2. power grid construction | 电网建设

23
China Southern Power Grid Co., Ltd 中国南方电网有限责任公司 March 2015 20153Progress Report of Qianhai Smart Grid Construction 前海智能电网建设情况汇报

Upload: vuonganh

Post on 13-Feb-2017

298 views

Category:

Documents


7 download

TRANSCRIPT

Page 1: 2. Power Grid Construction | 电网建设

China Southern Power Grid Co., Ltd 中国南方电网有限责任公司

March 2015 2015年3月

Progress Report of Qianhai Smart Grid Construction

前海智能电网建设情况汇报

Page 2: 2. Power Grid Construction | 电网建设

Contents | 目录

1. Urban Construction | 城市建设

2. Power Grid Construction | 电网建设

Page 3: 2. Power Grid Construction | 电网建设

前海基本情况

一、项目背景

Vision Plan of Qianhai | 前海远景规划图

Baoan district 宝安区

Nanshan district 南山区 Guiwan district

桂湾片区

Qianwan district 前湾片区

Mawan district 妈湾片区

Page 4: 2. Power Grid Construction | 电网建设

Land Grant | 土地出让

1. Urban Construction | 城市建设

Land Grant Situation: 前海土地出让情况:

Qianhai has made rapid

progress. By now, Qianhai

Authority has leased 18 pieces

of land within Unit 1, 2, 5, 9,

11 and 19, covering 1,058,800

km2.

前海已进入快速发展阶段,截

止目前,前海管理局已出让一、二、

五、九、十一、十九单元的18块地,

用地面积约105.88万平米。

Page 5: 2. Power Grid Construction | 电网建设

Projects under Construction | 在建项目

1. Urban Construction | 城市建设

Construction Projects in Qianhai: 前海在建项目:

No. | 序号 Projects | 项目

1 Qianhai Vanke Residence

前海万科公馆

2 Qianhai Young Men's Dream

Factory 前海青年梦工厂

3 Huarun Qianhai Center

华润前海中心

4 Zhuoyue Qianhai Center

卓越前海中心

5

Qianhai 1-4 Municipal Bid (Centralized Refrigeration

Station) 前海市政1-4标 (集中供冷站)

Zhuoyue Qianhai Center

卓越前海中心 Huarun Qianhai

Center 华润前海中心 Centralized

Refrigeration Station

集中供冷站

Qianhai Vanke Residence 万科企业公馆

Qianhai Young Men's

Dream Factory 前海青年梦工厂

Guiwan 桂湾

Qianwan前湾

Mawan妈湾

Page 6: 2. Power Grid Construction | 电网建设

Projects under Construction | 在建项目

1. Urban Construction | 城市建设

Qianhai Vanke Residence 前海万科企业公馆

Qianhai Young Men's Dream Factory 前海青年梦工厂

Page 7: 2. Power Grid Construction | 电网建设

Projects under Construction | 在建项目

1. Urban Construction | 城市建设

Zhuoyue Qianhai Center 卓越前海中心

Huarun Qianhai Center 华润前海中心

Page 8: 2. Power Grid Construction | 电网建设

A Glance of Qianhai | 前海剪影

1. Urban Construction | 城市建设

Page 9: 2. Power Grid Construction | 电网建设

Contents | 目录

1. Urban Construction | 城市建设

2. Power Grid Construction | 电网建设

Page 10: 2. Power Grid Construction | 电网建设

Temporary Power Supply | 临时供电

2. Power Grid Construction | 电网建设

Huahui Substation

花卉站

Guiwan 桂湾

Qianwan前湾

Mawan妈湾

10860kVA of temporary electricity capacity supplied by F28 of 110kV Huahui substation, has accessed to the power grid.

目前已接入临时用电容量10860kVA;由110kV花卉变电站F28专线供电。

10855kVA of electricity capacity has requested and waiting for installation, which planed to be supplied by the new feeder line of 110KV Baitian substation.

已报装但尚未接入容量10855kVA;计划由110kV白田变电站新出专线供电。

A large amount of power consumption for construction is estimated to be accessed in 2015, which will be supplied by new feeder lines.

预计2015年将有大量施工用电接入,届时将新出专线供电。

Temporary Power Supply Scheme : 临时供电方案:

Baitian Substation

白田站

Page 11: 2. Power Grid Construction | 电网建设

Permanent power supply: demands | 永久用电——需求

No. 序号

Projects 项目

Capacity 容量

Time 用电时间

1 Qianhai Vanke

Residence 前海万科企业公馆

7660 2014.10

2 Qianhai Young Men's

Dream Factory 前海青年梦工厂

4100 2014.12

3

Centralized Refrigeration Station

(Unit 2) 二单元集中供冷

18000 2016.3

4 Huarun Qianhai

Center 华润前海中心

38500 2016.2

5 Zhuoyue Qianhai

Center 卓越前海中心

12800 2016.2

1. Demands for permanent power supply in Qianhai ( Projects ) 1. 前海永久用电需求(项目)

2. Power Grid Construction | 电网建设

Zhuoyue Qianhai Center

卓越前海中心 Huarun Qianhai

Center 华润前海中心 Centralized

Refrigeration Station

集中供冷站

Qianhai Vanke Residence

前海万科企业公馆 Qianhai Young

Men's Dream Factory 前海青年梦工厂

Guiwan 桂湾

Qianwan前湾

Mawan妈湾

Page 12: 2. Power Grid Construction | 电网建设

Permanent power supply: demands | 永久用电——需求

2. Power Grid Construction | 电网建设

Centralized Refrigeration Stations Location Planning

前海集中供冷站选址规划

Stations 冷站

Max. Cooling Capacity (ton)

最大制冷量(冷吨) Service Area | 供冷区域

No. 1 48000 Unit 1 1单元

No. 2 49000 Unit 2 2单元

No. 3 45000 Block 1-2 Unit 1; Block 1-6 Unit 4 1单元1-2街坊,4单元1-6街坊

No. 4 32000 Block 3 Unit 1; Block 7-9 Unit 4 1单元3街坊,4单元7-9街坊

No. 5 50000 Unit 7; Unit 10; Block 1 Unit 9 7、10单元及9单元1街坊

No. 6 50000 Unit 9 (except block 1) 9单元1街坊以外部分

No. 7 60000 Unit 16 16单元

No. 8 47500 Unit 18 18单元

No. 9 31500 Unit 20 20单元

2

Centralized Refrigeration Stations Planning 集中供冷站规划

Page 13: 2. Power Grid Construction | 电网建设

Permanent Power Supply: Installation | 永久用电——报装

2. Power Grid Construction | 电网建设

2. Status of power supply points’ installation in Qianhai : 2. 前海永久用电报装情况:

Qianhai Vanke Residence

前海万科企业公馆

Qianhai Young Men's Dream Factory 前海青年梦工厂

Huarun Qianhai Center

华润前海中心

Zhuoyue Qianhai Center

卓越前海中心

Qianhai Vanke Residence : 7760kVA ;

前海万科企业公馆:7760kVA ;

Qianhai Young Men's Dream Factory : 4100kVA ;

前海青年梦工厂:4100kVA ;

Centralized Refrigeration Station : 18000kVA ;

集中供冷站:18000kVA ;

Zhuoyue Qianhai Center : 12800kVA .

卓越前海中心:12800kVA .

Page 14: 2. Power Grid Construction | 电网建设

Power supply scheme | 供电方案

2. Power Grid Construction | 电网建设

3. Power supply scheme : 3. 供电方案:

Transitional Stage Power supply scheme : step-down operation ;

前海永久用电过渡方案:降压运行;

Transformer: 10/20kV double-tap distribution transformer is selected ;

变压器:应选用10/20kV双抽头式配变;

Ring Main Unit: voltage level of 20kV is selected ;

环网柜:等中压设备选用20kV电压等级;

Cable: voltage level of 10kV is selected .

电缆:选用10kV电压等级。

Page 15: 2. Power Grid Construction | 电网建设

Connection Mode | 接线方式

2. Power Grid Construction | 电网建设

4. Connection mode of medium-voltage distribution (2-line closed loop with additional available connection) 4. 中压配电网接线模型(二线合环+联络线)

K1

#1 #2

K2 K3

#3 #4

K4K5 K6K8

K9 K10

K11 K12

变电站1 变电站2

K7

K1

#1 #2

K2 K3

#3 #4

K4K5 K6K8

K9 K10

K11 K12

K7

Substation 1 Substation 2

Page 16: 2. Power Grid Construction | 电网建设

Connection Mode | 接线方式

2. Power Grid Construction | 电网建设

4. Connection Mode : case 1 ( based on the present 110kV substation )

4. 接线方式——案例1(利用现有110kV变电站)

Baitian Substation 白田变电站

Qianhai Vanke Residence 前海万科企业公馆

7660kVA 4100kVA

Nanshan Substation 南山变电站

Qianhai Young Men's Dream Factory 前海青年梦工厂

Page 17: 2. Power Grid Construction | 电网建设

Connection Mode | 接线方式

2. Power Grid Construction | 电网建设

Guiwan 1# Substation 桂湾1变电站

18000kVA

Zhuoyue Qianhai Center 卓越前海中心

Centralized Refrigeration Station 集中供冷站

6400kVA 6400kVA

4. Connection Mode : case 2 ( based on new 220/20 kV substation )

4. 接线方式——案例2(新建220/20 kV变电站)

Page 18: 2. Power Grid Construction | 电网建设

Substation | 变电站

2. Power Grid Construction | 电网建设

5. Substation : Location Planning 5. 变电站——布点规划

110千伏白田站

妈湾1

妈湾4

妈湾3

妈湾2

铲湾3

星海(桂湾4)

桂湾3

桂湾2

兴怀(桂湾1)

铲湾2

铲湾1

110千伏妈湾站

110千伏蛇口站

110千伏一湾站

110千伏工业八路站

甲岸站 220千伏变电站

110千伏变电站

规划地铁变电站

招商局所属变电站

11 sites of 220kV substation are located

in Qianhai, 4 in Guiwan, 3 in Qianwan and

4 in Mawan respectively. 10 of them are

220/20kV substations, and the rest one is

a 220/110/20kV substation. 3720MVA of

electricity capacity is newly installed.

规划11座220千伏变电站,在桂湾、前湾、妈湾

三个片区分别布置4、3、4座变电站。其中

220/20千伏变电站10座,220/110/20千伏变电

站1座,新增变电容量372万千伏安。

Page 19: 2. Power Grid Construction | 电网建设

Substation | 变电站

2. Power Grid Construction | 电网建设

5. Substation: Production Time 5. 变电站——投产时间

Substation | 变电站 Planned Production Time

计划投产时间

Guiwan 1# Substation 桂湾一站

2015.09

Guiwan 4# Substation 桂湾四站

2015.11

Guiwan 桂湾

Qianwan前湾

Mawan妈湾

Guiwan 1# Substation

桂湾一站 Guiwan 4# Substation

桂湾四站

Page 20: 2. Power Grid Construction | 电网建设

Distributed Generation | 分布式电源

2. Power Grid Construction | 电网建设

6. DG Planning 6. 分布式电源规划

Guiwan 桂湾

Qianwan 前湾

PV : 10000 kW

Mawan 妈湾

10 MW photovoltaic power generation

project will be built in the Mawan district.

前海妈湾片区规划有10000kW光伏发电项目。

BAPV | 屋顶光伏发电

Page 21: 2. Power Grid Construction | 电网建设

Overhead Lines Undergrounding | 架空线下地

2. Power Grid Construction | 电网建设

7. overhead lines undergrounding project 7. 架空线下地工程

妈湾电厂

欢乐站

南热电厂

白田站

月亮湾电厂

妈贤甲乙线

妈岸甲乙线

妈欢甲乙线

欢西甲乙线

荆岸甲乙线

南热、仙热ⅠⅡ线

欢热ⅠⅡ线

甲岸站

Purpose : cooperate the city construction

目的:配合前海城市开发建设

project scale : HV overhead lines

undergrounding project covers 8 circuits

of 220kV overhead lines and 4 circuits of

110kV overhead lines

规模:高压架空线下地工程涉及前海范围内的8

回220千伏架空线路和4回110千伏架空线路;

Production time : the end of 2015

计划完成时间:2015年底。

Page 22: 2. Power Grid Construction | 电网建设

Business Card|名片

Contact Information|联系人信息

CSG

Dr. Fengshun Jiao

Shenzhen Power Supply Co., Ltd, CSG. Addr: No. 39, Center 1 Road, Futian district, Shenzhen 518000, P. R. China Tel: +86 136 0308 7681 Email: [email protected]

Page 23: 2. Power Grid Construction | 电网建设

Thank you for your attention!

汇报完毕,谢谢!