allantayengmanmfka2006tht
TRANSCRIPT
-
7/29/2019 AllanTayEngManMFKA2006THT
1/162
INDUSTRIALISED BUILDING SYSTEM FORMATION
SCHEDULING FOR PUBLIC BUILDINGS
ALLAN TAY ENG MIAN
A project report submitted in partial fulfillment of the
requirements for the award of the Degree of
Master of Science (Construction Management)
Faculty of Civil Engineering
Universiti Teknologi Malaysia
-
7/29/2019 AllanTayEngManMFKA2006THT
2/162
PPSSZZ 1199::1166 ((PPiinndd.. 11//9977))UUNNIIVVEERRSSIITTII TTEEKKNNOOLLOOGGII MMAALLAAYYSSIIAA
BORANG PENGESAHAN STATUS TESIS
J UDUL : INDUSTRIALISED BUILDING SYSTEM FORMATIONSCHEDULING FOR PUBLIC BUILDINGS
SESI PENGAJ IAN : 2005 / 2006
Saya
(HURUF BESAR)
mengaku membenarkan tesis (PSM/Sarjana/Doktor Falsafah)* ini disimpan di PerpustakaanUniversiti Teknologi Malaysia dengan syarat-syarat kegunaan seperti berikut:
1. Tesis adalah hakmilik Universiti Teknologi Malaysia.2. Perpustakaan Universiti Teknologi Malaysia dibenarkan membuat salinan untuk tujuan
pengajian sahaja.3. Perpustakaan dibenarkan membuat salinan tesis ini sebagai bahan pertukaran antara
institusi pengajian tinggi.4. ** Sila tanda ( )
SULIT (Mengandungi maklumat yang berdarjah keselamatan ataukepentingan Malaysia seperti yang termaktud di dalam
AKTA RAHSIA RASMI 1972)
TERHAD (Mengandungi maklumat yang TERHAD yang telah ditentukanoleh organisasi/badan di mana penyelidikan dijalankan)
TIDAK TERHAD
Disahkan oleh
(TANDATANGAN PENULIS) (TANDATANGAN PENYELIA)
Alamat Tetap:
PROF. MADYA DR. ABDUL KADIR
ALLAN TAY ENG MIAN
-
7/29/2019 AllanTayEngManMFKA2006THT
3/162
-
7/29/2019 AllanTayEngManMFKA2006THT
4/162
We hereby declare that I have read this project and in my opinion this project is
sufficient in terms of scope and quality for the award of the degree of Master of
Science (Construction Management) by taught course.
Signature :
Name of Supervisor I : ASSOC. PROF. DR. ABDUL KADIR
MARSONO
Date : April 2006
Signature :
Name of Supervisor II : DR. MASINE MD TAP
Date : April 2006
Signature :
Nameof Supervisor III : ASSOC PROF DR AHMAD
-
7/29/2019 AllanTayEngManMFKA2006THT
5/162
ii
I declared that this project report entitled INDUSTRIALISED BUILDING
SYSTEM FORMATION SCHEDULING FOR PUBLIC BUILDINGS is the result
of my own research expect as cited in references. This report has not been accepted
for any degree and is not concurrently submitted in candidature of any degree.
Signature :
Name : ALLAN TAY ENG MIAN
Date : APRIL 2006
-
7/29/2019 AllanTayEngManMFKA2006THT
6/162
iii
Especially to my beloved family
-
7/29/2019 AllanTayEngManMFKA2006THT
7/162
iv
ACKNOWLEDGEMENT
The author wish to express his sincere gratitude to all who have helpeddirectly or indirectly in his Masters Project research work, and a big thank you
especially to project supervisor, Associate Professor Dr. Abdul Kadir Marsono, for
his passionate assistance, guidance and concern. With his invaluable advice and
superb guidance, the author has successfully completed his Masters Project. It is
indeed a true honour and privilege for being able to work under the supervision ofsuch a dedicated and enthusiastic lecturer. Thank you Dr!
Special thanks are due to Dr. Masine Md Tap and Associate Professor Dr.
Ahmad Mahir Makhtar for their close guidance and assistance throughout the process
of carrying out the research work. Besides, the author would like to thank all parties
that have been so kindly in giving invaluable information and data to the author.
Special thanks are also due to Ir. Ihsan B. Atan, Construction Manager of Gerbang
Selatan Bersepadu Project, Pn. Naemah Bt. Abd. Jamil, JKR State Assistant
Director of Education Project, directors, project managers, supervisors and engineers
of Eastern Pretech (Malaysia) Sdn. Bhd., Precast Product Sdn. Bhd., Takenaka
Corporation (Malaysia) Sdn. Bhd., Jeks Engineering Sdn. Bhd., Pilot Construction
Sdn. Bhd. and staffs at JKR Johor State Headquarters for their invaluable help while
the author was carrying out the research work.
-
7/29/2019 AllanTayEngManMFKA2006THT
8/162
v
ABSTRACT
The construction industry plays a major role in our countrys economicgrowth. However, the industry is not without weaknesses. The challenges often
occur in the area of productivity, efficiency of work, quality of work and the delivery
of work. The intensive use of foreign unskilled workers, low technology equipments
and out-of-dated construction methods, have eventually caused low productivity and
inefficiency of work at construction site. IBS is one of the improved buildingsystems that are being introduced in the construction industry, to achieve the target
of faster completion with mass production of the building elements in places out of
its final location in a building. A study was conducted to analyse ways to improve
the implementation of IBS in terms of IBS scheduling at site for public buildings
especially schools in our country. A comparison between the scheduling of both theconventional method and the proposed IBS method was carried out using Microsoft
Project. The critical outputs in managing the scheduling of project such as time,
labour productivity and task factor were clearly analysed. Types of lifting system
were identified to ensure highest productivity and efficiency of work at site. Lastly,
comparative check of proposed new conceptual school building utilising standardIBS components with Uniform Building By-Law 1984 were also carried out in this
study.
-
7/29/2019 AllanTayEngManMFKA2006THT
9/162
vi
ABSTRAK
Industri pembinaan memainkan peranan yang penting di dalamperkembangan ekonomik negara kita. Walau bagaimanapun, industri ini tidak
terkecuali daripada kelemahannya. Cabaran pada kebiasaannya berlaku dari sudut
produktiviti, keberkesanan kerja, kualiti kerja dan penyiapan projek. Penggunaan
buruh asing yang tidak berkemahiran, penggunaan kelengkapan yang berteknologi
rendah dan teknik kerja yang sudah ketinggalan zaman telah menjurus kepadaproduktiviti dan keberkesanan kerja yang rendah di tapak pembinaan. IBS
merupakan salah satu sistem bangunan yang baru dan terkini yang diperkenalkan
dalam industri pembinaan tempatan, untuk mencapai sasaran perlaksaan projek yang
lebih pantas dengan penghasilan komponen bangunan di luar tapak pembinaan. Satu
kajian telah dilakukan untuk menganalisis langkah-langkah dalam mempertingkatkanaplikasi IBS dari segi penjadualan IBS di tapak untuk bangunan awam seperti
pembinaan sekolah di negara kita. Satu perbandingan di antara penjadualan untuk
kaedah konvensional dan cadangan kaedah IBS telah dilakukan dengan
menggunakan Microsoft Project. Output kritikal dalam pengurusan penjadualan
projek seperti masa, produktiviti buruh dan faktor kerja telah dianalisis dengan teliti.Jenis sistem kren yang ideal telah dipilih untuk memastikan produktiviti dan
keberkesanan kerja yang optimum di tapak pembinaan. Akhirnya, perbandingan telah
dibuat antara cadangan bangunan sekolah yang berkonsep baru dengan menggunakan
-
7/29/2019 AllanTayEngManMFKA2006THT
10/162
vii
TABLE OF CONTENTS
CHAPTER DESCRIPTION PAGE
TITL E i
DECLARATION ii
DEDICATION iii
ACKNOWLEDGEMENT iv
ABTRACT v
ABSTRAK vi
TABLE OF CONTENTS vii
LIST OF TABLES xii
LIST OF FIGURES xiii
LIST OF APPENDIXES xvii
CHAPTER 1 INTRODUCTION
1.1 Introduction 1
1.2 Problem Statement 4
-
7/29/2019 AllanTayEngManMFKA2006THT
11/162
viii
CHAPTER 2 LITERATURE REVIEW
2.1 Introduction 92.2 Industrialised Building System (IBS) 102.3 Typical classification of IBS 12
2.3.1 The frame system 14
2.3.2 Panel system 192.3.3 Box system 22
2.4 Classification for Types of IBS Used in Malaysia 242.5 The Benefits of IBS 252.6 Modular Coordination 272.7 Just-In-Time (JIT) Management in the Precast
Concrete Construction 29
2.8 Experiences Of Other Countries in IBS 322.8.1 The United States of America (U.S.A.) 32
2.8.2 Japan 33
2.8.3 Netherlands 342.8.4 Singapore 35
2.8.5 Thailand 38
2.8.6 Britain 40
2.8.7 Denmark 41
2.9
Malaysias own experience in IBS 412.10 Sequence of conventional construction method 452.11 Sequence of construction for IBS method 472.12 Scheduling of IBS components on site 49
-
7/29/2019 AllanTayEngManMFKA2006THT
12/162
ix
CHAPTER 3 METHODOLOGY
3.1 Introduction 56
3.2 First stage: Identification of research topic and
scope of study 56
3.3 Second stage: Data collection 58
3.4 Third stage: Results and analysis 623.5 Fourth stage: Make conclusion 63
CHAPTER 4 DATA ANALYSIS AND DISCUSSION
4.1 Introduction 64
4.2 Background Study 65
4.3 Case Studies 66
4.3.1 Construction site: Jusco Tebrau City, Johor 664.3.2 Construction site: Subang USJ Mydin
Wholesalers Hypermarket 67
4.3.3 Construction site: Kidney Dialysis Centre,Kuching 69
4.3.4 Precaster: Eastern Pretech (Malaysia)Sdn. Bhd. 70
4.3.5 Precaster: Precast Product Sdn. Bhd. 714.3.6 Precast Specialist Contractor: Takenaka
C i (M l i ) Sd Bhd 71
-
7/29/2019 AllanTayEngManMFKA2006THT
13/162
x
4.5 Results of Analysis 82
4.6 The Critical Outputs in Managing the Scheduling
of Project 87
4.6.1 Time factor 87
4.6.2 Labour productivity 92
4.6.3 Task factor 96
4.7 Lifting systems 99
4.8 Comparative check of proposed IBS school design
with Uniform Building By-Laws 1984 103
4.8.1 Part III: Space, Light and Ventilation Clause 38 (1) - Width of footway 104
4.8.2 Part III: Space, Light and Ventilation Clause 39 (3) Natural Lighting andVentilation 104
4.8.3 Part III: Space, Light and Ventilation Clause 39 (4) Natural Lighting andVentilation 104
4.8.4 Part III: Space, Light and Ventilation Clause 43 (a) Minimum dimensions oflatrines, water-closets and bathrooms 105
4.8.5 Part III: Space, Light and Ventilation Clause 44 (4) Height of rooms inresidential buildings, shophouses, schools, etc 105
4.8.6 Part V: Structural requirements Clause 53 (1), (2) Building materials 105
487 PartV:Structural requirements
-
7/29/2019 AllanTayEngManMFKA2006THT
14/162
xi
CHAPTER V CONCLUSIONS AND RECOMMENDATIONS
5.1 Conclusion 108
5.2 Recommendations 112
REFERENCES 115
APPENDIXES 120 - 135
-
7/29/2019 AllanTayEngManMFKA2006THT
15/162
xii
LIST OF TABLES
TABLE NO. TITLE PAGE
2.1 Building system classification according to relative
weight of component 13
2.2 Prefabricated housing market share in Japanese FiscalYear 1999 (April 1999-March 2000). 34
4.1 The proportion of bays for the proposed conceptual school 79
4.2 The summary for the comparisons of overall construction
period for the conventional Cast-In-Situ method and
precast IBS method 86
4.3 The approximate duration for the installation for each
component 88
4.4 The total components used in the assembly of the
proposed conceptual IBS school 97
4.5 A summary of the installation of precast components
-
7/29/2019 AllanTayEngManMFKA2006THT
16/162
xiii
LIST OF FIGURES
FIGURE NO. TITLE PAGE
1.1 The scenario of our construction industry today. 5
2.1 Frame System 12
2.2 Panel System 12
2.3 Box System 12
2.4 Examples of frame systems for industrialised buildings 14
2.5 A typical rectangular frame that consists of two precastconcrete columns and a precast horizontal beam 15
2.6 Another typical rectangular frame, which consists of two
columns and a horizontal beam, prefabricated using steel
sections 15
2.7 Examples of frame system for multi-storey buildings 16
2.8 Two examples of frame system for public buildings 17
-
7/29/2019 AllanTayEngManMFKA2006THT
17/162
xiv
2.12 The support of slabs along edges on bearing wall panels 20
2.13 Examples of the application of hollow core slab as slab
panels in the building construction 21
2.14 Application of panel system as interior walls 22
2.15 The use of wall panels in the building construction 22
2.16 Arrangement of box units into position onsite 23
2.17 The sequence of installation of box system onsite 24
2.18 The JIT principle in the construction industry scenario 31
2.19 Examples of innovative IBS components produced in
Singapore 37
2.20 The application of PLP in the construction industry in
Thailand 39
2.21 The sources of IBS in Malaysia according to the origin
of countries 42
2.22 Sequence of activities of IBS construction method 48
3.1 The flow chart of the research methodology 57
4.1 Jusco Tebrau City during construction period 67
-
7/29/2019 AllanTayEngManMFKA2006THT
18/162
xv
4.6 Structural overview of the proposed conceptual school
(view as per level only) 76
4.7 The allocation of classrooms for each 5 bays with the two
offices in between each classroom 78
4.8 The proposed conceptual school as generated in 3D
modelling using ACAD software (Perspective View) 80
4.9 The proposed conceptual school as generated in 3D
modelling using ACAD software (Front View) 80
4.10 The proposed conceptual school as generated in 3D
modelling using ACAD software (Back View) 81
4.11 The overall proposed conceptual school as generated in
3D modelling using ACAD software 82
4.12 The scheduling of conventional construction method
using Microsoft Project 83
4.13 The scheduling of IBS method using Microsoft Project
shows a significant time saving of up to 135 days compared
to the conventional method 85
4.14 The time frame for the installation sequence of precast
concrete elements at site 90
415 Delivery andunloadingof structural componentswill only
-
7/29/2019 AllanTayEngManMFKA2006THT
19/162
xvi
4.18 The lifting apparatuses used by the crane 99
4.19 The application of four-point picks in the construction
of the proposed IBS method school 101
-
7/29/2019 AllanTayEngManMFKA2006THT
20/162
xvii
LIST OF APPENDIXES
APPENDIX TITLE PAGE
A Gantt Chart for Conventional Method 120
B Gantt Chart for IBS Method 122
C 100 Metric Tonne Crane Specification 124
D Gantt Chart for four-point picks scheduling 128
E Gantt Chart for three-point picks scheduling 130
F Gantt Chart for two-point picks scheduling 132
G Gantt Chart for single-point picks scheduling 134
-
7/29/2019 AllanTayEngManMFKA2006THT
21/162
1
CHAPTER I
INTRODUCTION
1.1 Introduction
The construction industry plays a major role in our countrys economic
growth. According to CIDB (2000), over the last 20 years, the construction industry
in Malaysia has been consistently contributing between 3% to 5% of the nationalGDP. This shows how much the construction sector has been contributing towards
the economic growth of our country. According to Wang (1987), the construction
industry can serve as a barometer indicating the nations economic conditions. Brisk
construction activities generally show that the nations economy is booming and
progressing well, and whereas sluggish construction activities show that the
countrys economy condition is under depression.
-
7/29/2019 AllanTayEngManMFKA2006THT
22/162
2
Construction industry basically consists of various processes, involves many
parties and different stages of work. It involves the participation of various parties
from various sectors in order to ensure the efficiency of the construction work carried
out. The efficiency and success of construction development and activities depends
heavily on the quality of managerial and organizational performance plus the
effective co-ordination through good teamwork from the different parties. It is
therefore obvious that the development of the construction industry can only be
achieved if every team members play effective roles in their work.
The construction industry involves the participation of seven various sectors.
This includes the Client/Developer Sector, the Consultant Sector which includes
project management consultants, planners, architects, engineers, quantity surveyors,
land surveyors and other specialist consultants, the Contractor Sector which also
includes the main contractor, specialist and nominated sub-contractors, The Material
and Equipment Supplier Sector, Manpower Sector, which includes unskilled,semi-skilled and skilled workers, The Finance Sector which involves banks, finance
and credit companies and lastly, the Approving Sector, which involves the local
authorities, state and federal government. The efficiency and productivity of the
industry depends largely on how the various sectors can jointly co-operate and try to
understand each others needs and problems.
However, the industry is not without weaknesses. More often than not, the
-
7/29/2019 AllanTayEngManMFKA2006THT
23/162
3
delivery of work.
According to Ismail (2001), in the 7th Malaysia Plan, 800,000 units of houses
has been planned and out of that figure, 585,000 units or 73.1% were planned for low
and medium cost houses. The disappointing fact is that, only 20% of completed
houses were reported throughout the nation, despite numerous incentives and
promotions to encourage developers to venture into such housing category. What has
gone wrong?
Waleedet al. (2003) reported that, the announcement of the 8th Malaysia Plan
with the planning of 600,000 to 800,000 low and medium houses throughout the
nation is indeed welcoming news to the population of Malaysia, especially to the
middle and low income groups. However, it is undoubtedly an uphill task to
accomplish such target with the current conventional building system currently
practiced widely by the construction industry in our country.
Therefore, the former system must be reviewed and better still replaced with
a new system, which has better advantages in terms of improving productivity,
indoor quality, improvement of work durability and efficiency and overall cost
reduction. The introduction of the Industrialised Building System (IBS) with the
promise of improving productivity rate, lowering construction costs and meeting the
gro ing demand for affordable ho sing is indeed elcoming ne s to o r co ntr s
-
7/29/2019 AllanTayEngManMFKA2006THT
24/162
4
1.2 Problem Statement
With the ongoing construction trend in Malaysia, that is still very
comfortably using labour intensive and low technology methods of construction, this
has initially lead towards low productivity and inefficiency of work at construction
site. Moreover, with the Governments call for more affordable housing, the
construction industry has had to fulfil national housing and commercial needs which
has eventually led to devastating compromise in quality of work.
The highly dependency on unskilled and cheap foreign workers has definitely
contributed to low productivity of work, because although they may be cheap, but
they are not efficient and cause high wastage. The quality of work has also been
terribly affected due to unskilled working method. After completion defects,
structural failures and design inadequacies are some of the tell-tale sign of the current
construction scenario in our country. According to CIDB (2000), complaints made by
consumers through national media and to the authorities are some of the numerous
indications of low quality of work. At the end, these will lead to decreased quality of
life in uncomfortable and unfriendly environments. Figure 1.1 shows the scenario of
our construction industry today.
-
7/29/2019 AllanTayEngManMFKA2006THT
25/162
5
Figure 1.1: The scenario of our construction industry today.
Based on Figure 1.1, we can see that our construction industrys highly
dependency on untrained labours has led to the high usage of unskilled and cheap
foreign workers. This has prompted the current construction industry to be labourintensive, due to the high usage of unskilled workers in the construction field. Taking
into account of the high usage of foreign unskilled workers at site, it is difficult for
the construction sector to achieve high productivity of work at site.
However, if we were to introduce trained workers into the construction
projects, we can achieve high productivity and efficiency of work, since the workers
are able to carry out the work at site skilfully and effectively. These skilled and
Untrained Labour Trained Labour
ConstructionProjects
Labour
Intensive
IBS Trained
Personal
FACTORY
- Lean / sustainable projects
- Manufactured buildings
- Not labour intensive
-
7/29/2019 AllanTayEngManMFKA2006THT
26/162
6
that are less labour intensive.
Although the long-introduced Industrialised Building System (IBS) has
promised to solve and improved the current construction method and scenario in our
country, but the IBS method has been low in gaining popularity, partly due to lack of
awareness and coordination among the relevant parties. Currently, the level of usage
of IBS method is very low as compared to the conventional methods in building
construction. In spite of its many benefits, the different perceptions among the
construction players and practitioners towards its application in construction industry
has led to the low usage of IBS components in the construction industry.
Moreover, the benefits of IBS applications in the construction industry has
yet to be known and uncovered due to lack of research studies conducted in the
Malaysias construction perspective. Our local construction players are still in doubt
of the efficiency of IBS method of construction as compared to the conventional
method. The question to how much can the IBS method contributes towards reducing
the total construction period, the efficiency of the assembling and erection processes
at site and the production stage still lingers on and remain unanswered. At the end of
the day, the IBS method remains unknown and unfamiliar to the local construction
industry.
C rrentl p blic b ildings s ch as schools in Mala sia are still idel
-
7/29/2019 AllanTayEngManMFKA2006THT
27/162
7
teachers, and thus providing a conducive studying environment to the students is
normally out of the question.
It is hoped that the precast technology can bring out the tremendous potential
towards productivity improvement as it encompasses aspects of standardisation,
highly controlled and quality precast components which complements the various
programs to increase productivity and quality control through the adoption of
Modular Coordination (MC) and Industrialised Building System (IBS).
1.3 Objectives of Study
The objectives of this study are as follows:
(i)
To achieve faster construction by reducing overall construction time, utilizingIBS method.
(ii) To propose a new conceptual school building using standard IBS components,replacing the existing JKR conventional school buildings.
(iii) To identify the generality for the processes in an IBS scheduling.(iv) To identify ways to integrate IBS method into the scheduling of school
8
-
7/29/2019 AllanTayEngManMFKA2006THT
28/162
8
1.4 Scope of Study
The scope of this study is focused to building construction, especially
involving public projects such as school construction. The purpose of this study is to
determine whether the Industrialised Building System (IBS) can be implemented into
the construction of public projects in our country, especially in reducing the overall
construction period.
-
7/29/2019 AllanTayEngManMFKA2006THT
29/162
9
CHAPTER II
LITERATURE REVIEW
2.1 Introduction
This chapter highlights the subject of Industrialised Building System (IBS),
its importance and contribution to the construction industry, both internationally and
locally in Malaysia, and also to elaborate in details the sequence of construction of
both IBS and conventional working method. This chapter will also review on the
concepts of Modular Coordination (MC), Just-In-Time principles, the scheduling of
IBS components at site, types of scheduling methods and will emphasize on the
scheduling of public buildings in Malaysia utilising IBS method.
This chapter will also explore the literature information that will later
illustrate the research methodology that will be carried out in the following chapter.
-
7/29/2019 AllanTayEngManMFKA2006THT
30/162
10
2.2 Industrialised Building System (IBS)
According to Warszawski (1999), building system is defined as a set of
interrelated elements that act together to enable the designated performance of a
building. Industrialised Building System (IBS) is one of the improved building
systems that are being introduced to achieve the target of faster completion with
mass production of the building elements in places out of its final location in a
building.
Rollet (1986) also defined the word industrialising as to build on site with
elements or components produced by series in plants. An industrialised organisation
of building means that these components can be assembled together even though
they are produced on different plants as they have then to be compatible. Another
definition given by Trikha (1999), expounded that Industrialised Building System
(IBS) is a system in which concrete components, prefabricated at site or in factory
are assembled to form the structure with minimum in-situ construction.
Esa and Nuruddin (1998) also defined that an IBS is a continuum beginning
from utilising craftsmen for every aspect of construction to a system that make use of
manufacturing production in order to minimise resource wastage and enhance value
for end users.
-
7/29/2019 AllanTayEngManMFKA2006THT
31/162
11
In this well-defined concept by Junid (1986), the software element includes
the whole system design, a complex process of studying the requirement of the endusers, market analysis and forecast, development and production of standardised
components, establishment of manufacturing and assembly layout and processes,
allocation of resources and materials and definition of a building designer conceptual
framework. In short, the software element provides a prerequisite condition to create
the best environment for industrialised building system to expand further.
Junid (1986) further elaborated that the hardware element are categorised into
three major groups. These include frame or post and beam system, panel system and
box system. The framed structures are defined as those structure that carry loads
through their beams and girders to columns and then to the ground whilst in panel
system, the load are distributed through large floor and wall panels. The box systems
include those systems that employ three-dimensional modules (or boxes) for
fabrication of habitable units that are capable of withstanding load from various
directions due to their internal stability.
In short, Industrialised Building System (IBS) is a construction method that
offers economisation of design, site work and materials, provides shorter
construction time, saving in labour, better quality control, immunity to weather
changes and the most importantly, the cost factor. It has been proven successful in
some countries, namely Finland, Denmark, Netherlands, Singapore, England and the
12
-
7/29/2019 AllanTayEngManMFKA2006THT
32/162
12
2.3 Typical classification of IBS
There are various Industrialised Building Systems (IBS) used throughout the
world, and they can be classified into three major categories. According to Junid
(1986), the typical classifications are as follows:
(i) Frame or post and beam system(ii) Panel system(iii) Box system
Figure 2.1, Figure 2.2 and Figure 2.3 shows the concept of the system as
classified above. In the evaluation of the systems, various parameters such as the
industrialised process used, the transportation and erection problems, architectural
features and the sosio-economic problems must be considered.
Figure 2.1: Frame System (Junid, 1986) Figure 2.2: Panel System (Junid, 1986)
13
-
7/29/2019 AllanTayEngManMFKA2006THT
33/162
13
However, Majzub (1977) commented that the relative weight of components
should be used as a basis for building classification. The factor of weight has a hugeimpact on the transportability of the components and also has influence on the
production method of the components and their erection method on site. This
classification by weight can help to distinguish between various basic materials used
in the production of the components, which by itself help to determine the
characteristics of the studied system. Table 2.1 shows building system classification
according to relative weight of component.
Table 2.1: Building system classification according to relative weight of component
(Majzub, 1977)
No General System System Production Material
Light weight frame Wood, light gage metals
Medium light weight frame Metal, reinforced plastics,
laminated wood
1 Frame system
Heavy weight frame Heavy steel, concrete
Light and medium weightpanel
Wood frame, metal frameand composite materials
Heavy weight panel (factory
produced)
Concrete
2 Panel system
Heavy weight panel (tilt
up-produced on site)
Concrete
Medium weight box (mobile) Wood frame, light gage
metal, composite
Medium weight box
(sectional)
Wood frame, light gage
metal, composite
Heavy weight box (factory
d d)
Concrete
3 Box system
(modules)
14
-
7/29/2019 AllanTayEngManMFKA2006THT
34/162
14
2.3.1 The frame system
Frame structures may be defined as those structures that carry the loads
through their beams and girders to column and to the ground. Junid (1986) also
stated that, in such a system, the skeletal structures will help to reduce the number
and sizes of load carrying members. Their important feature is the capacity to
transfer heavy loads over large spans. For this reason, they are used in the
construction of bridges, parking lots, warehouses, industrial buildings, sport facilities
and so on. Figure 2.4 show examples of frame systems for industrialised buildings.
Figure 2.4: Examples of frame systems for industrialised buildings
(Construction Photos).
Warszawski (1999) mentioned that different variants of the structural scheme
allow for the most convenient partitioning of the frame into connected precast
elements Fore ample inat picalframes stem arectang larframeshallconsistof
15
-
7/29/2019 AllanTayEngManMFKA2006THT
35/162
15
The frame structures on its own, forms only the skeleton of the building and
do not enclose the space. Therefore, infill elements such as prefabricated panels or
building the infill elements on site or both need to be put up to complete the system.
Figure 2.5: A typical rectangular frame that consists of two precast concrete columns
and a precast horizontal beam (Construction Photos).
16
-
7/29/2019 AllanTayEngManMFKA2006THT
36/162
many bays as necessary, or upwards, for multi-storey buildings. Figure 2.7 show
examples of frame system for multi-storey buildings. Figure 2.8 shows two examples
of frame system for public buildings.
Proper attention is needed especially to their lateral stability either by
introduction of rigid connections at the corners, by bracing with diagonals, or by
attaching the multiframe to a rigid building component. Figure 2.9 show examples of
bracing for frame system at connection part.
Figure 2.7: Examples of frame system for multi-storey buildings (Construction
Photos).
17
-
7/29/2019 AllanTayEngManMFKA2006THT
37/162
Figure 2.8: Two examples of frame system for public buildings: (a) multi-storey car
park; (b) office building (Warszawski, 1999).
(a)
(b)
18
-
7/29/2019 AllanTayEngManMFKA2006THT
38/162
spans between supports. Figure 2.10 shows roof materials ready to be placed on the
roof frame of a typical frame system.
Figure 2.10: Roof materials ready to be placed on the roof frame of a typical frame
system (Construction Photos).
The modern skeleton structure, conventional or industrialised is the result of
rational use of materials of construction in the building. The great strength of new
building materials and the advancement in the construction technology have enabled
the frame system to span to a further distance and higher altitudes and thereby cater
to the increasing demands of this modern society.
This type of system is not very popular in the field of housing, although it isvery popular for large structures such as industrial and institutional buildings. The
advantage of the frame system is mainly in the interior flexibility, as large space can
be sed for different f nctions and can be easil changed or modified according to
19
-
7/29/2019 AllanTayEngManMFKA2006THT
39/162
2.3.2 Panel system
According to Junid (1986), panel system may be defined as those structures
that carry the load through large floor and wall panels. The panels can be made in
various forms and materials and are normally prefabricated at factory. Depending on
the scale of projects, some panels may be fabricated at site for easy transportation.
Concrete panel systems are extensively used in Europe for high rise building
for ease of construction purpose. In Malaysia, this system is slowly gaining
popularity in terms of high rise flats and low rise buildings. Other panel systems
available are as such wood, plastic, light weight metal and ferrocement materials.
Figure 2.11 shows panel system solutions applied to a typical residential building.
`
(a) (b)
(c) (d)
20
-
7/29/2019 AllanTayEngManMFKA2006THT
40/162
Slabs are usually supported along edges on bearing walls or beams in the
application of panel system in the construction of the building. The application of
this system offers advantages in terms of easy manufacturing even under field
conditions, relatively economical in terms of concrete and steel usage, and most
importantly, do not require concrete topping or special structural connections to
ensure a common action of adjacent panels. Figure 2.12 shows the support of slabs
along edges on bearing wall panels.
Figure 2.12: The support of slabs along edges on bearing wall panels: (a) view; (b)
section; (c) moment connection; (d) with temporary support
(a)
(b) (c) (d)
21
-
7/29/2019 AllanTayEngManMFKA2006THT
41/162
Figure 2.13: Examples of the application of hollow core slab as slab panels in the
building construction (Construction Photos).
The usage of panel system in the construction of interior walls and exterior
walls offer speed of construction in many ways. Figure 2.14 shows application of
panel system as interior walls. According to (Warszawski, 1999), wall panels
provides space enclosure, thermal insulation, sound isolation, exterior finish, housing
of windows, electrical conduits, and fixtures and structural support for floor slabs.
The exterior appearance of the wall panel is a very important architectural
consideration, and sometimes the main reason for the selection of a prefabricated
system. Figure 2.15 shows the use of wall panels in the building construction.
22
-
7/29/2019 AllanTayEngManMFKA2006THT
42/162
Figure 2.14: Application of panel system as interior walls: (a) cellular concrete; (b)
gypsum board (Warszawski, 1999).
Figure 2.15: The use of wall panels in the building construction (Construction
Photos).
(a) (b)
23
-
7/29/2019 AllanTayEngManMFKA2006THT
43/162
This system will require only large prefabricated sections to be transported or
handled at one time. This is an advantage due to high factory control and the number
of manhours required for the assembly on site can be reduced. The boxes can also be
stacked for high rise construction. In the case of high rise construction, the degree of
factory prefabrication is reduced for economic reasons of avoiding doubling of wall,
ceilings and floors. Depending on how it is used, the boxes can be made to be load
bearing or only support its own weight. The boxes can be produced in monolithic
form such as concrete boxes or be made in various sections joined together in the
factory. Figure 2.16 show arrangement of box units into position onsite.
Figure 2.16: Arrangement of box units into position onsite (Warszawski, 1999).
24
-
7/29/2019 AllanTayEngManMFKA2006THT
44/162
The construction building that implement this system, will achieve the
ultimate objective of industrialisation - a maximum saving of human labour onsite.
Figure 2.17 shows the sequence of installation of box system onsite.
Figure 2.17: The sequence of installation of box system onsite (Construction Photos).
2.4 Classification for Types of IBS Used in Malaysia
The Industrialised Building Systems (IBS) is a construction process that
utilizes techniques, products, components, or building systems which involve
prefabricated components and on-site installation. According to CIDB-(1) (2003),
from the structural classification, there are five IBS main groups identified as being
used in this country, and these are:
(i) Precast concrete framing, panel and box systems
25
-
7/29/2019 AllanTayEngManMFKA2006THT
45/162
(iii) Steel framing systemThis system covers steel trusses, columns beams and portal frame systems.
(iv) Prefabricated timber framing systemsThis system prefabricated timber trusses beams and columns.
(v) Blockwork systemsThis system includes interlocking concrete masonry units (CMU) and
lightweight concrete blocks.
2.5 The benefits of IBS
Commonly known and perceived by laymen as Dangerous, Difficult and
Dirty, the construction industry today has suffered spillover effect from the shortage
of foreign worker, unskilled workers at site and rise in both labour and material costs.
In order to revive and to further improve the image of the construction industry, IBS
can lead the way, given its advantages as an innovative construction method to the
construction industry.
The benefits of IBS can be presented as follows:
(i) The sa ing in man al labo r onsite ( p to 40 50% of the inp t in
26
-
7/29/2019 AllanTayEngManMFKA2006THT
46/162
(iii) The repetitive use of system formwork made up of steel, alumunium, etcand scaffolding provides considerable cost savings (Binget al., 2001).
(iv) Reduction of elimination props due to the absence of conventional timberprops through the usage of pre-fabricated components (CIDB-(2), 2003).
(v) An Industrialised Building System allows the flexibility in architecturaldesign in order to minimize the monotony of repetitive facades (Warszawski,
1999).
(vi) This provides earlier occupation of the building, thus reducing interestpayment or capital outlays (Peng, 1986).
(vii) Large production output and standardisation of precast elements allow ahigh degree of labour specialisation with the production process. In such
working condition, workers are exposed to their work repetitiously with
higher productivity level (Warszawski, 1999).
(viii) The reduction of construction waste with the usage of the standardizedcomponents and less in-site works, thus providing a cleaner site due to lesser
construction waste (CIDB-(2), 2003).
(i ) Constr ction operation is not affected b ad erse eather condition beca se
27
-
7/29/2019 AllanTayEngManMFKA2006THT
47/162
(xi) IBS provides safer construction sites due to the reduction of site workers,materials and construction waste (CIDB-(2), 2003).
2.6 Modular Coordination
Modular Coordination is a concept for coordinating dimension and space for
which buildings and components are dimensionalised and positioned in basic units or
modules. According to CIDB (2005) IBSDigest October December 2005 Issue,
MS 1064 introduces a certain geometric discipline using practical approaches which
relate to set-up coordination and measurement of components and spaces in the
building design.
The introduction of MC in the industry is to improve productivity and quality
in building construction as well as to act as a tool towards rationalisation and
industrialisation of the building industry. MC has been introduced in Malaysia since
1986, but has not been widely implemented in the building industry. The main
factors limiting the uses of MC in building industries is lack of knowledge on MC
concept and it requires precision dimensioning and proper planning.
The proper characteristics of MC are:
28
-
7/29/2019 AllanTayEngManMFKA2006THT
48/162
(iii) Ergonomically designed to promote efficiency.
(iv) Internationally accepted to support international market.
MC may be applied to the design, manufacture and assembly of buildings, its
components and installations. It also affects the work of positioning and
dimensioning during construction. The concept of MC is based on:
(i) The used of modules (basic modules and multi-modules)
(ii) A reference system to define coordinating spaces and zones for buildingelements and for the components which form them.
(iii) Rules for locating building elements within the reference system.
(iv) Rules for sizing building components in order to determine their worksizes.
(v) Rules for defining preferred sizes for building components andcoordinating dimensions for building.
The principal objective of implementing MC is to improve productivity
29
-
7/29/2019 AllanTayEngManMFKA2006THT
49/162
MC is an important factor in application of Industrialised Building System
IBS by way of standardization of components and dimensions such as reduce time of
production and installation of components, achieving repeatability and able to
construct building at lower cost.
2.7 J ust-In-Time (J IT) Management in the Precast Concrete Construction
Just-in-time (J IT) is defined as a philosophy of manufacturing based on
planned elimination of all waste and on continuous improvement of productivity
(Ahmad, 2005). It also has been described as an approach with the objective of
producing the right part in the right place at the right time (in other words, just in
time). Waste results from any activity that adds cost without adding value, such as
the unnecessary moving of materials, the accumulation of excess inventory, or the
use of faulty production methods that create products requiring subsequent rework
will be eliminated in J IT.
JIT (also known as lean production or stockless production) should improve
profits and return on investment by reducing inventory levels (increasing the
inventory turnover rate), reducing variability, improving product quality, reducing
production and delivery lead times, and reducing other costs (such as those
30
-
7/29/2019 AllanTayEngManMFKA2006THT
50/162
in a continuous on-going process has helped to increase the efficiency of operational
and big scale project economy.
In the conventional construction sector, we can see that most of the works are
carried out at site. Therefore, construction process and labour work will be severely
affected by the weather. If the current situation persists, the construction work will
continue to depend on continuous labour force and the production rate will remain at
its lowest.
The implementation of J IT principle in the construction sector through the
introduction of precast elements is hoped to achieve such success rate that has been
long tasted in the manufacturing sector. In this situation, the work process will be
done in a controlled and closed environment. The site will only be the installation
place, whereas the components produced from the factory will be delivered to the
site and ready for installation.
The use of precast elements can help control the usage of formworks,
reinforcements and concrete in order to prevent wastage. Proper monitoring and
control and the quality assurance of raw materials and the steel moulds can ensure
the production of high quality products. In this case, prefabrication can meet the
demand of lean production. Figure 2.18 shows the JIT principle in the construction
ind str scenario
31
-
7/29/2019 AllanTayEngManMFKA2006THT
51/162
Figure 2.18: The JIT principle in the construction industry scenario (Ahmad, 2005).
In the construction sector, we need a big space for the storage of materials at
site, and this will only reduce the capital budget. The need to prepare a large storage
area will not only waste money in allocating a large area for storage purposes, but if
the materials are not properly kept at site, it will affect the quality of the materials
greatly. Therefore, the implementation of JIT principle can save cost associated with
storage, since the materials will be delivered to the site in the right quantities and in a
controlled environment, to ensure that the quality of the components are guaranteed.
Since the materials will be delivered to the right place at the right time, this will also
reduce cost associated with storage of materials at site.
In this context, we can clearly see that the J IT principle has a good potential
in developing precast concrete components into eliminating the problem associated
with storage of materials at site, and also the heavy traffic problem at site. It is hoped
that the JIT principle can be fully implemented in the construction industry in our
Materials(not stored at site)
Delivered
In the right quantities In a controlled environment To the right place At the right time
J IT Concept
32
-
7/29/2019 AllanTayEngManMFKA2006THT
52/162
2.8 Experiences Of Other Countries in IBS
IBS is gaining wide popularity among construction practitioners worldwide.
It can be seen that the international acceptance of IBS method into the construction
industries of respective countries clearly shows that such method is beneficial to the
construction sectors. Below are some reviews on the IBS acceptance in several
countries around the world.
2.8.1 The United States of America (U.S.A.)
IBS has begun as early as the 1930s as seen by the construction of
prefabricated steel houses by General Homes back then. However, due to price in
competitiveness, high capital investment and inconsistent local codes, the early
dream to popularise IBS as an innovative construction method began to fade off.
However, after the Second World War, the trend was brought up again due to the
rising need to resolve the critical shortage of houses.
According to Jacqueline (1999), a study was carried out by Portland Cement
Association (PCA) indicated that 70% of buyers in the US market select their dream
house on the basis of cost/value alone. In other words, the advantages in terms of
33
-
7/29/2019 AllanTayEngManMFKA2006THT
53/162
In the United States of America (U.S.A.), timber framed is mostly used for
low rise housing, whereas concrete precast system is being used intensively
particularly in area that are vulnerable to environmental hazards as such hurricanes
and tornadoes. Concrete precast system is also applied in the construction of high
rise building in the USA due to its speed and ease in construction.
With the setting up of The Building America Industrialized Housing
Partnership (BAIHP), more researches and findings are carried out intensively to
formulate the best technology and construction methods to further promote IBS in
USA. Through such organization, IBS is gaining fast popularity in the USA market
in terms of high rise and low rise structures.
2.8.2 J apan
According to Nagahama (2000), the industrialisation of housing industry in
Japan started in 1960s and since then, the market share has changed dramatically
with the usage and application of IBS. As reported, from April 1999 - March 2000,
construction of prefabricated houses in Japan represented 20% of all houses built in
Japan during that period.
34
T bl 22 P f b i dh i k h i J Fi l Y 1999(A il
-
7/29/2019 AllanTayEngManMFKA2006THT
54/162
Table 2.2: Prefabricated housing market share in Japanese Fiscal Year 1999 (April
1999-March 2000) (Nagahama, 2000).
No Framing structure Prefabricated
Market Share, %
Growth Rate,
%
1 Steel framing 73 +3
2 Wood framing 18 +2
3 Concrete framing 9 -12
In spite of that, the Japan construction industry is still regarded as highly
integrated and automated production equipment and facilities to manufacture house
building components and offers home buyers both quality and aesthetic dream house.
2.8.3 Netherlands
In the past, the precast concrete in the Netherlands represents 10% of the total
housing market, although the conventional brick wall and masonry construction still
prevail in the market. Nevertheless, the industrialised housing is steadily increasing
its market share due to cost saving up to 30%. According to Jacqueline (1999), this
phenomenon is also substantiated by standardised components, flexible
manufacturing process and improved industrialised building technique.
35
I N th l d i idi ith hi h ti iti i th b ildi i d t
-
7/29/2019 AllanTayEngManMFKA2006THT
55/162
In Netherlands, coinciding with high activities in the building industry, new
ideas about efficiency were introduced in industrial production. There was a strong
belief that dimensional rules to manufacture modular parts of all kinds were the key
to a better building production at reduced costs. This was reflected in NEN 5700, the
first Dutch code on modular coordination, a two page document published in 1964,
in accordance with international ISO codes on the same subject. A direct relation was
suggested between dimensional co-ordination and an increased efficiency of the
building process and thus between standardization and industrialisation (NNI, 1978).
More codes were introduced thereafter, and this marks a milestone change in
the building industry in Netherlands. The building industry is changing from buildingon site using basic building materials to an assembly process: complete and complex
building parts are made in the factory and assembled on the site into a building.
Today, Netherlands is among one of the country that leads in the applicationof IBS components in the construction industry. Its strong concept on the benefits of
Open Building which aims to optimize the quality of the built environment, by
improving the relationship between the customer and the building industry has
attracted many countries worldwide to seek the expertise advice from the
Netherlands. The Open Building has indeed help to optimize building and
construction.
36
then was less on aesthetics By the mid 70s thehousing situation had improved and
-
7/29/2019 AllanTayEngManMFKA2006THT
56/162
then was less on aesthetics. By the mid 70s, the housing situation had improved and
more attention needed to be given to provide a total living environment for
residents. At this stage, the requirement for aesthetics and finishing quality began to
emerge. This trend carried on to the 80s and in the 90s, seeing new concepts like
mass customization emerging.
Based on the report by Tat and Hao (1999), during the period from
1973-1979, HDB of Singapore has again took a brave initiative to attempt IBS in
view of the need for accomplishing 100,000 dwelling units of housing units. As a
result of continuous effort, the HDB has made a remarkable achievement in the
adoption of IBS for the construction of the public housing program. These initiativesare the incorporation of modular co-ordination of its public housing designs, design
standardization and customization, prefabrication, and the mechanization of site
operations.
The setting up of HDB Prefabrication Technology Centre (PTC) in 1994
marks another milestone achievement in the application of IBS in Singapore. PTCs
main activities are to design, develop and produce prefabricated building products;
conduct research and development of advanced and innovative construction materials
and systems; manage and supply prefabricated building products; conduct training
and license its intellectual property rights.
37
-
7/29/2019 AllanTayEngManMFKA2006THT
57/162
Precast refuse chute Precast ferrocement secondary roof panels
Precast volumetric household shelter Precast column
Precast facade Precast parapet
38
285 Thailand
-
7/29/2019 AllanTayEngManMFKA2006THT
58/162
2.8.5 Thailand
The application of IBS as an innovative construction method in Thailand is
gaining higher popularity as compared to the scenario of the construction industry in
Thailand way back in the 1970s. According to Buddhi (2004), in 2004, the
government of Thailand has a plan to build about 600,000 units within three years for
the low to medium income level citizens. Most of these family units are detached
houses.
Commissioned developers and designers have proposed different housing
systems. However, it is important to note that in terms of material, production,
construction, etc., the design must be suitable for large scale construction within a
limited time and cost. In July 2004, the National Housing Authority (NHA) of
Thailand has approved the usage of the Precast Large Panel Construction. This
marks another milestone for the construction industry in Thailand, where several
thousand PLP houses will be built within a period of several years.
PLP is another example of IBS components widely used in Thailand. PLP
structural system consists of normally reinforced precast concrete panels, precast
slabs and foundations. No beam and columns are used except at few locations. In
terms of the speed of construction, the total time required is significantly less than
thecon entional s stem According to B ddhi (2004) for a t pical 23 bedroomt o
39
-
7/29/2019 AllanTayEngManMFKA2006THT
59/162
PLP Component Layout on Bed Casting of PLP components
Stacking of PLP components PLP components are lifted into position
40
Other advantages of using PLP, which includes mass production, no removal
-
7/29/2019 AllanTayEngManMFKA2006THT
60/162
g g , p ,
of formwork, less or comparable structural cost, quality control, usage of skilled
labour, low initial investment, modularization and automation and durability and
long term performance. Thailand is one of the countries actively introducing IBS
construction method into its construction industry. It is predicted that the
Government of Thailand will be able to achieve its target in providing 600,000 units
of housing units to its low and medium income group, thus providing the basic
necessities to its civilians, thanks to the application of IBS in its construction
industry.
2.8.6 Britain
The use of IBS in Britain became more evident in the mid 1900s after the
widespread destruction of housing units during the Second World War. According to
Jacqueline (1999), over 165,000 precast concrete dwellings had been built ranging
from small single bungalow to large high rise buildings by 1960.
In 1999, the precast concrete represents about 25% of the market for
cementitious products. This includes a wide range of products used in the
construction industry such as suspended floors, structural blocks, paving, cast stone
41
2.8.7 Denmark
-
7/29/2019 AllanTayEngManMFKA2006THT
61/162
According to Gibbons (1986), in Denmark, about 80% of the detached houses
produced since the mid-1960 were using IBS, most of it panelised system. The IBS
application in Denmark is aimed for domestic and export markets. For instance, its
international contractors such as Jespersen & Son and Larsen & Nielsen have
constructed many large-scale projects throughout the world, using prefabricated
concrete system produced from the local factories in their country.
In short, Denmark is not very lagging behind in terms of advancement in the
application of IBS in its construction industry. The construction companies from the
country are actively promoting IBS components from their country to the outside
world.
2.9 Malaysias own experience in IBS
The initiative to use and introduce IBS in Malaysia started off back in the
early sixties, when the Minister of Housing and Local Government visited some
European countries and evaluated their building systems performance. Din (1984)
reported that, it was then that the two pilot projects using IBS concept was carried
42
With reference to the two pilot projects, it is found out that in terms of
-
7/29/2019 AllanTayEngManMFKA2006THT
62/162
comparison of performance between IBS system and conventional system based on
cost, productivity and quality factor, the overall performance of IBS is more
competitive than the conventional method.
According to Badir et al. (2002), there are at least 21 suppliers and
manufacturers actively involved in promoting IBS in Malaysia. However, majority of
the IBS components are originated from the United States, Germany and Australia,
whereas Malaysia only contributed to a smaller portion of produced IBS components.
This shows that there are still ample of rooms for improvement and thus promoting
the application of IBS as an innovative construction method in our country is stillwidely open. Figure 2.21 shows the sources of IBS in Malaysia according to the
origin of countries.
UK
4%
Austria
8%
Australia
17%Germany
17%
US
25%
Othercountries
17%
Malaysia12%
Malaysia UK Austria
Australia Germany US
43
be increased from 30% to 50% commencing 2005. Housing developers, who utilize
-
7/29/2019 AllanTayEngManMFKA2006THT
63/162
IBS components exceeding 50%, will be given full exemption on levy imposed by
CIDB. This shows that the Government is trying to encourage the usage of IBS
components in the construction projects in our country.
According to CIDB-(2) (2003), only 15% of the local construction industry
has used IBS in Malaysia. Nevertheless, despite the high initial investment outlay,
some developers in Malaysia with sufficient economies of scale have taken proactive
steps and invested in IBS, mainly in formwork and structure. According to these
developers, IBS provided better and more consistent quality to their buildings, better
site management with less dependence on foreign workers.
According to MIGHT (2003) during a meeting on 24 January 2003 chaired
by Datuk Eddy Chen, REHDA Immediate Past Present, it is acknowledged that:
(i) IBS has been practised to a certain extent in Malaysia. PKNS, for instance,have built over 25,000 housing units using industrialized systems. JKR also
reported that they are using IBS for government quarters being constructed
all over Malaysia.
(ii) In JKRs case, they design the components (prefab slabs, beams, columns,infill panels) and based on the specifications, the market comes up with
44
(iv) That IBS should not only be related to high rise, but also low rise
-
7/29/2019 AllanTayEngManMFKA2006THT
64/162
developments and also commercial buildings.
(v) Modular coordination (MC) must be emphasized. Knowledge of MC at alllevels (including local authorities personnel) must be enhanced. Everybody,
from owner to designer to authorities and contractors must familiarize
themselves with MC to prevent occurrence of huge mould modifications for
every new projects which is cost ineffective.
(vi) From consultants point of view currently they have to do 2 designs(conventional & industrialized) because specifying the designs as
industrialised will result in the client getting very small number of tenderersduring tendering process.
(vii) Agreed that there should be elements of incentivisation to IBS users developers, consultants etc. Incentives should also be given for partial IBS
usage.
(viii) Whether our human resource is ready to adopt IBS.
Although the CIDB has drawn up the IBS Road Map, Modular Design Guide,
catalogues of prefabricated components and many other guides with some reference
to implementation goals and timelines, achievements to date are unclear and of little
impact To ards this end it is necessar for CIDB to engage e perts ith
45
The Government should set time-frame to gradually reduce intake of foreign
-
7/29/2019 AllanTayEngManMFKA2006THT
65/162
labour into the construction industry. A monitoring mechanism will also need to be
set up to track progress of IBS industry development with objective key performance
indicators (KPIs). Vellu (2004) was quoted as saying; successful implementation of
the shift to IBS is expected to help the government in meeting its target of decreasing
foreign labour dependence by 85%.
For this system to be successfully utilized, both public and private sectors
would need to play their roles in educating the local construction industry. But aside
from voluntarily changing mindset, there must be some push factor to catalyze the
shift in mindset. Perhaps a good combination of carrot and stick, i.e. incentives andregulatory requirements for the introduction and adoption of IBS should be the next
concrete plan of action to be spearheaded by CIDB to further promote IBS in the
construction industry in our country.
2.10 Sequence of conventional construction method
According to Bannet and Grice (1985), for the conventional constructionapproach, it is based on the rigid separation of design and construction. The design
team prepares detailed drawings, specification and often Bill of Quantity. The tender
46
ground. The building is actually made on the foundation. Usually a floor is laid on
-
7/29/2019 AllanTayEngManMFKA2006THT
66/162
the foundation. Beams will then be constructed, followed by the construction of
columns and slabs. Where it is necessary, staircases will be constructed, before
eventually roof beams are constructed, followed closely by the construction of roof
trusses. When the roof is to be framed on the site, the top sill plate is nailed on top of
the wall sections. Cutting and nailing each piece of wood one at a time takes a lot of
time. Not only must each piece be cut but each piece must be carried up the ladder to
the right place.
Water proof roofing materials will be placed to ensure the roof is water proof
before roof tiles are placed in position. Brick walls will be constructed wherenecessary, with allocations for the placement of doors and window panels. Painting
and aesthetic decoration on walls and floor slabs will follow up and the end product
will be a complete on-site building.
Certainly, with so much on-going works happening on site, many skilled and
unskilled labourers are needed to carry out the works on site. Formworks have to be
constructed to specified dimensions and concrete casting will be done when all the
formworks and reinforcements have been properly laid on site. Weather is a common
factor that affects the working schedule on site, and often, material wastage is a
problem faced by contractors.
47
2.11 Sequence of construction for IBS method
-
7/29/2019 AllanTayEngManMFKA2006THT
67/162
IBS method is different from the conventional construction method. Known
for its benefits in terms of shorter construction time, saving in labour, material saving,
better quality control, immunity to weather changes and the cost factor, IBS method
illustrates a different approach to the construction method commonly used. It offers
an alternative to the existing conventional building system.
Among one of the most important characteristics of IBS method is IBS
components are prefabricated offsite. According to Chew and Michael (1986),
prefabrication system of construction means breaking a whole housing unit into
different components such as the floors, walls, columns, beams, roofs, etc. and
having these components separately prefabricated or manufactured in modules or
standard dimensions in a factory. Figure 2.22 show sequence of activities of IBS
construction method.
48
-
7/29/2019 AllanTayEngManMFKA2006THT
68/162
Design Production line
Form a final unit Assemble and erection Delivery to site
Figure 2.22: Sequence of activities of IBS construction method (Construction
Photos).
IBS method emphasizes on prefabrication concept. Firstly, the design stage is
carried out where the IBS components are designed according to specifications. Then,
the components are prefabricated at factory, where components of IBS are
manufactured according to specified dimensions and specifications.
Quality-controlled and highly aesthetic end products through the processes of
controlled pre-fabrication and simplified installations has maintained and ensured the
quality of work in the construction industry.
49
IBS method offers a new concept in terms of speed of construction, and it
-
7/29/2019 AllanTayEngManMFKA2006THT
69/162
clearly shows many other benefits as compared to the conventional construction
method. According to Chew and Michael(1986), IBS also consists of 2 types of
prefabricated systems in the market, namely; fully prefabricated system and partially
prefabricated system.
Fully prefabricated system is referring to the components produced in the
factory and later transported to the site for erection. Fully prefabricated system
consists of 3 categories, namely; panel system, frame system and box system. Further
description and explanation of the above-mentioned systems has been clarified in the
sub-section before.
Partially prefabricated system is a type of system in construction where
certain elements that can be standardized are prefabricated in the factory, whereas
other components are cast in-situ. In this construction method, certain elements as
such wall panels, slab panels and staircase are considered as precast components,
while the columns, beams and the foundations are usually cast in-situ due to ease and
speed of construction. According to Chew and Michael (1986), this system usually
give more rigid construction and better water tightness characteristic, which are
normally a big problem with the usage of panel system and frame system.
50
workload on the production process in the very short run. Operations control entails
it i j b d d h diti d d/
-
7/29/2019 AllanTayEngManMFKA2006THT
70/162
monitoring job-order progress, and where necessary, expediting orders and/or
adjusting system capacity to make sure that the MPS is met. Scheduling should be
reviewed and agreed upon by the general contractor and/or the construction manager.
In designing a scheduling and control system for IBS formation scheduling,
provision must be made for efficient performance of the following functions:
(i) Allocating orders, equipment, and personnel to work centres or otherspecified locations. Essentially, this is short-run capacity planning at site.
(ii) Determining the sequence of order performance; that is establishing jobpriorities at site.
(iii) Initiating performance of the scheduled work. This is commonly termed thedispatching of orders for IBS formation at site.
(iv) Shop-floor control (or production activity control), which involves:(a) Reviewing the status and controlling the progress of orders as they are
being worked on.
(b)
Expediting late and critical orders.
(v) Revising the schedule to reflect recent changes in order status.
51
controlled quality and great precision. Once the precast components are produced
and pre fabricatedat fabrication plant theIBS components will later be transported
-
7/29/2019 AllanTayEngManMFKA2006THT
71/162
and pre-fabricated at fabrication plant, the IBS components will later be transported
to the site for assembly and erection purposes. This is where the scheduling of IBS
components is very vital as to ensure proper coordination of work and good timing
when assembling process is carried out at the site.
At the start of the day, the job dispatcher, or normally a site engineer assigned
to the scheduling task will select and sequence the available jobs to be run at
individual workstations at site. The engineers decisions would be based on the
operations and routing requirements of each job, status of existing jobs on the
machines, the queue of work before each machine, job priories, material availability,
anticipated job orders to be released later in the day, and worker and machine
capabilities.
To help organize the schedule, the engineer would draw on shop-floor
information from the previous day and external information provided by the
production control, process engineering, and so on. The engineer would also confer
with the foreman or supervisor of the department about the feasibility of the schedule,
especially with respect to workforce considerations and identifying potential
bottlenecks. Clear and visual schedule boards are efficient ways to communicate the
priority and status of work.
52
An experienced installer will prove helpful in these situations, especially if it
is necessary to alter the order Prior to delivering precast product and having
-
7/29/2019 AllanTayEngManMFKA2006THT
72/162
is necessary to alter the order. Prior to delivering precast product and having
expensive cranes, other equipment, and installation crews show up at the site, it is
essential that the site be properly prepared. The more site preparation you do, the
smoother, and it is hoped, and less costly the installation will go.
2.12.1 Scheduling Methods
In the scheduling phase of IBS components at the site, the cross-functional
team specifies the project plan in more detail. This phase begins with the
construction of a detailed list of project activities, called the work-breakdown
structure. A detailed time schedule for each activity in the work-breakdown structure
is then established, using several methods and software. When the time schedule is
completed, a time-phased budget, which is keyed to the start and completion times of
each of the project activities, can be developed. Finally, the project personnel can be
assigned to individual project activities.
Several types of scheduling methods are in use. These may be generallyclassified as Gantt Chart or Network methods. The Gantt Chart methods utilize a bar
or milestone chart. The network methods use a graph or network to show precedence
53
There are many scheduling software available in the current market
nowadays which makes scheduling an easier and simpler task This includes
-
7/29/2019 AllanTayEngManMFKA2006THT
73/162
nowadays, which makes scheduling an easier and simpler task. This includes
Primavera P3, Microsoft Project, Artimes, Pro-Plan, SureTrack Project Manager,
Milestone and so on. All these scheduling software plays a vital role in IBS
formation scheduling which makes job coordination and planning to be accurate and
speed up construction time.
2.12.1.1Microsoft Project as a Scheduling Software
In IBS scheduling, Microsoft Project is a software commonly used for
scheduling of project resources. It enables the control monitoring for the progress of
project activities and revises the plan accordingly. It has a combine element of Gantt
Chart and Network methods in order to enable scheduling to be done precisely.
The advantages of Microsoft Project as scheduling software in IBS
scheduling includes its ability to begin inputting activities data using Gantt Chart,
enables user to modify its planning sequences in case of any changes to the activities
and durations, and lastly, provides easy understanding to end user. Microsoft Projectalso enables planning and monitoring of activities on site to be much easier and more
efficient.
54
2.13 IBS Scheduling for Public Buildings
-
7/29/2019 AllanTayEngManMFKA2006THT
74/162
This study has been conducted to emphasize on analysing the best scheduling
ways for IBS components involving the construction of public buildings. Public
buildings here mainly referred to schools, universities, community halls and so on.
The reason why public buildings such as schools has been chosen as the subject of
this study, mainly is because, conventional construction method for schools would
normally take approximately 3 years or perhaps even longer, just to complete the
construction of the schools!
To add matters worst still, the newly-constructed school buildings often face
shortages of classrooms and facilities, as a result of ignorant contractors and
developers who wish to earn more, resulting in inadequate facilities being
constructed. Furthermore, the architectural concept of schools in Malaysia has not
changed for such a long time, often resulting in poor images in terms of aesthetic
value.
To date, our country still faces the shortages of school buildings to cater for
the increasing number of students. With the current speed of conventional
construction method involving construction of schools throughout the country, it
occurs that there is an urgent need to solve this problem as soon as possible. The
reason is that nless some methods are carried o t to impro e the c rrent
55
Therefore, IBS construction method has been identified as an alternative to
solvethisproblem.Therefore, thefocusof this studywill mainlybetargetingon IBS
-
7/29/2019 AllanTayEngManMFKA2006THT
75/162
solve this problem. Therefore, the focus of this study will mainly be targeting on IBS
application mainly on public buildings, especially in terms of schools in our country.
Proper scheduling techniques should be implemented especially on IBS components
at the site to ensure proper coordination of work and speedy construction. Efficient
scheduling of IBS components at site is vital in ensuring the smooth flow of
construction sequences at site.
56
-
7/29/2019 AllanTayEngManMFKA2006THT
76/162
CHAPTER II I
RESEARCH METHODOLOGY
3.1 Introduction
The research methodology in this chapter serves as a guide to the author in
achieving the objectives and scopes of the study. This chapter shall further discuss in
detail the research procedures, from how the data is collected till how it is processed
and analysed to achieve the objectives and scopes of the study.
3.2 First stage: Identification of research topic and scope of study
At this stage, it involves the identification and further understanding of the
57
Flow chart of the research methodology
-
7/29/2019 AllanTayEngManMFKA2006THT
77/162
Identification of the research topic and scopes of
Scope of study
Data Collection:
9 Construction sequence to follow conventional type ofconstruction.
9 Time frame for each IBS activities.9 Details of the proposed lifting system at site.
Results and analysis:
(i) Compare the scheduling process of both conventional andproposed IBS method.
(ii)Analyse the critical outputs in managing the scheduling ofproject.
(iii)Comparative check of proposed IBS school design with the
Uniform Building By-Law 1984.
First
stage
Second
stage
Third
stage
Literature reviewObjectives of study
58
3.3 Second stage: Data collection
-
7/29/2019 AllanTayEngManMFKA2006THT
78/162
Data collection is an essential aspect of the research methodology, where it
involves ways to collect data and information to assist in the data analysis and
interpretation. The data collection also emphasizes on the construction sequence of
IBS components to follow conventional construction method. This means that, the
sequence of construction and erection of IBS components at site shall follow the
sequence of conventional construction method.
Besides, data collection also involves the determination of time frame of
each activity in the proposed IBS method. For this purpose, it involves site studies at
several construction sites implementing IBS method in the construction process.
Interviews have also been conducted with several precasters, main contractors and
precast specialist sub-contractors in obtaining the data for the time frame of each
activity for the IBS method.
Other data collection also involves the details of the proposed lifting system
at site, with the capacity of cranes required, its working radius and its working
productivity while handling the installation of precast components at site. Site studies
for the lifting system have also been carried out at several sites utilizing IBS method
in its construction project. Further study which includes interview session with the
s pplier of the crane eq ipments for major constr ction projects in the co ntr has
59
productivity of different lifting systems and whether the productivity will be severely
affected if the lifting systems are not available or its usage are limited due to
-
7/29/2019 AllanTayEngManMFKA2006THT
79/162
machinery fault or unavailability of cranes at site.
A conceptual school building built using IBS components is modelled. At this
stage, the conceptual school is based on the criteria where the school building is
required to accommodate 1500 students for morning session only. Here, morning
session is referred to the period of studies from 8 am till 3 pm. This conceptual
school is based on the requirement where the students mainly comes from different
streams, such as technical, science, accountancy, agricultural science and art stream.
The school building is required to have full facilities, which includes
sufficient classroom where each classroom will only accommodate 30 students,
instead of the usual 50 to 60 students per classroom currently. This will enable
students to study in a more conducive learning environment, and hopefully gone
were the days where students were cramped inside a small classroom for each lesson.
Other amenities such assurau for Muslim prayers, locker cabinets, computer rooms,
meeting rooms for every curriculum activities, laboratories, libraries, toilets and so
on will be located strategically in the compound of the proposed conceptual school.
This conceptual school also emphasizes on having 1 classroom with two
attachedteachers room Inother ords therearenomorecentralisedteachersroom
60
Therefore, this study is conducted in order to achieve the aim of
constructing such conceptual school in our country, replacing the old conventional
-
7/29/2019 AllanTayEngManMFKA2006THT
80/162
schools that we have currently. In order to achieve such target and objective, it is
important to consider the construction process of the school. Currently, it is
saddening to see that a typical school in Malaysia will take approximately more than
2 years or perhaps longer, just to get it constructed. When the school is open to
students, problems such as insufficient classrooms and other facilities will greet thearrival of students, much to the displeasure of parents. It is hoped that the conceptual
school proposed in this study will soon overcome the problems arising, as mentioned
above.
In order to construct the proposed conceptual school, IBS construction
method has been proposed, where IBS components will be used in the construction
of the school. IBS construction method has been known for its speed of construction
benefit, high quality end products, and most importantly, it can help to solve the
shortages crisis of schools in our country in a faster and efficient way. This can
further solve the problem haunting the construction of schools currently, which take
years to complete the construction of the entire school buildings.
IBS components such as precast columns and beams are proposed in the
construction of the conceptual school. The use of precast columns and beams will
enhance the speed of completion of the entire school project. It is believed that with
61
process. In order to prepare a good scheduling for IBS components used in the
construction of the conceptual school, several factors have to be taken into
-
7/29/2019 AllanTayEngManMFKA2006THT
81/162
considerations. Such factors include production of IBS components at factory,
transportation to site location, labour supply, may it be in terms of skilled and
unskilled labourers, availability of components and lastly the erection and assembly
of IBS components at site.
In this context of study, the focus of study is particularly to emphasize on
the scheduling of IBS components at site. In other words, this study is mainly
focussed on assembly time of the conceptual school using IBS components.
Therefore, other factors such as production of IBS components at factory,
transportation to site location, labour supply and availability of IBS components has
to be maintained constant.
The reason being is that, when all other factors are maintained constant,
therefore, there should not be any problem occurring from the design stage till the
transportation stage. It will be presumed that all of these factors have been well taken
care of till the IBS components have arrived at the site. The only main concern would
be when the IBS components have arrived at the site, the scheduling of IBS
formation and erection has to be focussed in order to achieve effective work schedule
and speed of construction.
62
Further study will also be conducted to analyse how long does it takes to
assemble the components at the site to produce the entire conceptual building of the
-
7/29/2019 AllanTayEngManMFKA2006THT
82/162
proposed school. It is important also to determine whether it takes the same speed
and time to install the IBS components compared to conventional Cast-In-Situ
method. Scheduling of IBS components at site can also help to further determine the
work duration of the entire project implementing IBS components, as compared to
conventional methods.
3.4 Third stage: Results and analysis
At this stage, the assembly and erection of the proposed conceptual school
has been modelled using computer software and will be analysed. More emphasize is
on how the scheduling on assembly time is carried out efficiently at a site using IBS
components for the proposed conceptual school. Therefore, a comparison betweenthe work breakdown structure (WBS) between a typical school construction using
conventional construction method and the other using IBS components for the
proposed conceptual school will be further analysed. Microsoft Project will be the
scheduling software to be used for scheduling purposes, and the results generated by
the software will be carefully analysed at this stage.
63
3.5 Fourth stage: Make conclusion
-
7/29/2019 AllanTayEngManMFKA2006THT
83/162
At this final stage, a conclusion will be drawn out based on the results of the
analysis obtained. Final checking will be carried out at this stage to improve the
quality of the research study and also to improve the loop holes in the study
conducted.
64
-
7/29/2019 AllanTayEngManMFKA2006THT
84/162