03_pert cpm

Upload: hemal-gandhi

Post on 05-Apr-2018

227 views

Category:

Documents


1 download

TRANSCRIPT

  • 7/31/2019 03_Pert cpm

    1/28

    CPM/PERT

    Project Planning and AppraisalM. Arch

    SCET, Surat

    Prof. BhaskER V. Bhatt

  • 7/31/2019 03_Pert cpm

    2/28

    ProjectA project is a series of activities directed toaccomplishment of a desired objective .

    One definition of a project:A project is a temporary endeavor undertaken to create a "unique"product or service

    Plan your work first..then work your plan

  • 7/31/2019 03_Pert cpm

    3/28

    What is ProjectManagement?

    The application of a collection of tools and techniques todirect the use of diverse resources towards theaccomplishment of a unique, complex, one time task withintime, cost and quality constraints.

    Its origins lie in World War II, when the military authoritiesused the techniques of operational research to plan theoptimum use of resources.

    One of these techniques was the use of networks torepresent a system of related activities

  • 7/31/2019 03_Pert cpm

    4/28

    or rea ownStructure

    A method of breaking down a project into individualelements ( components, subcomponents, activities andtasks) in a hierarchical structure which can be scheduledand cost

    It defines tasks that can be completed independently of other tasks, facilitating resource allocation, assignment of responsibilities and measurement and control of the project

    It is foundation of project planning

    It is developed before identification of dependencies and

    estimation of activity durationsIt can be used to identity the tasks in the CPM and PERT

  • 7/31/2019 03_Pert cpm

    5/28

    Work Breakdown Structure for Computer Order Processing System Project

  • 7/31/2019 03_Pert cpm

    6/28

    Project Scheduling and ControlTechniques

    Network analysis is the general name given to certain specifictechniques which can be used for the planning, management andcontrol of projects.

    Gantt Chart

    Critical Path Method (CPM)

    Program Evaluation and Review Technique (PERT)

  • 7/31/2019 03_Pert cpm

    7/28

  • 7/31/2019 03_Pert cpm

    8/28

    History

    Developed in 1950s CPM by DuPont for chemical plantsPERT by U.S. Navy for Polaris missile

    PERT was developed by the US Navy for the planning and control of the Polaris missile program and the emphasis was on completing theprogram in the shortest possible time. In addition PERT had theability to cope with uncertain activity completion times (e.g. for aparticular activity the most likely completion time is 4 weeks but itcould be anywhere between 3 weeks and 8 weeks).

    CPM was developed by Du Pont and the emphasis was on thetrade-off between the cost of the project and its overallcompletion time (e.g. for certain activities it may be possible

    to decrease their completion times by spending more money -how does this affect the overall completion time of theproject?)

  • 7/31/2019 03_Pert cpm

    9/28

    CPM - Critical Path Method

    Definition: In CPM activities are shown as a network of precedence relationships using activity-on-nodenetwork construction

    Single estimate of activity timeDeterministic activity times

    USED IN : Production management - for the jobs of repetitive in nature where the activity time estimatescan be predicted with considerable certainty due tothe existence of past experience.

  • 7/31/2019 03_Pert cpm

    10/28

  • 7/31/2019 03_Pert cpm

    11/28

    Originated by H.L.Gantt in 1918

    Gantt chart

    Advantages- Gantt charts are quite commonly used.They provide an easy graphicalrepresentation of when activities (might)take place.

    Limitations- Do not clearly indicate details regardingthe progress of activities

    - Do not give a clear indication of interrelation ship between the separateactivities

  • 7/31/2019 03_Pert cpm

    12/28

    CPM/PERT

    These deficiencies can be eliminated to a large extent byshowing the interdependence of various activities bymeans of connecting arrows called network technique.

    Overtime CPM and PERT became one technique

    ADVANTAGES:Precedence relationshipslarge projectsmore efficient

  • 7/31/2019 03_Pert cpm

    13/28

    The Project NetworkUse of nodes and arrows

    Arrows An arrow leads from tail to head directionallyIndicate ACTIVITY, a time consuming effort that is required toperform a part of the work.

    Nodes A node is represented by a circle- Indicate EVENT, a point in time where one or more activities

    start and/or finish. Activity

    A task or a certain amount of work required in the project

    Requires time to complete Represented by an arrow

    Dummy Activity Indicates only precedence relationships Does not require any time of effort

  • 7/31/2019 03_Pert cpm

    14/28

    Project Network Event

    Signals the beginning or ending of an activity Designates a point in time Represented by a circle (node)

    Network

    Shows the sequential relationships among activities usingnodes and arrows

    Activity-on-node (AON) Nodes represent activities, and arrows show precedence

    relationships

    Activity-on-arrow (AOA) Arrows represent activities and nodes are events for points in

    time

  • 7/31/2019 03_Pert cpm

    15/28

    AOA Project Network for House

    3 2 0

    1 3

    1 11

    1 2 4 6 7

    3

    5

    Lay foundation

    Design house and obtain financing

    Order and receive materials

    Dummy

    Finishwork

    Select carpet

    Select paint

    Build house

    AON Project Network for House

    1 3

    2

    2

    4 3

    31 5

    1

    6 1

    7 1Start

    Design house and obtain financing

    Order and receive materials Select paintSelect carpet

    Lay foundations Build house

    Finish work

  • 7/31/2019 03_Pert cpm

    16/28

    A B

    C

    A must finish before either B or C can

    start A

    B

    C both A and B must finish before C can start

    D

    C

    B

    A both A and B must finish before either of C or D can start

    A

    C

    B

    D

    Dummy A must finish before B can start

    both A and C must finish before D can start

    Situations in network diagram

  • 7/31/2019 03_Pert cpm

    17/28

    Concurrent Activities

    2 3

    Lay foundation

    Order material

    (a) Incorrect precedence relationship

    (b) Correct precedence relationship

    3

    4 2

    Dummy Lay foundation

    Order material

    1

    2 0

  • 7/31/2019 03_Pert cpm

    18/28

  • 7/31/2019 03_Pert cpm

    19/28

    Critical Path

    Is that the sequence of activities and events where there isno slack i.e.. Zero slack

    Longest path through a networkminimum project completion time

  • 7/31/2019 03_Pert cpm

    20/28

    Benefits of CPM/PERT

    Useful at many stages of project managementMathematically simpleGive critical path and slack timeProvide project documentationUseful in monitoring costs

  • 7/31/2019 03_Pert cpm

    21/28

    Questions Answered by CPM & PERT

    Completion date?On Schedule?Within Budget?Critical Activities?How can the project be finished early at the least cost?

  • 7/31/2019 03_Pert cpm

    22/28

  • 7/31/2019 03_Pert cpm

    23/28

    For clarity, this list is kept to a minimum by specifying onlyimmediate relationships, that is relationships involving activitiesthat " occur near to each other in time".

  • 7/31/2019 03_Pert cpm

    24/28

    "What activities must be finished before this activity can start"

    could we complete this project in 30 weeks?

    could we complete this project in 2 weeks?

    One answer could be, if we first do activity 1, then activity 2, then activity 3,...., then activity 10, then activity 11 and the project would then take the sumof the activity completion times, 30 weeks.

    What is the minimum possible time in which we can complete this project ?

    Before starting any of the above activity, the questionsasked would be

  • 7/31/2019 03_Pert cpm

    25/28

    We shall see below how the network analysis diagram/picture we constructhelps us to answer this question.

  • 7/31/2019 03_Pert cpm

    26/28

    CRITICAL PATH TAKES24 WEEKS FOR THE COMPLETION OF THE PROJECT

  • 7/31/2019 03_Pert cpm

    27/28

    Limitations to CPM/PERT

    Clearly defined, independent and stableactivitiesSpecified precedence relationshipsOver emphasis on critical paths

  • 7/31/2019 03_Pert cpm

    28/28

    Thank you