03_pert cpm
TRANSCRIPT
-
7/31/2019 03_Pert cpm
1/28
CPM/PERT
Project Planning and AppraisalM. Arch
SCET, Surat
Prof. BhaskER V. Bhatt
-
7/31/2019 03_Pert cpm
2/28
ProjectA project is a series of activities directed toaccomplishment of a desired objective .
One definition of a project:A project is a temporary endeavor undertaken to create a "unique"product or service
Plan your work first..then work your plan
-
7/31/2019 03_Pert cpm
3/28
What is ProjectManagement?
The application of a collection of tools and techniques todirect the use of diverse resources towards theaccomplishment of a unique, complex, one time task withintime, cost and quality constraints.
Its origins lie in World War II, when the military authoritiesused the techniques of operational research to plan theoptimum use of resources.
One of these techniques was the use of networks torepresent a system of related activities
-
7/31/2019 03_Pert cpm
4/28
or rea ownStructure
A method of breaking down a project into individualelements ( components, subcomponents, activities andtasks) in a hierarchical structure which can be scheduledand cost
It defines tasks that can be completed independently of other tasks, facilitating resource allocation, assignment of responsibilities and measurement and control of the project
It is foundation of project planning
It is developed before identification of dependencies and
estimation of activity durationsIt can be used to identity the tasks in the CPM and PERT
-
7/31/2019 03_Pert cpm
5/28
Work Breakdown Structure for Computer Order Processing System Project
-
7/31/2019 03_Pert cpm
6/28
Project Scheduling and ControlTechniques
Network analysis is the general name given to certain specifictechniques which can be used for the planning, management andcontrol of projects.
Gantt Chart
Critical Path Method (CPM)
Program Evaluation and Review Technique (PERT)
-
7/31/2019 03_Pert cpm
7/28
-
7/31/2019 03_Pert cpm
8/28
History
Developed in 1950s CPM by DuPont for chemical plantsPERT by U.S. Navy for Polaris missile
PERT was developed by the US Navy for the planning and control of the Polaris missile program and the emphasis was on completing theprogram in the shortest possible time. In addition PERT had theability to cope with uncertain activity completion times (e.g. for aparticular activity the most likely completion time is 4 weeks but itcould be anywhere between 3 weeks and 8 weeks).
CPM was developed by Du Pont and the emphasis was on thetrade-off between the cost of the project and its overallcompletion time (e.g. for certain activities it may be possible
to decrease their completion times by spending more money -how does this affect the overall completion time of theproject?)
-
7/31/2019 03_Pert cpm
9/28
CPM - Critical Path Method
Definition: In CPM activities are shown as a network of precedence relationships using activity-on-nodenetwork construction
Single estimate of activity timeDeterministic activity times
USED IN : Production management - for the jobs of repetitive in nature where the activity time estimatescan be predicted with considerable certainty due tothe existence of past experience.
-
7/31/2019 03_Pert cpm
10/28
-
7/31/2019 03_Pert cpm
11/28
Originated by H.L.Gantt in 1918
Gantt chart
Advantages- Gantt charts are quite commonly used.They provide an easy graphicalrepresentation of when activities (might)take place.
Limitations- Do not clearly indicate details regardingthe progress of activities
- Do not give a clear indication of interrelation ship between the separateactivities
-
7/31/2019 03_Pert cpm
12/28
CPM/PERT
These deficiencies can be eliminated to a large extent byshowing the interdependence of various activities bymeans of connecting arrows called network technique.
Overtime CPM and PERT became one technique
ADVANTAGES:Precedence relationshipslarge projectsmore efficient
-
7/31/2019 03_Pert cpm
13/28
The Project NetworkUse of nodes and arrows
Arrows An arrow leads from tail to head directionallyIndicate ACTIVITY, a time consuming effort that is required toperform a part of the work.
Nodes A node is represented by a circle- Indicate EVENT, a point in time where one or more activities
start and/or finish. Activity
A task or a certain amount of work required in the project
Requires time to complete Represented by an arrow
Dummy Activity Indicates only precedence relationships Does not require any time of effort
-
7/31/2019 03_Pert cpm
14/28
Project Network Event
Signals the beginning or ending of an activity Designates a point in time Represented by a circle (node)
Network
Shows the sequential relationships among activities usingnodes and arrows
Activity-on-node (AON) Nodes represent activities, and arrows show precedence
relationships
Activity-on-arrow (AOA) Arrows represent activities and nodes are events for points in
time
-
7/31/2019 03_Pert cpm
15/28
AOA Project Network for House
3 2 0
1 3
1 11
1 2 4 6 7
3
5
Lay foundation
Design house and obtain financing
Order and receive materials
Dummy
Finishwork
Select carpet
Select paint
Build house
AON Project Network for House
1 3
2
2
4 3
31 5
1
6 1
7 1Start
Design house and obtain financing
Order and receive materials Select paintSelect carpet
Lay foundations Build house
Finish work
-
7/31/2019 03_Pert cpm
16/28
A B
C
A must finish before either B or C can
start A
B
C both A and B must finish before C can start
D
C
B
A both A and B must finish before either of C or D can start
A
C
B
D
Dummy A must finish before B can start
both A and C must finish before D can start
Situations in network diagram
-
7/31/2019 03_Pert cpm
17/28
Concurrent Activities
2 3
Lay foundation
Order material
(a) Incorrect precedence relationship
(b) Correct precedence relationship
3
4 2
Dummy Lay foundation
Order material
1
2 0
-
7/31/2019 03_Pert cpm
18/28
-
7/31/2019 03_Pert cpm
19/28
Critical Path
Is that the sequence of activities and events where there isno slack i.e.. Zero slack
Longest path through a networkminimum project completion time
-
7/31/2019 03_Pert cpm
20/28
Benefits of CPM/PERT
Useful at many stages of project managementMathematically simpleGive critical path and slack timeProvide project documentationUseful in monitoring costs
-
7/31/2019 03_Pert cpm
21/28
Questions Answered by CPM & PERT
Completion date?On Schedule?Within Budget?Critical Activities?How can the project be finished early at the least cost?
-
7/31/2019 03_Pert cpm
22/28
-
7/31/2019 03_Pert cpm
23/28
For clarity, this list is kept to a minimum by specifying onlyimmediate relationships, that is relationships involving activitiesthat " occur near to each other in time".
-
7/31/2019 03_Pert cpm
24/28
"What activities must be finished before this activity can start"
could we complete this project in 30 weeks?
could we complete this project in 2 weeks?
One answer could be, if we first do activity 1, then activity 2, then activity 3,...., then activity 10, then activity 11 and the project would then take the sumof the activity completion times, 30 weeks.
What is the minimum possible time in which we can complete this project ?
Before starting any of the above activity, the questionsasked would be
-
7/31/2019 03_Pert cpm
25/28
We shall see below how the network analysis diagram/picture we constructhelps us to answer this question.
-
7/31/2019 03_Pert cpm
26/28
CRITICAL PATH TAKES24 WEEKS FOR THE COMPLETION OF THE PROJECT
-
7/31/2019 03_Pert cpm
27/28
Limitations to CPM/PERT
Clearly defined, independent and stableactivitiesSpecified precedence relationshipsOver emphasis on critical paths
-
7/31/2019 03_Pert cpm
28/28
Thank you