half pit limits

31
University of Alberta MINE 32 5 – Mine Pl anning a nd Desig n Lec16_1 MINE 325 Mine Planning ec – ms Manual Method Ultimate or Final Pit Limits (1/5) Size and shape of mineable reserves and Lec15-2  based on: Technical , Economical , Safety constraints It is used in: The economic potential of a mineral deposit. Financing and Taxation. Short and long term mine plans. The boundaries outside which mine plant and structures should be located.

Upload: wilber-yucra

Post on 14-Oct-2015

32 views

Category:

Documents


2 download

TRANSCRIPT

  • University of AlbertaMINE 325 Mine Planning and Design

    Lec16_1

    MINE 325Mine Planning

    L 15 Pit Li it ILec15 Pit Limits IManual Method

    Ultimate or Final Pit Limits (1/5)

    Size and shape of mineable reserves and associated waste materials to be excavated

    Lec15-2

    associated waste materials to be excavated based on:

    Technical , Economical , Safety constraints It is used in: The economic potential of a mineral deposit. Financing and Taxation. Short and long term mine plans. The boundaries outside which mine plant and

    structures should be located.

  • University of AlbertaMINE 325 Mine Planning and Design

    Lec16_2

    Pit Limits (2/5) Lec15-3

    Pit Limits (3/5) Lec15-4

  • University of AlbertaMINE 325 Mine Planning and Design

    Lec16_3

    Pit Limits (4/5) Lec15-5

    Final Pit Limit method (5/5)

    Manual methodC t th d (2D 3D)

    Lec15-6

    Computer methods (2D, 3D) Manual methods are based on sections

    Involve Stripping Ratios (SR)

    Three stripping ratios which can be defined: Overall Stripping Ratio Incremental (Instantaneous) Stripping Ratio Break-even or maximum Stripping Ratio

  • University of AlbertaMINE 325 Mine Planning and Design

    Lec16_4

    MINE 325Mine Planning

    Stripping Ratio

    Stripping Ratios (1/6) Overall stripping ratio is the ratio of the total

    tonnage of waste divided by the total tonnage of

    Lec15-8

    tonnage of waste divided by the total tonnage of ore contained in the final pit (SRo)

    Incremental stripping ratio (or instantaneous stripping ratio)is the ratio of waste tonnage to ore tonnage as a result of expanding the pit by a unit volume (ISR)

    Break-even stripping ratio is the ratio of waste tonnage to ore tonnage where the cost of the waste removal exactly equals the value of the mineral (BESR or SRmax)

  • University of AlbertaMINE 325 Mine Planning and Design

    Lec16_5

    Stripping Ratios (2/6)

    SRo and ISR are physical ratios

    Lec15-9

    BESR is an economic ratio

    BESR will change depending on grades, costs and revenues

    Stripping ratio (3/6)The volume of the contained ore is expressed by

    2V h

    Lec15-10

    2V r hwhere r is the ore radius h is the ore thickness.

  • University of AlbertaMINE 325 Mine Planning and Design

    Lec16_6

    Stripping ratio (4/6) Chapter 4 pages 45 to 49

    . tanh r

    Lec15-11

    tancH h h h r

    tan tancH hR r

    213tip

    V r h Truncated tip

    2 21 13 3m tip c

    V V V R H r h

    Fully circumscribed cone

    213 c

    V R HMined volume (ore + waste)

    Stripping ratio (5/6) Chapter 4 pages 45 to 49

    1 1Mined volume (ore + waste)

    Lec15-12

    2 21 13 3m tip c

    V V V R H r h

    2w mV V r h

    Volume of waste

    ( )Waste volumeSR ( )

    SROre volume

    2

    2( )w m

    o

    V V r hSR overallV r h

  • University of AlbertaMINE 325 Mine Planning and Design

    Lec16_7

    Stripping ratio (6/6)Chapter 4 pages 45 to 49

    Lec15-13

    MINE 325Mine Planning

    Final Pit Limitsa t tsManual Method

  • University of AlbertaMINE 325 Mine Planning and Design

    Lec16_8

    Manual Method Basic Concepts - Sectional Calculation

    waste$NV = $GV $TC

    Net Value = Gross Value Total Cost

    Lec15-15

    the density of ore and waste is the

    0.6% Cu

    ISR = 2:1

    1 ton of Ore (0.6% Cu)

    3.2 tons of waste

    $NV = $GV - $TC

    BESR = 3.2:1 the density of ore and waste is the same, the ISR is the ratio of the length in ore to the length in waste. $NV = Cost of Stripping

    Manual Method Basic Concepts - Sectional Calculation

    waste

    Lec15-16

    0.6% Cu

    ISR = 2:1 BESR = 3.2:1

    Actual Stripping Ratios

    Allowable Stripping Ratios

    Pit Limit is adjusted until: ISR = BESR

  • University of AlbertaMINE 325 Mine Planning and Design

    Lec16_9

    Manual Method Basic Concepts - Both Walls in Waste

    Lec15-17

    Usually the width of cross section is assigned to each side ( f i fl f ti )(area of influence of section).

    Shape is moved vertically and horizontally on section until both sides fit the SR-Grade Curve

    Manual Method Sectional Calculation -Variable Grades

    Each block or polygon has a grade associated with it

    Lec15-18

    grade associated with it.

    Multiple layers of overburden type material can complicate

    Calculation of average grade in the ore is a length weighted average grade.

    Each side is done independently.

    can complicate the sectional calculation

  • University of AlbertaMINE 325 Mine Planning and Design

    Lec16_10

    Hand Method The Basic Concept - Example

    Lec15-19

    Ore Net Value$NV = $GV - $TC = $1.90 / unit volume Cost of stripping waste is $1/unit volume

    Hand Method the Basic ConceptExample- Strip 1

    The volumes are:Strip 1:

    31 7.5wV u

    Lec15-20

    31 5.0oV u

    The instantaneous stripping ratio (ISR) is defined as: 1wl

    ol

    VISRV

    1 1.5ISR

    Assuming that the net value from selling one unit volume of ore (that money remaining after all expenses have been paid) is $1.90

    cost for mining and disposing of the waste is $1/unit volume, the net value for strip I is

    1 5.0 x $1.90 - 7.5 x $1 = $2.00NV

  • University of AlbertaMINE 325 Mine Planning and Design

    Lec16_11

    Hand Method the Basic ConceptExample- Strip 2

    V u238 4= .

    Strip 2:

    Lec15-21

    V uV uISRNV

    w

    o

    2

    23

    2

    2

    8 4

    5 01 68

    =

    =

    =

    .

    ..

    5.0 x $1.90 - 8.4 x $1 = $1..10

    Hand Method the Basic ConceptExample- Strip 3

    Strip 3:

    V u339 45= .

    For strip 3, the net value is just about zero This pit position is termed

    Lec15-22

    V uV uISRNV

    w

    o

    3

    33

    3

    3

    9 45

    5 01 89

    =

    =

    =

    .

    ..

    5.0 x $1.90 - 9.45 x $1 = $$0.05 0

    zero. This pit position is termed 'breakeven' since the costs involved in mining the strip just equal the revenues.

    It is the location of the final pit wall.

  • University of AlbertaMINE 325 Mine Planning and Design

    Lec16_12

    Hand Method the Basic ConceptExample- Strip 4

    V u310 5=Strip 4:

    Lec15-23

    V uV uISRNV

    w

    o

    4

    43

    4

    4

    10 5

    5 02 1

    =

    =

    =

    =

    .

    ..

    5.0 x $1.90 - 10.5 x $1 = --$1.0

    Hand Method Example final pitISR = BESR

    Lec15-24

  • University of AlbertaMINE 325 Mine Planning and Design

    Lec16_13

    Hand Method the Basic ConceptThe overall stripping ratio (OSR) for this section is calculated as

    t A

    Lec15-25

    waste area AOSRore area B

    OSR = 0.8

    Hand Method the Basic Concepthow to find the final pit outline?

    Lec15-26

  • University of AlbertaMINE 325 Mine Planning and Design

    Lec16_14

    Hand Method the Basic ConceptBasic steps in determining pit limits

    the following basic steps involved indetermining pit limits remain the same:

    Lec15-27

    determining pit limits remain the same:1. A slice is selected.2. The contained value is compared with the

    costs.3. If the net value is positive, the pit can be

    d d If ti th it t texpanded. If negative, the pit contracts.4. The final pit position is where the net value

    of the slice is zero.ISR = BESR

    MINE 325

    Lec15-28

    Mine Planning

    M l M th dManual Method Net Value Calculation

  • University of AlbertaMINE 325 Mine Planning and Design

    Lec16_15

    Cutoff Grades

    The term cutoff grades refers to grades f hi h th d ti ti f t i l

    Lec15-29

    for which the destination of materials changes

    Cutoff grade is the grade at which the mineral resource can no longer be processed at a profit.processed at a profit.

    The break even cutoff grade is defined as the grade for which the net value is zero

    Manual Method Example Copper Deposit

    Lec15-30

    Find the Min and Max grade in the sectionsection

  • University of AlbertaMINE 325 Mine Planning and Design

    Lec16_16

    Net Value Calculationto construct a net value grade curve

    1. Compute the amount of saleable product copper (lb/s t of ore)

    Lec15-31

    copper (lb/s.t of ore)2. Calculate the gross value (GV) for the ore ( $/ s.t)3. Calculate the associated costs (TC) ($/s.t)4. Calculate the net value per ton of ore

    Net Value = GV TC5. Calculate the net value per ton of ore for another

    ore grade6. Construct a net value grade curve

    Net Value Calculationto construct a net value grade curve

    7. determine the breakeven cutoff grade

    Lec15-32

    8. Developing a stripping ratio grade curve

    9. Presenting the final curves10.Finding the location of pit limits

  • University of AlbertaMINE 325 Mine Planning and Design

    Lec16_17

    Manual Method Creating a Net Value to Grade Curve

    Net value must include all recoveries/losses due to processing

    Lec15-33

    due to processing Consider the following example: Mill recovery = 80% Mill concentrate grade = 20% Smelting loss = 10 lbs/st of conc. Refining loss = 5 lbs/st of copper Calculations for 0.55% Cu Mining cost $1 / ton

    Manual methodCreating a Net Value to Grade Curve

    It will be assumed thatPit l

    Lec15-34

    Pit slopes: Left hand side = 50 degrees Right hand side = 40 degrees

    Minimum width of the pit bottom = 100 ft; Material densities:

    Ore = 165 lb/cu-ft Waste rock = 165 lb/cu-ft Overburden =165 lb/cu-ft;

  • University of AlbertaMINE 325 Mine Planning and Design

    Lec16_18

    Manual Method Net Value to Grade Curve

    Mine Mill Concentrator Smelter Refinery

    Mill recovery = 80%loss = 5 lbs/st ofBlister copper

    loss = 10 lbs/stof concen

    Lec15-35

    0.55%

    blister copperconcentrate copperOre1 st = 2000lb weight

    grade

    lbs cu 11.0

    2000lb 20%

    8.8 8.58 8.56

    2000lb

    45.45 tonsCopper price $1 / lb

    233.1 tonsCopper price $1 / lbBy product $1.77 / st oreMining cost $1 / ton

    Manual Method Creating a Net Value to Grade Curve Mill recovered Quantity of Metal = Contained copper * recovery

    0.55% Cu 11 lb/st * recovery = 8.8 lb/st

    Lec15-36

    y Mill produces 20% concentrate

    Conc. Ratio = 400 lb/st conc / 8.8 lb ore = 45.45 tons of ore Means that ~45 tons of ore produces 1 ton conc.

    Smelter loses 10 lb/st conc = 0.22 lb/oreSmelter Recovered copper = 8.8 0.22 = 8.58 lb

    Refinery recovery = 2000 lb copper/ 8.58 lb copper/st ore= 233.1 tons ore

    Refining losses are 5lb/ton copper therefore loss of 0.02 lb of copper

    Refinery Recovered copper = 8.56 lb Cu / ton of ore

  • University of AlbertaMINE 325 Mine Planning and Design

    Lec16_19

    Manual method Creating a Net Value to Grade Curve

    Copper is $1.00 / lb other recovered $

    Lec15-37

    ppminerals (Au, Ag etc) total $1.77/ton of ore

    Revenue = 8.56lb * $1.00 + $1.77 = $10.33/ ton

    Manual method Creating a Net Value to Grade Curve

    Costs:Production costs:

    Lec15-38

    Production costs:Mining $1.00/ton, Milling $2.80/ton, Administration (15% of m&m) $0.57Total production costs $4.37

    Amortization and depreciation costs / ton ore 20% of production costs per ton ore = $0.87Treatment, refining, selling costs = $2.59

  • University of AlbertaMINE 325 Mine Planning and Design

    Lec16_20

    Manual method Creating a Net Value to Grade Curve

    Total costs of $7.83/ ton ore

    Lec15-39

    For 0.55% grade copper, Net Value = Revenue Costs =

    $10.33 - $7.83 = $2.50

    Net Value Curve

    4 00

    5.00

    Lec15-40

    y = 1556.1x - 6.064

    -1.00

    0.00

    1.00

    2.00

    3.00

    4.00

    0.00% 0.20% 0.40% 0.60% 0.80% 1.00%

    Net

    Val

    ue ($

    / to

    n of

    ore

    )

    -4.00

    -3.00

    -2.00

    Cu Grade

  • University of AlbertaMINE 325 Mine Planning and Design

    Lec16_21

    4.00

    5.00

    Net Value Curve

    Based on total costs of $7.83/ton of ore

    Lec15-41

    y = 1556.1x - 6.064

    -2.00

    -1.00

    0.00

    1.00

    2.00

    3.00

    0.00% 0.20% 0.40% 0.60% 0.80% 1.00%

    Net

    Val

    ue ($

    / to

    n of

    ore

    )

    Net Selling Price of $1.00/lb for the copper

    %CU Value

    0.55 $2.50

    0.37 -$0.31

    Break Even Grade

    Knowing the cost of waste

    -4.00

    -3.00

    Cu Grade

    gremoval, the curve can be

    converted to a stripping ratio grade curve

    4.00

    5.00

    Net Value Curve

    Cost of stripping is $1 00/ton

    Lec15-42

    y = 1556.1x - 6.064

    -2.00

    -1.00

    0.00

    1.00

    2.00

    3.00

    0.00% 0.20% 0.40% 0.60% 0.80% 1.00%

    Net

    Val

    ue ($

    / to

    n of

    ore

    )

    Cost of stripping is $1.00/ton

    Stripping ratios added to the curve.

    BESR =

    Net Value/ Stripping costMinimum Value

    3:1

    2:1

    1:10.5:1

    -4.00

    -3.00

    Cu Grade

    Minimum value is the cost of moving a ton of waste

  • University of AlbertaMINE 325 Mine Planning and Design

    Lec16_22

    Sectional CalculationVariable Grades-Example

    Lec15-43

    Manual method

    Stripping ratios and average grades are evaluated usually by direct measurement of

    Lec15-44

    evaluated usually by direct measurement of the lengths of the slope in ore and waste

    A final pit slope angle is chosen based on geotechnical considerations

  • University of AlbertaMINE 325 Mine Planning and Design

    Lec16_23

    Sectional Calculation - G1 Variable Grades-Example Contd

    Lec15-45

    Sectional Calculation G1Variable Grades-Example

    Lec15-46

    130 296( ) 1.79 :1;238

    SR actual ( ) 6.2 :1;SR allowable Conclusion: expand pit

    BESRISR

  • University of AlbertaMINE 325 Mine Planning and Design

    Lec16_24

    Sectional Calculation G1Variable Grades-Example

    Lec15-47

    Sectional Calculation G2 Variable Grades-Example Contd

    Lec15-48

  • University of AlbertaMINE 325 Mine Planning and Design

    Lec16_25

    Sectional Calculation Line G2Variable Grades-Example

    Lec15-49

    130 385( ) 3.3 :1156

    SR actual ( ) 5.6 :1SR allowable

    Conclusion: expand pit

    Sectional Calculation Line G3Variable Grades-Example Contd

    Lec15-50

  • University of AlbertaMINE 325 Mine Planning and Design

    Lec16_26

    Sectional Calculation Line G3Variable Grades-Example

    Lec15-51

    130 443( ) 5.51:1104

    SR actual ( ) 3.9 :1SR allowable

    Conclusion: contract pit

    Sectional Calculation - Line G4Variable Grades-Example Contd

    Lec15-52

  • University of AlbertaMINE 325 Mine Planning and Design

    Lec16_27

    Sectional Calculation Line G4Variable Grades-Example

    Lec15-53

    130 435( ) 5.43 :1104

    SR actual ( ) 5.4 :1SR allowable

    Conclusion: Final Pit

    Sectional CalculationsLec15-54

    Pit is outlined on each section.

    Number of sections required will depend on the complexity and shape of the deposit.

    Typically 8-20 sections are used.

  • University of AlbertaMINE 325 Mine Planning and Design

    Lec16_28

    Transfer to Plans

    Pit top and bottom are transferred to a plan view and

    Lec15-55

    pthe surface intersects connected.

    The ends must be done separately. At the pit ends a stripping wedge is calculated to complete the design.

    Sections

    Radial Section at Pit EndLec15-56

  • University of AlbertaMINE 325 Mine Planning and Design

    Lec16_29

    Radial Section at Pit EndLec15-57

    Parallel section

    radial section

    Radial Section at Pit EndLec15-58

  • University of AlbertaMINE 325 Mine Planning and Design

    Lec16_30

    Measured SR (for Radial Section)Lec15-59

    a

    b

    a = length in ore

    b = length in waste

    =slope angle

    Plan View

    Ba*cos b*cos

    includes angle of the wedge

    B

    A

    True SR (for Radial Section)

    The angles cancel out in the equationArea A = (a*cos)2 * / 2

    Lec15-60

    Area A = (a*cos)2 * / 2 Area B = [((a+b)*cos )2 - (a*cos )2] * / 2

    SR (true) = B/A =[(a+b)2-a2] / a2 = (1 + b/a)2 1

    SR (true) = [1 + SR(measured)] 2 - 1

  • University of AlbertaMINE 325 Mine Planning and Design

    Lec16_31

    Pit Ends

    Create a graph of Measured vs True SRM th SR th ti

    Lec15-61

    Measure the SR on the section Find the true SR from the graph Use the SR-Grade curve to adjust the

    position of the line

    True vs Measured SR CurveStripping Ratio

    Measured True16 00

    True vs Measured

    Lec15-62

    0.00 0.00

    0.25 0.56

    0.50 1.25

    0.75 2.06

    1.00 3.00

    1.25 4.06 4.00

    6.00

    8.00

    10.00

    12.00

    14.00

    16.00

    True

    SR

    1.50 5.25

    2.00 8.00

    2.50 11.25

    3.00 15.00

    0.00

    2.00

    0.00 1.00 2.00 3.00 4.00

    Measured SR