PROGRESS
REPORTINGTF-FPM, Duri Field
Standard Procedure
SOP-PC-035
Draft B 07.May.07
PURPOSE - Provide TF-FPM Project Controls personnel with a ready reference for
projects progress reporting and control.
CONTRACT The Contract requirements include
Attachment A-1, Clause 6.1, Project Controls procedure for progress reporting andcontrol.
Attachment A-1, Clause 6.2, Periodic Reports include: Monthly Status Report,Photographs, Weekly Progress Reports, Daily Record Keeping, Suppliers &
Subcontractor.
Main Contract, Clause 6.3 Records Retention Process: contractor to maintain true &correct records.
Exhibit A, Clause 9.2, Contractors weekly progress meeting. Attachment A-1, Clause 3, Supervision by Contractor for Work Performed by its
Subcontractor
RESPONSIBILITIES TF Planning Group has the main task of progress reporting &control. Specific personnel shall do the following.
Core Project Controls Consolidated the progress reporting of TF.o
PC Manager To ensure an effective program of progress reporting and control is
development and implemented under procedural control.o Planning Lead
to confirm, amend as appropriate, and publish this SOP to train staff across TF-PC groups progress reporting & control
methods to assign tasks to other Core PC Planning personnel in carrying out the
work of PC within the core group
o Core PC Planning & Control Personnel Undergo self-training of this SOP and methods
Seek special guidance from PC Lead and Planning Lead where needful Undertake and accomplish tasks as assigned by Planning Lead or as
otherwise found necessary to the proper conduct of PC on FPM.
OU Project Controls Consolidated progress reporting and control of TFSubcontractors, and input to Core PC.
o Engr/OU PC Leads to understand this SOP and put it into practice
-
8/13/2019 atti98fc
2/23
STANDARD OPERATING PROCEDURE
SOP-PC-035 - RevB (draft)
Page 2 of 9
to assign tasks for progress reporting and control to Engr/OU PCresources
o Engr/OU PC Personnel (including: QS) Undergo self-training of this SOP and methods Seek special guidance from PC Lead and PC Lead Lead where needful Undertake and accomplish tasks as assigned by PC Lead or as
otherwise found necessary to the proper conduct of PC on FPM.
PERIODIC REPORTS - This refers to Attachment A-1 Clause 6.2
Progress report will be included in Monthly Status Reports and Weekly Progress Reports
Monthly Status Report
There are 2 kind of monthly status report:1) Management summary
Along with other reports, the management summary will include:
A contract schedule analysis, any slippage of activities, a progress shortfall. Summary progress table with actual versus planned and forecast progress.
2) Detailed Report.The detailed report section of monthly status report will include a narrative
highlighting the main events for each work area, a status of objectives planned for
period ending, objectives for the next period, critical activities, area of concern, and astatement of recovery actions to be taken for activities behind schedule. The progress
report that should be included in the detailed are:
Detailed progress table showing period and cumulative planned/actual progressfigures for disciplines
Level 2 Progress Control Curves, e.g. for Engineering, Procurement andFabrication
Update Level 2 Overall Project Schedule Current Manpower Histograms per Contract Drawing Status Report including all revisions up to issued for construction and
identifying those drawings received at Site Work areas.
Updated Construction Report illustration the status and total quantities of forinstallation / assembly and erection progress achieved for each major contract.
A report of local content manpower, cost and contract utilization, showing asapplicable, actual against planned and forecast for the current period andcumulative to date.
Photographs
High Resolution Digitally Produced Photographs is provided in the Monthly report
indicating major equipment and construction progress and key events, each photographs
is indexed with the reference and this reference marked along with the direction, on anA3 plot plan.
-
8/13/2019 atti98fc
3/23
STANDARD OPERATING PROCEDURE
SOP-PC-035 - RevB (draft)
Page 3 of 9
Weekly Progress Report
Weekly Reports are submitted in an agreed format. The report will use Fridays as cut-
off for weekly reporting.
Each section contains:
A brief narrative on achievements Activities planned for the coming period Critical activities Problem areas A statement of recovery actions to be taken for activities behind schedule.Daily Records Keeping
Records are kept of daily weather conditions including: temperature, humidity, rainfall
and wind speed.
UNITIZED PROGRESS REPORTING- This refers to Attachment A-1 Clause 6.2
Unitized progress reporting is the act of quantifying the total scope (control base) of
direct work executed on a project and measuring completed work against the total scopeusing weighted work steps. It should be in adequate detail (typically by drawing) to
effectively status on a routine basis, typically weekly. The progress and performance
report provides the data to support the forecasting of direct or indirect labor costs.
The unitized progress report is used to determine actual progress and performance
Progress = Earned HoursTotal Control Base Hours
or:
Progress = Earned Value CostTotal Control Base Cost
Performance = Earned HoursActual Hours
Control Base - represents actual deliverables or quantities installed. The control base is
developed as a fall out from drawing issues. The control base is not always directly
related to budget, but is a key tool in determining current forecast.
During the front-end alignment process, the project team should establish the following:
Work breakdown structure
Understanding of setup requirements of Unitized Progress Systems
Level of detail
Frequency of reporting
Reporting requirements
Subcontractors reporting requirements
-
8/13/2019 atti98fc
4/23
STANDARD OPERATING PROCEDURE
SOP-PC-035 - RevB (draft)
Page 4 of 9
Work steps and weightings for progress calculations
Initially the database is loaded with the current budget estimate to establish the control
base. As deliverables are identified, estimates are downloaded into the database. As adatabase grows, the baseline is monitored to determine the need for reforecast of
quantities and/or progress baseline change. The database should always reflect the current
scope of work authorized for execution.
PROGRESS AND PERFORMANCE ASSESSMENT - This refers to Attachment A-1
Clause 6.2 & Attachment A-1, Clause 3
Physical Progress
Physical progress is the completion of a measurable portion of the deliverable in
comparison to the total. Physical completion is in no way linked to job hours budgeted or
expended. Work units are assigned to each line item or work activity, thus assigning a
weight relative to the total estimated scope of work. By estimating the percent completefor each item at the end of a reporting period, the current earned job hours are calculated.
The total current job hours divided by the total estimated job hours gives the percent
complete or the physical progress for all summary levels used in reporting and analysis.
Tools and Techniques For Progress and Performance Measurement
Progress and Performance Reviews
Progress and performance reviews are held as an integral part of the regular progress and
status meetings and are included in project reporting.
Variance AnalysisVariance analysis involves comparing actual project results to planned or expected
results. Cost and schedule variances are the most frequently analyzed, but variances from
the plan in the areas of scope, quality, and risk are often of equal or greater importance.
Trend Analysis
Trend analysis involves examining project results over time to determine if performance
is improving or deteriorating.
Earned Value Analysis
Earned value analysis in its various forms is the most commonly used method of
performance measurement. It integrates scope, cost, and schedule measures to help theproject management team assess project performance. Earned value involves calculating
3 key values for each activity:
The budget is that portion of the approved cost estimate planned to be spent on theactivity during a given period.
The actual cost is the total of direct and indirect costs incurred in accomplishing workon the activity during a given period.
-
8/13/2019 atti98fc
5/23
STANDARD OPERATING PROCEDURE
SOP-PC-035 - RevB (draft)
Page 5 of 9
The earned value is a percentage of the total budget equal to the percentage of the workactually completed. Many earned value implementations use only a few percentages
(e.g., 30 percent, 70 percent, 90 percent, 100 percent) to simplify data collection.
Some earned value implementations use only 0 percent or 100 percent (done or notdone) to help ensure objective measurement of performance.
These 3 values are used in combination to provide measures of whether or not work is
being accomplished as planned.
Earned Value = Percent Complete x Budget for that account
Cost & Schedule PerformanceEarned Value analysis can be used to calculate the performance of the work/projects
Performance against schedule is then simply a comparison of budgeted and earnedwork-hours (or cost). If budgeted work-hours are less than earned, the work is ahead
of schedule. The reverse would probably mean that the work is behind schedule.
Performance against budget is measured by comparing earned to actual work-hours(or cost). If actual work-hours are less than means the budget has been overrun.
The above can be express in the formula below as follows:
Schedule Variance (SV) = Earned Work-hours or cost Budgeted work hours or cost
= BCWP BCWS
Schedule Performance Index (SPI) = Earned work hours or cost to date
Budgeted work hours or cost to date
= BCWP
BCWS
Cost Variance (CV) = Earned Work hours or cost Actual work hours or cost= BCWP ACWP
Cost Performance Index (SPI) = Earned work hours or cost to date
Actual work hours or cost to date= BCWP
BCWS
Reporting and Corrective Actions
Performance reporting should provide the kinds of information and the level of detail
required by various stakeholders as documented in the Project Execution Plan. Common
formats for performance reports include bar charts (also called Gantt charts), S-curves,histograms, and tables. Typically the progress and performance status is represented
using 3-Part Curves. These curves illustrate actual progress, staffing, and performance
-
8/13/2019 atti98fc
6/23
STANDARD OPERATING PROCEDURE
SOP-PC-035 - RevB (draft)
Page 6 of 9
versus the plan and chart incremental and cumulative data. An example of a progress and
performance tables for Engineering and Construction is identified on Attachments B & D
OFFICE (including: ENGINEERING) PROGRESS AND PERFORMANCE
MEASUREMENT - This refers to Attachment A-1 Clause 6.2
Deliverable Progress Measurement
As a guideline for progress assessment and to determine percent complete fordeliverables prepared in the course of an engineering project, the users should apply the
milestone tables as agreed upon by the Project Team. The progress ranges shown for each
type of document / deliverable executed are representative of the work required tocomplete the deliverable. These should be reviewed and adjusted to suit the varied
circumstances inherent in each project. Any change to these guidelines should be
reviewed by the engineering department manager responsible for that particulardeliverable prior to their use on the project.
The ranges for progress measurement determined by the milestone pattern represent thespecific scope of work to be performed within that deliverable's budget. The length of theproject and the duration of its activities would affect the way progress is assessed as well
as the timing of the update cycle required for each project weekly, biweekly, or monthly.
The reporting frequency should be established early in the project.
Milestone Patterns / Incremental Miestone
Milestone patterns are a collection of predetermined progress steps that total to 100
percent completion at the end of the activity or deliverable. These milestones are tangibleand measurable events in time and are often linked to revisions, issue dates, or review
cycles of documents and deliverables.(see: Work Instructions for Engineering Progress Measurement)
Deliverable Groups or Activities
To facilitate the progressing of multiple deliverables of small budget impact, these can begrouped together in deliverable groups. The deliverable group will receive the budget and
the progress figures for all the items it contains. The individual deliverables can still be
listed in document listings, document control distributions, or transmittal logs.
As a rule of thumb, deliverable group budgets should not exceed 10 percent of the
operation budget and the duration they span should not exceed 3 months. This keeps theprogress items as specific deliverable items that can therefore be statused accurately.
Deliverable groups are to be used to facilitate progressing small items, not to avoid
detailed progress measurement of activities and deliverables with little impact value to
the Project.
-
8/13/2019 atti98fc
7/23
STANDARD OPERATING PROCEDURE
SOP-PC-035 - RevB (draft)
Page 7 of 9
Indirect and Support Activities
It is not recommended to status indirect and support activities within a unitized progress
report. These values offer no added value towards the actual physical percent complete.
CONSTRUCTION PROGRESS AND PERFORMANCE MEASUREMENT - This
refers to Attachment A-1 Clause 6.2 & Attachment A-1, Clause 3
Field progress is a key element in the control of project labor costs and schedules. Anaccurate measurement of progress serves as a basis for labor reforecast as well as an
indicator for performance against the project schedule. Performance is the comparison
between current earned value and value expended.
This measurement at specified periods serves as a tool for construction status and helps
the field Project Controls team to better forecast total installed costs and accuratelypredict project completion. Progress serves as an analysis tool for timely corrective and
preventive actions against unforecasted project delays and increased cost.
Subcontractor Performance (by Others)
TF via Construction Supervision group to supervise and monitor Services performed by
Subcontractors. Construction Supervision can ask Subcontractor to submit Level 3/Level4 Schedule in order to control and to measure the work performed.
Subcontractors to submit their weekly progress report and this report to be verified byConstruction Supervision:
The subcontractor weekly progress report to include:
Contract Number and Scope Summary Name of Subcontractor Summary of Services performed for the week Percentage complete (planned and actual) Details of accidents (if any) and near misses, corrective action adopted Reasons for schedule slippage (if any) and proposed means for recovery) Services to be performed in the next reporting period Daily manpower count by discipline including supervisor, inspectors, and safety
officers for the week
Details of Client and Subcontractors equipment deployed. Working, standby,breakdown.
Amounts invoiced, paid, remaining, overdue, disputed Interfaces with Client existing production facilities for the following month. Details of work stoppages and reasons Daily weather conditions
-
8/13/2019 atti98fc
8/23
STANDARD OPERATING PROCEDURE
SOP-PC-035 - RevB (draft)
Page 8 of 9
Progress Measurement
Earned Value Analysis
Progress for subcontracted activities can be calculated either by using the same method as
self-performed construction.
Percent complete of an activity is based on the measured quantity of work
installed divided by the projected total quantity of work installed for eachweighted work step.
Item Percent Complete = Quantity Installed 100Estimated Total Quantity
Summary Percent Complete = Earned Hours 100Control Base Hours
or:
Summary Percent Complete = Earned Value Cost 100Control Base Hours
or by some other method agreed to with the subcontractor at pre-award meetings.
One method commonly used is for the subcontractors to assess the percent complete for
each pay item reported and verified either by TF Project Controls or the subcontractsManager-Coordinator. Based on an agreed-upon initial weighting, an earned value is thus
obtained for each pay item and summarized for each subcontract. Total percent completefor all subcontractors work can then easily be obtained. If the work units are equivalent
to job hours used in self-performed progress measurement, total project field progress canbe computed by adding all earned units and dividing by total estimated units.
(see: Work Instructions for Construction Progress Measurement)
WORK INSTRUCTIONS & TEMPLATES - This SOP provides an overview of
progress reporting and control on the FPM scope of work. Work Instructions and
Templates are available for the following areas of work.
Work Instruction 01 Measuring & Reporting Engineering Progress & Productivity
Work Instruction 02 Measuring & Reporting Construction Progress & Productivity
-
8/13/2019 atti98fc
9/23
STANDARD OPERATING PROCEDURE
SOP-PC-035 - RevB (draft)
Page 9 of 9
REVISIONS TO THIS PROCEDURE The current SOP is a draft issued for earlyintegration efforts. Revision 0 of this SOP will be issued with PC Planning Lead with
approval by the PC Manager and PM in due course. Later revisions will be made by the
PC Planning Lead with concurrence by PC Manager and Program Manager. All PC staffwill be given copies or access to copies of the SOP. Updates to standard forms being
used will be provided by the Cost Lead as they become available.
ATTACHMENTS
A Sample of Engineering Progress Measurement Forms
B Sample of Engineering Weekly Progress ReportsC Sample of Weekly Progress Report Submitted by Subcontractors
D Sample of Construction Weekly Progress Reports
E Sample of Monthly ReportsF Sample of Level 2 Progress Control Curve & Schedule
G Sample of Productivity Profile Analysis
H Sample Form of Daily Record
Rev B as issued by Sony Runtulalu (Planning Lead)
-
8/13/2019 atti98fc
10/23
Page 1 of 2
PROGRESS
REPORTING
TF-FPM, Duri Field
Work Instruction 01
SOP-PC-035
07May07
WORK INSTRUCTION 01
MEASURING & REPORTING ENGINEERING
PROGRESS & PRODUCTIVITY
1) TF PC personnel who is responsible for measuring engineering progress is CostEngineer/Scheduler
2) Get the deliverable progress of each activity from discipline engineers.3) Calculate the progress. Method used to calculate the progress is Incremental
Milestone This method is applicable to any control account which includes subtasks
that must be handled in sequence. For example, drawing preparation includes the
sequential tasks or operations listed below. Completion of any subtask is consideredto be a milestone, which when completed represents a certain percentage of the total
installation. The percentage chosen to represent each milestone is normally based on
the number of work-hours estimated to be required to that point in relation to the
total. In the listing below, the attainment of each milestone has been judged to beequivalent to having completed the percentage listed of the total installation
Collecting Input 10%
Conceptual Design & Layout 25%
Performing & Issue Sketches to Drawing 40%
Drafting & Issue Drawing for Checking 55%
Release for Squad Check 75%
IFR 80%
IFA 90%
IFC 100%
4) Calculate the actual cost / actual man-hour from timesheet5) Calculate the productivity / performance
Performance = Earned Hours orActual Hours
Performance = Earned Value Cost
Actual Cost
6) Prepare progress report Weekly progress report will use Fridays as the cut-off forweekly reporting. (see: Attachment 02).
-
8/13/2019 atti98fc
11/23
STANDARD OPERATING PROCEDURE
SOP-PC-035 - Work Instruction 01
Page 2 of 2
7) Submit the Report to client and gives the copies to the respective Group Managersand PC Lead.
8) Filing the progress report document
-
8/13/2019 atti98fc
12/23
Page 1 of 3
PROGRESS
REPORTING
TF-FPM, Duri Field
Work Instruction 02
SOP-PC-035
07May07
WORK INSTRUCTIONS 02
MEASURING CONSTRUCTION PROGRESS
1) TF Project Control (PC) personnel who are responsible for measuring constructionprogress is QSs. QSs along with Construction Supervision (CS) & Quality Control(QC) is responsible for progress verification for work done by subcontractor.
2) Progress measurement for Bi-Weekly (or Weekly) Progress Report. Subcontractors tosubmit their progress mentioning the quantity of work performed to QS. QS to verify
the work performed done by subcon. The flow would be as follows:
Bi-weekly progress report:
Subcontractors prepare progress
report. Monday to Wednesday
Time interval for work done by
subcontractors to be verified (2weeks, start on Monday & end on
Friday)
Milestone: Friday- Cut off date of
progress report
Milestone: Subcon submit the
progress report to TF, shall not be
later than Wednesday
QS verify the progress report
(Thursday-Friday)
Milestone: Monday: PC prepare
progress report and submit to CPI
-
8/13/2019 atti98fc
13/23
STANDARD OPERATING PROCEDURE
SOP-PC-035 - Work Instruction 02
Page 2 of 3
3) Progress Measurement for Monthly Progress Report & Status. Subcontractors tosubmit their progress claim mentioning the quantity of work performed to CS
Representatives. CS Representatives have to verify the progress done by
Subcontractor. QC to check the quality & only the quantity accepted by QC canproceed to progress claim. When applicable verifications from 3
rdparty surveyors are
needed. QS to do the final verification. If accepted by QS, the progress claim canproceed to the next step. The flow would be as follows:
Subcontractor submit the
progress claim, 2 days
CS, verify, 2 days
QC, check the quality, only the
accepted quantity can proceed
to next step, 2 days
QS verify, 2 days
3rdParty Surveyor Verification (if
applicable), 2 days
Return to subcon for
final progress claim
submission
Subcontractor submit
final revision, 2 days
Time interval for work done by
subcontractors to be verified (1
month)
-
8/13/2019 atti98fc
14/23
STANDARD OPERATING PROCEDURE
SOP-PC-035 - Work Instruction 02
Page 3 of 3
4) QSs verify the quantity recorded by using several methods & tools (by checking thequantity one-by-one (unit/lump sum (ls)), by using table (ton/kg), by using software(e.g. Autodesk Land Development, Civil Cad & Teramodel for m3 unit), by using
reports provided by TF QC (for work like piping work). Specific methods for
progress measurement are attached to this document5) Subcontractors finally submit the progress report to TF PC based on the quantities
verified by TF QS. (see: Attachment C)
-
8/13/2019 atti98fc
15/23
Page 1 of 1
PROGRESS
REPORTING
TF-FPM, Duri Field
Work Instruction 03
SOP-PC-035
07May07
WORK INSTRUCTIONS 03
REPORTING CONSTRUCTION PROGRESS & PRODUCTIVITY
1) TF Project Control (PC) personnel who are responsible for reporting constructionprogress & productivity are Cost Engineers, Schedulers & Project Control Lead.
2) There are 2 period of reporting: Weekly/Bi-weekly progress report & Monthly StatusReport. Progress Measurement Work Instruction is available separately in this SOP.
3) For work done by Subcon, the progress can be obtained for progress report bySubcontractors verified by QSs. There are several methods to calculate progress, one
of them is Weight or Equivalent Unit. This method is applicable where the task beingcontrolled is a major effort involving a long period of time and is composed of two or
more overlapping subtasks, each with a different unit of work measurement.
Progress (Construction) = Equivalent UnitsTotal Equivalent Units
4) Calculate the productivity / performancea. Calculate the actual cost (the actual cost for Resource Unit Rate (RUR)
the actual can be obtained from timesheet)b. Calculate the productivity / performance
Performance = Earned ValueActual Value
5) Prepare progress report. Weekly/Bi-weekly progress report will use Fridays as thecut-off for weekly reporting. (see: Attachment D). Weekly Report should be
accompanied by photographs from site. Those photographs should be taken by QS.
Index each photograph with reference and this reference marked, on an A3 Plot Plan.Stamp all photographs with the date the photographs was taken.
6) Submit the Report to client and gives the copies to the respective Group Managersand PC Leads.
7) Filing the Progress Report
-
8/13/2019 atti98fc
16/23
Page 1 of 1
PROGRESS
REPORTINGTF-FPM, Duri Field
SOP-PC-035
Attachment A
07May07
Attachment ASample of Engineering Progress Measurement Forms
-
8/13/2019 atti98fc
17/23
Page 1 of 1
PROGRESS
REPORTINGTF-FPM, Duri Field
SOP-PC-035
Attachment B
07May07
Attachment BSample of Engineering Weekly Progress Reports
-
8/13/2019 atti98fc
18/23
-
8/13/2019 atti98fc
19/23
Page 1 of 1
PROGRESS
REPORTINGTF-FPM, Duri Field
SOP-PC-035
Attachment D
07May07
Attachment DSample of Construction Bi-Weekly Programme Reviews
-
8/13/2019 atti98fc
20/23
Page 1 of 1
PROGRESS
REPORTINGTF-FPM, Duri Field
SOP-PC-035
Attachment E
07May07
Attachment ESample of Monthly Reports
-
8/13/2019 atti98fc
21/23
Page 1 of 1
PROGRESS
REPORTINGTF-FPM, Duri Field
SOP-PC-035
Attachment F
07May07
Attachment FSample of Level 2 Update
Project Control Curve & Schedule
-
8/13/2019 atti98fc
22/23
Page 1 of 1
PROGRESS
REPORTINGTF-FPM, Duri Field
SOP-PC-035
Attachment G
07May07
Attachment GSample of Productivity Profile Analysis
-
8/13/2019 atti98fc
23/23
PROGRESS
REPORTINGTF-FPM, Duri Field
SOP-PC-035
Attachment H
07May07
Attachment HSample Form of Daily Record