    PROGRESS

    REPORTINGTF-FPM, Duri Field

    Standard Procedure

    SOP-PC-035

    Draft B 07.May.07

    PURPOSE - Provide TF-FPM Project Controls personnel with a ready reference for

    projects progress reporting and control.

    CONTRACT The Contract requirements include

    Attachment A-1, Clause 6.1, Project Controls procedure for progress reporting andcontrol.

    Attachment A-1, Clause 6.2, Periodic Reports include: Monthly Status Report,Photographs, Weekly Progress Reports, Daily Record Keeping, Suppliers &

    Subcontractor.

    Main Contract, Clause 6.3 Records Retention Process: contractor to maintain true &correct records.

    Exhibit A, Clause 9.2, Contractors weekly progress meeting. Attachment A-1, Clause 3, Supervision by Contractor for Work Performed by its

    Subcontractor

    RESPONSIBILITIES TF Planning Group has the main task of progress reporting &control. Specific personnel shall do the following.

    Core Project Controls Consolidated the progress reporting of TF.o

    PC Manager To ensure an effective program of progress reporting and control is

    development and implemented under procedural control.o Planning Lead

    to confirm, amend as appropriate, and publish this SOP to train staff across TF-PC groups progress reporting & control

    methods to assign tasks to other Core PC Planning personnel in carrying out the

    work of PC within the core group

    o Core PC Planning & Control Personnel Undergo self-training of this SOP and methods

    Seek special guidance from PC Lead and Planning Lead where needful Undertake and accomplish tasks as assigned by Planning Lead or as

    otherwise found necessary to the proper conduct of PC on FPM.

    OU Project Controls Consolidated progress reporting and control of TFSubcontractors, and input to Core PC.

    o Engr/OU PC Leads to understand this SOP and put it into practice

  • 8/13/2019 atti98fc

    2/23

    STANDARD OPERATING PROCEDURE

    SOP-PC-035 - RevB (draft)

    Page 2 of 9

    to assign tasks for progress reporting and control to Engr/OU PCresources

    o Engr/OU PC Personnel (including: QS) Undergo self-training of this SOP and methods Seek special guidance from PC Lead and PC Lead Lead where needful Undertake and accomplish tasks as assigned by PC Lead or as

    otherwise found necessary to the proper conduct of PC on FPM.

    PERIODIC REPORTS - This refers to Attachment A-1 Clause 6.2

    Progress report will be included in Monthly Status Reports and Weekly Progress Reports

    Monthly Status Report

    There are 2 kind of monthly status report:1) Management summary

    Along with other reports, the management summary will include:

    A contract schedule analysis, any slippage of activities, a progress shortfall. Summary progress table with actual versus planned and forecast progress.

    2) Detailed Report.The detailed report section of monthly status report will include a narrative

    highlighting the main events for each work area, a status of objectives planned for

    period ending, objectives for the next period, critical activities, area of concern, and astatement of recovery actions to be taken for activities behind schedule. The progress

    report that should be included in the detailed are:

    Detailed progress table showing period and cumulative planned/actual progressfigures for disciplines

    Level 2 Progress Control Curves, e.g. for Engineering, Procurement andFabrication

    Update Level 2 Overall Project Schedule Current Manpower Histograms per Contract Drawing Status Report including all revisions up to issued for construction and

    identifying those drawings received at Site Work areas.

    Updated Construction Report illustration the status and total quantities of forinstallation / assembly and erection progress achieved for each major contract.

    A report of local content manpower, cost and contract utilization, showing asapplicable, actual against planned and forecast for the current period andcumulative to date.

    Photographs

    High Resolution Digitally Produced Photographs is provided in the Monthly report

    indicating major equipment and construction progress and key events, each photographs

    is indexed with the reference and this reference marked along with the direction, on anA3 plot plan.

  • 8/13/2019 atti98fc

    3/23

    STANDARD OPERATING PROCEDURE

    SOP-PC-035 - RevB (draft)

    Page 3 of 9

    Weekly Progress Report

    Weekly Reports are submitted in an agreed format. The report will use Fridays as cut-

    off for weekly reporting.

    Each section contains:

    A brief narrative on achievements Activities planned for the coming period Critical activities Problem areas A statement of recovery actions to be taken for activities behind schedule.Daily Records Keeping

    Records are kept of daily weather conditions including: temperature, humidity, rainfall

    and wind speed.

    UNITIZED PROGRESS REPORTING- This refers to Attachment A-1 Clause 6.2

    Unitized progress reporting is the act of quantifying the total scope (control base) of

    direct work executed on a project and measuring completed work against the total scopeusing weighted work steps. It should be in adequate detail (typically by drawing) to

    effectively status on a routine basis, typically weekly. The progress and performance

    report provides the data to support the forecasting of direct or indirect labor costs.

    The unitized progress report is used to determine actual progress and performance

    Progress = Earned HoursTotal Control Base Hours

    or:

    Progress = Earned Value CostTotal Control Base Cost

    Performance = Earned HoursActual Hours

    Control Base - represents actual deliverables or quantities installed. The control base is

    developed as a fall out from drawing issues. The control base is not always directly

    related to budget, but is a key tool in determining current forecast.

    During the front-end alignment process, the project team should establish the following:

    Work breakdown structure

    Understanding of setup requirements of Unitized Progress Systems

    Level of detail

    Frequency of reporting

    Reporting requirements

    Subcontractors reporting requirements

  • 8/13/2019 atti98fc

    4/23

    STANDARD OPERATING PROCEDURE

    SOP-PC-035 - RevB (draft)

    Page 4 of 9

    Work steps and weightings for progress calculations

    Initially the database is loaded with the current budget estimate to establish the control

    base. As deliverables are identified, estimates are downloaded into the database. As adatabase grows, the baseline is monitored to determine the need for reforecast of

    quantities and/or progress baseline change. The database should always reflect the current

    scope of work authorized for execution.

    PROGRESS AND PERFORMANCE ASSESSMENT - This refers to Attachment A-1

    Clause 6.2 & Attachment A-1, Clause 3

    Physical Progress

    Physical progress is the completion of a measurable portion of the deliverable in

    comparison to the total. Physical completion is in no way linked to job hours budgeted or

    expended. Work units are assigned to each line item or work activity, thus assigning a

    weight relative to the total estimated scope of work. By estimating the percent completefor each item at the end of a reporting period, the current earned job hours are calculated.

    The total current job hours divided by the total estimated job hours gives the percent

    complete or the physical progress for all summary levels used in reporting and analysis.

    Tools and Techniques For Progress and Performance Measurement

    Progress and Performance Reviews

    Progress and performance reviews are held as an integral part of the regular progress and

    status meetings and are included in project reporting.

    Variance AnalysisVariance analysis involves comparing actual project results to planned or expected

    results. Cost and schedule variances are the most frequently analyzed, but variances from

    the plan in the areas of scope, quality, and risk are often of equal or greater importance.

    Trend Analysis

    Trend analysis involves examining project results over time to determine if performance

    is improving or deteriorating.

    Earned Value Analysis

    Earned value analysis in its various forms is the most commonly used method of

    performance measurement. It integrates scope, cost, and schedule measures to help theproject management team assess project performance. Earned value involves calculating

    3 key values for each activity:

    The budget is that portion of the approved cost estimate planned to be spent on theactivity during a given period.

    The actual cost is the total of direct and indirect costs incurred in accomplishing workon the activity during a given period.

  • 8/13/2019 atti98fc

    5/23

    STANDARD OPERATING PROCEDURE

    SOP-PC-035 - RevB (draft)

    Page 5 of 9

    The earned value is a percentage of the total budget equal to the percentage of the workactually completed. Many earned value implementations use only a few percentages

    (e.g., 30 percent, 70 percent, 90 percent, 100 percent) to simplify data collection.

    Some earned value implementations use only 0 percent or 100 percent (done or notdone) to help ensure objective measurement of performance.

    These 3 values are used in combination to provide measures of whether or not work is

    being accomplished as planned.

    Earned Value = Percent Complete x Budget for that account

    Cost & Schedule PerformanceEarned Value analysis can be used to calculate the performance of the work/projects

    Performance against schedule is then simply a comparison of budgeted and earnedwork-hours (or cost). If budgeted work-hours are less than earned, the work is ahead

    of schedule. The reverse would probably mean that the work is behind schedule.

    Performance against budget is measured by comparing earned to actual work-hours(or cost). If actual work-hours are less than means the budget has been overrun.

    The above can be express in the formula below as follows:

    Schedule Variance (SV) = Earned Work-hours or cost Budgeted work hours or cost

    = BCWP BCWS

    Schedule Performance Index (SPI) = Earned work hours or cost to date

    Budgeted work hours or cost to date

    = BCWP

    BCWS

    Cost Variance (CV) = Earned Work hours or cost Actual work hours or cost= BCWP ACWP

    Cost Performance Index (SPI) = Earned work hours or cost to date

    Actual work hours or cost to date= BCWP

    BCWS

    Reporting and Corrective Actions

    Performance reporting should provide the kinds of information and the level of detail

    required by various stakeholders as documented in the Project Execution Plan. Common

    formats for performance reports include bar charts (also called Gantt charts), S-curves,histograms, and tables. Typically the progress and performance status is represented

    using 3-Part Curves. These curves illustrate actual progress, staffing, and performance

  • 8/13/2019 atti98fc

    6/23

    STANDARD OPERATING PROCEDURE

    SOP-PC-035 - RevB (draft)

    Page 6 of 9

    versus the plan and chart incremental and cumulative data. An example of a progress and

    performance tables for Engineering and Construction is identified on Attachments B & D

    OFFICE (including: ENGINEERING) PROGRESS AND PERFORMANCE

    MEASUREMENT - This refers to Attachment A-1 Clause 6.2

    Deliverable Progress Measurement

    As a guideline for progress assessment and to determine percent complete fordeliverables prepared in the course of an engineering project, the users should apply the

    milestone tables as agreed upon by the Project Team. The progress ranges shown for each

    type of document / deliverable executed are representative of the work required tocomplete the deliverable. These should be reviewed and adjusted to suit the varied

    circumstances inherent in each project. Any change to these guidelines should be

    reviewed by the engineering department manager responsible for that particulardeliverable prior to their use on the project.

    The ranges for progress measurement determined by the milestone pattern represent thespecific scope of work to be performed within that deliverable's budget. The length of theproject and the duration of its activities would affect the way progress is assessed as well

    as the timing of the update cycle required for each project weekly, biweekly, or monthly.

    The reporting frequency should be established early in the project.

    Milestone Patterns / Incremental Miestone

    Milestone patterns are a collection of predetermined progress steps that total to 100

    percent completion at the end of the activity or deliverable. These milestones are tangibleand measurable events in time and are often linked to revisions, issue dates, or review

    cycles of documents and deliverables.(see: Work Instructions for Engineering Progress Measurement)

    Deliverable Groups or Activities

    To facilitate the progressing of multiple deliverables of small budget impact, these can begrouped together in deliverable groups. The deliverable group will receive the budget and

    the progress figures for all the items it contains. The individual deliverables can still be

    listed in document listings, document control distributions, or transmittal logs.

    As a rule of thumb, deliverable group budgets should not exceed 10 percent of the

    operation budget and the duration they span should not exceed 3 months. This keeps theprogress items as specific deliverable items that can therefore be statused accurately.

    Deliverable groups are to be used to facilitate progressing small items, not to avoid

    detailed progress measurement of activities and deliverables with little impact value to

    the Project.

  • 8/13/2019 atti98fc

    7/23

    STANDARD OPERATING PROCEDURE

    SOP-PC-035 - RevB (draft)

    Page 7 of 9

    Indirect and Support Activities

    It is not recommended to status indirect and support activities within a unitized progress

    report. These values offer no added value towards the actual physical percent complete.

    CONSTRUCTION PROGRESS AND PERFORMANCE MEASUREMENT - This

    refers to Attachment A-1 Clause 6.2 & Attachment A-1, Clause 3

    Field progress is a key element in the control of project labor costs and schedules. Anaccurate measurement of progress serves as a basis for labor reforecast as well as an

    indicator for performance against the project schedule. Performance is the comparison

    between current earned value and value expended.

    This measurement at specified periods serves as a tool for construction status and helps

    the field Project Controls team to better forecast total installed costs and accuratelypredict project completion. Progress serves as an analysis tool for timely corrective and

    preventive actions against unforecasted project delays and increased cost.

    Subcontractor Performance (by Others)

    TF via Construction Supervision group to supervise and monitor Services performed by

    Subcontractors. Construction Supervision can ask Subcontractor to submit Level 3/Level4 Schedule in order to control and to measure the work performed.

    Subcontractors to submit their weekly progress report and this report to be verified byConstruction Supervision:

    The subcontractor weekly progress report to include:

    Contract Number and Scope Summary Name of Subcontractor Summary of Services performed for the week Percentage complete (planned and actual) Details of accidents (if any) and near misses, corrective action adopted Reasons for schedule slippage (if any) and proposed means for recovery) Services to be performed in the next reporting period Daily manpower count by discipline including supervisor, inspectors, and safety

    officers for the week

    Details of Client and Subcontractors equipment deployed. Working, standby,breakdown.

    Amounts invoiced, paid, remaining, overdue, disputed Interfaces with Client existing production facilities for the following month. Details of work stoppages and reasons Daily weather conditions

  • 8/13/2019 atti98fc

    8/23

    STANDARD OPERATING PROCEDURE

    SOP-PC-035 - RevB (draft)

    Page 8 of 9

    Progress Measurement

    Earned Value Analysis

    Progress for subcontracted activities can be calculated either by using the same method as

    self-performed construction.

    Percent complete of an activity is based on the measured quantity of work

    installed divided by the projected total quantity of work installed for eachweighted work step.

    Item Percent Complete = Quantity Installed 100Estimated Total Quantity

    Summary Percent Complete = Earned Hours 100Control Base Hours

    or:

    Summary Percent Complete = Earned Value Cost 100Control Base Hours

    or by some other method agreed to with the subcontractor at pre-award meetings.

    One method commonly used is for the subcontractors to assess the percent complete for

    each pay item reported and verified either by TF Project Controls or the subcontractsManager-Coordinator. Based on an agreed-upon initial weighting, an earned value is thus

    obtained for each pay item and summarized for each subcontract. Total percent completefor all subcontractors work can then easily be obtained. If the work units are equivalent

    to job hours used in self-performed progress measurement, total project field progress canbe computed by adding all earned units and dividing by total estimated units.

    (see: Work Instructions for Construction Progress Measurement)

    WORK INSTRUCTIONS & TEMPLATES - This SOP provides an overview of

    progress reporting and control on the FPM scope of work. Work Instructions and

    Templates are available for the following areas of work.

    Work Instruction 01 Measuring & Reporting Engineering Progress & Productivity

    Work Instruction 02 Measuring & Reporting Construction Progress & Productivity

  • 8/13/2019 atti98fc

    9/23

    STANDARD OPERATING PROCEDURE

    SOP-PC-035 - RevB (draft)

    Page 9 of 9

    REVISIONS TO THIS PROCEDURE The current SOP is a draft issued for earlyintegration efforts. Revision 0 of this SOP will be issued with PC Planning Lead with

    approval by the PC Manager and PM in due course. Later revisions will be made by the

    PC Planning Lead with concurrence by PC Manager and Program Manager. All PC staffwill be given copies or access to copies of the SOP. Updates to standard forms being

    used will be provided by the Cost Lead as they become available.

    ATTACHMENTS

    A Sample of Engineering Progress Measurement Forms

    B Sample of Engineering Weekly Progress ReportsC Sample of Weekly Progress Report Submitted by Subcontractors

    D Sample of Construction Weekly Progress Reports

    E Sample of Monthly ReportsF Sample of Level 2 Progress Control Curve & Schedule

    G Sample of Productivity Profile Analysis

    H Sample Form of Daily Record

    Rev B as issued by Sony Runtulalu (Planning Lead)

  • 8/13/2019 atti98fc

    10/23

    Page 1 of 2

    PROGRESS

    REPORTING

    TF-FPM, Duri Field

    Work Instruction 01

    SOP-PC-035

    07May07

    WORK INSTRUCTION 01

    MEASURING & REPORTING ENGINEERING

    PROGRESS & PRODUCTIVITY

    1) TF PC personnel who is responsible for measuring engineering progress is CostEngineer/Scheduler

    2) Get the deliverable progress of each activity from discipline engineers.3) Calculate the progress. Method used to calculate the progress is Incremental

    Milestone This method is applicable to any control account which includes subtasks

    that must be handled in sequence. For example, drawing preparation includes the

    sequential tasks or operations listed below. Completion of any subtask is consideredto be a milestone, which when completed represents a certain percentage of the total

    installation. The percentage chosen to represent each milestone is normally based on

    the number of work-hours estimated to be required to that point in relation to the

    total. In the listing below, the attainment of each milestone has been judged to beequivalent to having completed the percentage listed of the total installation

    Collecting Input 10%

    Conceptual Design & Layout 25%

    Performing & Issue Sketches to Drawing 40%

    Drafting & Issue Drawing for Checking 55%

    Release for Squad Check 75%

    IFR 80%

    IFA 90%

    IFC 100%

    4) Calculate the actual cost / actual man-hour from timesheet5) Calculate the productivity / performance

    Performance = Earned Hours orActual Hours

    Performance = Earned Value Cost

    Actual Cost

    6) Prepare progress report Weekly progress report will use Fridays as the cut-off forweekly reporting. (see: Attachment 02).

  • 8/13/2019 atti98fc

    11/23

    STANDARD OPERATING PROCEDURE

    SOP-PC-035 - Work Instruction 01

    Page 2 of 2

    7) Submit the Report to client and gives the copies to the respective Group Managersand PC Lead.

    8) Filing the progress report document

  • 8/13/2019 atti98fc

    12/23

    Page 1 of 3

    PROGRESS

    REPORTING

    TF-FPM, Duri Field

    Work Instruction 02

    SOP-PC-035

    07May07

    WORK INSTRUCTIONS 02

    MEASURING CONSTRUCTION PROGRESS

    1) TF Project Control (PC) personnel who are responsible for measuring constructionprogress is QSs. QSs along with Construction Supervision (CS) & Quality Control(QC) is responsible for progress verification for work done by subcontractor.

    2) Progress measurement for Bi-Weekly (or Weekly) Progress Report. Subcontractors tosubmit their progress mentioning the quantity of work performed to QS. QS to verify

    the work performed done by subcon. The flow would be as follows:

    Bi-weekly progress report:

    Subcontractors prepare progress

    report. Monday to Wednesday

    Time interval for work done by

    subcontractors to be verified (2weeks, start on Monday & end on

    Friday)

    Milestone: Friday- Cut off date of

    progress report

    Milestone: Subcon submit the

    progress report to TF, shall not be

    later than Wednesday

    QS verify the progress report

    (Thursday-Friday)

    Milestone: Monday: PC prepare

    progress report and submit to CPI

  • 8/13/2019 atti98fc

    13/23

    STANDARD OPERATING PROCEDURE

    SOP-PC-035 - Work Instruction 02

    Page 2 of 3

    3) Progress Measurement for Monthly Progress Report & Status. Subcontractors tosubmit their progress claim mentioning the quantity of work performed to CS

    Representatives. CS Representatives have to verify the progress done by

    Subcontractor. QC to check the quality & only the quantity accepted by QC canproceed to progress claim. When applicable verifications from 3

    rdparty surveyors are

    needed. QS to do the final verification. If accepted by QS, the progress claim canproceed to the next step. The flow would be as follows:

    Subcontractor submit the

    progress claim, 2 days

    CS, verify, 2 days

    QC, check the quality, only the

    accepted quantity can proceed

    to next step, 2 days

    QS verify, 2 days

    3rdParty Surveyor Verification (if

    applicable), 2 days

    Return to subcon for

    final progress claim

    submission

    Subcontractor submit

    final revision, 2 days

    Time interval for work done by

    subcontractors to be verified (1

    month)

  • 8/13/2019 atti98fc

    14/23

    STANDARD OPERATING PROCEDURE

    SOP-PC-035 - Work Instruction 02

    Page 3 of 3

    4) QSs verify the quantity recorded by using several methods & tools (by checking thequantity one-by-one (unit/lump sum (ls)), by using table (ton/kg), by using software(e.g. Autodesk Land Development, Civil Cad & Teramodel for m3 unit), by using

    reports provided by TF QC (for work like piping work). Specific methods for

    progress measurement are attached to this document5) Subcontractors finally submit the progress report to TF PC based on the quantities

    verified by TF QS. (see: Attachment C)

  • 8/13/2019 atti98fc

    15/23

    Page 1 of 1

    PROGRESS

    REPORTING

    TF-FPM, Duri Field

    Work Instruction 03

    SOP-PC-035

    07May07

    WORK INSTRUCTIONS 03

    REPORTING CONSTRUCTION PROGRESS & PRODUCTIVITY

    1) TF Project Control (PC) personnel who are responsible for reporting constructionprogress & productivity are Cost Engineers, Schedulers & Project Control Lead.

    2) There are 2 period of reporting: Weekly/Bi-weekly progress report & Monthly StatusReport. Progress Measurement Work Instruction is available separately in this SOP.

    3) For work done by Subcon, the progress can be obtained for progress report bySubcontractors verified by QSs. There are several methods to calculate progress, one

    of them is Weight or Equivalent Unit. This method is applicable where the task beingcontrolled is a major effort involving a long period of time and is composed of two or

    more overlapping subtasks, each with a different unit of work measurement.

    Progress (Construction) = Equivalent UnitsTotal Equivalent Units

    4) Calculate the productivity / performancea. Calculate the actual cost (the actual cost for Resource Unit Rate (RUR)

    the actual can be obtained from timesheet)b. Calculate the productivity / performance

    Performance = Earned ValueActual Value

    5) Prepare progress report. Weekly/Bi-weekly progress report will use Fridays as thecut-off for weekly reporting. (see: Attachment D). Weekly Report should be

    accompanied by photographs from site. Those photographs should be taken by QS.

    Index each photograph with reference and this reference marked, on an A3 Plot Plan.Stamp all photographs with the date the photographs was taken.

    6) Submit the Report to client and gives the copies to the respective Group Managersand PC Leads.

    7) Filing the Progress Report

  • 8/13/2019 atti98fc

    16/23

    Page 1 of 1

    PROGRESS

    REPORTINGTF-FPM, Duri Field

    SOP-PC-035

    Attachment A

    07May07

    Attachment ASample of Engineering Progress Measurement Forms

  • 8/13/2019 atti98fc

    17/23

    Page 1 of 1

    PROGRESS

    REPORTINGTF-FPM, Duri Field

    SOP-PC-035

    Attachment B

    07May07

    Attachment BSample of Engineering Weekly Progress Reports

  • 8/13/2019 atti98fc

    18/23

  • 8/13/2019 atti98fc

    19/23

    Page 1 of 1

    PROGRESS

    REPORTINGTF-FPM, Duri Field

    SOP-PC-035

    Attachment D

    07May07

    Attachment DSample of Construction Bi-Weekly Programme Reviews

  • 8/13/2019 atti98fc

    20/23

    Page 1 of 1

    PROGRESS

    REPORTINGTF-FPM, Duri Field

    SOP-PC-035

    Attachment E

    07May07

    Attachment ESample of Monthly Reports

  • 8/13/2019 atti98fc

    21/23

    Page 1 of 1

    PROGRESS

    REPORTINGTF-FPM, Duri Field

    SOP-PC-035

    Attachment F

    07May07

    Attachment FSample of Level 2 Update

    Project Control Curve & Schedule

  • 8/13/2019 atti98fc

    22/23

    Page 1 of 1

    PROGRESS

    REPORTINGTF-FPM, Duri Field

    SOP-PC-035

    Attachment G

    07May07

    Attachment GSample of Productivity Profile Analysis

  • 8/13/2019 atti98fc

    23/23

    PROGRESS

    REPORTINGTF-FPM, Duri Field

    SOP-PC-035

    Attachment H

    07May07

    Attachment HSample Form of Daily Record