16
Spring 2002 ELCT 553 Synchronous generator:
Operation
10
Generator in parallel with alarge system
Infinite bus = generator withinfinite inertia and zero internal
reactance = ideal ac voltagesource
approximate representation of alarge power system
-
7/29/2019 -Syngenoperatn
11/16
Spring 2002 ELCT 553 Synchronous generator:
Operation
11
Governor characteristicf
[Hz]
fnl
sp=-DP/Df
P
[kW]
-
7/29/2019 -Syngenoperatn
12/16
Spring 2002 ELCT 553 Synchronous generator:
Operation
12
genbusf[Hz]
load
fnl
PB [kW] PB1 PG1 PG [kW]Pload
-
7/29/2019 -Syngenoperatn
13/16
Spring 2002 ELCT 553 Synchronous generator:
Operation
13
f
[Hz]
fnl
PG2PB2
Pload
PG1
Raise
Pload
PB1PB [kW] PG [kW]
-
7/29/2019 -Syngenoperatn
14/16
Spring 2002 ELCT 553 Synchronous generator:
Operation
14
Two generators in parallel
f [Hz]
f
P2
Pload
P1P1 [kW] P2 [kW]
-
7/29/2019 -Syngenoperatn
15/16
Spring 2002 ELCT 553 Synchronous generator:
Operation
15
Same load, raise unit 2, f increases,
load shifts from 1 to 2
f [Hz]
f
P2
Raise
Pload
P1P1 [kW] P2 [kW]
-
7/29/2019 -Syngenoperatn
16/16
Spring 2002 ELCT 553 Synchronous generator:
Operation
16
Excitation system
characteristicVT [kV]
Vnl
sq=-DQ/DV
Q
[kVAr]