proj_62_vkau001_2

Upload: falcon-egy

Post on 04-Apr-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/30/2019 proj_62_vkau001_2

    1/8

    Switching Studies for Islington Substation Capacitor Banks with Surge Arresters

    Vipashna Kaushik

    Department of Electrical and Computer EngineeringUniversity of Auckland, Auckland, New Zealand

    Abstract

    The following report has been commissioned by

    Transpower New Zealand Ltd. to make an assessment

    on the existing and proposed surge arresters at Islington

    Substation. Surge arresters are devices that protect

    components from transient overvoltages caused during

    capacitor switching. These arresters are installed on the

    two existing 220kV capacitor banks and are proposed to

    be installed on the two new 220kV capacitor banks in

    order to protect them from switching transients.Switching studies were done with a circuit breaker

    restrike occurring while isolating a capacitor bank. Two

    surge arrester voltage ratings were analyzed; 198kV and

    216kV in order to find which arrester would provide

    more protection. Surge arresters were then placed

    parallel to the capacitor banks in two different

    configurations. The energy absorbed by the surge

    arrester during a switching surge was calculated and

    compared to its energy rating capability. The 216kV

    surge arrester proved more suitable for the Islington

    substation capacitor banks as the maximum energy

    absorbed by this surge arrester was less than its energy

    absorption capability of 1555.2kJ.

    1. IntroductionThe Islington substation is a 220kV/66kV/33kV

    substation located in the South Island. Transpower New

    Zealand Ltd. is currently installing two capacitor banks

    in addition to the existing capacitor banks to provide

    voltage support to the surrounding areas at times of high

    demand (refer to Appendix 1) [1]. These will be

    switched on a daily basis to maintain control of the

    system voltage levels during load changes. While such

    switching has its advantages, it can also create high

    voltage and current transients that can destroy

    neighboring equipment in the substation. Surge arrestersare installed in such cases to protect the surrounding

    equipment from such high surges.

    A study had been carried out by the Power Systems

    Consultants (PSC) in Wellington to report the effect of

    capacitor bank switching on the proposed and existing

    capacitor banks [1]. These studies however did not

    include the existing or the proposed surge arresters. In

    order to give Transpower an accurate picture on the

    efficiency of the new surge arresters, the Islington

    substation was modelled with surge arresters on

    PSCAD.

    2. ScopeThe intent of this report is to provide information on the

    effect of capacitor bank switching on the selected surge

    arresters. Two worst case scenarios were taken into

    account: circuit breaker restrike and bus fault. The aim

    of this report is to recommend whether the transientsgenerated during these scenarios exceed the energy

    rating of the proposed surge arresters. The scenario ofrestrike has been discussed in detail in this report.

    3. Islington SubstationA substation is a place where voltages are increased and

    reduced for transmission and distribution purposes. They

    also serve as connection points between different parts

    of a transmission system. The Islington substation,

    located in the South Island near Christchurch, is part of a

    transmission and distribution system. As shown in

    Figure 1, the southern generators at Tekapo, Ohao,

    Benmore and Livingston are connected to Islingtonthrough 220kV lines. This is then reduced to 66kV and

    33kV in order to distribute it near the Christchurch area.

    Figure 1. Location of the Islington Substation

    4. Transients in Power SystemsAn electrical transient is initiated whenever there is a

    sudden change of circuit conditions. It is represented by

    voltages and currents that are higher in magnitude and

  • 7/30/2019 proj_62_vkau001_2

    2/8

    frequency than the system values. These transients

    mostly occur when lightning strikes the transmission line

    or when switching of a component is involved. The

    period of a transient is normally very short; they can

    however cause a lot of damage to the components in a

    substation.

    In this report the transients that are generated during theswitching of capacitor banks is focused on. The times

    that transients occur during switching are while a) the

    closing of a circuit breaker to energize the capacitor

    bank or b) the opening of a circuit breaker to isolate or

    de-energize the bank.

    All components in a utility are made of capacitive and

    inductive parameters. In an alternating current circuit,

    energy is transferred cyclically between the inductances

    and the capacitances of the circuit as the current and

    voltage rise and fall at the frequency of the supply [2].

    When a sudden circuit change takes place there is a

    redistribution of energy in order to meet the new

    conditions in the circuit [3]. However this redistributionof energy cannot take place instantaneously due to two

    reasons: a) the voltage across a capacitor cannot increase

    instantaneously without an infinite increase in current

    and b) an instantaneous change in the current across an

    inductor would require an infinite voltage to bring it

    about [3].

    5. Capacitor Bank SwitchingA capacitor bank is an assembly of capacitors and all

    necessary equipment in one location [4]. They are

    primarily installed in a transmission system for VAR

    control and voltage control, while the secondary benefits

    include an increase in the system capacity and a

    reduction in power losses [4]. The components in a

    substation are mostly inductive in nature and with the

    addition of capacitor banks, the system losses are

    reduced by improving the power factor of the system.

    These capacitor banks are normally switched on during

    peak loading periods and switched off during light

    loading periods. Such connecting of a capacitor bank to

    the bus line results in a rise in the voltage level of the

    system. The switching of the capacitor banks thus adds

    flexibility over the control of voltage and losses. This

    switching is carried out with the help of circuit breakers

    and an automatic control device that senses a particular

    condition and disconnects or connects the capacitor

    banks from the bus based on that condition [4].

    There is however a problem that is associated with the

    switching of a capacitor bank. Transient overvoltages

    are always created during this switching.

    Figure 2. Energizing a Capacitor bank.

    Figure 3. Overvoltage produced across capacitor

    The circuit in Figure 2 was simulated using PSCAD in

    order to investigate the occurrence of overvoltages while

    switching a capacitor. The circuit breaker is initially

    open and closes 0.53sec after the circuit is simulated. At

    this instant the voltage across the capacitor reaches a

    peak value of 1.6pu as shown in Figure 3. This occurs

    due to the redistribution of energy in the circuit.

    5.1.RestrikeRestrike is a phenomenon that occurs while de-

    energizing or isolating a capacitor during the zero

    current crossing [5]. At this point the voltage will be at

    its peak value and the capacitor is isolated while being

    charged to the peak line voltage [5]. This voltage gets

    trapped at the capacitor end of the circuit breaker and

    half a cycle later, the voltage on the source side of the

    circuit breaker is of the opposite polarity. There will

    then appear a rise in voltage across the contacts of the

    circuit breaker (TRV) and this voltage will overshoot to

    a value which is equal to the difference between the two

    contact voltages [5]. Due to the oscillatory nature of the

    circuit, this overshoot will then damp and return to the

    system voltage. In extreme cases, if the overshoot

    exceeds the dielectric strength of the insulation of the

    circuit breaker, there is a breakdown in the insulationand arcing results [5]. This is called a restrike of the

    circuit breaker. This has been illustrated in Figures 4 and

    5.

    0.40 0.50 0.60 0.70 0.80

    -90

    0

    90

    capacitor voltage

    0.002 0.00053.6

    1.

    0

    5000.0

    CB1

    IaCIa

    Ea

    Time(s)

    Voltage

    (kV)

  • 7/30/2019 proj_62_vkau001_2

    3/8

    Figure 4. De-energizing a capacitor bank

    Figure 5. Capacitor restrike

    5.2.Back-to-Back SwitchingThe switching of a capacitor bank that is connected in

    parallel with one or more than one capacitor bank is

    known as back-to-back switching. Generally back to

    back switching of a capacitor bank when a capacitor

    bank is already energized creates a higher magnitude of

    transients [5]. In the case of the Islington substation

    there are four capacitor banks that are connected in

    parallel and switched alternatively depending on theload conditions.

    The zero voltage that occurs at the moment of contact

    closure when the second capacitor is energized makes it

    appear to the system as a short circuit [5]. This

    temporary short circuit will cause any energized

    capacitor nearby to discharge into the second capacitor

    [5]. In addition, the two capacitors in parallel appear as

    a larger equivalent capacitance rather than one capacitor

    alone, making the inrush current magnitude much larger

    than for a single capacitor. However, when switching a

    bank in parallel with and in close proximity to another

    energized bank, the transient current is limited only by

    the impedance between the banks [5]. This impedance istypically very low by comparison and therefore results in

    much higher current values.

    5.3.Grounded/Ungrounded Capacitor banksThe capacitor banks at Islington are connected in two

    different configurations. The old capacitor banks C22 &

    C25 have an ungrounded star connection and the new

    capacitor banks have a grounded star connection. These

    two connections have been illustrated in Figure 6.

    Grounded capacitor banks provide a low impedancepath to earth from lightning surges and provide some

    voltage surge protection [5]. Hence they are preferred in

    substations that are effectively grounded such as the

    Islington substation.

    Ungrounded Capacitor banks need to have surge

    arresters connected across them to protect them. The

    absence of a physical connection to ground means that

    the transients have no path to travel [5].

    Figure 6. Grounded vs. Ungrounded capacitor bank

    6. Surge ArrestersA surge arrester is a non-linear resistor that provides a

    low-impedance path around the component being

    protected [6]. It protects equipment from overvoltages

    and surges that can result from circuit breaker operation

    and faults in the system.

    The non linear resistor has a property of diminishing its

    resistance sharply as the voltage at its terminal increases

    [3]. They are connected across the apparatus to be

    protected and so experience the system voltage under

    normal operating conditions. Their resistance is very

    high so the power dissipation is minimal [3]. On the

    incidence of a surge of voltage, the resistance falls

    rapidly as the voltage increases, thereby diverting much

    of the current and energy of the surge into the arrester

    [3]. In Figure 7 below, a surge arrester has been added

    to the earlier example in Figure 6. The addition of this

    surge arrester connected parallel to the capacitor has

    resulted in a reduction in the peak voltage across thecapacitor from 1.60pu to 1.40pu.

  • 7/30/2019 proj_62_vkau001_2

    4/8

    Figure 7. Energizing in the presence of a surge arrester

    Figure 8. Reduction in the initial overvoltage

    Another important property of protective devices is their

    ability to store and dissipate energy [6]. When current is

    diverted into a surge arrester, and voltage is generated

    across it, it is at the same time absorbing energy.

    When metal-oxide arresters are energized, valve

    elements of the arrester will absorb energy that results in

    a temperature increase of the valve elements [6]. Under

    normal operating conditions there is a balance between

    the heat generated by the valve elements and the heat

    dissipated by the arrester [6]. Overvoltage events disturbthis stable condition by causing the valve elements to

    absorb increased levels of energy. If the temperature rise

    of the valve elements due to energy absorption is too

    high, the arrester can be driven into a state of thermal

    runaway, resulting in further increase in valve element

    temperature [6]. If the temperature of a valve element

    reaches a high enough level, damage to the valve

    elements can occur, leading to an electrical breakdown

    and failure of the arrester [6].

    The amount of energy an arrester absorbs depends on

    the magnitude and duration of the surge. The surge

    arrester should be capable of handling this energy by

    either storing or dissipating it without damaging itself.

    The surge arresters used at Islington are metal oxide

    arresters. The surge arresters in this project were

    modelled with two different voltage ratings: 198kV and

    216kV. This was done to find the best possible rating for

    the surge arresters.

    7. Case StudiesThe Islington substation circuit is a complicated circuit

    and it needs a power systems software in order to

    analyze it. Power Systems Computer Aided Design

    (PSCAD) was used for this purpose as it is an

    Electromagnetic Transients Program (EMTP) software.

    In order to study the complete effect of switching

    overvoltages on surge arresters, a worst case scenario

    was modeled on PSCAD. These cases involved restrike

    occurring on the circuit breaker during the isolation of

    capacitor banks C22 and C21. These cases have been

    described in detail below:

    7.1.Case 1A

    Figure 9. Steps taken to complete Case 1A

    Simulations were carried out on PSCAD with the

    existing capacitor banks C22 & C25. A restrike occurred

    on the circuit breaker connecting C22 to the 220kV bus

    while isolating the capacitor bank (refer to Figure 10).

    The duration of the restrike was 20mS and it occurred

    half a cycle after the capacitor current is interrupted, on

    phases A and C, while phase B remained unaffected

    CBC22Ia

    CBC22a

    CBC22Ib

    CBC22b

    CBC22Ic

    CBC22c

    0.00050.002

    0.0023.6 0.0005

    0.0020.0005

    3.6

    3.6

    10000000.0

    Figure 10. Connection of Capacitor Bank C22

    The device illustrated in Figure 11 controls the opening

    of the circuit breaker on capacitor bank C22. The first

    input slider labeled Open ABC is set to open the

    circuit breaker at 0.5355sec. This is when the system

    current is at the zero crossing. The next slider labeled

    Restrike Start is set to start restrike at 0.1s. This is half

    a cycle after the circuit breaker opens.

    CASE 1A

    Restrike

    With Surge

    Arresters

    Without Surge

    Arresters0.40 0.50 0.60 0.70 0.80

    -90

    0

    90

    capacitor voltage

    0.002 0.00053.6

    1.

    0

    5000.0

    CB1

    IaCIa

    Ea

    Time(s)

    Voltage

    (kV)

  • 7/30/2019 proj_62_vkau001_2

    5/8

    TIME

    A

    B

    Compar-ator

    TIME

    A

    B

    Compar-ator

    Open ABC

    D

    +

    F

    +

    Restrike Duration

    A

    B

    Compar-ator

    TIME

    C+

    D+

    F

    +

    Open CB Control

    CBC22a

    CBC22c

    CBC22b

    Restrike start

    Figure 11. Restrike Control for Case 1A

    The last slider labeled Restrike Duration governs how

    long restrike lasts and is set to 0.02s. As a result of this

    control device, restrike only occurs on phases A and C,

    while the circuit breaker for phase B opens with no suchoccurrence. The peak voltages affecting the capacitor

    banks and other components were noted. This simulation

    was then repeated in the presence of surge arresters

    connected phase-to-ground. The results of this

    simulation can are compared in Table 1.

    7.2. Case 1B

    Figure 12. Steps taken to complete Case 1B

    Simulations were carried out with the two proposed 5th

    harmonic filter banks (C21 & C26) and the existing

    capacitor banks (C22 & C25). A restrike occurred on

    circuit breaker connecting C21 to the 220kV bus while

    isolating the capacitor bank (refer to Figure 13). In this

    case restrike occurred on phase A half a cycle later and

    was 20mS in duration. The same simulation was then

    repeated in the presence of surge arresters. The

    placement of these surge arresters was altered in the

    following ways:

    (i) Connected from the capacitor side of thecircuit breaker to ground (CapGnd).

    (ii) Across the capacitor section (CapSec)

    48 kV surge arresters were also placed across the tuning

    reactors.

    CBC21Ia

    CBC21a

    CBC21Ib

    CBC21b

    CBC21Ic

    CBC21c

    0.41

    0.1125

    3.6

    0.41

    0.1125

    0.41

    0.1125

    3.6

    3.6

    Figure 13. Connection of Capacitor Bank C21

    The sliders in the control device in Figure 14 are the

    same as those for Case 1A. The difference is that for

    Case 1B, restrike only occurs on phase A of circuit

    breaker CBC21.

    TIME

    A

    B

    Compar-ator

    TIME

    A

    B

    Compar-ator

    Open ABC

    D +

    F

    +

    Restrike Duration

    A

    B

    Compar-ator

    TIMEC

    +D

    +

    F

    +

    Open CB Control

    CBC21a

    CBC21c

    CBC21b

    Restrike Start

    Figure 14. Restrike Control for Case 1B

    7.3.ResultsThe following are the results from the case studies Case

    1A and Case 1B.

    Without

    SA(PU)

    With

    SA(PU)

    220Kv Bus 1.59 1.48

    66Kv Bus 1.23 1.19

    33Kv Bus 1.52 1.44

    C25 voltage 1.96 1.51

    C25 Current 45.84 45.02

    C22 Voltage 2.17 1.71

    C22 Current 48.77 45.63

    T3 Tertiary Line Voltage 1.12 1.1

    SVC current 1.94 1.8

    SVC 5th filter current 1.80 1.64

    SVC 7th filter current 3.51 3.14

    Table 1. Case 1A (existing capacitor banks)

    CASE 1B

    Restrike

    With surge

    arrester (SA)

    Without surge

    arrester (SA)

    SA-capacitor to

    ground

    SA-capacitor

    section

  • 7/30/2019 proj_62_vkau001_2

    6/8

    Table 2. Case 1B (new and existing capacitor banks)

    Figure 15. Circuit breaker voltage waveforms

    Figure 16. Circuit breaker voltage waveform with SA

    In Figures 15 and 16, the peak voltage across the circuit

    breaker reduces from -657.38 kV to -429.56 kV. This is

    the TRV voltage that builds up across the circuit

    breakers during a restrike.

    8. DiscussionAs can be noted from Table 1, surge voltages reduced

    proportionally after the addition of surge arresters.Because a surge arrester is a non-linear resistor, a high

    reduction in voltage is made only when the overvoltage

    is extremely high. This is evident from the results in

    Table 1 and 2.

    It was observed that the currents in C22 & C25 were

    very high while C22 was being de-energized. This

    occurred due to the back-to-back switching of capacitor

    banks C22 & C25. The factor limiting these inrush

    currents is the inductance between these two banks [5].

    However this impedance was very low (0.002 + 0.0005j)

    and hence there was a very high frequency current of the

    order 45.84pu and 48.77pu rushing in the existing

    capacitor banks. In order to investigate this further, the

    impedance was increased to 0.02 + 0.005j and the

    magnitude of inrush current reduced to 22.68pu.

    Changing the ungrounded connection of the old

    capacitor banks to a grounded connection did not create

    favorable results. The inrush currents remained the same

    as the previous values.

    It is not practically possible to change the connections of

    these components at Islington without a substantial

    investment being made in altering the connections.

    These observations should however be taken into

    account when installing new capacitor banks.

    From Table 2, it can be noted that the inrush currents

    entering the capacitor banks while de-energizing

    capacitor bank C21 have reduced. This is due to the fact

    that the new capacitor banks are 5th

    filter banks and the

    inductance of the tuning reactor is 0.41 + 0.1125j. This

    high impedance limits the currents and protects the

    capacitor banks. However, there is a rise in current in

    the existing capacitor banks C25 and C22 after the

    addition of surge arresters. The value for the tuning

    reactor was increased to 0.41 + 0.1125j for the old

    capacitor banks and this inrush currents reduced from

    approximately 12.55pu to 1.93pu for both the capacitor

    banks C22 & C25. This finding also supports thefindings in Case 1A mentioned earlier.

    There was not any marked difference in the voltage

    peaks after altering the placement of surge arresters

    (CapGnd-CapSec). Both configurations provided the

    same amount of protection for the circuit components.

    Without

    SA(P.U.)

    With

    SA(P.U.)

    With

    SA(P.U.)

    CapGnd CapSec

    220Kv Bus 1.17 1.07 1.06

    66Kv Bus 1.10 1.06 1.06

    33Kv Bus 1.07 1.03 1.03

    C25 voltage 1.08 1.04 1.04

    C25 Current 2.25 12.55 12.64

    C21 Voltage 2.40 1.24 1.24

    C21 Current 8.20 2.27 2.29

    C26 Voltage 2.31 1.23 1.23

    C26 Current 7.26 2.31 2.41

    C22 Voltage 1.09 1.03 1.02

    C22 Current 2.26 12.41 12.45

    T3 Tertiary Line

    Voltage 1.14 1.04 1.05

    SVC current 1.64 1.33 1.34

    SVC 5th filter

    current 1.78 1.36 1.36

    SVC 7th filter

    current 1.59 1.39 1.39

    0.525 0.550 0.575 0.600 0.625 0.650 0.675 0.700

    -600

    -300

    0

    300

    600CB C21 Voltage

    0.525 0.550 0.575 0.600 0.625 0.650 0.675 0.700

    -600

    -300

    0

    300

    600

    CBC21 Voltage

    Voltage

    (kV)

    Voltage

    (kV)

    Time(s)

    Time(s)

  • 7/30/2019 proj_62_vkau001_2

    7/8

    9. Energy CalculationsThe energy being absorbed by the surge arrester (Table

    3 & 4) was calculated by placing a voltage and current

    probe at the arrester and measuring the Vpk and Ipk

    entering this arrester. These two values were then

    multiplied by the time it took the surge to settle down to

    the system voltage. In the case of restrike, this was 20

    ms.

    Energy = Vpk* Ipk* t (1)

    Measured

    Parameters

    Energy Absorption (kJ) for 216kV

    and 198kV rated SA

    Restrike(216kV) Restrike(198kV

    C22 17.118 26.127C25 17.119 26.127C21 31.714 42.896C26 17.119 26.132

    Table 3. Maximum energy absorbed during Restrike

    Measured

    Parameters Energy Absorption (kJ)

    Bus Fault(216kV) Bus Fault(198kV)

    C22 1240.204 5609.126C25 1240.204 5609.126C21 1246.613 6303.676C26 1246.562 6304.666

    Table 4. Maximum energy absorbed during Bus Fault

    The energy absorption capabilities of both the surge

    arresters have been mentioned below:

    SA Energy Rating (216kV) = 1555.2kJ

    SA Energy Rating (198kV) = 1425.6kJ

    The energy absorbed by the surge arrester during

    restrike was less than that during bus fault. This was

    mainly due to the difference in duration of these two

    scenarios. The bus fault lasted 300ms while the restrike

    only lasted 20ms. Also the peak currents produced

    during bus fault were higher than the peak currents

    produced during restrike.

    The 216kV rated surge arrester would be a better option

    to use, as the maximum energy absorbed by the surge

    arrester in a worst case scenario was 1246.613kJ, which

    is well below its energy rating of 1555.2kJ.

    10.ConclusionsTransients that were generated during restrike have been

    successfully controlled with the addition surge arresters.

    The 216kV surge arrester performed better than the

    198kV surge arrester.

    Altering the placement of surge arresters did not supply

    any marked differences. Either of the two connections

    can be used for the new capacitor banks.

    The peak voltage (TRV) across the circuit breaker

    during a restrike reduced from -657.38 kV to -429.56

    kV.

    11.RecommendationsIt is recommended that in order to reduce the generation

    of transients, inductances between capacitor banks

    should be increased. Also controlled switching should be

    incorporated in order to ensure that switching does not

    occur at zero current crossings.

    Future capacitor banks should be connected in a

    grounded star connection.

  • 7/30/2019 proj_62_vkau001_2

    8/8

    Acknowledgements

    I would like to thank the following people:

    Dr. Nirmal Nair: for his guidance and support during the

    course of this project.

    Mr. Nihal Kularatna: for his advice on how to start a

    project effectively.

    Deeksha Srivastava: who has been a pleasure to work

    with these past few months.

    12.References[1] Deller, R. (2005) Proposed B.E. Final year project

    on 220kV Islington Capacitor bank switching studies,

    Transpower New Zealand Ltd.

    [2] Shwehdi, M. H. and Sultan, M. R. (2000) Power

    Factor Correction Capacitors; Essentials and Cautions

    Power Engineering Society Summer Meeting, 2000.

    IEEE Volume 3, 16-20 July 2000 Page(s):1317 - 1322

    [3] Greenwood, A. (1971) Electrical Transients in

    Power Systems John Wiley & Sons, New York.

    [4] IEEE guide for Application of Shunt Power

    Capacitors (1992). IEEE std. 1036-1992. Transmission

    and distribution committee of the IEEE Power

    Engineering Society.

    [5] IEEE Guide for the Protection of Shunt Capacitor

    Banks (2000). IEEE std. std C37.99-2000. Power

    System Relaying Committee of the IEEE Power

    Engineering Society.

    [6] IEEE Guide for the Application of Metal-OxideSurge Arresters for Alternating-Current Systems

    (1997). IEEE std. C62.22-1997. Surge protectivedevices committee of the IEEE Power Engineering

    Society.

    Appendix 1

    The single phase circuit in the column below illustrates

    the connections of the capacitor banks at Islington.

    They are all connected to each other through the 220kV

    bus line. The existing capacitor banks are C22 and C25

    and the proposed capacitor banks are C21 and C26.